Indian Institute Of Technology Delhi
Case study
Project:3750 TPD(Tonnes per Day)
Pyro Project
Loctaion:Dabok(nearUdaipur),
Rajasthan
Client: J.K.Lakshmi Cements Ltd.
Civil Consultant:M/S Magcons
Consulting Engineers Pvt
Ltd,Mumbai
Civil Contractor:M/S K.B.Mehta
Construction Pvt Ltd,Ahmedabad
Equipment Supplier:M/S LNVT
Sinoma,China
Project Overview
• Dabok Cement Factory used to be a part of
Udaipur Cement Works Limited(UCWL) some
years back.This cement factory got down and was
sold to J.K.Lakshmi Cement Company Limited.
• J.K. Lakshmi currently has the facility of grinding
the clinker and a packing plant but cement
production is not done here.
• J.K.Lakshmi decided for starting the production of
cement at the current location.
Existing Coal mill Existing Packing Plant
Components of A Cement Plant
• Quarry
• CS Silo/Blending Silo
• Preheater
• Kiln
• Cooling Tower
• Clinker Silo
• Grounding Mill
• Packing Plant
Current Status of Project
• The construction of the Blending Silo(85 m) is
completed from outside.Preparation for the
staging for the construction of the cone inside the
blending silo is going on.
• The first two floors of the preheater are
completed.Beam level of the 3rd floor(46 m) is
almost reached.
• Foundation of the preheater boiler is going on.
• Piers for the installation of the kiln are aready
constructed.
• Foundation work of the cooling tower is
almost over.The tunnel for the transport of
clinker from the cooling tower to the clinker
silo is under construction.
• Construction of the clinker silo has reached
almost upto the completion of the second
floor.
Site Soil Conditions
• The site is situated in Udaipur,Rajasthan which has got
hard,rocky soil conditions.
• All the foundations are Raft foundations.
Foundation of Preheater Shaft Cooling Tower Foundation Slab
Quarry
• The cement production plant
should be located where the
raw material for the
production is available nearby.
• The dark coloured rock in the
picture contains limestone and
two kinds of shale, all of which
are used in producing cement.
The light coloured material is
called over-burden, which is
not used in manufacturing, but
is set aside to be replaced
later during reclamation after
the quarry has reached the
end of its permit period and is
closed.
• The flat area in the quarry wall,
called the lift or bench, is the
depth to which holes are drilled
before charges are set for
blasting. Because of security
requirements, most quarries
subcontract the blasting
operations.
• After blasting, the waste stone is
brought to the end of the quarry
where quarrying first began. It
will be the first material to be
filled back in as part of the
reclamation process. Usable
stone is hauled by truck and
either dumped into the primary
crusher or piled nearby.
• The roads and piles must be kept
watered to reduce airborne dust.
•After the stone is dumped into the feed
chute from above, gravity moves it down
through the crusher, which reduces it to
about 3 inches in diameter. A bag filter
helps reduce airborne dust.
•From the crusher, the stone moves onto
a conveyor belt that carries it to the
manufacturing plant about 6 kms away
in our case.
•Long conveyor belts must be kept
adjusted to the proper tension. This is
done by using steel cables to suspend
concrete weights inside the towers.
•At each point where the conveyor
changes height or direction, another bag
filter helps to remove dust from the
crushed stone and from the air.
•The limestone and shale are finally
stockpiled at the far end of the
production line.
SAFETY PRECUATIONS UNDERTAKEN IN
MINING AREA
• Only the authorized employees are permitted to handle the
explosives.
• There are demarcations around the blast location like barricades,
flag signs etc.
• The blast holes are being loaded under the control and supervision
of the designated competent person.
• The controlled blasting technique is being adopted.
• Cellular phones are not allowed in the blasting zone.
• The explosive vans speed should not exceed 25km/hr.
• Warning signals are given within a radius of 500 meters from the
place of firing.
• After the blasting a siren is blown as signal if it is all clear and safe.
• As the blasting is very dangerous for the eye at some distance also,
safety glasses should be provided and used at the blasting site.
CS Silo/Blending Silo
• The stone is loaded with a
front-end loader one
bucketful at a time onto a
conveyor that carries it
into the blending silo.
• Limestone and shale is
blended inside the
blending silo.
• Blending silo consists a
concrete/steel cone
inside.
CS Silo/Blending Silo
• Blending silos are gravity blenders. Another
prevailing term is homogenising silos instead of
blending silos.
• Often the creation of horizontal layers with
differing quality can be observed when silos are
in batch production.
• Depending on the product characteristics and
flow properties, different blenders are used in
order to achieve a higher grade of homogeneity.
Types of Blending Silos
1. Blending silo with pipe blender
• The pipes, arranged on the outer wall of the blending silo, have different nominal
diameters. Because of the specially constructed product inlets, the product is pre-
mixed both when it flows in and out of the mixing pipe.
• The different pipe diameters and lengths create a varying speed and flow profile
in the pipes. This results in further product homogenisation.
2. Blending silo with central pipe blender
• The product is concentrically drawn from various levels and fed into the mixing
chamber via a central pipe located in the middle of the silo.
• Due to the specially constructed material intake zones, the product is already pre-
mixed when it flows in from the various zones.
• The resulting crosswise mixing of the product has a significant and therefore
reinforcing effect on the efficiency of blending.
• Furthermore, the product is guided concentrically to the blending pipe. This
prevents the development of asymmetrical flow zones to the greatest extent
possible.
Types of Blending Silos(contd.)
3. Blending silo with cone blender
• A blender fitting integrated in the silo cone serves to distribute the product evenly.
The product is mixed via various flow zones and is guided to the outlet of the
blending silo.
• Due to the conical shape of the blender, the product flows from top to bottom
with increasing speed. Due to the different flow speeds, there are varying
residence times for the product. This increases the blending effect.
• The blender is suitable both for the continuous and discontinuous blending of bulk
goods. Thus existing silos can be retrofitted quickly and easily.
4. Blending silo with screw mixer
• The intensive mixing takes place in the lower silo part. The product is continuously
collected from the cone by a central vertical mixing screw and conveyed upwards
through the mixing pipe to the roof of the silo.
• The blended material is picked up by an ejector which distributes it in fine layers
over the container's entire width.
• The silo can be filled or discharged at any time irrespective of the blending
