Composite construction in Bridge Deck systems
A Solution in City Environment for Speedy Construction with Industrialized
Full Length Prefabrication
By,
Suhas Khedkar , Kishore Saxena
Abstract
Rapid construction of flyovers in congested cities has become necessary, considering the present
traffic trends, and anticipated growth in future. Construction has to be done without closure of
roads and with minimum disturbance to the existing traffic. Use of Precast and Prefabricated
components for superstructure help in reduction of construction time, as superstructure
components can be kept ready elsewhere, when construction of foundations and substructure is in
progress. Erection of such components can be planned during night hours, when the traffic is
minimal; thus causing least hardships to the general public. Many flyovers have been constructed in
our country using full length precast prestressed girders, and cast in situ deck slab. Flyovers with full
length prefabricated girders in structural steel and composite RCC deck slab are very few. This paper
presents advantages of such structural system for congested cities.
Key Words: Structural Steel Bridge Girders, full length Industrialized Prefabrication , working
window, girder transportation , site erection
1. General
Many of our cities are very busy, over populated, and congested for both living
conditions, and traffic situation. The existing infrastructure is already overtaxed. This is
not only true in case of the major metropolitan cities, but also in case of second and
third level cities, particularly those in the vicinity of major cities. All these cities and
urban areas need better infrastructure for decongesting traffic. While the metropolitan
cities are moving from the era of flyover construction, to construction to that of
Elevated Transportation Corridors, covering multiple junctions, and longer routes
measuring in kilometres; smaller developing cities and towns need flyover bridges over
busy traffic junctions to help in decongestion of traffic. The typical site conditions pose
many constraints to any new construction. Although there are site specific problems,
many constraints are common. Engineers can adopt standard solutions in such
situations. The same can be modified suitably to address site specific issues, by a
judicious mix of different solutions.
2. Typical constraints in construction of flyovers in congested cities
Construction of flyovers in cities must be done in busy and congested city environment,
respecting all aspects: viz. No / minimal disturbance to traffic, safety of the citizens,
availability of small working windows, coordination with local bodies etc. All these need
to fit into the tight construction schedule, which is the basic demand of the present
times. The alignment of flyovers many a time passes through area with heavy
encroachment, further restricting available working space for construction. This needs
suitable consideration in designs, which may demand basic changes such as different
type of structure and construction materials. Sometimes the site constraints may
dictate choice of structural steel instead of Prestressed concrete (which is a normal
choice for construction); considering limitation of transportation and erection of heavy
segments and girders. It may also be a chosen solution by the owners to ensure speedy
and easier construction.
3. Possible solutions, Pros and Cons
Conventional method is to use cast in situ superstructure. However, it is time
consuming; as the construction is strictly sequential - Foundation, Substructure, and
then Superstructure by using scaffolding and formwork under each span. Construction
time can be reduced if precast superstructure elements are used, as precasting can be
done as a parallel activity when construction of foundations and substructure is in
progress at site. Such construction does not need staging under each span, if the
precast elements are erected using launching equipment.
Main advantage of using Precast / prefabricated structural elements being utilising time
required for construction of foundations and substructure for casting / fabricating
superstructure elements in a Precast Yard / Fabrication shop. Such construction helps in
achieving much better quality control, as it happens in a dedicated , specially designed
casting yard / fabrication shop; in controlled conditions and factory like environment;
which is another major advantage of such construction. Thus precasting /
prefabrication is called as Industrialised Construction.
Normal methods of superstructure construction of such urban flyovers, therefore; is to
use full length concrete girders or concrete box girder segments; precast in a dedicated
Casting Yard for the purpose, normally distant from the site; transported to respective
spans using a specially designed trailer, and erected using high capacity cranes or a
Launching Gantry, designed to suit the size and weight of segments, and span length.
The method is well established, and many flyovers and elevated roads have been
constructed using the method in various parts of our country.
However, weight of precast concrete elements, whether full length girders or box girder
segments typically ranges from 45 t upwards; and needs large capacity trailers for
transportation of the girders / segments and heavy erection equipment – Launching
Gantries or High Capacity cranes. When the alignment passes through roads of very
restricted width; deployment of such equipment is not possible. In such situations,
engineers have to look for further alternatives. These can be use of cast in situ
construction, or use of structural steel composite superstructure, which facilitates
reduction in weight of prefabricated girders; and obviates need for using high capacity
erection equipment.
There is a general feeling against use of structural steel girders in composite bridge
decks mainly due to two reasons: Higher cost and Corrosion Performance. However, in
certain situations, use of structural steel girders may be dictated by site constraints;
and the cost, if higher needs to be provided for in budgeting. The second issue of
corrosion performance can be addressed by a suitable choice of girder section, which
will enable easy maintenance.
4. Steel composite Bridge deck systems
Structural Steel Composite Bridge Decks consist of structural Steel girders with
Reinforced Concrete Deck Slabs. The deck slab transfers deck loads by transverse
spanning to the main girders spanning longitudinally. The system is designed to
develop composite action in longitudinal direction between the RCC deck and Steel
girders by providing shear connectors between the flange of the steel girders and deck
slab. The deck slab is cast in situ. The action is illustrated in Fig. 1 below:
Fig.1 Composite Action of Structural Steel Girders with RCC Deck Slab
Steel girders can be of various types; viz. Plate Girders, Box Girder, Multiple Box girders,
Steel Trusses or multiple Steel Trusses in place of individual girders spanning between
piers. The different types are illustrated in the figures below:
Fig. 2 Multiple Plate Girders
Fig. 3 Multiple Plate Girders Examples of Constructed bridges
Fig. 4 Twin Plate Girders with Transverse Composite Deck Slab
Fig. 5 Twin Plate Girders with Stringer Beams and Composite Deck Slab
Fiig.6 Composite Tapered Box Girder with Very Wide RCC Deck Slab
Fiig.7 Composite Twin Tapered Box Girder with Wide RCC Deck Slab
