SlideShare une entreprise Scribd logo
1  sur  85
Télécharger pour lire hors ligne
Advanced
Grid Connection Workshop
The Innovation Centre, Sci-Tech Daresbury,
16th July 2013

Welcome and Introduction
George Hall, Project Manager
The Wind-Tech Project
INNOVATIVE THINKING
FOR THE REAL WORLD
Programme
9.00

Welcome & introduction
Dr. George Hall, Wind-Tech Project, UCLan

9.10
9.20
9.50
10.45
11.00
12.00
12.30

Introduction to the workshop
Part 1: Variation in grid voltage and the need for DNO studies
Part 2: The rural grid in detail: Schematic diagrams for most rural connections
Morning Refreshments
Exercise 1: Completing a site survey for an example PV, hydro or wind project
Part 3: Larger grid connection projects and case studies
Geoff Owen, Grid Connections
Lunch

1.30
2.00
2.45
3.00

Part 3: Larger grid connection projects and case studies (continued)
Part 4: Additional grid connection
Afternoon refreshments
Exercise 2: Completing the ENA application form for an example project

4.30

Summary and surgery: one-to-one advice

Geoff Owen
Geoff Owen, Dr. George Hall

INNOVATIVE THINKING
FOR THE REAL WORLD
Today’s workshop
• Following the energy and grid connection basics workshop, today
we will investigate in more detail the complexity of connecting to
the grid;
• A more interactive workshop, with morning and afternoon group
exercises, with support from the Wind-Tech team;
• Follow-on support from the Wind-Tech team for companies
interested in wind turbine technologies, or other forms of
renewable technology, available after today’s workshop.

INNOVATIVE THINKING
FOR THE REAL WORLD
Today’s workshop
Please note:
The information provided today is done so in an advisory capacity
only. The supplier shall not incur any liability for any action or
omission arising out of any reliance being placed on this information
by any organisation or other person. Any organisation or person in
receipt of this information should take their own legal, financial and
other relevant professional advice when considering what action (if
any) to take in respect of any grid connection, renewable strategy,
initiative, proposal, or other involvement with any renewable
technology, before placing any reliance on anything contained
herein.

INNOVATIVE THINKING
FOR THE REAL WORLD
Advanced
Grid Connection Workshop
16th July 2013

Geoff Owen,
Grid Connections
INNOVATIVE THINKING
FOR THE REAL WORLD
Level 1 review
• Essential power terminology & application for renewable
generation projects
• G83 is under 16 amp per phase
• G59 is over 16 amps per phase
• One G83 project is allowed per customer
• Once a G83 project is fitted to increase or add another project
will require a G59 application & permission from the DNO
• The function of the DNO grid and connections
• Application and upstanding grid connectivity for renewable
energy projects

INNOVATIVE THINKING
FOR THE REAL WORLD
LEVEL 2
Workshop Content
Part 1:
Part 2:
Exercise 1:
Part 3:
Part 4:
Exercise 2:

Variation in grid voltage and the reason for
DNO studies
The rural grid in detail
Completing a site survey
Larger grid connection projects and case
studies
Additional grid connection considerations
Completing the ENA application form for an
example project
INNOVATIVE THINKING
FOR THE REAL WORLD
Renewable power generation
Essential considerations for projects
• If there is no consumer demand then there is limited
justification to install a generation project
• The Availability of FIT support will not be there for long
• The installation of renewable power technologies enables
consumers to take control of their energy costs and limit their
exposure to future price increases.

• De-centralised power generation can reduce transmission grid
losses.

INNOVATIVE THINKING
FOR THE REAL WORLD
Part 1: Variation in grid voltage and
the need for DNO studies
• For a generator to work and stay connected it must operate within
design parameters
• G83 upper cut of voltage stage 1 (@51.5HZ) 262.2 volts in 90
seconds
• G59 upper cut of voltage stage 1 (@51.5HZ) 253 volts in 90 seconds
• The grid supply transformer is set at 250 volts at the source, this
allows a head room of only 3 volts
• In periods of low customer load the grid volts are high through out
the grid system, generation may increase the grid voltage resulting
in invertors and protection relays operating with loss of generation,
and Grid voltage pushed beyond statutory levels

INNOVATIVE THINKING
FOR THE REAL WORLD
Why is the Grid connection process
so complicated?
•

Grid systems were never designed for multiple smaller
generation connections, designed for power flow in one
direction

•

DNO’s have to guarantee to the customers the quality
of supply and availability 24/7

•

Increasing number of projects could result in a unstable
Grid system, with undermining of network supply
security

INNOVATIVE THINKING
FOR THE REAL WORLD
DNO Responsibilities
These are the statutory obligations under the
terms of their licence
•
•
•
•
•

Secure operation and development of the network;
Safe & reliable operation of the network;
Ensure fair and equal access to the network;
Least cost options for connection;
Lifetime ownership of network not just your
connection.
INNOVATIVE THINKING
FOR THE REAL WORLD
Grid voltage variation
• The voltage level in the UK was
standardised with the EU

• The DNO is responsible for the supply
characteristics and is directly responsible
for guaranteeing the supply quality to all
customers
• The supply characteristics are declared
as 400/230 volts (+10% to -6%), 50Hz
damage to electrical equipment will
result if the if the supply voltage goes
outside of the stated range
• Customer switches on large motor
• G83 or G59 nuisance tripping

Low
customer
load

Maximum
253 volts
Normal grid 240
volts

high customer
load

Minimum 216 volts

Grid transformer output set at 250/433 volts
INNOVATIVE THINKING
FOR THE REAL WORLD
DNO’s EXISTING ELECTRICITY NETWORK (LV grid)
Voltage at source set
250/433 volts

Small 3 phase
Commercial supply
Supplying Sub station
Small single
phase cable to
house

Large 3 phase
Commercial
supply

Cable joints in
highway

3 C 300 mm W cable in pathway or road
DNO designs infrastructure connections to guarantee the supply quality

INNOVATIVE THINKING
FOR THE REAL WORLD
Voltage variation data with customer load
for proposed G83 generation
Peak 254 volts
252 volts
244 volts

Day 1

Day 2

Day 3

Switching on of motor load
INNOVATIVE THINKING
FOR THE REAL WORLD
Hz

Frequency variation data with customer load
for proposed G83 generation

50.3

50.18.

50.06

49.94

49.82
49.7

Day 1

Day 2

Day 3
INNOVATIVE THINKING
FOR THE REAL WORLD
Part 2: The rural grid in detail
Introduction to the complexity and schematic
view of most rural connection arrangements
for projects < 50kW
Warning
Excludes non-standard DNO supply systems that are awaiting a
system upgrade

Will the grid connection cost undermine the
F.I.T/energy reduction investment return?
INNOVATIVE THINKING
FOR THE REAL WORLD
Essential Information
Supplied by sustainable Energy Eystems
Installer of over 300 small WT’s in the last 5 years
What you must have
• Good healthy DNO supply

• Single phase or 3 phase

INNOVATIVE THINKING
FOR THE REAL WORLD
Examples of poor connection capability
• More than one property run
from the transformer
• End of line connection
• Long distance to three phase
line
• Low on site usage
• Old supply transformer
• High voltage tapings on the
supply transformer
INNOVATIVE THINKING
FOR THE REAL WORLD
Rural supplies
• 70 % of rural areas have a single phase supply
system
• A technical assessment must be made before
any applications are submitted to the DNO
• A project must initially have view of the likely
GRID connectivity and costs
• Submit a budgetary request to the DNO for
indicative costs
INNOVATIVE THINKING
FOR THE REAL WORLD
Rural overhead line supplies & grid connectivity

HV 3 phase
supply

• This supply arrangement provides
single phase to the customer
• MCS generator project
connectivity is 3.68kW

Transformer
HV to LV
single phase

• Cost to upgrade for 3 phase if pole
is suitable (£6k to £15k)
Single phase LV
supply to a
farm

INNOVATIVE THINKING
FOR THE REAL WORLD
70% of rural overhead line supplies are
single phase only
• This supply
arrangement can only
provide single phase to
the customer

HV 2
phase
supply

• MCS generator project
connectivity is 3.68kW
• Cost to upgrade to 3
phase, with a new pole
transformer = £18k

