From:    Nick Durand                           To: David Ficklin - OnGoal
                                                                                Rory O’Connor – OnGoal
                             Office: Kansas City                                Lee Turner – OnGoal
                             Date:    2.23.2011                                 Andy Heitmann – Turner
                                                                                Dave Dudzik - Turner
                             Re:      Sporting Kansas City                      Brandon Valdez-Turner
                                      Project Update – Week of
                                      2.23.2011

                              Current Activities this Week:
 Site/Playing field:
 Grading site on the East side of building to be ongoing.
 Cleaning up areas in preparation of plaza work is ongoing.
 Underground drainage and irrigation at the playing field
 is ongoing.

 Concrete Flatwork:
 Area 1-Suite and Press level tub intermediate stairs are
 ongoing.
 Area 1- Platform for Stadium Suite bar area is complete.
 Area 3-Base slab at cauldron club extended out for
 curtain wall installation is complete.
 Finishing of exposed concrete walls to be ongoing.
 Area 1- SOG work at SW toilet entry to be completed.              Installation of field drainage and irrigation
                                                                   lines.
 Masonry:
 Block installation at NW transformer area to be ongoing.
 Block installation at Terrace Bar is ongoing.
 Block installation at SW toilet entry to be ongoing.
 Sealing and final wash of block on the East side to begin.

 Stone:
 Area 1-Stone installation in area H to be ongoing.

 Steel:
 Installation of roll up doors in concessions is ongoing.
 Installation of stone support steel at Stadium Suite is
 ongoing.
 Area 3-Subroof under Stair #1 to be ongoing.
 Installation of SE corner screen wall tubes is ongoing.
 Installation of bar joists and roof decking in area H to begin.
 Installation of dock overhead doors to begin.
                                                                     Installation of Suite level intermediate stairs.

Building the Future
Roofing and Sheet metal:
 Area 1-Alucobond metal panel installation at Suite and
 Press level on field side is near complete.
 Alucobond metal panel and subgirt installation is
 ongoing at Concourse buildings.
 Drilling anchors for exterior fins is ongoing in all areas.
 Area 3-Concourse building roofing is ongoing in the SE.
 Louver installation at East side is complete.
 Gutter shrouds at canopy gutter are ongoing.
 Canopy deck flashing installation is ongoing.

 Polycarbonate:
 Area 1-Polycarbonate installation is ongoing.
 Area 2-Polycarbonate installation is ongoing.                   Block work at SW toilet entrance.

 Metal Stud Framing/Drywall/Ceilings:
 Area 1- Drywall installation is near complete.
 Area 3-Drywall installation and finishing is near complete.
 DAFS installation is ongoing at exterior soffits.
 Stud framing for North screenwall/ metal panels is ongoing.
 Drywall installation in concessions/retail areas is
 Ongoing.
 FRP installation in Concessions is ongoing.
 Ceiling grid installation is ongoing on all levels.

 Glass:
 Area 1-Storefront at 24-27 lines installation is
 complete.
 Area 1-installation of aluminum door frames is ongoing.
 Area 1-installation of store fronts at VIP entrance is
 complete.
 Installation of storefronts at Main Concourse retail
 buildings is ongoing.
 Installation of Press level Solar innovation sliders is
 ongoing.
 Area 1- installation of interior storefronts is ongoing.

 MEP:
 Ductwork installation in the west tower is complete           Installation of metal panels at concessions.
 and is ongoing on the East side field level.
 Plumbing rough is complete in the west tower and is
 ongoing on the East side field level.


Building the Future
Site-SE and SW transformers have been energized.
 NW transformer is now set and primary cables are being pulled to transformer.
 Installation of the backbone cable is complete and is terminated
 in the IT rooms.
 All racks and cabinets in the West tower have been
 assembled and termination of cables is near complete.
 Concession building rough in for all MEP is near complete.
 Installation of permanent lights and speakers in soffits is ongoing.
 Fixtures and devices are being installed in the West
 tower and termination of branch circuits is ongoing.
 South scoreboard module installation is complete.
 Sub air equipment is installed and all secondary
 work is complete.
 Area 1-installation of toilet fixtures on Suite and Field level
 is ongoing.
 Broadcast cable pulls from loading dock to the Video
 Production room is ongoing.
 Tie –in of canopy gutters to downspouts is ongoing.
 North scoreboard structure installation to begin.

