SlideShare une entreprise Scribd logo
1  sur  61
Télécharger pour lire hors ligne
Cork
19/jan/2016
Project SLOPE
1
WP 3 – Integration of novel intelligent
harvesting systems operating in mountain
areas (hardware development)
Project SLOPE
Greifenberg Presentation
CORK, JANUARY 2016
Foreword
Wp 3 is focused on the set up of machines and tools required to create an
intelligent interaction from rfid tag reader to black box back up with
innovative machinery covering the complete supply chain in harvesting
operations on steep terrains. The aim is to improve forestry workers safety,
productivity together with terrain sustainability.
Foreword
Technical innovation required will be implemented in machines which will
be ready to function to perform real forestry operations on difficult areas.
Foreword
The critical part of the wp 3 is to be able to manage interaction among
different machines and components keeping functionality also with relevant
changes carried out on the machines.
We do believe that we will be able to successfully manage the wp with the
most suitable components able to collect and transmit perfect data along
the supply chain
Mitigating action undertaken
New partner in the project for the processor head part.
Dow amendment
Task 3.2 changed with the purchase of a new processor
head and the analysis required
Start of wp 3 in month 6 affected by amendment and
mitigating action as reported previously
Suitable components choice and their availability
We will implement information with the other partners to
have the suitable components (antenna, reader and
interface pc and its programming) to proceed with the
deliverable to be submitted in month 26.
What we will be doing to finalise
deliverable 3.3
Let's see what we have been doing since
last January
Time plan
Task 3.3 parts
Tecno carriage
Chockers
Rope launcher
Tecno carriage work status
The carriage is ready. We still need to
implement the interface pc with its
software, the modification on existing
software with laboratory test to verify
interaction.
A mechanical part is being installed now
for the antenna. It will be a movable part
to be lifted upward and downward to
protect the component from the logs
We have planned testing activities with
Graphitech and CNR at the end of
January, beginning of February.
http://youtu.be/ihXUCTBtoVU
Chockers work status
Chokers are ready. The mechanical part is ready. We still need to manage
interaction between them and the new software
Testing activities will be carried out also between Tecno carriage and the
Chockers
Synthetic rope launcher EASER status
The prototype is ready. We have carried out testing activities up to 500
mt. We met difficulties due to the unwrapping of the textile rope. We
have newly re-designed the system and currently we are working on
testing activities with a new component tailored to our needs
The new project will consider the launch of the rope without the need
on unwrapping from the winches.
Synthetic rope launcher EASER status
Synthetic rope launcher EASER status
Synthetic rope launcher EASER status
Wp3 needs testing in machines and
component interactions. We will proceed
with the interface activities between the
carriage and the processor head first in
laboratory and then on field
3.3 - 3.4
Contact info
Diego Graifenberg: graifenberg@gmail.com
ProjectSLOPE
Mid termreviewmeeting
19th-21st January2016
Mid termreviewmeeting
19th-21st January2016
Overview
• Status: ongoing(70%)
• Duration: 17 months (from M9 to M25)
• Involved partners
‐ leader: Compolab
‐ participants:CNR, BOKU, Greifenberg
• Aim: add to a commercial processorhead grading and marking
capabilities while preservingthe existingones
• Output: D3.04 (P type deliverable, due to M25)
Previous status ofactivities
Mid termreviewmeeting
19th-21st January2016
Performed activities
Reverse engineering activities (Task3.2) completed
Deliverable D.3.09submitted inSeptember 2015
Mid termreviewmeeting
19th-21st January2016
Performedactivities
Designof thenovel intelligent processor head
Mid termreviewmeeting
19th-21st January2016
 SWquality index – Described inD4.05
 HIqualityindex – Described in D4.04
NIR qualityindex –Described in D4.03
Stress wave system
Hyperspectralimaging system
Near infraredimaging system
RFIDlabeller
Performedactivities
Envisaged sub-system
Cutting forces evaluation system  CPqualityindex – Described inD4.06
Mid termreviewmeeting
19th-21st January2016
Performedactivities
Cutting forces evaluation system
Mid termreviewmeeting
19th-21st January2016
Performedactivities
Cutting forces evaluation system
Performedactivities
Stress wave evaluation system
Lasermeasurementsystem
Longitudinalaxial modes analysis withthe
resonancemethod
Lasertriangulationsensorableto detectand
measuretheinducedfreevibrationof the
tree
Mid termreviewmeeting
19th-21st January2016
Accelerometersmeasurementsystem
Wavepressuretimeof flight
measurementsinthe processedlogs
Composedbytwoaccelerometersand a
sensorized hammerthat provides
themechanicalstimulusandtriggersignal
Performedactivities
Stress wave evaluation system
Mid termreviewmeeting
19th-21st January2016
Performedactivities
Stress wave evaluation system
Mid termreviewmeeting
19th-21st January2016
Mid termreviewmeeting
19th-21st January2016
Performedactivities
Hyperspectral imagingsystem + NIR imagingsystem
HyperspectralandNIRsensorswill bepositionedona
lifting/loweringbar(socalled scanbar)paralleltothechainsawbar
and placedin aseparated carterforprotectionfromdirty,lubricating
oil andchipping
Sensorsneed specificand verysmalldistance(~3mm)fromlog
surface
Velocityprofileof scanbarneed tobedefined
Performedactivities
Hyperspectral imagingsystem + NIR imagingsystem
Mid termreviewmeeting
19th-21st January2016
Performedactivities
RFIDlabeller
RFIDtagswill beplaced onthe
Systemwill beplaced ona movable
barand will becomposedby:
• RFIDtagroll
• RFIDloading andcutting
systemsystem
• Staplersystem
• RFIDantenna
• RFIDreader
Mid termreviewmeeting
19th-21st January2016