DNO HV/LV
transformer

Substation name and pole number

Single phase supply to
customer

• New lines and poles =
£80 = £120/m

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single phase rural
grid supplies with one customer
Proposed 3.68 kW single phase WT

Small LV grid cables
Single phase LV grid cable

G 83
generator

1 Customer

• Installed under G83
• May require later DNO grid upgrade

High voltage
lines
INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single phase rural
grid supplies to one customer
Proposed >11 kW < 50 kW single phase WT

Single phase LV grid Cable
Small LV grid cables

G 59
generator
• G59 application to DNO
• Installed under G59
• DNO grid upgrade & costs to connect

Customer no 1

High voltage
lines
INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single phase rural grid
supplies with more than one customer
Customer no. 3
Single phase LV grid cables
Small LV 3 phase grid cable

G 83
generator

Customer no. 2

Customer no. 1

• Single phase installed under G83 maximum of 3.68 kW
• May require later DNO grid upgrade

High voltage
lines

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single phase rural grid
supplies with more than one customer
Proposed 5 kW WT limited to ( 3.68 kW output)
Customer no 3
Small LV single phase grid cables

G 59
generator

Customer no 2

Customer no 1

• G59 application to DNO with technical details
• With DNO’s agreement installed under G83
maximum output 3.68 kW
• May attract DNO grid upgrade costs

High voltage
lines

INNOVATIVE THINKING
FOR THE REAL WORLD
Rural Case Study
Grid upgrade costs for exceeding 16 amps

• Evance 9000 installed in Rossendale
• Planning submitted and passed
• Application submitted to DNO for
connection of 5 kw
• Grid costs excessive £ 20,000
• Technical agreement with DNO to cap
turbine output to 3.6kW – nil cost

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single phase
rural grid supplies

Proposed 10 kW to 50 kW single phase WT
Customer no 3

Single phase LV grid cables

G 59
generator

Customer no 2

• G59 application to DNO
• installed under G 59
• DNO grid upgrade & costs to connect

Customer no 1

High voltage
lines

New S/S for
customer no 2
INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for split phase rural grid supplies
with more than one customer
Proposed 3.68 kW single phase WT
Customer no 2
Small LV grid cables
Split ( single) phase LV grid cable

G 83
generator

Customer no 1
Has 2 x 1 phase supplies

High voltage
lines

• 1x3.68 kW project installed under G83
• A second project will require G83 stage 2 application to DNO

INNOVATIVE THINKING
FOR THE REAL WORLD
Single (split) or three phase ?
• In a rural area if there is any doubt
• Competent electrician to carry out voltage test
a the source of the supply on the customers
side
• Contact the DNO

INNOVATIVE THINKING
FOR THE REAL WORLD
Overhead supply with
three phase transformer
HV 3 phase
supply

Overhead LV
3 phase
supply to
customer

• Maximum rated capacity
50KVA (approx 70 amps per
phase)

• MCS generator project
connectivity is 11kW
• Exceeding 11 kW will require
connection approval from the
DNO

Transformer
HV to LV 3
phase

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for 3 phase rural
grid supplies to one customer
Proposed 11 kW 3phase WT

3 phase LV grid cable
G 83
generator

Installed under G83
May require later DNO grid upgrade

Customer no 1

High voltage
lines

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for 3 phase rural grid
supplies to one customer
Proposed >11 kW <50kW 3phase WT

3 phase LV grid cable
G 59
generator

• G59 Application to DNO
• Installed under G 59
• Grid upgrade & costs to connect

Customer no 1

High voltage
lines

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single/3 phase rural grid
supplies with more than one customer
Proposed >11 kW < 50 kW 3 phase WT
Customer no 3
3 phase LV grid cable

G 59
generator

Customer no 2

• G59 Application to DNO
• Installed under G 59
• Grid upgrade to connect

Customer no 1

New S/S for
customer no 2

High voltage
lines

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single/3 phase rural grid
supplies with more than one customer
Proposed 3.68 kW single phase WT
Customer no 3
Small LV grid cables
3 phase LV grid cable

G 83
generator

Customer no 2

• Installed under G83
• May require later DNO grid upgrade

Customer no 1

High voltage
lines

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single/3 phase rural grid
supplies with more than one customer
Proposed 11 kW 3 phase WT
Customer no 3
3 phase LV grid cable

Single phase grid
service cable to
customer

G 83
generator

Customer no 2

Customer no 1

High voltage
lines

• Request to DNO to upgrade supply customer supply
from 1 phase to 3 phase ( from £1,500 to £ 4,500)
• Installed under G83
• May require later DNO grid upgrade to transformer

INNOVATIVE THINKING
FOR THE REAL WORLD
Connectivity for single/3 phase rural grid
supplies with more than one customer
Proposed >11 kW < 50 kW 3 phase WT
Customer no 3
3 phase LV grid cable

G 59
generator

Customer no 2

Customer no 1

High voltage
lines

New S/S for customer no 2
• G59 Application to DNO
• Installed under G 59
• Grid upgrade to connect

INNOVATIVE THINKING
FOR THE REAL WORLD
Larger rural supplies
The H pole
Maximum size of grid transformer 200kVA
feeding
• Dedicated customers
•Several costumers in one area
• MCS generator project connectivity is
11kW ( or 3.68kW for single phase supplies)
•Exceeding 11 kW will require connection
approval from the DNO

Larger generator projects will require
permission from the DNO to connect
240/415 volt LV grid to customers
11KV DNO grid

INNOVATIVE THINKING
FOR THE REAL WORLD
Firm grid connection quotation
• Will include:
–
–
–
–

Connection permission
Terms and conditions specific to the project
Any connection costs
Legal work if required

• On acceptance, the project work can commence
– You can install the project to the submitted design
– You must follow G83 & G59 Compliance stages
– You must complete the test and commissioning stages.

INNOVATIVE THINKING
FOR THE REAL WORLD
Case Study
Small Hydro G59 connection
Small 15kW hydro project in a remote valley
• Refer to site map for further information
• Large valley with no 3 phase grid supply
• A technical solution agreed with the DNO

INNOVATIVE THINKING
FOR THE REAL WORLD
Case Study Rural location:
10kWp School project
The Project
• Grid supply looks like it is 3 phase
• Installation has 3 phase TP/N switch fuse
• Sales person secured a 10 kWp PV array contract
• PV panels and inverters were installed
• Electrician was sent to complete the connection
to G83 standards
The issue
• The electrician discovered that the supply was
actually 3 x single phase supplies
• The incoming overhead grid lines to the grid
distribution transformer only have 2 cables.
• There is no 3 phase supply in the area
The Solution
• They submitted G83/2 application requesting
permission to connect multiple projects.
INNOVATIVE THINKING
FOR THE REAL WORLD
Case Study
Two incoming HV lines supplying village
No 3 phase supply

INNOVATIVE THINKING
FOR THE REAL WORLD
Case Study
Two incoming HV lines supplying village
No 3 phase supply

INNOVATIVE THINKING
FOR THE REAL WORLD
Do’s
•
•
•
•

Have a view of what is involved
Carry out a detailed site survey
Understand the potential connection costs
Make the right decisions, at the right time

Dont’s
•
•
•
•

Ignore grid connection
Leave it to the last minute
Make assumptions
Request a firm grid connection offer until you are in a position
to accept
INNOVATIVE THINKING
FOR THE REAL WORLD
Break time
INNOVATIVE THINKING
FOR THE REAL WORLD
Exercise 1: Completing a site survey
Group exercise with feedback and discussion
• You are going to a site, to undertake a survey for a
renewable energy project.
• Maximum of three groups
• List what you think you need to consider when
undertaking this site survey…
1. 50kW hydro 3 phase generator
2. 150 kW peak PV solar
3. G83 or G59 WT generation
INNOVATIVE THINKING
FOR THE REAL WORLD
Site Survey 1
Proposed 50kW Hydro project: The Weir

INNOVATIVE THINKING
FOR THE REAL WORLD
Site Survey 2: Burnley College
150 kW peak PV solar

Proposed PV 150
kWp project

INNOVATIVE THINKING
FOR THE REAL WORLD
Site Survey 3
Proposed 2 x 11 kW Gaia turbines
The project:
Green Farm

Existing supply

INNOVATIVE THINKING
FOR THE REAL WORLD
INNOVATIVE THINKING
FOR THE REAL WORLD

49
Part 3
large power connections

Have a view of what is involved
INNOVATIVE THINKING
FOR THE REAL WORLD
The UK Grid layout
Provides a network of cables and substations to transport power
to customers
Domestic
and small
industrial
supplies

240/415 volts

Manual connected network

Large
customers
supplies

Automatic connected network

Area
distribution
6.6kV11kV
Primary Grid
supply into areas
33kV 66kV

Bulk supply
point to DNO
132 kV
Power
stations
network
connected

Power Station

INNOVATIVE THINKING
FOR THE REAL WORLD
National grid transmission 400kV
Other considerations
• Network capacity issues
• Connection capacity race
• Technical, design for firm grid application,
correct choice of generator , thermal limits,
voltage limits, reverse power flow, switch gear
rating and fault levels, protection
arrangements, power quality , earthing
stability ,
• Competent design /experienced consultants
INNOVATIVE THINKING
FOR THE REAL WORLD
Grid connection project planning
1.
2.
3.
4.