process.
• The mixing screw is powered by a gear motor which is located in the middle of the
silo roof.
General Layout of CS Silo
Construction of Blending Silo
• PCC of raft
• RCC of raft
• Starter of the shell
• Erection of slip form assembly
• Slipping (75 mtr)
• Thickness reduction of shell
• Dismantling of slip form system
• Backfilling outside and inside plinth
• PCC & RCC of floor slab
• Staging of inverted cone
• Shuttering and reinforcement of
inverted cone
• Concreting of inverted cone
• Dismantling of staging
• Erection of roof girder 80 mtr
level
• Erection of rolladeck
• Tying of reinforcement
• Shuttering of roof slab
• Casting of roof slab
STAGING FOR THE CONE INSIDE THE BLENDING SILO:
1. Welding of iron brackets to the
inner wall of the silo
Triangular iron brackets
2. Erection of purlins and support
Purlins
Winch MachineGirder attached to winch machine
by pulley system
3. Erection of girder on the bracketsGirder carried to the silo with the
help of crane
4. Finished platform for the construction of cone
Embedded plates on the surface
of the silo
Embedded Plate(EP)
Openings in the silo
Openings
Construction of Preheater
• PCC of raft
• Casting of raft including tying of
reinforcement bars
• Shuttering etc. Complete
• Casting of ‘l' column till + 6 m lvl
• Backfilling & pcc in plinth
• Erection of hydraulic jumpform
rigs - 8 nos.
• Casting of ‘l' column upto 1st
• Casting of ‘l’ column till + 6 m lvl(
conventionally)
• Casting of 1st slab @ 8.5 m. Lvl.
• Casting of 'l' column from
2ndslab to 3rd slab
• Casting of 'l' column from 1st
slab to 2nd slab
• Casting of 2nd slab @ 31.0 m. Lvl
• Casting of 3rd slab @ 46.5 m. Lvl
• Casting of 'l' column from 3rd slab
to 4th slab
• Casting of tie beam @ 21.0 m. Lvl
• Casting of 4th slab @ 61.0 m. Lvl
• Casting of 'l' column from 4th
slab to 5th slab
• Casting of 5th slab @ 73.0 m. Lvl.
• Casting of 'l' column from 5th
slab to 6th slab
• Casting of 6th slab @ 85.0 m. Lvl
General Layout of Preheater
Operating Characteristics of
Preheater
• High-efficiency cyclones with low pressure drop resulting in low fuel
and power consumption
• Lowest NOx emission from unique high-temperature reduction
zone
• Simultaneous low CO emission specially due to calciner notch and
outlet loop duct
• Uncomplicated operation with single entry locations of calciner
fuel and tertiary air
• Suitable for firing both traditional and alternative fuels
Preheater Components
Cyclones
• Preheaters are based on proven low
pressure loss (LP) cyclones. The unique
design of the LP cyclone ensures high
thermal efficiency and low pressure drop
while enabling a flexible and space-saving
layout.
• LP cyclones have no horizontal surfaces on
the inside for material to accumulate,
thereby securing stable operation.
• The top stage has a special geometry to
provide the lowest dust loss while
maintaining low pressure drop. Typical LP Cyclone
Central Pipes
• Central pipes (thimbles) are standard in all cyclone
stages to provide high separation efficiency.
•The lowermost cyclones feature a cast, segmented
design with a hanging suspension system and common
elements throughout. This enables easy installation and
maintenance.
Cast Segmented
Central Pipe
• To prevent gas from bypassing up through the
material pipes between the cyclone stages, the
pipes are equipped with sluice flaps (tipping
valves) designed for full opening.
• Good meal distribution in the cyclone riser
ducts is ensured by adjustable spreader plates
in the distribution boxes.
Sluice Flaps & Distribution Box
Material Pipe Sluice Flaps
Dividing gates
• Robust dividing gates are used to precisely and
consistently distribute meal to the different sections
of the riser duct and calciner.
• One gate is capable of dividing meal into two, three,
or four different streams.
Meal dividing gate
Tertiary Air Duct Damper
• To balance the combustion air flow between the kiln
and calciner, a tertiary air duct damper is provided for
reliable regulation of the tertiary air gases.
• The damper design features a solid refractory blade
for long, reliable life.
Tertiary air duct damper
Preheater Operation
• Raw meal is introduced at the inlet gas duct to the Stage I (top)
cyclones. It is subsequently preheated by hot, counter current gas
flow as it is continuously collected and passed down the other
cyclone stages in the preheater to the calciner. Fuel is burned in the
calciner to achieve 92-95% of the total material calcination before
collection in the bottom cyclone and entrance into the kiln.
Combustion air for the calciner is taken from the kiln via the riser
duct and through a separate tertiary air duct from the cooler.
• Design is based on dividing the meal from the second-lowest stage
cyclone to the kiln riser and the calciner. These feed points are
separated by an expanded riser duct that forms a NOx reducing
zone. That is, the calcining chamber is built into the kiln riser. All of
the calciner fuel is introduced to the kiln riser duct with less oxygen
than required for complete combustion, thereby forming a reducing
atmosphere.
Preheater Operation(contd.)
• Above the reduction zone is the main calciner vessel, which
is divided into two or more sections separated by a notch.
The changes in cross-sectional areas create turbulence that
ensures effective mixing of fuel, raw meal and gas,
improving heat transfer and combustion. The calciner
outlet loop duct ensures optimum gas retention time,
further mixing and complete fuel combustion.
• Optionally, the second or third-lowest stage cyclone
material can be further split to allow for diversion of a
portion of the meal directly into the upper section of the
calciner. This creates a “hot zone” in the lower section of
the calciner that is conducive to burning difficult fuels and
further NOx reduction.
Jump Formwork used in Preheater construction Preheater Construction
Rotary Kiln
• The rotary kiln consists of a tube
made from steel plate and lined
with firebrick. The tube slopes
slightly and slowly rotates on its
axis at between 30 and 250
revolutions per hour.
• Raw mix is fed in at the upper
end, and the rotation of the kiln
causes it gradually to move
downhill to the other end of the
kiln. At the other end, fuel in the
form of gas, oil or pulverized solid
fuel is blown in through "burner-
pipe“ producing a large
concentric flame in the lower part
of the kiln tube.
Rotary Kiln(Contd.)
• As material moves under the
flame, it reaches its peak
temperature, before dropping
out of the kiln tube into the
cooler.
• Air is drawn first through the
cooler and then through the
kiln for combustion of the fuel.
In the cooler the air is heated
by the cooling clinker, so that
it may be 400 to 800 °C before
it enters the kiln, thus causing
intense and rapid combustion
of the fuel.
General Layout of Rotary Kiln
Cooling Tower
• Clinker cooler has two main
function to perform.
1. To cool the hot clinker quickly.
2. To provide necessary air for
burning of coal in pre-calciner
and kiln.
• After introducing of red hot
clinker into the cooler,
mechanically driven gates
