SlideShare une entreprise Scribd logo
1  sur  9
Télécharger pour lire hors ligne
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
In submitting this assignment, I certify that all this material is my own work, 
except where I have indicated otherwise with appropriate references. 
The steps you are required to take in constructing your Practical Scenario assignment are 
provided below as an aid to organising your answer. For example, you might like to use these 
points as a basis for section headings. 
1) Give an outline of the project that is the focus of your practical scenario, in 
Order to provide a context for your responses to the following: [5 marks] 
Page 1 of 9 
2) 
Drawing on your practical scenario: 
a) Describe the basis on which your contract selection was made and evaluate 
how well the contract generally performed against your contract selection 
criteria. [25 marks] 
b) List the aspects of design liability that were dealt with under the contract, 
Explaining why each was regarded as a significant feature of the project. 
[20 marks] 
c) How was risk apportioned in the contract? Evaluate the extent to which the 
Contract provisions met the actual on-site conditions encountered. [20 marks] 
d) What unforeseen problem(s) arose? [30 marks] 
i) Explain the basis for your choice of conflict management technique to 
settle the problem. 
Assuming the problem escalates into a full-blown dispute: 
ii) Identify and justify a choice of a preferred dispute resolution 
technique. 
iii) Analyse how the parties are likely to view each other once the dispute 
resolution technique has run its course. Were the alternatives feasible? 
Do not include the chosen standard form of contract with your answer but ensure that it is 
fully referenced. Where you include extracts from the literature or clauses/judgments from 
case law in your answer make sure they are clearly distinguished from the body of your 
answer by, for example, setting them in bold italics. Do not include unnecessary detail or 
padding. 
Maximum essay length 2,000 words (there is no minimum). 
(Write your assignment, with an appropriate title, here.)
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Section 1-Part A: Project Description 
Page 2 of 9 
Project Description 
Project: District Cooling Plant for Rihan Heights 
Location: United Arab Emirates 
Employer: MUBADALA Capital Land Real Estate L.L.C 
Architect: WS Atkins Partners Overseas 
Main Contractor: Kharafi National 
Type of Project: EPC Turnkey Project 
Type of Contract: Lump Sum Fixed Price 
Conditions of Contract: FIDIC – EPC Turnkey – First Edition 1999 
An EPC/Turnkey contract was signed between Mubadala Capital Land Real Estate and Kharafi 
National to construct a Central District Cooling Plant, Reticulation Pipes Networks and 
Installation of cooling equipment in the Energy Transfer Stations to service the Rihan Heights 
Development in Zayed Sports City- Abu Dhabi, United Arab Emirates. 
The main contractor scope includes design, procurement, delivery, construction, testing and 
commissioning, provision of spare parts and operation/maintenance of the plant for 12 months 
following commissioning and possessing the taking over certificate. 
Furthermore, the contractor is responsible for any coordination issues, which may arise with 
any other contractor(s) who may be involved in Zayed Sports City; which may include, but is 
not limited to, design changes, stockpiling the material on site and taking over work areas. 
There were two contractors, with which Kharafi has to coordinate. Firstly, the main contractor of 
Rihan Heights towers who constructed the Energy Transfer Stations rooms in basement floor 
where Kharafi is going to install the Cooling equipment. 
Secondly, the infrastructure contractor who is carrying out the utilities works which will serve 
the towers. The utilities service corridors were intersecting in plenty areas with the route of 
reticulation Pipes Networks of the District Cooling Plant.
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Section 1-Part B: Construction Law Aspects 
Law of Contract 
As per Field (2013), the law of contract was applied in the cooling plant project as follow: - 
Page 3 of 9 
• Offer and Acceptance 
Mubadala, Employer, wishes to enter into a contract for the Engineering, Procurement and 
Construction of District Cooling Plant for Rihan Heights and invited a firm price tender. 
The Employer received the tender documents of all tenderers (Offers) to evaluate all of them 
and then he accepted the offer of Kharafi awarding it the executing of the whole work under the 
offered lump sum fixed price. 
• Intention to Create a Legal Relation 
The Employer nominated Kharafi by issuing the letter of Acceptance confirming that; the 
contract documents will be issued within 45 days of issuing the letter of acceptance. Until 
finalizing the formal contract documents, the letter of acceptance together with the 
correspondences and the submitted tender shall constitute a binding contract between Kharafi 
and the Employer. 
The letter of acceptance was signed and then issued by Employer to Kharafi who accepted and 
signed it as well. 
• Agreement in the Eyes of the Law 
All the essential terms and conditions of the agreement, as was advised by Fenn et al., Mason 
and Lavers (2008:1-10), were included in the letter of acceptance, which was accepted and 
signed by both parties. These terms were; contract conditions, time for completion, 
responsibility of the Contractor towards exiting site conditions, Insurances, liquidated damages 
and advance payment. 
• Considerations 
The Employer stated in his letter of acceptance the consideration, which will be given to the 
Contractor in return back to his services. These considerations were valued as 53,166,016 
UAE Dirhams.
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Section 2: Contract Selection Criteria 
1.0 – Employer’s Selection Criteria 
