WAGON TEST
EQUIPMENTS
A schematic layout of rake test rig (RTR) is shown in. A rake of wagon stock can be tested with
this Test Rig. This Rig may also be used for testing the train in yards before attaching the engine.
The Rake Test Rig unit consists of air supply system and mobile test rig. The details are provided
in Annexure-I The mobile test rig is having a cubical structure and is mounted on wheels. It can be
taken to the yards and sick lines. The procedure is as follows:
A. Carry out Visual Examination of rake.
B. Prepare Test Rig for Rake Test.
C. Conduct Leakage, Service Application and Release Test. Visual inspection is a check of air
brake sub-assembly for any damage on the brake pipe, hose coupling etc and then rectifying
it. The steps are :-
i) Inspect loose suspension brackets and anti-pilferage devices of all air brake sub-assemblies.
ii) Visually inspect for any defect/damage in the brake pipe, hose pipe, coupling etc.
iii) Rectify or replace the problematic part/sub-assembly.
Procedure of Rake Testing for Freight Stock
Rake Test :
Rake Test can be performed by using a portable device called „Test Rig‟ or by Locomotive.
The Test Rig provides all facilities like locomotive to conduct the test. The source of
compressed air supply to the Test Rig is through a compressor installed in the wagon depot
for Brake Pipe and Feed Pipe of the test rig. The Air Dryer should also be provided just
before connecting brake pipe and feed pipe for air supply system and Mobile test Rig.
Attach the rake test rig to the rake through the couplings. Carry out following tests as per the
procedure given in G-97 Annexure-XI {MP guide No.11 (Rev.01) amendment No.01 of Jan-
2010} for checking capability of locomotives for Charging/Releasing of train brakes,
checking of leakage in the train, checking leakage in feed pipe, brake cylinder operative
percentage, and procedure to be followed at way side.
Following examination must be carried out before rake testing
 Hand Brakes of all wagons are fully released.
 Operating handle of empty load box is in correct position i.e. 'Empty' position when
wagon is empty or lightly loaded and in 'Loaded' position when wagon is loaded beyond
the specified value.
Hose couplings of brake pipe & feed pipe on consequent wagons are coupled to one
another to form a continuous air passage from the locomotive to the rear end of train.
 All the angle cocks except those at the rear end of the train are kept OPEN.
 Hose coupling at the rear end of the train is placed on hose coupling support.
 Isolating cocks of Distributor Valve on all wagons are in OPEN position.
Checking of Continuity and Leakage in Rake:
A. Attach the Diesel/Electric locomotive/Test Rig to the rake fitted with twin pipe air
brake system and couple brake pipes and feed pipes. Ensure correct coupling with
brake and feed pipe in a manner that there is no leakage of air from coupled joints.
B. The coupling should be done with angle cocks in closed position.
C. Open the angle cocks of loco after coupling feed pipe and brake pipe.
D. Open the angle cock of the brake pipes and the feed pipes on all the wagons and
check for continuity and leakage of brake pipe and feed pipe by reducing and
rebuilding brake pipe and feed pipe pressure operating by A9 brake valve & angle
cock fitted in feed pipe on locomotive (on wagon side) respectively. The verification
should invariably to be carried out through the pressure gauges (BP& FP) provided in
Guard's Brake Van.
NOTE: If the pressure is not within specified limit as given
above then check for leakage in rake and correct it.
Leakage Rate Test:
E. After the stabilizing pressure as given in above table, move the driver's automatic
brake valve handle (A-9) towards application position to reduce brake pipe pressure
from 5.0 kg/cm² to 4.0 kg/cm².
F. After the brake pipe pressure has been stabilized –
i) Close the brake pipe isolating cock provided between additional C2W Relay valve
and brake pipe of the locomotive or isolating cock of Test Rig for checking BP leakage.
ii) Close the isolating cock provided between feed valve and feed pipe of the locomotive
or isolating cock of FP for checking FP leakage.
G. Wait for 60 sec for temperature and gauge settlement then note the drop in pressure
in brake pipe & feed pipe pressure gauge in locomotive for 05 minutes.
H. The drop in brake pipe & feed pipe pressure gauge shall not be more than 0.25
kg/cm²/min. If the leakage rate is more than the value indicated in (H), check for
excessive leakage on individual wagon as indicated below –
1. A hissing sound would be audible at points where leakage is heavy.
2. Once the hissing sound is heard from a particular area, pin-point the location of leakage by
applying soap water solution.
3. Use permitted material viz. Teflon tape for arresting the leakage.
I. In case leakage is heavy and cannot be arrested, the wagon may have to be isolated/detached.
J. In case where leakage can be arrested temporarily by tap and the nature of leakage is such
that it requires attention at primary depot, clear marking on the wagon should be done to draw
attention of primary depot for adequate attention.
K. In case the leakage is from the distributor valve and cannot be arrested, isolation of the
wagon can be carried out by closing the distributor valve isolating cock. In such condition, clear
marking should be provided on the wagon to indicate this defect to primary depot. Do not close
brake pipe angle cocks under any circumstances, either for isolation of wagons or for any
purpose whatsoever, except for carrying out shunting operation after which the angle cocks
should again be opened to ensure continuity of brake pipe.
Service application and Release Test:
A. Move the driver's automatic brake valve handle (A-9) towards service
brake application position and drop the value of brake pipe pressure (BP)
between 1.3 to 1.6 kg/cm².
B. Brakes of all wagons should apply after brake application and brake
blocks on wagons should firmly grip on the wheel tread.
C. Check the piston strokes of all wagons. All Piston strokes should be