Fig.8 Composite Action of Structural Steel Trusses with RCC Deck Slab
Fig. 9 Modern Aesthetic Steel Girder Types With Composite Deck Slab
Fig. 10 Multiple Triangular Steel Trusses With Composite Deck Slab
Fiig.11 Composite Multicell Tapered Box Girder with Very Wide RCC Deck
Slab
5. Suitable Choice for an Urban flyover
Urban flyovers are normally designed for two lanes or three lanes of traffic, without
footpath. Normal span range is from 20 m to about 30 m. Obligatory spans are of longer
span length of 40 m and beyond. Choice of the deck system chosen for normal spans
needs to be changed for obligatory spans. This is normally the case even for flyovers
constructed using Prestressed concrete Superstructure. The carriageway width is 7.5 m
(Two Lane) or 11.25 m (Three Lane). Adding for Crash Barriers on both sides; the total
deck width is normally 8.5 m or 12.25 m. If Multiple Plate girders or Truss Type Girders
are adopted, a minimum of 4 girders will be needed for Two Lane flyovers and a
minimum of 5, preferably 6 girders will be needed for 3 lane flyovers. The girders can be
prefabricated in a separate fabrication shop, suitably located away from the site, and
brought to site on low bed trailers. Girders are erected using cranes, single or two
cranes operating in tandem. Deck system with even number of girders are technically
superior; as two girders can be braced together with intermediate diaphragms before
erection. This ensures lateral stability of girders during erection.
Single box for superstructure will be comparatively wider, and may pose difficulties for
transportation and handling, especially if fabricated in full length. To restrict weight and
dimensions for transportation, the girder may have to be fabricated in three or four
segments. All the span will therefore need intermediate staging supports; where
smaller prefabricated box segments can be erected. Joints and splices between the
segments will have to be done in situ. This will increase cycle time for erection of the
box girders.; and will also jeopardize fabrication quality compared to full scale
fabrication in fabrication shop.
It is possible to adopt Twin box girders or Three box girders under the deck. With this
arrangement, it will be more feasible to fabricate full length box girders, which can be
transported from the fabrication yard, and erected in full length, using a single crane or
two cranes in tandem of suitable capacity. Three box girders may be more suitable,
considering preference of IRC specifications for a minimum of three longitudinal girders
in bridge spans. The weight of individual girder will be much smaller, if three girders per
span are adopted. This will be helpful as smaller capacity cranes can be deployed for the
job, which will be more suitable for operation within the restricted working space
available in the congested area, although girder transportation and erection will have to
be necessarily done during night hours, when the traffic is expected to be minimal, and
diversion / stoppage of the same will not pose problems, or inconvenience to the
general public.
Box girders can be meticulously fabricated such that after completion of fabrication, the
girders can be given proper anticorrosive coatings from inside before closure from the
top and ends. After closure, since the inside of the girders is hermetically sealed, no
painting may be needed from inside during service life. It should be enough to paint
only outside surfaces of the box girders.
Box girders as such have following distinct advantages over plate girders, considering
structural behaviour , aesthetics and maintenance, in Indian environment.
Box girders have better torsional behavior; better lateral and torsional stability,
compared to plate girders. Single box girders can therefore be handled and erected
without lateral bracings for longer lengths.
In Plate girders all the stiffeners are visible. In box girders all the stiffeners can be
provided inside the box; and hidden from the view. No external stiffeners are
needed. Thus external surfaces are clean.
External surfaces do not have horizontal projections, unlike plate girders. The
horizontal flanges are potential places to gather dust, and become eye sores later
during service life. Cleaning of these areas cause additional maintenance
requirements.
Depths of box girders can be lower than the depths of plate girders; and will result
in a sleek superstructure. However, adopting very sleek sections (L/D = 20)
normally requires higher thickness of the plates in the lower flange and webs. This
will need special precautions during fabrication, and especially during welding.
Quality control on fabrication and welding will have to be more stringent, needing
special tests and frequent inspection. Rejection of fabricated components can also
be expected. Considering that Steel Composite flyover systems in our country is still
in the process of development. It is advisable to restrict the L/D ratio to about 16,
which will result in plate thicknesses which are quite moderate, and fabrication will
be easier.
For obligatory spans also, two or three box girders can be adopted, instead of a
single box girder, for uniformity in appearance. However, considering larger length;
full length girder may not be feasible for these spans. A couple of staging towers
will be necessary for erection of fabricated units / segments; which will have to be
spliced in situ. The staging towers will have to be protected by temporary
barricading, and use of sand filled barrels with rubber tires around them, to take
care of accidental impact due to vehicles. If multiple box girders are adopted, it will
be necessary to provide intermediate diaphragms connecting the girders in
transverse direction; for improved structural behavior, considering longer lengths
of obligatory spans. These girders can also be in the shape of box girders, so that
general appearance of the superstructure is not vitiated by the transverse girders.
Box girders give batter aesthetic appearance. These can be with tapered webs.;
which may be preferred for aesthetics. However, if the alignment is curved, and
radius of curvature is smaller; curved box girders (in plan) may have to be adopted.
It will also improve aesthetic appearance considerably. With tapered webs,
fabrication of curved box girders will be quite complicated, needing much more
precision, and development of more detailed fabrication / shop drawings.
Proportion of wastage in fabrication will also increase, leading to increased cost for
fabrication. This point should also be considered while choosing type of box girders,
whether with tapered or with vertical webs.
6. Conclusion
This paper discusses different types of deck systems for urban flyovers, and advantages
of Structural Steel Composite bridge decks over prestressed concrete decks, in specific
urban areas where alignment passes through very congested locality and with many
restrictions on access route in transportation and erection of precast / prefabricated
structural components, for location, maneuvering and operation of erection
equipment. Solution for ease in maintenance by choosing suitable girder profiles is also
suggested.
7. Acknowledgement
The authors are grateful to the organizers for extending invitation to contribute paper
for this National Conference CEMCON 2014 on Composite Construction & Modern
Concrete.