Planning information phase
Detailed design phase
Construction phase
Compliance and commissioning stage

Identifying a
suitable site

Permission and costs to connect
Budgetary/indicative quotation from DNO
INNOVATIVE THINKING
FOR THE REAL WORLD
New NHS build Ashton
Case study

Non contestable & contestable Grid costs

INNOVATIVE THINKING
FOR THE REAL WORLD
The I.C.P?
• Independent connection provider
• Lloyds registered to carry out contestable grid
works that will be finally adopted by the DNO
• May be able to carry out design work for you
project and project manage on you behalf
• Will apply for a Point of connection form the
DNO and the non contestable costs
INNOVATIVE THINKING
FOR THE REAL WORLD
Grid connection options
Grid connections are split into two
• Non contestable work – the work only the DNO or
his registered contractor can do
• Contestable work – The work that is open to
competition that any Lloyds registered I.C.P can
do, on completion will be adopted by the DNO
Choice
• Use the DNO for all the Grid connection work and an experienced
Grid engineer for the testing and compliance stages of the project
• Use an I.C.P to complete the contestable work and project manage
all the other requirements
INNOVATIVE THINKING
FOR THE REAL WORLD
Non contestable & contestable works
DNO existing 11kV cable
Contestable work

Non-contestable Work

New DNO HV S/S

Final HV joint
Network study and all
design approvals

New HV cable

Customer s HV
cable
To next substation

This one cable connection to the existing grid is called a INNOVATIVE THINKING
TEE or
FOR THE REAL WORLD
unsecured connection
Non-contestable & contestable works
DNO existing 11kV cable
Contestable work

Non-contestable Work

New DNO HV S/S

Final HV joints
Network study and all
design approvals

Customer’s HV cable
This cable connection to the existing grid is called a LOOPED or secured
firm connection
INNOVATIVE THINKING
FOR THE REAL WORLD
Larger single turbine –225kW
The project:
• In pre-planning stages
• 1 x ASCA 225kW turbine
• Hub height 32m / Blade diameter 28m / Tip height 46m
The Benefits:
• F.I.T. payment
The grid connection process:
• Rural location
• Grid connection point - 450m from preferred turbine
location
• In file - Grid connection budgetary quote - £168K
• Final – Grid connection £ 168,000
• Update – delayed due to planning consents
INNOVATIVE THINKING
FOR THE REAL WORLD
Site layout
Incoming 6,600 volt overhead Grid
line

Brown cables are low voltage

Proposed site of turbine

Incoming 6,600 volt overhead
Grid line
INNOVATIVE THINKING
FOR THE REAL WORLD
Extract from
Electricity Northwest’s
budgetary quote
This shows the proposed
connection plan
• The Map shows the
proposed route to connect
the turbine to the grid
• A new substation and
cables would be required

• Cables would follow the
road rather than cross
agricultural fields

INNOVATIVE THINKING
FOR THE REAL WORLD
2.25 MW turbine project
The project:

3 x 750 kW turbines

•

3 Turbines on farm near Chorley

•

Total project installation costs - approx £2.5M

The Benefits:
•

F.I.T / R.O.C payment

The grid connection process:
•

Rural location

•

Grid connection point 1.2km from site

•

Need to access 3rd party land to reach grid connection
point

•

Grid connection cost £227k (approx 10% of installation
cost)

•

DNO non–contestable - £26,000

•

DNO–contestable - £201,000

•

I.C.P- contestable - £119,000, excludes legal costs

•

Delays caused by ongoing negotiations with 3rd party
land owner land access payment

INNOVATIVE THINKING
FOR THE REAL WORLD
Connection options
Difficult negotiations with 3rd party
landowner
Project considered connecting to the
passing 33,000 volts system .

DNO non contestable estimate £345,864
DNO contestable estimate £387,803

INNOVATIVE THINKING
FOR THE REAL WORLD
Greenacres Farm 300kW AD plant
Greenacres Farm 300kW AD plant
18 months of planning and investment commitment
Agricultural consultant involved
Option no 1 for 300 kW of AD generation

• Initial budgetary Grid quote of £100,000
• non-contestable cost of £10,000
Option no 2 for 600kW of AD generation
• The connection cost remained the same but the extra upgrade
works on the system to allow more generation were estimated
at £251,000
INNOVATIVE THINKING
FOR THE REAL WORLD
The basic Grid connection issues
for each Project
• Is there a Grid connection at a cost that the
project can afford ?
What other issues do I have to consider?
• Site location of new DNO Substation
• Permission & cost to lay new DNO cables on 3rd
party land
• Grid connection options
INNOVATIVE THINKING
FOR THE REAL WORLD
Connections have commercial risk
• Actual connection capacity can only be secured
when accepting a firm offer, and is subject to terms
and conditions
• Outstanding offers can become interactive
• Grid systems are dynamic
• In some areas larger projects >5MW may be in a
queue or waiting for connection room on the grid to
become available.
INNOVATIVE THINKING
FOR THE REAL WORLD
Approximate Connection delivery
times
•
•
•
•
•

415 volt ( 3-phase)
2 months
11 kV
6 months
33 kV
>12 months
66kV/132kV
> 18 months
132kV upwards & NGT level

Legal works can take 3 to 12 months to complete
INNOVATIVE THINKING
FOR THE REAL WORLD
Part 4: Additional grid
connection considerations
1.
2.
3.
4.
5.
6.

I.D.N.O & mpan no’s
Power factor
3 phase power calculation
Fault levels
Likely grid connection costs
G59 testing & Commissioning

INNOVATIVE THINKING
FOR THE REAL WORLD
MPAN numbers
Identifying the DNO
• MPAN (Meter Point Administration
Number)
• This is found on the electricity bill
issued by the supplier
• The full MPAN is 21 digits and should
be printed in the format as shown on a
recent electricity bill

www.energylinx.co.uk/mpan.htm
INNOVATIVE THINKING
FOR THE REAL WORLD
The Distribution Network Owner

•Establishes and maintains Electricity Distribution connections to its customers –
first for load, and more recently generation
• Does not make, own, buy or sell electricity, though other parts of the groups may

INNOVATIVE THINKING
FOR THE REAL WORLD
From electricity board to DNO’s
Takeovers, mergers and acquisitions
MPAN ID Previous name
11
14
12
19
10
13
18
16
17
20
21
22
15
23

East Midlands Electricity
Midlands Electricity
London Electricity
The SEE board
Eastern Electricity
Manweb
Scottish Power
Norweb (UU)
Scottish Hydro Electric
Southern Electric
South Wales Electricity
South western Electricity
Northern Electricity
Yorkshire Electricity

Recent name
Central Networks E.ON

EDF now UK Power Networks

Scottish Power SP Energy Networks
Electricity North West
Scottish & Southern Energy now
SSE Power Distribution
Western Power Distribution
CE Electric (YEDL NEDL) now
Northern Power Grid

