SlideShare une entreprise Scribd logo
1  sur  91
October 8, 2014 
Envelope Compliance 
ASHRAE 90.1 and NECB 2011
OVERVIEW 
 Code requirements and the Standards 
 Broad overview of the Standards 
 ASHRAE 90.1 prescriptive requirements 
2 
and trade-off method for Envelope 
 NECB Prescriptive requirements and 
trade-off method for Envelope 
 Summary comparison of the prescriptive 
requirements and what it means in the 
BC building context 
 Looking at different methods of 
accounting for thermal bridging
BCBC 2012 
3
VANCOUVER BUILDING BY-LAW 
4
STANDARDS IN CODES 
5 
ASHRAE 90.1 2004 – Previous BCBC 
ASHRAE 90.1 2007 – Previous VBBL 
ASHRAE 90.1 2010 & NECB 2011 – 
Current BCBC and VBBL
ASHRAE 90.1 2010 
6 
WHO ARE THEY? 
American Society of Heating 
Refrigeration and Air-conditioning 
Engineers 
WHAT IS THE STANDARD? 
First addition developed in 1970 
In 1999 the standard was put into 
continuous maintenance 
Applies to all commercial buildings 
and MURBS greater than 3 stories.
ASHRAE 90.1 OVERVIEW 
7 
ALTERNATIVE PATHS FOR 
COMPLIANCE 
Prescriptive 
Trade-off 
Energy cost budget 
PRESCRIPTIVE PATH (OR TRADE-OFF) 
REQUIRE THAT ALL PARTS OF THE 
STANDARD BE MET: 
Part 5 - Building envelope 
Part 6 - Heating, ventilating and 
air-conditioning 
Part 7 - Service water heating 
Part 8 - Power 
Part 9 - Lighting 
Mandatory Part 10 - Other equipment 
Provisions
ASHRAE 90.1 OVERVIEW 
8 
ASHRAE 2004 
Baseline 
ASHRAE 2007 
Increased BE 
requirements 
ASHRAE 2010 
No major changes 
in BE requirements
NECB 2011 
 Developed by Natural Resources 
9 
Canada & the National Research 
Council for Canada 
 What is the Standard? 
 Last version was in 1997 (MNECB) 
 Design intent was to be roughly equivalent 
to ASHRAE 90.1 2010 
 Applies to new buildings (except part 9), 
additions to existing building, but silent on 
renovations 
 Before now, not referenced in BCBC or 
VBBL 
 MNECB is referenced in LEED
NECB OVERVIEW 
10 
ALTERNATIVE PATHS FOR COMPLIANCE 
 Prescriptive 
 Trade-off (simple or detailed) 
 Energy simulation (building energy compliance) 
PRESCRIPTIVE PATH (OR TRADE-OFF) REQUIRE THAT ALL 
PARTS OF THE STANDARD BE MET: 
 Part 3 – Building envelope 
 Part 4 – Lighting 
 Part 5 – Heating, ventilating and air-conditioning systems 
 Part 6 – Service water heating systems 
 Part 7 – Electrical power systems and motors
ZONES AND HEATING DEGREE DAYS (HDD) 
11 
ASHRAE 90.1 Climate zones for BC
ZONES AND HEATING DEGREE DAYS (HDD) 
12
ASHRAE 90.1 2010 
BUILDING ENVELOPE
ASHRAE 90.1- BUILDING ENVELOPE 
14
ASHRAE 90.1- MANDATORY PROVISIONS 
THIS MEANS THAT THE 
BUILDING SHOULD BE 
DESIGNED TO MEET 
THESE PROVISIONS: 
Insulation 
Air leakage 
• Air-barrier 
selection and 
design 
• Limit to 
fenestration and 
doors including 
cargo doors 
• Vestibule 
Fenestration and 
Doors values 
• NFRC 
15
ASHRAE 90.1 MANDATORY PROVISIONS 
16 
ASHREA 90.1 
Air leakage 
limits 
NAFS 
Air Leakage 
limits 
ASHRAE Type Limit 
Glazed Swinging entrance 
door & revolving doors 
1.0 cfm/ft2 at 1.57psf 
Curtain wall & Storefront 0.06cfm/ft2 at 1.57psf 
Other products 0.2cfm/ft2 at 1.57psf or 
0.3 cfm/ft2 at 6.24psf 
NAFS defines air leakage by performance 
class (R, LC, CW and AW) and air infiltration / 
exfiltration levels (A2, A3 and Fixed) and can 
be more stringent: 
Fixed as low as 0.2 L/s.m2 at 300Pa (or 0.04cfm/ft2 at 
6.24psf) 
Operable as low as 0.5 L/s.m2 at 300Pa (or 0.1cfm/ft2 
at 6.24psf)
ASHRAE 90.1 PRESCRIPTIVE METHOD 
17 
THE PRESCRIPTIVE 
METHOD CAN ONLY BE 
USED IF: 
The vertical 
fenestration ≤ 40% 
of Gross wall Area 
The skylight 
fenestration ≤ 5% 
of gross roof area
ASHRAE 90.1 - OPAQUE AREAS 
 For conditioned spaces the 
18 
exterior building envelope 
shall comply with, to either: 
the residential or the non-residential 
requirements in 
the tables 
 For semi-heated spaces the 
semi-exterior building 
envelope needs to comply 
with the requirements in the 
tables
ASHRAE 90.1 - PRESCRIPTIVE OPAQUE AREAS 
19 
THE TABLES CONTAINING THE THERMAL PERFORMANCE 
REQUIREMENTS ARE PROVIDED IN THE STANDARD, BY CLIMATIC 
ZONES, AND LOOK LIKE THIS: 
For all opaque elements (except doors) compliance should be 
demonstrated by the following methods: 
 Maximum U-factors, C-factors or F-factors for the entire assembly 
 Minimum rated R values of insulation 
Exception: For multiple assemblies within a single class of 
construction for a single conditioning space, weighed average can be 
used.
ASHRAE 90.1 PRESCRIPTIVE OPAQUE AREAS 
20 
Components 
Zone 5 
Non-Residential Residential Semi-Heated 
U factor R value U factor R value U factor R value 
Roof - insulation above 
deck 
0.048 
(R20.8) 
20.0c.i. 0.048 
(R20.8) 
20.0c.i. 0.119 
(R8.4) 
7.6c.i. 
Roof - Attic 0.027 
(R37.0) 
38.0 0.027 
(R37.0) 
38.0 0.053 
(R18.9) 
19.0 
Walls - Mass 0.090 
(R11.1) 
11.4c.i. 0.080 
(R12.5) 
13.3c.i. 0.151 
(R6.6) 
5.7c.i. 
Walls - Steel framed 0.064 
(R15.6) 
13.0+7.5c.i. 0.064 
(R15.6) 
13.0+7.5c.i. 0.124 
(R8.1) 
13.0 
Walls - Wood framed 0.064 
(R15.6) 
13.0+3.8c.i. 0.051 
(R19.6) 
13.0+7.5c.i. 0.089 
(R11.2) 
13.0
ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 
21 
SO THAT MEANS: 
 If there is more than nails or screws going through the 
insulation, it is not continuous 
 If there are studs, girts, clips, even brick ties they need 
to be accounted for. 
 This can be done by calculating the effective U (or R) 
values of these assemblies
ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 
22 
NOMINAL R VALUES 
Rated R values which do not 
take into account framing or 
other element interrupting 
the insulation 
vs. EFFECTIVE R VALUES 
Calculated R 
values which 
allows for the 
impact of 
thermal bridges
ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 
23 
Zone 4&5 = 0.064
ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 
24 
Zone 4 = 0.064 Zone 5 = 0.051
ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 
25 
Components 
Residential 
R values 
Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 
Roof - insulation 
above deck 
20.0c.i. 20.0c.i. 20.0c.i. 20.0c.i. 20.0c.i. 
Roof - Attic 38.0 38.0 38.0 38.0 49.0 
Walls - Mass 11.4c.i. 13.3c.i. 15.2c.i. 15.2c.i. 25.0c.i. 
Walls - Steel framed 13.0+7.5c.i. 13.0+7.5c.i. 13.0+7.5c.i. 13.0+15.6c.i. 13.0+18.8c.i. 
Walls - Wood 
framed 
13.0+3.8c.i. 13.0+7.5c.i. 13.0+7.5c.i. 13.0+7.5c.i. 13.0+15.6c.i.
ASHRAE 90.1 PRESCRIPTIVE - FENESTRATION 
Windows <40% of gross wall area and Skylights <5% gross roof area 
26 
All fenestration compliance 
shall be demonstrated 
through meeting: 
• U factor no greater than the 
prescriptive requirements 
• SHGC no greater than the 
prescriptive requirements 
If there are multiple assemblies, compliance shall be based on an area-weighted 
average U-factor or SHGC (for a single space-conditioning and 
within a single class of construction). 
The SHGC can be reduced using a multiplier when a permanent projection 
provides shading for the window
ASHRAE 90.1 PRESCRIPTIVE - FENESTRATION 
27 
Components 
Zone 5 
Residential Non-Residential Semi-Heated 
U factor SHGC U factor SHGC U factor SHGC 
Non-Metal Framing 0.35 
0.40 for 
all 
0.35 
0.40 for 
all 
1.20 
0.40 for 
all 
Metal Framing (curtain 
wall and storefront) 0.45 0.45 1.20 
Metal Framing (entrance 
doors) 0.80 0.80 1.20 
Metal Framing (operable 
and fixed windows, non-entrance 
doors) 0.55 0.55 1.20 
Skylight (glass, 
without curb) 
0-2% 
0.69 
0.49 
0.69 
0.49 
1.36 
NR 
2-5% 0.39 0.39 NR
ASHRAE 90.1 TRADE-OFF 
28 
The trade-off method allows greater flexibility when some of the building envelope 
components are not meeting: 
• The basic requirements for the Prescriptive method (e.g. > 40% window 
to wall ratio and/or >5% skylight to roof ratio) 
• The prescriptive R or U values 
• Trade-offs are made between any building envelope components 
(but just building envelope component) 
• It implies that some of the building envelope components exceed 
the minimum requirements 
• Schedules of operation, lighting power, equipment power, occupant 
density, and mechanical systems need to be the same for both the 
proposed building and the base building
ASHRAE 90.1 TRADE-OFF 
29 
THE BUILDING ENVELOPE COMPLIES WHEN: 
Envelope performance 
factor of proposed building 
Envelope performance 
factor of base building ≤ 
The base building is a building that has 40% fenestration 
to gross wall area and for which all BE components meet 
the prescriptive minimum U value 
The envelope performance factor is calculated using the 
information contained in normative appendix C
ASHRAE 90.1 TRADE-OFF 
30 
Need to : 
 Do take-offs for all the different BE 
components i.e. floor, roof, wall and 
fenestration assemblies for every 
space-conditioning category and 
every orientation. 
 Evaluate the U values of each 
component including SHGC and VT 
for fenestration. 
 Enter all the numbers into a series 
of equations that you can find in 
normative Appendix C*. 
COMcheck * (Now has Canadian climate data). 
Axis – Raymond Letkeman Architects
COMCHECK 
31
COMCHECK 
32
NECB 2011 
BUILDING ENVELOPE
NECB 
34
NECB - MANDATORY PROVISIONS 
35 
NO SPECIFIC 
MANDATORY 
PROVISIONS 
But more specific than ASHRAE 
on how to deal with effect of 
structural members that may 
partially and completely 
penetrate the envelope 
In the 
prescriptive 
requirements, we 
find that : 
Insulation should be installed in a manner that avoids 
affecting its R value (convection, wetting, etc.). 
Insulation value required depends on zone, assembly 
(wall, roof or floor) and location (above or below 
grade or spaces heated to different temperature) 
Air leakage should be controlled, including at 
fenestration and doors, which have limits of air 
leakage allowable 
A vestibule is likely required
NECB - PRESCRIPTIVE METHOD 
THE PRESCRIPTIVE 
METHOD CAN ONLY 
36 
BE USED IF: 
FDWR ≤ 0.40 for HDD < 4000 
FDWR ≤(2000- 0.2*HDD) 
3000 
for 4000 ≤ HDD ≤ 7000 
FDWR ≤ 0.20 for HDD > 7000 
& 
The skylight fenestration ≤ 
5% of gross roof area
NECB - THERMAL BRIDGING 
THERMAL BRIDGING 
37 
CREATED BY 
STRUCTURAL 
MEMBERS 
The thermal bridging effect of closely spaced 
repetitive structural members (e.g. studs) and of 
ancillary members (e.g. sill and plates) should be 
taken into account. 
The thermal bridging of major structural elements 
that are parallel to the building envelope can be 
ignored, provided that they do not increase the 
thermal transmittance to more than twice than 
permitted. 
The thermal bridging of major structural elements 
that must penetrate the building envelope need 
not be taken into account, provided that the sum of 
the areas is less than 2% of the above ground 
building envelope. 
Service equipment, shelf angle, ties and associate fasteners as well as minor 
structural members need not be taken into account!!!
NECB PRESCRIPTIVE INSULATION 
38 
The prescriptive method requires: 
4xW W 
W 
4xW
NECB PRESCRIPTIVEWALLS ABOVE GRADE 
 No difference between residential 
and non-residential 
 No difference between the different 
type of construction 
39 
Assemblies 
Any Occupancy 
R values (effective) 
Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 
Walls 18 20.4 23 27 31 
Roofs 25 31 31 35 40 
Floors 25 31 31 35 40 
Walls - mass 11.4 
Walls - steel framed 15.6 
Walls - wood framed 19.6 
Roofs - insulation above 20.8 
Roofs - attic 37.0
NECB PRESCRIPTIVE FENESTRATION AND DOORS 
40 
Components 
U values (effective) 
Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 
All Fenestration 0.42 0.39 0.39 0.39 0.28 
All Doors 0.42 0.39 0.39 0.39 0.28 
 No difference between residential and non-residential 
 No difference between the different type of assemblies 
 No SHGC requirements 
 Exceptions: 
 Skylights that represent < 2% of gross roof area can have a 
thermal transmittance of no more than 0.60 
 Doors that represent < 2% of gross wall area can have a 
thermal transmittance of no more than 0.77 
Non-metal 0.35 
Metal framing (CW) 0.45 
Metal framing (others) 0.55 
Entrance doors 0.80 
Skylights 0.58
NECB - PRESCRIPTIVE METHOD 
41
NECB - TRADE-OFF METHODS 
42 
THERE ARE 2 TRADE-OFF PATHS: 
Simple trade-off 
calculations 
Detailed trade-off path 
Proposed Bldg 
Envelope 
Annual Energy 
Consumption 
