SlideShare une entreprise Scribd logo
1  sur  36
Télécharger pour lire hors ligne
Project SLOPE
1
WP 6 – System integration
Project SLOPE
Mid-term Review
2/Jul/2015
T6.1– Definition of the integration steps
Brussels, July 2nd, 2015
Task Overview
Mid-term Review
2/Jul/2015
• Status: Completed (100%)
• Length: 7 Months (From M10 to M16)
• 5 Involved Partners
• Leader: GraphiTech
• Participants: COMPOLAB, MHG, FLY, ITENE
• Aim: Achieve a complete integration of the different components
that are part of the SLOPE platform to be tested on pilot areas
• Output:
• D.6.01 System integration and validation plan
Mid-term Review
2/Jul/15
Work Package key aspects
• Build a working system
• Ready for pilots and on-the-field testing
• 3 Main tasks:
• First Integration - Forest Inventory & Harvesting
System
• Second Integration - Forest Management
• Third Integration – System Validation
• Technical and Economical Analysis
• Overall solution costs
• Social impacts
• Environmental impacts
T.6.2
T.6.3
T.6.4
Mid-term Review
2/Jul/15
Process
• Evaluate existing software development processes
• Definition of the integration strategy
• Enrich each integration task (6.2, 6.3, 6.4) with the chosen
strategy
Mid-term Review
2/Jul/15
SW Development processes evaluation
• Different processes studied and evaluated:
• Heavyweight:
• Waterfall
• Unified process
• Spiral
• Lightweight (AGILE):
• Extreme programming
• Scrum
• Conclusions:
• Best choice: AGILE (but not enough)
• Too many development teams
• Mix waterfall and Agile
Mid-term Review
2/Jul/15
Integration Strategy
Waterfall + agile like approach
• 3 major loops of integration and lab validation
• 4 minor loops of iterative evolution
• Bug fixing and integration at high frequency
• Parallel support for real use case pilots
T.6.2
T.6.3
T.6.4
Mid-term Review
2/Jul/15
Integration Strategy
For each main integration step:
• Definition of the involved components
• Timeline with integration steps, milestones, telcos, days for testing
• One testing scenario based on the use case
• Recognize Involved actors
• Definition of required HW and SW
• Functional requirements
• defining a function
• Non-functional requirements
• defining a criteria for an operation
• Testing approach
Mid-term Review
2/Jul/15
Step 1 (T6.02) - Components
Mid-term Review
2/Jul/15
Step 1 (T6.02) -Timeline
• 4 agile-like integration sprints (bimonthly)
• 2 sprint overlapping with step 2
• 1 monitoring meeting every 2 weeks
• 1 Round of testing at the end of each sprint
• Incremental built of D.6.02.1 System Integration Report I
• Incremental build of D.6.04.1 Techno-economic evaluation I
Mid-term Review
2/Jul/15
Step 1 (T6.02) – Integration
1. Connection of the 3D modelling for harvesting planning (T.2.4) with the FIS
2. Connection of handheld devices (e.g. RFID UHF readers) with the FIS
3. Connection of cable crane and processor head enhanced HW with the FIS
4. Connection of truck control units with the FIS
5. Connection of planning and editing functionalities already available in the
3D modelling for harvesting planning system with the FIS
Mid-term Review
2/Jul/15
Step 1 (T6.02) – Actors, HW and SW
• Actors:
• Forest Planner
• Forest operator
• On-field harvesting operator
• Forestry expert
• Cableway Operator
• Hardware:
• RFID Handheld (Tablet / Smartphone)
• GPS Sensor (integrated inside the handheld or
external)
• Industrial PC installed inside the harvesting
machine
• CompactRIO Custom system
• Desktop Computer
• Wifi/3G connectivity
• Software:
• 3D Planning for Harvesting
software
• Forest Information System
(Web Services and Database)
• Web Mapping Service
(GeoServer)
Mid-term Review
2/Jul/15
Step 1 (T6.02) – Functional Requirements
3 Analytics
3.1 Show satellite imagery HIGH
3.2 Toggle aerial imagery visualization of the
stand
HIGH
3.3 Toggle NIR imagery visualization of the stand HIGH
3.4 Toggle open data visualization MEDIUM
3.5 Toggle digital surface model visualization HIGH
3.6 Distance measurement HIGH
3.7 Area measurement HIGH
3.8 Terrain profiling HIGH
3.9 Point of interest visualization MEDIUM
4.0 Toggle roads visualization HIGH
4 Operation
4.1 Cableway planning HIGH
4.1.1 Add/Remove pillars HIGH
4.1.2 Show harvesting area HIGH
4.1.3 Show cable information (angles, height from
terrain, length)
HIGH
4.1.4 Show cable line profile MEDIUM
4.2 Working area setup
4.2.1 Draw working area HIGH
4.2.2 Place harvesting machines HIGH
4.2.3 Place other resources HIGH
4.2.4 Plan routes MEDIUM
4.3 Track felling activities MEDIUM
4.4 Toggle building and terminals visualization MEDIUM
4.5 Track logistics MEDIUM
4.5.1 Show truck movements MEDIUM
4.5.2 Track wood storage areas MEDIUM
4.5.3 Track sawmills MEDIUM
4.5.4 Show logs inventory MEDIUM
4.6 Track harvesting progress HIGH
4.6.1 Real-time updates and statistics MEDIUM
4.7 Show weather conditions and forecast HIGH
5 Forest
5.1 Toggle stand visualization HIGH
5.2 Toggle simple tree models visualization (from UAV) HIGH
5.3 Toggle complex tree models visualization (from TLS) HIGH
5.4 Single tree selection and inspection HIGH
5.5 Single tree virtual marking HIGH
5.5.1 Issue a report MEDIUM
5.5.2 Update tree properties (Quality indices, status, etc.) HIGH
5.6 Retrieve forest area information MEDIUM
Mid-term Review
2/Jul/15
Step 1 (T6.02) – Non-Functional Requirements
Forest Information System (FIS)
1 User friendliness HIGH
2 Compatibility with all the desktop browsers HIGH
3 Compatibility with mobile browsers MEDIUM
4 Cross platform HIGH
5 Dynamic interface MEDIUM
Mobile scenario
6 Easy identification of virtually marked trees on the field HIGH
7 GPS signal should work in the forest MEDIUM
8 Offline fault tolerance MEDIUM
In-vehicle scenario
8 Offline fault tolerance MEDIUM
Mid-term Review
2/Jul/15
Step 1 (T6.03) –Testing
• One validation every 2 months
• 2-3 days of work
• Test of each requirement in laboratory conditions