 Elevators:
 F1 elevator installation is near completion.                    Installation of storefronts at V.I.P entrance.
 P2 & P3 elevator installation is ongoing.
 P4 & P5 elevator installation is ongoing.
 P1 has been delivered and installation to begin.

 Painting:
 Area 1-Painting at Field level is ongoing.
 Area 1-Painting in Main Concourse buildings is ongoing.
 Area 1-Painting on Press and Suite level is near complete.
 Sealing of exposed concrete floors is ongoing.
 Resinous flooring at field level is ongoing.
 Resinous flooring in Concessions, Suite, and Press
  is ongoing.
 Painting of stair structure and walls is ongoing.

 Tile:
 Tile in Suites on Suite level is complete.
 Tile installation in club areas at Suite and Press levels    Tile installation at Field Club.
 has begun.
 Tile in restrooms at all levels is ongoing.



Building the Future
Food Service:
 Countertop installation in Concessions is complete.
 Installation of all counters and kitchen equipment at Mezz level, Suite level, and Press
 level to be ongoing.
 Cooler installation in concessions and cauldron club is near complete.
 Exhaust hood installation in cauldron club to begin.


 Projected Activities occurring next Week:

 Concrete Flatwork:
 Area 1-Suite and Press level tub intermediate stairs to be
 completed.
 Finishing of exposed walls to be completed.
 Cauldron Club topping slab installation to begin.

 Stone/masonry:
 Block installation at NW transformer area to be complete.
 Block installation at Terrace Bar to be ongoing.                Painting is ongoing in RR’s at Main
 Block installation at SW toilet entry to be complete.           Concourse.
 Stone installation in area H to be ongoing.

 Steel:
 Installation of roll up doors in concessions to be complete.
 Installation of stone support steel at Stadium Suite to be
 ongoing.
 Area 3-Subroof under Stair #1 to be complete.
 Installation of SE corner screen wall tubes to be complete.
 Installation of bar joists and roof decking in area H to
 be completed.
 Installation of dock overhead doors to be ongoing.


 Roofing and Sheet metal:
 Canopy gutter shroud installation to be ongoing.
 Area 3-North East concourse roof to begin.
 Installation of metal panels at concessions to be ongoing. Overhead door installation at loading dock.
 Field measuring for metal panels at Stadium Suite to be
 complete.
 Installation of coping cap at concourse roof to be ongoing.


Building the Future
Metal Stud Framing/drywall soffits:
 Area 1- Drywall installation to be complete.
 Area 3-Drywall installation and finishing to be complete.
 DAFS installation to be ongoing at exterior soffits.
 Stud framing for North screenwall/ metal panels to be complete.
 Drywall installation in concessions/retail to be complete.
 FRP installation in Concessions to be ongoing.
 Ceiling grid installation to be ongoing on all levels.

 Glass:
 Area 1-Aluminum door frame installation to be ongoing.
 Installation of storefronts at Main Concourse buildings
 to be ongoing.
 Installation of interior glazing at Field and Mezz. level to
 be near complete.
 Installation of Solar innovation sliders at back of suites on
  Press level to be ongoing.
                                                                 Locker installation at field level.
 MEP:
 NW transformer to be energized.
 Installation of North Scoreboard to be ongoing.
 Preliminary hydrostatic testing of the fire sprinkler lines to begin.
 Energizing mechanical equipment to begin commissioning/start up.

 Paint:
 Area 1-Painting of the Suite and Press level areas to
 be near complete.
 Painting of the Main Concourse buildings to be ongoing.
 Painting at Field level to be ongoing.
 Sealing of concrete floors to be ongoing.
 Painting of stair #4 and #9 to be complete.
 Resinous flooring to be ongoing in concessions.

 Playing Field:
 Installation of underground drainage and irrigation lines
 to be ongoing.                                                  Drilling for fin anchors is ongoing.




Building the Future
Additional Photos:




Framing for metal panels at North main                  Subroof installation under Stair #1.
concourse.