The decision of employer to select EPC/Turnkey contract was based on the followings; 
Firstly, The EPC contract reduces the opportunity for claims as the design and construction 
are the single point of responsibility of one part as was stated by Huse (2002:18). In the 
traditional method of procurement the claims always result from instructions or directions given 
by the engineer. 
Secondly, getting cost certainty is a target for the employer. The Lump Sum pricing method, 
which is often used in the EPC contract enables, the Employer to get such certainty as was 
stated by Huse (2002:19). 
Thirdly, the employer needs for fast track procurement so he has chosen the EPC contract. 
The speed of procurement is another feature of the EPC contract, as was stated by Huse 
(2002:20), as it combines the two phases of design and construction. In certain cases the 
contractor may start construction before completion of design. Consequently, EPC contract can 
lead to earlier completion of project. 
Fourthly, the employer was seeking for efficiency, which is a result of EPC contracts because 
the contractor designs and builds the works so he doesn’t need time to understand the 
Employer’s design. Also the design in EPC projects always takes into consideration the 
construction method of contractor, providing more efficiency and timely completion. 
Finally, the employer needs the contractor to deliver a cooling system ‘Fit for the Purpose’ for 
which it was made. Under EPC contract, the contractor is strictly liable for delivering the fitness 
for purpose and he is responsible for the failure of the design to the standards required. 
2.0 – Contractor’s Selection Criteria 
The contract selection criteria of contractor, Kharafi, do match with the employer selection 
criteria as followings; 
• The contractor was looking for EPC contract as he has a massive experience in 
constructing cooling plants beside he owns all design capabilities, so the contractor 
doesn’t need the design to be supplied by design consultant as he can take this 
chance and get more financial profits by doing both. 
• The contractor was looking for efficiency and delivering this fast track project on time to 
maintain his image as an experienced contractor for constructing cooling plants so that 
the EPC contract is the key for achieving such targets as performing the design by his 
own will give the opportunity to consider his method of construction during the design, 
which will lead to more efficiency and completion the project on time. 
• The contractor was looking for building a long-term relationship with the employer in 
order to win future opportunities so that avoiding issuing claims was an important step 
in building such relationship. The EPC contract will let the design and construction to 
be the sole responsibility of contractor so that the claims, which always result from the 
designer faults and instructions, will be eliminated. 
Page 4 of 9
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Page 5 of 9 
Section 3: Design Liability 
1.0 - Contract Liability 
According to the contract between the Employer and Kharafi National, the contractor shall be 
responsible for the design of the works and for the accuracy of all Employer requirements 
including design criteria and calculations as was stated in FIDIC (1999:17). Even any data 
received by the contractor, from the Employer shall not relieve the contractor from his 
responsibility for the design. 
Another contract was signed between Kharafi and piles subcontractor and according to this 
contract, the design and executing of piles is the sole responsibility of the subcontractor but the 
site investigation was the responsibility of Kharafi. 
One event was encountered during the project as follows; - 
Two of the executed piles were failed in the pile tests thus the subcontractor claimed for the 
cost of demolishing the piles and re-digging it because the consultant and Kharafi delivered 
and signed off the piles. The main contractor, Kharafi, rejected the claim as the sole 
responsibility of that failure is still with the subcontractor, according to the signed contract, even 
if the work was delivered and signed off. 
2.0 - Law of Tort Liability 
Kharafi owned a duty of care for its design and for delivering the cooling plant, which has to be 
fit for the purpose. Furthermore, Kharafi had a duty of care regarding visiting the site to have 
fully and properly informed itself of the site conditions. 
During the project life cycle, there was no evidence for any deviations from Kharafi side for its 
duty of care towards the Employer as there were no records for damages during the defect 
liability period.
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Section 4: Unforeseen Ground Conditions Risk 
The Employer assigned the risk of ground conditions to the contractor, Kharafi, as during the 
tender stage Kharafi was invited as a nominated contractor to visit the site and execute the 
necessary ground investigations to be fully aware of site ground conditions for which they will 
be liable according to the contract’s particular conditions. 
The preliminary investigations were carried out in the tender stage, showed that the nature of 
site soil doesn’t require digging piles so that Kharafi didn’t price for such piles. After awarding 
the project and getting into site to start carrying out more investigations it was appeared on the 
surface that it was required to dig and cast piles on which the plant foundations will be rested. 
The contractor executed the required piles in a cost of 200,000 AED. 
Apparently, the contractor encountered loss due to the possession of the ground conditions risk 
as the investigation which were done during the tender weren’t precise enough to enable the 
tender team to include the price of piles in the their offer to employer. 
Furthermore, the execution of the required piles didn’t generate only the loss of 200,000 AED 
but it allowed for more fiscal losses as follows: - 