• Based on functional test case
• Incremental document
• Threshold to be reached 70%
Test N° Test case Description
Expected
result
Obtained
Result
Anomaly Performed Passed
1 … … … … YES/NO YES/NO
1
Mid-term Review
2/Jul/15
Step 2 (T6.03) - Components
Mid-term Review
2/Jul/15
Step 2 (T6.03) -Timeline
• 4 agile-like integration sprints (bimonthly)
• 2 sprint overlapping with step 3
• 1 Virtual meeting every 2 weeks
• 1 Round of testing at the end of each sprint
• Incremental built of D.6.02.2 System Integration Report II
• Incremental build of D.6.04.2 Techno-economic evaluation II
Mid-term Review
2/Jul/15
Step 2 (T6.03) – Integration
1. Refinement of already existing Web services to access the FIS
2. Development of new Web Services functions to cope with online
purchasing/invoicing, real-time operation control and logistic optimization
3. Connection of purchasing/invoicing system with the FIS
4. Connection of real-time operation control system with the FIS
Mid-term Review
2/Jul/15
Step 2 (T6.03) – Actors, HW and SW
• Actors:
• Forest Planner
• Forestry expert
• Truck Operator
• Hardware:
• In-vehicle GPS System
• Software:
• Real-time enterprise resource
planning system
• Online selling and auction system
• MHG Mobile app
Mid-term Review
2/Jul/15
Step 2 (T6.03) – Functional Requirements
4 Operation
4.8 Schedule operations and give work orders MEDIUM
7 Purchasing
7.1 Online auction MEDIUM
7.2 Direct selling MEDIUM
8 Business Analytics
8.1 Harvesting cost estimation HIGH
8.2 Income estimation HIGH
9 Resource inspection
9.1 Staff monitoring MEDIUM
9.1.2 Update human resource usage MEDIUM
9.2 Machinery monitoring MEDIUM
9.2.1 Update machine status MEDIUM
9.3 Terminals monitoring MEDIUM
9.3.1 Update terminal status MEDIUM
9.3.2 Documentation with mobile app MEDIUM
9.3.3 Biomass quality monitoring MEDIUM
9.3.4 Road side storage monitoring MEDIUM
9.3.5 Transport monitoring & reports (delivery notes) MEDIUM
Mid-term Review
2/Jul/15
Step 2 (T6.03) –Testing
• One validation every 2 months
• 2-3 days of work
• Test of each requirement in laboratory conditions
• Based on functional test case
• Incremental document
• Threshold to be reached 80%
Test N° Test case Description
Expected
result
Obtained
Result
Anomaly Performed Passed
1 … … … … YES/NO YES/NO
1
Mid-term Review
2/Jul/15
Step 3 (T6.04) - Components
Mid-term Review
2/Jul/15
Step 3 (T6.04) -Timeline
• 4 agile-like integration sprints (bimonthly)
• 1 Virtual meeting every 2 weeks
• 1 Round of testing at the end of each sprint
• Incremental built of D.6.023
• Actors, requirements and test case as union of the first two steps
• Threshold to be reached 90%
Mid-term Review
2/Jul/15
Conclusions
• Guidelines for efficient and continuous integration
• 4 sprints with validation and reporting per task
• Regular monitoring meetings
• Incremental testing phase
• Ready for changing requirements
• Partners
• Forestry Actors
Mid-term Review
2/Jul/15
Contact info
Daniele Magliocchetti: daniele.magliocchetti@graphitech.it
Thank you for your attention
Project SLOPE
Mid-term Review
2/Jul/2015
T6.2– First Integration
Forest Inventory & Harvesting System
Brussels, July 2nd, 2015
Task Overview
Mid-term Review
2/Jul/2015
• Status: In progress (20%)
• Length: 14 Months (From M14 to M27)
• 8 Involved Partners
• Leader: GraphiTech
• Participants: COMPOLAB, MHG, FLY, GRE, TRE, ITENE, CNR
• Aim:
• Integration of forest information system (FIS) with harvesting
measurement systems and software components
• Output:
• D.6.21 System integration report I
• D.6.41 SLOPE System Techno-Economic Evaluation Report I
Mid-term Review
2/Jul/15
Task Overview
1. Connection of the 3D modelling for harvesting planning (T.2.4) with the FIS
2. Connection of handheld devices (e.g. RFID UHF readers) with the FIS
3. Connection of cable crane and processor head enhanced HW with the FIS
4. Connection of truck control units with the FIS
5. Connection of planning and editing functionalities already available in the
3D modelling for harvesting planning system with the FIS
Mid-term Review
2/Jul/15
Task Overview
• Currently at M18
• Major effort spent on:
• Interface improvements
• Alpha 1.0
• Alpha 1.1
• Alpha 1.2 Early Access Preview
• DB and Webservices improvements
• Connection of viewer with DB and Webservices
• First Integration and validation planned after review
Mid-term Review
2/Jul/15
Alpha 1.0
• Focused on functions
• Features:
• Measurements
• Stem readings
• Cable crane placement
• Forest visualization
• 3D moving objects
• DSM visualization
• WMS support
Mid-term Review
2/Jul/15
Alpha 1.1
• New Interface
• Menu bar
• Floating panels
• Improved Features:
• Pilot specific layers and
functions
• Distance and Measurements
• Weather forecast
• Pickable objects
• Terrain analysis
• Cable crane placement
• Forest visualization
Mid-term Review
2/Jul/15
Demo
Mid-term Review
2/Jul/15
Alpha 1.2 early access preview
• Features:
• Cable crane placement, profiling and animation
• Multilanguage support
• 3D moving objects along a path
• Focused on refinements and FIS connection
Mid-term Review
2/Jul/15
Alpha 1.2 Upcoming
• Features:
• New languages
• New WMS data for Austrian pilot
• Point cloud visualization
• Point of interest (sawmills, storage areas, etc.)
• Project saving
Mid-term Review
2/Jul/15
Conclusions and FutureWork
• Web platform in a good shape
• Many functionalities not connected with the FIS
• Mobile devices
• Cable crane
• Truck control units
Next Steps:
• First validation
• Connect missing components to the FIS
• Fill the database with real-time data
• Expose all the available data throught the 3D Viewer
Mid-term Review
2/Jul/15
Contact info
Daniele Magliocchetti: daniele.magliocchetti@graphitech.it
Michele Andreolli: michele.andreolli@graphitech.it
Federico Devigili: federico.devigili@graphitech.it
Thank you for your attention