moves it to the rear end of
cooler. Three pair of gates are
installed inside the cooler. A
single pair consist of fixed gate
and movable gate. To and fro
moment of movable gate
pressurized which cools it
quickly.
Cooling Tower(Contd.)
• Clinker cools down gradually
as it moves, due to the air
blow by the fans which is
taken from the atmosphere.
Air falling over clinker is highly
pressurized which cools it
quickly. Clinker escaping out of
the cooler is fed to a hammer
crusher, since lumpy material
requires crushing.
• Crushed material is
transported to clinker silo
through deep bucket conveyor.
Temperature of clinker
escaping out of cooler is about
208 degree celcius.
Grate Cooler Operation
• The grate cooler operates with a cross current principle in which the
clinker is moved across the grate while cooling air blow in from below
through the grate and clinker layer.
• The hot clinker falls from kiln and forms clinker bed on the grate and
transported through the cooler over alternatively fixed and reciprocating
grates. At the inlet of first great clinker is quenched and spread across the
cooler width by the increased cooling air.
• The grate is fabricated to be as possible to obtained a thick clinker layer
and a uniform distribution of air through the clinker bed in the interest of
heat recovery.
• During the clinker transport from the cooler a part of dust and small size
clinker is falls from the grates and collected into hoppers under the grates.
The drag chain and rotary air lock system fed these clinker and dust in
clinker transport system. A dust collection ESP is also installed beside the
cooler known as cooler ESP. Exhaust gases from collection is fed to the ESP
for dust collection.
Grate Cooler Operation(Contd.)
• Grate cooler consist of
1. Cooling grate Plates
2. Standard Plates
3. Cooling housing
4. Drive unit
5. Grate aeration system
6. Clinker crusher
7. Conveying unit
8. Cooling fan
Tunnel Construction under cooling tower Columns construction of Cooling Tower
Coal Mill
• The coal mill works for producing the pulverized
coal for burning to increase the temperature of
kiln, pre-heater, raw mill .It works as same as raw
mill for lime-stone grinding & the coal mill grind
& transfer the coal to the furnace for burning.
• The raw mill is grounded dried swept away by fan
through the separator to bag filter or ESP. finally
it is stored in to the fine coal bin hot air for coal
mill is supplied by cooler exhaust hot gases or
pre-heater outlet gases before GTC circulation.
The function of coal mill is to ground suitable
grate coal and for feeding the same in to the kiln
and calciner in fluidized form.
• Coal from stock yard is fed for stacking and
reclaiming in to the stacker and reclaimer. Pre-
homogenized raw coal is feed in to the coal mill
hopper with the help of belt conveyer.
Coal Mill(Contd.)
• The raw is then fed to the coal mill VRM via
weigh feeder, drag chain and screw conveyer.
• Coal Mill is an important integral part of cement
plant. Here large size of approx size 600mm, is
ground fine to the size of 90 micron. Coal from
coal mill is used to feed kiln and calciner. Outlet
temperature of coal from coal mill is different in
different seasons.
• Coal from mines is initially crushed at crusher
site. Coal is then sent to stacking making mixture
homogenized. Reclaimer picks up the coal and
coal is fed to the coal mill hopper through belt
conveyer.
• Coal taken out from hopper is feed inside VRM
with the help of a screw conveyer which is
mounted just below the hopper.
• Coal inside VRM is grounded between roller and
table.
Coal Mill(Contd.)
• Hot air from cooler ESP fan is taken inside VRM and
is used for drying of coal.
• Fine coal from VRM moves to the cyclone, where
most of the coal is separated from air and the coal
which does not get collected due to ultra fine size is
separated with the help of ESP. LV separator is for
separating coarse and fine particles.
• Coal is fed to screw conveyer through rotary lock,
which transport it to the FK pumps. Two FK pump
delivers material to the storage bins. There are two
Storage bins
1. Kiln Bin
2. Pre-calciner Bin
• Fine Coal is then transported to the kiln and pre-
calciner by kiln firing FK pump and pre-calciner FK
pump respectively.
Clinker Silo
• Storage of cement clinker is a prerequisite for continuous
kiln operation. Constantly increasing kiln capacities ensure
storage volumes of 200,000 cubic meter or more.The
situation on site as well as the specific properties of the
material determine the configuration of the storage and
handling equipment. Above all the following aspects need
to be taken into consideration here:
• Available space
• Statics, soil bearing capacity and groundwater situation
• Bulk material temperature and flow properties
• Environmental regulations and aesthetics
• Investment and operational costs
• Capacity and unloading capacity (in automatic
operation)
Construction Of Clinker Silo
1. PCC of angular raft
2. RCCof angular raft
3. Shell wall (1100 mm thick) From
top of raft to GL by conventional
method
4. Backfilling in foundation
5. Casting of shell wall (600 mm thick)
From GL to +6.00 mtr by
conventionally
6. Erection of self climbing hydraulic
system
7. Casting of shell from +6.0 mtr to
35.0 mtr
Construction Of Clinker Silo(Contd.)
8. Dismantling of self climbing
hydraulic rigs
9. Casting of 1st lift of tunnel with
starter
10. PCC of tunnels including sand
filling upto 536.00 lvl
11. Casting of wall of tunnels
12. Casting of top slab of tunnels
13. Back-filing in foundation of
tunnels
14. Laying of floor PCC
15. Laying of grade slab over PCC
Jump formwork used in Clinker Silo Clinker Silo Construction
Quality Control
• Quality control is error prevention rather than error detection.
• Online reaction to special cause of variation will lead to progressive
improvement in the process, performance and cost.
• Fundamental improvement in quality results from testing rational
prediction about special process using statistical method. The effective
pursuit of quality permanent commitment through out an organization.
• Pitfall of the successful implantation of the permanent quality
improvement culture are:
 Lack of top management support.
 Lack of middle management support.
 Commitment to only department.
 Haphazard approach a little of this and that with no meaning change in
the system.
 Measurement of success and guidance program on the basis of short-
term profile.
Inference
• The Indian cement industry has been on a high growth
trajectory for more than a decade, led by buoyancy in
sectors such as real estate and construction. The
industry has witnessed continuous modernisation and
adoption of new technologies in recent years.
• The modern Indian cement plants are state-of-the-art
plants and amongst the best in the world. In order to
meet the expanding demand, cement companies are
fast developing new plants.
• Cement plant construction is quite a specific
construction and it requires high quality and precision
with adequate safety.
Cement Manufacturing Plant Construction