within the specified limits for different types of wagons. The piston
strokes are given below in table.
If the piston stroke is incorrect then, record “A” Dimension, it should be 70 ±20 mm in
empty and loaded condition.
D. Check all brake cylinders. Wagons with in-operative brake cylinders should be
marked unfit and detached.
E. After the release of brake, the piston of brake cylinder should be fully inside and
brake blocks
are free from the wheels.
F. Guard‟s emergency brake valve: Ensure that Guard Emergency brake valve is
working properly by operating it.
G. BPC (Brake Power Certificate): Ensure that Loco Pilot, Guard and TXR have
checked the details given in the certificate and signed for its compliance.
TOOLS AND EQUIPMENTS:
[1] Rake Test Rig/Locomotive.
[2] Open End spanner 18x19”
[3] Spanner 10 mm & 12 mm
SINGLE WAGON TEST
“Single wagon Test” is performed on a wagon to ensure proper functioning of the air
brake system. It is generally performed on the sick wagon attended in the sick line or
whenever a subassembly of the air brake system is replaced either in depot or
workshop. Single wagon test is also carried out after POH and after every change of
distributor valve in the workshop.
The different tests to be performed on the subassemblies of a wagon are as follows:
Test1: Leakage Test.
Test2: Sensitivity and Insensitivity Test.
Test3: Brake Application and Release Test.
Test4: Graduated Application and Release Test.
Test5: Check and adjust Slack Adjuster
SINGLE WAGON TEST
A. TOOLS AND EQUIPMENT
1. Test Rig
2. Spanners 10mm, 12mm
B. CONCEPT
Single Wagon Test is performed, by using a portable device called “Test Rig”. This test
rig provides all facilities similar to a driver‟s brake valve. The source of compressed air
for conducting the test is through a compressor installed in depots and workshops for
conducting various tests without the need of a locomotive. The part description and
specification are given in table below.
PROCEDURE FOR SINGLE WAGON TESTING (Single Pipe)
A systematic lay-out of Single Wagon Test Rig (SWTR) is shown in fig. 7.33. This SWTR
is utilised for testing the air brake system fitted on single wagon. The wagon should not
be connected with the locomotive at the time of testing. The following procedure shall be
followed for testing.
i. The wagon under testing is to be coupled at one end with the SWTR coupling head BP
and the other end should be closed with dummy coupling head. Pressure gauge should be
fitted on brake cylinder.
ii. Couple the SWTR to the main line of compressor.
iii. Place the isolating cock of distributor valve on the wagon in open position i.e., the
handle should be vertically down wards.
iv. Set the pressure reducing valve (1) to 5 + 0.1 Kg/cm2 Open the cocks (2) and (8) and
so the angle cocks on the both ends of the wagons. Move the driver‟s brake valve (3) in
the charging and release position.
v. Wait for about 5 minutes to charge the complete system.
vi . Check the pressure in BP pressure gauge (7). Pressure should be 5+ 0.1 Kg. /cm2 in
BP. If there is pressure drop in the gauge (7) detect the source of leakage and eliminate it.
vii. Close cocks (2) & (8). Check the leakage on BP for one minute.
viii. Open cock (2). Bring Driver‟s brake valve in full-service application position.
ix. Record the brake cylinder filling time from 0 to 3.6 Kg. /cm2 in brake cylinder
pressure gauge.
x. Record maximum pressure in brake cylinder.
xi. Record the pressure drop in BP from pressure gauge (4).
xii. Record the piston stroke of brake cylinder.
xiii. Bring Driver‟s brake valve in the charging and release position.
xiv. Record the brake cylinder draining time from 3.8 + 0.1 to 0.4 Kg. /cm2 in brake
cylinder pressure gauge & check complete release of brakes i.e., piston should reach its
initial position.
xvi. Open cock (6) for checking sensitivity of brakes. Record time within which brakes
get applied.
xvii. Close cock (6) and open cock (2). Wait till brakes are released.
xviii. Close cock (2) and open cock (7) for checking the insensitivity of brakes. The
brakes should not apply.
xix. Close cock (7) and (8) and open cock (2), BP pressure should rise to 5 Kg. /cm2
xx. Close cock (2) and open cock (5) for emergency application.
xxi. Record the brake cylinder charging time from 0 to 3.6 Kg. /cm2 in BC pressure
gauge.
xxii. Record maximum BC pressure.
xxiii. Check the leakage in BC for 5 minutes.
xxiv. Pull the manual release lever of distributor valve for about 10 sec. Brake cylinder
pressure should become zero automatically.
xxv. The above tests should be done in both empty and loaded condition.
xxvi. The results of test shall be recorded in the test proforma attached herewith
10. Record the brake cylinder filling time from 0 to 3.6 kg/cm2 in brake cylinder pressure
gauge.
11. Record maximum pressure in brake cylinder.
12. Record the pressure drop in BP from pressure gauge (7).
13. Record the piston stroke of brake cylinder.
14. Bring Driver's brake valve in charging and release position.
15. Record the brake cylinder draining time from 3.8 to 0.4 kg/cm2 in brake cylinder
pressure gauge & check complete release of brakes i.e., piston should reach its initial
position.
16. Close cock (5) and open cock (11) for charging the reservoir to 5 kg/cm2
17 Open cock (9) for checking sensitivity of brakes. Record the time
within which brakes applied.
18 close cock (9) and open cock (5). Wait till brakes are released.
19 Close cock (5) and open cock (10) for checking the insensitivity of
brakes.
20 Close cock (10) and (11) and open cock (5). BP pressure should rise
to 5 Kg/cm2.
21 Close cock (5) and open cock (8) for emergency application.
22 Record the brake cylinder charging time from 0 to 3.6 kg/cm2 in BC
pressure gauge.
23 Record maximum BC pressure.
24 Check the leakage in BC for 5 minutes.
25 The above tests should be done in both empty and loaded
condition.
26 The results of test shall be recorded in the test proforma as given
PROFORMA FOR SINGLE WAGON TEST FOR WAGONS OTHER THAN BOBR &
BOBRN (Single pipe/Twin pipe)
PRES CRIBED
LIMITS
THANK YOU