crosssection ofeach log
RFIDtagwill befixed onlogs by
staple(mostreliablesystem)
RFIDtags
Minimumlog
diameter(~20cm)
Logcross
section
Performedactivities
RFIDlabeller
Mid termreviewmeeting
19th-21st January2016
Performedactivities
RFIDlabeller
Mid termreviewmeeting
19th-21st January2016
Performedactivities
RFIDlabeller
Mid termreviewmeeting
19th-21st January2016
Actual activities status
Mid termreviewmeeting
19th-21st January2016
Designofthenovelintelligentprocessorheadiscompleted
Sensorshavebeen selected, purchasedand arrived
NationalInstrumentscomponentsforsensorsacquisition havebeen selected, purchased
and arrived
NationalInstrumentscomponentsforthenewmachinecontrolhavebeen selected and
purchased
IndustrialPChavebeen selected, purchasedand arrived
Actuators:
hydrauliccylindersforstress wavesystemand RFIDlabeller designed andordered
electrical actuatorsforscan barandRFIDlabeller selected andpurchased
Mid termreviewmeeting
19th-21st January2016
Ongoing activities
Designofharnesswiring
Designofaddedhydrauliccircuit
Electricalpowersupplysystem
Productionofthedesignedcustomparts
Assemblyofthenovelprocessorhead
D.3.04isplannedtobecompletedbytheendofMarch2016
Contact info
GaspareL’Episcopia:gaspare.lepiscopia@compolab.it
StefanoMarrazza: stefano.marrazza@compolab.it
Thank you for your attention
Mid termreviewmeeting
19th-21st January2016
Cork
19/jan/2016
Project SLOPE
40
T 3.5 - Intelligent transport truck
Cork, January 19th, 2016
Cork
19/jan/2016
Scope
41
 Status: 100%
 Length: 12 months (M12 to M24)
 Partners involved:
 ITENE (leader), CNR, MHG, BOKU
 Aim: Track trucks and loaded logs and send the
information into the SLOPE system
 Output: Deliverable D3.05 (finished)
Cork
19/jan/2016
General Architecture
42
Cork
19/jan/2016
43
Use case
Cork
19/jan/2016
Hardware
44
Cork
19/jan/2016
Hardware
45
 Raspberry Pi 2 Model B
 900MHz Quad core ARM V7 processor
 1GB of RAM
 GlobalSat BU-353-S4 USB GPS - GPS data acquisition
 Huawei E3256 USB GPRS – GPRS connection
 Belkin F8T013-1 – Bluetooth USB adapter
 Edimax EW-7811Un – Wireless USB adapter
 CAEN R1240I – qID – portable RFID reader
Cork
19/jan/2016
Software
46
 Raspbian Linux distribution as an operative system. Raspbian is
a free operating system based on Debian and optimized for the
rpi hardware.
 PostgreSQL as a database software. PostgreSQL is cross
platform, open source and free to use.
 Python 3 as programming language. Python is a general-
purpose, object-oriented, high-level programming language
defined for code readability. Python is free and open source.
Cork
19/jan/2016
Main Screen
47
Main screen to
engage the system
and monitor status
Cork
19/jan/2016
Test Screen
48
Test screen to try the
different parts of the
system and check
functionalities.
Cork
19/jan/2016
Configuration Screen
49
Configuration screen
to set different
options of the
solution.
Cork
19/jan/2016
Manual RFID Reader Screen
50
Manual RFID Screen
to control and
monitor the activity of
the portable RFID
reader.
Cork
19/jan/2016
Next steps
51
 Optimize software and functioning - T7.2, T7.3
 Prepare participation in SLOPE pilots – T7.3
Cork
19/jan/2016
Contact info
52
 Juan de Dios Díaz (juan.diaz@itene.com)
 Emilio Gonzalez (egonzalez@itene.com)
 Thanks for your attention!!
Cork
19/jan/2016
Task 3.6: data management backup
Objectives
The goals of this task are:
• to develop system for data exchange between hardware in
field and central computer of FIS
• to provide a data backup strategy
Cork
19/jan/2016
Task 3.6: data management backup
Task Leader: CNR
Task Partecipants: Compolab, Greifenberg, Graphitech, Itene,
(Treemetrics)
March 2015 to February 2016
Status: 50%
D.3.07 Black-box for backup and data transmission
Prototype: portable and internal powered black box for daily/weekly
data back up and for data transmission in areas without GPRS
coverage (M.25)
Cork
19/jan/2016
 the “black box” solution is a portable storage (SSHD or similar)
 the external storage will be connected with USB to the industrial PC
hosted by the excavator
 it is used for storing critical data (backup)
 the dedicated GPRS module (USB) is installed in industrial PC and is
used for communication with the central server in a case of the network
coverage
 the portable storage is transferred to the office / operator house and
after connecting to internet, automatically synchronizing data with the
database in a case of no network coverage in forest
Task 3.6: data management backup
detailed concept
industrial PC
Database
banana PI computer
FRID
weight
fuel
???
Data storage
CP
NIR
HI
SW
camera
kinect
banana PI
CAN-bus
RFID antena
RFID controler
load cell
A/D converterWIFI antena
PC processor
CAN-bus CAN-bus
USB
Fuel consumption
Position
Time of installing log
Time of cycle
RFID of logs
Total weight of logs
TECHNO PLC
banana PI
SSD “black box”
cRIO - control
PC processor
USB
SW
sensors
Fuel consumption
Position
Time of installing log
Time of cycle
RFID of logs
Total weight of logs
WIFI antena
GPRS/UMTS
USB
LAN
cDAQ - sensors
LAN
Data from FIS:
quality indexes for
RFID trees, suggested
cutting plan
Data for FIS:
logs quality, quantity,
suitability for each
RFID log
Backup of all data,
including WP4
quality indexed
pressure
sensors
NIR
sensors
HI
sensors
CF
sensors
termometer
actuators guages
encoders
Cork
19/jan/2016
Banana PI Pro
Cork
19/jan/2016
 select and purchase optimal hardware (CNR, Graphitech and COMPOLAB)
 integrate the hardware modules with PC chassis (CNR and COMPOLAB)
 define structures of data (both; to be transmitted via 3G and stored for further
use in FIS (Graphitech + Treemetrics)
 to develop the software for communication of the cable crane and central
computer (Greifenberg, CNR and COMPOLAB)
 to develop the software for field instruments and GPRS communication (CNR
and COMPOLAB)
 to develop software tools for merging the data with FIS (Graphitech)
 to extensively test the solution both in lab and in field (all partners)
Task 3.6: data management backup
work plan
Thank you very much