Contenu connexe

Tendances

Tendances (20)

Cement industry : grinding process of ball mill
Cement industry : grinding process of ball millCement industry : grinding process of ball mill
Cement industry : grinding process of ball mill
 
Cement mill notebook
Cement mill notebookCement mill notebook
Cement mill notebook
 
Formulas kiln
Formulas kilnFormulas kiln
Formulas kiln
 
Rotary kiln
Rotary kilnRotary kiln
Rotary kiln
 
Asphalt batch plant by majid
Asphalt batch plant by majidAsphalt batch plant by majid
Asphalt batch plant by majid
 
Armoured face conveyor
Armoured face conveyorArmoured face conveyor
Armoured face conveyor
 
COAL HANDLING PLANT
COAL  HANDLING PLANTCOAL  HANDLING PLANT
COAL HANDLING PLANT
 
Process for non process1
Process for non process1Process for non process1
Process for non process1
 
Cement Manufacturing hrs_eng
Cement Manufacturing hrs_engCement Manufacturing hrs_eng
Cement Manufacturing hrs_eng
 
Drilling equipments
Drilling equipmentsDrilling equipments
Drilling equipments
 
An Introduction to Rotary Kilns
An Introduction to Rotary KilnsAn Introduction to Rotary Kilns
An Introduction to Rotary Kilns
 
Manufacturing and Quality Control of Cement.
Manufacturing and Quality Control of Cement.Manufacturing and Quality Control of Cement.
Manufacturing and Quality Control of Cement.
 
Working of dragline
Working of draglineWorking of dragline
Working of dragline
 
Cement manufacturing process by shubham malviya
Cement manufacturing process by shubham malviyaCement manufacturing process by shubham malviya
Cement manufacturing process by shubham malviya
 
Cement course
Cement courseCement course
Cement course
 
Cement rotary kiln questions & answers
Cement rotary kiln questions & answersCement rotary kiln questions & answers
Cement rotary kiln questions & answers
 
Blasting
BlastingBlasting
Blasting
 
cement-plant-operation-handbook
cement-plant-operation-handbookcement-plant-operation-handbook
cement-plant-operation-handbook
 
classifications and working of mills in a power plant
classifications and working of mills in a power plantclassifications and working of mills in a power plant
classifications and working of mills in a power plant
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Presentation on CFBC Boilers
 

En vedette

Production & Operations Management
Production & Operations ManagementProduction & Operations Management
Production & Operations ManagementShri Hari Agrawal
 
Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...
Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...
Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...Ajjay Kumar Gupta
 
Cement Process Chemistry
Cement Process ChemistryCement Process Chemistry
Cement Process ChemistryShambhudayal
 
Heat optimisation pradeep kumar
Heat optimisation  pradeep kumarHeat optimisation  pradeep kumar
Heat optimisation pradeep kumarpradeepdeepi
 
Ring formation in kilns
Ring formation in kilnsRing formation in kilns
Ring formation in kilnspradeepdeepi
 
Neha Samant Resume
Neha Samant ResumeNeha Samant Resume
Neha Samant Resumeneha samant
 
LinkedIn Tips for Maximizing Employee Profiles Linking to Company Profiles
LinkedIn Tips for Maximizing Employee Profiles Linking to Company ProfilesLinkedIn Tips for Maximizing Employee Profiles Linking to Company Profiles
LinkedIn Tips for Maximizing Employee Profiles Linking to Company ProfilesGilmore Global
 
The Business of Real Estate
The Business of Real EstateThe Business of Real Estate
The Business of Real Estatemicmac60
 
Real estate profiles 101
Real estate profiles 101Real estate profiles 101
Real estate profiles 101Rise Realty
 
Filter bag sdl presentation v3
Filter bag sdl presentation v3Filter bag sdl presentation v3
Filter bag sdl presentation v3UNIDO SA
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 10
Course on Regulation and Sustainable Energy in Developing Countries - Session 10Course on Regulation and Sustainable Energy in Developing Countries - Session 10
Course on Regulation and Sustainable Energy in Developing Countries - Session 10Leonardo ENERGY
 
Project Portfolio Management - An insiders overview
Project Portfolio Management - An insiders overviewProject Portfolio Management - An insiders overview
Project Portfolio Management - An insiders overviewSaji Madapat
 

En vedette (20)

cement plant report
cement plant reportcement plant report
cement plant report
 
Cement plant-operation-handbook by yaser elkelawy
Cement plant-operation-handbook by yaser elkelawyCement plant-operation-handbook by yaser elkelawy
Cement plant-operation-handbook by yaser elkelawy
 
Cement
CementCement
Cement
 
Production & Operations Management
Production & Operations ManagementProduction & Operations Management
Production & Operations Management
 
Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...
Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...
Cement Manufacturing Plant, Detailed Project Report, Profile, Business Plan, ...
 