INNOVATIVE THINKING
FOR THE REAL WORLD
IDNO Independent Distribution
Network Operators
They own cables and substations inside of a DNO’s geological area
ID
24
25
26

Name
Envoy
ESP
Energetics

27
28

GTC
EDF IDNO

Licensee
Independent Power Networks
ESP Electricity
Global Utilities Connections
(electric)Ltd
The Electricity Network Company Ltd.
UK Power Network (IDNO) Ltd

INNOVATIVE THINKING
FOR THE REAL WORLD
What is power factor and kVar?
Customers peak
consumption 400kW
= 557 Line amps

Reactive energy
300 kVar
= 443 Line amps

Pf angle

Pf = 400/500
= 0.8 = 36 degrees
Increase the Pf to 0.9
= 25 degrees
500kVa reduces to
444kVa and line
current reduces to
640 amps

The grid supplies the customer THINKING
INNOVATIVE
with 500 kVa = 721 line amps REAL WORLD
FOR THE
Three phase
FORMULA

TRIANGLE

Power = volts x 1.732 x amps

Amps

=

power
volts line x 1.732

POWER

Line
VOLTS

1.732

x

AMPS

INNOVATIVE THINKING
FOR THE REAL WORLD
Three phase calculations
• Calculating kW power for small three-phase supplies
• Power = line Voltage x line amps x PF x 1.732

(for small supplies assume PF as 1)
• (K)Watts = Line volts x Line amps x 1.732

• Line (phase) Amps =

Power (K)Watts
line volts x 1.732
INNOVATIVE THINKING
FOR THE REAL WORLD
Calculating phase line current for
three-phase project
• PV array is rated at 11.4 kWp (11,400 watts)
• What is the maximum line current output in amps if the line voltage
is: (assume PF as 1)
• Line voltage is 415 volts
• Line voltage is 400 volts
• Formula is amps = power kW / line voltage x 1.732

Answer
• 15.86 amps line current
• 16.45 amps line current
INNOVATIVE THINKING
FOR THE REAL WORLD
Fault level current
This is the maximum fault current that a generator can
deliver to a short circuit fault
• For inverter driven generation
The maximum fault current = output +5 %
• For rotating generators
This will require power engineering expertise with
technical details of the rotating generator and
calculations
INNOVATIVE THINKING
FOR THE REAL WORLD
Likely grid connection costs
•

Turn the voltage down at PMT

= £2,500

•

Isolation and safe working on O/H lines

= £ 2000

•

Turn the voltage down at S/S

= £1,500

•

HV DNO Grid network Study from

= £2,000

•

New PMT and transformer

= (£10,000 to £32,000)

•

New ground mounted HV S/S

= £40,000

•

New ground S/S with transformer

= £65,000

•

HV cable laying

= £100 to £200 / m

•

LV cable laying

= £80 to £150 / m

•

New O/H lines and poles

= £80 - £120 / m
INNOVATIVE THINKING
FOR THE REAL WORLD
Testing and commissioning
& compliance
• Refer to Technical notes supplied
• G59 Testing & commissioning and compliance
with DNO’s requirements
Outsource to a competent experienced engineer

INNOVATIVE THINKING
FOR THE REAL WORLD
Break time
INNOVATIVE THINKING
FOR THE REAL WORLD
Exercise 2:
Completing the ENA form for an example project
• Complete and submit to
ENW using the ENW form
for a 150 kWp PV solar
project.
• The customers supply is 946
kW with a power factor of
0.95
• The estimated weekend
base load is 145 kW
• Firm quotation is required
INNOVATIVE THINKING
FOR THE REAL WORLD
Generator customer grid assessment
Required on the standard EA form
Questions A2 A3 A4
Diagram no 1 (A2)
The Grid supply
Import Power Kw

Customers
intake load
In KW

Power
Station

Customers
SITE

Diagram no 3 (A4)
Grid supply
meter & fuses

Import Power zero Kw

Customers
intake load
In kW

The Grid Supply

Export power in Kw
Power
Station

Customers
SITE

Diagram no 2 (A3)
Import Power Kw

Customers
intake load
In kW

The Grid supply

Power
Station

Customer
generator
Customers
SITE

Grid supply
meter & fuses

Customer
generator

INNOVATIVE THINKING
FOR THE REAL WORLD

Grid supply
meter & fuses
Group Exercise
Repeat using the ENA form
• Complete and submit to
ENW a ENA form for 150
kWp PV solar project.
• The customers supply is 946
kW with a power factor of
0.95
• Estimate the weekend base
load
• Firm quotation is required

INNOVATIVE THINKING
FOR THE REAL WORLD
INNOVATIVE THINKING
FOR THE REAL WORLD

84
Advanced
Grid Connection Workshop
16th July 2013

Summary and surgery
Geoff Owen,
George Hall

S

INNOVATIVE THINKING
FOR THE REAL WORLD

Contenu connexe

Tendances

4 cired2013 distributed energy resources
4   cired2013 distributed energy resources4   cired2013 distributed energy resources
4 cired2013 distributed energy resources
Dutch Power
 

Tendances (20)

Vanadium Redox Flow Battery
Vanadium Redox Flow Battery Vanadium Redox Flow Battery
Vanadium Redox Flow Battery
 
4 cired2013 distributed energy resources
4   cired2013 distributed energy resources4   cired2013 distributed energy resources
4 cired2013 distributed energy resources
 
Paul Fleming a Coenercat, sessió de Girona (28.11.2013)
Paul Fleming a Coenercat, sessió de Girona (28.11.2013)Paul Fleming a Coenercat, sessió de Girona (28.11.2013)
Paul Fleming a Coenercat, sessió de Girona (28.11.2013)
 
Lessons learned from project implementation and tips for working with your lo...
Lessons learned from project implementation and tips for working with your lo...Lessons learned from project implementation and tips for working with your lo...
Lessons learned from project implementation and tips for working with your lo...
 
Economics of Solar Park
Economics of Solar ParkEconomics of Solar Park
Economics of Solar Park
 
Energy Efficiency and Sustainability: Safaricom Perspective
Energy Efficiency and Sustainability: Safaricom PerspectiveEnergy Efficiency and Sustainability: Safaricom Perspective
Energy Efficiency and Sustainability: Safaricom Perspective
 
Energy, Energy Efficiency &amp; Sustainability
Energy, Energy Efficiency &amp; SustainabilityEnergy, Energy Efficiency &amp; Sustainability
Energy, Energy Efficiency &amp; Sustainability
 
Low cost DC_Nanogrids_2015
Low cost DC_Nanogrids_2015Low cost DC_Nanogrids_2015
Low cost DC_Nanogrids_2015
 
Redox flow battery - Power Sector
Redox flow battery - Power SectorRedox flow battery - Power Sector
Redox flow battery - Power Sector
 
KEMA - Frits Verheij
KEMA - Frits VerheijKEMA - Frits Verheij
KEMA - Frits Verheij
 
Analysis of Community Microgrids: The path to resilient and sustainable commu...
Analysis of Community Microgrids: The path to resilient and sustainable commu...Analysis of Community Microgrids: The path to resilient and sustainable commu...
Analysis of Community Microgrids: The path to resilient and sustainable commu...
 
Photovoltaics
PhotovoltaicsPhotovoltaics
Photovoltaics
 
Learn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC ConductorLearn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC Conductor
 
Webinaire : Comment optimiser la performance, la maintenance et la durée de v...
Webinaire : Comment optimiser la performance, la maintenance et la durée de v...Webinaire : Comment optimiser la performance, la maintenance et la durée de v...
Webinaire : Comment optimiser la performance, la maintenance et la durée de v...
 
UniEnergy Technologies Vanadium Flow Battery-Energy Storage
UniEnergy Technologies Vanadium Flow Battery-Energy StorageUniEnergy Technologies Vanadium Flow Battery-Energy Storage
UniEnergy Technologies Vanadium Flow Battery-Energy Storage
 
Webinar - Meet the Belgian players : innovation & knowhow for the implementat...
Webinar - Meet the Belgian players : innovation & knowhow for the implementat...Webinar - Meet the Belgian players : innovation & knowhow for the implementat...
Webinar - Meet the Belgian players : innovation & knowhow for the implementat...
 