Contenu connexe

Tendances

2nd Technical Meeting - WP7
2nd Technical Meeting - WP72nd Technical Meeting - WP7
2nd Technical Meeting - WP7SLOPE Project
 
3rd Technical Meeting - WP7
3rd Technical Meeting - WP73rd Technical Meeting - WP7
3rd Technical Meeting - WP7SLOPE Project
 
Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4SLOPE Project
 
Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3SLOPE Project
 
Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7SLOPE Project
 
Kick-Off Meeting - WP2
Kick-Off Meeting - WP2Kick-Off Meeting - WP2
Kick-Off Meeting - WP2SLOPE Project
 
Slope Final Review Meeting - WP1
Slope Final Review Meeting - WP1 Slope Final Review Meeting - WP1
Slope Final Review Meeting - WP1 SLOPE Project
 
4th Technical Meeting - WP4
4th Technical Meeting - WP44th Technical Meeting - WP4
4th Technical Meeting - WP4SLOPE Project
 
2nd Technical Meeting - WP6
2nd Technical Meeting - WP62nd Technical Meeting - WP6
2nd Technical Meeting - WP6SLOPE Project
 
3rd Technical Meeting - WP5
3rd Technical Meeting - WP53rd Technical Meeting - WP5
3rd Technical Meeting - WP5SLOPE Project
 
4th Technical Meeting - WP3
4th Technical Meeting - WP34th Technical Meeting - WP3
4th Technical Meeting - WP3SLOPE Project
 
4th Technical Meeting - WP6
4th Technical Meeting - WP64th Technical Meeting - WP6
4th Technical Meeting - WP6SLOPE Project
 
1st Technical Meeting - WP2
1st Technical Meeting - WP21st Technical Meeting - WP2
1st Technical Meeting - WP2SLOPE Project
 
Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6SLOPE Project
 
3rd Technical Meeting - WP2
3rd Technical Meeting - WP23rd Technical Meeting - WP2
3rd Technical Meeting - WP2SLOPE Project
 
2nd Technical Meeting - WP1
2nd Technical Meeting - WP12nd Technical Meeting - WP1
2nd Technical Meeting - WP1SLOPE Project
 
3rd Technical Meeting - WP6
3rd Technical Meeting - WP63rd Technical Meeting - WP6
3rd Technical Meeting - WP6SLOPE Project
 
2nd Technical Meeting - WP2
2nd Technical Meeting - WP22nd Technical Meeting - WP2
2nd Technical Meeting - WP2SLOPE Project
 
Kick-Off Meeting - WP7
Kick-Off Meeting - WP7Kick-Off Meeting - WP7
Kick-Off Meeting - WP7SLOPE Project
 
Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2SLOPE Project
 

Tendances (20)

2nd Technical Meeting - WP7
2nd Technical Meeting - WP72nd Technical Meeting - WP7
2nd Technical Meeting - WP7
 
3rd Technical Meeting - WP7
3rd Technical Meeting - WP73rd Technical Meeting - WP7
3rd Technical Meeting - WP7
 
Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4Slope Final Review Meeting - WP4
Slope Final Review Meeting - WP4
 
Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3Mid-term Review Meeting - WP3
Mid-term Review Meeting - WP3
 
Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7Slope Final Review Meeting - WP7
Slope Final Review Meeting - WP7
 
Kick-Off Meeting - WP2
Kick-Off Meeting - WP2Kick-Off Meeting - WP2
Kick-Off Meeting - WP2
 
Slope Final Review Meeting - WP1
Slope Final Review Meeting - WP1 Slope Final Review Meeting - WP1
Slope Final Review Meeting - WP1
 
