2024: The FAR, Federal Acquisition Regulations, Part 30
Biosolids Pic 3 presentation final
1. City of Toronto
Class Environmental Assessment
for Biosolids Management at the
Highland Creek TP
Public Information
Centre No. 3
November 19, 2015
1
2. Outline
Project Background
Class EA Project Scope and Project Team
Biosolids Management Alternatives
Impact Assessment of Alternatives
- Health
- Environment
- Community
- Cost
Summary of Findings
Next Steps
2
4. Highland Creek Treatment Plant (HCTP)
- Connected population of ~500,000
- Rated capacity of 219 ML/d, generates approximately 40,000 wet tonnes of
biosolids each year
4
5. Rationale for the HCTP Biosolids Management Class EA
- The existing multiple hearth incinerators were commissioned in 1976 and are
nearing the end of their useful life
- The incinerator emissions meet all regulatory standards
- Urgent repairs to multiple hearth incinerators are underway, and will extend the
life of the incinerators for up to 10 years
- The City needs to plan now, to provide time for design and construction of a new
biosolids management facility
5
6. Class EA Process
The Class EA follows step-wise process to
evaluate options and identify a preferred
approach for managing biosolids
We are here
6
8. Step-Wise Evaluation Process
Short-list -
feasible for
HCTP
Class EA
Report
Long-list
Screening -
‘must-meet’
criteria
Detailed
comparative
evaluation
Preferred
biosolids
management
alternative
30-Day Public Review
Period
and
City Council Approval
required before
implementation
Step 1 Step 2
8
9. How alternatives were assessed in the Class EA Process?
EnvironmentCommunityHuman Health Cost
Best Biosolids
Management Alternative
for Highland Creek
Treatment Plant
Short-List of Feasible Biosolids Management
Alternatives for
Highland Creek Treatment Plant
Evaluation Criteria Categories
9
10. Scope of Information Developed
+ Focused Studies
- Health Impact Assessment (HIA)
- Human health risk assessment
(HHRA)
- Cumulative air impact
assessment (modelling)
- Noise impact assessment
- Traffic route assessment
+ Community feedback
- Public Information Centre No. 1
on June 16, 2014
- Public Information Centre No. 2
on April 9, 2015
- Public Information Centre No. 3
on November 19, 2015
(here today)
- HIA Stakeholders Workshops (2)
10
11. Information Developed for Biosolids Management Alternatives
+ Facilities Requirements
- Process description, schematic
- Footprint requirement on site
- Emission control
- Odour management
- Health and safety features
- Noise
- On-site storage
+ Management Approach
- Market/outlet description
- Market/outlet reliability
- Contingency
+ Operations Needs
- Staffing
- Electricity use
- Natural gas use
- Water use
- Truck fuel use
+ Costs
- Capital, operating and life-cycle
+ Impacts
- Contaminant emissions
- Traffic, noise, dust, odour during
construction
- Traffic, noise, dust, odour during
operation
- Greenhouse gas generation
11
12. Project Team
Biosolids
Engineering
Toronto
Water
CIMA
Air Quality and
Noise Modelling
Toronto
Environment
and Energy
Golder
Human Health
Impact
Assessment
Toronto
Public Health
Intrinsik
(HHRA)
Habitat
Health
Impact (HIA)
Project Management
Toronto Engineering and
Construction Services
CIMA
12
14. Alternative 1 – On-site Fluidized Bed Incineration
Two new fluidized bed incinerators would replace existing multiple-hearth
incinerators
New emission cleaning equipment to reduce particulates and mercury
Ash management in one of two ways:
- Landfill
- Recycling
Fluidized bed incinerator operating at G.E.
Booth (Lakeview) Wastewater Treatment
Plant in Mississauga
14
15. Alternative 2 – Haul Biosolids Off-site for Management
Contractors would haul biosolids from site
- 4 to 6 trucks daily
New facilities include:
- Truck loading facility with odour control
- Additional digesters
Off-site management could
include:
- Land application
- Composting
- Processing into fertilizer
- Landfill
Similar to Ashbridges Bay
TP contract program
15
16. Alternative 3 – On-site Pelletization and Off-site Pellet Management
New facilities include:
- Pelletizer process building with
odour control
- Truck loading with odour control
Contractor would haul pellets from
site for distribution
- 1 to 2 trucks per day
Pellets would be marketed as a
fertilizer product
Similar to Ashbridges Bay TP
pelletizer program
Pelletization facility and pellet
storage silos at the City of
Toronto Ashbridges Bay TP.