Contenu connexe

Tendances

Bridge
Bridge Bridge
Bridge
illpa
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Piyush Kumar Santhalia
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
AELC
 

Tendances (20)

Composite deck bridge systems
Composite deck bridge systemsComposite deck bridge systems
Composite deck bridge systems
 
Bridge
BridgeBridge
Bridge
 
Essentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designersEssentials slide in bridge construction a guide for bridge designers
Essentials slide in bridge construction a guide for bridge designers
 
Bridge
Bridge Bridge
Bridge
 
ppt
pptppt
ppt
 
Undergraduate major project_-_design_of
Undergraduate major project_-_design_ofUndergraduate major project_-_design_of
Undergraduate major project_-_design_of
 
Construction methods of Bridges and its types
Construction methods of Bridges and its typesConstruction methods of Bridges and its types
Construction methods of Bridges and its types
 
Bridges precast
Bridges precastBridges precast
Bridges precast
 
Concrete bridge-design-to-bs5400
Concrete bridge-design-to-bs5400Concrete bridge-design-to-bs5400
Concrete bridge-design-to-bs5400
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
Cantilever bridge construction
Cantilever bridge constructionCantilever bridge construction
Cantilever bridge construction
 
presentation
presentationpresentation
presentation
 
Bridge
BridgeBridge
Bridge
 
Bridge
BridgeBridge
Bridge
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Bridges by span
Bridges by spanBridges by span
Bridges by span
 
