SlideShare une entreprise Scribd logo
1  sur  32
Télécharger pour lire hors ligne
Power Procurement Strategy
01.03.16
IIT-Kanpur
ForPublic Use
POWER SECTOR OVERVIEW
Source:ExecutiveSummary of October 2015, CEA *including renewable generation
Category
Installed
Capacity
(MW)
Share in
Total(%)
Generation
(BUs)
Share in
Total(%)
Coal 170,138 61% 836 80%
Gas 24,473 9% 41 4%
Diesel 994 0.4% 1.4 0%
Hydro 42,473 15% 129 12%
Nuclear 5,780 2% 36 3%
RE 36,471 13% - -
Total 280,328 1042
Installed Capacity (All)
Coal,61%Hydro,
15%
RE, 13%
Gas
9%
Nuclear,2%
Diesel,0.4%
Source:ExecutiveSummary of October 2015, CEA *including renewable generation
Category
Installed
Capacity(MW)
Share in total
RE (%)
Wind Power 23,763 65%
Small Hydro 4,102 11%
Bio Power 4,546 12%
Solar 4,061 11%
Total 36,471
Installed Capacity (Renewable)
Wind
Power,
65%
Bio Power,
13%
Small
Hydro, 11%
Solar,
11%
16.73 19.25
27.28
67.55
88.5
100
0
20
40
60
80
100
120
8th Plan 9th Plan 10th Plan 11th Plan 12th Plan
(2012-17)
13th Plan
(2017-22)
GigaWatt
Generation CapacityAddition (GW)
69.21
Actual
till
Oct’15
• Investmentsof around US$ 225 billion planned for the power sector during the 12th Plan.
• In addition, Renewable energy capacity of 175 GW is planned till 2022.
Source:CEA
Growing impetus on capacity addition
Ambitious targets to capacity addition
Power Situation in the Country
Year
Installed Capacity
(at the end of FY)
(MW)
PeakMet
( MW )
2009-10 1,59,398 1,04,009
2010-11 1,73,626 1,10,256
2011-12 1,99,877 1,16,191
2012-13 2,23,344 1,23,294
2013-14 2,43,029 1,29,815
2014-15 2,67,367 1,41,160
2015-16* 2,843,03 1,48,463
• In last six years, capacity has increased by 1,24,905 MW and demand has
increasedby 44,454 MW only.
• The country as a whole has witnessed a decline in the deficits.
Source:Executive Summary, Power Sector, CEA, *Upto Dec, 2015
Financial health of Generators
• Total installed capacity in the Country is 2,80,328 MW
• Peak demand met : 1,48,005 MW
• PLF of coal/lignite plants
– Around 65% in FY 14-15
– Around 62% in FY 15-16 (till Oct)
– FY 07-08 - 78%
• PLF of gas based plants: 25% due to shortage of fuel
• Stranded capacity in the country: A total 50,000 MW stressed
– 27,880 MW of coal capacity stranded
– 24,000 MW of Gas based Capacity stranded
• Key Issues: Lack of fuel, Transmission, Competition, Weak distribution
system, Discoms’ inability to buy
Financial Health of Discoms
• Discomsaccumulated losses stand at about 3 lakh crores
• Yearly losses of Discomsis about Rs 70,000 crore
• The gap between average cost of supply of power and average
tariff is about 80 paise per unit.
• Most of the Discomsin the country incurring losses .
• No investment is being made in the Distribution infrastructure and
intra-statetransmission network resulting in intrastate congestion
• States prefer to do load shedding than buying cheap power from
Exchange.
State wise status
Population (in Cr)
Avg. MW Supply
FY 14-15
Per Capita Consum kWh
(2011-12)
Punjab 2.8 5,623 1,799
Gujarat 6.0 9,344 1,663
Haryana 2.5 5,978 1,628
Delhi 1.7 3,991 1,587
Chhattisgarh 2.6 3,810 1,320
Himachal Pradesh 0.7 1,287 1,289
Tamil Nadu 7.2 10,517 1,277
Uttarakhand 1.0 1,529 1,232
Maharashtra 11.2 11,507 1,204
Andhra Pradesh 8.5 10,034 1,157
Odisha 4.2 3,099 1,146
Karnataka 6.1 6,803 1,081
Jammu & Kashmir 1.3 1,296 1,015
Rajasthan 6.9 6,529 927
Jharkhand 3.3 844 790
Madhya Pradesh 7.3 7,171 672
Kerala 3.3 1,935 594
West Bengal 9.1 5,319 564
Uttar Pradesh 20.0 9,916 450
Assam 3.1 679 250
Bihar 10.4 1,538 134
Long Term
Short-Term
PPA for over 25 yearsthrough long term
Source:Percentageasper CERC Reporton ShortTerm Power Market FY-14
93.86%
6.1%
90.5%
Throughtraders 3.2% 3.4%
DirectBilateral 0.5% 1.5%
9.5%
Exchanges 0.4% 2.73%
UnscheduledInterchange 2.1% 1.9%
FY 2009 FY 2015
• Short term market grew at an encouragingrate with a CAGR of 22% (FY-09 to FY 15).
• Power Exchanges witnessed growth at a CAGR of 62% (FY-09 to FY 15).
Indian Power Market Snapshot
Coal production and supply
in the Country
Total Coal
Production (MT)
YoYinc (%) Import (MT) YoYinc (%)
Import Cost
(CroresINR)
2009-10 532 73 39,180
2010-11 533 0.12% 69 -5.92% 41,550
2011-12 540 1.36% 103 49.24% 78,838
2012-13 556 3.05% 146 41.74% 86,846
2013-14 566 1.68% 167 14.45% 92,329
2014-15 612 8.25% 212 27.12% 1,04,524
11
• In FY 15, the domestic coal production increased by 8.5% to 612 MT.
• The GoI has set a target of increasing domestic coal production to
1.5 billion tonnes (including one bt from CIL) by FY 2021
• This could create a surplus situation and reduce import of coal
which in FY 15 was worth Rs.1045 Billion.
Source:Coal Statistics, Ministry of Coal
Impact of coal availability on
Power Markets
• Increased availability of coal for the power sector has had a positive
impact.
• Generation has increased by 6% and many stranded plants have started
operating
• Sale of power on IEX has increased
12