Reference Bldg 
Envelope energy 
target 
≤ 
Calculation are done using an energy 
model with set requirements 
≤ 
Proposed building 
Reference building
NECB - DETAILED TRADE-OFF METHOD 
THE DETAILED 
METHOD 
CONSISTS OF: 
43 
Same building size and shape, roof slope, and 
building orientation for the proposed and 
reference building 
Same assumptions for space heating and cooling 
Allowable fenestration and door areas in the 
proposed building can be varied, while it is set per 
the prescriptive requirements in the reference 
building 
Take into account thermal mass and SHGC 
Air leakage and solar absorbance cannot be varied
COMPARISON OF 2 STANDARDS 
44 
ASHRAE 90.1 2010 NECB 2011 
Mandatory 
requirements 
Yes, for all methods Not for energy modeling 
Prescriptive 
requirements 
Generally less 
demanding R values 
Stringent, specific 
• Framing Take into account Take into account 
• Structure Not clear Specific (if this then…) 
• Cladding attachments Take into account Some can be ignored 
• Service penetrations Ignore Specific (if this then…) 
• Walls More categories Less categories 
• Fenestration & doors More categories Less categories 
Trade-off methods Complex, no benefit if 
FDWR <40% 
Simple or software 
Benefit if FDWR <40%
OVERALL 
45 
Prescriptive method, for 
either standard, is for 
simpler buildings 
Trade-off method may get you the 
desired result, but cannot do 
anything for you when most of the 
BE components are below
CONCLUSION REGARDING THE STANDARDS 
 Wood frame is well suited for prescriptive but: 
46 
 New standards will generally require exterior insulation to meet the 
max U-factor with 2x6 residential 
 Only zone 4 in ASHRAE (but not in NEBC) could do without exterior 
insulation in residential 
 For non-combustible building, the prescriptive method is not a likely 
candidate 
 This is especially true for exposed concrete tower and buildings with 
high window/wall ratio 
 Exterior insulated assemblies can probably meet it but structure 
penetrating through (balcony slabs, parapet, etc.) need to be taken into 
account 
 The trade-off methods is an option 
 NECB simplified is the easiest but not necessarily best 
 You need to have something to trade off with 
 Glazing ratio has the biggest impact and it is hard to make up for it with 
insulation
EFFECTIVE R VALUES
CONSIDERING THERMAL BRIDGING 
Computer Modeling 
Hand Calculations 
 Series calculation method 
 Parallel path calculation method 
 Isothermal planes method 
Lab Measurement 
48
ACCEPTABLE CALCULATION METHODS 
49 
Construction Classes 
Testing or 
Modeling 
Series 
calculation 
method 
Parallel path 
calculation 
method 
Isothermal 
planes 
method 
Roofs 
Insulation above deck P P 
Attic (wood joists) P P 
Attic (steel joists) P P 
Walls 
Mass P P 
Steel framed P P 
Wood framed P P
WHERE TO FIND INFORMATION 
50 
Resource material 
ASHRAE 90.1 
Appendix A
TABLES –WOOD FRAMED WALLS 
51
TABLES – STEEL FRAMED WALLS 
52
TABLES – MASS WALLS 
53 
If adding steel studs 
with Batt , table 9.2B 
can be used (as per 
previous)
AREA WEIGHTED AVERAGE (SAME CLASS) 
54 
R1.25 for 9” slab edge 
R15 for 8’3” wall 
1 
푅 
= 
0.75 × 1 
1.25 + 8.25 × 1 
15 
9 
푅 ≅ 7.8
L2,par 
apet 
Lro 
of 
HEAT LOSS 
55
3D MODELING 
 Time-transient dynamic 3D heat 
56 
transfer model that is capable of 
accurately modeling: 
 Complex geometries 
 Radiation through air spaces 
 Radiation to the interior and 
exterior space 
 Conduction of small areas of highly 
thermal conductive materials 
through larger areas of highly 
insulating materials 
 Calibrate the model using existing lab 
testing
COMMON CONSTRUCTION 
57
COMMON CONSTRUCTION DETAILS 
58
CLADDING ATTACHMENTS 
Horizontal Vertical Z-Girts Z-Girts Mixed Z-Girts Intermittent Z-Girts 
59
EFFECT OF THERMAL BRIDGING IN 3D 
60 
NECB 2011 
ASHRAE 90.1 
2010 
* Assembly does not include 
any interior insulation but the 
wall cavity and different 
materials offer additional 
insulating value. 
*
IMPROVED GIRT SYSTEMS 
61
CLIP SYSTEMS 
62
Spray Foam 
GLAZING SPANDREL AREAS 
63 
No Spray Foam
GLAZING SPANDREL AREAS 
3.4 
4.2 
4.8 5.0 
7.4 
8.2 
8.8 9.1 
10 
9 
8 
7 
6 
5 
4 
3 
2 
1 
0 
0 5 10 15 20 25 30 
Spandrel Section R Value 
Back Pan Insulation 
Detail 22 (Air in Stud Cavity) Detail 23 (Spray Foam in Stud Cavity) 
64
CONCRETEWALLS 
65 
≈ ≈
CONCRETE WALLS 
66
CONSIDERING THERMAL BRIDGING 
67 
Resource 
material 
Building 
Envelope 
Thermal Bridging 
Guide
BE THERMAL BRIDGING GUIDE 
 ASHRAE 90.1 does not 
68 
address major thermal 
bridges such as slab 
edges, shelf angles, 
parapets, flashings at 
window perimeters, etc. 
 In practice, these details 
are largely overlooked.
WHAT IS THE GUIDE 
69 
 Started with AHSRAE 1635RP project 
when linear transmittance got 
introduced to North America 
 BE Thermal Guide looked at over 400 
details familiar to the BC MURB market 
including:
CONCEPTUAL LEAP 
70 
Types of Transmittances 
Clear Field Linear Point 
o   U 
psi chi
LINEAR TRANSMITTANCE 
71 
oQ Q sla b Q 
Additional heat loss 
due to the slab
OVERVIEW OF THE GUIDE 
72 
 Introduction 
 Part 1 Building Envelope Thermal Analysis 
(BETA) Guide 
 Part 2 Energy and Cost Analysis 
 Part 3 Significance, Insights, and Next Steps 
 Appendix A Material Data Catalogue 
 Appendix B Thermal Data Catalogue 
 Appendix C Energy Modeling Analysis and Results 
 Appendix D Construction Costs 
 Appendix E Cost Benefit Analysis
RESULTS – APPENDIX B 
73
FROM BAD TO BETTER 
74
HOW MUCH EXTRA LOST CAN DETAILS ADD? 
 Standard 90.1 Prescriptive Requirements for Zone 5 Non- 
75 
Residential 
 Mass Wall, U-0.090 or R-11.4 ci 
 Steel-Framed Wall, U-0.064 or R-13 + R-7.5 ci 
Mass wall with R-12 insulation inboard Steel stud with R-10 exterior insulation and horizontal 
girts at 24”o.c and R-12 in the stud cavity
EXAMPLE BUILDING 
 Mass Concrete Wall 
76 
 Exposed concrete slab 
 Un-insulated concrete parapet 
 Punched window in concrete 
opening 
 Steel-Framed Wall 
 Exterior insulated structural steel 
floor intersection 
 Insulated steel stud parapet 
 Punched window in steel stud 
opening with perimeter flashing 
 10 floors 
 20% glazing 
 No Balconies 
 Standard details
IMPACT OF DETAILS 
Transmittance Type 
77 
Mass Concrete Wall Exterior Insulated Steel Stud 
Heat Loss 
(BTU/hr oF) 
% of Total 
Heat Loss 
(BTU/hr oF) 
% of Total 
Clear Wall 118 52 % 98 67 % 
Slab 92 40% 24 17 % 
Parapet 9 4% 4 3 % 
Window transition 8 4% 19 13 % 
Total 227 100 % 145 100 %
IMPACT OF DETAILS 
Performance Metric 
78 
Mass Concrete Wall Exterior Insulated Steel Stud 
ASHRAE 
Prescriptive 
Requirements 
Overall 
Performance 
ASHRAE 
Prescriptive 
Requirements 
Overall 
Performance 
U 
(Btu/hrft2oF) 
0.09 0.14 0.064 0.091 
“Effective” R 
(hr ft2 oF/BTU) 
R-11 R-7 R-15.6 R-11 
% Difference 44% 35%
IMPACT OF DETAILS 
79 
0.14 
0.12 
0.1 
0.08 
0.06 
0.04 
0.02 
0 
Additional Contribution to Space Heating Energy (GJ/m2 of Floor Area) 
Clear Wall Only Including Poor Details Including Efficient Details 
Details can 
have a 
greater 
impact 
More 
Insulation is 
not the silver 
bullet
CONCLUSION 
 Details such as slab 
80 
penetration are easy to 
account for in calculation 
 Codes do not yet take into 
account details such as 
window transitions 
 It will likely become 
increasingly more difficult to 
ignore thermal bridging at 
intersections of assemblies 
 Move beyond simply adding 
“more insulation”
MORRISON HERSHFIELD 
CORPORATE PROFILE 
PRESENTER AND CONTACT 
SOPHIE MERCIER, P.ENG. 
smercier@morrisonhershfield.com 
604.454.2020
CORPORATE OVERVIEW 
 Established in 1946 
 MHGI = MHL + MHC 
 Technical divisions 
 16 offices across North America 
 Over 750 employees 
Our Vision 
To be the first call for engineering 
solutions that make a difference 
82
MORRISON HERSHFIELD GROUP INC. 
83 
Morrison Hershfield Limited 
Canada (580 staff) 
Technical Divisions: 
 Buildings & Facilities 
 Infrastructure & Transportation 
 Industrial 
Offices: 
 Vancouver, Victoria & Nanaimo, BC 
 Calgary and Edmonton AB 
 Toronto, Burlington and 
Ottawa ON 
 St. John’s, NL
MORRISON HERSHFIELD GROUP INC. 
Morrison Hershfield Corporation 
84 
USA (120 staff) 
Technical Divisions: 
 Telecommunications 
 Buildings & Facilities 
Offices: 
 Atlanta GA 
 San Francisco CA 
 Portland and Seattle OR 
 Fort Lauderdale FL 
 Raleigh NC
DIVISIONAL PROFILE - CANADA 
85 
Infrastructure & Transportation 
 Roads & Highways 
 Rail & Transit 
 Transportation Structures 
 Airport Development 
 Water & Wastewater 
Buildings & Facilities 
 Building Envelope 
 Mechanical / Electrical / Structural 
Design 
 Fire Protection & Life Safety 
 Facility Assessment 
 LEED & Sustainability 
 Life Sciences 
Industrial 
 Telecommunications 
 Data Centers 
 Oil & Gas 
 Power 
 Forestry 
Integrated 
Multi-Disciplinary Bundles 
 Public Private Partnerships 
(MHP) 
 Public Sector Projects 
 Private Sector Projects 
 Asset / Facility Managers 
 Green / Sustainability (MH 
Green) 
 Energy 
 Water and Wastewater
BUILDINGS & FACILTIIES 
Building Envelope 
 Condition Assessments / Testing 
 Failure Analysis 
 Design Development, New & Remedial 
 Research & Development 
 Investigation of Materials & Systems Performance 
 Expert Engineering Advice 
Facility Assessment & Management Planning 
 Facility Condition Reviews & Technical Audits 
 Maintenance Plans & Reserve Funds 
 Due Diligence Evaluations 
Life Sciences 
 Laboratories, Pharmaceutical, Vivaria 
 Healthcare and Wellness 
LEED & Sustainability 
 LEED Consulting 
 Life Expectancy / Life Cycle Analysis 
 Materials / Equipment Selection 
 Design Review & Analysis 
86 
Mechanical / Electrical / Structural Design 
 Concept, Detailed Design 
 Condition Assessments 
 Building Automation 
 Electrical Cogeneration 
 Utilities Master Plans 
 Project Procurement / Tender Support 
 Energy Management 
Fire Protection & Life Safety 
 Fire Protection Systems Design 
 Code Consulting 
 Plan Reviews & Inspections 
 Hazard Evaluations
TRANSPORTATION 
Roads & Highways 
 Feasibility & Conceptual Design Studies 
 Functional Planning & Detailed Design 
 Traffic Modeling and Demand Forecasting 
 Environmental Assessments and Public Consultation 
 Construction Administration & Supervision 
Rail & Transit 
 Planning & Development 
 Implementation & Operations 
 Detailed Design 
 Construction Management 
Airport Development 
 Area Development Planning & Feasibility Studies 
 Contract Administration & Construction Supervision 
 Testing & Commissioning 
 Renewals Planning 
87 
Transportation Structures 
 Conceptual, Preliminary & Detailed Design 
 Restoration, Rehabilitation & Repair 
 Cost / Benefit, Life Cycle & Constructability Analysis 
 Bridge Inspections and Condition Surveys 
 Contract Administration & Construction Inspection
INFRASTRUCTURE 
88 
Water & Waste Water 
 Feasibility Studies, Pre-Design & Detailed Design 
 Plant System Improvements 
 Resident engineering 
 Quality Control & Commissioning 
Land Development 
 Residential, Industrial and Commercial 
 Institutional 
 Golf Course Engineering 
 Resort Development Engineering 
Environment 
 Environmental Planning 
 Natural Sciences
INDUSTRIAL 
89 
Telecom 
 Wireless 
 Wireline 
 Cable 
 Broadcast 
 Private Radio 
Data Centers 
 Internet Data Centers 
 Enterprise Data Centers 
 Municipalities, Universities, 
Schools & Health Care 
Oil & Gas 
 Oil Sands 
 Refineries 
 Petrochemical Plants 
 Secondary Manufacturing 
Facilities 
 Specialty Service Complexes 
Power 
 Primary Generation & Cogeneration 
Plants 
 Distributed Power Generation 
 Overhead & Underground Power 
Distribution 
 Switch Gear & Transformer Yard 
Development 
Forestry 
 Log Yards, Green Lumber & 
Finished Lumber Yards 
 OSB Mills 
 Pulp Mills 
 Saw Mills 
 Specialty Facilities
SUSTAINABILITY 
The Challenge 
Sustainability is a top priority. Our collective challenge is to 
significantly reduce our impact on the local and global environment and 
begin to rebuild our natural capital in an economically and socially 
responsible manner. 
Our Commitment 
To help clients understand 
their environmental challenges 
and to incorporate sustainable 
design solutions to help them 
meet these challenges. 
90
THANK YOU 
morrisonhershfield.com