Cement Process Chemistry
Cement Process ChemistryCement Process Chemistry
Cement Process Chemistry
 
Heat optimisation pradeep kumar
Heat optimisation  pradeep kumarHeat optimisation  pradeep kumar
Heat optimisation pradeep kumar
 
Ring formation in kilns
Ring formation in kilnsRing formation in kilns
Ring formation in kilns
 
Neha Samant Resume
Neha Samant ResumeNeha Samant Resume
Neha Samant Resume
 
sohail_cv (1)
sohail_cv (1)sohail_cv (1)
sohail_cv (1)
 
LinkedIn Tips for Maximizing Employee Profiles Linking to Company Profiles
LinkedIn Tips for Maximizing Employee Profiles Linking to Company ProfilesLinkedIn Tips for Maximizing Employee Profiles Linking to Company Profiles
LinkedIn Tips for Maximizing Employee Profiles Linking to Company Profiles
 
The Business of Real Estate
The Business of Real EstateThe Business of Real Estate
The Business of Real Estate
 
Real estate profiles 101
Real estate profiles 101Real estate profiles 101
Real estate profiles 101
 
Filter bag sdl presentation v3
Filter bag sdl presentation v3Filter bag sdl presentation v3
Filter bag sdl presentation v3
 
Course on Regulation and Sustainable Energy in Developing Countries - Session 10
Course on Regulation and Sustainable Energy in Developing Countries - Session 10Course on Regulation and Sustainable Energy in Developing Countries - Session 10
Course on Regulation and Sustainable Energy in Developing Countries - Session 10
 
Presentation uks
Presentation uksPresentation uks
Presentation uks
 
Ee opportunities
Ee opportunities Ee opportunities
Ee opportunities
 
13 Deadly Mistakes of Construction Bidding
13 Deadly Mistakes of Construction Bidding13 Deadly Mistakes of Construction Bidding
13 Deadly Mistakes of Construction Bidding
 
Project Portfolio Management - An insiders overview
Project Portfolio Management - An insiders overviewProject Portfolio Management - An insiders overview
Project Portfolio Management - An insiders overview
 
Cement carbonation: can it help or hinter CO2 storage? - presentation given b...
Cement carbonation: can it help or hinter CO2 storage? - presentation given b...Cement carbonation: can it help or hinter CO2 storage? - presentation given b...
Cement carbonation: can it help or hinter CO2 storage? - presentation given b...
 

Similaire à Cement Manufacturing Plant Construction

Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxARUNKUMARC39
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)S M Rahat Rahman
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxChinnuNinan
 
deep foundation for hidth buliding (7).ppt
deep foundation  for hidth buliding (7).pptdeep foundation  for hidth buliding (7).ppt
deep foundation for hidth buliding (7).pptAbdulwalimusemohamed
 
Fluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdfFluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdfLokmanDridah
 
Underwater construction
Underwater constructionUnderwater construction
Underwater constructionHetviPatel58
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)ManviVarshney2
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge TrainingAbhishek Bharti
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...Arman Hashmi
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)SSudhaVelan
 
Concrete blocks and their types
Concrete blocks and their typesConcrete blocks and their types
Concrete blocks and their typesMaliha Mehr
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsAkash Tilokani
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptVaibhavSoni742163
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptHarshKumarEname
 

Similaire à Cement Manufacturing Plant Construction (20)

Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)Deep Foundation (Construction Engineering)
Deep Foundation (Construction Engineering)
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
 
deep foundation for hidth buliding (7).ppt
deep foundation  for hidth buliding (7).pptdeep foundation  for hidth buliding (7).ppt
deep foundation for hidth buliding (7).ppt
 
Fluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdfFluids & cementing 2022-2023 (1) (1).pdf
Fluids & cementing 2022-2023 (1) (1).pdf
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
WELL COMPLETIONS.pptx
WELL COMPLETIONS.pptxWELL COMPLETIONS.pptx
WELL COMPLETIONS.pptx
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
Concrete blocks and their types
Concrete blocks and their typesConcrete blocks and their types
Concrete blocks and their types
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm Walls
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 

Dernier

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 

Dernier (20)