Contenu connexe

Tendances

3rd Technical Meeting - WP5
3rd Technical Meeting - WP53rd Technical Meeting - WP5
3rd Technical Meeting - WP5SLOPE Project
 
2nd Technical Meeting - WP6
2nd Technical Meeting - WP62nd Technical Meeting - WP6
2nd Technical Meeting - WP6SLOPE Project
 
2nd Technical Meeting - WP1
2nd Technical Meeting - WP12nd Technical Meeting - WP1
2nd Technical Meeting - WP1SLOPE Project
 
3rd Technical Meeting - WP6
3rd Technical Meeting - WP63rd Technical Meeting - WP6
3rd Technical Meeting - WP6SLOPE Project
 
2nd Technical Meeting - WP8
2nd Technical Meeting - WP82nd Technical Meeting - WP8
2nd Technical Meeting - WP8SLOPE Project
 
1st Technical Meeting - WP1
1st Technical Meeting - WP11st Technical Meeting - WP1
1st Technical Meeting - WP1SLOPE Project
 
Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3SLOPE Project
 
Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6SLOPE Project
 
SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1SLOPE Project
 
2nd Technical Meeting - WP5
2nd Technical Meeting - WP52nd Technical Meeting - WP5
2nd Technical Meeting - WP5SLOPE Project
 
Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8SLOPE Project
 
Kick-Off Meeting - WP7
Kick-Off Meeting - WP7Kick-Off Meeting - WP7
Kick-Off Meeting - WP7SLOPE Project
 
4th Technical Meeting - WP3
4th Technical Meeting - WP34th Technical Meeting - WP3
4th Technical Meeting - WP3SLOPE Project
 
Kick-Off Meeting - WP3
Kick-Off Meeting - WP3Kick-Off Meeting - WP3
Kick-Off Meeting - WP3SLOPE Project
 
Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8SLOPE Project
 
1st Technical Meeting - WP5
1st Technical Meeting - WP51st Technical Meeting - WP5
1st Technical Meeting - WP5SLOPE Project
 
Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1SLOPE Project
 
4th Technical Meeting - WP5
4th Technical Meeting - WP54th Technical Meeting - WP5
4th Technical Meeting - WP5SLOPE Project
 
Slope Final Review Meeting - WP3
Slope Final Review Meeting - WP3Slope Final Review Meeting - WP3
Slope Final Review Meeting - WP3SLOPE Project
 
3rd Technical Meeting - WP7
3rd Technical Meeting - WP73rd Technical Meeting - WP7
3rd Technical Meeting - WP7SLOPE Project
 