Source:Demand and Supply of Coal from Coal Statistics 2014-15, Ministry of Coal
3.61
3.28
3.89 3.76
4.49
4.18 4.17
2.68 2.62 2.56 2.74 2.82
3.68
3.03
0.00
1.00
2.00
3.00
4.00
5.00
0
1000
2000
3000
4000
5000
6000
7000
Apr May Jun Jul Aug Sep Oct
Price(Rs./kWh)
AverageDailyMW
Average Daily Sale Bids (MW) and Market Clearing Price
2014-15 2015-16 2014-15 2015-16
Price and Volume: Bilateral vs. IEX DAM
2.62 6.17 11.80 13.79 22.35 28.92 28.12 16.27
21.92
26.72
27.70
35.84 36.64
35.11 35.50
20.37
7.16
5.33
3.58 3.47
3.73
2.87
3.46
2.80
7.46
5.32
4.74
4.23 4.34 4.24
4.30
4.06
-1
1
2
3
4
5
6
7
8
-
5
10
15
20
25
30
35
40
FY08-09 FY09-10 FY10-11 FY11-12 FY12-13 FY13-14 FY14-15 FY15-16
Price(Rs./kWh)
Volume(BU)
IEX Volume Trader Volume IEX Price Bilateral Price
Prices at the Exchange have always been lower than Bilateral Prices
*Data up to Sep 2015, Source: CERC MMC Reports
Opportunities for DISCOMS
Option with the Discoms: Utilising Exchange Market
• PPA for base load only
i. Discoms should tie-up PPA only to manage their base
demand
ii. Many Discoms have tied PPAs to meet their peak
demand as well. The Discoms have to pay the capacity
charge for this quantum even in the off peak time
example Gujarat, Haryana, Delhi, Punjab
iii. So for optimum utilisation, Long Term PPA should be
only for base demand and seasonal variations should
be bought through other available market options
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
36
34
32
30
28
26
24
22
PPA (Base load) contract
ShortTerm Market (for Peak Load)
Day Ahead
Sell
BuyBuy
Sell
Forecasted
demand
Ancillary
Service
Intra Day
Market
Real-time
demand
Surpluses/Deficits - Balance physical supply and demand
Meeting Shortages/Surplus through STM
Maximizing efficiency – Ideal Scenario
Forecasted Demand
Curve of the Discom
Actual Demand Real time variations
Cost Optimizationthrough Exchange
Replacement of high variable cost power by Exchange
power
• Replacement of high variable cost power by Exchange power
I. Under long termPPA two component
• Capacity charges (commitment charges): paid irrespective of whether
discom purchase power from these plants or not
• Energy charges : Paid corresponding to the number of units of power
purchased from that particular plant
II. Discoms can replace costlier long termpower by procurementfrom IEX,if,
• Energy charge of power plant is greater than IEX rates
• During night hours prices at IEX are further low and savings can be
enhanced
III. Discoms can continue paying fixed charge to Long Term PPAs and
substitutewhereenergycharge is higher than IEX price
IV. IEX prices are around 25%-30% lower than the Bilateral Prices
Cost Optimisation by Discoms
• Discoms can devise least cost option to meet demand in the state by tracking prices
at IEX
– Energy chargegreaterthan prevailingACP can be substituted with powerfrom IEX
– During off-peakhours,when prices atIEX are low, savings can be enhanced replacingpower
from LT to PX Transactions
Type DispatchMode
Capacity
(MW)
Energy Charge
(INR/kWh)
Plant A Hydro MustRun 100 0.00
Plant B Hydro MustRun 150 0.00
Plant C Nuclear MustRun 500 2.80
Plant D Coal Merit 120 3.00
Plant E Coal Merit 120 3.20
Plant F Coal Merit 100 3.50
Plant G Coal Merit 90 3.80
Plant H Coal Merit 90 4.00
Merit BasedCapacity (MW) 520
Substitutedwithpower@INR
2.50 during off peakhours
fromIEX
Substitutedwithpower@INR
3.45 from IEX
ACP=
INR3.45/kWh
Merit Order for Dispatch in State
Off-peak ACP=
INR2.50/kWh
*Assumptions:12 number of hours areconsidered in off-peak hours
PotentialSavings: INR 50 Crore a month
Discoms exhaust long term and
medium term contracts first
despite availability of power at
cheaper prices at PXs
Long Term
Medium Term
Short Term
Purchase on economic principle of Merit Order
Optimization of Power Procurement Cost
PPA 1 I 3.70
PPA 2 I 4.06
Long Term
Contracts
Bilateral
Contracts
Exchange
CapacityTied up by Discom
IEX Price I 2.45
Merit Order Baseline
PPA 3 I 3.00
PPA 4 I 1.99
PPA 5 I 2.00
PPA I Variable
Cost
Must Run Plants
(includes all hydro, nuclear or
other ‘take or pay’ type
contractual plants)
Contract1 I 4.70
Contract2 I 3.50
Contract3 I 2.10
Merit order dispatch schedule to be prepared based on
Variable cost and considering Exchange Prices
PPA 1 I 3.70
PPA 2 I 4.06
IEX Price I 2.45
PPA 3 I 3.00
PPA 4 I 1.99
PPA 5 I 2.00
Must Run Plants
(includes all hydro, nuclear or
other ‘take or pay’ type
contractual plants)
Contract1 I 4.70
Contract2 I 3.50
Contract3 I 2.10
IncreasingVariableCost
TobedispatchedinthisOrderbasedonEnergy
DemandoftheDiscom
Merit Order Baseline
Merit order dispatch schedule to be prepared based on
Variable cost and considering Exchange Prices
Replacement Potential:
Regionwise plants with high variable cost as compared to IEX prices
Region Station Capacity (MW)
Energy Charge
(Rs/kWh)
IEX Price in the Region*
(Rs./kWh)
East
Barh 660 4.06
2.22Farakka-I , II & III 2100 2.78 - 2.8
Kahalgaon-I & II 2340 2.42 - 2.57
North