• The plant structure was on the critical path and the required duration of 25 days to 
execute the piles weren’t planned in the schedule of project. These 25 days caused 
delays to the critical path and thus to the project completion date. The contractor 
decided accelerating the schedule by increasing the manpower and extending the 
working hours, which increased the expenditures. 
Page 6 of 9
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Page 7 of 9 
Section 5: Managing Conflict 
Clause 5.1 of the project contract’s particular conditions stated that the contractor should 
ensure that the works are fully coordinated and integrated with the activities of other 
contractors. Therefore the coordination between Kharafi and the other contractors is the sole 
responsibility of Kharafi. A coordination meeting was held between Kharafi and the 
infrastructure contractor to coordinate the work amicably and the most critical issue was the 
dewatering system of the infrastructure contractor, which is located inside the boundary of 
Ancillary building’s foundations, one of the cooling plant structures. 
The Planned date to start the work in the building’s foundations was set to be on 22-Feb-11 
thus the infrastructure contractor have to remove his system before this date as was agreed in 
that meeting. 
Unlike the agreed sequence of work, the infrastructure contractor didn’t remove his dewatering 
system before 22-Feb-11 to enable Kharafi starting their foundation works. The result of the 
aforementioned situation was delays of 20 days to the completion date of the cooling plant so 
that Kharafi raised a claim asking for an extension of time and prolongation cost. 
At this point the conflict between Kharafi and employer occurred because the employer referred 
to the contract clause 5.1, which stated clearly that Kharafi owns the coordination responsibility, 
therefore the employer rejected the claim in accordance with this clause. 
Kharafi asked for a meeting to negotiate with employer the validity of their claim. Kharafi started 
the negotiation meeting with a positional approach stating that the coordination with the 
infrastructure contractor occurred according to the formal minutes of meeting so the 
encountered delays weren’t due to the lack of coordination but were due to the fault of 
infrastructure contractor as he was using an old dewatering system, which stopped within 7 
days after operating it. Kharafi confirmed that they notified the infrastructure contractor several 
times; however, it is not Kharafi’s responsibility to fix the system or force the other contractor to 
replace his faulty system. Kharafi started with a positional approach as they think the delay 
occurred was out of their control and the coordination as requested by contract was done as 
was proved by the recorded minutes of meeting. 
However, the employer insisted that Kharafi owns the sole responsibility of the event according 
to the contract’s clause 5.1 plus in fact Kharafi has done a mistake by not informing the 
employer in writing with that event. 
Kharafi then had taken the principled approach to be more flexible in sorting out the issue to 
maintain the relationship with an important employer like MUBADALA. Kharafi stated that they 
insisting on their right to have an extension of time but they will withdraw their claim for 
prolongation cost.
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Page 8 of 9 
Section 6: Dispute Resolution 
There are different techniques by which the disputes can be resolved such as Mediation, 
Adjudication, Arbitration and Litigation. The preferred techniques are the mediation, 
adjudication and arbitration because they are faster, and cheaper than the litigation besides 
they maintain the confidentiality rather than the litigation where the case will become public and 
will attract the press interest as was stated by Fenn et al., Mason and Lavers (2008:7-32) 
The chosen techniques as per clauses 20.2, 20.4 and 20.5 of the general conditions of the 
contract, FIDIC (1999:53-55), between Kharafi and Employer were Adjudication and Arbitration. 
The dispute wasn’t resolved during the negotiation the employer adopted a positional approach 
and clause 5.1 blocked the negotiation as the employer referred to this clause, which confirms 
that the coordination between the work of Kharafi and the other contractors is the sole 
responsibility of the former. 
On the other hand the plant contractor confirmed that they complied with the contract clause by 
coordinating closely with the other contractor, however, the faulty dewatering system is out of 
the plant contractor control as they notified him with the potential delays but they cant direct the 
other contractor to change his system specially the replacement of dewatering system will incur 
additional cost to that contractor. 
During the arbitration, it was found that Kharafi wasn’t entitled to an extension of time because; 
• They are liable for such delays because Kharafi owns the sole responsibility of 
coordination with the infrastructure contractor. 
• They had to send notification to the Employer regarding the delay issue to enable him 
directing the infrastructure contractor, according to the contract between them, to 
replace such faulty system.
AR50123 Assignment 
Name: (Sameh Kandil Mohammed Ibrahim) 
Page 9 of 9 
References 
1. Field, Chris, 2013 (Viewed 2013-04-04). Elements of a Contract. 
www.lawhandbook.org.au/handbook/ch12s01s02.php. 
2. Fenn Peter et al., Mason Jim, Lavers Anthony. (2008). Unit3 – AR50123: 
Construction Law. United Kingdom: Distance Learning Unit, University of 
Bath. 
3. FIDIC, 1999. Conditions of Contract for EPC/Turnkey Projects. 1st ed. 
Federation Internationale des Ingenieurs-Conseils (FIDIC). ISBN 2-88432- 
021-0. 
4. Huse, Joseph A., 2002. Understanding and Negotiating Turnkey and EPC 
Contracts. 2nd ed. London: Sweet & Maxwell Ltd. ISBN 0 421 674105.