16
17. Transportation Mode and Route Assessment
An assessment of transport modes was
completed – haulage by large (40 tonne)
truck was identified as best mode
Transport of ash (Alt. 1), biosolids (Alt. 2) or
pellets (Alt. 3) from the HCTP would be
required
- Alternative 1: 89 trucks over a 2 week period
each year
- Alternative 2: 1,300 per year – 5 per day, 5 days
per week, 52 weeks per year
- Pelletization – 390 per year – 1 to 2 each day, 5
days per week, 52 weeks per year
Through a detailed assessment of all possible
routes from HCTP to 401 – 2 routes were
short-listed
0
500
1000
1500
Alt. 1 Alt. 2 Alt. 3
Trucks Per Year
17
21. General Approach to Evaluating Alternatives
Public and project team input to select a long list
of evaluation criteria
In general, all short-listed alternatives are:
- Feasible
- Allowable within existing regulations
- Demonstrated/proven in Ontario
The following slides present findings for each
evaluation category
21
22. Health Assessment of
Biosolids Management
Alternatives
Health Impact
Assessment (HIA)
Human Health
EnvironmentCommunity Cost
22
23. Health Impact Assessment (HIA)
Helps to address community concerns about potential health impacts
of the project
Helps to distinguish between the alternatives
Enhances and complements the Class Environmental Assessment
(EA)
Provides Medical Officer of Health with important information to
inform his recommendations to the Board of Health
A separate HIA report was prepared as part of the Class EA
The HIA was peer reviewed by independent team experts
23
25. List of Health Areas in HIA
Most important health factors Other health factors
Air quality
Traffic Safety
Soil quality
Neighbourhood characteristics:
• Recreation and leisure
• Access to transport
• Community and social cohesion
• Housing/property values
Stress – risk perception:
• Noise
• Odour
Climate change
Job opportunities / economics
25
26. Health Impacts Assessment for
Highland Creek Treatment Plant
Dr. David McKeown
Medical Officer of Health
October 26, 2015
26
27. Findings of the HIA
Overall, the health impacts associated with
the alternatives are very small
There are no appreciable differences in
health impacts among the alternatives
All alternatives evaluated achieve
significant reductions in air emissions
compared to the current multiple hearth
incinerators
27
28. Air Quality – Criteria Air Contaminants
• While there are differences, the contribution from the alternatives to air
pollution-related respiratory and cardiovascular hospitalizations and mortality
is very small
28
29. Air Quality – Carcinogens
Health Benchmark
ILCR – Incremental Life-time Cancer Risk
29
31. Human Health Risk from Air Emissions
Contribution of the HCTP to the overall health risk from air
pollution is very small for Base Case and all alternatives
• Chronic non-cancer inhalation CRs range between 3 and 12 orders of
magnitude below (i.e., <0.001% of) the relevant human health-based
benchmarks.
• For carcinogens, incremental lifetime cancer risks were between 3 and
10 orders of magnitude below (i.e., <0.001% of) the acceptable
incremental lifetime cancer risk benchmark of one-in-one-million.