Badarpur TPS 705 5.09
3.18
Auraiya-Wtd 663 4.36
Dadri-Wtd 830 4.27
NCTPP Dadri I & II 1820 3.81 - 4.18
Tanda 440 3.63
Anta-Wtd 419 3.55
Faridabad-Wtd 431 3.35
Unchahar-I, II & III 1050 2.89
South
Simhadri-I & II 2000 2.74
2.99
Ramagundam I, II & III 2600 2.54 - 2.71
West
Mouda 1000 3.89
2.18Kawas-Wtd 656 3.36
Gandhar-Wtd 657 3.28
*IEX Average area prices for the month of June'15
Cost Optimisation Potential in Bihar
Annual: Plant-wise
Source:
• Variable Cost taken from ARR of NBPDCL & SBPDCL
• Variable Cost of Rs. 4.06 is considered as 4.06 for April 15 as per ARR of FY 2015-16
• Source for Volume:
• Volume of CGS taken from ERPC
• Volume of SGS taken from ARR
S. No Power Plant
Allocated
Capacity
(MW)
Variable
Cost-FY15
(Rs./kWh)
Replaceable
Volume (MU)
Annual
Volume
(MU)
Potential
Savings (Cr)
1 KBUNL Stage 1 U-1 220 4.06 700 700 112
2 BARH STPS II 430 4.06 1,290 1,290 174
3 Adani-Gujarat 300 3.17 515 1,612 20
4 Barauni TPS 220 3.00 359 836 9
5 Farakka STPS I & II 379 2.80 1,189 3,429 18
6 Farakka STPS III 55 2.78 203 714 2
7 KhSTPS I 293 2.57 223 2,220 0
8 KhSTPS II 78 2.42 0 515 0
9 Talcher STPS I 344 1.47 0 2,855 0
10 GMR 200 1.46 0 870 0
Total 2,419 4,476 15,041 335
Cost Optimization by Bihar
• Bihar has initiated the process of Cost Optimization
• The costlier power from Barh & Dadri stations is replaced by
the cheaper power from IEX.
• The Energy Charges of these power plants are greater than
the IEX rates.
• Bihar has made a saving of over 11 crores in 21 days
Due to low prices at the Exchange there is further potential to
increase savings
Utility Software created by IEX for Bid
Optimization
• IEX has created a utility software for Discoms and is providing it
free of cost
• The software is customised for each Discom to take into account
its existing PPAs along with their variable cost and status of must
run plants etc.
• Based on the inputs fed into the software, it provides with the
optimisation bid which should be put into the IEX bidding platform
along with details of backing down if the Bid is selected
• Benefits:
– Discoms need not be bothered about Exchange prices for bidding
– The software will create bid as per the Discoms merit order and other
constraints fed to it
– On acceptance of the Bid, the Discom can backdown the plants
Banking Transactions
• Banking transactions takes place directly between
Discoms, the transactions are cashless in nature,
where one Discom banks power to other for utilising
it later.
• Commercial considerations required for Banking
transactions with the reference price available.
Case Study: Banking @ 500 MW quantum
MONTH
DRAWALby
Discom-1 (MUs)
IEX PRICE
(Rs/KWh)
DRAWALby
Discom-2 (MUs)
IEX PRICE
(Rs/KWh)
Nov'14 365 2.63
Dec'14 372 2.96
Jan'15 372 2.70
Feb'15 320 2.60
Jun'15 350 3.18
Jul'15 362 3.2
Aug'15 362 2.64
Sept'15 372 3.43
Weighted Avg (as per
dataavailaible)
1429 2.72 1446 3.11
TOTAL 1429 2.72 1446 3.11
Profit/Lossto
Discom-1 Rs Crore
(60)
Cost BenefitAnalysis for Open Access Consumer
*Assumption: Buy Quantity is 10 MW for 24 hours and 1000 Portfolios are selected everyday
VoltageLevel 33 kV 132 kV
VolumeTraded in MW 10 10
HoursTraded 24 24
Total Volume in MWh (at Regional Periphery) 240 240
IEX Rate at Regional Periphery (inINR per unit) 3.00 3.00
Losses
AssamWithdrawalPOCLoss 2.05% 2.05%
StateLoss 3.64% 3.64%
Wheeling Losses 17.60% 0.00%
Cost After Losses (inINR per unit) 3.73 3.17
Charges
StateTransmission Charges (in Rs/unit ) 0.42 0.42
AssamWithdrawalPOCCharges (in Rs/unit) 0.17 0.17
Wheeling Charges(in Rs/unit) 0.22 0.00
NLDC Operating Charges+ NLDCApplication Charges + SLDCCharges* 0.03 0.03
IEX Transaction Charges @ Rs 20 per MW (in INR/unit) 0.02 0.02
ProfessionalFees ( If transacted through Member)* * 0.02 0.02
CrossSubsidy Charges (in INR/unit) 0.54 0.54
IEX Rate @ ex ABTMeter (inINR/unit) 5.15 4.37
Energy Charges (inINR/unit) 7.16 7.16
Savings Per Unit (inINR/unit) 2.01 2.79
Cost saving potential for Industries
Comparison with State tariff
*IEX Landed cost calculated at Rs 3 per unit, the actual price on
most days is lower than this
6.35
6.50
5.65
7.66
6.00
7.01
4.80
6.14
7.16
5.50
4.70
6.33 6.20
5.60
4.20
3.73
4.17 3.99
6.09
4.62
5.28
3.65
4.90
5.15
4.47
4.04
5.64 5.67
5.26
4.16
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
HT Tariff @ 33 kV IEX Landed Cost @ Rs 3 / unit
Thank You
31
Growing Share of Short Term Market in
Total Gen.
2.7 7.1 13.5 14.8
23.0
30.0 29.4
14.9
26.8
29.7
36.6
36.6
35.8 34.56
3.3
6.2
10.3
15.4
14.5
17.4 15.58
14.4
25.8
28.1
27.8
24.8
21.5
19.45
7.4%
8.6%
10.0%
10.8% 10.9% 10.9%
9.5%
0%
2%
4%
6%
8%
10%
12%
0
20
40
60
80
100
120
FY08-09 FY09-10 FY10-11 FY11-12 FY12-13 FY13-14 FY14-15
ShareofShortTermTradeinTotGen(%)
Volume(BU)
PXs Trader Direct UI Share of ST in Tot Gen
• Short term market growing at an encouragingrate with a CAGR of 22% in the past six years.
• Power Exchanges witnessing growth at a CAGR of 62% (last six years).32