Contenu connexe

Tendances

Tendances (20)

Renzo piano
Renzo pianoRenzo piano
Renzo piano
 
NARI GANDHI
NARI GANDHINARI GANDHI
NARI GANDHI
 
Disney Concert Hall - Frank Gehry
Disney Concert Hall - Frank GehryDisney Concert Hall - Frank Gehry
Disney Concert Hall - Frank Gehry
 
Kessaku Phoenix
Kessaku PhoenixKessaku Phoenix
Kessaku Phoenix
 
Literature study Hostels
Literature study HostelsLiterature study Hostels
Literature study Hostels
 
Report on High Rise
Report on High RiseReport on High Rise
Report on High Rise
 
ARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAK
ARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAKARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAK
ARCHITECTURAL DESIGN- A Magnificent Memorial-PADAYARTI SMARAK
 
WALT DISNEY CONCERT HALL
WALT DISNEY CONCERT HALLWALT DISNEY CONCERT HALL
WALT DISNEY CONCERT HALL
 
Long Span Building Construction
Long Span Building ConstructionLong Span Building Construction
Long Span Building Construction
 
Nari gandhi
Nari gandhiNari gandhi
Nari gandhi
 
GRIHA Presentation
GRIHA Presentation GRIHA Presentation
GRIHA Presentation
 
Commerzbank headquarters
Commerzbank headquartersCommerzbank headquarters
Commerzbank headquarters
 
John F Kennedy Centre for Performing Arts-Washington DC
John F Kennedy Centre for Performing Arts-Washington DCJohn F Kennedy Centre for Performing Arts-Washington DC
John F Kennedy Centre for Performing Arts-Washington DC
 
A Presentation on GRIHA
A Presentation on GRIHA A Presentation on GRIHA
A Presentation on GRIHA
 
Passive Architecture Case Examples
Passive Architecture Case ExamplesPassive Architecture Case Examples
Passive Architecture Case Examples
 
Instacon tower mohali
Instacon tower mohaliInstacon tower mohali
Instacon tower mohali
 
Literature Study on sports pavilion
Literature Study on sports pavilionLiterature Study on sports pavilion
Literature Study on sports pavilion
 
YMCA Camp Lakeside
YMCA Camp Lakeside YMCA Camp Lakeside
YMCA Camp Lakeside
 
Energy efficient hotel
Energy efficient hotelEnergy efficient hotel
Energy efficient hotel
 
Green skyscraper's
Green skyscraper'sGreen skyscraper's
Green skyscraper's
 

En vedette

Building emvelopes and thermal mass walls
Building emvelopes and thermal mass wallsBuilding emvelopes and thermal mass walls
Building emvelopes and thermal mass walls
nuform
 

En vedette (20)

AIA Chicago Presentation
AIA Chicago PresentationAIA Chicago Presentation
AIA Chicago Presentation
 
ZERO ENERGY BUILDING ENVELOPE COMPONENTS
ZERO ENERGY BUILDING ENVELOPE COMPONENTSZERO ENERGY BUILDING ENVELOPE COMPONENTS
ZERO ENERGY BUILDING ENVELOPE COMPONENTS
 
Necb discussion-document
Necb discussion-documentNecb discussion-document
Necb discussion-document
 
