SlideShare une entreprise Scribd logo
1  sur  12
Liberty University BUSI 313 quiz 3 complete solutions correct answers slideshare
Four different versions
https://www.coursemerit.com/solution-details/20164/ Liberty-University-BUSI-313-quiz-3-complete-solutions-correct-answers-A-work
Question 1 The attempt to recognize and manage potential and unforeseen trouble spots that
may occur when a project is implemented is known as
Question 2 Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an
opportunity to ensure that it definitely happens.
Question 3 Fixedprice contracts are an example of transferring risk from an owner to a contractor.
Question 4 Which of the following is NOT included in a Failure Mode and Effects Analysis?
Question 5 After your team has successfully identified potential risks that could affect the project,
what is the next step?
Question 6 Adopting proven technology instead of experimental technology is an example of
mitigating a risk.
Question 7 If, during risk response development, you successfully identify how you will respond to
a risk, contingency planning is unnecessary.
Question 8 The probability that a risk event will occur is higher during the initial stages of a
project.
Question 9 Regina's boss has told her that her project is very important. If the critical path is
delayed, she will be given whatever she needs to get it back on schedule. Her project is classified
as ________ constrained.
Question 10 Gene is trying to order the concrete needed to continue his project. However, the
supplier will not be able to deliver it until next week. This is an example of what kind of resource
constraint?
Question 11 Rachel is working on a project that technically allows three activities to be done at
the same time. If they were to be implemented at the same time, she would need 5 contractors in
order for the activities to be completed on time. There are only 3 available for her to use. This is
an example of what type of constraint?
Question 12 Project budgets are developed by timephasing which of the following?
Question 13 If resources are truly limited and activity time estimates are accurate, the
resourceconstrained schedule will materialize as the project is implemented, not the
timeconstrained schedule.
Question 14 When resource constraints are added to technical constraints the original project
network may change as well as the completion date.
Question 15 In a resourceconstrained project, the first priority in assigning resources is usually
given to activities with the
Question 16 Sequential activities hold just as much potential for resource conflicts as parallel
activities.
Question 17 These are all guidelines a project manager should consider when assigning project
work EXCEPT
Question 18 The higher the cost slope of an activity the lower the cost to reduce its duration.
Question 19 One of the advantages of using a Project CostDuration Graph is that it keeps the
importance of indirect costs in the forefront of decision making.
Question 20 When reducing project duration, there will always be an optimum cost time point
where the total cost of the project is less than it was when the project was initially planned under
normal conditions.
Question 21 When reducing project duration, the crash cost per unit has to be calculated and the
maximum units each activity can be reduced must be known. After this, the critical path must be
identified. What is the next step?
Question 22 The cost slope of an activity is calculated by dividing the run by the rise.
Question 23 According to Brooks' Law, adding more people to a late project is most likely to have
which of the following impacts?
Question 24 Reducing project duration
Question 25 As a project is crashed and project duration is reduced, direct costs typically
An uncertain event or condition that, if it occurs, has a positive or negative effect on
project objectives is termed a
The chances of a risk event occurring as a project proceeds through its life cycle tend
to
The cost impact of a risk event occurring as a project proceeds through its life cycle
tends to
The attempt to recognize and manage potential and unforeseen trouble spots that may
occur when a project is implemented is known as
Which of the following is NOT one of the steps in the risk management process
The initial step in the risk management process is to
One common mistake made early in the risk identification process is to
Organizations use ____ in conjunction with work breakdown structures to help
management teams identify and eventually analyze risk
Which of the following groups should NOT be a part of the risk identification process?
After your team has successfully identified potential risks that could affect the project,
what is the next step
A list of questions that address traditional areas of uncertainty on a project is termed a
____ focuses on how to respond to events that have a positive impact on a project
Tools such as a risk assessment form and a risk severity matrix are used to
Based on the following, which event should you be most concerned about
____ is a measure of how easy it would be to notice that a risk event was going to
occur in time to take mitigating action, that is, how much warning you would have
Purchasing an accident insurance policy would be an example of responding to a risk
by ____ it
The risk management tool that is divided into three color-coded zones representing
major, moderate, and minor risks is the risk
The risk assessment form contains all of the following EXCEPT
Risks are evaluated in terms of
Adopting proven technology instead of experimental technology in order to eliminate
technical failure would be an example of which risk response
Which of the following activities might you consider adding a time buffer to
Which of the following is NOT included in a Failure Mode and Effects Analysis
A fixed price contract is an example of
Which of the following is NOT one of the potential responses to a specific risk event
A Risk Response Matrix contains all of the following EXCEPT
A key distinction between a risk response and a contingency plan is
The risk associated with the unlikelihood that one of the key members will be struck by
lightning would most likely be handled by which of the following
Funds that are for identified risks that have a low probability of occurring and that
decrease as the project progresses are called ______ reserves
Risks that can result in a system or process that will not work are known as
Which of the following is NOT involved in risk control
Which of the following is identified to cover major unforeseen risks and, hence, are
applied to the total project
Change management systems are designed to accomplish all of the following EXCEPT
An uncertain event or condition that, if it occurs, has a positive or negative effect on
project objectives is known as a ____
The likelihood of a risk event occurring ____ as a project goes through its life cycle
The first step in the risk management process is ____
The significance of a risk is assessed in terms of the ____ and the impact of the event
A list of questions that address traditional areas of uncertainty on a project is known as
a
The measurement of how easy it would be to detect that the event was going to occur
in time to take mitigating action is known as
The ____ form identifies each risk event, the likelihood of it occurring, the potential
impact, when it may occur, and the degree of difficulty in detecting it
The ____ matrix is divided into red, yellow, and green zones representing major,
