1. Tom Magiropoulos Building Supervisor
Address: 49 Foxlow St, Canley Heights
NSW, 2165.
Phone No.: (02) 9609-2838
Mobile No.: 0419231258
E-Mail Address: elpitha@tpg.com.au
tomconstruction8@gmail.com
Date of Birth: 20/11/1960
I would like to obtain a position where my work & experience is mostly needed &
appreciate. I can utilize my knowledge, skills, experience & work to the best of my
ability.
Work Experience & Qualifications
• Started in 1978 as a Bricklayer & Concreting .
• In 1980 I started my own Bricklaying Company called Baliza Holdings Pty Ltd.
- Meanwhile I was supervising up to 13 Bricklayers for the Company
(Baliza Holdings Pty Ltd).
Job included the following:
- Reading of Plans.
- Setting out of building.
- Checking out levels.
• In December 1994 – I Completed the Associate Diploma in Applied Science
(Building) at TAFE.
- I applied for Builder’s License for my company Baliza Holdings Pty Ltd.
- By completing this course I gave myself the ability of doing various
projects from Houses to Multi-Storey units with basement parking.
• At the same time I also learnt Auto CAD Drafting – I’ve designed & currently
still designing a lot of clientele plans, including Design & Construction of my
own projects.
* In 2000 – Started working as a Sole Trader & was working in joint ventures with
Architect Mr. George Katsilis (mobile No: 0414645176 )doing projects up to
$1.7 million in the Eastern Suburbs.
• From 2000 to 2006 – Currently I also developing & constructing of Spec-Homes
(Duplexes,Townhouse|Villa ect).
2. PROJECTS I HAVE RECENTLY CONSTRUCTED
* Year 1999
15 South Terrace , Bankstown Three storey building
8 units with 2 shops and a basement
carpark
Cost $1,550,000 George Katsilis Architects 0414645176
I was the Project Manager Supervisor on this project
I started from the earth works , piling ,deep excavation through to finishes and
landscaping.
* Started 2001 Completed April 2002
42 Benelong Cr , Bellevue Hill Two storey building , with a basement
Garage.
Cost $700,000 + Variations Pre-Design Architects 93881579
I was the Foreman on this project
I started from the earth works , contiguous piling and underpinning to support the
existing house which was 7 m above the proposed garages under it, also deep
excavation ,construction of a first floor ,through to finishes and landscaping.
* Started May 2002
71 Latimer Rd , Bellevue Hill Two storey full brick , concrete slab const
Cost $1,250,000 + Variations BMA Architects , Bondi . Date comp: 2003
I was the Foreman on this project
I started from the earth works , contiguous piling to support the existing
swimming pool and neighboring property . Excavation ,construction of a
2 storey brick and slab construction house ,through to finishes and landscaping.
* Started Nov 2002
63 Hamilton Rd, Fairfield Three storey BrickVeneer
Cost $700,000 + Variations 4 X 2 bed Townhouses
Date comp: Aug 2003
I was the Project Manager Foreman on this project
I started from the earth works , excavation ,construction of a
3 storey BV and slab construction Townhouses ,through to finishes and
landscaping.
3. * Started Nov 2003
5 Alderney Rd, Merrylands Two storey BrickVeneer
Duplex
Private Client Date comp: July 2004
I was the Project Manager Foreman on this project
I started from the earth works , excavation ,construction of a
2 storey BV Duplex and slab construction ,through to finishes and landscaping.
* Started Jan 2005
39 Mavis Ave, Peakhurst Tri-Level with Attic
Duplex
My Development Date comp: Nov 2005
I was the Project Manager Foreman on this project
I started from the earth works , Bulk excavation ,construction of a
2 storey Full Brick and slab Duplex construction ,through to finishes and
landscaping
* Started Nov 2006
Bellevue Hill 6 Car Basement
Project Management With a 3 storey solid brick const above
Construction Cost $ 2.3M Date comp: July 2008
I was the Project Manager Building Supervisor on this project
I started from the earth works , Bulk excavation in sand stone ,
Construction of a basement in sandstone, with a 3 storey full brick and concrete
structure , through to internal finishes .
* Started Nov 2008
Bellevue Hill 2 Car Basement &Major Renovations
Project Management
Construction Cost $1.3M Date comp: Dec 2009
I am the Project Manager Building Supervisor on this project
I started from the earth works , Bulk excavation in sand ,construction of a
Concrete basement ,Underpinning the 3 storey full brick and concrete structure
through to internal finishes .
