SlideShare une entreprise Scribd logo
1  sur  17
of
Cross Border Facility Project, at
Lork-Kampot, Cambodia
&
COVERED WALKWAY
As of August 12th, 2014
Presented by KLK CGT Co., Ltd
1
2
On overall Cover Walkway
is 60% completed
4 majors works remain:
(1) Steel Frames Top, (one side only)
(2) Roof Tiles,
(3) Decors,
Anyway all materials and labors
are 90% on site. So, it will be
completed at least 95% by 30 Sep
2014.
(4) Issue of Column Lining. The Item is not
in the BOQ. A daywork or contingency for
this item is proposing and need to be
approved ASAP.
* Firstly, Engineer is asked to
issue instruction for carrying
out the works of column lining.
After conducting site reviews, the following conclusion are:
I. With the current resources, try all the best it can achieve:
 Three (3) buildings (1. CCA, 2. Admin, and 3. Electricity
& Pump Room) will be effortfullly completed by 31 Aug
2014. To achieve 98% completion of these 3 Bldgs
works has to be helped to facilitate by Consultant &
Employer (MPWT).
II. However, Contractor’s efforts need to be added such as
materials and labors in order to complete other buildings
& external works by end of September 2014, includes:
 External Works such as Concrete Road Slab, Street
Lightings, Garden & Tree Planting, Water Tank etc… will
be completed by mid September.
 Three (3) buildings: (1. Immigration, 2. Staff
Accommodation and 3. Veterinary & Plant Bldgs) will be
effortfully completed only 95% by 30 September 2014.
3
4
On overall CCA Bldg is 85% completed
(1) External Ceiling & (2) Interior
Lighting , all will be completed
by 31 Aug 2014
(3) Windows and Entrance Doors: it is now
working on the frames, glass to be on site
on 25 Aug 2014
3 majors works remain:
CCA Building, about 85% completed except the following works to
be finished:
1) Exterior ceiling: support structures is 100% completed and all
ceiling materials are already on site; but 1 more team of
exterior ceiling workers need to bee added, because the current
team is working for interior ceiling of SA buildings.
2) Interior Lighting: materials & electricians are not in place. Need
to be mobilized by next Monday 18th of Aug.
3) 4 Restrooms (WC) : works are progressing but only for floor and
wall tile mount; to be completed by 31 Aug 2014, 3 more skill
worker is needed to attached toilets & tub to water tapes. All
materials are on site.
4) Window: works are progressing and will be completed by 24
Aug 2014. Frame & other accessories materials are on site, but
Glass is not yet. Glass need to be mobilized by 20 Aug.
5) Interior & Exterior final layer of painting: works are progressing,
will be completed by 31 Aug.
6) Site Clean up: 5 workers for this works already mobilized on 13
Aug.
5
6
On overall Admin Bldg is 90% completed
4 majors works remain:
(1) Exterior Ceiling,
(2) Interior Lighting,
(3) Glass window & Entrance Door,
(4) Door replacement; anyway
material already on site.
Administration Building, about 90% completed except the following works to be
finished:
1) Replacement of Doors: Old doors was removed and materials already on site;
but workers not in place. Need at least 10 more workers and to be mobilized by
18 Aug.
2) Exterior Ceiling: support structures is 100% completed and all ceiling materials
are already on site; but 1 more team of exterior ceiling workers need to bee
added by 18 Aug.
3) Interior Lighting: materials & workers are not in place. Need to be mobilized by
next Monday 18th of Aug.
4) 8 Restrooms (WC) : works are progressing; will be completed by 24 Aug 2014.
all materials & worker are on site.
5) Main Entrance & Windows: works are progressing and will be completed by 24
Aug 2014. Frame & other accessories materials are on site, but Glass is not yet.
Glass need to be mobilized by 20 Aug.
6) Interior & Exterior final layer of painting: works are progressing, will be
completed by 31 Aug.
7) Roof Varnish Painting: will be completed by 31 Aug 2014, but materials and
worker need to mobilized by 20 Aug.
8) Stair handrail: materials & workers are not in place. Need to be mobilized by
next Monday 18th of Aug, but need to be quick approval by Consultant on the
materials & shop drawing.
9) Site Clean up: 5 workers for this works already mobilized on 13 Aug.
7
Electricity & Pump Room: Building 100% completed,
generator is already on site but haven’t yet moved
into the room and connected with cable. It need to
be tested and moved in and connected by 25 Aug.
8
9
7 majors works remain:
(1) Roof and Decors, (1/4 is
completed),
(2) Exterior & Interior Ceiling,
(3) Interior Lighting,
(4) Air Conditioning,
(5) Glass window & Doors,
(6) Floor Tiles & Stairs;
(7) Exterior and Interior Painting.
On Overall 70% is completed.
To be finished by 30 Sep 2014
Immigration Building, about 70% completed; the following works to be
finished:
1) Roof Top (Tray-So), and Roof tiles: All materials & labors are onsite.
- Roof Top (Tray-So): need 45 days to be completed.
- Roof Tile: ¼ completed, and ¾ will be completed by 15 Sep.
2) Decors (Bottom & Top): Top 80% completed, and Bottom is ¼ completed.
All materials and labor are on site. Need time 20 days.