moderate, and minor risks
According to the Failure Mode and Effects Analysis (FMEA), Impact x Probability x
Detection = ____
When considering risk response development, reducing the likelihood that an event will
occur and/or reducing the impact that an adverse event would have on a project is
known as ____ the risk
When considering risk response development, changing the plan to eliminate the risk or
condition is known as ____ the risk
When considering risk response development, passing risk to another party instead of
changing it is known as ____ the risk
When considering risk response development, assuming the risk because the chance
of such an event is slim is known as ____ the risk
Testing a new project on a smaller isolated area prior to installing it for the entire
organization is an example of ____ a risk
Performance bonds, warranties, and insurance are examples of ____ a risk
Choosing to move a concert indoors to eliminate the threat of bad weather is an
example of ____ a risk.
Flooding would be devastating to the project; however, it is very unlikely. The project
manager is most likely to ____ this risk
The event or point in time when a contingency plan will be implemented is called a
____
____ reserves are identified for specific work packages and are distributed by the
project manager and the team members.
____ reserves are controlled by the project manager and the owner of the project and
are used to cover major unforeseen risks to the entire project
A ____ is an alternative that will be used if a possible foreseen risk event becomes a
reality
____ systems involve reporting, controlling, and recording changes to the project
baseline
The probability that a risk event will occur is higher during the initial stages of a project
Risk events that occur in the early stages of a project will have a greater cost impact
than those that occur in later stages
Risk management is a reactive approach that is designed to ensure that surprises are
reduced and that negative consequences associated with undesirable events are
minimized
One common mistake that is made early on in the risk identification process is to focus
on consequences and not on the events that could produce consequences
The project being delayed is an example of a major risk that should be assessed
The first step in the risk management process is risk assessment
A risk profile is a list of questions that have been developed and refined from previous,
similar projects
The risk identification process should be limited to just the core project team.
While a "can do" attitude is essential during implementation, project managers have to
encourage critical thinking when it comes to risk identification
Responses to all identifiable risks should be a top priority for the project manager
When considering risk value, the lower the value, the higher the level of risk
If, during risk response development, you successfully identify how you will respond to
a risk, contingency planning is unnecessary
Adopting proven technology instead of experimental technology is an example of
mitigating a risk
A risk is an uncertain event that, if it occurs, can have a positive or negative effect on
project objectives
Performance bonds, warranties, and guarantees are financial instruments used to
share risk.
Fixed-price contracts are an example of transferring risk from an owner to a contractor
When developing a response to a risk by scheduling outdoor work in the summer,
investing in up-front safety training, or choosing high-quality materials, these are
examples of retaining a risk
Budget reserves are set up to cover identified risks associated with specific segments
of a project while management reserves are set up to cover unidentified risks
associated with the total project
Change management systems involve reporting, controlling, and recording changes to
the project baseline
Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an
opportunity to ensure that it definitely happens
Contingency funding is made up of budget reserves and management reserves
Resources are adequate, but demand varies widely over the life of the project. Delaying
noncritical activities to lower peak demand on resources is known as resource
If resources are not adequate to meet peak demands, the resulting reschedule is
termed
Which of the following is NOT a potential consequence of failing to identify limited
resources before project implementation
When developing a new software package, logically, the software must be designed
before the code is written, and the code must be written before it is tested. These
activities are dependent on each other by ______ constraints
When considering the sequence and timing of activities, which of the following is NOT
one of the types of project network constraints
Sam, the project engineer, has been scheduled to run the product system test at the
same time he is to build a marketing prototype. This is an example of what type of
resource constraint
Susan is to conduct environmental testing but the chamber cannot hold all the
equipment that she wants to test. This is an example of a constraint that could impact
the sequence and timing of activities in a project network. What type of constraint is it
All of the following are types of resource constraints EXCEPT
Gene is trying to order the concrete needed to continue his project. However, the
supplier will not be able to deliver it until next week. This is an example of what kind of
resource constraint
A special truck that George needs on his project has been scheduled on another
project. This is an example of what type of resource constraint?
Most of the scheduling methods available today require the project manager to classify
the project as either _____ constrained or ______ constrained
Regina's boss has told her that her project is very important. If the critical path is
delayed, she will be given whatever she needs to get it back on schedule. Her project is
classified as ______ constrained
In reviewing the status of her project with top management, Shirley was told that there
are only two programmers that she can use for her project. Her project is classified as
_______ constrained
All resource leveling techniques involve
Technical constraints have been carefully considered when developing a project
network. Which of the following is true at this point
Rachel is working on a project that technically allows three activities to be done at the
same time. If they were to be implemented at the same time, she would need 5
contractors in order for the activities to be completed on time. There are only 3
available for her to use. This is an example of what type of constraint
Resource leveling or smoothing can have all the following results on a project EXCEPT
Jan is trying to reallocate resources in a time-constrained project to create smoother
resource utilization. She should first identify activities with the
In a resource-constrained project, which of the following is most likely to be changed
In a resource-constrained project, the first priority in assigning resources is usually
given to activities with the
In a resource-constrained project the second priority in assigning resources is usually
given to activities with the
Tony has realized that two activities in his project cannot be done at the same time
because not enough resources are available. Activity 3 is critical and has a duration of
5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide
which activity should be scheduled first
Splitting an activity can result in all of the following EXCEPT
All of the following are benefits of scheduling resources before project implementation
EXCEPT
These are all guidelines a project manager should consider when assigning project
work EXCEPT
When a company will reduce the number of projects they have to manage internally to
only core projects and send noncritical projects to contractors and consulting firms this
is called
Which of the following is NOT one of the more common problems associated with
scheduling multiproject resources
In a resource-constrained project the third priority in assigning resources is usually
given to activities with the
Why is it necessary to have a time-phased budget baseline
Project budgets are developed by time-phasing which of the following
A project budget report is showing our project as spending $35,000 against a budgeted
amount of $40,000. Which of the following is true
Delaying noncritical activities to lower peak demand and, thus, increase resource
utilization is called resource ____
A(n) ________ constraint addresses the sequence in which project activities must
occur even after considering resource constraints
Having one person responsible for performing several activities, all due at the same
time, is an example of a(n) _____ constraint
Trying to renovate a ship compartment that is too small for more than one person is an
example of a(n) _____ resource constraint
A shortage of programmers to write software is an example of a(n) _____ type of
resource constraint
The shortage of computer chips to produce a circuit board is an example of a(n)
______ type of resource constraint
If three copiers are needed to produce a final report on time and only two are available,
the project is facing a(n) ________ type of resource constraint
Resource dependency takes priority over the technological dependency but does not
violate _____ dependencies
In order that the new product is on the shelf for the Christmas buying season, the
development of the new product would be classified as a(n) ________ -constrained
project
Beth has two engineers assigned to her project and does not have access to more
even if the result means extending the completion date on her project. She is managing
a(n) ________ -constrained project
All leveling techniques delay noncritical activities by using ________ to reduce peak
demand
When scheduling activities in a resource-constrained project, typically the activity
scheduled first has the ______ amount of slack
Since resource leveling or smoothing delays noncritical activities, a common result is an
increase in network _____
When the work in an activity is interrupted to work on another activity and is then
resumed at a later point in time, it is called ____
In scheduling resource-constrained projects, _____ are typically used rather than
optimum mathematical solutions
When classifying projects, ________ constrained means that project duration is fixed
and resources are flexible
When classifying projects, ________ constrained means that a specific resource is
fixed and the duration of the project is flexible
Start-up and shutdown costs are major considerations when using the ______
scheduling technique
After resource leveling or smoothing one goal is that the amount of resources needed
over the life of the project will be
Many companies are ______ project work to contractors and consultants as a means of
dealing with the peaks and valleys of resource allocation among projects
When a project is classified as resource-constrained and a resource constraint exists,
the project duration is typically ____
In reality resource allocation generally occurs in a(n) ______ environment where the
demands of one project have to be reconciled with the needs of other projects
Without a ____ budget a good project schedule and cost control are impossible
A project cost baseline is also called ____
The fact that you must pour foundation before you frame the house and that you have
to frame the house before you can put on the roof demonstrates scheduling constraints
Too many parallel activities for one individual is an example of a resource constraint
The level of resources each activity will need to be completed in the given amount of
time has been estimated; therefore, there are no resource constraints
Resource leveling or smoothing is only used on projects which are resource
constrained
Resource bottlenecks are one of the three more common problems encountered in
managing multiproject resource schedules
The inability to fit more than two earth movers on a construction site at the same time
when more are needed to complete the activity on time is an example of a physical
constraint
In a resource-constrained project, the completion date is most likely to change.
Having too few programmers and too many engineers is an example of a people
resource constraint
If a project needs one earth mover six months from now in order to complete one
activity, and the organization has four such machines, there is no equipment resource
constraint
A lack of readily available engineers is a technical constraint
Resource dependency takes priority over technological dependency but it does not
violate it
To determine if a project is time-constrained or resource-constrained you would consult
the project priority matrix
Sequential activities hold just as much potential for resource conflicts as parallel
activities.
All leveling techniques delay noncritical activities by using positive slack to smooth out
the resource requirements
Since resource leveling or smoothing delays noncritical activities, a common result is a
decrease in network sensitivity
Scheduling projects classified as resource-constrained focuses on completing the
project as soon as possible under the given resource constraints
When resource constraints are added to technical constraints the original project
network may change as well as the completion date
When scheduling activities in a resource-constrained project typically the activity
scheduled first has the most amount of slack
A project budget report is showing our project as spending $35,000 against a budgeted
amount of $40,000. We can assume that everything is going as planned and that we
are under budget
Splitting is a scheduling technique used to get a better schedule or better resource
utilization and should be used without hesitation
Without a time-phased budget a good project schedule and cost control are impossible
If resources are truly limited and activity time estimates are accurate, the resource-
constrained schedule will materialize as the project is implemented, not the time-
constrained schedule
Project managers should always assign the best people to the most difficult tasks
1. The president of a software company remarks in a speech that new technologically advanced
software will be available in one year. This is an example of reducing project duration caused by:
2. Intense global competition and rapid technological advances create pressure on developing
projects rapidly. This is an example of reducing project duration caused by:
3. A contractor finished a bridge across a lake 18 months early and received more than $6 million
for the early completion. This is an example of reducing project duration caused by:
4. Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an
example of reducing project duration caused by:
5. Total project costs include all of the following except:
6. Which of the following is not considered a project indirect cost?