Community Microgrids: The Path to Resilience and Sustainability (5/10/18)
Community Microgrids: The Path to Resilience and Sustainability (5/10/18)Community Microgrids: The Path to Resilience and Sustainability (5/10/18)
Community Microgrids: The Path to Resilience and Sustainability (5/10/18)
 
Tata power delhi distribution's solar journey
Tata power delhi distribution's solar journeyTata power delhi distribution's solar journey
Tata power delhi distribution's solar journey
 
European Utility Week (2/2) | Paris - 12 au 14 novembre 2019
European Utility Week (2/2) | Paris - 12 au 14 novembre 2019European Utility Week (2/2) | Paris - 12 au 14 novembre 2019
European Utility Week (2/2) | Paris - 12 au 14 novembre 2019
 
BIPV Solar - Transparent - Rooftop - Generate Power
BIPV Solar - Transparent - Rooftop - Generate PowerBIPV Solar - Transparent - Rooftop - Generate Power
BIPV Solar - Transparent - Rooftop - Generate Power
 

Similaire à Advanced grid connection workshop 16 07 13 presentation

Singapore Smart Grid From Concept to Reality Slides.pdf
Singapore Smart Grid From Concept to Reality Slides.pdfSingapore Smart Grid From Concept to Reality Slides.pdf
Singapore Smart Grid From Concept to Reality Slides.pdf
PohLianLam1
 
Show and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdfShow and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdf
SIFOfgem
 
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
iQHub
 
Broadband tech 2005
Broadband tech 2005Broadband tech 2005
Broadband tech 2005
eaiti
 

Similaire à Advanced grid connection workshop 16 07 13 presentation (20)

Singapore Smart Grid From Concept to Reality Slides.pdf
Singapore Smart Grid From Concept to Reality Slides.pdfSingapore Smart Grid From Concept to Reality Slides.pdf
Singapore Smart Grid From Concept to Reality Slides.pdf
 
Advance Power Electronic Converters for Renewable Energy Systems
Advance Power Electronic Converters for Renewable Energy SystemsAdvance Power Electronic Converters for Renewable Energy Systems
Advance Power Electronic Converters for Renewable Energy Systems
 
Show and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdfShow and Tell - Renewable Energy integration and Circular Economy.pdf
Show and Tell - Renewable Energy integration and Circular Economy.pdf
 
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
UNLOCKING NETWORK CAPACITY FOR INCREASING NUMBERS OF EVS ON DISTRIBUTION NETW...
 
Morelia workshop presentation william ross
Morelia workshop presentation william rossMorelia workshop presentation william ross
Morelia workshop presentation william ross
 
Sgcp13laguna
Sgcp13lagunaSgcp13laguna
Sgcp13laguna
 
Opportunities for Power Electronics in Renewable Electricity Generation 2016 ...
Opportunities for Power Electronics in Renewable Electricity Generation 2016 ...Opportunities for Power Electronics in Renewable Electricity Generation 2016 ...
Opportunities for Power Electronics in Renewable Electricity Generation 2016 ...
 
Design drivers for monitoring critical infrastructure
Design drivers for monitoring critical infrastructureDesign drivers for monitoring critical infrastructure
Design drivers for monitoring critical infrastructure
 
1.1 integrating renewables srm
1.1 integrating renewables   srm1.1 integrating renewables   srm
1.1 integrating renewables srm
 
Sckipio and Actiontec Present at Broadband Multimedia Marketers Association o...
Sckipio and Actiontec Present at Broadband Multimedia Marketers Association o...Sckipio and Actiontec Present at Broadband Multimedia Marketers Association o...
Sckipio and Actiontec Present at Broadband Multimedia Marketers Association o...
 
Broadband tech 2005
Broadband tech 2005Broadband tech 2005
Broadband tech 2005
 
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
 
Oliver Spink
Oliver SpinkOliver Spink
Oliver Spink
 
wireless charging of an electrical vechicle 2
wireless charging of an electrical vechicle 2wireless charging of an electrical vechicle 2
wireless charging of an electrical vechicle 2
 
Panduit EMEA SI Webinar 4
Panduit EMEA SI Webinar 4Panduit EMEA SI Webinar 4
Panduit EMEA SI Webinar 4
 
Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier
 
Solar pv plant and india
Solar pv plant and indiaSolar pv plant and india
Solar pv plant and india
 
Siemon Carrie Higbie
Siemon Carrie HigbieSiemon Carrie Higbie
Siemon Carrie Higbie
 
Low power in vlsi with upf basics part 1
Low power in vlsi with upf basics part 1Low power in vlsi with upf basics part 1
Low power in vlsi with upf basics part 1
 
PON design considerations for FTTH FTTx
PON design considerations for FTTH FTTxPON design considerations for FTTH FTTx
PON design considerations for FTTH FTTx
 

Dernier

Dernier (20)

Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Developing An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilDeveloping An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of Brazil
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 

