SlideShare une entreprise Scribd logo
1  sur  24
A PRESENTATION ON
INDUSTRIAL SUMMER TRAINING
220/132/33 KV S/S BARAHUA GORAKHPUR
DEPARTMENT OF ELECTRICAL ENGINEERING
SUBMITTED TO : SUBMITTED BY :
MR. DEEPAK GUPTA SHUBHAM PATEL
ASSISTANT PROFESSOR E.E. – 4TH YEAR
ROLL NO. 1575120050
KIPM COLLEGE OF ENGINEERING AND TECHNOLOGY
GIDA , GORAKHPUR
CONTENT
 INTRODUCTION
 SUB-STATION PROFILE
 INCOMING / OUTGOING
 SUB-STATION
 SELECTION OF SITE
 COMPONENT OF S/S
 SINGLE LINE DIAGRAM
 CONCLUSION
 REFERENCE
INTRODUCTION
 Uttar Pradesh Power Corporation Limited (UPPCL) is
the company responsible for electricity transmission and
distribution within the Indian state of Uttar Pradesh .
 The creation of Uttar Pradesh Power Corporation Ltd.
(UPPCL) on January 14, 2000.
 UPPCL Barahua 220 KV substation was established in
1979.
 UPPCL Barahua substation is basically contains two
substation one of 220/132 KV & other one of 132/33
KV.
SUB-STATION PROFILE
 VOLTAGE RATIO (220/132/11)KV T/F
1. 160 MVA T/F 1ST (AREVA)
2. 160 MVA T/F 2ND ( EMCO )
3. 100 MVA T/F 1ST ( MITSHIBUSI )
4. 100 MVA T/F 2ND ( MITSHIBUSI )
 VOLTAGE RATIO ( 132/33 ) KV T/F
1. 63 MVA T/F ( ADITYA )
2. 40 MVA T/F ( AREVA )
INCOMING/OUTGOING
 INCOMING LINES (220 KV )
1. PGCIL (220 KV )
2. NTPC TANDA (220 KV )
3. GKP CIRCUIT 1ST (220 KV )
4. GKP CIRCUIT 2ND (220 KV )
 OUTGOING LINES( 132 KV )
1. MOHADDIPUR ( 132 KV )
2. KAURIRAM ( 132 KV )
3. BARHALGANJ ( 132 KV )
4. ANAND NAGAR ( 132 KV )
5. FCI CIRCUIT 1ST ( 132 KV )
6. FCI CIRCUIT 2ND ( 132 KV )
7. IGL ( 132 KV )
8. GIDA ( 132 KV )
 OUTGOING LINES ( 33 KV )
1. LAL DIGGI ( 33 KV )
2. NAUSARH ( 33 KV )
3. RUSTAMPUR ( 33 KV )
4. PGCIL ( 33 KV )
5. HARPUR ( 33 KV )
6. SAHJANWA ( 33 KV )
7. GIDA ( 33 KV )
8. JACK BUS ( 33 KV )
SUB-STATION
 A substation is a part of an electrical generation,
transmission, and distribution system.
 The assembly of apparatus used to change some
characteristics (e.g. Voltage ac to dc freq. p.f. etc) of
electric supply is called sub-station.
 Substations transform voltage from high to low, or the
reverse, or perform any of several other important
functions.
 Between the generating station and consumer, electric
power may flow through several substations at different
voltage levels.
Fig.1. Barahuwa Substation
TYPES OF SUB-STATION
 Substations may be described by their voltage
class, their applications within the power system.
1. Transmission substation
2. Distribution substation
3. Converter substation
SELECTION OF SITE
 The site chosen should be as near to the load center as
possible.
 It should be easily approachable by road or rail for
transportation of equipments.
 Land should be fairly leveled to minimize development
cost.
 Source of water should be as near to the site as possible.
This is because water is required for various construction
activities (especially civil works), earthing and for
drinking purposes etc.
 The sub-station site should be as near to the town / city
but should be clear of public places, aerodromes, and
Military / police installations.
COMPONENT OF S/S
The equipment required for a transformer Sub-Station
depends upon the type of Sub-Station –
 Bus-bar
 Insulators
 Circuit breaker
 Instrument Transformer
 Current Transformer
 Voltage Transformer
 Transformer
 Lightening arrestors
 Wave trap
 Bus-bar:
 The bus is a line in which the incoming feeders
come into and get into the instruments for further
step up or step down.
 The first bus is used for putting the incoming
feeders in LA single line.
 Insulators:
 The insulator serves two purpose –
1. they support the conductor (or bus bar)
2. confine the current to the conductor.
 The most commonly used material for the
manufactures of insulators is porcelain.
 Transformer:
 Transformer is a static machine, which transform
the potential of alternating current at same
frequency.
 It means the transformer transforms the low voltage
into high voltage and high voltage into low voltage
at same frequency.
 It works on the principle of static induction principle.
Fig.2. 220/132 KV 160 MVA Transformer at barahuwa sub-station
TYPES OF TRANSFORMER:
 Power Transformer
 Instrument Transformer
 Auto Transformer
1. POWER TRANSFORMER:
Fig 3: 132/33 KV 40 MVA transformer at barahuwa sub-station
2. INSTRUMENT TRANSFORMER:
There are two types of instrument transformer-
 Current T/f
 Potential T/f
 CVT
1. Current Transformer:
 A current transformer is essentially a step-down
transformer which steps-down the current in a
known ratio.
 Current transformers are basically used to take the
readings of the currents entering the substation.
Fig.4. Current Transformer
2. Potential Transformer:
 It is essentially a step – down transformer and step
down the voltage in known ratio.
Fig.5. Potential Transformer ( Voltage Transformer )
3. C V T:
 A capacitor voltage transformer (CVT ) is a
transformer used in power systems to step-down
extra high voltage signals .
 It provide low voltage signals either for
measurement or to operate a protective relay.
 Circuit breaker:
 A circuit breaker is an equipment, which can open
or close a circuit under normal as well as fault
condition.
 These circuit breaker breaks for a fault which can
damage other instrument in the station.
 It is so designed that it can be operated manually
(or by remote control) under normal conditions and
automatically under fault condition.
Fig.6. Vaccum Circuit Breaker Fig.7. Gas Circuit Breaker
 Lightening Arrester:
 To discharge the switching and lightening voltage
surges to earth.
Fig.8. Lightening arrester
SINGLE LINE DIAGRAM
(SLD)
Fig 9: single line diagram of 220 KV substation Barahuwa
CONCLUSION
 The three wings of electrical system viz. generation,
transmission and distribution are connected to each
other and that too very perfectly.
 Effective voltage control
 Reliable supply by feeding the network at various
points
 Fault analysis improvement in respective field
 Establishment of economic load distribution
REFERENCES
 IEEE Journals
 Electrical Magazines
 Substation Report of UPPCL
 “Electrical Power System” by C.L. Wadhwa
 “Electrical Power System” by D Daas
 “Electrical Power Distribution System” by V.
Kamaraju
 “Power system stability and control” by P Kundur
 “Power system dynamics” by P Sauer and M A Pai
 “Nonlinear Power Flow control design” by David G
Wilson
Industrial Training Presentation on 220/132/33 KV Barahua Substation