All alternatives contribute less than 1% to the total cumulative
risk in the study area, and would represent an improvement to
the current situation
31
32. Human Health Risk – Multi-media Assessment
What was evaluated:
- Long-term accumulation of chemicals in soil, dust, and backyard
produce from biosolids management alternatives
- Human health risk due to exposure to air, soil, dust and home
grown produce
Results:
- Similar to air, risks due exposure from
biosolids management alternatives are
extremely small and several orders of
magnitude below health benchmarks
32
33. Traffic Safety – Route 1 and Route 4
Route 1 (Morningside) Route 4 (Port Union)
- No bike route interference
- No left turns at unsignalized intersections
- 4 schools, 3 child care /recreation
centres/libraries
- Morningside has highest youth population in
study area
- No legal truck restrictions
- Left turn lane on Manse Rd. and Lawrence
Ave. E. short for a truck
- 1 km stretch of non-buffered sidewalks
- 500 m through residential areas
- Bike route planned along Port Union Road
- No left turns at unsignalized intersections
- 1 school, 2 child care/recreation
centres/libraries
- No legal truck restrictions
- No maneuverability restrictions
- Mostly all buffered sidewalks
- 650 m through residential areas
- No criteria with high impact score
33
34. Traffic Safety
• While there are differences, the contribution of alternatives to increased risk
of injuries and fatalities is very small
34
35. Traffic Safety
Alternative 1:
Fluidized
Bed Incineration
Alternative 2:
Biosolids Transport
Off-site for
Management
Alternative 3:
Pelletization Process
and Distribution of
Fertilizer Product
85 trucks/year 1,300 trucks/year 433 trucks/year
Route 1 Route 4 Route 1 Route 4 Route 1 Route 4
Total vehicle kilometers per year 595 510 9100 7800 3031 2598
Estimated number of
fatalities per 100 years
(fatality rate x total vehicle
kilometers x 100)
0.00013 0.00011 0.00200 0.00172 0.00067 0.00057
% Increase over existing Same Same 18x 16x 5x 4x
Based on pedestrian/traffic injury rates, predicted average risk of <1
additional injury over a 100 year period for all alternatives
35
Note: Route 1 – Morningside Avenue , Route 4 – Port Union Road
36. Stress and Risk Perception - Noise and Odour
Alternative 2 and 3 have a
greater potential to result in
an increase in odour and
noise impacts
Any increase in stress
would be very small and not
a health concern
36
37. Other Health Areas
Neighbourhood characteristics
- No health effects for any alternative
Climate change (greenhouse gas)
- All alternatives represent less than 0.1% of typical per capital
greenhouse gas emissions (based on a service area of 500,000)
and less than 0.04% of the City’s greenhouse gas reduction goal
Employment
- None of the alternatives have an impact on overall employment in
Toronto
37
38. Health Equity
Truck routes were assessed in terms of the proximity to vulnerable
populations:
- Neighbourhood Improvement Areas
- Locations with high senior and child/youth populations, including:
• Schools
• Churches
• Senior homes
• Child care centres
- Cross walks
- Bicycle routes
Route 4 is predicted to have a slightly lower impact on the
community in relation to pedestrian safety, noise and vulnerable
populations
38
39. Health Impact Assessment Conclusions
Overall, the health impacts are very small and there
are no appreciable difference in the alternatives
Specific findings:
- All alternatives achieve notable reductions in health risks related to
inhalation and multi-media exposure due to air emissions compared to the
existing situation
- Among the three alternatives, Alternative 1 is anticipated to result in the
highest risk related to air emissions; whereas, Alternatives 2 and 3 would
increase risks related to truck traffic (safety, odour, noise)
- With respect to the preferred route, Route 4 is predicted to have slightly
less impact than Route 1 – for the purpose of this Class EA, both routes
are considered to be viable
39
41. Environmental Criteria
Protect air quality – minimize emissions to environment
Provide a reliable and sustainable biosolids management solution
Recover soil and fertilizer value
Minimize use of energy and other resources
Minimize greenhouse gas emissions
Minimize risk of spills
Minimize impacts during construction
41
42. Air Quality
The health risk to people in the study area from exposure to emissions