7. Project costs are generally classified as ____ costs.
8. Low-cost, realistic, efficient methods for completing an activity under normal conditions are
supported by ____ time.
9. The shortest possible time an activity can be completed realistically is called ___ time.
10. The most common response for meeting unattainable deadlines is to
11. ____ costs are incurred when completing an activity in its realistically shortest time.
12. An activity's crash costs include ____ costs.
13. Cost slope can be determined by dividing the
14. The less steep the cost slope of an activity, the
15. Which of the following correctly calculates an activity's cost slope?
16. An activity's cost slope represents an activity's
17. In selecting the best activity to reduce you would first select the activity with the
18. The optimum duration for a project is at the point where:
19. Creating a Project Cost-Duration graph is useful:
20. Crashing a project should occur:
21. If a network has several critical or near-critical paths it is deemed to be:
22. The project direct-cost line near the normal point is usually:
23. The relationship between cost and time for various durations is assumed to be:
24. A common method for shortening the project time is to:
25. A positive situation where moving toward the optimum time can result in very real, large
savings—this occurs when the network is:
26. Which of the following is/are included in a Project Cost-Duration Graph?
27. One way of reducing project costs is identifying tasks that _________ can do themselves.
28. The most common method for shortening project time is to
29. Which of the following is not one of the more commonly used options for cutting project
costs?
30. Which of the following is the most common method for shortening project time?
31. According to Brooks' Law, adding more people to a late project is most likely to have which
of the following impact?
32. Which of the following is the easiest method for shortening project time?
33. Which of the following is not one of the techniques for accelerating project completion?
34. When the project team is salaried, which of the following is the preferred choice for
accelerating project completion?
35. The Snapshot from Practice "Cell-Phone Wars" is an excellent example of reducing project
duration due to:
36. When a politician makes a public statement that a new building will be available in two years,
a(n) ________ duration has reduced the project duration.
37. Intense global competition and rapid technological advances combine to create a(n) ________
imposed project duration date.
38. The Snapshot from Practice which detailed the Northridge earthquake demonstrated the
importance of reducing a project's ______.
39. Sometimes very high ________ costs are recognized before a project begins and reducing
these costs through shorter project durations becomes a high priority.
40. The ________ project cost is the sum of the indirect and direct costs.
41. Costs such as supervision, administration, consultants, and interest are examples of ________
project costs.
42. Costs such as labor, materials, equipment, or contractors are examples of ________ project
costs.
43. Direct costs are assignable directly to a project ________.
44. Because direct costs are assumed to be developed from normal methods and time, any
reduction in activity time should ________ the cost of the activity.
45. To shorten the duration of a project the project manager should limit the choices of activities
to just those which ________.
46. The ________ time for an activity represents low-costs, realistic, efficient methods for
completing the activity under typical conditions.
47. Shortening an activity is called ________.
48. The direct costs for completing an activity as early as possible is called its ________.
49. An activity's ________ is calculated by dividing the rise by the run.
50. Subtracting an activity's normal cost from the crash cost will calculate an activity's ________.
51. Subtracting an activity's crash time from the normal time will calculate an activity's ________.
52. When considering whether to move the project to its optimum cost-time position, the manager
should also consider ________.
53. A network is considered to be ________ if it has a predominate critical path with no other
path close in terms of slack.
54. The easiest way to add more resources to a project is not to add more people, but to schedule
________.
55. According to ________,adding more manpower to a late software project makes it later.
56. The easiest way to add more labor to a project is not to add more people, but to add
___________.
57. ____________ is the rearranging of the project network logic so that critical activities are
done in parallel rather than sequentially.
58. ___________ is probably the most common response for meeting unattainable deadlines.
59. In the "I'll Bet You..." Snapshot from Practice, the draftsman won ___________ for making a
very difficult deadline.
60. A rule of thumb for moderate- to high-technology firms is that a six-month delay in bringing
a product to market can result in a gross profit loss of about 35 percent.
61. Imposed project durations almost always leads to a higher-cost project than one planned with
detailed scheduling of all the project's activities.
62. Managers have several effective methods for crashing specific project activities when
resources are not constrained.
63. Indirect costs generally represent overhead costs such as supervision, administration,
consultants, and interest.
64. The total cost for each possible duration of a project is the sum of labor, materials, and
equipment.
65. Direct costs are so named because they can be assigned directly to a work package and
activity.
66. Because direct costs are assumed to be developed from normal methods and time, any
reduction in activity time should add to the costs of the activity.
67. The sum of the costs of all the work packages represents the total direct costs for the project.
68. Incentive contracts can make reduction of project time rewarding—usually for both the
project contractor and owner.
69. Shortening an activity's duration is termed crashing.
70. Expected time for an activity represents low-cost, realistic, efficient methods for completing
the activity under anticipated conditions.
71. Crash cost is the incremental cost incurred when an activity is reduced in duration.
72. The cost slope of an activity is calculated by dividing the run by the rise.
73. Crash time is the greatest time reduction possible under realistic conditions.
74. The higher the slope of an activity the greater the cost to reduce its duration.
75. Creating a Project Cost-Duration Graph in the pre-project planning phase without an imposed
duration is the best time to use this tool.
76. Crashing a more expensive activity may be wise if fewer inherent risks are involved.
77. A project network is classified as sensitive if it has a large number of interacting paths.
78. Collecting crash times for a moderate-size project is relatively easy.
79. While the relationship between normal and crash times is really curvilinear, the assumption
that it is linear is seldom a concern for practicing managers.
80. The accuracy of crash times and costs is frequently rough at best, when compared with
normal time and cost.
81. One of the advantages of using a Project Cost-Duration Graph is that it keeps the importance
of indirect costs in the forefront of decision making.