4th Technical Meeting - WP4
4th Technical Meeting - WP44th Technical Meeting - WP4
4th Technical Meeting - WP4
 
2nd Technical Meeting - WP6
2nd Technical Meeting - WP62nd Technical Meeting - WP6
2nd Technical Meeting - WP6
 
3rd Technical Meeting - WP5
3rd Technical Meeting - WP53rd Technical Meeting - WP5
3rd Technical Meeting - WP5
 
4th Technical Meeting - WP3
4th Technical Meeting - WP34th Technical Meeting - WP3
4th Technical Meeting - WP3
 
4th Technical Meeting - WP6
4th Technical Meeting - WP64th Technical Meeting - WP6
4th Technical Meeting - WP6
 
1st Technical Meeting - WP2
1st Technical Meeting - WP21st Technical Meeting - WP2
1st Technical Meeting - WP2
 
Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6Slope Final Review Meeting - WP6
Slope Final Review Meeting - WP6
 
3rd Technical Meeting - WP2
3rd Technical Meeting - WP23rd Technical Meeting - WP2
3rd Technical Meeting - WP2
 
2nd Technical Meeting - WP1
2nd Technical Meeting - WP12nd Technical Meeting - WP1
2nd Technical Meeting - WP1
 
3rd Technical Meeting - WP6
3rd Technical Meeting - WP63rd Technical Meeting - WP6
3rd Technical Meeting - WP6
 
2nd Technical Meeting - WP2
2nd Technical Meeting - WP22nd Technical Meeting - WP2
2nd Technical Meeting - WP2
 
Kick-Off Meeting - WP7
Kick-Off Meeting - WP7Kick-Off Meeting - WP7
Kick-Off Meeting - WP7
 
Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2Slope Final Review Meeting - WP2
Slope Final Review Meeting - WP2
 

En vedette

Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8SLOPE Project
 
3rd Technical Meeting - WP4
3rd Technical Meeting - WP43rd Technical Meeting - WP4
3rd Technical Meeting - WP4SLOPE Project
 
Mid-term Review Meeting - WP5
Mid-term Review Meeting - WP5Mid-term Review Meeting - WP5
Mid-term Review Meeting - WP5SLOPE Project
 
Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2SLOPE Project
 
SLOPE Final Conference - novel planning tool
SLOPE Final Conference - novel planning toolSLOPE Final Conference - novel planning tool
SLOPE Final Conference - novel planning toolSLOPE Project
 
4th Technical Meeting - WP5
4th Technical Meeting - WP54th Technical Meeting - WP5
4th Technical Meeting - WP5SLOPE Project
 
1st Technical Meeting - WP6
1st Technical Meeting - WP61st Technical Meeting - WP6
1st Technical Meeting - WP6SLOPE Project
 
Kick-Off Meeting - WP4
Kick-Off Meeting - WP4Kick-Off Meeting - WP4
Kick-Off Meeting - WP4SLOPE Project
 
SLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomassSLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomassSLOPE Project
 
Kick-Off Meeting - WP8
Kick-Off Meeting - WP8Kick-Off Meeting - WP8
Kick-Off Meeting - WP8SLOPE Project
 
SLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of treesSLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of treesSLOPE Project
 
4th Technical Meeting - WP7
4th Technical Meeting - WP74th Technical Meeting - WP7
4th Technical Meeting - WP7SLOPE Project
 
1st Technical Meeting - WP5
1st Technical Meeting - WP51st Technical Meeting - WP5
1st Technical Meeting - WP5SLOPE Project
 
Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1SLOPE Project
 
1st Technical Meeting - WP4
1st Technical Meeting - WP41st Technical Meeting - WP4
1st Technical Meeting - WP4SLOPE Project
 
1st Technical Meeting - WP1
1st Technical Meeting - WP11st Technical Meeting - WP1
1st Technical Meeting - WP1SLOPE Project
 

En vedette (16)

Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8Mid-term Review Meeting - WP8
Mid-term Review Meeting - WP8
 
3rd Technical Meeting - WP4
3rd Technical Meeting - WP43rd Technical Meeting - WP4
3rd Technical Meeting - WP4
 
Mid-term Review Meeting - WP5
Mid-term Review Meeting - WP5Mid-term Review Meeting - WP5
Mid-term Review Meeting - WP5
 
Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2Mid-term Review Meeting - WP2
Mid-term Review Meeting - WP2
 
SLOPE Final Conference - novel planning tool
SLOPE Final Conference - novel planning toolSLOPE Final Conference - novel planning tool
SLOPE Final Conference - novel planning tool
 
4th Technical Meeting - WP5
4th Technical Meeting - WP54th Technical Meeting - WP5
4th Technical Meeting - WP5
 
1st Technical Meeting - WP6
1st Technical Meeting - WP61st Technical Meeting - WP6
1st Technical Meeting - WP6
 
Kick-Off Meeting - WP4
Kick-Off Meeting - WP4Kick-Off Meeting - WP4
Kick-Off Meeting - WP4
 
SLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomassSLOPE Final Conference - online purchase of timber and biomass
SLOPE Final Conference - online purchase of timber and biomass
 
Kick-Off Meeting - WP8
Kick-Off Meeting - WP8Kick-Off Meeting - WP8
Kick-Off Meeting - WP8
 
SLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of treesSLOPE Final Conference - electronic marking of trees
SLOPE Final Conference - electronic marking of trees
 
4th Technical Meeting - WP7
4th Technical Meeting - WP74th Technical Meeting - WP7
4th Technical Meeting - WP7
 
1st Technical Meeting - WP5
1st Technical Meeting - WP51st Technical Meeting - WP5
1st Technical Meeting - WP5
 
Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1Mid-term Review Meeting - WP1
Mid-term Review Meeting - WP1
 
1st Technical Meeting - WP4
1st Technical Meeting - WP41st Technical Meeting - WP4
1st Technical Meeting - WP4
 
1st Technical Meeting - WP1
1st Technical Meeting - WP11st Technical Meeting - WP1
1st Technical Meeting - WP1
 

Similaire à 3rd Technical Meeting - WP3

IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)
IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)
IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)IRJET Journal
 
Iirdem design and implementation of finger writing in air by using open cv (c...
Iirdem design and implementation of finger writing in air by using open cv (c...Iirdem design and implementation of finger writing in air by using open cv (c...
Iirdem design and implementation of finger writing in air by using open cv (c...Iaetsd Iaetsd
 
Performance Analysis of VoIP by Communicating Two Systems
Performance Analysis of VoIP by Communicating Two Systems Performance Analysis of VoIP by Communicating Two Systems
Performance Analysis of VoIP by Communicating Two Systems IOSR Journals
 
IRJET- IoT based Smart Helmet for Coal Mining Tracking
IRJET- IoT based Smart Helmet for Coal Mining TrackingIRJET- IoT based Smart Helmet for Coal Mining Tracking
IRJET- IoT based Smart Helmet for Coal Mining TrackingIRJET Journal
 
IRJET-Raspberry Pi Based Reader for Blind People
IRJET-Raspberry Pi Based Reader for Blind PeopleIRJET-Raspberry Pi Based Reader for Blind People
IRJET-Raspberry Pi Based Reader for Blind PeopleIRJET Journal
 
IPLOOK EPC product information
IPLOOK EPC product informationIPLOOK EPC product information
IPLOOK EPC product informationIPLOOK Networks
 
Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...
Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...
Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...Flink Forward
 
slide_rftrack_22082015
slide_rftrack_22082015slide_rftrack_22082015
slide_rftrack_22082015Marco Rainone
 
IPv4 to IPv6 network transformation
IPv4 to IPv6 network transformationIPv4 to IPv6 network transformation
IPv4 to IPv6 network transformationNikolay Milovanov
 
openstackreferencearchitecturewhitepaper
openstackreferencearchitecturewhitepaperopenstackreferencearchitecturewhitepaper
openstackreferencearchitecturewhitepaperRichard Haigh
 
Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...
Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...
Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...IRJET Journal
 
Venkatesh_updated_Resume
Venkatesh_updated_ResumeVenkatesh_updated_Resume
Venkatesh_updated_Resumevenkatpip
 
AtifBhatti resume
AtifBhatti resumeAtifBhatti resume
AtifBhatti resumeAtif Bhatti
 
Resume_Ray_OConnell_2015_1
Resume_Ray_OConnell_2015_1Resume_Ray_OConnell_2015_1
Resume_Ray_OConnell_2015_1Ray O'Connell
 

Similaire à 3rd Technical Meeting - WP3 (20)

IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)
IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)
IRJET- Implementation of FSK Transceiver using Software Defined Radio (SDR)
 
Iirdem design and implementation of finger writing in air by using open cv (c...
Iirdem design and implementation of finger writing in air by using open cv (c...Iirdem design and implementation of finger writing in air by using open cv (c...
Iirdem design and implementation of finger writing in air by using open cv (c...
 
Nasa final report
Nasa final reportNasa final report
Nasa final report
 
Performance Analysis of VoIP by Communicating Two Systems
Performance Analysis of VoIP by Communicating Two Systems Performance Analysis of VoIP by Communicating Two Systems
Performance Analysis of VoIP by Communicating Two Systems
 
Profibus system engineering and monitoring - Andy Verwer and Peter Thomas
Profibus system engineering and monitoring - Andy Verwer and Peter ThomasProfibus system engineering and monitoring - Andy Verwer and Peter Thomas
Profibus system engineering and monitoring - Andy Verwer and Peter Thomas
 
IRJET- IoT based Smart Helmet for Coal Mining Tracking
IRJET- IoT based Smart Helmet for Coal Mining TrackingIRJET- IoT based Smart Helmet for Coal Mining Tracking
IRJET- IoT based Smart Helmet for Coal Mining Tracking
 
IRJET-Raspberry Pi Based Reader for Blind People
IRJET-Raspberry Pi Based Reader for Blind PeopleIRJET-Raspberry Pi Based Reader for Blind People
IRJET-Raspberry Pi Based Reader for Blind People
 
IPLOOK EPC product information
IPLOOK EPC product informationIPLOOK EPC product information
IPLOOK EPC product information
 
Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...
Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...
Virtual Flink Forward 2020: Keynote: The Evolution of Data Infrastructure at ...
 