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 

Cement Manufacturing Plant Construction

  • 1. Indian Institute Of Technology Delhi
  • 2. Case study Project:3750 TPD(Tonnes per Day) Pyro Project Loctaion:Dabok(nearUdaipur), Rajasthan Client: J.K.Lakshmi Cements Ltd. Civil Consultant:M/S Magcons Consulting Engineers Pvt Ltd,Mumbai Civil Contractor:M/S K.B.Mehta Construction Pvt Ltd,Ahmedabad Equipment Supplier:M/S LNVT Sinoma,China
  • 3. Project Overview • Dabok Cement Factory used to be a part of Udaipur Cement Works Limited(UCWL) some years back.This cement factory got down and was sold to J.K.Lakshmi Cement Company Limited. • J.K. Lakshmi currently has the facility of grinding the clinker and a packing plant but cement production is not done here. • J.K.Lakshmi decided for starting the production of cement at the current location.
  • 4. Existing Coal mill Existing Packing Plant
  • 5. Components of A Cement Plant • Quarry • CS Silo/Blending Silo • Preheater • Kiln • Cooling Tower • Clinker Silo • Grounding Mill • Packing Plant
  • 6. Current Status of Project • The construction of the Blending Silo(85 m) is completed from outside.Preparation for the staging for the construction of the cone inside the blending silo is going on. • The first two floors of the preheater are completed.Beam level of the 3rd floor(46 m) is almost reached. • Foundation of the preheater boiler is going on. • Piers for the installation of the kiln are aready constructed.
  • 7. • Foundation work of the cooling tower is almost over.The tunnel for the transport of clinker from the cooling tower to the clinker silo is under construction. • Construction of the clinker silo has reached almost upto the completion of the second floor.
  • 8. Site Soil Conditions • The site is situated in Udaipur,Rajasthan which has got hard,rocky soil conditions. • All the foundations are Raft foundations. Foundation of Preheater Shaft Cooling Tower Foundation Slab
  • 9. Quarry • The cement production plant should be located where the raw material for the production is available nearby. • The dark coloured rock in the picture contains limestone and two kinds of shale, all of which are used in producing cement. The light coloured material is called over-burden, which is not used in manufacturing, but is set aside to be replaced later during reclamation after the quarry has reached the end of its permit period and is closed.
  • 10. • The flat area in the quarry wall, called the lift or bench, is the depth to which holes are drilled before charges are set for blasting. Because of security requirements, most quarries subcontract the blasting operations. • After blasting, the waste stone is brought to the end of the quarry where quarrying first began. It will be the first material to be filled back in as part of the reclamation process. Usable stone is hauled by truck and either dumped into the primary crusher or piled nearby. • The roads and piles must be kept watered to reduce airborne dust.
  • 11. •After the stone is dumped into the feed chute from above, gravity moves it down through the crusher, which reduces it to about 3 inches in diameter. A bag filter helps reduce airborne dust. •From the crusher, the stone moves onto a conveyor belt that carries it to the manufacturing plant about 6 kms away in our case. •Long conveyor belts must be kept adjusted to the proper tension. This is done by using steel cables to suspend concrete weights inside the towers. •At each point where the conveyor changes height or direction, another bag filter helps to remove dust from the crushed stone and from the air. •The limestone and shale are finally stockpiled at the far end of the production line.
  • 12. SAFETY PRECUATIONS UNDERTAKEN IN MINING AREA • Only the authorized employees are permitted to handle the explosives. • There are demarcations around the blast location like barricades, flag signs etc. • The blast holes are being loaded under the control and supervision of the designated competent person. • The controlled blasting technique is being adopted. • Cellular phones are not allowed in the blasting zone. • The explosive vans speed should not exceed 25km/hr. • Warning signals are given within a radius of 500 meters from the place of firing. • After the blasting a siren is blown as signal if it is all clear and safe. • As the blasting is very dangerous for the eye at some distance also, safety glasses should be provided and used at the blasting site.
  • 13. CS Silo/Blending Silo • The stone is loaded with a front-end loader one bucketful at a time onto a conveyor that carries it into the blending silo. • Limestone and shale is blended inside the blending silo. • Blending silo consists a concrete/steel cone inside.
  • 14. CS Silo/Blending Silo • Blending silos are gravity blenders. Another prevailing term is homogenising silos instead of blending silos. • Often the creation of horizontal layers with differing quality can be observed when silos are in batch production. • Depending on the product characteristics and flow properties, different blenders are used in order to achieve a higher grade of homogeneity.
  • 15. Types of Blending Silos 1. Blending silo with pipe blender • The pipes, arranged on the outer wall of the blending silo, have different nominal diameters. Because of the specially constructed product inlets, the product is pre- mixed both when it flows in and out of the mixing pipe. • The different pipe diameters and lengths create a varying speed and flow profile in the pipes. This results in further product homogenisation. 2. Blending silo with central pipe blender • The product is concentrically drawn from various levels and fed into the mixing chamber via a central pipe located in the middle of the silo. • Due to the specially constructed material intake zones, the product is already pre- mixed when it flows in from the various zones. • The resulting crosswise mixing of the product has a significant and therefore reinforcing effect on the efficiency of blending. • Furthermore, the product is guided concentrically to the blending pipe. This prevents the development of asymmetrical flow zones to the greatest extent possible.
  • 16. Types of Blending Silos(contd.) 3. Blending silo with cone blender • A blender fitting integrated in the silo cone serves to distribute the product evenly. The product is mixed via various flow zones and is guided to the outlet of the blending silo. • Due to the conical shape of the blender, the product flows from top to bottom with increasing speed. Due to the different flow speeds, there are varying residence times for the product. This increases the blending effect. • The blender is suitable both for the continuous and discontinuous blending of bulk goods. Thus existing silos can be retrofitted quickly and easily. 4. Blending silo with screw mixer • The intensive mixing takes place in the lower silo part. The product is continuously collected from the cone by a central vertical mixing screw and conveyed upwards through the mixing pipe to the roof of the silo. • The blended material is picked up by an ejector which distributes it in fine layers over the container's entire width. • The silo can be filled or discharged at any time irrespective of the blending process. • The mixing screw is powered by a gear motor which is located in the middle of the silo roof.