Contenu connexe

Tendances

Indian railway report main
Indian railway report mainIndian railway report main
Indian railway report mainVicky Gupta
 
Roller bearing used in railway coaches
Roller bearing used in railway coachesRoller bearing used in railway coaches
Roller bearing used in railway coachessachin deora
 
Carriage and wagon
Carriage and wagon Carriage and wagon
Carriage and wagon Deewan singh
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...haxxo24
 
G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...
G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...
G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...SrinivasaRao Guduru
 
SUMMER TRAINING PPT On Coach Care Centre (SICK LINE)
SUMMER TRAINING PPTOnCoach Care Centre (SICK LINE) SUMMER TRAINING PPTOnCoach Care Centre (SICK LINE)
SUMMER TRAINING PPT On Coach Care Centre (SICK LINE) Amit Verma
 
A project on buffer
A project on bufferA project on buffer
A project on bufferRitesh Rohan
 
Lhb coach documentation
Lhb coach  documentationLhb coach  documentation
Lhb coach documentationTURENDARSAHU
 
Summer Internship/Training report at Indian Railway
Summer Internship/Training report at Indian RailwaySummer Internship/Training report at Indian Railway
Summer Internship/Training report at Indian RailwayChirag Jain
 
Rake maintenance (C&W Depot AGC ) Indian Railways
Rake maintenance (C&W Depot AGC )  Indian RailwaysRake maintenance (C&W Depot AGC )  Indian Railways
Rake maintenance (C&W Depot AGC ) Indian RailwaysDeewan singh
 
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01SrinivasaRao Guduru
 
Coach care centre new delhi
Coach care centre new delhiCoach care centre new delhi
Coach care centre new delhiHome
 
Summer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgitSummer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgitItnesh Kumar
 
Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)SrinivasaRao Guduru
 
Training report on railways (all workshop)
Training report on railways (all workshop)Training report on railways (all workshop)
Training report on railways (all workshop)anand prasad
 
Revised Wagon Maintenance Manual.pdf
Revised Wagon Maintenance Manual.pdfRevised Wagon Maintenance Manual.pdf
Revised Wagon Maintenance Manual.pdfmajjisatish
 

Tendances (20)

RAILWAY PPT
RAILWAY PPTRAILWAY PPT
RAILWAY PPT
 
Indian railway report main
Indian railway report mainIndian railway report main
Indian railway report main
 
Roller bearing used in railway coaches
Roller bearing used in railway coachesRoller bearing used in railway coaches
Roller bearing used in railway coaches
 
Carriage and wagon
Carriage and wagon Carriage and wagon
Carriage and wagon
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...
 