Resume General
Resume GeneralResume General
Resume General
 
slide_rftrack_22082015
slide_rftrack_22082015slide_rftrack_22082015
slide_rftrack_22082015
 
IPv4 to IPv6 network transformation
IPv4 to IPv6 network transformationIPv4 to IPv6 network transformation
IPv4 to IPv6 network transformation
 
openstackreferencearchitecturewhitepaper
openstackreferencearchitecturewhitepaperopenstackreferencearchitecturewhitepaper
openstackreferencearchitecturewhitepaper
 
Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...
Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...
Prediction of Wireless Sensor Network and Attack using Machine Learning Techn...
 
TransPAC2 Workplan - Measurement (v9)
TransPAC2 Workplan - Measurement (v9)TransPAC2 Workplan - Measurement (v9)
TransPAC2 Workplan - Measurement (v9)
 
LVTS Projects
LVTS ProjectsLVTS Projects
LVTS Projects
 
MONITORING FIXTURES OF CNC MACHINE
MONITORING FIXTURES OF CNC MACHINEMONITORING FIXTURES OF CNC MACHINE
MONITORING FIXTURES OF CNC MACHINE
 
Venkatesh_updated_Resume
Venkatesh_updated_ResumeVenkatesh_updated_Resume
Venkatesh_updated_Resume
 
AtifBhatti resume
AtifBhatti resumeAtifBhatti resume
AtifBhatti resume
 
Resume_Ray_OConnell_2015_1
Resume_Ray_OConnell_2015_1Resume_Ray_OConnell_2015_1
Resume_Ray_OConnell_2015_1
 

Plus de SLOPE Project

Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8SLOPE Project
 
Slope Final Review Meeting - Introduction
Slope Final Review Meeting - Introduction Slope Final Review Meeting - Introduction
Slope Final Review Meeting - Introduction SLOPE Project
 
Slope Final Review Meeting - WP5
Slope Final Review Meeting - WP5Slope Final Review Meeting - WP5
Slope Final Review Meeting - WP5SLOPE Project
 
SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3SLOPE Project
 
SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4SLOPE Project
 
SLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarderSLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarderSLOPE Project
 
SLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forestSLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forestSLOPE Project
 
SLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systemsSLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systemsSLOPE Project
 
SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3SLOPE Project
 
SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4SLOPE Project
 
SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1SLOPE Project
 
SLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machinesSLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machinesSLOPE Project
 
SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5SLOPE Project
 
SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4SLOPE Project
 
SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2SLOPE Project
 
SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1SLOPE Project
 
SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2SLOPE Project
 
SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2SLOPE Project
 
SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1SLOPE Project
 
SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7SLOPE Project
 

Plus de SLOPE Project (20)

Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8Slope Final Review Meeting - WP8
Slope Final Review Meeting - WP8
 
Slope Final Review Meeting - Introduction
Slope Final Review Meeting - Introduction Slope Final Review Meeting - Introduction
Slope Final Review Meeting - Introduction
 
Slope Final Review Meeting - WP5
Slope Final Review Meeting - WP5Slope Final Review Meeting - WP5
Slope Final Review Meeting - WP5
 
SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3SLOPE 2nd workshop - presentation 3
SLOPE 2nd workshop - presentation 3
 
SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4SLOPE 2nd workshop - presentation 4
SLOPE 2nd workshop - presentation 4
 
SLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarderSLOPE Final Conference - innovative cable yarder
SLOPE Final Conference - innovative cable yarder
 
SLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forestSLOPE Final Conference - sensors for timber grading in forest
SLOPE Final Conference - sensors for timber grading in forest
 
SLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systemsSLOPE Final Conference - remote sensing systems
SLOPE Final Conference - remote sensing systems
 
SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3SLOPE 3rd workshop - presentation 3
SLOPE 3rd workshop - presentation 3
 
SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4SLOPE 3rd workshop - presentation 4
SLOPE 3rd workshop - presentation 4
 
SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1SLOPE 3rd workshop - presentation 1
SLOPE 3rd workshop - presentation 1
 
SLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machinesSLOPE Final Conference - intelligent machines
SLOPE Final Conference - intelligent machines
 
SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5SLOPE 4th workshop - presentation 5
SLOPE 4th workshop - presentation 5
 
SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4SLOPE 4th workshop - presentation 4
SLOPE 4th workshop - presentation 4
 
SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2SLOPE 4th workshop - presentation 2
SLOPE 4th workshop - presentation 2
 
SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1SLOPE 4th workshop - presentation 1
SLOPE 4th workshop - presentation 1
 
SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2SLOPE 3rd workshop - presentation 2
SLOPE 3rd workshop - presentation 2
 
SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2SLOPE 2nd workshop - presentation 2
SLOPE 2nd workshop - presentation 2
 
SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1SLOPE 2nd workshop - presentation 1
SLOPE 2nd workshop - presentation 1
 
SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7SLOPE 1st workshop - presentation 7
SLOPE 1st workshop - presentation 7
 

Dernier

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 

Dernier (20)

Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 

3rd Technical Meeting - WP3

  • 1. Cork 19/jan/2016 Project SLOPE 1 WP 3 – Integration of novel intelligent harvesting systems operating in mountain areas (hardware development)
  • 3. Foreword Wp 3 is focused on the set up of machines and tools required to create an intelligent interaction from rfid tag reader to black box back up with innovative machinery covering the complete supply chain in harvesting operations on steep terrains. The aim is to improve forestry workers safety, productivity together with terrain sustainability.
  • 4. Foreword Technical innovation required will be implemented in machines which will be ready to function to perform real forestry operations on difficult areas.
  • 5. Foreword The critical part of the wp 3 is to be able to manage interaction among different machines and components keeping functionality also with relevant changes carried out on the machines. We do believe that we will be able to successfully manage the wp with the most suitable components able to collect and transmit perfect data along the supply chain
  • 6. Mitigating action undertaken New partner in the project for the processor head part. Dow amendment Task 3.2 changed with the purchase of a new processor head and the analysis required Start of wp 3 in month 6 affected by amendment and mitigating action as reported previously Suitable components choice and their availability
  • 7. We will implement information with the other partners to have the suitable components (antenna, reader and interface pc and its programming) to proceed with the deliverable to be submitted in month 26. What we will be doing to finalise deliverable 3.3
  • 8. Let's see what we have been doing since last January
  • 9.
  • 11. Task 3.3 parts Tecno carriage Chockers Rope launcher
  • 12. Tecno carriage work status The carriage is ready. We still need to implement the interface pc with its software, the modification on existing software with laboratory test to verify interaction. A mechanical part is being installed now for the antenna. It will be a movable part to be lifted upward and downward to protect the component from the logs We have planned testing activities with Graphitech and CNR at the end of January, beginning of February. http://youtu.be/ihXUCTBtoVU
  • 13. Chockers work status Chokers are ready. The mechanical part is ready. We still need to manage interaction between them and the new software Testing activities will be carried out also between Tecno carriage and the Chockers
  • 14. Synthetic rope launcher EASER status The prototype is ready. We have carried out testing activities up to 500 mt. We met difficulties due to the unwrapping of the textile rope. We have newly re-designed the system and currently we are working on testing activities with a new component tailored to our needs The new project will consider the launch of the rope without the need on unwrapping from the winches.
  • 15. Synthetic rope launcher EASER status
  • 16. Synthetic rope launcher EASER status
  • 17. Synthetic rope launcher EASER status
  • 18. Wp3 needs testing in machines and component interactions. We will proceed with the interface activities between the carriage and the processor head first in laboratory and then on field 3.3 - 3.4
  • 19. Contact info Diego Graifenberg: graifenberg@gmail.com
  • 21. Mid termreviewmeeting 19th-21st January2016 Overview • Status: ongoing(70%) • Duration: 17 months (from M9 to M25) • Involved partners ‐ leader: Compolab ‐ participants:CNR, BOKU, Greifenberg • Aim: add to a commercial processorhead grading and marking capabilities while preservingthe existingones • Output: D3.04 (P type deliverable, due to M25)
  • 22. Previous status ofactivities Mid termreviewmeeting 19th-21st January2016
  • 23. Performed activities Reverse engineering activities (Task3.2) completed Deliverable D.3.09submitted inSeptember 2015 Mid termreviewmeeting 19th-21st January2016
  • 24. Performedactivities Designof thenovel intelligent processor head Mid termreviewmeeting 19th-21st January2016
  • 25.  SWquality index – Described inD4.05  HIqualityindex – Described in D4.04 NIR qualityindex –Described in D4.03 Stress wave system Hyperspectralimaging system Near infraredimaging system RFIDlabeller Performedactivities Envisaged sub-system Cutting forces evaluation system  CPqualityindex – Described inD4.06 Mid termreviewmeeting 19th-21st January2016
  • 28. Performedactivities Stress wave evaluation system Lasermeasurementsystem Longitudinalaxial modes analysis withthe resonancemethod Lasertriangulationsensorableto detectand measuretheinducedfreevibrationof the tree Mid termreviewmeeting 19th-21st January2016 Accelerometersmeasurementsystem Wavepressuretimeof flight measurementsinthe processedlogs Composedbytwoaccelerometersand a sensorized hammerthat provides themechanicalstimulusandtriggersignal
  • 29. Performedactivities Stress wave evaluation system Mid termreviewmeeting 19th-21st January2016
  • 30. Performedactivities Stress wave evaluation system Mid termreviewmeeting 19th-21st January2016
  • 31. Mid termreviewmeeting 19th-21st January2016 Performedactivities Hyperspectral imagingsystem + NIR imagingsystem HyperspectralandNIRsensorswill bepositionedona lifting/loweringbar(socalled scanbar)paralleltothechainsawbar and placedin aseparated carterforprotectionfromdirty,lubricating oil andchipping Sensorsneed specificand verysmalldistance(~3mm)fromlog surface Velocityprofileof scanbarneed tobedefined
  • 32. Performedactivities Hyperspectral imagingsystem + NIR imagingsystem Mid termreviewmeeting 19th-21st January2016