Contenu connexe

Tendances

Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
Jamal Nelson, CCM
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report Sample
Elias Ibrahim
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Adrias TAN
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
Iffat Al Gharbi
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
JB Nartey
 

Tendances (20)

Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report Sample
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Recent NEC3 Case Review and its Application
Recent NEC3 Case Review and its ApplicationRecent NEC3 Case Review and its Application
Recent NEC3 Case Review and its Application
 
Cl report final
Cl report finalCl report final
Cl report final
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...Why does an eot not automatically entitle a contractor to prolongation costs ...
Why does an eot not automatically entitle a contractor to prolongation costs ...
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
DEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSESDEFECTS LIABILITY AND TAKING OVER CLAUSES
DEFECTS LIABILITY AND TAKING OVER CLAUSES
 

Similaire à Kandil_Sameh_AR50123

Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
Maatla Moadi
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
Melvin Lim
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
DarrenTofu
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
Praveen Premkumar
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docx
FairFASST
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
Egyptian Engineers Association
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
Yong Sy
 

Similaire à Kandil_Sameh_AR50123 (20)

Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Fidic
FidicFidic
Fidic
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Construction law cl3 (completed)
Construction law cl3 (completed)Construction law cl3 (completed)
Construction law cl3 (completed)
 
contract procedure
contract procedurecontract procedure
contract procedure
 
ZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docxZA CONTRACT AL NOOR.docx
ZA CONTRACT AL NOOR.docx
 
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdfAN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 