Tile and millwork installation at Executive Suites.     South scoreboard module installation is complete.




    Building the Future

Contenu connexe

En vedette

Richa initial pages
Richa   initial pagesRicha   initial pages
Richa initial pages
Neh Alvaro
 
FASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government ContractorsFASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government Contractors
DecosimoCPAs
 
Bodegones1º
Bodegones1ºBodegones1º
Bodegones1º
edupocs
 
texturas2012
texturas2012texturas2012
texturas2012
edupocs
 
British Journal of Developmental Psychology
British Journal of Developmental PsychologyBritish Journal of Developmental Psychology
British Journal of Developmental Psychology
Wiley-Blackwell
 
3212148 customer-satisfaction
3212148 customer-satisfaction3212148 customer-satisfaction
3212148 customer-satisfaction
Vishal Kapoor
 

En vedette (20)

Financial Expert Witness Issues: How to Handle the Dangerous Financial Expert...
Financial Expert Witness Issues: How to Handle the Dangerous Financial Expert...Financial Expert Witness Issues: How to Handle the Dangerous Financial Expert...
Financial Expert Witness Issues: How to Handle the Dangerous Financial Expert...
 
Engaging augmented reality experiences
Engaging augmented reality experiencesEngaging augmented reality experiences
Engaging augmented reality experiences
 
The Changing Landscape of Recruiting Physicians to Your Practice - David Cran...
The Changing Landscape of Recruiting Physicians to Your Practice - David Cran...The Changing Landscape of Recruiting Physicians to Your Practice - David Cran...
The Changing Landscape of Recruiting Physicians to Your Practice - David Cran...
 
Richa initial pages
Richa   initial pagesRicha   initial pages
Richa initial pages
 
FASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government ContractorsFASB Proposals Affecting Government Contractors
FASB Proposals Affecting Government Contractors
 
FHWA and Chicago HS for Agricultural Sciences shadow day 02-08-12 pictures
FHWA and Chicago HS for Agricultural Sciences shadow day 02-08-12 picturesFHWA and Chicago HS for Agricultural Sciences shadow day 02-08-12 pictures
FHWA and Chicago HS for Agricultural Sciences shadow day 02-08-12 pictures
 
Presentación3
Presentación3Presentación3
Presentación3
 
Bodegones1º
Bodegones1ºBodegones1º
Bodegones1º
 
Time to Change - Youth Mental Health
Time to Change - Youth Mental HealthTime to Change - Youth Mental Health
Time to Change - Youth Mental Health
 
Honda Accord Riverside
Honda Accord RiversideHonda Accord Riverside
Honda Accord Riverside
 
texturas2012
texturas2012texturas2012
texturas2012
 
Metodos de estudio
Metodos de estudioMetodos de estudio
Metodos de estudio
 
Dickginas
DickginasDickginas
Dickginas
 
Matt's awesome adventure
Matt's awesome adventureMatt's awesome adventure
Matt's awesome adventure
 
Samoloty
SamolotySamoloty
Samoloty
 
British Journal of Developmental Psychology
British Journal of Developmental PsychologyBritish Journal of Developmental Psychology
British Journal of Developmental Psychology
 
3212148 customer-satisfaction
3212148 customer-satisfaction3212148 customer-satisfaction
3212148 customer-satisfaction
 
Marketing Monday Presentation 2/28/2011
Marketing Monday Presentation 2/28/2011Marketing Monday Presentation 2/28/2011
Marketing Monday Presentation 2/28/2011
 
Linie lotnicze
Linie lotniczeLinie lotnicze
Linie lotnicze
 
Valuation of Physician Practices - David Cranford, Shannon Farr
Valuation of Physician Practices - David Cranford, Shannon FarrValuation of Physician Practices - David Cranford, Shannon Farr
Valuation of Physician Practices - David Cranford, Shannon Farr
 

Dernier

🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
Diya Sharma
 
Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...
Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...
Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...
baharayali
 
+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...
+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...
+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...
Health
 

Dernier (20)

ALL NFL NETWORK CONTACTS- April 29, 2024
ALL NFL NETWORK CONTACTS- April 29, 2024ALL NFL NETWORK CONTACTS- April 29, 2024
ALL NFL NETWORK CONTACTS- April 29, 2024
 