  • 33. Performedactivities RFIDlabeller RFIDtagswill beplaced onthe Systemwill beplaced ona movable barand will becomposedby: • RFIDtagroll • RFIDloading andcutting systemsystem • Staplersystem • RFIDantenna • RFIDreader Mid termreviewmeeting 19th-21st January2016 crosssection ofeach log RFIDtagwill befixed onlogs by staple(mostreliablesystem) RFIDtags Minimumlog diameter(~20cm) Logcross section
  • 37. Actual activities status Mid termreviewmeeting 19th-21st January2016 Designofthenovelintelligentprocessorheadiscompleted Sensorshavebeen selected, purchasedand arrived NationalInstrumentscomponentsforsensorsacquisition havebeen selected, purchased and arrived NationalInstrumentscomponentsforthenewmachinecontrolhavebeen selected and purchased IndustrialPChavebeen selected, purchasedand arrived Actuators: hydrauliccylindersforstress wavesystemand RFIDlabeller designed andordered electrical actuatorsforscan barandRFIDlabeller selected andpurchased
  • 38. Mid termreviewmeeting 19th-21st January2016 Ongoing activities Designofharnesswiring Designofaddedhydrauliccircuit Electricalpowersupplysystem Productionofthedesignedcustomparts Assemblyofthenovelprocessorhead D.3.04isplannedtobecompletedbytheendofMarch2016
  • 40. Cork 19/jan/2016 Project SLOPE 40 T 3.5 - Intelligent transport truck Cork, January 19th, 2016
  • 41. Cork 19/jan/2016 Scope 41  Status: 100%  Length: 12 months (M12 to M24)  Partners involved:  ITENE (leader), CNR, MHG, BOKU  Aim: Track trucks and loaded logs and send the information into the SLOPE system  Output: Deliverable D3.05 (finished)
  • 45. Cork 19/jan/2016 Hardware 45  Raspberry Pi 2 Model B  900MHz Quad core ARM V7 processor  1GB of RAM  GlobalSat BU-353-S4 USB GPS - GPS data acquisition  Huawei E3256 USB GPRS – GPRS connection  Belkin F8T013-1 – Bluetooth USB adapter  Edimax EW-7811Un – Wireless USB adapter  CAEN R1240I – qID – portable RFID reader
  • 46. Cork 19/jan/2016 Software 46  Raspbian Linux distribution as an operative system. Raspbian is a free operating system based on Debian and optimized for the rpi hardware.  PostgreSQL as a database software. PostgreSQL is cross platform, open source and free to use.  Python 3 as programming language. Python is a general- purpose, object-oriented, high-level programming language defined for code readability. Python is free and open source.
  • 47. Cork 19/jan/2016 Main Screen 47 Main screen to engage the system and monitor status
  • 48. Cork 19/jan/2016 Test Screen 48 Test screen to try the different parts of the system and check functionalities.
  • 50. Cork 19/jan/2016 Manual RFID Reader Screen 50 Manual RFID Screen to control and monitor the activity of the portable RFID reader.
  • 51. Cork 19/jan/2016 Next steps 51  Optimize software and functioning - T7.2, T7.3  Prepare participation in SLOPE pilots – T7.3
  • 52. Cork 19/jan/2016 Contact info 52  Juan de Dios Díaz (juan.diaz@itene.com)  Emilio Gonzalez (egonzalez@itene.com)  Thanks for your attention!!
  • 53. Cork 19/jan/2016 Task 3.6: data management backup Objectives The goals of this task are: • to develop system for data exchange between hardware in field and central computer of FIS • to provide a data backup strategy
  • 54. Cork 19/jan/2016 Task 3.6: data management backup Task Leader: CNR Task Partecipants: Compolab, Greifenberg, Graphitech, Itene, (Treemetrics) March 2015 to February 2016 Status: 50% D.3.07 Black-box for backup and data transmission Prototype: portable and internal powered black box for daily/weekly data back up and for data transmission in areas without GPRS coverage (M.25)
  • 55. Cork 19/jan/2016  the “black box” solution is a portable storage (SSHD or similar)  the external storage will be connected with USB to the industrial PC hosted by the excavator  it is used for storing critical data (backup)  the dedicated GPRS module (USB) is installed in industrial PC and is used for communication with the central server in a case of the network coverage  the portable storage is transferred to the office / operator house and after connecting to internet, automatically synchronizing data with the database in a case of no network coverage in forest Task 3.6: data management backup detailed concept
  • 56. industrial PC Database banana PI computer FRID weight fuel ??? Data storage CP NIR HI SW camera kinect
  • 57. banana PI CAN-bus RFID antena RFID controler load cell A/D converterWIFI antena PC processor CAN-bus CAN-bus USB Fuel consumption Position Time of installing log Time of cycle RFID of logs Total weight of logs TECHNO PLC
  • 58. banana PI SSD “black box” cRIO - control PC processor USB SW sensors Fuel consumption Position Time of installing log Time of cycle RFID of logs Total weight of logs WIFI antena GPRS/UMTS USB LAN cDAQ - sensors LAN Data from FIS: quality indexes for RFID trees, suggested cutting plan Data for FIS: logs quality, quantity, suitability for each RFID log Backup of all data, including WP4 quality indexed pressure sensors NIR sensors HI sensors CF sensors termometer actuators guages encoders
  • 60. Cork 19/jan/2016  select and purchase optimal hardware (CNR, Graphitech and COMPOLAB)  integrate the hardware modules with PC chassis (CNR and COMPOLAB)  define structures of data (both; to be transmitted via 3G and stored for further use in FIS (Graphitech + Treemetrics)  to develop the software for communication of the cable crane and central computer (Greifenberg, CNR and COMPOLAB)  to develop the software for field instruments and GPRS communication (CNR and COMPOLAB)  to develop software tools for merging the data with FIS (Graphitech)  to extensively test the solution both in lab and in field (all partners) Task 3.6: data management backup work plan