Tendances (20)

3rd Technical Meeting - WP5
3rd Technical Meeting - WP53rd Technical Meeting - WP5
3rd Technical Meeting - WP5
 
2nd Technical Meeting - WP6
2nd Technical Meeting - WP62nd Technical Meeting - WP6
2nd Technical Meeting - WP6
 
2nd Technical Meeting - WP1
2nd Technical Meeting - WP12nd Technical Meeting - WP1
2nd Technical Meeting - WP1
 
3rd Technical Meeting - WP6
3rd Technical Meeting - WP63rd Technical Meeting - WP6
3rd Technical Meeting - WP6
 
2nd Technical Meeting - WP8
2nd Technical Meeting - WP82nd Technical Meeting - WP8
2nd Technical Meeting - WP8
 
1st Technical Meeting - WP1
1st Technical Meeting - WP11st Technical Meeting - WP1
1st Technical Meeting - WP1
 
Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3
 
Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6
 
SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1
 
2nd Technical Meeting - WP5
2nd Technical Meeting - WP52nd Technical Meeting - WP5
2nd Technical Meeting - WP5
 
Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8
 
Kick-Off Meeting - WP7
Kick-Off Meeting - WP7Kick-Off Meeting - WP7
Kick-Off Meeting - WP7
 
4th Technical Meeting - WP3
4th Technical Meeting - WP34th Technical Meeting - WP3
4th Technical Meeting - WP3
 
Kick-Off Meeting - WP3
Kick-Off Meeting - WP3Kick-Off Meeting - WP3
Kick-Off Meeting - WP3
 
Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8
 
1st Technical Meeting - WP5
1st Technical Meeting - WP51st Technical Meeting - WP5
1st Technical Meeting - WP5
 
Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1
 
4th Technical Meeting - WP5
4th Technical Meeting - WP54th Technical Meeting - WP5
4th Technical Meeting - WP5
 
Slope Final Review Meeting - WP3
Slope Final Review Meeting - WP3Slope Final Review Meeting - WP3
Slope Final Review Meeting - WP3
 
3rd Technical Meeting - WP7
3rd Technical Meeting - WP73rd Technical Meeting - WP7
3rd Technical Meeting - WP7
 

En vedette

Mid-term Review Meeting - WP4
Mid-term Review Meeting - WP4Mid-term Review Meeting - WP4
Mid-term Review Meeting - WP4SLOPE Project
 
Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2SLOPE Project
 
4th Technical Meeting - WP4
4th Technical Meeting - WP44th Technical Meeting - WP4
4th Technical Meeting - WP4SLOPE Project
 
SLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarderSLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarderSLOPE Project
 
4th Technical Meeting - WP8
4th Technical Meeting - WP84th Technical Meeting - WP8
4th Technical Meeting - WP8SLOPE Project
 
3rd Technical Meeting - WP2
3rd Technical Meeting - WP23rd Technical Meeting - WP2
3rd Technical Meeting - WP2SLOPE Project
 
1st Technical Meeting - WP8
1st Technical Meeting - WP81st Technical Meeting - WP8
1st Technical Meeting - WP8SLOPE Project
 
3rd Technical Meeting - WP8
3rd Technical Meeting - WP83rd Technical Meeting - WP8
3rd Technical Meeting - WP8SLOPE Project
 
SLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomassSLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomassSLOPE Project
 
Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2SLOPE Project
 
1st Technical Meeting - WP4
1st Technical Meeting - WP41st Technical Meeting - WP4
1st Technical Meeting - WP4SLOPE Project
 
Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7SLOPE Project
 
Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4SLOPE Project
 
2nd Technical Meeting - WP4
2nd Technical Meeting - WP42nd Technical Meeting - WP4
2nd Technical Meeting - WP4SLOPE Project
 
SLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of treesSLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of treesSLOPE Project
 
Kick-Off Meeting - WP1
Kick-Off Meeting - WP1Kick-Off Meeting - WP1
Kick-Off Meeting - WP1SLOPE Project
 
SLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machinesSLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machinesSLOPE Project
 
Mid-term Review Meeting - WP7
Mid-term Review Meeting - WP7Mid-term Review Meeting - WP7
Mid-term Review Meeting - WP7SLOPE Project
 

En vedette (18)

Mid-term Review Meeting - WP4
Mid-term Review Meeting - WP4Mid-term Review Meeting - WP4
Mid-term Review Meeting - WP4
 
Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2
 
4th Technical Meeting - WP4
4th Technical Meeting - WP44th Technical Meeting - WP4
4th Technical Meeting - WP4
 
SLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarderSLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarder
 
4th Technical Meeting - WP8
4th Technical Meeting - WP84th Technical Meeting - WP8
4th Technical Meeting - WP8
 
3rd Technical Meeting - WP2
3rd Technical Meeting - WP23rd Technical Meeting - WP2
3rd Technical Meeting - WP2
 
1st Technical Meeting - WP8
1st Technical Meeting - WP81st Technical Meeting - WP8
1st Technical Meeting - WP8
 
3rd Technical Meeting - WP8
3rd Technical Meeting - WP83rd Technical Meeting - WP8
3rd Technical Meeting - WP8
 
SLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomassSLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomass
 
Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2
 
1st Technical Meeting - WP4
1st Technical Meeting - WP41st Technical Meeting - WP4
1st Technical Meeting - WP4
 
Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7
 
Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4
 
2nd Technical Meeting - WP4
2nd Technical Meeting - WP42nd Technical Meeting - WP4
2nd Technical Meeting - WP4
 
SLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of treesSLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of trees
 
Kick-Off Meeting - WP1
Kick-Off Meeting - WP1Kick-Off Meeting - WP1
Kick-Off Meeting - WP1
 
SLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machinesSLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machines
 
Mid-term Review Meeting - WP7
Mid-term Review Meeting - WP7Mid-term Review Meeting - WP7
Mid-term Review Meeting - WP7
 

Similaire à Mid-term Review Meeting - WP6

201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin Teoh201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin TeohHui Qin Teoh, PMP®
 
Monitoring_Plans.pptx
Monitoring_Plans.pptxMonitoring_Plans.pptx
Monitoring_Plans.pptxlovelampsys
 
TIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediationTIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediationThe Incredible Automation Day
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptxsharpan
 
Managing projects by data
Managing projects by dataManaging projects by data
Managing projects by dataMobi Marketing
 
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...Nesma
 
Maximo_Mini LMM November 2005.ppt
Maximo_Mini LMM November 2005.pptMaximo_Mini LMM November 2005.ppt
Maximo_Mini LMM November 2005.pptTareqAkhdar
 
Blog #02 - Project management report for a call tracking system - A sample as...
Blog #02 - Project management report for a call tracking system - A sample as...Blog #02 - Project management report for a call tracking system - A sample as...
Blog #02 - Project management report for a call tracking system - A sample as...hiranya mht
 
LG Inform Learning Day
LG Inform Learning DayLG Inform Learning Day
LG Inform Learning DayLG Inform Plus
 
2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwp2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwpATTRACTIVE DANUBE
 
January 2020 Page 1 of 5 Project Fields to Include .docx
  January 2020  Page 1 of 5 Project Fields to Include .docx  January 2020  Page 1 of 5 Project Fields to Include .docx
January 2020 Page 1 of 5 Project Fields to Include .docxShiraPrater50
 
Production-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.pptProduction-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.pptJohnRichard90
 
Projektværktøjsdagen 2014 rapid implementation of ppm tool
Projektværktøjsdagen 2014   rapid implementation of ppm toolProjektværktøjsdagen 2014   rapid implementation of ppm tool
Projektværktøjsdagen 2014 rapid implementation of ppm toolThomas Røygaard
 
Structured NERC CIP Process Improvement Using Six Sigma
Structured NERC CIP Process Improvement Using Six SigmaStructured NERC CIP Process Improvement Using Six Sigma
Structured NERC CIP Process Improvement Using Six SigmaEnergySec
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11Robert (Bob) Owens
 

Similaire à Mid-term Review Meeting - WP6 (20)

201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin Teoh201601007 Limelight - Hui Qin Teoh
201601007 Limelight - Hui Qin Teoh
 
Monitoring_Plans.pptx
Monitoring_Plans.pptxMonitoring_Plans.pptx
Monitoring_Plans.pptx
 
IQA_Project
IQA_ProjectIQA_Project
IQA_Project
 
TIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediationTIAD : From standardization to automated alerts remediation
TIAD : From standardization to automated alerts remediation
 
The construction programme - assurance and controls
The construction programme - assurance and controlsThe construction programme - assurance and controls
The construction programme - assurance and controls
 
rough-work.pptx
rough-work.pptxrough-work.pptx
rough-work.pptx
 
Managing projects by data
Managing projects by dataManaging projects by data
Managing projects by data
 
PI Training July 2015
PI Training July 2015PI Training July 2015
PI Training July 2015
 
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
 
Maximo_Mini LMM November 2005.ppt
Maximo_Mini LMM November 2005.pptMaximo_Mini LMM November 2005.ppt
Maximo_Mini LMM November 2005.ppt
 
Blog #02 - Project management report for a call tracking system - A sample as...
Blog #02 - Project management report for a call tracking system - A sample as...Blog #02 - Project management report for a call tracking system - A sample as...
Blog #02 - Project management report for a call tracking system - A sample as...
 
LG Inform Learning Day
LG Inform Learning DayLG Inform Learning Day
LG Inform Learning Day
 
2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwp2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwp
 
PMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time managementPMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time management
 
January 2020 Page 1 of 5 Project Fields to Include .docx
  January 2020  Page 1 of 5 Project Fields to Include .docx  January 2020  Page 1 of 5 Project Fields to Include .docx
January 2020 Page 1 of 5 Project Fields to Include .docx
 
Production-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.pptProduction-Cutover-Strategy1-1qvnpnh.ppt
Production-Cutover-Strategy1-1qvnpnh.ppt
 
Projektværktøjsdagen 2014 rapid implementation of ppm tool
Projektværktøjsdagen 2014   rapid implementation of ppm toolProjektværktøjsdagen 2014   rapid implementation of ppm tool
Projektværktøjsdagen 2014 rapid implementation of ppm tool
 