Plus de Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

Plus de Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 

Kandil_Sameh_AR50123

  • 1. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) In submitting this assignment, I certify that all this material is my own work, except where I have indicated otherwise with appropriate references. The steps you are required to take in constructing your Practical Scenario assignment are provided below as an aid to organising your answer. For example, you might like to use these points as a basis for section headings. 1) Give an outline of the project that is the focus of your practical scenario, in Order to provide a context for your responses to the following: [5 marks] Page 1 of 9 2) Drawing on your practical scenario: a) Describe the basis on which your contract selection was made and evaluate how well the contract generally performed against your contract selection criteria. [25 marks] b) List the aspects of design liability that were dealt with under the contract, Explaining why each was regarded as a significant feature of the project. [20 marks] c) How was risk apportioned in the contract? Evaluate the extent to which the Contract provisions met the actual on-site conditions encountered. [20 marks] d) What unforeseen problem(s) arose? [30 marks] i) Explain the basis for your choice of conflict management technique to settle the problem. Assuming the problem escalates into a full-blown dispute: ii) Identify and justify a choice of a preferred dispute resolution technique. iii) Analyse how the parties are likely to view each other once the dispute resolution technique has run its course. Were the alternatives feasible? Do not include the chosen standard form of contract with your answer but ensure that it is fully referenced. Where you include extracts from the literature or clauses/judgments from case law in your answer make sure they are clearly distinguished from the body of your answer by, for example, setting them in bold italics. Do not include unnecessary detail or padding. Maximum essay length 2,000 words (there is no minimum). (Write your assignment, with an appropriate title, here.)
  • 2. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Section 1-Part A: Project Description Page 2 of 9 Project Description Project: District Cooling Plant for Rihan Heights Location: United Arab Emirates Employer: MUBADALA Capital Land Real Estate L.L.C Architect: WS Atkins Partners Overseas Main Contractor: Kharafi National Type of Project: EPC Turnkey Project Type of Contract: Lump Sum Fixed Price Conditions of Contract: FIDIC – EPC Turnkey – First Edition 1999 An EPC/Turnkey contract was signed between Mubadala Capital Land Real Estate and Kharafi National to construct a Central District Cooling Plant, Reticulation Pipes Networks and Installation of cooling equipment in the Energy Transfer Stations to service the Rihan Heights Development in Zayed Sports City- Abu Dhabi, United Arab Emirates. The main contractor scope includes design, procurement, delivery, construction, testing and commissioning, provision of spare parts and operation/maintenance of the plant for 12 months following commissioning and possessing the taking over certificate. Furthermore, the contractor is responsible for any coordination issues, which may arise with any other contractor(s) who may be involved in Zayed Sports City; which may include, but is not limited to, design changes, stockpiling the material on site and taking over work areas. There were two contractors, with which Kharafi has to coordinate. Firstly, the main contractor of Rihan Heights towers who constructed the Energy Transfer Stations rooms in basement floor where Kharafi is going to install the Cooling equipment. Secondly, the infrastructure contractor who is carrying out the utilities works which will serve the towers. The utilities service corridors were intersecting in plenty areas with the route of reticulation Pipes Networks of the District Cooling Plant.
  • 3. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Section 1-Part B: Construction Law Aspects Law of Contract As per Field (2013), the law of contract was applied in the cooling plant project as follow: - Page 3 of 9 • Offer and Acceptance Mubadala, Employer, wishes to enter into a contract for the Engineering, Procurement and Construction of District Cooling Plant for Rihan Heights and invited a firm price tender. The Employer received the tender documents of all tenderers (Offers) to evaluate all of them and then he accepted the offer of Kharafi awarding it the executing of the whole work under the offered lump sum fixed price. • Intention to Create a Legal Relation The Employer nominated Kharafi by issuing the letter of Acceptance confirming that; the contract documents will be issued within 45 days of issuing the letter of acceptance. Until finalizing the formal contract documents, the letter of acceptance together with the correspondences and the submitted tender shall constitute a binding contract between Kharafi and the Employer. The letter of acceptance was signed and then issued by Employer to Kharafi who accepted and signed it as well. • Agreement in the Eyes of the Law All the essential terms and conditions of the agreement, as was advised by Fenn et al., Mason and Lavers (2008:1-10), were included in the letter of acceptance, which was accepted and signed by both parties. These terms were; contract conditions, time for completion, responsibility of the Contractor towards exiting site conditions, Insurances, liquidated damages and advance payment. • Considerations The Employer stated in his letter of acceptance the consideration, which will be given to the Contractor in return back to his services. These considerations were valued as 53,166,016 UAE Dirhams.