Contenu connexe

Tendances

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk toleranceGlen Alleman
 
Managing Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t MagicManaging Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t MagicTechWell
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertaintyGlen Alleman
 
Iwsm2014 defining technical risk in software development (vard antinyan)
Iwsm2014   defining technical risk in software development (vard antinyan)Iwsm2014   defining technical risk in software development (vard antinyan)
Iwsm2014 defining technical risk in software development (vard antinyan)Nesma
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
 
Project examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersProject examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersJohn Goodpasture
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementGlen Alleman
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk ManagementGlen Alleman
 
Agile project management and normative
Agile project management and normativeAgile project management and normative
Agile project management and normativeGlen Alleman
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMRGlen Alleman
 
Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)Glen Alleman
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)Glen Alleman
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?Glen Alleman
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual EssayPrince Bertrand
 

Tendances (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
Building risk tolerance
Building risk toleranceBuilding risk tolerance
Building risk tolerance
 
Managing Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t MagicManaging Risk in Agile Development: It Isn’t Magic
Managing Risk in Agile Development: It Isn’t Magic
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertainty
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Iwsm2014 defining technical risk in software development (vard antinyan)
Iwsm2014   defining technical risk in software development (vard antinyan)Iwsm2014   defining technical risk in software development (vard antinyan)
Iwsm2014 defining technical risk in software development (vard antinyan)
 
NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5NCV 4 Project Management Hands-On Support Slide Show - Module5
NCV 4 Project Management Hands-On Support Slide Show - Module5
 
Project examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbersProject examples for sampling and the law of large numbers
Project examples for sampling and the law of large numbers
 
Increasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk ManagementIncreasing the Probability of Success with Continuous Risk Management
Increasing the Probability of Success with Continuous Risk Management
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk Management
 
Agile project management and normative
Agile project management and normativeAgile project management and normative
Agile project management and normative
 
Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
Pmi 19 26
Pmi 19 26Pmi 19 26
Pmi 19 26
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMR
 
Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)
 
Risk ppt1672
Risk ppt1672Risk ppt1672
Risk ppt1672
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)
 
What Does Done Look Like?
What Does Done Look Like?What Does Done Look Like?
What Does Done Look Like?
 
Bertrand's Individual Essay
Bertrand's Individual EssayBertrand's Individual Essay
Bertrand's Individual Essay
 

Similaire à LIBU BUSI 313 quiz solutions risks project management

Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxMehediHasan636262
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
Risk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansRisk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansMohamed Saeed
 
Risk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansRisk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansMohamed Saeed
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docxjesusamckone
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docxRAJU852744
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentationRaven Morgan
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docx372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docxBHANU281672
 
372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docx372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docxpriestmanmable
 
Risky Business
Risky BusinessRisky Business
Risky Business3gamma
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdfNmnKmr2
 
Table of Contents Project Outline. …………………………………………………………………….docx
 Table of Contents Project Outline. …………………………………………………………………….docx Table of Contents Project Outline. …………………………………………………………………….docx
Table of Contents Project Outline. …………………………………………………………………….docxMARRY7
 
Schwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptSchwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptAyidAlmgati
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxaryan532920
 
5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docx5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docxgilbertkpeters11344
 

Similaire à LIBU BUSI 313 quiz solutions risks project management (20)

Lecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptxLecture 6 Managing risk.pptx
Lecture 6 Managing risk.pptx
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
Risk management
Risk managementRisk management
Risk management
 
Risk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ansRisk 3 simplelearn-exam2-ans
Risk 3 simplelearn-exam2-ans
 
Risk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansRisk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ans
 
Project risk management
Project risk managementProject risk management
Project risk management
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
 
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
130 MASTERING RISK AND PROCUREMENT IN PROJECT MANAGEMENTre.docx
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docx372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docx
 
372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docx372the risk report described in . The risk report will be .docx
372the risk report described in . The risk report will be .docx
 
Risky Business
Risky BusinessRisky Business
Risky Business
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdf
 
Table of Contents Project Outline. …………………………………………………………………….docx
 Table of Contents Project Outline. …………………………………………………………………….docx Table of Contents Project Outline. …………………………………………………………………….docx
Table of Contents Project Outline. …………………………………………………………………….docx
 
Schwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptSchwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.ppt
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docx5 Project Risk Managementadrian825iStockThinkstockLe.docx
5 Project Risk Managementadrian825iStockThinkstockLe.docx
 

Plus de Song Love

Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...Song Love
 
Economics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers keyEconomics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers keySong Love
 
Acc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers keyAcc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers keySong Love
 
Itm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers keyItm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers keySong Love
 
Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...Song Love
 
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers keyTutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers keySong Love
 
Statistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers keyStatistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers keySong Love
 
Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...Song Love
 
Liberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshareLiberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshareSong Love
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshareLiberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshareLiberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshareLiberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshareLiberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshareLiberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshareSong Love
 
Psyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers keyPsyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers keySong Love
 
1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers key1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers keySong Love
 
Liberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshareLiberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshareSong Love
 
Liberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshareLiberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshareSong Love
 
Liberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshareLiberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshareSong Love
 

Plus de Song Love (20)

Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...
 
Economics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers keyEconomics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers key
 
Acc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers keyAcc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers key
 
Itm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers keyItm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers key
 
Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...
 
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers keyTutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
 
Statistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers keyStatistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers key
 
Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...
 
Liberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshareLiberty university busi 313 quiz 4 complete solutions correct answers slideshare
Liberty university busi 313 quiz 4 complete solutions correct answers slideshare
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshareLiberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshareLiberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshareLiberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshareLiberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshareLiberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshare
 
Psyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers keyPsyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers key
 
1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers key1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers key
 
Liberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshareLiberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshare
 
Liberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshareLiberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshare
 
Liberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshareLiberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshare
 

Dernier

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 

Dernier (20)

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 

LIBU BUSI 313 quiz solutions risks project management

  • 1. Liberty University BUSI 313 quiz 3 complete solutions correct answers slideshare Four different versions https://www.coursemerit.com/solution-details/20164/ Liberty-University-BUSI-313-quiz-3-complete-solutions-correct-answers-A-work Question 1 The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as Question 2 Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens. Question 3 Fixedprice contracts are an example of transferring risk from an owner to a contractor. Question 4 Which of the following is NOT included in a Failure Mode and Effects Analysis? Question 5 After your team has successfully identified potential risks that could affect the project, what is the next step? Question 6 Adopting proven technology instead of experimental technology is an example of mitigating a risk. Question 7 If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary. Question 8 The probability that a risk event will occur is higher during the initial stages of a project. Question 9 Regina's boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is classified as ________ constrained. Question 10 Gene is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint? Question 11 Rachel is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time. There are only 3 available for her to use. This is
  • 2. an example of what type of constraint? Question 12 Project budgets are developed by timephasing which of the following? Question 13 If resources are truly limited and activity time estimates are accurate, the resourceconstrained schedule will materialize as the project is implemented, not the timeconstrained schedule. Question 14 When resource constraints are added to technical constraints the original project network may change as well as the completion date. Question 15 In a resourceconstrained project, the first priority in assigning resources is usually given to activities with the Question 16 Sequential activities hold just as much potential for resource conflicts as parallel activities. Question 17 These are all guidelines a project manager should consider when assigning project work EXCEPT Question 18 The higher the cost slope of an activity the lower the cost to reduce its duration. Question 19 One of the advantages of using a Project CostDuration Graph is that it keeps the importance of indirect costs in the forefront of decision making. Question 20 When reducing project duration, there will always be an optimum cost time point where the total cost of the project is less than it was when the project was initially planned under normal conditions. Question 21 When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step? Question 22 The cost slope of an activity is calculated by dividing the run by the rise. Question 23 According to Brooks' Law, adding more people to a late project is most likely to have which of the following impacts? Question 24 Reducing project duration Question 25 As a project is crashed and project duration is reduced, direct costs typically
  • 3. An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a The chances of a risk event occurring as a project proceeds through its life cycle tend to The cost impact of a risk event occurring as a project proceeds through its life cycle tends to The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as Which of the following is NOT one of the steps in the risk management process The initial step in the risk management process is to One common mistake made early in the risk identification process is to Organizations use ____ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk Which of the following groups should NOT be a part of the risk identification process? After your team has successfully identified potential risks that could affect the project, what is the next step A list of questions that address traditional areas of uncertainty on a project is termed a ____ focuses on how to respond to events that have a positive impact on a project Tools such as a risk assessment form and a risk severity matrix are used to Based on the following, which event should you be most concerned about ____ is a measure of how easy it would be to notice that a risk event was going to occur in time to take mitigating action, that is, how much warning you would have Purchasing an accident insurance policy would be an example of responding to a risk by ____ it The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk The risk assessment form contains all of the following EXCEPT Risks are evaluated in terms of Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of which risk response Which of the following activities might you consider adding a time buffer to Which of the following is NOT included in a Failure Mode and Effects Analysis A fixed price contract is an example of Which of the following is NOT one of the potential responses to a specific risk event A Risk Response Matrix contains all of the following EXCEPT A key distinction between a risk response and a contingency plan is The risk associated with the unlikelihood that one of the key members will be struck by lightning would most likely be handled by which of the following Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves Risks that can result in a system or process that will not work are known as Which of the following is NOT involved in risk control Which of the following is identified to cover major unforeseen risks and, hence, are applied to the total project Change management systems are designed to accomplish all of the following EXCEPT An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is known as a ____ The likelihood of a risk event occurring ____ as a project goes through its life cycle The first step in the risk management process is ____
  • 4. The significance of a risk is assessed in terms of the ____ and the impact of the event A list of questions that address traditional areas of uncertainty on a project is known as a The measurement of how easy it would be to detect that the event was going to occur in time to take mitigating action is known as The ____ form identifies each risk event, the likelihood of it occurring, the potential impact, when it may occur, and the degree of difficulty in detecting it The ____ matrix is divided into red, yellow, and green zones representing major, moderate, and minor risks According to the Failure Mode and Effects Analysis (FMEA), Impact x Probability x Detection = ____ When considering risk response development, reducing the likelihood that an event will occur and/or reducing the impact that an adverse event would have on a project is known as ____ the risk When considering risk response development, changing the plan to eliminate the risk or condition is known as ____ the risk When considering risk response development, passing risk to another party instead of changing it is known as ____ the risk When considering risk response development, assuming the risk because the chance of such an event is slim is known as ____ the risk Testing a new project on a smaller isolated area prior to installing it for the entire organization is an example of ____ a risk Performance bonds, warranties, and insurance are examples of ____ a risk Choosing to move a concert indoors