Advanced grid connection workshop 16 07 13 presentation

  • 1. Advanced Grid Connection Workshop The Innovation Centre, Sci-Tech Daresbury, 16th July 2013 Welcome and Introduction George Hall, Project Manager The Wind-Tech Project INNOVATIVE THINKING FOR THE REAL WORLD
  • 2. Programme 9.00 Welcome & introduction Dr. George Hall, Wind-Tech Project, UCLan 9.10 9.20 9.50 10.45 11.00 12.00 12.30 Introduction to the workshop Part 1: Variation in grid voltage and the need for DNO studies Part 2: The rural grid in detail: Schematic diagrams for most rural connections Morning Refreshments Exercise 1: Completing a site survey for an example PV, hydro or wind project Part 3: Larger grid connection projects and case studies Geoff Owen, Grid Connections Lunch 1.30 2.00 2.45 3.00 Part 3: Larger grid connection projects and case studies (continued) Part 4: Additional grid connection Afternoon refreshments Exercise 2: Completing the ENA application form for an example project 4.30 Summary and surgery: one-to-one advice Geoff Owen Geoff Owen, Dr. George Hall INNOVATIVE THINKING FOR THE REAL WORLD
  • 3. Today’s workshop • Following the energy and grid connection basics workshop, today we will investigate in more detail the complexity of connecting to the grid; • A more interactive workshop, with morning and afternoon group exercises, with support from the Wind-Tech team; • Follow-on support from the Wind-Tech team for companies interested in wind turbine technologies, or other forms of renewable technology, available after today’s workshop. INNOVATIVE THINKING FOR THE REAL WORLD
  • 4. Today’s workshop Please note: The information provided today is done so in an advisory capacity only. The supplier shall not incur any liability for any action or omission arising out of any reliance being placed on this information by any organisation or other person. Any organisation or person in receipt of this information should take their own legal, financial and other relevant professional advice when considering what action (if any) to take in respect of any grid connection, renewable strategy, initiative, proposal, or other involvement with any renewable technology, before placing any reliance on anything contained herein. INNOVATIVE THINKING FOR THE REAL WORLD
  • 5. Advanced Grid Connection Workshop 16th July 2013 Geoff Owen, Grid Connections INNOVATIVE THINKING FOR THE REAL WORLD
  • 6. Level 1 review • Essential power terminology & application for renewable generation projects • G83 is under 16 amp per phase • G59 is over 16 amps per phase • One G83 project is allowed per customer • Once a G83 project is fitted to increase or add another project will require a G59 application & permission from the DNO • The function of the DNO grid and connections • Application and upstanding grid connectivity for renewable energy projects INNOVATIVE THINKING FOR THE REAL WORLD
  • 7. LEVEL 2 Workshop Content Part 1: Part 2: Exercise 1: Part 3: Part 4: Exercise 2: Variation in grid voltage and the reason for DNO studies The rural grid in detail Completing a site survey Larger grid connection projects and case studies Additional grid connection considerations Completing the ENA application form for an example project INNOVATIVE THINKING FOR THE REAL WORLD
  • 8. Renewable power generation Essential considerations for projects • If there is no consumer demand then there is limited justification to install a generation project • The Availability of FIT support will not be there for long • The installation of renewable power technologies enables consumers to take control of their energy costs and limit their exposure to future price increases. • De-centralised power generation can reduce transmission grid losses. INNOVATIVE THINKING FOR THE REAL WORLD
  • 9. Part 1: Variation in grid voltage and the need for DNO studies • For a generator to work and stay connected it must operate within design parameters • G83 upper cut of voltage stage 1 (@51.5HZ) 262.2 volts in 90 seconds • G59 upper cut of voltage stage 1 (@51.5HZ) 253 volts in 90 seconds • The grid supply transformer is set at 250 volts at the source, this allows a head room of only 3 volts • In periods of low customer load the grid volts are high through out the grid system, generation may increase the grid voltage resulting in invertors and protection relays operating with loss of generation, and Grid voltage pushed beyond statutory levels INNOVATIVE THINKING FOR THE REAL WORLD
  • 10. Why is the Grid connection process so complicated? • Grid systems were never designed for multiple smaller generation connections, designed for power flow in one direction • DNO’s have to guarantee to the customers the quality of supply and availability 24/7 • Increasing number of projects could result in a unstable Grid system, with undermining of network supply security INNOVATIVE THINKING FOR THE REAL WORLD
  • 11. DNO Responsibilities These are the statutory obligations under the terms of their licence • • • • • Secure operation and development of the network; Safe & reliable operation of the network; Ensure fair and equal access to the network; Least cost options for connection; Lifetime ownership of network not just your connection. INNOVATIVE THINKING FOR THE REAL WORLD
  • 12. Grid voltage variation • The voltage level in the UK was standardised with the EU • The DNO is responsible for the supply characteristics and is directly responsible for guaranteeing the supply quality to all customers • The supply characteristics are declared as 400/230 volts (+10% to -6%), 50Hz damage to electrical equipment will result if the if the supply voltage goes outside of the stated range • Customer switches on large motor • G83 or G59 nuisance tripping Low customer load Maximum 253 volts Normal grid 240 volts high customer load Minimum 216 volts Grid transformer output set at 250/433 volts INNOVATIVE THINKING FOR THE REAL WORLD
  • 13. DNO’s EXISTING ELECTRICITY NETWORK (LV grid) Voltage at source set 250/433 volts Small 3 phase Commercial supply Supplying Sub station Small single phase cable to house Large 3 phase Commercial supply Cable joints in highway 3 C 300 mm W cable in pathway or road DNO designs infrastructure connections to guarantee the supply quality INNOVATIVE THINKING FOR THE REAL WORLD
  • 14. Voltage variation data with customer load for proposed G83 generation Peak 254 volts 252 volts 244 volts Day 1 Day 2 Day 3 Switching on of motor load INNOVATIVE THINKING FOR THE REAL WORLD
  • 15. Hz Frequency variation data with customer load for proposed G83 generation 50.3 50.18. 50.06 49.94 49.82 49.7 Day 1 Day 2 Day 3 INNOVATIVE THINKING FOR THE REAL WORLD
  • 16. Part 2: The rural grid in detail Introduction to the complexity and schematic view of most rural connection arrangements for projects < 50kW Warning Excludes non-standard DNO supply systems that are awaiting a system upgrade Will the grid connection cost undermine the F.I.T/energy reduction investment return? INNOVATIVE THINKING FOR THE REAL WORLD
  • 17. Essential Information Supplied by sustainable Energy Eystems Installer of over 300 small WT’s in the last 5 years What you must have • Good healthy DNO supply • Single phase or 3 phase INNOVATIVE THINKING FOR THE REAL WORLD
  • 18. Examples of poor connection capability • More than one property run from the transformer • End of line connection • Long distance to three phase line • Low on site usage • Old supply transformer • High voltage tapings on the supply transformer INNOVATIVE THINKING FOR THE REAL WORLD
  • 19. Rural supplies • 70 % of rural areas have a single phase supply system • A technical assessment must be made before any applications are submitted to the DNO • A project must initially have view of the likely GRID connectivity and costs • Submit a budgetary request to the DNO for indicative costs INNOVATIVE THINKING FOR THE REAL WORLD
  • 20. Rural overhead line supplies & grid connectivity HV 3 phase supply • This supply arrangement provides single phase to the customer • MCS generator project connectivity is 3.68kW Transformer HV to LV single phase • Cost to upgrade for 3 phase if pole is suitable (£6k to £15k) Single phase LV supply to a farm INNOVATIVE THINKING FOR THE REAL WORLD
  • 21. 70% of rural overhead line supplies are single phase only • This supply arrangement can only provide single phase to the customer HV 2 phase supply • MCS generator project connectivity is 3.68kW • Cost to upgrade to 3 phase, with a new pole transformer = £18k DNO HV/LV transformer Substation name and pole number Single phase supply to customer • New lines and poles = £80 = £120/m INNOVATIVE THINKING FOR THE REAL WORLD
  • 22. Connectivity for single phase rural grid supplies with one customer Proposed 3.68 kW single phase WT Small LV grid cables Single phase LV grid cable G 83 generator 1 Customer • Installed under G83 • May require later DNO grid upgrade High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 23. Connectivity for single phase rural grid supplies to one customer Proposed >11 kW < 50 kW single phase WT Single phase LV grid Cable Small LV grid cables G 59 generator • G59 application to DNO • Installed under G59 • DNO grid upgrade & costs to connect Customer no 1 High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 24. Connectivity for single phase rural grid supplies with more than one customer Customer no. 3 Single phase LV grid cables Small LV 3 phase grid cable G 83 generator Customer no. 2 Customer no. 1 • Single phase installed under G83 maximum of 3.68 kW • May require later DNO grid upgrade High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 25. Connectivity for single phase rural grid supplies with more than one customer Proposed 5 kW WT limited to ( 3.68 kW output) Customer no 3 Small LV single phase grid cables G 59 generator Customer no 2 Customer no 1 • G59 application to DNO with technical details • With DNO’s agreement installed under G83 maximum output 3.68 kW • May attract DNO grid upgrade costs High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 26. Rural Case Study Grid upgrade costs for exceeding 16 amps • Evance 9000 installed in Rossendale • Planning submitted and passed • Application submitted to DNO for connection of 5 kw • Grid costs excessive £ 20,000 • Technical agreement with DNO to cap turbine output to 3.6kW – nil cost INNOVATIVE THINKING FOR THE REAL WORLD
