SlideShare une entreprise Scribd logo
1  sur  14
Cost Indices for
Industrial Application
Dr. K. Shahzad Baig
Memorial University of Newfoundland (MUN) Canada
Cost Indexes
 Cost Index is ratio of cost today to cost in the past
• Indicates change in cost over time; therefore, they account
for the impact of inflation
• Index is dimensionless
• CPI (Consumer Price Index) is a good example
Formula for total
cost is
Finding Cost Indexes
© 2012 by McGraw-Hill All Rights Reserved15-10
Cost indexes are maintained in areas such as construction, chemical
and mechanical industries
• Updated monthly and annually; many include regionalized and
international project indexes
• Indexes in these areas are often subdivided into smaller
components and can be used in preliminary, as well as detailed
design stages
Examples are:
 Chemical Engineering Plant Cost Index (CEPCI)
www.che.com/pci
 McGraw-Hill Construction Index
www.construction.com
 US Department of Labor, Bureau of Labor Statistics
www.bls.gov
Example: Cost Index Method
© 2012 by McGraw-Hill All Rights Reserved15-9
Problem: Estimate the total cost of labor today in US dollars for a
maritime construction project using data from a similar project in
Europe completed in 1998.
Labor index, 1998: 789.6 Cost in 1998: €3.9 million
Labor index, current: 1165.8 Currently, 1 € = 1.5 US$
Solution: Let t = today and 0 = 1998 base
Ct = 3.9 million × (1165.8/789.6) = €5.76 million
= €5.76 × 1.5 = $8.64 million
Cost-Capacity Combined with Cost
Index
Multiply the cost-capacity equation by a cost index (It/I0) to
adjust for time differences and obtain estimates of current
cost (in constant-value dollars)
Example
A 100 hp air compressor costs $3000 five years ago when the cost index was
130. Estimate the cost of a 300 hp compressor today when the cost index is
255.
Solution:
Let C300 represent the cost estimate today. Exponent is 0.9 for 5-300 hp air
compressors.
C300 = 3000(300/100)0.9(255/130)
= $15,817
Study Method
The study estimate uses a list of the major equipment included in
the process, such as pumps, compressors and turbines, columns
and vessels, heat exchangers, etc.
After sizing is done, the cost is determined for each piece of
equipment.
Also called the major equipment or factored estimate, the study
estimate usually needs cost charts and process flow diagrams
the Lang factor is a ratio of the total cost of installing a process in a plant to
the cost of its major technical components
Inflation When costs are to be projected into the future
due to inflation, it is a highly speculative exercise, but it is
necessary for estimating investment costs, operating
expenses, etc.
Inflation is the increase in price of goods without a
corresponding increase in productivity. A method for
estimating an inflated cost is
where Ci = inflated cost
f1 = inflation rate the first year
f2 = inflation rate the second year
f3 = inflation rate the third year
CP = cost in a base year
𝑪𝒊 = 𝟏 + 𝒇 𝟏 𝟏 + 𝒇 𝟐 𝟏 + 𝒇 𝟑 𝑪 𝒑
The assumed inflation factors f are obtained from federal
economic reports, financial sources such as banks and
investment houses, and news media. These factors must be
reviewed periodically to update estimates.
Example , Inflation
A dryer today costs $475,000. The projected inflation rates
for the next 3 years are 3, 4.2, and 4.7 percent. Calculate the
projected cost in 3 years.
Preliminary Estimate Methods
A refinement of the Lang factor method is the Hand method.
Equipment is grouped in categories, such as heat exchangers and
pumps, and then a factor is applied to each group to obtain the
installed cost. Wroth compiled a more detailed list of installation
factors.
The Lang and Hand methods start with purchased equipment costs
whereas the Wroth method begins with delivered equipment costs,
so delivery charges must be included in the Lang and Hand methods.
At best the Lang and Hand methods will yield study quality
estimates, and the Wroth method might yield a preliminary quality
estimate.
Lang proposed three separate factors based on the type of
process plant.
For solids, the factor is 3.10;
For combined solids and fluids, 3.63;
For fluids alone, 4.74.
These factors were meant to cover all the costs associated with
the Total Installed Cost of a plant,
Lang’s Method
Total plant cost (TPC) =
= Total equipment cost (TEC) x 3 x Equipment factor
TEC = $1.5M
TPC = $1.5M X 3 X4.74 = $7.11M
Definitive Estimate Methods
Modular methods are an extension of the multiple-factor
methods and have been proposed by several authors.
It began with equipment FOB equipment costs the module
material cost was obtained. Labor for erection and setting
equipment was added to the material cost as well as indirect
costs for freight, insurance, engineering, and field expenses to
give a total module cost.
Such items as contingencies, contractors’ fees, auxiliaries, site
development land, and industrial buildings were added if
applicable.
Detailed Estimate Method
For estimates in the detailed category, a standard of account
needs to be used to prevent oversight of certain significant
items in the capital cost.
Each item in the standard is estimated and provides the capital
cost estimate;
then this estimate serves for cost control during the construction
phase of a project.
Following books were used in preparation of notes
 Blank, L., Tarquin. A. 2005. Engineering Economy. 6th Edition, McGraw-Hill.
 Eschenbach, T. G. 2003. Engineering Economy”, 2nd Edition, Oxford University Press
 Riggs, J. L., Bedworth, D. D., Randhawa, S. U. 1996. Engineering Economics”, 4th Edition, Tata McGraw-Hill.
 Riggs, J. L., West. T. M. 1986. Essentials of Engineering Economics”, 2nd Edition, McGraw-Hill.
 Peter, M. S., Timmerhaus, K. D. 1991. Plant Design and Economics for Chemical Engineers. 4th Edition, McGraw-
Hill.