Bridge introduction
Bridge introductionBridge introduction
Bridge introduction
 
Bridge Lecture Slide by Micotol
Bridge Lecture Slide by MicotolBridge Lecture Slide by Micotol
Bridge Lecture Slide by Micotol
 

Similaire à Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena

Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
Rajendra Jhurawat
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
Sravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
Civil Engineers
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
toddr4
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
FAIZAL MUHAMMED
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Dr.Subramanian Narayanan
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
atiulla001
 

Similaire à Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena (20)

fastrack technologies in bridges ppt
fastrack technologies in bridges pptfastrack technologies in bridges ppt
fastrack technologies in bridges ppt
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Jaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training reportJaipur metro rail corporation summer training report
Jaipur metro rail corporation summer training report
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Full span hsr guideway 02 12 2015
Full span hsr guideway 02 12 2015Full span hsr guideway 02 12 2015
Full span hsr guideway 02 12 2015
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Presentation PPT.pdf
Presentation PPT.pdfPresentation PPT.pdf
Presentation PPT.pdf
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
Futuristic Composite Bridges-ING IABSE June 2016-pp 1-11
 
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
IRJET- Integral Abutment Bridge- A Review and Comparison of the Integral Brid...
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
 
Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!
 

Composite construction in Bridge Deck systems by Suhas Khedkar Kishore Saxena

  • 1. Composite construction in Bridge Deck systems A Solution in City Environment for Speedy Construction with Industrialized Full Length Prefabrication By, Suhas Khedkar , Kishore Saxena Abstract Rapid construction of flyovers in congested cities has become necessary, considering the present traffic trends, and anticipated growth in future. Construction has to be done without closure of roads and with minimum disturbance to the existing traffic. Use of Precast and Prefabricated components for superstructure help in reduction of construction time, as superstructure components can be kept ready elsewhere, when construction of foundations and substructure is in progress. Erection of such components can be planned during night hours, when the traffic is minimal; thus causing least hardships to the general public. Many flyovers have been constructed in our country using full length precast prestressed girders, and cast in situ deck slab. Flyovers with full length prefabricated girders in structural steel and composite RCC deck slab are very few. This paper presents advantages of such structural system for congested cities. Key Words: Structural Steel Bridge Girders, full length Industrialized Prefabrication , working window, girder transportation , site erection 1. General Many of our cities are very busy, over populated, and congested for both living conditions, and traffic situation. The existing infrastructure is already overtaxed. This is not only true in case of the major metropolitan cities, but also in case of second and third level cities, particularly those in the vicinity of major cities. All these cities and urban areas need better infrastructure for decongesting traffic. While the metropolitan cities are moving from the era of flyover construction, to construction to that of Elevated Transportation Corridors, covering multiple junctions, and longer routes measuring in kilometres; smaller developing cities and towns need flyover bridges over busy traffic junctions to help in decongestion of traffic. The typical site conditions pose many constraints to any new construction. Although there are site specific problems, many constraints are common. Engineers can adopt standard solutions in such situations. The same can be modified suitably to address site specific issues, by a judicious mix of different solutions. 2. Typical constraints in construction of flyovers in congested cities Construction of flyovers in cities must be done in busy and congested city environment, respecting all aspects: viz. No / minimal disturbance to traffic, safety of the citizens,
  • 2. availability of small working windows, coordination with local bodies etc. All these need to fit into the tight construction schedule, which is the basic demand of the present times. The alignment of flyovers many a time passes through area with heavy encroachment, further restricting available working space for construction. This needs suitable consideration in designs, which may demand basic changes such as different type of structure and construction materials. Sometimes the site constraints may dictate choice of structural steel instead of Prestressed concrete (which is a normal choice for construction); considering limitation of transportation and erection of heavy segments and girders. It may also be a chosen solution by the owners to ensure speedy and easier construction. 