Structured NERC CIP Process Improvement Using Six Sigma
Structured NERC CIP Process Improvement Using Six SigmaStructured NERC CIP Process Improvement Using Six Sigma
Structured NERC CIP Process Improvement Using Six Sigma
 
ASAP Overview.ppt
ASAP Overview.pptASAP Overview.ppt
ASAP Overview.ppt
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
 

Plus de SLOPE Project

SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3SLOPE Project
 
SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4SLOPE Project
 
SLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forestSLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forestSLOPE Project
 
SLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systemsSLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systemsSLOPE Project
 
SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3SLOPE Project
 
SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4SLOPE Project
 
SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1SLOPE Project
 
SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5SLOPE Project
 
SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4SLOPE Project
 
SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2SLOPE Project
 
SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1SLOPE Project
 
SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2SLOPE Project
 
SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2SLOPE Project
 
SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7SLOPE Project
 
SLOPE 1st workshop - presentation 6
SLOPE 1st workshop - presentation 6SLOPE 1st workshop - presentation 6
SLOPE 1st workshop - presentation 6SLOPE Project
 
SLOPE 1st workshop - presentation 5
SLOPE 1st workshop - presentation 5SLOPE 1st workshop - presentation 5
SLOPE 1st workshop - presentation 5SLOPE Project
 
SLOPE 1st workshop - presentation 4
SLOPE 1st workshop - presentation 4SLOPE 1st workshop - presentation 4
SLOPE 1st workshop - presentation 4SLOPE Project
 
SLOPE 1st workshop - presentation 3
SLOPE 1st workshop - presentation 3SLOPE 1st workshop - presentation 3
SLOPE 1st workshop - presentation 3SLOPE Project
 

Plus de SLOPE Project (18)

SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3
 
SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4
 
SLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forestSLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forest
 
SLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systemsSLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systems
 
SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3
 
SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4
 
SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1
 
SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5
 
SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4
 
SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2
 
SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1
 
SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2
 
SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2
 
SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7
 
SLOPE 1st workshop - presentation 6
SLOPE 1st workshop - presentation 6SLOPE 1st workshop - presentation 6
SLOPE 1st workshop - presentation 6
 
SLOPE 1st workshop - presentation 5
SLOPE 1st workshop - presentation 5SLOPE 1st workshop - presentation 5
SLOPE 1st workshop - presentation 5
 
SLOPE 1st workshop - presentation 4
SLOPE 1st workshop - presentation 4SLOPE 1st workshop - presentation 4
SLOPE 1st workshop - presentation 4
 
SLOPE 1st workshop - presentation 3
SLOPE 1st workshop - presentation 3SLOPE 1st workshop - presentation 3
SLOPE 1st workshop - presentation 3
 

Dernier

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxShobhayan Kirtania
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 

Dernier (20)

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptx
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 