* Started Feb 2010
4. Company: 3rd
Dimension Group
Position: Contract ConstructionSite Supervisor
Construction Cost $Various Resigned from Position Sept 2010
3rd
Dimension Group does a lot of commercial and BER (Universities fitout )
For companies such as Watpac , Grocon , Feredon const, Hansen Yuncken &
Fugen ,majority of the work was detailed carpentry fitout the also do shop fitout.
My position was to inspect,co-ordinate and supervise 3-5 sites and 15-25 men
Mostly carpenters.
* Started Feb 2011
Company : Service World Const
20a Vaucluse Rd Vaucluse
Architect Bruce Stafford 7 Car Basement
Position Site Supervisor With a 3 storey solid brick & Slab Const
Construction Cost $ 6 M Date comp: Sept 2012
I am the Site Building Supervisor on this project
I started from the earth works , Bulk excavation in sand stone ,
Construction of a basement in sandstone , with a 3 storey full brick and concrete
structure ,With high quality Internal finishes throughout .
I supervise all trades during construction
I am also a hands on person.
Web Page Attached of this project
•
• Started Oct 2012
Company : Construction8 PL
69 Portland st ,Dover Hts Underground Basement
Architects MPRDG (Brian Mason) & 3Storey Building full
Owner Mr Elliot Rusanow (Nephew of Frank Lowy) Brick &concrete
Position Site Supervisor Construction
Date Comp Nov 2013
Construction Cost $ 2.6 M
I am the Site Building Supervisor on this project
I started from the earth works , Bulk excavation in sand ,
Construction of a basement in sand ,had to do 4m deep piling to peremeter of site
with a 3 storey full brick and concrete structure above ,
With high quality Internal finishes through out .
I supervise all trades during construction
• Started Nov 2013
5. Company : Construction8 PL
28 PEEL st ,Dover Hts Underground Basement
Architects RD NAHUM & 2 Storey Building full
Owner Mr Larry Narunsky Brick &concrete
Position Site Supervisor Construction
Date Comp June 2014
Construction Cost $ 1.25 M
I am the Site Building Supervisor on this project
I started from the earth works , Bulk excavation in sand ,
Construction of a basement in sand ,had to do 4m deep piling
with a 2 storey full brick and concrete structure above ,
With high quality Internal finishes through out .
I supervise all trades during construction
• Started June 2014
Company : Construction8 PL
55 Salisbury Rd Bellevue Hill
Architects Bevan Boss Designs 2 Storey Building fully
Owner Mr Elliott Placks Renovated with FF Addition
Position Site Supervisor Construction
Date Comp April 2015
Construction Cost $ 1.65 M
I am the Site Building Supervisor on this project
New Basement Garage and entry Portico
Renovate Existing 2 storey full brick and concrete structure GF ,
With a New FF Brick Veneer construction
With high quality Internal finishes through out .
Renovate existing Pool and landscaped Gardens
I supervise all trades during construction
•
LICENSES & CERTIFICATES
• Gold Drivers License.No2850XG
6. • Office of Fair Trading Contractors License – (License No.: 63115C).
• Office of Fair Trading Bricklayer & Stonemason License.(Lic NoQR31369)
• Work Cover Occupational Health & Safety General Induction for
Construction in NSW license No:CGI00774414SEQ1
• Work Cover Boom Lift Licence
• Associate Diploma of Applied Science (Building).
•
I have held a Home Owners Warranty To a Value $5,000,000.00
REFERENCE STATEMENT
22 December 2007
7. From: Dr Sam lyer
214 Enmore Rd
Enmore 2042
Phone 0403 204420
To Whom It May Concern
Reference for Mr Tom Magiropoulos
Mr Tom Magiropoulos has been hired by me to be the building supervisor in the
construction of a three level house with a basement garage that I am constructing as an
Owner Builder.
The construction work has involved shoring works and deep sand excavation together
with substantial rock (sandstone) excavation. Further to this, the project involves
concreting, brickworks, waterproofing and final finishes.
I found Tom to be knowledgeable in solving problems as they arose, advising tradesmen
and organizing the running of the project, such as working out quantities, ordering
materials, programming of trades sequence, checking on progress payments of
sub-contractors etc
The project is of a high quality standard and is due to be completed in early 2008, and is
projected be completed within the initial cost budget.
I would be happy to employ Mr Magiropoulos in any future similar project that I may under
take, and have no hesitation in recommending him.
Dr Sam lyer