G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...
G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...
G 80. inspection and maintenance of centre buffer couplers ( for workshop sta...
 
SUMMER TRAINING PPT On Coach Care Centre (SICK LINE)
SUMMER TRAINING PPTOnCoach Care Centre (SICK LINE) SUMMER TRAINING PPTOnCoach Care Centre (SICK LINE)
SUMMER TRAINING PPT On Coach Care Centre (SICK LINE)
 
A project on buffer
A project on bufferA project on buffer
A project on buffer
 
ICF Bogie
ICF BogieICF Bogie
ICF Bogie
 
Lhb coach documentation
Lhb coach  documentationLhb coach  documentation
Lhb coach documentation
 
Summer Internship/Training report at Indian Railway
Summer Internship/Training report at Indian RailwaySummer Internship/Training report at Indian Railway
Summer Internship/Training report at Indian Railway
 
Rake maintenance (C&W Depot AGC ) Indian Railways
Rake maintenance (C&W Depot AGC )  Indian RailwaysRake maintenance (C&W Depot AGC )  Indian Railways
Rake maintenance (C&W Depot AGC ) Indian Railways
 
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
Maintenance instructions on Air Suspension RDSO 2009-CG-CMI-01
 
Coach care centre new delhi
Coach care centre new delhiCoach care centre new delhi
Coach care centre new delhi
 
Summer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgitSummer training report coach care new Delhi rkgit
Summer training report coach care new Delhi rkgit
 
Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)Handbook on maintenance of air brake system in lhb coaches (ftil type)
Handbook on maintenance of air brake system in lhb coaches (ftil type)
 
Training report
Training reportTraining report
Training report
 
Hand book on C&W
Hand book on C&W Hand book on C&W
Hand book on C&W
 
Training report on railways (all workshop)
Training report on railways (all workshop)Training report on railways (all workshop)
Training report on railways (all workshop)
 
Revised Wagon Maintenance Manual.pdf
Revised Wagon Maintenance Manual.pdfRevised Wagon Maintenance Manual.pdf
Revised Wagon Maintenance Manual.pdf
 

Similaire à WAGON TEST EQUIPMENTS.pdf

report on Industrial training
report on Industrial training report on Industrial training
report on Industrial training hisham munir
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...haxxo24
 
summertraining at rdso lucknow
summertraining at rdso lucknowsummertraining at rdso lucknow
summertraining at rdso lucknowpradeep verma
 
Pamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogiePamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogieSrinivasaRao Guduru
 
Indian Railways Training on Coach Care Centre
Indian Railways Training on Coach Care CentreIndian Railways Training on Coach Care Centre
Indian Railways Training on Coach Care CentreRao Khola
 
Pamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coachesPamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coachesSrinivasaRao Guduru
 
Various Mechanical Units Involved in The Bottling Of LPG cylinders
Various Mechanical Units Involved in The Bottling Of LPG cylindersVarious Mechanical Units Involved in The Bottling Of LPG cylinders
Various Mechanical Units Involved in The Bottling Of LPG cylindersMohit Dhull
 
2003 TOYOTA CELICA Service Repair Manual
2003 TOYOTA CELICA Service Repair Manual2003 TOYOTA CELICA Service Repair Manual
2003 TOYOTA CELICA Service Repair Manualjsemd suekd
 
2002 TOYOTA CELICA Service Repair Manual
2002 TOYOTA CELICA Service Repair Manual2002 TOYOTA CELICA Service Repair Manual
2002 TOYOTA CELICA Service Repair Manualjksmttemmd
 
2001 TOYOTA CELICA Service Repair Manual
2001 TOYOTA CELICA Service Repair Manual2001 TOYOTA CELICA Service Repair Manual
2001 TOYOTA CELICA Service Repair Manualjkmsrremmd
 
2000 TOYOTA CELICA Service Repair Manual
2000 TOYOTA CELICA Service Repair Manual2000 TOYOTA CELICA Service Repair Manual
2000 TOYOTA CELICA Service Repair Manualjksemndmm
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...f8iosedkdm3e
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...ran4gangbi
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...zu0582kui
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...fijsekkkdmdm3e
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...lunrizan628
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...qiuqiaoxi0
 

Similaire à WAGON TEST EQUIPMENTS.pdf (20)

report on Industrial training
report on Industrial training report on Industrial training
report on Industrial training
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...
 