3) Ceiling (Interior and exterior): Support structure is 100% completed. Ceiling
attachment will be started whenever roof completed. Materials and Labor
are in place. It only take 10 days. So will be completed by 25 Sep.
4) Interior Lighting: materials & workers are not in place. Need to be
mobilized by 20 Sep and immediately start whenever ceiling completed.
5) Restrooms (WC) : 10% completed. It will be completed by 20 Sep since all
materials & worker are on site.
6) Window: works are progressing and will be completed by mid Sep 2014.
Frame & other accessories materials are on site, but Glass is not yet. Glass
need to be mobilized by 20 Sep.
7) Floor tile & stairs: 10% completed. To be completed by 30 Sep since all
materials and workers are on site.
8) Interior & Exterior of painting: works are progressing, will be completed by
30 Sep.
10
11
On Overall 70% is completed.
Anyway all materials and labors
are 90% on site. So, it will be
completed by 30 Sep 2014.
7 majors works remain:
(1) Roof and Decors,
(2) Interior Ceiling,
(3) Interior Lighting,
(4) Air Conditioning,
(5) Glass window & Doors,
(6) Floor Tiles & Stairs;
(7) Exterior and Interior Painting.
Staff Accom Building, about 70% completed; the following works to be
finished:
1) Roof tiles: All materials & labors are onsite.
- Roof Tile: ¼ completed, and ¾ will be completed by 31 Aug.
2) Ceiling (Interior and exterior): Support structure was started on 13 Aug.
Ceiling attachment will be started whenever roof completed. Materials and
Labor are in place. It only take 10 days. So will be completed by 10 Sep.
3) Doors: Doors on ground floor was 90% completed (remaining only 4 for rest
rooms. All materials and labors are on site, so will be completed by mid
September.
4) Interior Lighting: materials & workers are not in place. Need to be mobilized
by 20 Sep and immediately start whenever ceiling completed.
5) Restrooms (WC) : not yet start but it will be completed by 20 Sep since all
materials & worker are on site.
6) Window: works are progressing and will be completed by mid Sep 2014.
Frame & other accessories materials are on site, but Glass is not yet. Glass
need to be mobilized by 20 Sep.
7) Floor tile & stair: 10% completed. To be completed by 30 Sep since all
materials and workers are on site.
8) Interior & Exterior of painting: coating works are progressing, will be
completed by 30 Sep.
12
13
On Overall 50% is completed.
Since the building is small and
all materials and labors are 90%
on site. So, it will be completed
by 30 Sep 2014.
8 majors works remain:
(1) Structure and Brick Works,
(2) Roof and Decors,
(3) Interior Ceiling,
(4) Electrical and mechanical works,
(5) Air Conditioning,
(6) Glass window & Doors,
(7) Floor Tiles & Stairs;
(8) Exterior and Interior Painting.
Veterinary & Plant Building, about 50% completed; the following works to be
finished:
1) Structure and Concrete Work: 90% completed
2) Roof tiles: not yet start, but all materials & labors are onsite; will be
completed by mid September.
2) Ceiling (Interior and exterior): will be started whenever roof completed.
Materials and Labor are in place. It only take 10 days. So will be completed
by 20 Sep.
3) Doors: materials & workers are not in place. Need to be mobilized by 20
Sep
4) Interior Lighting: materials & workers are not in place. Need to be
mobilized by 20 Sep and immediately start whenever ceiling completed.
5) Restrooms (WC) : not yet start but it will be completed by 30 Sep since all
materials & worker are on site.
6) Window: not yet start, but will be completed by end of Sep 2014. Frame &
other accessories materials are on site, but Glass is not yet. Glass need to
be mobilized by 20 Sep.
7) Floor tile: 0% completed. To be completed by 30 Sep since all materials and
workers are on site.
8) Interior & Exterior of painting: not yet start, will be completed by 30 Sep.
14
15
On Overall 50% is completed.
Additional materials and labors are needed and to be on site by 25 Aug
for completion by 30 Sep 2014.
External Works: about 50% completed; the following works to
be finished:
1) Street Lighting: Poles 80% completed. Cable & Lamps are not
connected. Electricians are not in place. Need to be mobilized by
15 Sep.
2) Road Concrete Slab: 30% completed, Materials and Labor need to
be added. 100% of materials to be on site by 25 Aug 2014.
2) Flag Poles: 50% completed. Steel Flag Pole is not on site yet. It need
to be on site by 15 Sep.
3) Garden and Tree Planting: curbs for garden are 90% completed.
Materials and labors Need to be mobilized by 10 Sep.
4) Immigration Control Booths: 70% completed. All materials and
labors are already on site.
5) Gates: 0% completed and not on site.
6) Others: Transformer & Electrical Supply, Fire Fighting System,
Water Tape System,
7) Site Clean up: 5 workers for this works already mobilized on 13
Aug.
16
Contractor need advance financing estimately
about US$500,000 to complete the works by
September 2014.
Relay on IPCs of June & July (estimate about
$700,000 including price adjustment) will not be
enough fund to purchase all materials to the site.
Even if IPCs process today it will take another two
months to get the money (will be by 15 Oct)
THANK YOU!
17