Adoption and Compliance with Energy Codes: ASHRAE 90.1 and NECB
Adoption and Compliance with Energy Codes: ASHRAE 90.1 and NECBAdoption and Compliance with Energy Codes: ASHRAE 90.1 and NECB
Adoption and Compliance with Energy Codes: ASHRAE 90.1 and NECB
 
National Energy Code for Buildings
National Energy Code for BuildingsNational Energy Code for Buildings
National Energy Code for Buildings
 
Building emvelopes and thermal mass walls
Building emvelopes and thermal mass wallsBuilding emvelopes and thermal mass walls
Building emvelopes and thermal mass walls
 
Re-glazing of an All Glass Tower
Re-glazing of an All Glass TowerRe-glazing of an All Glass Tower
Re-glazing of an All Glass Tower
 
High Performance Walls - Solutions for Thermal Bridging
High Performance Walls - Solutions for Thermal BridgingHigh Performance Walls - Solutions for Thermal Bridging
High Performance Walls - Solutions for Thermal Bridging
 
Conform for residential
Conform for residentialConform for residential
Conform for residential
 
Carbon Neutral Apartment Retrofits
Carbon Neutral Apartment RetrofitsCarbon Neutral Apartment Retrofits
Carbon Neutral Apartment Retrofits
 
Thermal performance of concrete masonry
Thermal performance of concrete masonryThermal performance of concrete masonry
Thermal performance of concrete masonry
 
Adoption and Compliance with Canadian Energy Codes - Lessons from BC
Adoption and Compliance with Canadian Energy Codes - Lessons from BCAdoption and Compliance with Canadian Energy Codes - Lessons from BC
Adoption and Compliance with Canadian Energy Codes - Lessons from BC
 
Optimizing Concrete Thermal Bridges - Balcony and Slab Edge Thermal Breaks
Optimizing Concrete Thermal Bridges - Balcony and Slab Edge Thermal BreaksOptimizing Concrete Thermal Bridges - Balcony and Slab Edge Thermal Breaks
Optimizing Concrete Thermal Bridges - Balcony and Slab Edge Thermal Breaks
 
Building the Future: Net Zero and Net Zero Ready
Building the Future: Net Zero and Net Zero ReadyBuilding the Future: Net Zero and Net Zero Ready
Building the Future: Net Zero and Net Zero Ready
 
TEMP. CONTROL
TEMP. CONTROLTEMP. CONTROL
TEMP. CONTROL
 
Transcript_Necb
Transcript_NecbTranscript_Necb
Transcript_Necb
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Air conditioning system
Air conditioning systemAir conditioning system
Air conditioning system
 
Asian architcture presentation slide (Billah)
Asian architcture presentation slide (Billah)Asian architcture presentation slide (Billah)
Asian architcture presentation slide (Billah)
 
Structural systems in high rise buildings
Structural systems in high rise buildingsStructural systems in high rise buildings
Structural systems in high rise buildings
 

Similaire à 2014 BCBC Envelope Compliance - ASHRAE 90.1 and NECB

Insulated metal panels edc1
Insulated metal panels edc1Insulated metal panels edc1
Insulated metal panels edc1
Derrick Teal
 
Moving Towards More Energy Efficient Wood Frame Building Enclosures
Moving Towards More Energy Efficient Wood Frame Building EnclosuresMoving Towards More Energy Efficient Wood Frame Building Enclosures
Moving Towards More Energy Efficient Wood Frame Building Enclosures
RDH Building Science
 

Similaire à 2014 BCBC Envelope Compliance - ASHRAE 90.1 and NECB (20)

Building Design Factors that Affect LEED Energy Credits
Building Design Factors that Affect LEED Energy CreditsBuilding Design Factors that Affect LEED Energy Credits
Building Design Factors that Affect LEED Energy Credits
 
Building Enclosures of the Future - Building Tomorrow's Buildings Today
Building Enclosures of the Future - Building Tomorrow's Buildings TodayBuilding Enclosures of the Future - Building Tomorrow's Buildings Today
Building Enclosures of the Future - Building Tomorrow's Buildings Today
 
New Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy PerformanceNew Code Requirements for Fenestration Energy Performance
New Code Requirements for Fenestration Energy Performance
 
IECC 2009 Training
IECC 2009 TrainingIECC 2009 Training
IECC 2009 Training
 
2009 IECC: Commercial
2009 IECC: Commercial2009 IECC: Commercial
2009 IECC: Commercial
 
2015 IECC Key Highlights & Updates
2015 IECC Key Highlights & Updates2015 IECC Key Highlights & Updates
2015 IECC Key Highlights & Updates
 
Insulated metal panels edc1
Insulated metal panels edc1Insulated metal panels edc1
Insulated metal panels edc1
 
360786862-Indice-de-Normas.pdf
360786862-Indice-de-Normas.pdf360786862-Indice-de-Normas.pdf
360786862-Indice-de-Normas.pdf
 
Energy Efficiency Ontario Building Code - Bob Bach - 2012
Energy Efficiency Ontario Building Code - Bob Bach - 2012Energy Efficiency Ontario Building Code - Bob Bach - 2012
Energy Efficiency Ontario Building Code - Bob Bach - 2012
 
Thermal Performance
Thermal PerformanceThermal Performance
Thermal Performance
 
Comparision of ASCE ASCE7-10 to ASCE7-16 Of Wind load
Comparision of ASCE ASCE7-10 to ASCE7-16 Of Wind loadComparision of ASCE ASCE7-10 to ASCE7-16 Of Wind load
Comparision of ASCE ASCE7-10 to ASCE7-16 Of Wind load
 
2009 IECC: Advanced
2009 IECC: Advanced2009 IECC: Advanced
2009 IECC: Advanced
 
Scroll compressors for propane (R290)
Scroll compressors for propane (R290)Scroll compressors for propane (R290)
Scroll compressors for propane (R290)
 
Technical specification EEE
Technical specification EEETechnical specification EEE
Technical specification EEE
 
What is ASHRAE 90.1?
What is ASHRAE 90.1?What is ASHRAE 90.1?
What is ASHRAE 90.1?
 
Bob Bach: Energy Efficiency in the Ontario Building Code
Bob Bach: Energy Efficiency in the Ontario Building CodeBob Bach: Energy Efficiency in the Ontario Building Code
Bob Bach: Energy Efficiency in the Ontario Building Code
 
2009 IECC: Residential Provisions
2009 IECC: Residential Provisions2009 IECC: Residential Provisions
2009 IECC: Residential Provisions
 
Integrative design working with your MEP
Integrative design working with your MEPIntegrative design working with your MEP
Integrative design working with your MEP
 
Integrative Design Working With Your MEP
Integrative Design Working With Your MEPIntegrative Design Working With Your MEP
Integrative Design Working With Your MEP
 
Moving Towards More Energy Efficient Wood Frame Building Enclosures
Moving Towards More Energy Efficient Wood Frame Building EnclosuresMoving Towards More Energy Efficient Wood Frame Building Enclosures
Moving Towards More Energy Efficient Wood Frame Building Enclosures
 

Dernier

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Victor Rentea
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 

Dernier (20)

FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Exploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with MilvusExploring Multimodal Embeddings with Milvus
Exploring Multimodal Embeddings with Milvus
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 

