Title of Seminar-
LINE OF BALANCE
• Prepared by- Miss. Patil Shivanjali .M.
• Class- B.E. (CIVIL)
• Division- B
• Roll no-128
• Batch-B7
• Guided by- Prof. Paithankar
Line of Balance
• Line of Balance is a management control process for collecting,
measuring and presenting facts relating to time, cost and
accomplishment- all measured against a specific plan.
• It is a method of showing the repetitive work e.g. projects like
highways, pipelines, high rise buildings, hotel bedroom: bridge etc. In
these types of projects there is set of tasks repeated across many areas.
• These types of schedule effectively model by Arrow and precedence
Diagramming. The LOB technique is graphical representation that can
used in conjunction with Arrow or precedence Diagrams.
• It illustrate the process, status, background, timing and phasing of the
project activities, this providing management with measuring tools
that help.
1. Comparison between actual progresses and a formal objective plan.
2. From established plans examining only deviation and evaluating
their degree of severity with respect to the remainder of the project.
3. Getting timely data and information regarding trouble areas and
specifying those areas. And specifying those areas where suitable
corrective action is required.
4. Forecasting future performance.
Advantages of LOB
• It clearly indicates the amount of work taking place in a definite area
at a specific time.
• It has the ability to show and optimize the resources used for large
number of repetitive activities, implemented in several locations.
• All information available for each and every activity of project, cause
easier analysis, cost and time optimization.
• Superior presentation and visualization of setup.
• Modification, update and changes can be easily made in schedule.
• It helps in simpler and clearer resource management and optimization
functions.
• Visualization of productivity and team location.
• It allows project managers to understand situation in middle of project,
whether they can meet the schedule if they continue working as they
have been.
• Well managing the several sub-contractors in the project
Disadvantages of LOB
• A clear critical path of project schedule cannot be generated.
• It could be divided only by location.
• In CPM scheduling the user could divide project by location and other
systems like trades, in LOB only location.
• Productivity rates in LOB schedule do not include the effect of crews,
learning curve, or if the individuals working in crews changed.
Scheduling with LOB
Following procedure should be adopted for preparing line of balance
schedule:
• Prepare a logic diagram
• To complete each operation, calculate the estimate of man hours required
• Select a buffer times which will lookout against the risk of interference
between operation
• Calculate the requisite output target so as to meet a given project
completion date.
• Complete LOB schedule
• In order to bring more balance schedule, inspect the schedule and access
possible attentive.
• The above construction procedure gives a proper LOB schedule. This basic
methodology is to determine the available resources, and evaluate the construction
rates that can be achieved.
• Consider the example of residential building project, where five buildings are to
be constructed. Following steps explain how the line of balance technique can be
used in scheduling.
• Th logic diagram is drawn below showing the different activities of the
construction single building, along with continuity of work.
• The buffer time is usually placed between each activity for margin of
error in the time taken to complete each of these activity.
• The above construction plan indicates that to complete one sequence
of activities total 60 days duration is required.
• The target output of project can be expressed in terms of
accomplishment of each building. In the following diagram, handover
dates are drawn for each of five buildings.
• Handover data for first building in on day 60, for second building is on
day 65, for third building is on day 70 and for 4th and 5th building 75
& 80 respectively.
• If these handover dates are joined by a straight line, this indicates the
handover schedule of the building in every 5 day.
• The constriction of each of five buildings is drawn in logic diagram
with buffer time to match handover schedule.
• The starting and finishing point of every activity is then joined by
sloping line.
• For example, earthwork, foundation- structure, superstructure and
finishing for all the buildings are joined by sloping line as shown in fig
which forms a series of band are nothing but the line of balance for
each gang.
• All the sloping lines are parallel.
THANK YOU

Contenu connexe

Tendances

Programme evaluation review technique
Programme evaluation review techniqueProgramme evaluation review technique
Programme evaluation review techniquesaheli chakraborty
 
Mba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aMba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aRai University
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerPraveen Malik, PMP
 
AgileGraphingCookbook
AgileGraphingCookbookAgileGraphingCookbook
AgileGraphingCookbookpbaxter
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chartdanishrafiq
 
Project presentation
Project presentationProject presentation
Project presentationali ucar
 
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...p6academy
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraAmit Kumar Senapati, PMP®
 
Gantt chart cpm
Gantt chart cpmGantt chart cpm
Gantt chart cpmMimin Adam
 
Modelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish RelationshipsModelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish RelationshipsFelipe Moreira
 
Layout planning
Layout planningLayout planning
Layout planning8979473684
 
4D bim construction scheduling on the 1885 St. James pl. project
4D bim construction scheduling on the 1885 St. James pl. project4D bim construction scheduling on the 1885 St. James pl. project
4D bim construction scheduling on the 1885 St. James pl. projectDat Lien
 
AAI Notable Projects
AAI Notable ProjectsAAI Notable Projects
AAI Notable ProjectsSrijita Mori
 

Tendances (20)

Programme evaluation review technique
Programme evaluation review techniqueProgramme evaluation review technique
Programme evaluation review technique
 
Mba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aMba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart a
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
How Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project ManagerHow Project Network Diagram's Can Help You Become A Better Project Manager
How Project Network Diagram's Can Help You Become A Better Project Manager
 
AgileGraphingCookbook
AgileGraphingCookbookAgileGraphingCookbook
AgileGraphingCookbook
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Project presentation
Project presentationProject presentation
Project presentation
 
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...Dashboard / Digest / Compliance reporting of key performance, quality and oth...
Dashboard / Digest / Compliance reporting of key performance, quality and oth...
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
 
Gantt chart cpm
Gantt chart cpmGantt chart cpm
Gantt chart cpm
 
Modelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish RelationshipsModelling Line of Balance Schedules with Start-Finish Relationships
Modelling Line of Balance Schedules with Start-Finish Relationships
 