Contenu connexe

Tendances

Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in india
Bhargav Parmar
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
IPPAI
 
NTPC LTD.
NTPC LTD.NTPC LTD.
Business Plan: Biomass Power Plant
Business Plan: Biomass Power PlantBusiness Plan: Biomass Power Plant
Business Plan: Biomass Power Plant
Sunil Kumar
 
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South AsiaSAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
IPPAI
 
CDM Potential of Renewable Energy Technologies in India
CDM Potential of Renewable Energy Technologies in IndiaCDM Potential of Renewable Energy Technologies in India
CDM Potential of Renewable Energy Technologies in India
Pallav Purohit
 

Tendances (20)

Solar power projects under rec mechanism in india
Solar power projects under rec mechanism in indiaSolar power projects under rec mechanism in india
Solar power projects under rec mechanism in india
 
Managing fuel supply & uncertainty in India
Managing fuel supply & uncertainty in IndiaManaging fuel supply & uncertainty in India
Managing fuel supply & uncertainty in India
 
Thermal power sector
Thermal power sectorThermal power sector
Thermal power sector
 
Energy
EnergyEnergy
Energy
 
ntpc annual presentation
ntpc annual presentationntpc annual presentation
ntpc annual presentation
 
Power sector reforms
Power sector reformsPower sector reforms
Power sector reforms
 
Power energy generation report
Power energy generation reportPower energy generation report
Power energy generation report
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
 
NTPC LTD.
NTPC LTD.NTPC LTD.
NTPC LTD.
 
Energy in pakistan
Energy in pakistanEnergy in pakistan
Energy in pakistan
 
Making sense of kusum
Making sense of kusumMaking sense of kusum
Making sense of kusum
 
Business Plan: Biomass Power Plant
Business Plan: Biomass Power PlantBusiness Plan: Biomass Power Plant
Business Plan: Biomass Power Plant
 
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South AsiaSAARC Energy Ring - a Vision to Promote Energy Security in South Asia
SAARC Energy Ring - a Vision to Promote Energy Security in South Asia
 
Hydropower in-india-key-enablers-for-better-tomorrow
Hydropower in-india-key-enablers-for-better-tomorrowHydropower in-india-key-enablers-for-better-tomorrow
Hydropower in-india-key-enablers-for-better-tomorrow
 
Making tariff rationalization for domestic consumers a winning proposition fo...
Making tariff rationalization for domestic consumers a winning proposition fo...Making tariff rationalization for domestic consumers a winning proposition fo...
Making tariff rationalization for domestic consumers a winning proposition fo...
 
Cutter - E3 Valuing Storage short
Cutter - E3 Valuing Storage shortCutter - E3 Valuing Storage short
Cutter - E3 Valuing Storage short
 
Electricity Tariffs for the Period 2011-2015 in Sri Lanka
Electricity Tariffs for the Period 2011-2015 in Sri LankaElectricity Tariffs for the Period 2011-2015 in Sri Lanka
Electricity Tariffs for the Period 2011-2015 in Sri Lanka
 
CDM Potential of Renewable Energy Technologies in India
CDM Potential of Renewable Energy Technologies in IndiaCDM Potential of Renewable Energy Technologies in India
CDM Potential of Renewable Energy Technologies in India
 
Renewable energy industry jan 2016
Renewable energy industry jan 2016Renewable energy industry jan 2016
Renewable energy industry jan 2016
 
Ntpc information
Ntpc informationNtpc information
Ntpc information
 

En vedette

Materiales 1º eso 2012 2013
Materiales 1º eso 2012 2013Materiales 1º eso 2012 2013
Materiales 1º eso 2012 2013
IES Heliche
 
Technical Documentation_Glass Break Vehicular Alarm System
Technical Documentation_Glass Break Vehicular Alarm SystemTechnical Documentation_Glass Break Vehicular Alarm System
Technical Documentation_Glass Break Vehicular Alarm System
Emmanuel Chidinma
 
Sist resp(2)
Sist resp(2)Sist resp(2)
Sist resp(2)
zaquel
 
Comentario de mapa de tiempo
Comentario de mapa de tiempoComentario de mapa de tiempo
Comentario de mapa de tiempo
Diego M
 
CONTAMINACION DE El TREN
CONTAMINACION DE El TRENCONTAMINACION DE El TREN
CONTAMINACION DE El TREN
paopu14
 

En vedette (18)

Blok 2012 13 P1 15-09-2012
Blok 2012 13 P1 15-09-2012Blok 2012 13 P1 15-09-2012
Blok 2012 13 P1 15-09-2012
 
Ch34 28
Ch34 28Ch34 28
Ch34 28
 
Deriva continental
Deriva continentalDeriva continental
Deriva continental
 
Actividad 8 taller práctico 10 claves para la implementación de tendencias y ...
Actividad 8 taller práctico 10 claves para la implementación de tendencias y ...Actividad 8 taller práctico 10 claves para la implementación de tendencias y ...
Actividad 8 taller práctico 10 claves para la implementación de tendencias y ...
 