Harish rathi
Harish rathiHarish rathi
Harish rathi
 
summertraining at rdso lucknow
summertraining at rdso lucknowsummertraining at rdso lucknow
summertraining at rdso lucknow
 
Pamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogiePamphlet on air suspension system for fiat bogie
Pamphlet on air suspension system for fiat bogie
 
Emission Control.pdf
Emission Control.pdfEmission Control.pdf
Emission Control.pdf
 
Indian Railways Training on Coach Care Centre
Indian Railways Training on Coach Care CentreIndian Railways Training on Coach Care Centre
Indian Railways Training on Coach Care Centre
 
Pamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coachesPamphlet on air suspension system fitted on hybrid coaches
Pamphlet on air suspension system fitted on hybrid coaches
 
Fmp 8000 manual
Fmp 8000 manualFmp 8000 manual
Fmp 8000 manual
 
Various Mechanical Units Involved in The Bottling Of LPG cylinders
Various Mechanical Units Involved in The Bottling Of LPG cylindersVarious Mechanical Units Involved in The Bottling Of LPG cylinders
Various Mechanical Units Involved in The Bottling Of LPG cylinders
 
2003 TOYOTA CELICA Service Repair Manual
2003 TOYOTA CELICA Service Repair Manual2003 TOYOTA CELICA Service Repair Manual
2003 TOYOTA CELICA Service Repair Manual
 
2002 TOYOTA CELICA Service Repair Manual
2002 TOYOTA CELICA Service Repair Manual2002 TOYOTA CELICA Service Repair Manual
2002 TOYOTA CELICA Service Repair Manual
 
2001 TOYOTA CELICA Service Repair Manual
2001 TOYOTA CELICA Service Repair Manual2001 TOYOTA CELICA Service Repair Manual
2001 TOYOTA CELICA Service Repair Manual
 
2000 TOYOTA CELICA Service Repair Manual
2000 TOYOTA CELICA Service Repair Manual2000 TOYOTA CELICA Service Repair Manual
2000 TOYOTA CELICA Service Repair Manual
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
 
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
Volvo A40F FS A40FFS Articulated Dump Truck Service Repair Manual Instant Dow...
 

Plus de TCCW1

Hot Axle.pdf
Hot Axle.pdfHot Axle.pdf
Hot Axle.pdfTCCW1
 
train parting.pdf
train parting.pdftrain parting.pdf
train parting.pdfTCCW1
 
Wheel Gauage.pdf
Wheel Gauage.pdfWheel Gauage.pdf
Wheel Gauage.pdfTCCW1
 
LHB BOGIE.pptx
LHB BOGIE.pptxLHB BOGIE.pptx
LHB BOGIE.pptxTCCW1
 
3 LHB brake binding.pdf
3 LHB brake binding.pdf3 LHB brake binding.pdf
3 LHB brake binding.pdfTCCW1
 
7 WSP.pdf
7  WSP.pdf7  WSP.pdf
7 WSP.pdfTCCW1
 
3 Fiba in Lhb.pdf
3 Fiba in Lhb.pdf3 Fiba in Lhb.pdf
3 Fiba in Lhb.pdfTCCW1
 
lhb ki testing.pdf
lhb ki testing.pdflhb ki testing.pdf
lhb ki testing.pdfTCCW1
 
TROUBLE SHOOTING OF AIR BRAKE.pptx
TROUBLE SHOOTING  OF AIR BRAKE.pptxTROUBLE SHOOTING  OF AIR BRAKE.pptx
TROUBLE SHOOTING OF AIR BRAKE.pptxTCCW1
 
lhb alarm.pdf
lhb alarm.pdflhb alarm.pdf
lhb alarm.pdfTCCW1
 
lhb alarm.ppt
lhb alarm.pptlhb alarm.ppt
lhb alarm.pptTCCW1
 
INTRODUCTION OF CARRIAGE & WAGON, VARIOUS TYPES OF WAGON
INTRODUCTION OF CARRIAGE  & WAGON, VARIOUS  TYPES OF WAGON INTRODUCTION OF CARRIAGE  & WAGON, VARIOUS  TYPES OF WAGON
INTRODUCTION OF CARRIAGE & WAGON, VARIOUS TYPES OF WAGON TCCW1
 
WSP EXAMINATION.pdf
WSP EXAMINATION.pdfWSP EXAMINATION.pdf
WSP EXAMINATION.pdfTCCW1
 
PPT Open Line LHB.pdf
PPT Open Line LHB.pdfPPT Open Line LHB.pdf
PPT Open Line LHB.pdfTCCW1
 