Mid-term Review Meeting - WP6

  • 1. Project SLOPE 1 WP 6 – System integration
  • 2. Project SLOPE Mid-term Review 2/Jul/2015 T6.1– Definition of the integration steps Brussels, July 2nd, 2015
  • 3. Task Overview Mid-term Review 2/Jul/2015 • Status: Completed (100%) • Length: 7 Months (From M10 to M16) • 5 Involved Partners • Leader: GraphiTech • Participants: COMPOLAB, MHG, FLY, ITENE • Aim: Achieve a complete integration of the different components that are part of the SLOPE platform to be tested on pilot areas • Output: • D.6.01 System integration and validation plan
  • 4. Mid-term Review 2/Jul/15 Work Package key aspects • Build a working system • Ready for pilots and on-the-field testing • 3 Main tasks: • First Integration - Forest Inventory & Harvesting System • Second Integration - Forest Management • Third Integration – System Validation • Technical and Economical Analysis • Overall solution costs • Social impacts • Environmental impacts T.6.2 T.6.3 T.6.4
  • 5. Mid-term Review 2/Jul/15 Process • Evaluate existing software development processes • Definition of the integration strategy • Enrich each integration task (6.2, 6.3, 6.4) with the chosen strategy
  • 6. Mid-term Review 2/Jul/15 SW Development processes evaluation • Different processes studied and evaluated: • Heavyweight: • Waterfall • Unified process • Spiral • Lightweight (AGILE): • Extreme programming • Scrum • Conclusions: • Best choice: AGILE (but not enough) • Too many development teams • Mix waterfall and Agile
  • 7. Mid-term Review 2/Jul/15 Integration Strategy Waterfall + agile like approach • 3 major loops of integration and lab validation • 4 minor loops of iterative evolution • Bug fixing and integration at high frequency • Parallel support for real use case pilots T.6.2 T.6.3 T.6.4
  • 8. Mid-term Review 2/Jul/15 Integration Strategy For each main integration step: • Definition of the involved components • Timeline with integration steps, milestones, telcos, days for testing • One testing scenario based on the use case • Recognize Involved actors • Definition of required HW and SW • Functional requirements • defining a function • Non-functional requirements • defining a criteria for an operation • Testing approach
  • 9. Mid-term Review 2/Jul/15 Step 1 (T6.02) - Components
  • 10. Mid-term Review 2/Jul/15 Step 1 (T6.02) -Timeline • 4 agile-like integration sprints (bimonthly) • 2 sprint overlapping with step 2 • 1 monitoring meeting every 2 weeks • 1 Round of testing at the end of each sprint • Incremental built of D.6.02.1 System Integration Report I • Incremental build of D.6.04.1 Techno-economic evaluation I
  • 11. Mid-term Review 2/Jul/15 Step 1 (T6.02) – Integration 1. Connection of the 3D modelling for harvesting planning (T.2.4) with the FIS 2. Connection of handheld devices (e.g. RFID UHF readers) with the FIS 3. Connection of cable crane and processor head enhanced HW with the FIS 4. Connection of truck control units with the FIS 5. Connection of planning and editing functionalities already available in the 3D modelling for harvesting planning system with the FIS
  • 12. Mid-term Review 2/Jul/15 Step 1 (T6.02) – Actors, HW and SW • Actors: • Forest Planner • Forest operator • On-field harvesting operator • Forestry expert • Cableway Operator • Hardware: • RFID Handheld (Tablet / Smartphone) • GPS Sensor (integrated inside the handheld or external) • Industrial PC installed inside the harvesting machine • CompactRIO Custom system • Desktop Computer • Wifi/3G connectivity • Software: • 3D Planning for Harvesting software • Forest Information System (Web Services and Database) • Web Mapping Service (GeoServer)
  • 13. Mid-term Review 2/Jul/15 Step 1 (T6.02) – Functional Requirements 3 Analytics 3.1 Show satellite imagery HIGH 3.2 Toggle aerial imagery visualization of the stand HIGH 3.3 Toggle NIR imagery visualization of the stand HIGH 3.4 Toggle open data visualization MEDIUM 3.5 Toggle digital surface model visualization HIGH 3.6 Distance measurement HIGH 3.7 Area measurement HIGH 3.8 Terrain profiling HIGH 3.9 Point of interest visualization MEDIUM 4.0 Toggle roads visualization HIGH 4 Operation 4.1 Cableway planning HIGH 4.1.1 Add/Remove pillars HIGH 4.1.2 Show harvesting area HIGH 4.1.3 Show cable information (angles, height from terrain, length) HIGH 4.1.4 Show cable line profile MEDIUM 4.2 Working area setup 4.2.1 Draw working area HIGH 4.2.2 Place harvesting machines HIGH 4.2.3 Place other resources HIGH 4.2.4 Plan routes MEDIUM 4.3 Track felling activities MEDIUM 4.4 Toggle building and terminals visualization MEDIUM 4.5 Track logistics MEDIUM 4.5.1 Show truck movements MEDIUM 4.5.2 Track wood storage areas MEDIUM 4.5.3 Track sawmills MEDIUM 4.5.4 Show logs inventory MEDIUM 4.6 Track harvesting progress HIGH 4.6.1 Real-time updates and statistics MEDIUM 4.7 Show weather conditions and forecast HIGH 5 Forest 5.1 Toggle stand visualization HIGH 5.2 Toggle simple tree models visualization (from UAV) HIGH 5.3 Toggle complex tree models visualization (from TLS) HIGH 5.4 Single tree selection and inspection HIGH 5.5 Single tree virtual marking HIGH 5.5.1 Issue a report MEDIUM 5.5.2 Update tree properties (Quality indices, status, etc.) HIGH 5.6 Retrieve forest area information MEDIUM
  • 14. Mid-term Review 2/Jul/15 Step 1 (T6.02) – Non-Functional Requirements Forest Information System (FIS) 1 User friendliness HIGH 2 Compatibility with all the desktop browsers HIGH 3 Compatibility with mobile browsers MEDIUM 4 Cross platform HIGH 5 Dynamic interface MEDIUM Mobile scenario 6 Easy identification of virtually marked trees on the field HIGH 7 GPS signal should work in the forest MEDIUM 8 Offline fault tolerance MEDIUM In-vehicle scenario 8 Offline fault tolerance MEDIUM
  • 15. Mid-term Review 2/Jul/15 Step 1 (T6.03) –Testing • One validation every 2 months • 2-3 days of work • Test of each requirement in laboratory conditions • Based on functional test case • Incremental document • Threshold to be reached 70% Test N° Test case Description Expected result Obtained Result Anomaly Performed Passed 1 … … … … YES/NO YES/NO 1