2014 BCBC Envelope Compliance - ASHRAE 90.1 and NECB

  • 1. October 8, 2014 Envelope Compliance ASHRAE 90.1 and NECB 2011
  • 2. OVERVIEW  Code requirements and the Standards  Broad overview of the Standards  ASHRAE 90.1 prescriptive requirements 2 and trade-off method for Envelope  NECB Prescriptive requirements and trade-off method for Envelope  Summary comparison of the prescriptive requirements and what it means in the BC building context  Looking at different methods of accounting for thermal bridging
  • 5. STANDARDS IN CODES 5 ASHRAE 90.1 2004 – Previous BCBC ASHRAE 90.1 2007 – Previous VBBL ASHRAE 90.1 2010 & NECB 2011 – Current BCBC and VBBL
  • 6. ASHRAE 90.1 2010 6 WHO ARE THEY? American Society of Heating Refrigeration and Air-conditioning Engineers WHAT IS THE STANDARD? First addition developed in 1970 In 1999 the standard was put into continuous maintenance Applies to all commercial buildings and MURBS greater than 3 stories.
  • 7. ASHRAE 90.1 OVERVIEW 7 ALTERNATIVE PATHS FOR COMPLIANCE Prescriptive Trade-off Energy cost budget PRESCRIPTIVE PATH (OR TRADE-OFF) REQUIRE THAT ALL PARTS OF THE STANDARD BE MET: Part 5 - Building envelope Part 6 - Heating, ventilating and air-conditioning Part 7 - Service water heating Part 8 - Power Part 9 - Lighting Mandatory Part 10 - Other equipment Provisions
  • 8. ASHRAE 90.1 OVERVIEW 8 ASHRAE 2004 Baseline ASHRAE 2007 Increased BE requirements ASHRAE 2010 No major changes in BE requirements
  • 9. NECB 2011  Developed by Natural Resources 9 Canada & the National Research Council for Canada  What is the Standard?  Last version was in 1997 (MNECB)  Design intent was to be roughly equivalent to ASHRAE 90.1 2010  Applies to new buildings (except part 9), additions to existing building, but silent on renovations  Before now, not referenced in BCBC or VBBL  MNECB is referenced in LEED
  • 10. NECB OVERVIEW 10 ALTERNATIVE PATHS FOR COMPLIANCE  Prescriptive  Trade-off (simple or detailed)  Energy simulation (building energy compliance) PRESCRIPTIVE PATH (OR TRADE-OFF) REQUIRE THAT ALL PARTS OF THE STANDARD BE MET:  Part 3 – Building envelope  Part 4 – Lighting  Part 5 – Heating, ventilating and air-conditioning systems  Part 6 – Service water heating systems  Part 7 – Electrical power systems and motors
  • 11. ZONES AND HEATING DEGREE DAYS (HDD) 11 ASHRAE 90.1 Climate zones for BC
  • 12. ZONES AND HEATING DEGREE DAYS (HDD) 12
  • 13. ASHRAE 90.1 2010 BUILDING ENVELOPE
  • 14. ASHRAE 90.1- BUILDING ENVELOPE 14
  • 15. ASHRAE 90.1- MANDATORY PROVISIONS THIS MEANS THAT THE BUILDING SHOULD BE DESIGNED TO MEET THESE PROVISIONS: Insulation Air leakage • Air-barrier selection and design • Limit to fenestration and doors including cargo doors • Vestibule Fenestration and Doors values • NFRC 15
  • 16. ASHRAE 90.1 MANDATORY PROVISIONS 16 ASHREA 90.1 Air leakage limits NAFS Air Leakage limits ASHRAE Type Limit Glazed Swinging entrance door & revolving doors 1.0 cfm/ft2 at 1.57psf Curtain wall & Storefront 0.06cfm/ft2 at 1.57psf Other products 0.2cfm/ft2 at 1.57psf or 0.3 cfm/ft2 at 6.24psf NAFS defines air leakage by performance class (R, LC, CW and AW) and air infiltration / exfiltration levels (A2, A3 and Fixed) and can be more stringent: Fixed as low as 0.2 L/s.m2 at 300Pa (or 0.04cfm/ft2 at 6.24psf) Operable as low as 0.5 L/s.m2 at 300Pa (or 0.1cfm/ft2 at 6.24psf)
  • 17. ASHRAE 90.1 PRESCRIPTIVE METHOD 17 THE PRESCRIPTIVE METHOD CAN ONLY BE USED IF: The vertical fenestration ≤ 40% of Gross wall Area The skylight fenestration ≤ 5% of gross roof area
  • 18. ASHRAE 90.1 - OPAQUE AREAS  For conditioned spaces the 18 exterior building envelope shall comply with, to either: the residential or the non-residential requirements in the tables  For semi-heated spaces the semi-exterior building envelope needs to comply with the requirements in the tables
  • 19. ASHRAE 90.1 - PRESCRIPTIVE OPAQUE AREAS 19 THE TABLES CONTAINING THE THERMAL PERFORMANCE REQUIREMENTS ARE PROVIDED IN THE STANDARD, BY CLIMATIC ZONES, AND LOOK LIKE THIS: For all opaque elements (except doors) compliance should be demonstrated by the following methods:  Maximum U-factors, C-factors or F-factors for the entire assembly  Minimum rated R values of insulation Exception: For multiple assemblies within a single class of construction for a single conditioning space, weighed average can be used.
  • 20. ASHRAE 90.1 PRESCRIPTIVE OPAQUE AREAS 20 Components Zone 5 Non-Residential Residential Semi-Heated U factor R value U factor R value U factor R value Roof - insulation above deck 0.048 (R20.8) 20.0c.i. 0.048 (R20.8) 20.0c.i. 0.119 (R8.4) 7.6c.i. Roof - Attic 0.027 (R37.0) 38.0 0.027 (R37.0) 38.0 0.053 (R18.9) 19.0 Walls - Mass 0.090 (R11.1) 11.4c.i. 0.080 (R12.5) 13.3c.i. 0.151 (R6.6) 5.7c.i. Walls - Steel framed 0.064 (R15.6) 13.0+7.5c.i. 0.064 (R15.6) 13.0+7.5c.i. 0.124 (R8.1) 13.0 Walls - Wood framed 0.064 (R15.6) 13.0+3.8c.i. 0.051 (R19.6) 13.0+7.5c.i. 0.089 (R11.2) 13.0
  • 21. ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 21 SO THAT MEANS:  If there is more than nails or screws going through the insulation, it is not continuous  If there are studs, girts, clips, even brick ties they need to be accounted for.  This can be done by calculating the effective U (or R) values of these assemblies
  • 22. ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 22 NOMINAL R VALUES Rated R values which do not take into account framing or other element interrupting the insulation vs. EFFECTIVE R VALUES Calculated R values which allows for the impact of thermal bridges
  • 23. ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 23 Zone 4&5 = 0.064
  • 24. ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 24 Zone 4 = 0.064 Zone 5 = 0.051
  • 25. ASHRAE 90.1 PRESCRIPTIVE - OPAQUE AREAS 25 Components Residential R values Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 Roof - insulation above deck 20.0c.i. 20.0c.i. 20.0c.i. 20.0c.i. 20.0c.i. Roof - Attic 38.0 38.0 38.0 38.0 49.0 Walls - Mass 11.4c.i. 13.3c.i. 15.2c.i. 15.2c.i. 25.0c.i. Walls - Steel framed 13.0+7.5c.i. 13.0+7.5c.i. 13.0+7.5c.i. 13.0+15.6c.i. 13.0+18.8c.i. Walls - Wood framed 13.0+3.8c.i. 13.0+7.5c.i. 13.0+7.5c.i. 13.0+7.5c.i. 13.0+15.6c.i.
  • 26. ASHRAE 90.1 PRESCRIPTIVE - FENESTRATION Windows <40% of gross wall area and Skylights <5% gross roof area 26 All fenestration compliance shall be demonstrated through meeting: • U factor no greater than the prescriptive requirements • SHGC no greater than the prescriptive requirements If there are multiple assemblies, compliance shall be based on an area-weighted average U-factor or SHGC (for a single space-conditioning and within a single class of construction). The SHGC can be reduced using a multiplier when a permanent projection provides shading for the window
  • 27. ASHRAE 90.1 PRESCRIPTIVE - FENESTRATION 27 Components Zone 5 Residential Non-Residential Semi-Heated U factor SHGC U factor SHGC U factor SHGC Non-Metal Framing 0.35 0.40 for all 0.35 0.40 for all 1.20 0.40 for all Metal Framing (curtain wall and storefront) 0.45 0.45 1.20 Metal Framing (entrance doors) 0.80 0.80 1.20 Metal Framing (operable and fixed windows, non-entrance doors) 0.55 0.55 1.20 Skylight (glass, without curb) 0-2% 0.69 0.49 0.69 0.49 1.36 NR 2-5% 0.39 0.39 NR
  • 28. ASHRAE 90.1 TRADE-OFF 28 The trade-off method allows greater flexibility when some of the building envelope components are not meeting: • The basic requirements for the Prescriptive method (e.g. > 40% window to wall ratio and/or >5% skylight to roof ratio) • The prescriptive R or U values • Trade-offs are made between any building envelope components (but just building envelope component) • It implies that some of the building envelope components exceed the minimum requirements • Schedules of operation, lighting power, equipment power, occupant density, and mechanical systems need to be the same for both the proposed building and the base building
  • 29. ASHRAE 90.1 TRADE-OFF 29 THE BUILDING ENVELOPE COMPLIES WHEN: Envelope performance factor of proposed building Envelope performance factor of base building ≤ The base building is a building that has 40% fenestration to gross wall area and for which all BE components meet the prescriptive minimum U value The envelope performance factor is calculated using the information contained in normative appendix C
  • 30. ASHRAE 90.1 TRADE-OFF 30 Need to :  Do take-offs for all the different BE components i.e. floor, roof, wall and fenestration assemblies for every space-conditioning category and every orientation.  Evaluate the U values of each component including SHGC and VT for fenestration.  Enter all the numbers into a series of equations that you can find in normative Appendix C*. COMcheck * (Now has Canadian climate data). Axis – Raymond Letkeman Architects
  • 33. NECB 2011 BUILDING ENVELOPE
  • 35. NECB - MANDATORY PROVISIONS 35 NO SPECIFIC MANDATORY PROVISIONS But more specific than ASHRAE on how to deal with effect of structural members that may partially and completely penetrate the envelope In the prescriptive requirements, we find that : Insulation should be installed in a manner that avoids affecting its R value (convection, wetting, etc.). Insulation value required depends on zone, assembly (wall, roof or floor) and location (above or below grade or spaces heated to different temperature) Air leakage should be controlled, including at fenestration and doors, which have limits of air leakage allowable A vestibule is likely required
  • 36. NECB - PRESCRIPTIVE METHOD THE PRESCRIPTIVE METHOD CAN ONLY 36 BE USED IF: FDWR ≤ 0.40 for HDD < 4000 FDWR ≤(2000- 0.2*HDD) 3000 for 4000 ≤ HDD ≤ 7000 FDWR ≤ 0.20 for HDD > 7000 & The skylight fenestration ≤ 5% of gross roof area
  • 37. NECB - THERMAL BRIDGING THERMAL BRIDGING 37 CREATED BY STRUCTURAL MEMBERS The thermal bridging effect of closely spaced repetitive structural members (e.g. studs) and of ancillary members (e.g. sill and plates) should be taken into account. The thermal bridging of major structural elements that are parallel to the building envelope can be ignored, provided that they do not increase the thermal transmittance to more than twice than permitted. The thermal bridging of major structural elements that must penetrate the building envelope need not be taken into account, provided that the sum of the areas is less than 2% of the above ground building envelope. Service equipment, shelf angle, ties and associate fasteners as well as minor structural members need not be taken into account!!!
  • 38. NECB PRESCRIPTIVE INSULATION 38 The prescriptive method requires: 4xW W W 4xW
  • 39. NECB PRESCRIPTIVEWALLS ABOVE GRADE  No difference between residential and non-residential  No difference between the different type of construction 39 Assemblies Any Occupancy R values (effective) Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 Walls 18 20.4 23 27 31 Roofs 25 31 31 35 40 Floors 25 31 31 35 40 Walls - mass 11.4 Walls - steel framed 15.6 Walls - wood framed 19.6 Roofs - insulation above 20.8 Roofs - attic 37.0
  • 40. NECB PRESCRIPTIVE FENESTRATION AND DOORS 40 Components U values (effective) Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 All Fenestration 0.42 0.39 0.39 0.39 0.28 All Doors 0.42 0.39 0.39 0.39 0.28  No difference between residential and non-residential  No difference between the different type of assemblies  No SHGC requirements  Exceptions:  Skylights that represent < 2% of gross roof area can have a thermal transmittance of no more than 0.60  Doors that represent < 2% of gross wall area can have a thermal transmittance of no more than 0.77 Non-metal 0.35 Metal framing (CW) 0.45 Metal framing (others) 0.55 Entrance doors 0.80 Skylights 0.58
  • 41. NECB - PRESCRIPTIVE METHOD 41