Contenu connexe

Dernier

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 

Dernier (20)

(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 

En vedette

How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
ThinkNow
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

En vedette (20)

2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot2024 State of Marketing Report – by Hubspot
2024 State of Marketing Report – by Hubspot
 
Everything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPTEverything You Need To Know About ChatGPT
Everything You Need To Know About ChatGPT
 
Product Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage EngineeringsProduct Design Trends in 2024 | Teenage Engineerings
Product Design Trends in 2024 | Teenage Engineerings
 
How Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental HealthHow Race, Age and Gender Shape Attitudes Towards Mental Health
How Race, Age and Gender Shape Attitudes Towards Mental Health
 
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdfAI Trends in Creative Operations 2024 by Artwork Flow.pdf
AI Trends in Creative Operations 2024 by Artwork Flow.pdf
 
Skeleton Culture Code
Skeleton Culture CodeSkeleton Culture Code
Skeleton Culture Code
 
PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 

Progress of CBF works, at Lork-Kampot (Cambodia) as of 12 Aug-14.

  • 1. of Cross Border Facility Project, at Lork-Kampot, Cambodia & COVERED WALKWAY As of August 12th, 2014 Presented by KLK CGT Co., Ltd 1
  • 2. 2 On overall Cover Walkway is 60% completed 4 majors works remain: (1) Steel Frames Top, (one side only) (2) Roof Tiles, (3) Decors, Anyway all materials and labors are 90% on site. So, it will be completed at least 95% by 30 Sep 2014. (4) Issue of Column Lining. The Item is not in the BOQ. A daywork or contingency for this item is proposing and need to be approved ASAP. * Firstly, Engineer is asked to issue instruction for carrying out the works of column lining.
  • 3. After conducting site reviews, the following conclusion are: I. With the current resources, try all the best it can achieve:  Three (3) buildings (1. CCA, 2. Admin, and 3. Electricity & Pump Room) will be effortfullly completed by 31 Aug 2014. To achieve 98% completion of these 3 Bldgs works has to be helped to facilitate by Consultant & Employer (MPWT). II. However, Contractor’s efforts need to be added such as materials and labors in order to complete other buildings & external works by end of September 2014, includes:  External Works such as Concrete Road Slab, Street Lightings, Garden & Tree Planting, Water Tank etc… will be completed by mid September.  Three (3) buildings: (1. Immigration, 2. Staff Accommodation and 3. Veterinary & Plant Bldgs) will be effortfully completed only 95% by 30 September 2014. 3
  • 4. 4 On overall CCA Bldg is 85% completed (1) External Ceiling & (2) Interior Lighting , all will be completed by 31 Aug 2014 (3) Windows and Entrance Doors: it is now working on the frames, glass to be on site on 25 Aug 2014 3 majors works remain:
  • 5. CCA Building, about 85% completed except the following works to be finished: 1) Exterior ceiling: support structures is 100% completed and all ceiling materials are already on site; but 1 more team of exterior ceiling workers need to bee added, because the current team is working for interior ceiling of SA buildings. 2) Interior Lighting: materials & electricians are not in place. Need to be mobilized by next Monday 18th of Aug. 3) 4 Restrooms (WC) : works are progressing but only for floor and wall tile mount; to be completed by 31 Aug 2014, 3 more skill worker is needed to attached toilets & tub to water tapes. All materials are on site. 4) Window: works are progressing and will be completed by 24 Aug 2014. Frame & other accessories materials are on site, but Glass is not yet. Glass need to be mobilized by 20 Aug. 5) Interior & Exterior final layer of painting: works are progressing, will be completed by 31 Aug. 6) Site Clean up: 5 workers for this works already mobilized on 13 Aug. 5