  • 27. Connectivity for single phase rural grid supplies Proposed 10 kW to 50 kW single phase WT Customer no 3 Single phase LV grid cables G 59 generator Customer no 2 • G59 application to DNO • installed under G 59 • DNO grid upgrade & costs to connect Customer no 1 High voltage lines New S/S for customer no 2 INNOVATIVE THINKING FOR THE REAL WORLD
  • 28. Connectivity for split phase rural grid supplies with more than one customer Proposed 3.68 kW single phase WT Customer no 2 Small LV grid cables Split ( single) phase LV grid cable G 83 generator Customer no 1 Has 2 x 1 phase supplies High voltage lines • 1x3.68 kW project installed under G83 • A second project will require G83 stage 2 application to DNO INNOVATIVE THINKING FOR THE REAL WORLD
  • 29. Single (split) or three phase ? • In a rural area if there is any doubt • Competent electrician to carry out voltage test a the source of the supply on the customers side • Contact the DNO INNOVATIVE THINKING FOR THE REAL WORLD
  • 30. Overhead supply with three phase transformer HV 3 phase supply Overhead LV 3 phase supply to customer • Maximum rated capacity 50KVA (approx 70 amps per phase) • MCS generator project connectivity is 11kW • Exceeding 11 kW will require connection approval from the DNO Transformer HV to LV 3 phase INNOVATIVE THINKING FOR THE REAL WORLD
  • 31. Connectivity for 3 phase rural grid supplies to one customer Proposed 11 kW 3phase WT 3 phase LV grid cable G 83 generator Installed under G83 May require later DNO grid upgrade Customer no 1 High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 32. Connectivity for 3 phase rural grid supplies to one customer Proposed >11 kW <50kW 3phase WT 3 phase LV grid cable G 59 generator • G59 Application to DNO • Installed under G 59 • Grid upgrade & costs to connect Customer no 1 High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 33. Connectivity for single/3 phase rural grid supplies with more than one customer Proposed >11 kW < 50 kW 3 phase WT Customer no 3 3 phase LV grid cable G 59 generator Customer no 2 • G59 Application to DNO • Installed under G 59 • Grid upgrade to connect Customer no 1 New S/S for customer no 2 High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 34. Connectivity for single/3 phase rural grid supplies with more than one customer Proposed 3.68 kW single phase WT Customer no 3 Small LV grid cables 3 phase LV grid cable G 83 generator Customer no 2 • Installed under G83 • May require later DNO grid upgrade Customer no 1 High voltage lines INNOVATIVE THINKING FOR THE REAL WORLD
  • 35. Connectivity for single/3 phase rural grid supplies with more than one customer Proposed 11 kW 3 phase WT Customer no 3 3 phase LV grid cable Single phase grid service cable to customer G 83 generator Customer no 2 Customer no 1 High voltage lines • Request to DNO to upgrade supply customer supply from 1 phase to 3 phase ( from £1,500 to £ 4,500) • Installed under G83 • May require later DNO grid upgrade to transformer INNOVATIVE THINKING FOR THE REAL WORLD
  • 36. Connectivity for single/3 phase rural grid supplies with more than one customer Proposed >11 kW < 50 kW 3 phase WT Customer no 3 3 phase LV grid cable G 59 generator Customer no 2 Customer no 1 High voltage lines New S/S for customer no 2 • G59 Application to DNO • Installed under G 59 • Grid upgrade to connect INNOVATIVE THINKING FOR THE REAL WORLD
  • 37. Larger rural supplies The H pole Maximum size of grid transformer 200kVA feeding • Dedicated customers •Several costumers in one area • MCS generator project connectivity is 11kW ( or 3.68kW for single phase supplies) •Exceeding 11 kW will require connection approval from the DNO Larger generator projects will require permission from the DNO to connect 240/415 volt LV grid to customers 11KV DNO grid INNOVATIVE THINKING FOR THE REAL WORLD
  • 38. Firm grid connection quotation • Will include: – – – – Connection permission Terms and conditions specific to the project Any connection costs Legal work if required • On acceptance, the project work can commence – You can install the project to the submitted design – You must follow G83 & G59 Compliance stages – You must complete the test and commissioning stages. INNOVATIVE THINKING FOR THE REAL WORLD
  • 39. Case Study Small Hydro G59 connection Small 15kW hydro project in a remote valley • Refer to site map for further information • Large valley with no 3 phase grid supply • A technical solution agreed with the DNO INNOVATIVE THINKING FOR THE REAL WORLD
  • 40. Case Study Rural location: 10kWp School project The Project • Grid supply looks like it is 3 phase • Installation has 3 phase TP/N switch fuse • Sales person secured a 10 kWp PV array contract • PV panels and inverters were installed • Electrician was sent to complete the connection to G83 standards The issue • The electrician discovered that the supply was actually 3 x single phase supplies • The incoming overhead grid lines to the grid distribution transformer only have 2 cables. • There is no 3 phase supply in the area The Solution • They submitted G83/2 application requesting permission to connect multiple projects. INNOVATIVE THINKING FOR THE REAL WORLD
  • 41. Case Study Two incoming HV lines supplying village No 3 phase supply INNOVATIVE THINKING FOR THE REAL WORLD
  • 42. Case Study Two incoming HV lines supplying village No 3 phase supply INNOVATIVE THINKING FOR THE REAL WORLD
  • 43. Do’s • • • • Have a view of what is involved Carry out a detailed site survey Understand the potential connection costs Make the right decisions, at the right time Dont’s • • • • Ignore grid connection Leave it to the last minute Make assumptions Request a firm grid connection offer until you are in a position to accept INNOVATIVE THINKING FOR THE REAL WORLD
  • 45. Exercise 1: Completing a site survey Group exercise with feedback and discussion • You are going to a site, to undertake a survey for a renewable energy project. • Maximum of three groups • List what you think you need to consider when undertaking this site survey… 1. 50kW hydro 3 phase generator 2. 150 kW peak PV solar 3. G83 or G59 WT generation INNOVATIVE THINKING FOR THE REAL WORLD
  • 46. Site Survey 1 Proposed 50kW Hydro project: The Weir INNOVATIVE THINKING FOR THE REAL WORLD
  • 47. Site Survey 2: Burnley College 150 kW peak PV solar Proposed PV 150 kWp project INNOVATIVE THINKING FOR THE REAL WORLD
  • 48. Site Survey 3 Proposed 2 x 11 kW Gaia turbines The project: Green Farm Existing supply INNOVATIVE THINKING FOR THE REAL WORLD
  • 50. Part 3 large power connections Have a view of what is involved INNOVATIVE THINKING FOR THE REAL WORLD
  • 51. The UK Grid layout Provides a network of cables and substations to transport power to customers Domestic and small industrial supplies 240/415 volts Manual connected network Large customers supplies Automatic connected network Area distribution 6.6kV11kV Primary Grid supply into areas 33kV 66kV Bulk supply point to DNO 132 kV Power stations network connected Power Station INNOVATIVE THINKING FOR THE REAL WORLD National grid transmission 400kV
  • 52. Other considerations • Network capacity issues • Connection capacity race • Technical, design for firm grid application, correct choice of generator , thermal limits, voltage limits, reverse power flow, switch gear rating and fault levels, protection arrangements, power quality , earthing stability , • Competent design /experienced consultants INNOVATIVE THINKING FOR THE REAL WORLD
  • 53. Grid connection project planning 1. 2. 3. 4. Planning information phase Detailed design phase Construction phase Compliance and commissioning stage Identifying a suitable site Permission and costs to connect Budgetary/indicative quotation from DNO INNOVATIVE THINKING FOR THE REAL WORLD
  • 54. New NHS build Ashton Case study Non contestable & contestable Grid costs INNOVATIVE THINKING FOR THE REAL WORLD
  • 55. The I.C.P? • Independent connection provider • Lloyds registered to carry out contestable grid works that will be finally adopted by the DNO • May be able to carry out design work for you project and project manage on you behalf • Will apply for a Point of connection form the DNO and the non contestable costs INNOVATIVE THINKING FOR THE REAL WORLD
  • 56. Grid connection options Grid connections are split into two • Non contestable work – the work only the DNO or his registered contractor can do • Contestable work – The work that is open to competition that any Lloyds registered I.C.P can do, on completion will be adopted by the DNO Choice • Use the DNO for all the Grid connection work and an experienced Grid engineer for the testing and compliance stages of the project • Use an I.C.P to complete the contestable work and project manage all the other requirements INNOVATIVE THINKING FOR THE REAL WORLD