3. Possible solutions, Pros and Cons Conventional method is to use cast in situ superstructure. However, it is time consuming; as the construction is strictly sequential - Foundation, Substructure, and then Superstructure by using scaffolding and formwork under each span. Construction time can be reduced if precast superstructure elements are used, as precasting can be done as a parallel activity when construction of foundations and substructure is in progress at site. Such construction does not need staging under each span, if the precast elements are erected using launching equipment. Main advantage of using Precast / prefabricated structural elements being utilising time required for construction of foundations and substructure for casting / fabricating superstructure elements in a Precast Yard / Fabrication shop. Such construction helps in achieving much better quality control, as it happens in a dedicated , specially designed casting yard / fabrication shop; in controlled conditions and factory like environment; which is another major advantage of such construction. Thus precasting / prefabrication is called as Industrialised Construction. Normal methods of superstructure construction of such urban flyovers, therefore; is to use full length concrete girders or concrete box girder segments; precast in a dedicated Casting Yard for the purpose, normally distant from the site; transported to respective spans using a specially designed trailer, and erected using high capacity cranes or a Launching Gantry, designed to suit the size and weight of segments, and span length. The method is well established, and many flyovers and elevated roads have been constructed using the method in various parts of our country. However, weight of precast concrete elements, whether full length girders or box girder segments typically ranges from 45 t upwards; and needs large capacity trailers for transportation of the girders / segments and heavy erection equipment – Launching Gantries or High Capacity cranes. When the alignment passes through roads of very restricted width; deployment of such equipment is not possible. In such situations, engineers have to look for further alternatives. These can be use of cast in situ construction, or use of structural steel composite superstructure, which facilitates reduction in weight of prefabricated girders; and obviates need for using high capacity
  • 3. erection equipment. There is a general feeling against use of structural steel girders in composite bridge decks mainly due to two reasons: Higher cost and Corrosion Performance. However, in certain situations, use of structural steel girders may be dictated by site constraints; and the cost, if higher needs to be provided for in budgeting. The second issue of corrosion performance can be addressed by a suitable choice of girder section, which will enable easy maintenance. 4. Steel composite Bridge deck systems Structural Steel Composite Bridge Decks consist of structural Steel girders with Reinforced Concrete Deck Slabs. The deck slab transfers deck loads by transverse spanning to the main girders spanning longitudinally. The system is designed to develop composite action in longitudinal direction between the RCC deck and Steel girders by providing shear connectors between the flange of the steel girders and deck slab. The deck slab is cast in situ. The action is illustrated in Fig. 1 below: Fig.1 Composite Action of Structural Steel Girders with RCC Deck Slab Steel girders can be of various types; viz. Plate Girders, Box Girder, Multiple Box girders, Steel Trusses or multiple Steel Trusses in place of individual girders spanning between piers. The different types are illustrated in the figures below:
  • 4. Fig. 2 Multiple Plate Girders
  • 5. Fig. 3 Multiple Plate Girders Examples of Constructed bridges Fig. 4 Twin Plate Girders with Transverse Composite Deck Slab Fig. 5 Twin Plate Girders with Stringer Beams and Composite Deck Slab
  • 6. Fiig.6 Composite Tapered Box Girder with Very Wide RCC Deck Slab Fiig.7 Composite Twin Tapered Box Girder with Wide RCC Deck Slab Fig.8 Composite Action of Structural Steel Trusses with RCC Deck Slab
  • 7. Fig. 9 Modern Aesthetic Steel Girder Types With Composite Deck Slab Fig. 10 Multiple Triangular Steel Trusses With Composite Deck Slab Fiig.11 Composite Multicell Tapered Box Girder with Very Wide RCC Deck Slab 5. Suitable Choice for an Urban flyover Urban flyovers are normally designed for two lanes or three lanes of traffic, without footpath. Normal span range is from 20 m to about 30 m. Obligatory spans are of longer span length of 40 m and beyond. Choice of the deck system chosen for normal spans
  • 8. needs to be changed for obligatory spans. This is normally the case even for flyovers constructed using Prestressed concrete Superstructure. The carriageway width is 7.5 m (Two Lane) or 11.25 m (Three Lane). Adding for Crash Barriers on both sides; the total deck width is normally 8.5 m or 12.25 m. If Multiple Plate girders or Truss Type Girders are adopted, a minimum of 4 girders will be needed for Two Lane flyovers and a minimum of 5, preferably 6 girders will be needed for 3 lane flyovers. The girders can be prefabricated in a separate fabrication shop, suitably located away from the site, and brought to site on low bed trailers. Girders are erected using cranes, single or two cranes operating in tandem. Deck system with even number of girders are technically superior; as two girders can be braced together with intermediate diaphragms before erection. This ensures lateral stability of girders during erection. Single box for superstructure will be comparatively wider, and may pose difficulties for transportation and handling, especially if fabricated in full length. To restrict weight and dimensions for transportation, the girder may have to be fabricated in three or four segments. All the