Contenu connexe

Tendances

PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclVISHAL VERMA
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONRavi Phadtare
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurkishankky
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Sakshi Rastogi
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdfSagarRana91
 
Report on industrial summer training on 220 kv substation
Report  on industrial summer training on 220 kv substationReport  on industrial summer training on 220 kv substation
Report on industrial summer training on 220 kv substationAshutosh Srivastava
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training pptsitesh95074
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmissionprasantakcs
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppclSunny Daksh
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv student
 

Tendances (20)

PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
132 kv
132 kv132 kv
132 kv
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
substation internship report
substation internship report substation internship report
substation internship report
 
220 Kv / 132 Kv GSS PPT
220 Kv / 132 Kv GSS PPT220 Kv / 132 Kv GSS PPT
220 Kv / 132 Kv GSS PPT
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf33-11-kv-substation-training-report (1) (1).pdf
33-11-kv-substation-training-report (1) (1).pdf
 
Report on industrial summer training on 220 kv substation
Report  on industrial summer training on 220 kv substationReport  on industrial summer training on 220 kv substation
Report on industrial summer training on 220 kv substation
 
Sub station training ppt
Sub station training pptSub station training ppt
Sub station training ppt
 
Electric substation
Electric substation Electric substation
Electric substation
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
Substation
Substation Substation
Substation
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
 