Contenu connexe

Tendances

Mass transfer operations
Mass transfer operationsMass transfer operations
Mass transfer operationsJagdeesh Shukla
 
Zero liquid discharge
Zero liquid dischargeZero liquid discharge
Zero liquid dischargeUmangi Mehta
 
Fuels and Combustion Lectures (GIKI)
Fuels and Combustion Lectures (GIKI)Fuels and Combustion Lectures (GIKI)
Fuels and Combustion Lectures (GIKI)SAFFI Ud Din Ahmad
 
Cooling Towers - An Extensive Approach
Cooling Towers - An Extensive ApproachCooling Towers - An Extensive Approach
Cooling Towers - An Extensive ApproachNoaman Ahmed
 
Cooling towers
Cooling towersCooling towers
Cooling towersctlin5
 
Types of Distillation & column internals
Types of Distillation & column internalsTypes of Distillation & column internals
Types of Distillation & column internalsBharat Kumar
 
Introduction to plant design economics
Introduction to plant design economicsIntroduction to plant design economics
Introduction to plant design economicsSunita Jobli
 
Chilton Colburn Analogy - Overall Concept
Chilton Colburn Analogy - Overall ConceptChilton Colburn Analogy - Overall Concept
Chilton Colburn Analogy - Overall ConceptSyedHameedAnwarSahib
 
heat transfer through fins
heat transfer through finsheat transfer through fins
heat transfer through finsprasantjangir
 
Transport phenomena Solved problems
Transport phenomena Solved problemsTransport phenomena Solved problems
Transport phenomena Solved problemsWolkite University
 
Chemical reaction engineering
Chemical reaction engineeringChemical reaction engineering
Chemical reaction engineering1langshen
 
Fbc fluidized bed combustion
Fbc fluidized bed combustionFbc fluidized bed combustion
Fbc fluidized bed combustionGulab Siraskar
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation iBich Lien Pham
 
Overal Heat Transfer Coefficient
Overal Heat Transfer CoefficientOveral Heat Transfer Coefficient
Overal Heat Transfer CoefficientDheirya Joshi
 

Tendances (20)

Mass transfer operations
Mass transfer operationsMass transfer operations
Mass transfer operations
 
Zero liquid discharge
Zero liquid dischargeZero liquid discharge
Zero liquid discharge
 
Heat exchanger
Heat exchanger Heat exchanger
Heat exchanger
 
Fuels and Combustion Lectures (GIKI)
Fuels and Combustion Lectures (GIKI)Fuels and Combustion Lectures (GIKI)
Fuels and Combustion Lectures (GIKI)
 
Cooling Towers - An Extensive Approach
Cooling Towers - An Extensive ApproachCooling Towers - An Extensive Approach
Cooling Towers - An Extensive Approach
 
Waste heat recovery
Waste heat recoveryWaste heat recovery
Waste heat recovery
 
Cooling towers
Cooling towersCooling towers
Cooling towers
 
Types of Distillation & column internals
Types of Distillation & column internalsTypes of Distillation & column internals
Types of Distillation & column internals
 
Introduction
IntroductionIntroduction
Introduction
 
Introduction to plant design economics
Introduction to plant design economicsIntroduction to plant design economics
Introduction to plant design economics
 
Chilton Colburn Analogy - Overall Concept
Chilton Colburn Analogy - Overall ConceptChilton Colburn Analogy - Overall Concept
Chilton Colburn Analogy - Overall Concept
 