  • 17. General Layout of CS Silo
  • 18. Construction of Blending Silo • PCC of raft • RCC of raft • Starter of the shell • Erection of slip form assembly • Slipping (75 mtr) • Thickness reduction of shell • Dismantling of slip form system • Backfilling outside and inside plinth • PCC & RCC of floor slab • Staging of inverted cone
  • 19. • Shuttering and reinforcement of inverted cone • Concreting of inverted cone • Dismantling of staging • Erection of roof girder 80 mtr level • Erection of rolladeck • Tying of reinforcement • Shuttering of roof slab • Casting of roof slab
  • 20. STAGING FOR THE CONE INSIDE THE BLENDING SILO: 1. Welding of iron brackets to the inner wall of the silo Triangular iron brackets 2. Erection of purlins and support Purlins
  • 21. Winch MachineGirder attached to winch machine by pulley system
  • 22. 3. Erection of girder on the bracketsGirder carried to the silo with the help of crane
  • 23. 4. Finished platform for the construction of cone
  • 24. Embedded plates on the surface of the silo Embedded Plate(EP) Openings in the silo Openings
  • 25. Construction of Preheater • PCC of raft • Casting of raft including tying of reinforcement bars • Shuttering etc. Complete • Casting of ‘l' column till + 6 m lvl • Backfilling & pcc in plinth • Erection of hydraulic jumpform rigs - 8 nos. • Casting of ‘l' column upto 1st • Casting of ‘l’ column till + 6 m lvl( conventionally) • Casting of 1st slab @ 8.5 m. Lvl.
  • 26. • Casting of 'l' column from 2ndslab to 3rd slab • Casting of 'l' column from 1st slab to 2nd slab • Casting of 2nd slab @ 31.0 m. Lvl • Casting of 3rd slab @ 46.5 m. Lvl • Casting of 'l' column from 3rd slab to 4th slab • Casting of tie beam @ 21.0 m. Lvl • Casting of 4th slab @ 61.0 m. Lvl • Casting of 'l' column from 4th slab to 5th slab • Casting of 5th slab @ 73.0 m. Lvl. • Casting of 'l' column from 5th slab to 6th slab • Casting of 6th slab @ 85.0 m. Lvl
  • 27. General Layout of Preheater
  • 28. Operating Characteristics of Preheater • High-efficiency cyclones with low pressure drop resulting in low fuel and power consumption • Lowest NOx emission from unique high-temperature reduction zone • Simultaneous low CO emission specially due to calciner notch and outlet loop duct • Uncomplicated operation with single entry locations of calciner fuel and tertiary air • Suitable for firing both traditional and alternative fuels
  • 29. Preheater Components Cyclones • Preheaters are based on proven low pressure loss (LP) cyclones. The unique design of the LP cyclone ensures high thermal efficiency and low pressure drop while enabling a flexible and space-saving layout. • LP cyclones have no horizontal surfaces on the inside for material to accumulate, thereby securing stable operation. • The top stage has a special geometry to provide the lowest dust loss while maintaining low pressure drop. Typical LP Cyclone
  • 30. Central Pipes • Central pipes (thimbles) are standard in all cyclone stages to provide high separation efficiency. •The lowermost cyclones feature a cast, segmented design with a hanging suspension system and common elements throughout. This enables easy installation and maintenance. Cast Segmented Central Pipe • To prevent gas from bypassing up through the material pipes between the cyclone stages, the pipes are equipped with sluice flaps (tipping valves) designed for full opening. • Good meal distribution in the cyclone riser ducts is ensured by adjustable spreader plates in the distribution boxes. Sluice Flaps & Distribution Box Material Pipe Sluice Flaps
  • 31. Dividing gates • Robust dividing gates are used to precisely and consistently distribute meal to the different sections of the riser duct and calciner. • One gate is capable of dividing meal into two, three, or four different streams. Meal dividing gate Tertiary Air Duct Damper • To balance the combustion air flow between the kiln and calciner, a tertiary air duct damper is provided for reliable regulation of the tertiary air gases. • The damper design features a solid refractory blade for long, reliable life. Tertiary air duct damper
  • 32. Preheater Operation • Raw meal is introduced at the inlet gas duct to the Stage I (top) cyclones. It is subsequently preheated by hot, counter current gas flow as it is continuously collected and passed down the other cyclone stages in the preheater to the calciner. Fuel is burned in the calciner to achieve 92-95% of the total material calcination before collection in the bottom cyclone and entrance into the kiln. Combustion air for the calciner is taken from the kiln via the riser duct and through a separate tertiary air duct from the cooler. • Design is based on dividing the meal from the second-lowest stage cyclone to the kiln riser and the calciner. These feed points are separated by an expanded riser duct that forms a NOx reducing zone. That is, the calcining chamber is built into the kiln riser. All of the calciner fuel is introduced to the kiln riser duct with less oxygen than required for complete combustion, thereby forming a reducing atmosphere.
  • 33. Preheater Operation(contd.) • Above the reduction zone is the main calciner vessel, which is divided into two or more sections separated by a notch. The changes in cross-sectional areas create turbulence that ensures effective mixing of fuel, raw meal and gas, improving heat transfer and combustion. The calciner outlet loop duct ensures optimum gas retention time, further mixing and complete fuel combustion. • Optionally, the second or third-lowest stage cyclone material can be further split to allow for diversion of a portion of the meal directly into the upper section of the calciner. This creates a “hot zone” in the lower section of the calciner that is conducive to burning difficult fuels and further NOx reduction.
  • 34. Jump Formwork used in Preheater construction Preheater Construction
  • 35. Rotary Kiln • The rotary kiln consists of a tube made from steel plate and lined with firebrick. The tube slopes slightly and slowly rotates on its axis at between 30 and 250 revolutions per hour. • Raw mix is fed in at the upper end, and the rotation of the kiln causes it gradually to move downhill to the other end of the kiln. At the other end, fuel in the form of gas, oil or pulverized solid fuel is blown in through "burner- pipe“ producing a large concentric flame in the lower part of the kiln tube.
  • 36. Rotary Kiln(Contd.) • As material moves under the flame, it reaches its peak temperature, before dropping out of the kiln tube into the cooler. • Air is drawn first through the cooler and then through the kiln for combustion of the fuel. In the cooler the air is heated by the cooling clinker, so that it may be 400 to 800 °C before it enters the kiln, thus causing intense and rapid combustion of the fuel.
  • 37. General Layout of Rotary Kiln