  • 6. 6 On overall Admin Bldg is 90% completed 4 majors works remain: (1) Exterior Ceiling, (2) Interior Lighting, (3) Glass window & Entrance Door, (4) Door replacement; anyway material already on site.
  • 7. Administration Building, about 90% completed except the following works to be finished: 1) Replacement of Doors: Old doors was removed and materials already on site; but workers not in place. Need at least 10 more workers and to be mobilized by 18 Aug. 2) Exterior Ceiling: support structures is 100% completed and all ceiling materials are already on site; but 1 more team of exterior ceiling workers need to bee added by 18 Aug. 3) Interior Lighting: materials & workers are not in place. Need to be mobilized by next Monday 18th of Aug. 4) 8 Restrooms (WC) : works are progressing; will be completed by 24 Aug 2014. all materials & worker are on site. 5) Main Entrance & Windows: works are progressing and will be completed by 24 Aug 2014. Frame & other accessories materials are on site, but Glass is not yet. Glass need to be mobilized by 20 Aug. 6) Interior & Exterior final layer of painting: works are progressing, will be completed by 31 Aug. 7) Roof Varnish Painting: will be completed by 31 Aug 2014, but materials and worker need to mobilized by 20 Aug. 8) Stair handrail: materials & workers are not in place. Need to be mobilized by next Monday 18th of Aug, but need to be quick approval by Consultant on the materials & shop drawing. 9) Site Clean up: 5 workers for this works already mobilized on 13 Aug. 7
  • 8. Electricity & Pump Room: Building 100% completed, generator is already on site but haven’t yet moved into the room and connected with cable. It need to be tested and moved in and connected by 25 Aug. 8
  • 9. 9 7 majors works remain: (1) Roof and Decors, (1/4 is completed), (2) Exterior & Interior Ceiling, (3) Interior Lighting, (4) Air Conditioning, (5) Glass window & Doors, (6) Floor Tiles & Stairs; (7) Exterior and Interior Painting. On Overall 70% is completed. To be finished by 30 Sep 2014
  • 10. Immigration Building, about 70% completed; the following works to be finished: 1) Roof Top (Tray-So), and Roof tiles: All materials & labors are onsite. - Roof Top (Tray-So): need 45 days to be completed. - Roof Tile: ¼ completed, and ¾ will be completed by 15 Sep. 2) Decors (Bottom & Top): Top 80% completed, and Bottom is ¼ completed. All materials and labor are on site. Need time 20 days. 3) Ceiling (Interior and exterior): Support structure is 100% completed. Ceiling attachment will be started whenever roof completed. Materials and Labor are in place. It only take 10 days. So will be completed by 25 Sep. 4) Interior Lighting: materials & workers are not in place. Need to be mobilized by 20 Sep and immediately start whenever ceiling completed. 5) Restrooms (WC) : 10% completed. It will be completed by 20 Sep since all materials & worker are on site. 6) Window: works are progressing and will be completed by mid Sep 2014. Frame & other accessories materials are on site, but Glass is not yet. Glass need to be mobilized by 20 Sep. 7) Floor tile & stairs: 10% completed. To be completed by 30 Sep since all materials and workers are on site. 8) Interior & Exterior of painting: works are progressing, will be completed by 30 Sep. 10
  • 11. 11 On Overall 70% is completed. Anyway all materials and labors are 90% on site. So, it will be completed by 30 Sep 2014. 7 majors works remain: (1) Roof and Decors, (2) Interior Ceiling, (3) Interior Lighting, (4) Air Conditioning, (5) Glass window & Doors, (6) Floor Tiles & Stairs; (7) Exterior and Interior Painting.