Pressure drop calculations
Pressure drop calculationsPressure drop calculations
Pressure drop calculations
 
heat transfer through fins
heat transfer through finsheat transfer through fins
heat transfer through fins
 
ELECTRODIALYSIS
ELECTRODIALYSISELECTRODIALYSIS
ELECTRODIALYSIS
 
Transport phenomena Solved problems
Transport phenomena Solved problemsTransport phenomena Solved problems
Transport phenomena Solved problems
 
Chemical reaction engineering
Chemical reaction engineeringChemical reaction engineering
Chemical reaction engineering
 
Fbc fluidized bed combustion
Fbc fluidized bed combustionFbc fluidized bed combustion
Fbc fluidized bed combustion
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Overal Heat Transfer Coefficient
Overal Heat Transfer CoefficientOveral Heat Transfer Coefficient
Overal Heat Transfer Coefficient
 
Cooling tower
Cooling towerCooling tower
Cooling tower
 

Similaire à Cost Indices for Industrial Application

Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01hlksd
 
cost estimation techniques
cost estimation techniquescost estimation techniques
cost estimation techniquesabid khaliq
 
cost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfcost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfArnabChakraborty499766
 
Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial toolsOmid Aminzadeh Gohari
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Economic Analysis - PPT.pptx
Economic Analysis - PPT.pptxEconomic Analysis - PPT.pptx
Economic Analysis - PPT.pptxSulemanAhmad21
 
Comparison between SAM and RETScreen
Comparison between SAM and RETScreenComparison between SAM and RETScreen
Comparison between SAM and RETScreenAnkit Thiranh
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimatesnagashree123
 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential BuildingIRJET Journal
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...IOSR Journals
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of EstimationMuthanna Abbu
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 

Similaire à Cost Indices for Industrial Application (20)

Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 
cost estimation techniques
cost estimation techniquescost estimation techniques
cost estimation techniques
 
cost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfcost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdf
 
Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial tools
 
CCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost EstimatingCCP_SEC2_ Cost Estimating
CCP_SEC2_ Cost Estimating
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Cost estimation techniques
Cost estimation techniquesCost estimation techniques
Cost estimation techniques
 
Cost managment
Cost managmentCost managment
Cost managment
 
E.c.v Introduction
E.c.v IntroductionE.c.v Introduction
E.c.v Introduction
 
Project cost management
Project cost management Project cost management
Project cost management
 
Economic Analysis - PPT.pptx
Economic Analysis - PPT.pptxEconomic Analysis - PPT.pptx
Economic Analysis - PPT.pptx
 
B0342014027
B0342014027B0342014027
B0342014027
 
Comparison between SAM and RETScreen
Comparison between SAM and RETScreenComparison between SAM and RETScreen
Comparison between SAM and RETScreen
 
Preparation and approaches of cost estimates
Preparation and approaches of cost estimatesPreparation and approaches of cost estimates
Preparation and approaches of cost estimates
 
IRJET- Life Cycle Cost Analysis of a Residential Building
IRJET-  	  Life Cycle Cost Analysis of a Residential BuildingIRJET-  	  Life Cycle Cost Analysis of a Residential Building
IRJET- Life Cycle Cost Analysis of a Residential Building
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 

Plus de K. Shahzad Baig

Nominal and Effective Interest Rate
Nominal and Effective Interest RateNominal and Effective Interest Rate
Nominal and Effective Interest RateK. Shahzad Baig
 
Interest Why Engineers should know ?
InterestWhy Engineers should know ?InterestWhy Engineers should know ?
Interest Why Engineers should know ?K. Shahzad Baig
 
Projects, Investment, Profitability
Projects, Investment, ProfitabilityProjects, Investment, Profitability
Projects, Investment, ProfitabilityK. Shahzad Baig
 
Taxes and Insurance Engineering point of view
Taxes and InsuranceEngineering point of viewTaxes and InsuranceEngineering point of view
Taxes and Insurance Engineering point of viewK. Shahzad Baig
 
Estimation of Fixed Capital Cost
Estimation of Fixed Capital CostEstimation of Fixed Capital Cost
Estimation of Fixed Capital CostK. Shahzad Baig
 
Summary of Production Costs
Summary of Production CostsSummary of Production Costs
Summary of Production CostsK. Shahzad Baig
 
Purchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous EquipmentPurchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous EquipmentK. Shahzad Baig
 