Layout planning
Layout planningLayout planning
Layout planning
 
4D bim construction scheduling on the 1885 St. James pl. project
4D bim construction scheduling on the 1885 St. James pl. project4D bim construction scheduling on the 1885 St. James pl. project
4D bim construction scheduling on the 1885 St. James pl. project
 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
 
Project management
Project managementProject management
Project management
 
Ecv
EcvEcv
Ecv
 
4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimates
 
AAI Notable Projects
AAI Notable ProjectsAAI Notable Projects
AAI Notable Projects
 
Anitha Vanga
Anitha VangaAnitha Vanga
Anitha Vanga
 
Vignesh Nagarajan CV
Vignesh Nagarajan CVVignesh Nagarajan CV
Vignesh Nagarajan CV
 

Similaire à LINE OF BALANACE

Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling DiagramsSaqib Raza
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxsurekha1287
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterpreetidamakale
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxRaoAnkitYadav1
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxRaoAnkitYadav1
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfGagandeepKaur617299
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11Robert (Bob) Owens
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptxJanak82
 
2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdfAhmedshayor
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxMariaNambahu
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.pptMdHelalHossain6
 

Similaire à LINE OF BALANACE (20)

Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Software Project Scheduling Diagrams
Software Project Scheduling DiagramsSoftware Project Scheduling Diagrams
Software Project Scheduling Diagrams
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Chapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapterChapt5.pptx it is notes of the 5th chapter
Chapt5.pptx it is notes of the 5th chapter
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
 
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
AMTPJ-Presentn-Lvl3 Sched Dev-2010-11
 
10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx10.3_Construction Management_Day 8.pptx
10.3_Construction Management_Day 8.pptx
 
Unit IV-Project Management
Unit IV-Project ManagementUnit IV-Project Management
Unit IV-Project Management
 
2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf2nd and 3rd Lecture (Maintenance).pptx.pdf
2nd and 3rd Lecture (Maintenance).pptx.pdf
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 

Dernier

Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 

Dernier (20)

Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

LINE OF BALANACE

  • 1. Title of Seminar- LINE OF BALANCE • Prepared by- Miss. Patil Shivanjali .M. • Class- B.E. (CIVIL) • Division- B • Roll no-128 • Batch-B7 • Guided by- Prof. Paithankar
  • 2. Line of Balance • Line of Balance is a management control process for collecting, measuring and presenting facts relating to time, cost and accomplishment- all measured against a specific plan. • It is a method of showing the repetitive work e.g. projects like highways, pipelines, high rise buildings, hotel bedroom: bridge etc. In these types of projects there is set of tasks repeated across many areas. • These types of schedule effectively model by Arrow and precedence Diagramming. The LOB technique is graphical representation that can used in conjunction with Arrow or precedence Diagrams.
  • 3. • It illustrate the process, status, background, timing and phasing of the project activities, this providing management with measuring tools that help. 1. Comparison between actual progresses and a formal objective plan. 2. From established plans examining only deviation and evaluating their degree of severity with respect to the remainder of the project. 3. Getting timely data and information regarding trouble areas and specifying those areas. And specifying those areas where suitable corrective action is required. 4. Forecasting future performance.
  • 4. Advantages of LOB • It clearly indicates the amount of work taking place in a definite area at a specific time. • It has the ability to show and optimize the resources used for large number of repetitive activities, implemented in several locations. • All information available for each and every activity of project, cause easier analysis, cost and time optimization. • Superior presentation and visualization of setup. • Modification, update and changes can be easily made in schedule.
  • 5. • It helps in simpler and clearer resource management and optimization functions. • Visualization of productivity and team location. • It allows project managers to understand situation in middle of project, whether they can meet the schedule if they continue working as they have been. • Well managing the several sub-contractors in the project
  • 6. Disadvantages of LOB • A clear critical path of project schedule cannot be generated. • It could be divided only by location. • In CPM scheduling the user could divide project by location and other systems like trades, in LOB only location. • Productivity rates in LOB schedule do not include the effect of crews, learning curve, or if the individuals working in crews changed.
  • 7. Scheduling with LOB Following procedure should be adopted for preparing line of balance schedule: • Prepare a logic diagram • To complete each operation, calculate the estimate of man hours required • Select a buffer times which will lookout against the risk of interference between operation • Calculate the requisite output target so as to meet a given project completion date. • Complete LOB schedule • In order to bring more balance schedule, inspect the schedule and access possible attentive.
  • 8. • The above construction procedure gives a proper LOB schedule. This basic methodology is to determine the available resources, and evaluate the construction rates that can be achieved. • Consider the example of residential building project, where five buildings are to be constructed. Following steps explain how the line of balance technique can be used in scheduling. • Th logic diagram is drawn below showing the different activities of the construction single building, along with continuity of work.
  • 9. • The buffer time is usually placed between each activity for margin of error in the time taken to complete each of these activity. • The above construction plan indicates that to complete one sequence of activities total 60 days duration is required. • The target output of project can be expressed in terms of accomplishment of each building. In the following diagram, handover dates are drawn for each of five buildings.
  • 10. • Handover data for first building in on day 60, for second building is on day 65, for third building is on day 70 and for 4th and 5th building 75 & 80 respectively. • If these handover dates are joined by a straight line, this indicates the handover schedule of the building in every 5 day.
  • 11. • The constriction of each of five buildings is drawn in logic diagram with buffer time to match handover schedule. • The starting and finishing point of every activity is then joined by sloping line. • For example, earthwork, foundation- structure, superstructure and finishing for all the buildings are joined by sloping line as shown in fig which forms a series of band are nothing but the line of balance for each gang. • All the sloping lines are parallel.