33kv substation
33kv substation33kv substation
33kv substation
 

Similaire à Industrial Training Presentation on 220/132/33 KV Barahua Substation

Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation Madeen Kumar
 
Industrial summer training
Industrial summer trainingIndustrial summer training
Industrial summer trainingShubham Patel
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substationShivamUpadhyay86734
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxShubhoDas5
 
introductory presentation on the transformer
introductory presentation on the transformer   introductory presentation on the transformer
introductory presentation on the transformer Sagarkv3
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfDevesh54
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxsohaib268827
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxSNEHAKANWAR1
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training reportGyanendra Prakash
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
 
Trainingreport 120930165750-phpapp01
Trainingreport 120930165750-phpapp01Trainingreport 120930165750-phpapp01
Trainingreport 120930165750-phpapp01Vinay Vashisht
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working modelgiriraj bairwa
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)shovandey07
 
Training report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalTraining report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalPiyush Dwivedi
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Ajeet Chaurasia
 

Similaire à Industrial Training Presentation on 220/132/33 KV Barahua Substation (20)

Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
 
finalseminar.docx
finalseminar.docxfinalseminar.docx
finalseminar.docx
 
Industrial summer training
Industrial summer trainingIndustrial summer training
Industrial summer training
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substation
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
33 kv substation vt report
33 kv substation vt report33 kv substation vt report
33 kv substation vt report
 
33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
introductory presentation on the transformer
introductory presentation on the transformer   introductory presentation on the transformer
introductory presentation on the transformer
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training report
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Trainingreport 120930165750-phpapp01
Trainingreport 120930165750-phpapp01Trainingreport 120930165750-phpapp01
Trainingreport 120930165750-phpapp01
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 
Final report of 220kv gss working model
Final report of 220kv gss working modelFinal report of 220kv gss working model
Final report of 220kv gss working model
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)
 
Training report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electricalTraining report of secl , khairha coal mine , sohagpur area for electrical
Training report of secl , khairha coal mine , sohagpur area for electrical
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 