WhatsApp Chat: 📞 8617697112 Birbhum Call Girl available for hotel room package
WhatsApp Chat: 📞 8617697112 Birbhum  Call Girl available for hotel room packageWhatsApp Chat: 📞 8617697112 Birbhum  Call Girl available for hotel room package
WhatsApp Chat: 📞 8617697112 Birbhum Call Girl available for hotel room package
 
Who Is Emmanuel Katto Uganda? His Career, personal life etc.
Who Is Emmanuel Katto Uganda? His Career, personal life etc.Who Is Emmanuel Katto Uganda? His Career, personal life etc.
Who Is Emmanuel Katto Uganda? His Career, personal life etc.
 
08448380779 Call Girls In International Airport Women Seeking Men
08448380779 Call Girls In International Airport Women Seeking Men08448380779 Call Girls In International Airport Women Seeking Men
08448380779 Call Girls In International Airport Women Seeking Men
 
Trossard's Message Bridging Celebrities and Sports in Euro Cup 2024.docx
Trossard's Message Bridging Celebrities and Sports in Euro Cup 2024.docxTrossard's Message Bridging Celebrities and Sports in Euro Cup 2024.docx
Trossard's Message Bridging Celebrities and Sports in Euro Cup 2024.docx
 
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
Spain Vs Italy 20 players confirmed for Spain's Euro 2024 squad, and three po...
 
Croatia vs Italy Euro Cup 2024 Three pitfalls for Spalletti’s Italy in Group ...
Croatia vs Italy Euro Cup 2024 Three pitfalls for Spalletti’s Italy in Group ...Croatia vs Italy Euro Cup 2024 Three pitfalls for Spalletti’s Italy in Group ...
Croatia vs Italy Euro Cup 2024 Three pitfalls for Spalletti’s Italy in Group ...
 
08448380779 Call Girls In IIT Women Seeking Men
08448380779 Call Girls In IIT Women Seeking Men08448380779 Call Girls In IIT Women Seeking Men
08448380779 Call Girls In IIT Women Seeking Men
 
UEFA Euro 2024 Squad Check-in Who is Most Favorite.docx
UEFA Euro 2024 Squad Check-in Who is Most Favorite.docxUEFA Euro 2024 Squad Check-in Who is Most Favorite.docx
UEFA Euro 2024 Squad Check-in Who is Most Favorite.docx
 
TAM Sports_IPL 17 Till Match 37_Celebrity Endorsement _Report.pdf
TAM Sports_IPL 17 Till Match 37_Celebrity Endorsement _Report.pdfTAM Sports_IPL 17 Till Match 37_Celebrity Endorsement _Report.pdf
TAM Sports_IPL 17 Till Match 37_Celebrity Endorsement _Report.pdf
 
Technical Data | Sig Sauer Easy6 BDX 1-6x24 | Optics Trade
Technical Data | Sig Sauer Easy6 BDX 1-6x24 | Optics TradeTechnical Data | Sig Sauer Easy6 BDX 1-6x24 | Optics Trade
Technical Data | Sig Sauer Easy6 BDX 1-6x24 | Optics Trade
 
08448380779 Call Girls In Karol Bagh Women Seeking Men
08448380779 Call Girls In Karol Bagh Women Seeking Men08448380779 Call Girls In Karol Bagh Women Seeking Men
08448380779 Call Girls In Karol Bagh Women Seeking Men
 
🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...🔝|97111༒99012🔝 Call Girls In  {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
🔝|97111༒99012🔝 Call Girls In {Delhi} Cr Park ₹5.5k Cash Payment With Room De...
 