  • 42. NECB - TRADE-OFF METHODS 42 THERE ARE 2 TRADE-OFF PATHS: Simple trade-off calculations Detailed trade-off path Proposed Bldg Envelope Annual Energy Consumption Reference Bldg Envelope energy target ≤ Calculation are done using an energy model with set requirements ≤ Proposed building Reference building
  • 43. NECB - DETAILED TRADE-OFF METHOD THE DETAILED METHOD CONSISTS OF: 43 Same building size and shape, roof slope, and building orientation for the proposed and reference building Same assumptions for space heating and cooling Allowable fenestration and door areas in the proposed building can be varied, while it is set per the prescriptive requirements in the reference building Take into account thermal mass and SHGC Air leakage and solar absorbance cannot be varied
  • 44. COMPARISON OF 2 STANDARDS 44 ASHRAE 90.1 2010 NECB 2011 Mandatory requirements Yes, for all methods Not for energy modeling Prescriptive requirements Generally less demanding R values Stringent, specific • Framing Take into account Take into account • Structure Not clear Specific (if this then…) • Cladding attachments Take into account Some can be ignored • Service penetrations Ignore Specific (if this then…) • Walls More categories Less categories • Fenestration & doors More categories Less categories Trade-off methods Complex, no benefit if FDWR <40% Simple or software Benefit if FDWR <40%
  • 45. OVERALL 45 Prescriptive method, for either standard, is for simpler buildings Trade-off method may get you the desired result, but cannot do anything for you when most of the BE components are below
  • 46. CONCLUSION REGARDING THE STANDARDS  Wood frame is well suited for prescriptive but: 46  New standards will generally require exterior insulation to meet the max U-factor with 2x6 residential  Only zone 4 in ASHRAE (but not in NEBC) could do without exterior insulation in residential  For non-combustible building, the prescriptive method is not a likely candidate  This is especially true for exposed concrete tower and buildings with high window/wall ratio  Exterior insulated assemblies can probably meet it but structure penetrating through (balcony slabs, parapet, etc.) need to be taken into account  The trade-off methods is an option  NECB simplified is the easiest but not necessarily best  You need to have something to trade off with  Glazing ratio has the biggest impact and it is hard to make up for it with insulation
  • 48. CONSIDERING THERMAL BRIDGING Computer Modeling Hand Calculations  Series calculation method  Parallel path calculation method  Isothermal planes method Lab Measurement 48
  • 49. ACCEPTABLE CALCULATION METHODS 49 Construction Classes Testing or Modeling Series calculation method Parallel path calculation method Isothermal planes method Roofs Insulation above deck P P Attic (wood joists) P P Attic (steel joists) P P Walls Mass P P Steel framed P P Wood framed P P
  • 50. WHERE TO FIND INFORMATION 50 Resource material ASHRAE 90.1 Appendix A
  • 52. TABLES – STEEL FRAMED WALLS 52
  • 53. TABLES – MASS WALLS 53 If adding steel studs with Batt , table 9.2B can be used (as per previous)
  • 54. AREA WEIGHTED AVERAGE (SAME CLASS) 54 R1.25 for 9” slab edge R15 for 8’3” wall 1 푅 = 0.75 × 1 1.25 + 8.25 × 1 15 9 푅 ≅ 7.8
  • 55. L2,par apet Lro of HEAT LOSS 55
  • 56. 3D MODELING  Time-transient dynamic 3D heat 56 transfer model that is capable of accurately modeling:  Complex geometries  Radiation through air spaces  Radiation to the interior and exterior space  Conduction of small areas of highly thermal conductive materials through larger areas of highly insulating materials  Calibrate the model using existing lab testing
  • 59. CLADDING ATTACHMENTS Horizontal Vertical Z-Girts Z-Girts Mixed Z-Girts Intermittent Z-Girts 59
  • 60. EFFECT OF THERMAL BRIDGING IN 3D 60 NECB 2011 ASHRAE 90.1 2010 * Assembly does not include any interior insulation but the wall cavity and different materials offer additional insulating value. *
  • 63. Spray Foam GLAZING SPANDREL AREAS 63 No Spray Foam
  • 64. GLAZING SPANDREL AREAS 3.4 4.2 4.8 5.0 7.4 8.2 8.8 9.1 10 9 8 7 6 5 4 3 2 1 0 0 5 10 15 20 25 30 Spandrel Section R Value Back Pan Insulation Detail 22 (Air in Stud Cavity) Detail 23 (Spray Foam in Stud Cavity) 64
  • 67. CONSIDERING THERMAL BRIDGING 67 Resource material Building Envelope Thermal Bridging Guide
  • 68. BE THERMAL BRIDGING GUIDE  ASHRAE 90.1 does not 68 address major thermal bridges such as slab edges, shelf angles, parapets, flashings at window perimeters, etc.  In practice, these details are largely overlooked.
  • 69. WHAT IS THE GUIDE 69  Started with AHSRAE 1635RP project when linear transmittance got introduced to North America  BE Thermal Guide looked at over 400 details familiar to the BC MURB market including:
  • 70. CONCEPTUAL LEAP 70 Types of Transmittances Clear Field Linear Point o   U psi chi
  • 71. LINEAR TRANSMITTANCE 71 oQ Q sla b Q Additional heat loss due to the slab
  • 72. OVERVIEW OF THE GUIDE 72  Introduction  Part 1 Building Envelope Thermal Analysis (BETA) Guide  Part 2 Energy and Cost Analysis  Part 3 Significance, Insights, and Next Steps  Appendix A Material Data Catalogue  Appendix B Thermal Data Catalogue  Appendix C Energy Modeling Analysis and Results  Appendix D Construction Costs  Appendix E Cost Benefit Analysis
  • 74. FROM BAD TO BETTER 74
  • 75. HOW MUCH EXTRA LOST CAN DETAILS ADD?  Standard 90.1 Prescriptive Requirements for Zone 5 Non- 75 Residential  Mass Wall, U-0.090 or R-11.4 ci  Steel-Framed Wall, U-0.064 or R-13 + R-7.5 ci Mass wall with R-12 insulation inboard Steel stud with R-10 exterior insulation and horizontal girts at 24”o.c and R-12 in the stud cavity
  • 76. EXAMPLE BUILDING  Mass Concrete Wall 76  Exposed concrete slab  Un-insulated concrete parapet  Punched window in concrete opening  Steel-Framed Wall  Exterior insulated structural steel floor intersection  Insulated steel stud parapet  Punched window in steel stud opening with perimeter flashing  10 floors  20% glazing  No Balconies  Standard details
  • 77. IMPACT OF DETAILS Transmittance Type 77 Mass Concrete Wall Exterior Insulated Steel Stud Heat Loss (BTU/hr oF) % of Total Heat Loss (BTU/hr oF) % of Total Clear Wall 118 52 % 98 67 % Slab 92 40% 24 17 % Parapet 9 4% 4 3 % Window transition 8 4% 19 13 % Total 227 100 % 145 100 %
  • 78. IMPACT OF DETAILS Performance Metric 78 Mass Concrete Wall Exterior Insulated Steel Stud ASHRAE Prescriptive Requirements Overall Performance ASHRAE Prescriptive Requirements Overall Performance U (Btu/hrft2oF) 0.09 0.14 0.064 0.091 “Effective” R (hr ft2 oF/BTU) R-11 R-7 R-15.6 R-11 % Difference 44% 35%
  • 79. IMPACT OF DETAILS 79 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 Additional Contribution to Space Heating Energy (GJ/m2 of Floor Area) Clear Wall Only Including Poor Details Including Efficient Details Details can have a greater impact More Insulation is not the silver bullet
  • 80. CONCLUSION  Details such as slab 80 penetration are easy to account for in calculation  Codes do not yet take into account details such as window transitions  It will likely become increasingly more difficult to ignore thermal bridging at intersections of assemblies  Move beyond simply adding “more insulation”
  • 81. MORRISON HERSHFIELD CORPORATE PROFILE PRESENTER AND CONTACT SOPHIE MERCIER, P.ENG. smercier@morrisonhershfield.com 604.454.2020
  • 82. CORPORATE OVERVIEW  Established in 1946  MHGI = MHL + MHC  Technical divisions  16 offices across North America  Over 750 employees Our Vision To be the first call for engineering solutions that make a difference 82
  • 83. MORRISON HERSHFIELD GROUP INC. 83 Morrison Hershfield Limited Canada (580 staff) Technical Divisions:  Buildings & Facilities  Infrastructure & Transportation  Industrial Offices:  Vancouver, Victoria & Nanaimo, BC  Calgary and Edmonton AB  Toronto, Burlington and Ottawa ON  St. John’s, NL
  • 84. MORRISON HERSHFIELD GROUP INC. Morrison Hershfield Corporation 84 USA (120 staff) Technical Divisions:  Telecommunications  Buildings & Facilities Offices:  Atlanta GA  San Francisco CA  Portland and Seattle OR  Fort Lauderdale FL  Raleigh NC
  • 85. DIVISIONAL PROFILE - CANADA 85 Infrastructure & Transportation  Roads & Highways  Rail & Transit  Transportation Structures  Airport Development  Water & Wastewater Buildings & Facilities  Building Envelope  Mechanical / Electrical / Structural Design  Fire Protection & Life Safety  Facility Assessment  LEED & Sustainability  Life Sciences Industrial  Telecommunications  Data Centers  Oil & Gas  Power  Forestry Integrated Multi-Disciplinary Bundles  Public Private Partnerships (MHP)  Public Sector Projects  Private Sector Projects  Asset / Facility Managers  Green / Sustainability (MH Green)  Energy  Water and Wastewater
  • 86. BUILDINGS & FACILTIIES Building Envelope  Condition Assessments / Testing  Failure Analysis  Design Development, New & Remedial  Research & Development  Investigation of Materials & Systems Performance  Expert Engineering Advice Facility Assessment & Management Planning  Facility Condition Reviews & Technical Audits  Maintenance Plans & Reserve Funds  Due Diligence Evaluations Life Sciences  Laboratories, Pharmaceutical, Vivaria  Healthcare and Wellness LEED & Sustainability  LEED Consulting  Life Expectancy / Life Cycle Analysis  Materials / Equipment Selection  Design Review & Analysis 86 Mechanical / Electrical / Structural Design  Concept, Detailed Design  Condition Assessments  Building Automation  Electrical Cogeneration  Utilities Master Plans  Project Procurement / Tender Support  Energy Management Fire Protection & Life Safety  Fire Protection Systems Design  Code Consulting  Plan Reviews & Inspections  Hazard Evaluations
  • 87. TRANSPORTATION Roads & Highways  Feasibility & Conceptual Design Studies  Functional Planning & Detailed Design  Traffic Modeling and Demand Forecasting  Environmental Assessments and Public Consultation  Construction Administration & Supervision Rail & Transit  Planning & Development  Implementation & Operations  Detailed Design  Construction Management Airport Development  Area Development Planning & Feasibility Studies  Contract Administration & Construction Supervision  Testing & Commissioning  Renewals Planning 87 Transportation Structures  Conceptual, Preliminary & Detailed Design  Restoration, Rehabilitation & Repair  Cost / Benefit, Life Cycle & Constructability Analysis  Bridge Inspections and Condition Surveys  Contract Administration & Construction Inspection
  • 88. INFRASTRUCTURE 88 Water & Waste Water  Feasibility Studies, Pre-Design & Detailed Design  Plant System Improvements  Resident engineering  Quality Control & Commissioning Land Development  Residential, Industrial and Commercial  Institutional  Golf Course Engineering  Resort Development Engineering Environment  Environmental Planning  Natural Sciences
  • 89. INDUSTRIAL 89 Telecom  Wireless  Wireline  Cable  Broadcast  Private Radio Data Centers  Internet Data Centers  Enterprise Data Centers  Municipalities, Universities, Schools & Health Care Oil & Gas  Oil Sands  Refineries  Petrochemical Plants  Secondary Manufacturing Facilities  Specialty Service Complexes Power  Primary Generation & Cogeneration Plants  Distributed Power Generation  Overhead & Underground Power Distribution  Switch Gear & Transformer Yard Development Forestry  Log Yards, Green Lumber & Finished Lumber Yards  OSB Mills  Pulp Mills  Saw Mills  Specialty Facilities
  • 90. SUSTAINABILITY The Challenge Sustainability is a top priority. Our collective challenge is to significantly reduce our impact on the local and global environment and begin to rebuild our natural capital in an economically and socially responsible manner. Our Commitment To help clients understand their environmental challenges and to incorporate sustainable design solutions to help them meet these challenges. 90