Plus de TCCW1 (14)

Hot Axle.pdf
Hot Axle.pdfHot Axle.pdf
Hot Axle.pdf
 
train parting.pdf
train parting.pdftrain parting.pdf
train parting.pdf
 
Wheel Gauage.pdf
Wheel Gauage.pdfWheel Gauage.pdf
Wheel Gauage.pdf
 
LHB BOGIE.pptx
LHB BOGIE.pptxLHB BOGIE.pptx
LHB BOGIE.pptx
 
3 LHB brake binding.pdf
3 LHB brake binding.pdf3 LHB brake binding.pdf
3 LHB brake binding.pdf
 
7 WSP.pdf
7  WSP.pdf7  WSP.pdf
7 WSP.pdf
 
3 Fiba in Lhb.pdf
3 Fiba in Lhb.pdf3 Fiba in Lhb.pdf
3 Fiba in Lhb.pdf
 
lhb ki testing.pdf
lhb ki testing.pdflhb ki testing.pdf
lhb ki testing.pdf
 
TROUBLE SHOOTING OF AIR BRAKE.pptx
TROUBLE SHOOTING  OF AIR BRAKE.pptxTROUBLE SHOOTING  OF AIR BRAKE.pptx
TROUBLE SHOOTING OF AIR BRAKE.pptx
 
lhb alarm.pdf
lhb alarm.pdflhb alarm.pdf
lhb alarm.pdf
 
lhb alarm.ppt
lhb alarm.pptlhb alarm.ppt
lhb alarm.ppt
 
INTRODUCTION OF CARRIAGE & WAGON, VARIOUS TYPES OF WAGON
INTRODUCTION OF CARRIAGE  & WAGON, VARIOUS  TYPES OF WAGON INTRODUCTION OF CARRIAGE  & WAGON, VARIOUS  TYPES OF WAGON
INTRODUCTION OF CARRIAGE & WAGON, VARIOUS TYPES OF WAGON
 
WSP EXAMINATION.pdf
WSP EXAMINATION.pdfWSP EXAMINATION.pdf
WSP EXAMINATION.pdf
 
PPT Open Line LHB.pdf
PPT Open Line LHB.pdfPPT Open Line LHB.pdf
PPT Open Line LHB.pdf
 

Dernier

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 

Dernier (20)