  • 4. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Section 2: Contract Selection Criteria 1.0 – Employer’s Selection Criteria The decision of employer to select EPC/Turnkey contract was based on the followings; Firstly, The EPC contract reduces the opportunity for claims as the design and construction are the single point of responsibility of one part as was stated by Huse (2002:18). In the traditional method of procurement the claims always result from instructions or directions given by the engineer. Secondly, getting cost certainty is a target for the employer. The Lump Sum pricing method, which is often used in the EPC contract enables, the Employer to get such certainty as was stated by Huse (2002:19). Thirdly, the employer needs for fast track procurement so he has chosen the EPC contract. The speed of procurement is another feature of the EPC contract, as was stated by Huse (2002:20), as it combines the two phases of design and construction. In certain cases the contractor may start construction before completion of design. Consequently, EPC contract can lead to earlier completion of project. Fourthly, the employer was seeking for efficiency, which is a result of EPC contracts because the contractor designs and builds the works so he doesn’t need time to understand the Employer’s design. Also the design in EPC projects always takes into consideration the construction method of contractor, providing more efficiency and timely completion. Finally, the employer needs the contractor to deliver a cooling system ‘Fit for the Purpose’ for which it was made. Under EPC contract, the contractor is strictly liable for delivering the fitness for purpose and he is responsible for the failure of the design to the standards required. 2.0 – Contractor’s Selection Criteria The contract selection criteria of contractor, Kharafi, do match with the employer selection criteria as followings; • The contractor was looking for EPC contract as he has a massive experience in constructing cooling plants beside he owns all design capabilities, so the contractor doesn’t need the design to be supplied by design consultant as he can take this chance and get more financial profits by doing both. • The contractor was looking for efficiency and delivering this fast track project on time to maintain his image as an experienced contractor for constructing cooling plants so that the EPC contract is the key for achieving such targets as performing the design by his own will give the opportunity to consider his method of construction during the design, which will lead to more efficiency and completion the project on time. • The contractor was looking for building a long-term relationship with the employer in order to win future opportunities so that avoiding issuing claims was an important step in building such relationship. The EPC contract will let the design and construction to be the sole responsibility of contractor so that the claims, which always result from the designer faults and instructions, will be eliminated. Page 4 of 9
  • 5. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Page 5 of 9 Section 3: Design Liability 1.0 - Contract Liability According to the contract between the Employer and Kharafi National, the contractor shall be responsible for the design of the works and for the accuracy of all Employer requirements including design criteria and calculations as was stated in FIDIC (1999:17). Even any data received by the contractor, from the Employer shall not relieve the contractor from his responsibility for the design. Another contract was signed between Kharafi and piles subcontractor and according to this contract, the design and executing of piles is the sole responsibility of the subcontractor but the site investigation was the responsibility of Kharafi. One event was encountered during the project as follows; - Two of the executed piles were failed in the pile tests thus the subcontractor claimed for the cost of demolishing the piles and re-digging it because the consultant and Kharafi delivered and signed off the piles. The main contractor, Kharafi, rejected the claim as the sole responsibility of that failure is still with the subcontractor, according to the signed contract, even if the work was delivered and signed off. 2.0 - Law of Tort Liability Kharafi owned a duty of care for its design and for delivering the cooling plant, which has to be fit for the purpose. Furthermore, Kharafi had a duty of care regarding visiting the site to have fully and properly informed itself of the site conditions. During the project life cycle, there was no evidence for any deviations from Kharafi side for its duty of care towards the Employer as there were no records for damages during the defect liability period.
  • 6. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Section 4: Unforeseen Ground Conditions Risk The Employer assigned the risk of ground conditions to the contractor, Kharafi, as during the tender stage Kharafi was invited as a nominated contractor to visit the site and execute the necessary ground investigations to be fully aware of site ground conditions for which they will be liable according to the contract’s particular conditions. The preliminary investigations were carried out in the tender stage, showed that the nature of site soil doesn’t require digging piles so that Kharafi didn’t price for such piles. After awarding the project and getting into site to start carrying out more investigations it was appeared on the surface that it was required to dig and cast piles on which the plant foundations will be rested. The contractor executed the required piles in a cost of 200,000 AED. Apparently, the contractor encountered loss due to the possession of the ground conditions risk as the investigation which were done during the tender weren’t precise enough to enable the tender team to include the price of piles in the their offer to employer. Furthermore, the execution of the required piles didn’t generate only the loss of 200,000 AED but it allowed for more fiscal losses as follows: - • The plant structure was on the critical path and the required duration of 25 days to execute the piles weren’t planned in the schedule of project. These 25 days caused delays to the critical path and thus to the project completion date. The contractor decided accelerating the schedule by increasing the manpower and extending the working hours, which increased the expenditures. Page 6 of 9