  • 38. Cooling Tower • Clinker cooler has two main function to perform. 1. To cool the hot clinker quickly. 2. To provide necessary air for burning of coal in pre-calciner and kiln. • After introducing of red hot clinker into the cooler, mechanically driven gates moves it to the rear end of cooler. Three pair of gates are installed inside the cooler. A single pair consist of fixed gate and movable gate. To and fro moment of movable gate pressurized which cools it quickly.
  • 39. Cooling Tower(Contd.) • Clinker cools down gradually as it moves, due to the air blow by the fans which is taken from the atmosphere. Air falling over clinker is highly pressurized which cools it quickly. Clinker escaping out of the cooler is fed to a hammer crusher, since lumpy material requires crushing. • Crushed material is transported to clinker silo through deep bucket conveyor. Temperature of clinker escaping out of cooler is about 208 degree celcius.
  • 40. Grate Cooler Operation • The grate cooler operates with a cross current principle in which the clinker is moved across the grate while cooling air blow in from below through the grate and clinker layer. • The hot clinker falls from kiln and forms clinker bed on the grate and transported through the cooler over alternatively fixed and reciprocating grates. At the inlet of first great clinker is quenched and spread across the cooler width by the increased cooling air. • The grate is fabricated to be as possible to obtained a thick clinker layer and a uniform distribution of air through the clinker bed in the interest of heat recovery. • During the clinker transport from the cooler a part of dust and small size clinker is falls from the grates and collected into hoppers under the grates. The drag chain and rotary air lock system fed these clinker and dust in clinker transport system. A dust collection ESP is also installed beside the cooler known as cooler ESP. Exhaust gases from collection is fed to the ESP for dust collection.
  • 41. Grate Cooler Operation(Contd.) • Grate cooler consist of 1. Cooling grate Plates 2. Standard Plates 3. Cooling housing 4. Drive unit 5. Grate aeration system 6. Clinker crusher 7. Conveying unit 8. Cooling fan
  • 42. Tunnel Construction under cooling tower Columns construction of Cooling Tower
  • 43. Coal Mill • The coal mill works for producing the pulverized coal for burning to increase the temperature of kiln, pre-heater, raw mill .It works as same as raw mill for lime-stone grinding & the coal mill grind & transfer the coal to the furnace for burning. • The raw mill is grounded dried swept away by fan through the separator to bag filter or ESP. finally it is stored in to the fine coal bin hot air for coal mill is supplied by cooler exhaust hot gases or pre-heater outlet gases before GTC circulation. The function of coal mill is to ground suitable grate coal and for feeding the same in to the kiln and calciner in fluidized form. • Coal from stock yard is fed for stacking and reclaiming in to the stacker and reclaimer. Pre- homogenized raw coal is feed in to the coal mill hopper with the help of belt conveyer.
  • 44. Coal Mill(Contd.) • The raw is then fed to the coal mill VRM via weigh feeder, drag chain and screw conveyer. • Coal Mill is an important integral part of cement plant. Here large size of approx size 600mm, is ground fine to the size of 90 micron. Coal from coal mill is used to feed kiln and calciner. Outlet temperature of coal from coal mill is different in different seasons. • Coal from mines is initially crushed at crusher site. Coal is then sent to stacking making mixture homogenized. Reclaimer picks up the coal and coal is fed to the coal mill hopper through belt conveyer. • Coal taken out from hopper is feed inside VRM with the help of a screw conveyer which is mounted just below the hopper. • Coal inside VRM is grounded between roller and table.
  • 45. Coal Mill(Contd.) • Hot air from cooler ESP fan is taken inside VRM and is used for drying of coal. • Fine coal from VRM moves to the cyclone, where most of the coal is separated from air and the coal which does not get collected due to ultra fine size is separated with the help of ESP. LV separator is for separating coarse and fine particles. • Coal is fed to screw conveyer through rotary lock, which transport it to the FK pumps. Two FK pump delivers material to the storage bins. There are two Storage bins 1. Kiln Bin 2. Pre-calciner Bin • Fine Coal is then transported to the kiln and pre- calciner by kiln firing FK pump and pre-calciner FK pump respectively.
  • 46. Clinker Silo • Storage of cement clinker is a prerequisite for continuous kiln operation. Constantly increasing kiln capacities ensure storage volumes of 200,000 cubic meter or more.The situation on site as well as the specific properties of the material determine the configuration of the storage and handling equipment. Above all the following aspects need to be taken into consideration here: • Available space • Statics, soil bearing capacity and groundwater situation • Bulk material temperature and flow properties • Environmental regulations and aesthetics • Investment and operational costs • Capacity and unloading capacity (in automatic operation)
  • 47. Construction Of Clinker Silo 1. PCC of angular raft 2. RCCof angular raft 3. Shell wall (1100 mm thick) From top of raft to GL by conventional method 4. Backfilling in foundation 5. Casting of shell wall (600 mm thick) From GL to +6.00 mtr by conventionally 6. Erection of self climbing hydraulic system 7. Casting of shell from +6.0 mtr to 35.0 mtr
  • 48. Construction Of Clinker Silo(Contd.) 8. Dismantling of self climbing hydraulic rigs 9. Casting of 1st lift of tunnel with starter 10. PCC of tunnels including sand filling upto 536.00 lvl 11. Casting of wall of tunnels 12. Casting of top slab of tunnels 13. Back-filing in foundation of tunnels 14. Laying of floor PCC 15. Laying of grade slab over PCC
  • 49. Jump formwork used in Clinker Silo Clinker Silo Construction
  • 50. Quality Control • Quality control is error prevention rather than error detection. • Online reaction to special cause of variation will lead to progressive improvement in the process, performance and cost. • Fundamental improvement in quality results from testing rational prediction about special process using statistical method. The effective pursuit of quality permanent commitment through out an organization. • Pitfall of the successful implantation of the permanent quality improvement culture are:  Lack of top management support.  Lack of middle management support.  Commitment to only department.  Haphazard approach a little of this and that with no meaning change in the system.  Measurement of success and guidance program on the basis of short- term profile.
  • 51. Inference • The Indian cement industry has been on a high growth trajectory for more than a decade, led by buoyancy in sectors such as real estate and construction. The industry has witnessed continuous modernisation and adoption of new technologies in recent years. • The modern Indian cement plants are state-of-the-art plants and amongst the best in the world. In order to meet the expanding demand, cement companies are fast developing new plants. • Cement plant construction is quite a specific construction and it requires high quality and precision with adequate safety.