  • 57. Non contestable & contestable works DNO existing 11kV cable Contestable work Non-contestable Work New DNO HV S/S Final HV joint Network study and all design approvals New HV cable Customer s HV cable To next substation This one cable connection to the existing grid is called a INNOVATIVE THINKING TEE or FOR THE REAL WORLD unsecured connection
  • 58. Non-contestable & contestable works DNO existing 11kV cable Contestable work Non-contestable Work New DNO HV S/S Final HV joints Network study and all design approvals Customer’s HV cable This cable connection to the existing grid is called a LOOPED or secured firm connection INNOVATIVE THINKING FOR THE REAL WORLD
  • 59. Larger single turbine –225kW The project: • In pre-planning stages • 1 x ASCA 225kW turbine • Hub height 32m / Blade diameter 28m / Tip height 46m The Benefits: • F.I.T. payment The grid connection process: • Rural location • Grid connection point - 450m from preferred turbine location • In file - Grid connection budgetary quote - £168K • Final – Grid connection £ 168,000 • Update – delayed due to planning consents INNOVATIVE THINKING FOR THE REAL WORLD
  • 60. Site layout Incoming 6,600 volt overhead Grid line Brown cables are low voltage Proposed site of turbine Incoming 6,600 volt overhead Grid line INNOVATIVE THINKING FOR THE REAL WORLD
  • 61. Extract from Electricity Northwest’s budgetary quote This shows the proposed connection plan • The Map shows the proposed route to connect the turbine to the grid • A new substation and cables would be required • Cables would follow the road rather than cross agricultural fields INNOVATIVE THINKING FOR THE REAL WORLD
  • 62. 2.25 MW turbine project The project: 3 x 750 kW turbines • 3 Turbines on farm near Chorley • Total project installation costs - approx £2.5M The Benefits: • F.I.T / R.O.C payment The grid connection process: • Rural location • Grid connection point 1.2km from site • Need to access 3rd party land to reach grid connection point • Grid connection cost £227k (approx 10% of installation cost) • DNO non–contestable - £26,000 • DNO–contestable - £201,000 • I.C.P- contestable - £119,000, excludes legal costs • Delays caused by ongoing negotiations with 3rd party land owner land access payment INNOVATIVE THINKING FOR THE REAL WORLD
  • 63. Connection options Difficult negotiations with 3rd party landowner Project considered connecting to the passing 33,000 volts system . DNO non contestable estimate £345,864 DNO contestable estimate £387,803 INNOVATIVE THINKING FOR THE REAL WORLD
  • 64. Greenacres Farm 300kW AD plant Greenacres Farm 300kW AD plant 18 months of planning and investment commitment Agricultural consultant involved Option no 1 for 300 kW of AD generation • Initial budgetary Grid quote of £100,000 • non-contestable cost of £10,000 Option no 2 for 600kW of AD generation • The connection cost remained the same but the extra upgrade works on the system to allow more generation were estimated at £251,000 INNOVATIVE THINKING FOR THE REAL WORLD
  • 65. The basic Grid connection issues for each Project • Is there a Grid connection at a cost that the project can afford ? What other issues do I have to consider? • Site location of new DNO Substation • Permission & cost to lay new DNO cables on 3rd party land • Grid connection options INNOVATIVE THINKING FOR THE REAL WORLD
  • 66. Connections have commercial risk • Actual connection capacity can only be secured when accepting a firm offer, and is subject to terms and conditions • Outstanding offers can become interactive • Grid systems are dynamic • In some areas larger projects >5MW may be in a queue or waiting for connection room on the grid to become available. INNOVATIVE THINKING FOR THE REAL WORLD
  • 67. Approximate Connection delivery times • • • • • 415 volt ( 3-phase) 2 months 11 kV 6 months 33 kV >12 months 66kV/132kV > 18 months 132kV upwards & NGT level Legal works can take 3 to 12 months to complete INNOVATIVE THINKING FOR THE REAL WORLD
  • 68. Part 4: Additional grid connection considerations 1. 2. 3. 4. 5. 6. I.D.N.O & mpan no’s Power factor 3 phase power calculation Fault levels Likely grid connection costs G59 testing & Commissioning INNOVATIVE THINKING FOR THE REAL WORLD
  • 69. MPAN numbers Identifying the DNO • MPAN (Meter Point Administration Number) • This is found on the electricity bill issued by the supplier • The full MPAN is 21 digits and should be printed in the format as shown on a recent electricity bill www.energylinx.co.uk/mpan.htm INNOVATIVE THINKING FOR THE REAL WORLD
  • 70. The Distribution Network Owner •Establishes and maintains Electricity Distribution connections to its customers – first for load, and more recently generation • Does not make, own, buy or sell electricity, though other parts of the groups may INNOVATIVE THINKING FOR THE REAL WORLD
  • 71. From electricity board to DNO’s Takeovers, mergers and acquisitions MPAN ID Previous name 11 14 12 19 10 13 18 16 17 20 21 22 15 23 East Midlands Electricity Midlands Electricity London Electricity The SEE board Eastern Electricity Manweb Scottish Power Norweb (UU) Scottish Hydro Electric Southern Electric South Wales Electricity South western Electricity Northern Electricity Yorkshire Electricity Recent name Central Networks E.ON EDF now UK Power Networks Scottish Power SP Energy Networks Electricity North West Scottish & Southern Energy now SSE Power Distribution Western Power Distribution CE Electric (YEDL NEDL) now Northern Power Grid INNOVATIVE THINKING FOR THE REAL WORLD
  • 72. IDNO Independent Distribution Network Operators They own cables and substations inside of a DNO’s geological area ID 24 25 26 Name Envoy ESP Energetics 27 28 GTC EDF IDNO Licensee Independent Power Networks ESP Electricity Global Utilities Connections (electric)Ltd The Electricity Network Company Ltd. UK Power Network (IDNO) Ltd INNOVATIVE THINKING FOR THE REAL WORLD
  • 73. What is power factor and kVar? Customers peak consumption 400kW = 557 Line amps Reactive energy 300 kVar = 443 Line amps Pf angle Pf = 400/500 = 0.8 = 36 degrees Increase the Pf to 0.9 = 25 degrees 500kVa reduces to 444kVa and line current reduces to 640 amps The grid supplies the customer THINKING INNOVATIVE with 500 kVa = 721 line amps REAL WORLD FOR THE
  • 74. Three phase FORMULA TRIANGLE Power = volts x 1.732 x amps Amps = power volts line x 1.732 POWER Line VOLTS 1.732 x AMPS INNOVATIVE THINKING FOR THE REAL WORLD
  • 75. Three phase calculations • Calculating kW power for small three-phase supplies • Power = line Voltage x line amps x PF x 1.732 (for small supplies assume PF as 1) • (K)Watts = Line volts x Line amps x 1.732 • Line (phase) Amps = Power (K)Watts line volts x 1.732 INNOVATIVE THINKING FOR THE REAL WORLD
  • 76. Calculating phase line current for three-phase project • PV array is rated at 11.4 kWp (11,400 watts) • What is the maximum line current output in amps if the line voltage is: (assume PF as 1) • Line voltage is 415 volts • Line voltage is 400 volts • Formula is amps = power kW / line voltage x 1.732 Answer • 15.86 amps line current • 16.45 amps line current INNOVATIVE THINKING FOR THE REAL WORLD
  • 77. Fault level current This is the maximum fault current that a generator can deliver to a short circuit fault • For inverter driven generation The maximum fault current = output +5 % • For rotating generators This will require power engineering expertise with technical details of the rotating generator and calculations INNOVATIVE THINKING FOR THE REAL WORLD
  • 78. Likely grid connection costs • Turn the voltage down at PMT = £2,500 • Isolation and safe working on O/H lines = £ 2000 • Turn the voltage down at S/S = £1,500 • HV DNO Grid network Study from = £2,000 • New PMT and transformer = (£10,000 to £32,000) • New ground mounted HV S/S = £40,000 • New ground S/S with transformer = £65,000 • HV cable laying = £100 to £200 / m • LV cable laying = £80 to £150 / m • New O/H lines and poles = £80 - £120 / m INNOVATIVE THINKING FOR THE REAL WORLD
  • 79. Testing and commissioning & compliance • Refer to Technical notes supplied • G59 Testing & commissioning and compliance with DNO’s requirements Outsource to a competent experienced engineer INNOVATIVE THINKING FOR THE REAL WORLD
  • 81. Exercise 2: Completing the ENA form for an example project • Complete and submit to ENW using the ENW form for a 150 kWp PV solar project. • The customers supply is 946 kW with a power factor of 0.95 • The estimated weekend base load is 145 kW • Firm quotation is required INNOVATIVE THINKING FOR THE REAL WORLD
  • 82. Generator customer grid assessment Required on the standard EA form Questions A2 A3 A4 Diagram no 1 (A2) The Grid supply Import Power Kw Customers intake load In KW Power Station Customers SITE Diagram no 3 (A4) Grid supply meter & fuses Import Power zero Kw Customers intake load In kW The Grid Supply Export power in Kw Power Station Customers SITE Diagram no 2 (A3) Import Power Kw Customers intake load In kW The Grid supply Power Station Customer generator Customers SITE Grid supply meter & fuses Customer generator INNOVATIVE THINKING FOR THE REAL WORLD Grid supply meter & fuses
  • 83. Group Exercise Repeat using the ENA form • Complete and submit to ENW a ENA form for 150 kWp PV solar project. • The customers supply is 946 kW with a power factor of 0.95 • Estimate the weekend base load • Firm quotation is required INNOVATIVE THINKING FOR THE REAL WORLD
  • 85. Advanced Grid Connection Workshop 16th July 2013 Summary and surgery Geoff Owen, George Hall S INNOVATIVE THINKING FOR THE REAL WORLD