Materiales 1º eso 2012 2013
Materiales 1º eso 2012 2013Materiales 1º eso 2012 2013
Materiales 1º eso 2012 2013
 
SF_A_Part3R7_LP_CDI
SF_A_Part3R7_LP_CDISF_A_Part3R7_LP_CDI
SF_A_Part3R7_LP_CDI
 
Identidad digital 201016
Identidad digital 201016Identidad digital 201016
Identidad digital 201016
 
Practica de word
Practica de wordPractica de word
Practica de word
 
Palestra 7: Empreendendo na produção de leite
Palestra 7: Empreendendo na produção de leitePalestra 7: Empreendendo na produção de leite
Palestra 7: Empreendendo na produção de leite
 
1213 003-tarifes-curs-2012-2013
1213 003-tarifes-curs-2012-20131213 003-tarifes-curs-2012-2013
1213 003-tarifes-curs-2012-2013
 
What is On Page SEO and How to use it?
What is On Page SEO and How to use it?What is On Page SEO and How to use it?
What is On Page SEO and How to use it?
 
מפתחים וחיות אחרות
מפתחים וחיות אחרותמפתחים וחיות אחרות
מפתחים וחיות אחרות
 
Technical Documentation_Glass Break Vehicular Alarm System
Technical Documentation_Glass Break Vehicular Alarm SystemTechnical Documentation_Glass Break Vehicular Alarm System
Technical Documentation_Glass Break Vehicular Alarm System
 
The verb have got
The verb have gotThe verb have got
The verb have got
 
Aula1a
Aula1aAula1a
Aula1a
 
Sist resp(2)
Sist resp(2)Sist resp(2)
Sist resp(2)
 
Comentario de mapa de tiempo
Comentario de mapa de tiempoComentario de mapa de tiempo
Comentario de mapa de tiempo
 
CONTAMINACION DE El TREN
CONTAMINACION DE El TRENCONTAMINACION DE El TREN
CONTAMINACION DE El TREN
 

Similaire à Power procurement strategy--Mr. rohit bajaj

Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2
Faizan Shabbir
 
India : Power Sector Report_August 2013
India : Power Sector Report_August 2013India : Power Sector Report_August 2013
India : Power Sector Report_August 2013
India Brand Equity Foundation
 
Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdf
BlentBulut5
 
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdfPLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
mza.arifin
 

Similaire à Power procurement strategy--Mr. rohit bajaj (20)

Energy Analysis Plays an Important Role in Purchase Decisions
Energy Analysis Plays an Important Role in Purchase DecisionsEnergy Analysis Plays an Important Role in Purchase Decisions
Energy Analysis Plays an Important Role in Purchase Decisions
 
Biomass power plant
Biomass power plant Biomass power plant
Biomass power plant
 
Ntpc business strategy
Ntpc business strategyNtpc business strategy
Ntpc business strategy
 
Wind Energy Available for Sale in Tamil Nadu
Wind Energy Available for Sale in Tamil NaduWind Energy Available for Sale in Tamil Nadu
Wind Energy Available for Sale in Tamil Nadu
 
Load Research Concept and Approach _Kolkata.pptx
Load Research Concept and Approach  _Kolkata.pptxLoad Research Concept and Approach  _Kolkata.pptx
Load Research Concept and Approach _Kolkata.pptx
 
Energy cost and energy shortage in nepal potential of solar, wind and other f...
Energy cost and energy shortage in nepal potential of solar, wind and other f...Energy cost and energy shortage in nepal potential of solar, wind and other f...
Energy cost and energy shortage in nepal potential of solar, wind and other f...
 
Energy comsats 12_oct13_2
Energy comsats 12_oct13_2Energy comsats 12_oct13_2
Energy comsats 12_oct13_2
 
Economy and energy security for pakistan
Economy and energy security for pakistanEconomy and energy security for pakistan
Economy and energy security for pakistan
 
Future of the Indian power sector
Future of the Indian power sectorFuture of the Indian power sector
Future of the Indian power sector
 
India : Power Sector Report_August 2013
India : Power Sector Report_August 2013India : Power Sector Report_August 2013
India : Power Sector Report_August 2013
 
Captive Power Plants
Captive Power PlantsCaptive Power Plants
Captive Power Plants
 
Day2: Fuel supply issues ppt sunil wadhwa
Day2: Fuel supply issues ppt   sunil wadhwaDay2: Fuel supply issues ppt   sunil wadhwa
Day2: Fuel supply issues ppt sunil wadhwa
 
Dalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdfDalmia Cement Ariyalur_240314_114438.pdf
Dalmia Cement Ariyalur_240314_114438.pdf
 
Economy and Energy Security for Pakistan - What lies ahead
Economy and Energy Security for Pakistan -What lies aheadEconomy and Energy Security for Pakistan -What lies ahead
Economy and Energy Security for Pakistan - What lies ahead
 
Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014Bhutan Country Presentation at ACEF 2014
Bhutan Country Presentation at ACEF 2014
 
Energy audit tata power solar
Energy audit   tata power solarEnergy audit   tata power solar
Energy audit tata power solar
 
REC status
REC statusREC status
REC status
 
Small Power Generation Plant
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation Plant
 
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdfPLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
 
Energy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industriesEnergy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industries
 

Dernier

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Dernier (20)

Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 

Power procurement strategy--Mr. rohit bajaj

  • 3. Source:ExecutiveSummary of October 2015, CEA *including renewable generation Category Installed Capacity (MW) Share in Total(%) Generation (BUs) Share in Total(%) Coal 170,138 61% 836 80% Gas 24,473 9% 41 4% Diesel 994 0.4% 1.4 0% Hydro 42,473 15% 129 12% Nuclear 5,780 2% 36 3% RE 36,471 13% - - Total 280,328 1042 Installed Capacity (All) Coal,61%Hydro, 15% RE, 13% Gas 9% Nuclear,2% Diesel,0.4%
  • 4. Source:ExecutiveSummary of October 2015, CEA *including renewable generation Category Installed Capacity(MW) Share in total RE (%) Wind Power 23,763 65% Small Hydro 4,102 11% Bio Power 4,546 12% Solar 4,061 11% Total 36,471 Installed Capacity (Renewable) Wind Power, 65% Bio Power, 13% Small Hydro, 11% Solar, 11%
  • 5. 16.73 19.25 27.28 67.55 88.5 100 0 20 40 60 80 100 120 8th Plan 9th Plan 10th Plan 11th Plan 12th Plan (2012-17) 13th Plan (2017-22) GigaWatt Generation CapacityAddition (GW) 69.21 Actual till Oct’15 • Investmentsof around US$ 225 billion planned for the power sector during the 12th Plan. • In addition, Renewable energy capacity of 175 GW is planned till 2022. Source:CEA Growing impetus on capacity addition Ambitious targets to capacity addition
  • 6. Power Situation in the Country Year Installed Capacity (at the end of FY) (MW) PeakMet ( MW ) 2009-10 1,59,398 1,04,009 2010-11 1,73,626 1,10,256 2011-12 1,99,877 1,16,191 2012-13 2,23,344 1,23,294 2013-14 2,43,029 1,29,815 2014-15 2,67,367 1,41,160 2015-16* 2,843,03 1,48,463 • In last six years, capacity has increased by 1,24,905 MW and demand has increasedby 44,454 MW only. • The country as a whole has witnessed a decline in the deficits. Source:Executive Summary, Power Sector, CEA, *Upto Dec, 2015
  • 7. Financial health of Generators • Total installed capacity in the Country is 2,80,328 MW • Peak demand met : 1,48,005 MW • PLF of coal/lignite plants – Around 65% in FY 14-15 – Around 62% in FY 15-16 (till Oct) – FY 07-08 - 78% • PLF of gas based plants: 25% due to shortage of fuel • Stranded capacity in the country: A total 50,000 MW stressed – 27,880 MW of coal capacity stranded – 24,000 MW of Gas based Capacity stranded • Key Issues: Lack of fuel, Transmission, Competition, Weak distribution system, Discoms’ inability to buy
  • 8. Financial Health of Discoms • Discomsaccumulated losses stand at about 3 lakh crores • Yearly losses of Discomsis about Rs 70,000 crore • The gap between average cost of supply of power and average tariff is about 80 paise per unit. • Most of the Discomsin the country incurring losses . • No investment is being made in the Distribution infrastructure and intra-statetransmission network resulting in intrastate congestion • States prefer to do load shedding than buying cheap power from Exchange.
  • 9. State wise status Population (in Cr) Avg. MW Supply FY 14-15 Per Capita Consum kWh (2011-12) Punjab 2.8 5,623 1,799 Gujarat 6.0 9,344 1,663 Haryana 2.5 5,978 1,628 Delhi 1.7 3,991 1,587 Chhattisgarh 2.6 3,810 1,320 Himachal Pradesh 0.7 1,287 1,289 Tamil Nadu 7.2 10,517 1,277 Uttarakhand 1.0 1,529 1,232 Maharashtra 11.2 11,507 1,204 Andhra Pradesh 8.5 10,034 1,157 Odisha 4.2 3,099 1,146 Karnataka 6.1 6,803 1,081 Jammu & Kashmir 1.3 1,296 1,015 Rajasthan 6.9 6,529 927 Jharkhand 3.3 844 790 Madhya Pradesh 7.3 7,171 672 Kerala 3.3 1,935 594 West Bengal 9.1 5,319 564 Uttar Pradesh 20.0 9,916 450 Assam 3.1 679 250 Bihar 10.4 1,538 134
  • 10. Long Term Short-Term PPA for over 25 yearsthrough long term Source:Percentageasper CERC Reporton ShortTerm Power Market FY-14 93.86% 6.1% 90.5% Throughtraders 3.2% 3.4% DirectBilateral 0.5% 1.5% 9.5% Exchanges 0.4% 2.73% UnscheduledInterchange 2.1% 1.9% FY 2009 FY 2015 • Short term market grew at an encouragingrate with a CAGR of 22% (FY-09 to FY 15). • Power Exchanges witnessed growth at a CAGR of 62% (FY-09 to FY 15). Indian Power Market Snapshot
  • 11. Coal production and supply in the Country Total Coal Production (MT) YoYinc (%) Import (MT) YoYinc (%) Import Cost (CroresINR) 2009-10 532 73 39,180 2010-11 533 0.12% 69 -5.92% 41,550 2011-12 540 1.36% 103 49.24% 78,838 2012-13 556 3.05% 146 41.74% 86,846 2013-14 566 1.68% 167 14.45% 92,329 2014-15 612 8.25% 212 27.12% 1,04,524 11 • In FY 15, the domestic coal production increased by 8.5% to 612 MT. • The GoI has set a target of increasing domestic coal production to 1.5 billion tonnes (including one bt from CIL) by FY 2021 • This could create a surplus situation and reduce import of coal which in FY 15 was worth Rs.1045 Billion. Source:Coal Statistics, Ministry of Coal