Unveiling the Mystery of Main Bazar Chart
Unveiling the Mystery of Main Bazar ChartUnveiling the Mystery of Main Bazar Chart
Unveiling the Mystery of Main Bazar Chart
 
08448380779 Call Girls In Lajpat Nagar Women Seeking Men
08448380779 Call Girls In Lajpat Nagar Women Seeking Men08448380779 Call Girls In Lajpat Nagar Women Seeking Men
08448380779 Call Girls In Lajpat Nagar Women Seeking Men
 
Personal Brand Exploration - By Bradley Dennis
Personal Brand Exploration - By Bradley DennisPersonal Brand Exploration - By Bradley Dennis
Personal Brand Exploration - By Bradley Dennis
 
Spain Vs Albania- Spain at risk of being thrown out of Euro 2024 with Tournam...
Spain Vs Albania- Spain at risk of being thrown out of Euro 2024 with Tournam...Spain Vs Albania- Spain at risk of being thrown out of Euro 2024 with Tournam...
Spain Vs Albania- Spain at risk of being thrown out of Euro 2024 with Tournam...
 
Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...
Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...
Asli Kala jadu, Black magic specialist in Pakistan Or Kala jadu expert in Egy...
 
+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...
+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...
+971565801893>>SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHAB...
 
Sports Writing (Rules,Tips, Examples, etc)
Sports Writing (Rules,Tips, Examples, etc)Sports Writing (Rules,Tips, Examples, etc)
Sports Writing (Rules,Tips, Examples, etc)
 

Sporting Park Construction Update (2/23/11)