  • 16. Mid-term Review 2/Jul/15 Step 2 (T6.03) - Components
  • 17. Mid-term Review 2/Jul/15 Step 2 (T6.03) -Timeline • 4 agile-like integration sprints (bimonthly) • 2 sprint overlapping with step 3 • 1 Virtual meeting every 2 weeks • 1 Round of testing at the end of each sprint • Incremental built of D.6.02.2 System Integration Report II • Incremental build of D.6.04.2 Techno-economic evaluation II
  • 18. Mid-term Review 2/Jul/15 Step 2 (T6.03) – Integration 1. Refinement of already existing Web services to access the FIS 2. Development of new Web Services functions to cope with online purchasing/invoicing, real-time operation control and logistic optimization 3. Connection of purchasing/invoicing system with the FIS 4. Connection of real-time operation control system with the FIS
  • 19. Mid-term Review 2/Jul/15 Step 2 (T6.03) – Actors, HW and SW • Actors: • Forest Planner • Forestry expert • Truck Operator • Hardware: • In-vehicle GPS System • Software: • Real-time enterprise resource planning system • Online selling and auction system • MHG Mobile app
  • 20. Mid-term Review 2/Jul/15 Step 2 (T6.03) – Functional Requirements 4 Operation 4.8 Schedule operations and give work orders MEDIUM 7 Purchasing 7.1 Online auction MEDIUM 7.2 Direct selling MEDIUM 8 Business Analytics 8.1 Harvesting cost estimation HIGH 8.2 Income estimation HIGH 9 Resource inspection 9.1 Staff monitoring MEDIUM 9.1.2 Update human resource usage MEDIUM 9.2 Machinery monitoring MEDIUM 9.2.1 Update machine status MEDIUM 9.3 Terminals monitoring MEDIUM 9.3.1 Update terminal status MEDIUM 9.3.2 Documentation with mobile app MEDIUM 9.3.3 Biomass quality monitoring MEDIUM 9.3.4 Road side storage monitoring MEDIUM 9.3.5 Transport monitoring & reports (delivery notes) MEDIUM
  • 21. Mid-term Review 2/Jul/15 Step 2 (T6.03) –Testing • One validation every 2 months • 2-3 days of work • Test of each requirement in laboratory conditions • Based on functional test case • Incremental document • Threshold to be reached 80% Test N° Test case Description Expected result Obtained Result Anomaly Performed Passed 1 … … … … YES/NO YES/NO 1
  • 22. Mid-term Review 2/Jul/15 Step 3 (T6.04) - Components
  • 23. Mid-term Review 2/Jul/15 Step 3 (T6.04) -Timeline • 4 agile-like integration sprints (bimonthly) • 1 Virtual meeting every 2 weeks • 1 Round of testing at the end of each sprint • Incremental built of D.6.023 • Actors, requirements and test case as union of the first two steps • Threshold to be reached 90%
  • 24. Mid-term Review 2/Jul/15 Conclusions • Guidelines for efficient and continuous integration • 4 sprints with validation and reporting per task • Regular monitoring meetings • Incremental testing phase • Ready for changing requirements • Partners • Forestry Actors
  • 25. Mid-term Review 2/Jul/15 Contact info Daniele Magliocchetti: daniele.magliocchetti@graphitech.it Thank you for your attention
  • 26. Project SLOPE Mid-term Review 2/Jul/2015 T6.2– First Integration Forest Inventory & Harvesting System Brussels, July 2nd, 2015
  • 27. Task Overview Mid-term Review 2/Jul/2015 • Status: In progress (20%) • Length: 14 Months (From M14 to M27) • 8 Involved Partners • Leader: GraphiTech • Participants: COMPOLAB, MHG, FLY, GRE, TRE, ITENE, CNR • Aim: • Integration of forest information system (FIS) with harvesting measurement systems and software components • Output: • D.6.21 System integration report I • D.6.41 SLOPE System Techno-Economic Evaluation Report I
  • 28. Mid-term Review 2/Jul/15 Task Overview 1. Connection of the 3D modelling for harvesting planning (T.2.4) with the FIS 2. Connection of handheld devices (e.g. RFID UHF readers) with the FIS 3. Connection of cable crane and processor head enhanced HW with the FIS 4. Connection of truck control units with the FIS 5. Connection of planning and editing functionalities already available in the 3D modelling for harvesting planning system with the FIS
  • 29. Mid-term Review 2/Jul/15 Task Overview • Currently at M18 • Major effort spent on: • Interface improvements • Alpha 1.0 • Alpha 1.1 • Alpha 1.2 Early Access Preview • DB and Webservices improvements • Connection of viewer with DB and Webservices • First Integration and validation planned after review
  • 30. Mid-term Review 2/Jul/15 Alpha 1.0 • Focused on functions • Features: • Measurements • Stem readings • Cable crane placement • Forest visualization • 3D moving objects • DSM visualization • WMS support
  • 31. Mid-term Review 2/Jul/15 Alpha 1.1 • New Interface • Menu bar • Floating panels • Improved Features: • Pilot specific layers and functions • Distance and Measurements • Weather forecast • Pickable objects • Terrain analysis • Cable crane placement • Forest visualization
  • 33. Mid-term Review 2/Jul/15 Alpha 1.2 early access preview • Features: • Cable crane placement, profiling and animation • Multilanguage support • 3D moving objects along a path • Focused on refinements and FIS connection
  • 34. Mid-term Review 2/Jul/15 Alpha 1.2 Upcoming • Features: • New languages • New WMS data for Austrian pilot • Point cloud visualization • Point of interest (sawmills, storage areas, etc.) • Project saving
  • 35. Mid-term Review 2/Jul/15 Conclusions and FutureWork • Web platform in a good shape • Many functionalities not connected with the FIS • Mobile devices • Cable crane • Truck control units Next Steps: • First validation • Connect missing components to the FIS • Fill the database with real-time data • Expose all the available data throught the 3D Viewer
  • 36. Mid-term Review 2/Jul/15 Contact info Daniele Magliocchetti: daniele.magliocchetti@graphitech.it Michele Andreolli: michele.andreolli@graphitech.it Federico Devigili: federico.devigili@graphitech.it Thank you for your attention