to eliminate the threat of bad weather is an example of ____ a risk. Flooding would be devastating to the project; however, it is very unlikely. The project manager is most likely to ____ this risk The event or point in time when a contingency plan will be implemented is called a ____ ____ reserves are identified for specific work packages and are distributed by the project manager and the team members. ____ reserves are controlled by the project manager and the owner of the project and are used to cover major unforeseen risks to the entire project A ____ is an alternative that will be used if a possible foreseen risk event becomes a reality ____ systems involve reporting, controlling, and recording changes to the project baseline The probability that a risk event will occur is higher during the initial stages of a project Risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages Risk management is a reactive approach that is designed to ensure that surprises are reduced and that negative consequences associated with undesirable events are minimized One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences The project being delayed is an example of a major risk that should be assessed The first step in the risk management process is risk assessment A risk profile is a list of questions that have been developed and refined from previous, similar projects The risk identification process should be limited to just the core project team.
  • 5. While a "can do" attitude is essential during implementation, project managers have to encourage critical thinking when it comes to risk identification Responses to all identifiable risks should be a top priority for the project manager When considering risk value, the lower the value, the higher the level of risk If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary Adopting proven technology instead of experimental technology is an example of mitigating a risk A risk is an uncertain event that, if it occurs, can have a positive or negative effect on project objectives Performance bonds, warranties, and guarantees are financial instruments used to share risk. Fixed-price contracts are an example of transferring risk from an owner to a contractor When developing a response to a risk by scheduling outdoor work in the summer, investing in up-front safety training, or choosing high-quality materials, these are examples of retaining a risk Budget reserves are set up to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project Change management systems involve reporting, controlling, and recording changes to the project baseline Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens Contingency funding is made up of budget reserves and management reserves Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource If resources are not adequate to meet peak demands, the resulting reschedule is termed Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by ______ constraints When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it All of the following are types of resource constraints EXCEPT Gene is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint A special truck that George needs on his project has been scheduled on another project. This is an example of what type of resource constraint? Most of the scheduling methods available today require the project manager to classify the project as either _____ constrained or ______ constrained
  • 6. Regina's boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is classified as ______ constrained In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project. Her project is classified as _______ constrained All resource leveling techniques involve Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point Rachel is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time. There are only 3 available for her to use. This is an example of what type of constraint Resource leveling or smoothing can have all the following results on a project EXCEPT Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization. She should first identify activities with the In a resource-constrained project, which of the following is most likely to be changed In a resource-constrained project, the first priority in assigning resources is usually given to activities with the In a resource-constrained project the second priority in assigning resources is usually given to activities with the Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first Splitting an activity can result in all of the following EXCEPT All of the following are benefits of scheduling resources before project implementation EXCEPT These are all guidelines a project manager should consider when assigning project work EXCEPT When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called Which of the following is NOT one of the more common problems associated with scheduling multiproject resources In a resource-constrained project the third priority in assigning resources is usually given to activities with the Why is it necessary to have a time-phased budget baseline Project budgets are developed by time-phasing which of the following A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource ____ A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints Having one person responsible for performing several activities, all due at the same time, is an example of a(n) _____ constraint Trying to renovate a ship compartment that is too small for more than one person is an example of a(n) _____ resource constraint A shortage of programmers to write software is an example of a(n) _____ type of resource constraint
  • 7. The shortage of computer chips to produce a circuit board is an example of a(n) ______ type of resource constraint If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint Resource dependency takes priority over the technological dependency but does not violate _____ dependencies In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n) ________ -constrained project Beth has two engineers assigned to her project and does not have access to more even if the result means extending the completion date on her project. She is managing a(n) ________ -constrained project All leveling techniques delay noncritical activities by using ________ to reduce peak demand When scheduling activities in a resource-constrained project, typically the activity scheduled first has the ______ amount of slack Since resource leveling or smoothing delays noncritical activities, a common result is an increase in network _____ When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called ____ In scheduling resource-constrained projects, _____ are typically used rather than optimum mathematical solutions When classifying projects, ________ constrained means that project duration is fixed and resources are flexible When classifying projects, ________ constrained means that a specific resource is fixed and the duration of the project is flexible Start-up and shutdown costs are major considerations when using the ______ scheduling technique After resource leveling or smoothing one goal is that the amount of resources needed over the life of the project will be Many companies are ______ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects When a project is classified as resource-constrained and a resource constraint exists, the project duration is typically ____ In reality resource allocation generally occurs in a(n) ______ environment where the demands of one project have to be reconciled with the needs of other projects Without a ____ budget a good project schedule and cost control are impossible A project cost baseline is also called ____ The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints Too many parallel activities for one individual is an example of a resource constraint The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints Resource leveling or smoothing is only used on projects which are resource constrained Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint In a resource-constrained project, the completion date is most likely to change.