  • 12. Staff Accom Building, about 70% completed; the following works to be finished: 1) Roof tiles: All materials & labors are onsite. - Roof Tile: ¼ completed, and ¾ will be completed by 31 Aug. 2) Ceiling (Interior and exterior): Support structure was started on 13 Aug. Ceiling attachment will be started whenever roof completed. Materials and Labor are in place. It only take 10 days. So will be completed by 10 Sep. 3) Doors: Doors on ground floor was 90% completed (remaining only 4 for rest rooms. All materials and labors are on site, so will be completed by mid September. 4) Interior Lighting: materials & workers are not in place. Need to be mobilized by 20 Sep and immediately start whenever ceiling completed. 5) Restrooms (WC) : not yet start but it will be completed by 20 Sep since all materials & worker are on site. 6) Window: works are progressing and will be completed by mid Sep 2014. Frame & other accessories materials are on site, but Glass is not yet. Glass need to be mobilized by 20 Sep. 7) Floor tile & stair: 10% completed. To be completed by 30 Sep since all materials and workers are on site. 8) Interior & Exterior of painting: coating works are progressing, will be completed by 30 Sep. 12
  • 13. 13 On Overall 50% is completed. Since the building is small and all materials and labors are 90% on site. So, it will be completed by 30 Sep 2014. 8 majors works remain: (1) Structure and Brick Works, (2) Roof and Decors, (3) Interior Ceiling, (4) Electrical and mechanical works, (5) Air Conditioning, (6) Glass window & Doors, (7) Floor Tiles & Stairs; (8) Exterior and Interior Painting.
  • 14. Veterinary & Plant Building, about 50% completed; the following works to be finished: 1) Structure and Concrete Work: 90% completed 2) Roof tiles: not yet start, but all materials & labors are onsite; will be completed by mid September. 2) Ceiling (Interior and exterior): will be started whenever roof completed. Materials and Labor are in place. It only take 10 days. So will be completed by 20 Sep. 3) Doors: materials & workers are not in place. Need to be mobilized by 20 Sep 4) Interior Lighting: materials & workers are not in place. Need to be mobilized by 20 Sep and immediately start whenever ceiling completed. 5) Restrooms (WC) : not yet start but it will be completed by 30 Sep since all materials & worker are on site. 6) Window: not yet start, but will be completed by end of Sep 2014. Frame & other accessories materials are on site, but Glass is not yet. Glass need to be mobilized by 20 Sep. 7) Floor tile: 0% completed. To be completed by 30 Sep since all materials and workers are on site. 8) Interior & Exterior of painting: not yet start, will be completed by 30 Sep. 14
  • 15. 15 On Overall 50% is completed. Additional materials and labors are needed and to be on site by 25 Aug for completion by 30 Sep 2014.
  • 16. External Works: about 50% completed; the following works to be finished: 1) Street Lighting: Poles 80% completed. Cable & Lamps are not connected. Electricians are not in place. Need to be mobilized by 15 Sep. 2) Road Concrete Slab: 30% completed, Materials and Labor need to be added. 100% of materials to be on site by 25 Aug 2014. 2) Flag Poles: 50% completed. Steel Flag Pole is not on site yet. It need to be on site by 15 Sep. 3) Garden and Tree Planting: curbs for garden are 90% completed. Materials and labors Need to be mobilized by 10 Sep. 4) Immigration Control Booths: 70% completed. All materials and labors are already on site. 5) Gates: 0% completed and not on site. 6) Others: Transformer & Electrical Supply, Fire Fighting System, Water Tape System, 7) Site Clean up: 5 workers for this works already mobilized on 13 Aug. 16
  • 17. Contractor need advance financing estimately about US$500,000 to complete the works by September 2014. Relay on IPCs of June & July (estimate about $700,000 including price adjustment) will not be enough fund to purchase all materials to the site. Even if IPCs process today it will take another two months to get the money (will be by 15 Oct) THANK YOU! 17