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 

WAGON TEST EQUIPMENTS.pdf

  • 2. A schematic layout of rake test rig (RTR) is shown in. A rake of wagon stock can be tested with this Test Rig. This Rig may also be used for testing the train in yards before attaching the engine. The Rake Test Rig unit consists of air supply system and mobile test rig. The details are provided in Annexure-I The mobile test rig is having a cubical structure and is mounted on wheels. It can be taken to the yards and sick lines. The procedure is as follows: A. Carry out Visual Examination of rake. B. Prepare Test Rig for Rake Test. C. Conduct Leakage, Service Application and Release Test. Visual inspection is a check of air brake sub-assembly for any damage on the brake pipe, hose coupling etc and then rectifying it. The steps are :- i) Inspect loose suspension brackets and anti-pilferage devices of all air brake sub-assemblies. ii) Visually inspect for any defect/damage in the brake pipe, hose pipe, coupling etc. iii) Rectify or replace the problematic part/sub-assembly. Procedure of Rake Testing for Freight Stock Rake Test :
  • 3. Rake Test can be performed by using a portable device called „Test Rig‟ or by Locomotive. The Test Rig provides all facilities like locomotive to conduct the test. The source of compressed air supply to the Test Rig is through a compressor installed in the wagon depot for Brake Pipe and Feed Pipe of the test rig. The Air Dryer should also be provided just before connecting brake pipe and feed pipe for air supply system and Mobile test Rig. Attach the rake test rig to the rake through the couplings. Carry out following tests as per the procedure given in G-97 Annexure-XI {MP guide No.11 (Rev.01) amendment No.01 of Jan- 2010} for checking capability of locomotives for Charging/Releasing of train brakes, checking of leakage in the train, checking leakage in feed pipe, brake cylinder operative percentage, and procedure to be followed at way side.
  • 4. Following examination must be carried out before rake testing  Hand Brakes of all wagons are fully released.  Operating handle of empty load box is in correct position i.e. 'Empty' position when wagon is empty or lightly loaded and in 'Loaded' position when wagon is loaded beyond the specified value. Hose couplings of brake pipe & feed pipe on consequent wagons are coupled to one another to form a continuous air passage from the locomotive to the rear end of train.  All the angle cocks except those at the rear end of the train are kept OPEN.  Hose coupling at the rear end of the train is placed on hose coupling support.  Isolating cocks of Distributor Valve on all wagons are in OPEN position.
  • 5. Checking of Continuity and Leakage in Rake: A. Attach the Diesel/Electric locomotive/Test Rig to the rake fitted with twin pipe air brake system and couple brake pipes and feed pipes. Ensure correct coupling with brake and feed pipe in a manner that there is no leakage of air from coupled joints. B. The coupling should be done with angle cocks in closed position. C. Open the angle cocks of loco after coupling feed pipe and brake pipe. D. Open the angle cock of the brake pipes and the feed pipes on all the wagons and check for continuity and leakage of brake pipe and feed pipe by reducing and rebuilding brake pipe and feed pipe pressure operating by A9 brake valve & angle cock fitted in feed pipe on locomotive (on wagon side) respectively. The verification should invariably to be carried out through the pressure gauges (BP& FP) provided in Guard's Brake Van.
  • 6. NOTE: If the pressure is not within specified limit as given above then check for leakage in rake and correct it.
  • 7.
  • 8. Leakage Rate Test: E. After the stabilizing pressure as given in above table, move the driver's automatic brake valve handle (A-9) towards application position to reduce brake pipe pressure from 5.0 kg/cm² to 4.0 kg/cm². F. After the brake pipe pressure has been stabilized – i) Close the brake pipe isolating cock provided between additional C2W Relay valve and brake pipe of the locomotive or isolating cock of Test Rig for checking BP leakage. ii) Close the isolating cock provided between feed valve and feed pipe of the locomotive or isolating cock of FP for checking FP leakage. G. Wait for 60 sec for temperature and gauge settlement then note the drop in pressure in brake pipe & feed pipe pressure gauge in locomotive for 05 minutes. H. The drop in brake pipe & feed pipe pressure gauge shall not be more than 0.25 kg/cm²/min. If the leakage rate is more than the value indicated in (H), check for excessive leakage on individual wagon as indicated below –
  • 9. 1. A hissing sound would be audible at points where leakage is heavy. 2. Once the hissing sound is heard from a particular area, pin-point the location of leakage by applying soap water solution. 3. Use permitted material viz. Teflon tape for arresting the leakage. I. In case leakage is heavy and cannot be arrested, the wagon may have to be isolated/detached. J. In case where leakage can be arrested temporarily by tap and the nature of leakage is such that it requires attention at primary depot, clear marking on the wagon should be done to draw attention of primary depot for adequate attention. K. In case the leakage is from the distributor valve and cannot be arrested, isolation of the wagon can be carried out by closing the distributor valve isolating cock. In such condition, clear marking should be provided on the wagon to indicate this defect to primary depot. Do not close brake pipe angle cocks under any circumstances, either for isolation of wagons or for any purpose whatsoever, except for carrying out shunting operation after which the angle cocks should again be opened to ensure continuity of brake pipe.
  • 10. Service application and Release Test: A. Move the driver's automatic brake valve handle (A-9) towards service brake application position and drop the value of brake pipe pressure (BP) between 1.3 to 1.6 kg/cm². B. Brakes of all wagons should apply after brake application and brake blocks on wagons should firmly grip on the wheel tread. C. Check the piston strokes of all wagons. All Piston strokes should be within the specified limits for different types of wagons. The piston strokes are given below in table.