  • 1. From: Nick Durand To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 2.23.2011 Andy Heitmann – Turner Dave Dudzik - Turner Re: Sporting Kansas City Brandon Valdez-Turner Project Update – Week of 2.23.2011 Current Activities this Week: Site/Playing field: Grading site on the East side of building to be ongoing. Cleaning up areas in preparation of plaza work is ongoing. Underground drainage and irrigation at the playing field is ongoing. Concrete Flatwork: Area 1-Suite and Press level tub intermediate stairs are ongoing. Area 1- Platform for Stadium Suite bar area is complete. Area 3-Base slab at cauldron club extended out for curtain wall installation is complete. Finishing of exposed concrete walls to be ongoing. Area 1- SOG work at SW toilet entry to be completed. Installation of field drainage and irrigation lines. Masonry: Block installation at NW transformer area to be ongoing. Block installation at Terrace Bar is ongoing. Block installation at SW toilet entry to be ongoing. Sealing and final wash of block on the East side to begin. Stone: Area 1-Stone installation in area H to be ongoing. Steel: Installation of roll up doors in concessions is ongoing. Installation of stone support steel at Stadium Suite is ongoing. Area 3-Subroof under Stair #1 to be ongoing. Installation of SE corner screen wall tubes is ongoing. Installation of bar joists and roof decking in area H to begin. Installation of dock overhead doors to begin. Installation of Suite level intermediate stairs. Building the Future
  • 2. Roofing and Sheet metal: Area 1-Alucobond metal panel installation at Suite and Press level on field side is near complete. Alucobond metal panel and subgirt installation is ongoing at Concourse buildings. Drilling anchors for exterior fins is ongoing in all areas. Area 3-Concourse building roofing is ongoing in the SE. Louver installation at East side is complete. Gutter shrouds at canopy gutter are ongoing. Canopy deck flashing installation is ongoing. Polycarbonate: Area 1-Polycarbonate installation is ongoing. Area 2-Polycarbonate installation is ongoing. Block work at SW toilet entrance. Metal Stud Framing/Drywall/Ceilings: Area 1- Drywall installation is near complete. Area 3-Drywall installation and finishing is near complete. DAFS installation is ongoing at exterior soffits. Stud framing for North screenwall/ metal panels is ongoing. Drywall installation in concessions/retail areas is Ongoing. FRP installation in Concessions is ongoing. Ceiling grid installation is ongoing on all levels. Glass: Area 1-Storefront at 24-27 lines installation is complete. Area 1-installation of aluminum door frames is ongoing. Area 1-installation of store fronts at VIP entrance is complete. Installation of storefronts at Main Concourse retail buildings is ongoing. Installation of Press level Solar innovation sliders is ongoing. Area 1- installation of interior storefronts is ongoing. MEP: Ductwork installation in the west tower is complete Installation of metal panels at concessions. and is ongoing on the East side field level. Plumbing rough is complete in the west tower and is ongoing on the East side field level. Building the Future
  • 3. Site-SE and SW transformers have been energized. NW transformer is now set and primary cables are being pulled to transformer. Installation of the backbone cable is complete and is terminated in the IT rooms. All racks and cabinets in the West tower have been assembled and termination of cables is near complete. Concession building rough in for all MEP is near complete. Installation of permanent lights and speakers in soffits is ongoing. Fixtures and devices are being installed in the West tower and termination of branch circuits is ongoing. South scoreboard module installation is complete. Sub air equipment is installed and all secondary work is complete. Area 1-installation of toilet fixtures on Suite and Field level is ongoing. Broadcast cable pulls from loading dock to the Video Production room is ongoing. Tie –in of canopy gutters to downspouts is ongoing. North scoreboard structure installation to begin. Elevators: F1 elevator installation is near completion. Installation of storefronts at V.I.P entrance. P2 & P3 elevator installation is ongoing. P4 & P5 elevator installation is ongoing. P1 has been delivered and installation to begin. Painting: Area 1-Painting at Field level is ongoing. Area 1-Painting in Main Concourse buildings is ongoing. Area 1-Painting on Press and Suite level is near complete. Sealing of exposed concrete floors is ongoing. Resinous flooring at field level is ongoing. Resinous flooring in Concessions, Suite, and Press is ongoing. Painting of stair structure and walls is ongoing. Tile: Tile in Suites on Suite level is complete. Tile installation in club areas at Suite and Press levels Tile installation at Field Club. has begun. Tile in restrooms at all levels is ongoing. Building the Future
  • 4. Food Service: Countertop installation in Concessions is complete. Installation of all counters and kitchen equipment at Mezz level, Suite level, and Press level to be ongoing. Cooler installation in concessions and cauldron club is near complete. Exhaust hood installation in cauldron club to begin. Projected Activities occurring next Week: Concrete Flatwork: Area 1-Suite and Press level tub intermediate stairs to be completed. Finishing of exposed walls to be completed. Cauldron Club topping slab installation to begin. Stone/masonry: Block installation at NW transformer area to be complete. Block installation at Terrace Bar to be ongoing. Painting is ongoing in RR’s at Main Block installation at SW toilet entry to be complete. Concourse. Stone installation in area H to be ongoing. Steel: Installation of roll up doors in concessions to be complete. Installation of stone support steel at Stadium Suite to be ongoing. Area 3-Subroof under Stair #1 to be complete. Installation of SE corner screen wall tubes to be complete. Installation of bar joists and roof decking in area H to be completed. Installation of dock overhead doors to be ongoing. Roofing and Sheet metal: Canopy gutter shroud installation to be ongoing. Area 3-North East concourse roof to begin. Installation of metal panels at concessions to be ongoing. Overhead door installation at loading dock. Field measuring for metal panels at Stadium Suite to be complete. Installation of coping cap at concourse roof to be ongoing. Building the Future
  • 5. Metal Stud Framing/drywall soffits: Area 1- Drywall installation to be complete. Area 3-Drywall installation and finishing to be complete. DAFS installation to be ongoing at exterior soffits. Stud framing for North screenwall/ metal panels to be complete. Drywall installation in concessions/retail to be complete. FRP installation in Concessions to be ongoing. Ceiling grid installation to be ongoing on all levels. Glass: Area 1-Aluminum door frame installation to be ongoing. Installation of storefronts at Main Concourse buildings to be ongoing. Installation of interior glazing at Field and Mezz. level to be near complete. Installation of Solar innovation sliders at back of suites on Press level to be ongoing. Locker installation at field level. MEP: NW transformer to be energized. Installation of North Scoreboard to be ongoing. Preliminary hydrostatic testing of the fire sprinkler lines to begin. Energizing mechanical equipment to begin commissioning/start up. Paint: Area 1-Painting of the Suite and Press level areas to be near complete. Painting of the Main Concourse buildings to be ongoing. Painting at Field level to be ongoing. Sealing of concrete floors to be ongoing. Painting of stair #4 and #9 to be complete. Resinous flooring to be ongoing in concessions. Playing Field: Installation of underground drainage and irrigation lines to be ongoing. Drilling for fin anchors is ongoing. Building the Future
  • 6. Additional Photos: Framing for metal panels at North main Subroof installation under Stair #1. concourse. Tile and millwork installation at Executive Suites. South scoreboard module installation is complete. Building the Future