  • 8. Having too few programmers and too many engineers is an example of a people resource constraint If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint A lack of readily available engineers is a technical constraint Resource dependency takes priority over technological dependency but it does not violate it To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix Sequential activities hold just as much potential for resource conflicts as parallel activities. All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints When resource constraints are added to technical constraints the original project network may change as well as the completion date When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. We can assume that everything is going as planned and that we are under budget Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation Without a time-phased budget a good project schedule and cost control are impossible If resources are truly limited and activity time estimates are accurate, the resource- constrained schedule will materialize as the project is implemented, not the time- constrained schedule Project managers should always assign the best people to the most difficult tasks 1. The president of a software company remarks in a speech that new technologically advanced software will be available in one year. This is an example of reducing project duration caused by: 2. Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example of reducing project duration caused by: 3. A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion. This is an example of reducing project duration caused by: 4. Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by: 5. Total project costs include all of the following except: 6. Which of the following is not considered a project indirect cost?
  • 9. 7. Project costs are generally classified as ____ costs. 8. Low-cost, realistic, efficient methods for completing an activity under normal conditions are supported by ____ time. 9. The shortest possible time an activity can be completed realistically is called ___ time. 10. The most common response for meeting unattainable deadlines is to 11. ____ costs are incurred when completing an activity in its realistically shortest time. 12. An activity's crash costs include ____ costs. 13. Cost slope can be determined by dividing the 14. The less steep the cost slope of an activity, the 15. Which of the following correctly calculates an activity's cost slope? 16. An activity's cost slope represents an activity's 17. In selecting the best activity to reduce you would first select the activity with the 18. The optimum duration for a project is at the point where: 19. Creating a Project Cost-Duration graph is useful: 20. Crashing a project should occur: 21. If a network has several critical or near-critical paths it is deemed to be: 22. The project direct-cost line near the normal point is usually: 23. The relationship between cost and time for various durations is assumed to be: 24. A common method for shortening the project time is to: 25. A positive situation where moving toward the optimum time can result in very real, large savings—this occurs when the network is: 26. Which of the following is/are included in a Project Cost-Duration Graph? 27. One way of reducing project costs is identifying tasks that _________ can do themselves. 28. The most common method for shortening project time is to 29. Which of the following is not one of the more commonly used options for cutting project
  • 10. costs? 30. Which of the following is the most common method for shortening project time? 31. According to Brooks' Law, adding more people to a late project is most likely to have which of the following impact? 32. Which of the following is the easiest method for shortening project time? 33. Which of the following is not one of the techniques for accelerating project completion? 34. When the project team is salaried, which of the following is the preferred choice for accelerating project completion? 35. The Snapshot from Practice "Cell-Phone Wars" is an excellent example of reducing project duration due to: 36. When a politician makes a public statement that a new building will be available in two years, a(n) ________ duration has reduced the project duration. 37. Intense global competition and rapid technological advances combine to create a(n) ________ imposed project duration date. 38. The Snapshot from Practice which detailed the Northridge earthquake demonstrated the importance of reducing a project's ______. 39. Sometimes very high ________ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority. 40. The ________ project cost is the sum of the indirect and direct costs. 41. Costs such as supervision, administration, consultants, and interest are examples of ________ project costs. 42. Costs such as labor, materials, equipment, or contractors are examples of ________ project costs. 43. Direct costs are assignable directly to a project ________. 44. Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should ________ the cost of the activity. 45. To shorten the duration of a project the project manager should limit the choices of activities to just those which ________. 46. The ________ time for an activity represents low-costs, realistic, efficient methods for completing the activity under typical conditions.
  • 11. 47. Shortening an activity is called ________. 48. The direct costs for completing an activity as early as possible is called its ________. 49. An activity's ________ is calculated by dividing the rise by the run. 50. Subtracting an activity's normal cost from the crash cost will calculate an activity's ________. 51. Subtracting an activity's crash time from the normal time will calculate an activity's ________. 52. When considering whether to move the project to its optimum cost-time position, the manager should also consider ________. 53. A network is considered to be ________ if it has a predominate critical path with no other path close in terms of slack. 54. The easiest way to add more resources to a project is not to add more people, but to schedule ________. 55. According to ________,adding more manpower to a late software project makes it later. 56. The easiest way to add more labor to a project is not to add more people, but to add ___________. 57. ____________ is the rearranging of the project network logic so that critical activities are done in parallel rather than sequentially. 58. ___________ is probably the most common response for meeting unattainable deadlines. 59. In the "I'll Bet You..." Snapshot from Practice, the draftsman won ___________ for making a very difficult deadline. 60. A rule of thumb for moderate- to high-technology firms is that a six-month delay in bringing a product to market can result in a gross profit loss of about 35 percent. 61. Imposed project durations almost always leads to a higher-cost project than one planned with detailed scheduling of all the project's activities. 62. Managers have several effective methods for crashing specific project activities when resources are not constrained. 63. Indirect costs generally represent overhead costs such as supervision, administration, consultants, and interest. 64. The total cost for each possible duration of a project is the sum of labor, materials, and equipment. 65. Direct costs are so named because they can be assigned directly to a work package and
  • 12. activity. 66. Because direct costs are assumed to be developed from normal methods and time, any reduction in activity time should add to the costs of the activity. 67. The sum of the costs of all the work packages represents the total direct costs for the project. 68. Incentive contracts can make reduction of project time rewarding—usually for both the project contractor and owner. 69. Shortening an activity's duration is termed crashing. 70. Expected time for an activity represents low-cost, realistic, efficient methods for completing the activity under anticipated conditions. 71. Crash cost is the incremental cost incurred when an activity is reduced in duration. 72. The cost slope of an activity is calculated by dividing the run by the rise. 73. Crash time is the greatest time reduction possible under realistic conditions. 74. The higher the slope of an activity the greater the cost to reduce its duration. 75. Creating a Project Cost-Duration Graph in the pre-project planning phase without an imposed duration is the best time to use this tool. 76. Crashing a more expensive activity may be wise if fewer inherent risks are involved. 77. A project network is classified as sensitive if it has a large number of interacting paths. 78. Collecting crash times for a moderate-size project is relatively easy. 79. While the relationship between normal and crash times is really curvilinear, the assumption that it is linear is seldom a concern for practicing managers. 80. The accuracy of crash times and costs is frequently rough at best, when compared with normal time and cost. 81. One of the advantages of using a Project Cost-Duration Graph is that it keeps the importance of indirect costs in the forefront of decision making.