Mass Transfer Equipment Cost
Mass Transfer Equipment CostMass Transfer Equipment Cost
Mass Transfer Equipment CostK. Shahzad Baig
 
HEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTSHEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTSK. Shahzad Baig
 
Gross Profit, Net Profit
Gross Profit, Net ProfitGross Profit, Net Profit
Gross Profit, Net Profit K. Shahzad Baig
 
Estimation of Capital Investments
Estimation of Capital  Investments Estimation of Capital  Investments
Estimation of Capital Investments K. Shahzad Baig
 
Fluctuation of money value with time
Fluctuation of money value with timeFluctuation of money value with time
Fluctuation of money value with timeK. Shahzad Baig
 
Economics for Engineers, Why ?
Economics for Engineers, Why ?Economics for Engineers, Why ?
Economics for Engineers, Why ?K. Shahzad Baig
 
Psychrometric chart, How to read
Psychrometric chart, How to readPsychrometric chart, How to read
Psychrometric chart, How to readK. Shahzad Baig
 

Plus de K. Shahzad Baig (20)

Income tax
Income taxIncome tax
Income tax
 
Nominal and Effective Interest Rate
Nominal and Effective Interest RateNominal and Effective Interest Rate
Nominal and Effective Interest Rate
 
Interest Why Engineers should know ?
InterestWhy Engineers should know ?InterestWhy Engineers should know ?
Interest Why Engineers should know ?
 
Projects, Investment, Profitability
Projects, Investment, ProfitabilityProjects, Investment, Profitability
Projects, Investment, Profitability
 
Taxes and Insurance Engineering point of view
Taxes and InsuranceEngineering point of viewTaxes and InsuranceEngineering point of view
Taxes and Insurance Engineering point of view
 
Estimation of Fixed Capital Cost
Estimation of Fixed Capital CostEstimation of Fixed Capital Cost
Estimation of Fixed Capital Cost
 
Summary of Production Costs
Summary of Production CostsSummary of Production Costs
Summary of Production Costs
 
Purchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous EquipmentPurchase Cost of Miscellaneous Equipment
Purchase Cost of Miscellaneous Equipment
 
Mass Transfer Equipment Cost
Mass Transfer Equipment CostMass Transfer Equipment Cost
Mass Transfer Equipment Cost
 
HEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTSHEAT-TRANSFER EQUIPMENT COSTS
HEAT-TRANSFER EQUIPMENT COSTS
 
Gross Profit, Net Profit
Gross Profit, Net ProfitGross Profit, Net Profit
Gross Profit, Net Profit
 
Manufacturing Costs
Manufacturing Costs Manufacturing Costs
Manufacturing Costs
 
Capital Investment
Capital InvestmentCapital Investment
Capital Investment
 
Estimation of Capital Investments
Estimation of Capital  Investments Estimation of Capital  Investments
Estimation of Capital Investments
 
Production Costs
Production CostsProduction Costs
Production Costs
 
Location of an industry
Location of an industryLocation of an industry
Location of an industry
 
Fluctuation of money value with time
Fluctuation of money value with timeFluctuation of money value with time
Fluctuation of money value with time
 
Economics for Engineers, Why ?
Economics for Engineers, Why ?Economics for Engineers, Why ?
Economics for Engineers, Why ?
 
Psychrometric chart, How to read
Psychrometric chart, How to readPsychrometric chart, How to read
Psychrometric chart, How to read
 
The Scientific Methods
The Scientific MethodsThe Scientific Methods
The Scientific Methods
 

Dernier

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 

Dernier (20)

Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 

Cost Indices for Industrial Application

  • 1. Cost Indices for Industrial Application Dr. K. Shahzad Baig Memorial University of Newfoundland (MUN) Canada
  • 2. Cost Indexes  Cost Index is ratio of cost today to cost in the past • Indicates change in cost over time; therefore, they account for the impact of inflation • Index is dimensionless • CPI (Consumer Price Index) is a good example Formula for total cost is
  • 3. Finding Cost Indexes © 2012 by McGraw-Hill All Rights Reserved15-10 Cost indexes are maintained in areas such as construction, chemical and mechanical industries • Updated monthly and annually; many include regionalized and international project indexes • Indexes in these areas are often subdivided into smaller components and can be used in preliminary, as well as detailed design stages Examples are:  Chemical Engineering Plant Cost Index (CEPCI) www.che.com/pci  McGraw-Hill Construction Index www.construction.com  US Department of Labor, Bureau of Labor Statistics www.bls.gov
  • 4. Example: Cost Index Method © 2012 by McGraw-Hill All Rights Reserved15-9 Problem: Estimate the total cost of labor today in US dollars for a maritime construction project using data from a similar project in Europe completed in 1998. Labor index, 1998: 789.6 Cost in 1998: €3.9 million Labor index, current: 1165.8 Currently, 1 € = 1.5 US$ Solution: Let t = today and 0 = 1998 base Ct = 3.9 million × (1165.8/789.6) = €5.76 million = €5.76 × 1.5 = $8.64 million
  • 5. Cost-Capacity Combined with Cost Index Multiply the cost-capacity equation by a cost index (It/I0) to adjust for time differences and obtain estimates of current cost (in constant-value dollars)
  • 6. Example A 100 hp air compressor costs $3000 five years ago when the cost index was 130. Estimate the cost of a 300 hp compressor today when the cost index is 255. Solution: Let C300 represent the cost estimate today. Exponent is 0.9 for 5-300 hp air compressors. C300 = 3000(300/100)0.9(255/130) = $15,817
  • 7. Study Method The study estimate uses a list of the major equipment included in the process, such as pumps, compressors and turbines, columns and vessels, heat exchangers, etc. After sizing is done, the cost is determined for each piece of equipment. Also called the major equipment or factored estimate, the study estimate usually needs cost charts and process flow diagrams the Lang factor is a ratio of the total cost of installing a process in a plant to the cost of its major technical components
  • 8. Inflation When costs are to be projected into the future due to inflation, it is a highly speculative exercise, but it is necessary for estimating investment costs, operating expenses, etc. Inflation is the increase in price of goods without a corresponding increase in productivity. A method for estimating an inflated cost is where Ci = inflated cost f1 = inflation rate the first year f2 = inflation rate the second year f3 = inflation rate the third year CP = cost in a base year 𝑪𝒊 = 𝟏 + 𝒇 𝟏 𝟏 + 𝒇 𝟐 𝟏 + 𝒇 𝟑 𝑪 𝒑
  • 9. The assumed inflation factors f are obtained from federal economic reports, financial sources such as banks and investment houses, and news media. These factors must be reviewed periodically to update estimates. Example , Inflation A dryer today costs $475,000. The projected inflation rates for the next 3 years are 3, 4.2, and 4.7 percent. Calculate the projected cost in 3 years.
  • 10. Preliminary Estimate Methods A refinement of the Lang factor method is the Hand method. Equipment is grouped in categories, such as heat exchangers and pumps, and then a factor is applied to each group to obtain the installed cost. Wroth compiled a more detailed list of installation factors. The Lang and Hand methods start with purchased equipment costs whereas the Wroth method begins with delivered equipment costs, so delivery charges must be included in the Lang and Hand methods. At best the Lang and Hand methods will yield study quality estimates, and the Wroth method might yield a preliminary quality estimate.
  • 11. Lang proposed three separate factors based on the type of process plant. For solids, the factor is 3.10; For combined solids and fluids, 3.63; For fluids alone, 4.74. These factors were meant to cover all the costs associated with the Total Installed Cost of a plant, Lang’s Method Total plant cost (TPC) = = Total equipment cost (TEC) x 3 x Equipment factor TEC = $1.5M TPC = $1.5M X 3 X4.74 = $7.11M
  • 12. Definitive Estimate Methods Modular methods are an extension of the multiple-factor methods and have been proposed by several authors. It began with equipment FOB equipment costs the module material cost was obtained. Labor for erection and setting equipment was added to the material cost as well as indirect costs for freight, insurance, engineering, and field expenses to give a total module cost. Such items as contingencies, contractors’ fees, auxiliaries, site development land, and industrial buildings were added if applicable.
  • 13. Detailed Estimate Method For estimates in the detailed category, a standard of account needs to be used to prevent oversight of certain significant items in the capital cost. Each item in the standard is estimated and provides the capital cost estimate; then this estimate serves for cost control during the construction phase of a project.
  • 14. Following books were used in preparation of notes  Blank, L., Tarquin. A. 2005. Engineering Economy. 6th Edition, McGraw-Hill.  Eschenbach, T. G. 2003. Engineering Economy”, 2nd Edition, Oxford University Press  Riggs, J. L., Bedworth, D. D., Randhawa, S. U. 1996. Engineering Economics”, 4th Edition, Tata McGraw-Hill.  Riggs, J. L., West. T. M. 1986. Essentials of Engineering Economics”, 2nd Edition, McGraw-Hill.  Peter, M. S., Timmerhaus, K. D. 1991. Plant Design and Economics for Chemical Engineers. 4th Edition, McGraw- Hill.