  • 11. If the piston stroke is incorrect then, record “A” Dimension, it should be 70 ±20 mm in empty and loaded condition. D. Check all brake cylinders. Wagons with in-operative brake cylinders should be marked unfit and detached. E. After the release of brake, the piston of brake cylinder should be fully inside and brake blocks are free from the wheels. F. Guard‟s emergency brake valve: Ensure that Guard Emergency brake valve is working properly by operating it. G. BPC (Brake Power Certificate): Ensure that Loco Pilot, Guard and TXR have checked the details given in the certificate and signed for its compliance.
  • 12. TOOLS AND EQUIPMENTS: [1] Rake Test Rig/Locomotive. [2] Open End spanner 18x19” [3] Spanner 10 mm & 12 mm
  • 13. SINGLE WAGON TEST “Single wagon Test” is performed on a wagon to ensure proper functioning of the air brake system. It is generally performed on the sick wagon attended in the sick line or whenever a subassembly of the air brake system is replaced either in depot or workshop. Single wagon test is also carried out after POH and after every change of distributor valve in the workshop. The different tests to be performed on the subassemblies of a wagon are as follows: Test1: Leakage Test. Test2: Sensitivity and Insensitivity Test. Test3: Brake Application and Release Test. Test4: Graduated Application and Release Test. Test5: Check and adjust Slack Adjuster SINGLE WAGON TEST
  • 14. A. TOOLS AND EQUIPMENT 1. Test Rig 2. Spanners 10mm, 12mm B. CONCEPT Single Wagon Test is performed, by using a portable device called “Test Rig”. This test rig provides all facilities similar to a driver‟s brake valve. The source of compressed air for conducting the test is through a compressor installed in depots and workshops for conducting various tests without the need of a locomotive. The part description and specification are given in table below.
  • 15. PROCEDURE FOR SINGLE WAGON TESTING (Single Pipe) A systematic lay-out of Single Wagon Test Rig (SWTR) is shown in fig. 7.33. This SWTR is utilised for testing the air brake system fitted on single wagon. The wagon should not be connected with the locomotive at the time of testing. The following procedure shall be followed for testing. i. The wagon under testing is to be coupled at one end with the SWTR coupling head BP and the other end should be closed with dummy coupling head. Pressure gauge should be fitted on brake cylinder. ii. Couple the SWTR to the main line of compressor. iii. Place the isolating cock of distributor valve on the wagon in open position i.e., the handle should be vertically down wards. iv. Set the pressure reducing valve (1) to 5 + 0.1 Kg/cm2 Open the cocks (2) and (8) and so the angle cocks on the both ends of the wagons. Move the driver‟s brake valve (3) in the charging and release position.
  • 16. v. Wait for about 5 minutes to charge the complete system. vi . Check the pressure in BP pressure gauge (7). Pressure should be 5+ 0.1 Kg. /cm2 in BP. If there is pressure drop in the gauge (7) detect the source of leakage and eliminate it. vii. Close cocks (2) & (8). Check the leakage on BP for one minute. viii. Open cock (2). Bring Driver‟s brake valve in full-service application position. ix. Record the brake cylinder filling time from 0 to 3.6 Kg. /cm2 in brake cylinder pressure gauge. x. Record maximum pressure in brake cylinder. xi. Record the pressure drop in BP from pressure gauge (4). xii. Record the piston stroke of brake cylinder. xiii. Bring Driver‟s brake valve in the charging and release position. xiv. Record the brake cylinder draining time from 3.8 + 0.1 to 0.4 Kg. /cm2 in brake cylinder pressure gauge & check complete release of brakes i.e., piston should reach its initial position.
  • 17. xvi. Open cock (6) for checking sensitivity of brakes. Record time within which brakes get applied. xvii. Close cock (6) and open cock (2). Wait till brakes are released. xviii. Close cock (2) and open cock (7) for checking the insensitivity of brakes. The brakes should not apply. xix. Close cock (7) and (8) and open cock (2), BP pressure should rise to 5 Kg. /cm2 xx. Close cock (2) and open cock (5) for emergency application. xxi. Record the brake cylinder charging time from 0 to 3.6 Kg. /cm2 in BC pressure gauge. xxii. Record maximum BC pressure. xxiii. Check the leakage in BC for 5 minutes. xxiv. Pull the manual release lever of distributor valve for about 10 sec. Brake cylinder pressure should become zero automatically. xxv. The above tests should be done in both empty and loaded condition. xxvi. The results of test shall be recorded in the test proforma attached herewith
  • 18. 10. Record the brake cylinder filling time from 0 to 3.6 kg/cm2 in brake cylinder pressure gauge. 11. Record maximum pressure in brake cylinder. 12. Record the pressure drop in BP from pressure gauge (7). 13. Record the piston stroke of brake cylinder. 14. Bring Driver's brake valve in charging and release position. 15. Record the brake cylinder draining time from 3.8 to 0.4 kg/cm2 in brake cylinder pressure gauge & check complete release of brakes i.e., piston should reach its initial position. 16. Close cock (5) and open cock (11) for charging the reservoir to 5 kg/cm2
  • 19. 17 Open cock (9) for checking sensitivity of brakes. Record the time within which brakes applied. 18 close cock (9) and open cock (5). Wait till brakes are released. 19 Close cock (5) and open cock (10) for checking the insensitivity of brakes. 20 Close cock (10) and (11) and open cock (5). BP pressure should rise to 5 Kg/cm2. 21 Close cock (5) and open cock (8) for emergency application. 22 Record the brake cylinder charging time from 0 to 3.6 kg/cm2 in BC pressure gauge. 23 Record maximum BC pressure. 24 Check the leakage in BC for 5 minutes. 25 The above tests should be done in both empty and loaded condition. 26 The results of test shall be recorded in the test proforma as given
  • 20. PROFORMA FOR SINGLE WAGON TEST FOR WAGONS OTHER THAN BOBR & BOBRN (Single pipe/Twin pipe)