Dernier

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 

Dernier (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 

Industrial Training Presentation on 220/132/33 KV Barahua Substation

  • 1. A PRESENTATION ON INDUSTRIAL SUMMER TRAINING 220/132/33 KV S/S BARAHUA GORAKHPUR DEPARTMENT OF ELECTRICAL ENGINEERING SUBMITTED TO : SUBMITTED BY : MR. DEEPAK GUPTA SHUBHAM PATEL ASSISTANT PROFESSOR E.E. – 4TH YEAR ROLL NO. 1575120050 KIPM COLLEGE OF ENGINEERING AND TECHNOLOGY GIDA , GORAKHPUR
  • 2. CONTENT  INTRODUCTION  SUB-STATION PROFILE  INCOMING / OUTGOING  SUB-STATION  SELECTION OF SITE  COMPONENT OF S/S  SINGLE LINE DIAGRAM  CONCLUSION  REFERENCE
  • 3. INTRODUCTION  Uttar Pradesh Power Corporation Limited (UPPCL) is the company responsible for electricity transmission and distribution within the Indian state of Uttar Pradesh .  The creation of Uttar Pradesh Power Corporation Ltd. (UPPCL) on January 14, 2000.  UPPCL Barahua 220 KV substation was established in 1979.  UPPCL Barahua substation is basically contains two substation one of 220/132 KV & other one of 132/33 KV.
  • 4. SUB-STATION PROFILE  VOLTAGE RATIO (220/132/11)KV T/F 1. 160 MVA T/F 1ST (AREVA) 2. 160 MVA T/F 2ND ( EMCO ) 3. 100 MVA T/F 1ST ( MITSHIBUSI ) 4. 100 MVA T/F 2ND ( MITSHIBUSI )  VOLTAGE RATIO ( 132/33 ) KV T/F 1. 63 MVA T/F ( ADITYA ) 2. 40 MVA T/F ( AREVA )
  • 5. INCOMING/OUTGOING  INCOMING LINES (220 KV ) 1. PGCIL (220 KV ) 2. NTPC TANDA (220 KV ) 3. GKP CIRCUIT 1ST (220 KV ) 4. GKP CIRCUIT 2ND (220 KV )  OUTGOING LINES( 132 KV ) 1. MOHADDIPUR ( 132 KV ) 2. KAURIRAM ( 132 KV ) 3. BARHALGANJ ( 132 KV ) 4. ANAND NAGAR ( 132 KV ) 5. FCI CIRCUIT 1ST ( 132 KV ) 6. FCI CIRCUIT 2ND ( 132 KV ) 7. IGL ( 132 KV ) 8. GIDA ( 132 KV )
  • 6.  OUTGOING LINES ( 33 KV ) 1. LAL DIGGI ( 33 KV ) 2. NAUSARH ( 33 KV ) 3. RUSTAMPUR ( 33 KV ) 4. PGCIL ( 33 KV ) 5. HARPUR ( 33 KV ) 6. SAHJANWA ( 33 KV ) 7. GIDA ( 33 KV ) 8. JACK BUS ( 33 KV )
  • 7. SUB-STATION  A substation is a part of an electrical generation, transmission, and distribution system.  The assembly of apparatus used to change some characteristics (e.g. Voltage ac to dc freq. p.f. etc) of electric supply is called sub-station.  Substations transform voltage from high to low, or the reverse, or perform any of several other important functions.  Between the generating station and consumer, electric power may flow through several substations at different voltage levels.
  • 9. TYPES OF SUB-STATION  Substations may be described by their voltage class, their applications within the power system. 1. Transmission substation 2. Distribution substation 3. Converter substation
  • 10. SELECTION OF SITE  The site chosen should be as near to the load center as possible.  It should be easily approachable by road or rail for transportation of equipments.  Land should be fairly leveled to minimize development cost.  Source of water should be as near to the site as possible. This is because water is required for various construction activities (especially civil works), earthing and for drinking purposes etc.  The sub-station site should be as near to the town / city but should be clear of public places, aerodromes, and Military / police installations.
  • 11. COMPONENT OF S/S The equipment required for a transformer Sub-Station depends upon the type of Sub-Station –  Bus-bar  Insulators  Circuit breaker  Instrument Transformer  Current Transformer  Voltage Transformer  Transformer  Lightening arrestors  Wave trap
  • 12.  Bus-bar:  The bus is a line in which the incoming feeders come into and get into the instruments for further step up or step down.  The first bus is used for putting the incoming feeders in LA single line.  Insulators:  The insulator serves two purpose – 1. they support the conductor (or bus bar) 2. confine the current to the conductor.  The most commonly used material for the manufactures of insulators is porcelain.
  • 13.  Transformer:  Transformer is a static machine, which transform the potential of alternating current at same frequency.  It means the transformer transforms the low voltage into high voltage and high voltage into low voltage at same frequency.  It works on the principle of static induction principle. Fig.2. 220/132 KV 160 MVA Transformer at barahuwa sub-station
  • 14. TYPES OF TRANSFORMER:  Power Transformer  Instrument Transformer  Auto Transformer 1. POWER TRANSFORMER: Fig 3: 132/33 KV 40 MVA transformer at barahuwa sub-station
  • 15. 2. INSTRUMENT TRANSFORMER: There are two types of instrument transformer-  Current T/f  Potential T/f  CVT 1. Current Transformer:  A current transformer is essentially a step-down transformer which steps-down the current in a known ratio.  Current transformers are basically used to take the readings of the currents entering the substation.
  • 17. 2. Potential Transformer:  It is essentially a step – down transformer and step down the voltage in known ratio. Fig.5. Potential Transformer ( Voltage Transformer )
  • 18. 3. C V T:  A capacitor voltage transformer (CVT ) is a transformer used in power systems to step-down extra high voltage signals .  It provide low voltage signals either for measurement or to operate a protective relay.  Circuit breaker:  A circuit breaker is an equipment, which can open or close a circuit under normal as well as fault condition.  These circuit breaker breaks for a fault which can damage other instrument in the station.  It is so designed that it can be operated manually (or by remote control) under normal conditions and automatically under fault condition.
  • 19. Fig.6. Vaccum Circuit Breaker Fig.7. Gas Circuit Breaker
  • 20.  Lightening Arrester:  To discharge the switching and lightening voltage surges to earth. Fig.8. Lightening arrester
  • 21. SINGLE LINE DIAGRAM (SLD) Fig 9: single line diagram of 220 KV substation Barahuwa
  • 22. CONCLUSION  The three wings of electrical system viz. generation, transmission and distribution are connected to each other and that too very perfectly.  Effective voltage control  Reliable supply by feeding the network at various points  Fault analysis improvement in respective field  Establishment of economic load distribution
  • 23. REFERENCES  IEEE Journals  Electrical Magazines  Substation Report of UPPCL  “Electrical Power System” by C.L. Wadhwa  “Electrical Power System” by D Daas  “Electrical Power Distribution System” by V. Kamaraju  “Power system stability and control” by P Kundur  “Power system dynamics” by P Sauer and M A Pai  “Nonlinear Power Flow control design” by David G Wilson