Notes de l'éditeur

  1. Shifting perspectives logo
  2. I am Sophie… A little bit of house keep to start: AIBC Credit sign in sheet 3hr session, 2 breaks Washroom Cellphone Now with the program… read the slide
  3. So why are we talking about energy standards today. Because they are part of the Code and as professionals we have to make sure they are being met Reference in the Code is found under part 10 And It is in schedule B that you are signing for it The snap shot of the schedule here shows the envelope requirement, but there is a similar requirement for the mechanical and electrical. Sentence (2) If a building is less than 5 storeys in building height,the parts of the building that are classified as Group C major occupancies shall be provided with thermal insulation that conforms to Table 10.2.1.1. Sentence (4) Buildings or parts of buildings described in Sentence 1.3.3.3.(1), Division A, that are not Group C major occupancies, shall be provided with thermal insulation between heated and unheated space, the exterior air and exterior soil in conformance with Table 10.2.1.1.B. These requirements will be found in a new section: 9.36. Energy Efficiency. This section will replace the insulation tables in Part 10, but the water efficiency requirements in Part 10 will remain in effect. Existing section 9.36. Secondary Suites will be renumbered as 9.37. Secondary Suites. We are providing a PDF of the new section 9.36. Eneregy Efficiency to allow Building Code users to become familiar with the requirements before December 19th, 2014.
  4. So why are we talking about energy standards today. Because they are part of the Code and as professionals we have to make sure they are being met Reference in the Code is found under part 10 And It is in schedule B that you are signing for it The snap shot of the schedule here shows the envelope requirement, but there is a similar requirement for the mechanical and electrical. Sentence (2) If a building is less than 5 storeys in building height,the parts of the building that are classified as Group C major occupancies shall be provided with thermal insulation that conforms to Table 10.2.1.1. Sentence (4) Buildings or parts of buildings described in Sentence 1.3.3.3.(1), Division A, that are not Group C major occupancies, shall be provided with thermal insulation between heated and unheated space, the exterior air and exterior soil in conformance with Table 10.2.1.1.B. These requirements will be found in a new section: 9.36. Energy Efficiency. This section will replace the insulation tables in Part 10, but the water efficiency requirements in Part 10 will remain in effect. Existing section 9.36. Secondary Suites will be renumbered as 9.37. Secondary Suites. We are providing a PDF of the new section 9.36. Eneregy Efficiency to allow Building Code users to become familiar with the requirements before December 19th, 2014.
  5. If we look at the adoption of standards in Codes BCBC adopted ASHRAE in 2008, and up to now it is the 2004 version that has been in the Code ASHRAE has been in VBBL for more than a decade and the version we have been dealing with in the last few year is 2007 NECB (or MNECB 1997) has not been part of Codes in BC, LEED, not BC codes, is where there is a reference to MNECB It is also interesting to note that the City of Vancouver has recently started collecting compliance documentation for ASHREA. This is something I believe the province is also working on.
  6. Read the slide Continuous maintenance means that there can be updates in between versions, and that new versions come out regularly Applies to new buildings, addition to existing buildings, alterations to existing building, replacements of portions of existing building
  7. With ASHRAE, there are 3 alternative paths for compliance 1-prescriptive 2-Trade-off 3-Energy cost budget which is the Whole Building energy modeling approach All 3 methods require that the mandatory provisions be fulfill Prescriptive path and Trade off methods involves many different building systems and If this path is chosen, all the building systems listed here need to meet the prescriptively requirement of their respective parts This means that all these professionals need to work together to achieve compliance and there is a need for someone coordinating the process, Ultimately, if EVEN one of the building systems listed cannot meet the prescriptive requirements, than NONE of them can go that route and the Energy cost budget path needs to be taken.
  8. Looking at the evolution of ASHRAE, if we were to consider the 2004 version as the base line, Although mechanical and electrical system have been evolving every version most of the building envelope changes happened with the 2007 version The suggested BE changes that were put forward for 2010 version actually got defeated My understanding is that the Goal for 2010 was to achieve 30% energy saving over 2004 But I believe that without the increase of the BE requirements going into 2010, it is falling a little bit short on that
  9. NECB is a Canadian Standard, It was developed by Natural Resources Canada and National research Council for Canada The latest version of this standard was in 1997, and it was called the Model National Energy Code LEED v4 will be a US version only though some Canadian adaptations will be accepted by USGBC. ASHRAE 2010 is the version used in LEED v4. NECB 2011 will likely be accepted as an equivalent, with some modifications. It will be announced in 3 weeks at the CaGBC conference.    People will HAVE to use v4 as of June 2015 in Canada. But they could do so earlier. 
  10. Like in ASHREA, Compliance can be achieve through 3 alternative paths 1-prescriptive 2-Trade-off methods (here there is 2 a simple method and a detailed one) 3-Energy simulation Again, just like AHSRAE, if the prescriptive path is desired, than all the building system needs to meet it If even one cannot, than the prescriptive path cannot be use for any of them
  11. ASHREA has a list of Cities with there zones, only when a city is not listed you should look at weather data to establish the HHD NECB states that the Climatic values are established by the Authorities having jurisdiction, or in the absence of such, we should be using what is in the Code The funny part about that is that in the lower mainland we are on the at the upper limit of zone 4 and that when you start going up the hills you are in Zone 5 What about the rest of BC? A lot of the municipalities in ASHRAE are listed as Zone 5 including Nanaimo, Victoria, Vancouver and New West One of the distinction with ASHRAE is the determination of the zone as Humid (A), Dry (B) and Marine (C), which from an envelope perspective doesn’t make a difference because we still have the same U value requirements. But they may make a difference from an mechanical or energy modeling perspective
  12. NECB is defined by degree days and broken into 1000 heating degree-day increments. (A heating degree day (HDD) is defined as the number of days the outside temperature is below the indoor set point temperature; for standard room temperatures these are defined in the building codes under climatic data.)ASHRAE uses a more complex system to define climate zones, intended to include heating, cooling, solar angle and latent loads. Climate zones for Canada are defined in Appendix B (Table B-2.) In both compliance paths the building performance requirements are defined by the climate zone, and in one location the requirements in one standard might be more stringent than in the other. For example, Victoria is ASHRAE zone 5c and NECB zone 4, while Nanaimo, which is 100 kilometres away, is ASHRAE Zone 5c but NECB zone 5. Therefore, when deciding which path to follow the climate zone must be reviewed.
  13. So let’s start with ASHRAE Again, we will be focusing here on the envelope section of the standard And we will look at the prescriptive and trade-off method only The energy cost budget method is covered under a different traning which will be given by my colleague Christian Cianfrone (On ???)
  14. If we look at the compliance paths again we see that regardless of the path chosen Whether it is the Prescriptive path, the BE trade-off option or the Energy Cost budget method, one need to meet the mandatory provisions Then there is the submittals section which is in essence the compliance documentation that you are currently required to submit to the City Like I mentioned earlier, The province is also working on something But the bottom line is, the forms are there, they are helpful tools to make sure every is addressed properly, they should be used
  15. The mandatory provisions form part of the Compliance Documentations, (the form looks different than the 2007 or 2004 version but it is more or less the same) To be able to meet these provisions, attention should be given to every single one of them at an early stage. A lot of this information should actually be incorporated in the specifications Insulation needs to be… Air leakage refers to the selection and construction of the air barrier - this is part of the code already (part 5). AB needs to be Continuous, to be structurally supported and to consist of appropriate materials Air leakage rate are limited for glazing assemblies and doors. In general NAFS is more demanding but I encourage you to verify the requirements. Typical window is 0.2 cfm/ft2 at 75Pa in ASHREA and 0.1 in NAFS. And in Vancouver, and anywhere else in BC, you need a vestibule unless you meet one of the exceptions listed (among them size of lobby or using a revolving doors) Finally, when we are talking of U values for windows, they are the values that are determined, certified and labeled in accordance with NFRC The NFRC values are for specific window sizes
  16. Mandatory requirements are certainly something you want to include in your specifications and design documents (Air barrier!) You will want to include the performance requirements for pre-fabricated assemblies (especially windows and Doors) that would include, U Values, SHGC and the air leakage limits There might be other standard that need to be addressed, NAFS being one of them when it comes to air leakage In general NAFS is more demanding but I encourage you to verify the requirements. Typical window is 0.2 cfm/ft2 at 75Pa in ASHREA and 0.1 in NAFS.
  17. So 1st, lets look at the prescriptive approach… Read the slides That is for each space conditioning category (Residential, Non-Residential and semi-heated) Does that look like anything typical that is being built in downtown Vancouver? Glazing proportion of you typical downtown high-rise is probably over 70% So not only these 2 conditions need to be met but Then all components (opaque wall and roof areas, fenestration, skylight and doors) need to meet the Rvalues listed in the prescriptive tables Note that Spandrel in glazing is considered an opaque wall assembly and we will see in later why spandrels are a “no go” for the prescriptive method
  18. To be able to determine the Rvalue requirements, the environmental separations need to be understood The lines in dark gray are typical exterior building envelope and would need to meet the full Rvalue requirement either under the residential or non-residential categories That would be for example between a conditioned space and the exterior or between a conditioned space and a ventilated space The light grey line defines walls that would have to meet the requirements of a semi-heated space That would be for example between a conditioned space and a semi-conditioned space or an unconditioned space, or between a Semi-heated space and the exterior
  19. Read the first sentence… click Zones are defined in Appendix B of the standard (The zone are defined by the HDD and the ABC refers to the type of climate, in this case C is marine climate) Each one of the space conditioning categories are listed at the top of the table… here click Read the second part of the slide Maximum U Factor is in essence the effective thermal résistance of the assembly, including air films, or if you take 1/U it becomes the effective Rvalue Minimum Rated Rvalue of insulation is for the thermal resistance of the insulation only whether in the framing cavities or installed as continuous insulation inboard or outboard of the framing There is quite a number of these tables and the idea today is not to go over them but to give you an understanding of what information is available and where you can find it There is a possibility within the standard prescriptive method, it is that …. Read exception
  20. These are some of the values that can be found in the standard for some components when constructed in Zone 5 Inverted or conventional roof assemblies are fairly simple as typically we find continuous insulation on these roofs and that is what is in the table (the c.i. is for continuous insulation) Attics, typically wood frame , would require R38 insulation between rafters Mass Wall at .09 is an effective Rvalue of R11.1 (why is it lower than the continuous insulation ???) Steel studs at .064 is an effective Rvalue of R15.6, or from a nominal value approach we are looking at R13 batt within the 3 5/8” steel studs and 1 ½” of continuous rigid insulation But what do they mean by continuous insulation…
  21. Just read the slide
  22. Nominal R values… Effective R values… For e.g. R-20 Batt in 6”SS is about R9 R-20 Batt in 6” wood studs is about R16