  • 7. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Page 7 of 9 Section 5: Managing Conflict Clause 5.1 of the project contract’s particular conditions stated that the contractor should ensure that the works are fully coordinated and integrated with the activities of other contractors. Therefore the coordination between Kharafi and the other contractors is the sole responsibility of Kharafi. A coordination meeting was held between Kharafi and the infrastructure contractor to coordinate the work amicably and the most critical issue was the dewatering system of the infrastructure contractor, which is located inside the boundary of Ancillary building’s foundations, one of the cooling plant structures. The Planned date to start the work in the building’s foundations was set to be on 22-Feb-11 thus the infrastructure contractor have to remove his system before this date as was agreed in that meeting. Unlike the agreed sequence of work, the infrastructure contractor didn’t remove his dewatering system before 22-Feb-11 to enable Kharafi starting their foundation works. The result of the aforementioned situation was delays of 20 days to the completion date of the cooling plant so that Kharafi raised a claim asking for an extension of time and prolongation cost. At this point the conflict between Kharafi and employer occurred because the employer referred to the contract clause 5.1, which stated clearly that Kharafi owns the coordination responsibility, therefore the employer rejected the claim in accordance with this clause. Kharafi asked for a meeting to negotiate with employer the validity of their claim. Kharafi started the negotiation meeting with a positional approach stating that the coordination with the infrastructure contractor occurred according to the formal minutes of meeting so the encountered delays weren’t due to the lack of coordination but were due to the fault of infrastructure contractor as he was using an old dewatering system, which stopped within 7 days after operating it. Kharafi confirmed that they notified the infrastructure contractor several times; however, it is not Kharafi’s responsibility to fix the system or force the other contractor to replace his faulty system. Kharafi started with a positional approach as they think the delay occurred was out of their control and the coordination as requested by contract was done as was proved by the recorded minutes of meeting. However, the employer insisted that Kharafi owns the sole responsibility of the event according to the contract’s clause 5.1 plus in fact Kharafi has done a mistake by not informing the employer in writing with that event. Kharafi then had taken the principled approach to be more flexible in sorting out the issue to maintain the relationship with an important employer like MUBADALA. Kharafi stated that they insisting on their right to have an extension of time but they will withdraw their claim for prolongation cost.
  • 8. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Page 8 of 9 Section 6: Dispute Resolution There are different techniques by which the disputes can be resolved such as Mediation, Adjudication, Arbitration and Litigation. The preferred techniques are the mediation, adjudication and arbitration because they are faster, and cheaper than the litigation besides they maintain the confidentiality rather than the litigation where the case will become public and will attract the press interest as was stated by Fenn et al., Mason and Lavers (2008:7-32) The chosen techniques as per clauses 20.2, 20.4 and 20.5 of the general conditions of the contract, FIDIC (1999:53-55), between Kharafi and Employer were Adjudication and Arbitration. The dispute wasn’t resolved during the negotiation the employer adopted a positional approach and clause 5.1 blocked the negotiation as the employer referred to this clause, which confirms that the coordination between the work of Kharafi and the other contractors is the sole responsibility of the former. On the other hand the plant contractor confirmed that they complied with the contract clause by coordinating closely with the other contractor, however, the faulty dewatering system is out of the plant contractor control as they notified him with the potential delays but they cant direct the other contractor to change his system specially the replacement of dewatering system will incur additional cost to that contractor. During the arbitration, it was found that Kharafi wasn’t entitled to an extension of time because; • They are liable for such delays because Kharafi owns the sole responsibility of coordination with the infrastructure contractor. • They had to send notification to the Employer regarding the delay issue to enable him directing the infrastructure contractor, according to the contract between them, to replace such faulty system.
  • 9. AR50123 Assignment Name: (Sameh Kandil Mohammed Ibrahim) Page 9 of 9 References 1. Field, Chris, 2013 (Viewed 2013-04-04). Elements of a Contract. www.lawhandbook.org.au/handbook/ch12s01s02.php. 2. Fenn Peter et al., Mason Jim, Lavers Anthony. (2008). Unit3 – AR50123: Construction Law. United Kingdom: Distance Learning Unit, University of Bath. 3. FIDIC, 1999. Conditions of Contract for EPC/Turnkey Projects. 1st ed. Federation Internationale des Ingenieurs-Conseils (FIDIC). ISBN 2-88432- 021-0. 4. Huse, Joseph A., 2002. Understanding and Negotiating Turnkey and EPC Contracts. 2nd ed. London: Sweet & Maxwell Ltd. ISBN 0 421 674105.