span will therefore need intermediate staging supports; where smaller prefabricated box segments can be erected. Joints and splices between the segments will have to be done in situ. This will increase cycle time for erection of the box girders.; and will also jeopardize fabrication quality compared to full scale fabrication in fabrication shop. It is possible to adopt Twin box girders or Three box girders under the deck. With this arrangement, it will be more feasible to fabricate full length box girders, which can be transported from the fabrication yard, and erected in full length, using a single crane or two cranes in tandem of suitable capacity. Three box girders may be more suitable, considering preference of IRC specifications for a minimum of three longitudinal girders in bridge spans. The weight of individual girder will be much smaller, if three girders per span are adopted. This will be helpful as smaller capacity cranes can be deployed for the job, which will be more suitable for operation within the restricted working space available in the congested area, although girder transportation and erection will have to be necessarily done during night hours, when the traffic is expected to be minimal, and diversion / stoppage of the same will not pose problems, or inconvenience to the general public. Box girders can be meticulously fabricated such that after completion of fabrication, the girders can be given proper anticorrosive coatings from inside before closure from the top and ends. After closure, since the inside of the girders is hermetically sealed, no painting may be needed from inside during service life. It should be enough to paint only outside surfaces of the box girders.
  • 9. Box girders as such have following distinct advantages over plate girders, considering structural behaviour , aesthetics and maintenance, in Indian environment. Box girders have better torsional behavior; better lateral and torsional stability, compared to plate girders. Single box girders can therefore be handled and erected without lateral bracings for longer lengths. In Plate girders all the stiffeners are visible. In box girders all the stiffeners can be provided inside the box; and hidden from the view. No external stiffeners are needed. Thus external surfaces are clean. External surfaces do not have horizontal projections, unlike plate girders. The horizontal flanges are potential places to gather dust, and become eye sores later during service life. Cleaning of these areas cause additional maintenance requirements. Depths of box girders can be lower than the depths of plate girders; and will result in a sleek superstructure. However, adopting very sleek sections (L/D = 20) normally requires higher thickness of the plates in the lower flange and webs. This will need special precautions during fabrication, and especially during welding. Quality control on fabrication and welding will have to be more stringent, needing special tests and frequent inspection. Rejection of fabricated components can also be expected. Considering that Steel Composite flyover systems in our country is still in the process of development. It is advisable to restrict the L/D ratio to about 16, which will result in plate thicknesses which are quite moderate, and fabrication will be easier. For obligatory spans also, two or three box girders can be adopted, instead of a single box girder, for uniformity in appearance. However, considering larger length; full length girder may not be feasible for these spans. A couple of staging towers will be necessary for erection of fabricated units / segments; which will have to be spliced in situ. The staging towers will have to be protected by temporary barricading, and use of sand filled barrels with rubber tires around them, to take care of accidental impact due to vehicles. If multiple box girders are adopted, it will be necessary to provide intermediate diaphragms connecting the girders in transverse direction; for improved structural behavior, considering longer lengths of obligatory spans. These girders can also be in the shape of box girders, so that general appearance of the superstructure is not vitiated by the transverse girders. Box girders give batter aesthetic appearance. These can be with tapered webs.; which may be preferred for aesthetics. However, if the alignment is curved, and radius of curvature is smaller; curved box girders (in plan) may have to be adopted. It will also improve aesthetic appearance considerably. With tapered webs,
  • 10. fabrication of curved box girders will be quite complicated, needing much more precision, and development of more detailed fabrication / shop drawings. Proportion of wastage in fabrication will also increase, leading to increased cost for fabrication. This point should also be considered while choosing type of box girders, whether with tapered or with vertical webs. 6. Conclusion This paper discusses different types of deck systems for urban flyovers, and advantages of Structural Steel Composite bridge decks over prestressed concrete decks, in specific urban areas where alignment passes through very congested locality and with many restrictions on access route in transportation and erection of precast / prefabricated structural components, for location, maneuvering and operation of erection equipment. Solution for ease in maintenance by choosing suitable girder profiles is also suggested. 7. Acknowledgement The authors are grateful to the organizers for extending invitation to contribute paper for this National Conference CEMCON 2014 on Composite Construction & Modern Concrete.