  23. There are tables in the appendix A that help you with determining the U values For example here we have the Ufactors for steel stud assemblies, but there are a numbers of other tables for other types of assemblies We should remember that good practice for steed stud assemblies is to have at least ¼ of the insulation outboard , this for durability purposes. So using the base wall assembly shouldn’t really be an option Looking at the table above, it looks like to have a value < 0.064 (which is required for SS assemblies in residential or non-residential buildings in zone 4 et zone 5) we are looking at 1 to 2” of insulation depending on the type But then again, this is not considering Z girts or clips. If the assemblies are substantially different that what is in the table they can always be calculated We will look at that later in the presentation
  24. This is the Ufactors for wood stud assemblies, Looking at the table above, it looks like to have a value < 0.051 (which is required for wood assemblies in residential buildings zone 5) we are looking at 1inch of insulation depending on the type Looks like exterior insulation is required … Click Zone 4 (R<0.064) is the only one that can have insulation installed only within the stud space A lot of people ask if they were to use 2 part spray foam if they would meet the requirement of .051… yes but why would you. It is very expensive, 3 passes.
  25. Check the Values!!! Why are the changes happening like they do??? Why 15.6 or 18.8, why does the roof ext ins doesn’t change All I have put here for comparison are the Minimum rated R values of insulation for different components per Zone fro a residential building Zone 5: Vancouver, Victoria, Penticton and Kamloops Zone 6: Prince Rupert Zone 7: Prince George Zone 8: Ft Nelson Go through the numbers one per one Obviously there are more components than this, for example there are values for floors, below grade walls and slab on grade, And I have kind of ignored the Structural steel buildings which are also in the tables
  26. Now looking at Fenestration, and remembering that we are dealing here with a building that has less the 40% window to wall ratio and less than 5% skylight to roof ratio Than all fenestration needs to meet a minimum U factor and solar Heat Gain Coefficient Read the 2 arrows
  27. So if we look at the Vancouver region (zone 5) , the fenestration need to meet the following values Read the table For e.g. window-wall with a good low-e coating, argon and warm edge spacers can meet values below 0.40 A vinyl window with the same sealed unit with be below 0.32 Curtain wall , and espescially storefront, can vary greatly depending on if it is a structural silicone CW or the type of thermal break it incorporate, but 0.45 can be met with the right selection More tables can be found in the standard for the different zones,
  28. So now that we have reviewed the prescriptive path, we have found out that it is somewhat restrictive The trade-off method allow more flexibility Often buildings have fenestration that exceed the 40%, that is especially through in Vancouver!!! Or some of the building envelope components do not quite meet the minimum R value required through the prescriptive path That is when the trade-off method may come in handy, as oppose to having to do the whole energy modeling But it needs to be understood that the trade-offs only happen between BE components, And to be successful, some of the BE components will have the exceed the minimum requirements to compensate for what doesn’t.
  29. Read the slide
  30. To demonstrate compliance using the trade-off method, in broad terms you need to: Do take offs And numbers in equations Software ENVStd Was not updated with the latest version of ashrae, and COMcheck does not include Canadian climate data …so these calculations now need to be done by hand Or if you are like me and you glaze over at the sight of an equation, than you ask someone that has more patience than you to do it One thing that the trade-off method does is determine the Daylighting potential using the VT. A benefit will result when the glazing used in the proposed building has a high VT. The VT is not taken into account with the prescriptive method
  31. Easy interface, Read the user guide on how to define areas There is also in there a good database of values for fenestration which links to NFRC
  32. Much like AHREA, NECB puts a certain limit on the fenestration The limit on the vertical fenestration varies depending on the HDD FDWR is the vertical fenestration and doors to wall area ratio It shows that up north, where it is very cold, like in Ft. Nelson if I remember well, the FDWR is limited to 20% Here in the lowermainland we are still looking at 40% The Skylight limitation is th Same as ASHRAE, i.e. 5% But NECB is more prescriptive than that!!
  33. The reason why the penetrations can be ignored to a certain degree in the effective R value calculation is that there are very prescriptive requirements on how to deal with these penetrations, for example: 1. Where an interior wall penetrates an exterior wall and breaks the continuity of the building envelope it should be insulated on both sides (inward or outward) to 4 times the un-insulated thickness of the penetrating wall. So If we have a inside concrete wall that connects to an exposed exterior concrete wall and breaks the insulation, this wall needs to be insulated inward (if it is an 8” wall e.g.) for up to 32” with the same insulation that is on the exterior wall. Similar accommodation has to be made if that wall goes through the roof insulation, think about a planter wall for example 2. In another situation, where building envelope assembly in the same plane intersect but their insulation do not, one of the two insulation need to extend beyond the other one by at least 4 times the distance separating the two insulation. AS far as the salb is concerned, remember that you can igore it if it is less than 2% but otherwise you need to consider it
  34. OK ASHREA is in Imperial, NECB is in metric , For easier comparison I converted all the numbers in imperial R values (metric U/5.678 = imperial U and R = 1/U) The table above applies to all types of construction it doesn’t whether the building is residential or not, or whether the walls are mass walls, steels studs or wood frame construction, As a comparison, ASHRAE for zone 5 residential requires the following effective R value for the walls …click And for the roofs … click We can see that NECB is more stringent for the walls, and somewhere in the middle for the roof Still R31 would require about 6inches of continuous rigid insulation above the deck, 2” or 1/3 more than what would be required by ASHRAE
  35. The table above applies to all fenestration and doors, regardless if it is a residential or non-residential building or if it is a metal, wood or vinyl window. There are a few exception as noted There is no SHGC requirements When comparing to ASHRAE… CLICK We see that NECB is more stringent, at least with the metal framed windows, including curtain wall and storefront, And if the proportion of skylight is between 2% and 5% But how does this compare to the Energy efficiency act Metal 0.45 Non-metal 0.35
  36. ASHRAE as a category for semi-heated space in their table. With NECB, the insulating value depends on the delta in temperature between the two spaces
  37. What is a model that conform to ASHRAE 140???
  38. Read In other word it is a simplified energy model that doesn’t trade with the mechanical and electrical systems
  39. If above 40% cannot use prescriptive, but can use trade off (to a limit). That would still allow you to use prescriptive with other building systems. However if the prescriptive or trade-off method cannot be met, then you need to model your whole building, you cannot use prescriptive. AND at the end of it, even the prescriptive method are fairly complex in the sense that they are open to interpretation as how to calculate R value to consider or ignore things that are not expressively in the prescriptive tables…
  40. So to recap what we discussed in the standards,
  41. So let’s start with ASHRAE Again, we will be focusing here on the envelope section of the standard And we will look at the prescriptive and trade-off method only The energy cost budget method is covered under a different traning which will be given by my colleague Christian Cianfrone (On ???)
  42. How is Thermal bridging typically evaluated? Hand calculation for simple assemblies – clear wall Lab Testing (hot Box) for standard assemblies (would be hard and expensive to test every iteration) - used to valid some results Computer modeling - Current common methods use 2D programs such as THERM to calculate thermal bridging Knowing material properties, it will give you the average heat loss (U-value) through the assembly in 2D But this can only take you so far.
  43. Probably your best Resource when it comes to U Factors (or effective R values) is thje Normative Appendix A in Ashrae 90.1 It contains R-values for certain buildign materials (although not that many) But it especially contains a series of tables for different assemblies for which the r value are already calculated
  44. Concrete with 1” of rigid is 0.157 or R=6.36 Looking at the previous table for a 6” steel stud with BATT we are looking at about R15
  45. It also give you the possibility to used area-weighted average as long as the assemblies have similar thermal mass or walls of same class and construction The area-weighted average U-Factor is based on different U-factor for each of these assemblies which is averaged over their length. If we are considering the prescriptive method for mass wall the requirement is U 0.080 for a residential building (or an effective R value of 12.5), the 7.3 does meet that.
  46. Ok so if we are using the area weighted average to characterize thermal bridges, Are we really getting what is happening in real life That is easy for clear wall assemblies, and comparisons, but how do you deal with slabs and parapets and other types of anomalies The reality is that the effect of thermal bridge goes beyond the little portion of slab I showed you doing the area weighted average calculation Sometime the effect of the thermal bridge can affect area 1 to 2 m away from the anomaly, depending on how conductive the material penetrating the envelope is So the answer to that can only be to look at it in 3D
  47. 3D modeling is done using Finite element analysis It can deal with … read the points An the good thing about 3D model, is that it can be very accurate. Projects we have done developeing some of this has shown vey good relationship with result of Lab tests
  48. So with this in mind, lets look at the typical lower mainland construction Wood frame is fairly easy, non-combustible construction however is more complicated in part because of: -the conductivity of steel -the way the are often built – think about exposed concrete and The amount of thermal bridges is significant and a lot of the details don’t easily conform to the prescriptive approach of either standards
  49. The type of details we are finding on concrete towers are pretty much like this Window wall and interior insulated concrete And now that we are seeing more and more exterior insulated construction Sub-girts, and the likes, still having the deal with the slabs in one way or another -how much heat are we loosing through a girt at the slab vs a girt at the steel stud?
  50. But how do you deal with this in 2D
  51. This graph shows the effective R-values of the previous steel stud assemblies for varying amount of exterior insulation, along with the minimum requirements from ASHRAE 90.1-2010 and NECB 2011 The straight light blue line here shows what ASHRAE says the value of the wall would be with continuous exterior insulation. As you can see, with cladding attachments, the effective assembly U-values fall short of that to varying degrees. This indicates that it may be very difficult to reach prescriptive requirements in most climate zones with solely exterior insulation.
  52. You can see with the spray foam case, the stud cavity is much closer to the room temperature and the frame temp is lowered. So how does that relate in terms of thermal effectiveness?
  53. Here you can see that adding an R-11 spray foam only, on average, adds about an R-4 to the assembly This is understandable since there is just so much aluminum in a curtain wall system where heat can bypass the backpan and sprayfoam. The next question designers have to consider is, with that much spray foam and only getting back R-4, is it financially worth it? In some cases, in order to meet code requirements, they may have to go that route.
  54. I have presented 2 example aboev of results for assemblies using a finite element 3D model Probably your best Resource when it comes to U Factors (or effective R values) is thje Normative Appendix A in Ashrae 90.1 It contains R-values for certain buildign materials (although not that many) But it especially contains a series of tables for different assemblies for which the r value are already calculated
  55. Offcial Launch Oct 16
  56. So let’s start with ASHRAE Again, we will be focusing here on the envelope section of the standard And we will look at the prescriptive and trade-off method only The energy cost budget method is covered under a different traning which will be given by my colleague Christian Cianfrone (On ???)