  • 12. Impact of coal availability on Power Markets • Increased availability of coal for the power sector has had a positive impact. • Generation has increased by 6% and many stranded plants have started operating • Sale of power on IEX has increased 12 Source:Demand and Supply of Coal from Coal Statistics 2014-15, Ministry of Coal 3.61 3.28 3.89 3.76 4.49 4.18 4.17 2.68 2.62 2.56 2.74 2.82 3.68 3.03 0.00 1.00 2.00 3.00 4.00 5.00 0 1000 2000 3000 4000 5000 6000 7000 Apr May Jun Jul Aug Sep Oct Price(Rs./kWh) AverageDailyMW Average Daily Sale Bids (MW) and Market Clearing Price 2014-15 2015-16 2014-15 2015-16
  • 13. Price and Volume: Bilateral vs. IEX DAM 2.62 6.17 11.80 13.79 22.35 28.92 28.12 16.27 21.92 26.72 27.70 35.84 36.64 35.11 35.50 20.37 7.16 5.33 3.58 3.47 3.73 2.87 3.46 2.80 7.46 5.32 4.74 4.23 4.34 4.24 4.30 4.06 -1 1 2 3 4 5 6 7 8 - 5 10 15 20 25 30 35 40 FY08-09 FY09-10 FY10-11 FY11-12 FY12-13 FY13-14 FY14-15 FY15-16 Price(Rs./kWh) Volume(BU) IEX Volume Trader Volume IEX Price Bilateral Price Prices at the Exchange have always been lower than Bilateral Prices *Data up to Sep 2015, Source: CERC MMC Reports
  • 15. Option with the Discoms: Utilising Exchange Market • PPA for base load only i. Discoms should tie-up PPA only to manage their base demand ii. Many Discoms have tied PPAs to meet their peak demand as well. The Discoms have to pay the capacity charge for this quantum even in the off peak time example Gujarat, Haryana, Delhi, Punjab iii. So for optimum utilisation, Long Term PPA should be only for base demand and seasonal variations should be bought through other available market options
  • 16. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 36 34 32 30 28 26 24 22 PPA (Base load) contract ShortTerm Market (for Peak Load) Day Ahead Sell BuyBuy Sell Forecasted demand Ancillary Service Intra Day Market Real-time demand Surpluses/Deficits - Balance physical supply and demand Meeting Shortages/Surplus through STM Maximizing efficiency – Ideal Scenario Forecasted Demand Curve of the Discom Actual Demand Real time variations
  • 18. Replacement of high variable cost power by Exchange power • Replacement of high variable cost power by Exchange power I. Under long termPPA two component • Capacity charges (commitment charges): paid irrespective of whether discom purchase power from these plants or not • Energy charges : Paid corresponding to the number of units of power purchased from that particular plant II. Discoms can replace costlier long termpower by procurementfrom IEX,if, • Energy charge of power plant is greater than IEX rates • During night hours prices at IEX are further low and savings can be enhanced III. Discoms can continue paying fixed charge to Long Term PPAs and substitutewhereenergycharge is higher than IEX price IV. IEX prices are around 25%-30% lower than the Bilateral Prices
  • 19. Cost Optimisation by Discoms • Discoms can devise least cost option to meet demand in the state by tracking prices at IEX – Energy chargegreaterthan prevailingACP can be substituted with powerfrom IEX – During off-peakhours,when prices atIEX are low, savings can be enhanced replacingpower from LT to PX Transactions Type DispatchMode Capacity (MW) Energy Charge (INR/kWh) Plant A Hydro MustRun 100 0.00 Plant B Hydro MustRun 150 0.00 Plant C Nuclear MustRun 500 2.80 Plant D Coal Merit 120 3.00 Plant E Coal Merit 120 3.20 Plant F Coal Merit 100 3.50 Plant G Coal Merit 90 3.80 Plant H Coal Merit 90 4.00 Merit BasedCapacity (MW) 520 Substitutedwithpower@INR 2.50 during off peakhours fromIEX Substitutedwithpower@INR 3.45 from IEX ACP= INR3.45/kWh Merit Order for Dispatch in State Off-peak ACP= INR2.50/kWh *Assumptions:12 number of hours areconsidered in off-peak hours PotentialSavings: INR 50 Crore a month
  • 20. Discoms exhaust long term and medium term contracts first despite availability of power at cheaper prices at PXs Long Term Medium Term Short Term Purchase on economic principle of Merit Order Optimization of Power Procurement Cost
  • 21. PPA 1 I 3.70 PPA 2 I 4.06 Long Term Contracts Bilateral Contracts Exchange CapacityTied up by Discom IEX Price I 2.45 Merit Order Baseline PPA 3 I 3.00 PPA 4 I 1.99 PPA 5 I 2.00 PPA I Variable Cost Must Run Plants (includes all hydro, nuclear or other ‘take or pay’ type contractual plants) Contract1 I 4.70 Contract2 I 3.50 Contract3 I 2.10 Merit order dispatch schedule to be prepared based on Variable cost and considering Exchange Prices
  • 22. PPA 1 I 3.70 PPA 2 I 4.06 IEX Price I 2.45 PPA 3 I 3.00 PPA 4 I 1.99 PPA 5 I 2.00 Must Run Plants (includes all hydro, nuclear or other ‘take or pay’ type contractual plants) Contract1 I 4.70 Contract2 I 3.50 Contract3 I 2.10 IncreasingVariableCost TobedispatchedinthisOrderbasedonEnergy DemandoftheDiscom Merit Order Baseline Merit order dispatch schedule to be prepared based on Variable cost and considering Exchange Prices
  • 23. Replacement Potential: Regionwise plants with high variable cost as compared to IEX prices Region Station Capacity (MW) Energy Charge (Rs/kWh) IEX Price in the Region* (Rs./kWh) East Barh 660 4.06 2.22Farakka-I , II & III 2100 2.78 - 2.8 Kahalgaon-I & II 2340 2.42 - 2.57 North Badarpur TPS 705 5.09 3.18 Auraiya-Wtd 663 4.36 Dadri-Wtd 830 4.27 NCTPP Dadri I & II 1820 3.81 - 4.18 Tanda 440 3.63 Anta-Wtd 419 3.55 Faridabad-Wtd 431 3.35 Unchahar-I, II & III 1050 2.89 South Simhadri-I & II 2000 2.74 2.99 Ramagundam I, II & III 2600 2.54 - 2.71 West Mouda 1000 3.89 2.18Kawas-Wtd 656 3.36 Gandhar-Wtd 657 3.28 *IEX Average area prices for the month of June'15
  • 24. Cost Optimisation Potential in Bihar Annual: Plant-wise Source: • Variable Cost taken from ARR of NBPDCL & SBPDCL • Variable Cost of Rs. 4.06 is considered as 4.06 for April 15 as per ARR of FY 2015-16 • Source for Volume: • Volume of CGS taken from ERPC • Volume of SGS taken from ARR S. No Power Plant Allocated Capacity (MW) Variable Cost-FY15 (Rs./kWh) Replaceable Volume (MU) Annual Volume (MU) Potential Savings (Cr) 1 KBUNL Stage 1 U-1 220 4.06 700 700 112 2 BARH STPS II 430 4.06 1,290 1,290 174 3 Adani-Gujarat 300 3.17 515 1,612 20 4 Barauni TPS 220 3.00 359 836 9 5 Farakka STPS I & II 379 2.80 1,189 3,429 18 6 Farakka STPS III 55 2.78 203 714 2 7 KhSTPS I 293 2.57 223 2,220 0 8 KhSTPS II 78 2.42 0 515 0 9 Talcher STPS I 344 1.47 0 2,855 0 10 GMR 200 1.46 0 870 0 Total 2,419 4,476 15,041 335
  • 25. Cost Optimization by Bihar • Bihar has initiated the process of Cost Optimization • The costlier power from Barh & Dadri stations is replaced by the cheaper power from IEX. • The Energy Charges of these power plants are greater than the IEX rates. • Bihar has made a saving of over 11 crores in 21 days Due to low prices at the Exchange there is further potential to increase savings
  • 26. Utility Software created by IEX for Bid Optimization • IEX has created a utility software for Discoms and is providing it free of cost • The software is customised for each Discom to take into account its existing PPAs along with their variable cost and status of must run plants etc. • Based on the inputs fed into the software, it provides with the optimisation bid which should be put into the IEX bidding platform along with details of backing down if the Bid is selected • Benefits: – Discoms need not be bothered about Exchange prices for bidding – The software will create bid as per the Discoms merit order and other constraints fed to it – On acceptance of the Bid, the Discom can backdown the plants
  • 27. Banking Transactions • Banking transactions takes place directly between Discoms, the transactions are cashless in nature, where one Discom banks power to other for utilising it later. • Commercial considerations required for Banking transactions with the reference price available.
  • 28. Case Study: Banking @ 500 MW quantum MONTH DRAWALby Discom-1 (MUs) IEX PRICE (Rs/KWh) DRAWALby Discom-2 (MUs) IEX PRICE (Rs/KWh) Nov'14 365 2.63 Dec'14 372 2.96 Jan'15 372 2.70 Feb'15 320 2.60 Jun'15 350 3.18 Jul'15 362 3.2 Aug'15 362 2.64 Sept'15 372 3.43 Weighted Avg (as per dataavailaible) 1429 2.72 1446 3.11 TOTAL 1429 2.72 1446 3.11 Profit/Lossto Discom-1 Rs Crore (60)
  • 29. Cost BenefitAnalysis for Open Access Consumer *Assumption: Buy Quantity is 10 MW for 24 hours and 1000 Portfolios are selected everyday VoltageLevel 33 kV 132 kV VolumeTraded in MW 10 10 HoursTraded 24 24 Total Volume in MWh (at Regional Periphery) 240 240 IEX Rate at Regional Periphery (inINR per unit) 3.00 3.00 Losses AssamWithdrawalPOCLoss 2.05% 2.05% StateLoss 3.64% 3.64% Wheeling Losses 17.60% 0.00% Cost After Losses (inINR per unit) 3.73 3.17 Charges StateTransmission Charges (in Rs/unit ) 0.42 0.42 AssamWithdrawalPOCCharges (in Rs/unit) 0.17 0.17 Wheeling Charges(in Rs/unit) 0.22 0.00 NLDC Operating Charges+ NLDCApplication Charges + SLDCCharges* 0.03 0.03 IEX Transaction Charges @ Rs 20 per MW (in INR/unit) 0.02 0.02 ProfessionalFees ( If transacted through Member)* * 0.02 0.02 CrossSubsidy Charges (in INR/unit) 0.54 0.54 IEX Rate @ ex ABTMeter (inINR/unit) 5.15 4.37 Energy Charges (inINR/unit) 7.16 7.16 Savings Per Unit (inINR/unit) 2.01 2.79
  • 30. Cost saving potential for Industries Comparison with State tariff *IEX Landed cost calculated at Rs 3 per unit, the actual price on most days is lower than this 6.35 6.50 5.65 7.66 6.00 7.01 4.80 6.14 7.16 5.50 4.70 6.33 6.20 5.60 4.20 3.73 4.17 3.99 6.09 4.62 5.28 3.65 4.90 5.15 4.47 4.04 5.64 5.67 5.26 4.16 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 HT Tariff @ 33 kV IEX Landed Cost @ Rs 3 / unit
  • 32. Growing Share of Short Term Market in Total Gen. 2.7 7.1 13.5 14.8 23.0 30.0 29.4 14.9 26.8 29.7 36.6 36.6 35.8 34.56 3.3 6.2 10.3 15.4 14.5 17.4 15.58 14.4 25.8 28.1 27.8 24.8 21.5 19.45 7.4% 8.6% 10.0% 10.8% 10.9% 10.9% 9.5% 0% 2% 4% 6% 8% 10% 12% 0 20 40 60 80 100 120 FY08-09 FY09-10 FY10-11 FY11-12 FY12-13 FY13-14 FY14-15 ShareofShortTermTradeinTotGen(%) Volume(BU) PXs Trader Direct UI Share of ST in Tot Gen • Short term market growing at an encouragingrate with a CAGR of 22% in the past six years. • Power Exchanges witnessing growth at a CAGR of 62% (last six years).32