from biosolids management alternatives was evaluated in the HHRA
Air quality modelling of 43 chemicals of concern (COC) was used to
determine:
- A change in emissions from alternatives (trucks and facilities) compared to the
existing case (multiple hearth incinerators)
- The incremental change in background air quality as a result of emissions
Acetaldehyde Acrolein Antimony
Arsenic Barium Benzene
Beryllium Boron 1,3-Butadiene
Cadmium Carbon monoxide* Carbon tetrachloride
Chloroform Chromium Cobalt
Copper 1,4-Dichlorobenzene 1,2-Dichloroethane
Dichloromethane Ethylene dibromide Formaldehyde
Lead Manganese Mercury
Molybdenum Nickel compounds Nitrogen oxides*
Ozone*
Particulate matter less than 2.5 microns in
diameter (PM2.5)*
Particulate matter less than 10 microns in
diameter (PM10)*
Polychlorinated biphenyls (PCBs)
Polychlorinated dibenzo-p-dioxins and
furans1
Polycyclic aromatic hydrocarbons (PAHs)2
Selenium Strontium Sulphur dioxide*
Tetrachloroethylene Toluene Trichloroethylene
Vinyl Chloride Zinc
42
44. Modelled NOx from Biosolids Management Alternatives (Scale is 600x finer)
Criteria air chemical contributions
to respiratory and cardiovascular
induced hospitalizations and
mortality are very small (less
than 0.0004% from all
alternatives)
44
45. Protect Air Quality- Minimize Emissions to Environment
Air Quality Modelling in Study Area
- Predicted emission rates for all COC are less than 1% of City of Toronto
emissions
- All alternatives result in a decrease in chemical emissions, except for
those chemicals associated with diesel fuel (Truck traffic)
- Modelling predicts that the biosolids management alternatives will not
have an impact on air quality in the study area
Other findings
- The further trucks need to travel to bring biosolids/pellets to their final
destination, the greater the contribution of emissions
In general, all alternatives have similar, low impact
45
46. Provide a Reliable and Sustainable Biosolids Management Solution
What is environmental impact of disruption to service?
- Solids/biosolids storage in wastewater treatment plant – treatment
performance and effluent quality to Lake Ontario
- Need to haul biosolids to landfill disposal
Risk Mitigation Overall
Alternative 1 –
Fluidized Bed
Incineration
• Maintenance shut-down for
incinerator
• Full redundant standby
capacity
• Limited on-site storage
Same as
existing
Alternative 2 –
Haul biosolids off-
site
• Reliance on contractors
• Weather affects management
• Depends on suitable land
application/disposal sites
• Further distances may be
required for reliable sites
• Limited (3 to 4 d) on-site
storage
• Multiple contractors
(limited potential with
small HCTP quantities)
Least reliable
Alternative 3 –
Pelletization and
Pellet
management
• Weather affects management
• Maintenance shut-down
periods are required
• Full redundant standby
capacity
• Limited (3 to 4 d) on-site
storage
• Emergency truck loading
and landfill disposal
Less reliable
than existing
46
47. Recover Soil and Fertilizer Value
Opportunity Opportunity
Alternative 1 –
Fluidized Bed
Incineration
Very limited opportunity to recover
nutrients from ash
Very limited
opportunity
Alternative 2 – Haul
Biosolids Off-Site
High potential
for beneficial use or
further processing
into a fertilizer
Good opportunity,
although, potential for
landfilling a portion
Alternative 3 –
Pelletization and
Pellet Management
Pellet is a fertilizer
product that will
have primary use on
agricultural land
Good opportunity,
biosolids not
pelletized (in
emergency) will need
to be landfilled
47
48. Minimize Energy and Other Resources
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
Base Case -
Current MH
Incineration
Alt 1 -
Fluidized Bed
Incineration
Alt 2 - Haul
Biosolids Off-
Site
Alt 3 -
Pelletization
Electricity Use (kW.h per year)
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
Base Case -
Current MH
Incineration
Alt 1 -
Fluidized Bed
Incineration
Alt 2 - Haul
Biosolids Off-
Site
Alt 3 -
Pelletization
Natural Gas Use (m3 per year)
0
100,000
200,000
300,000
400,000
500,000
600,000
Base Case -
Current MH
Incineration
Alt 1 -
Fluidized Bed
Incineration
Alt 2 - Haul
Biosolids Off-
Site
Alt 3 -
Pelletization
Diesel Fuel Use (L per year)
Alternative 2 has most impact, due to
significantly higher diesel fuel use compared
to other alternatives, with potentially
additional resources (fuel, chemicals) use for
further processing and land application
Alternatives 1 and 3 would result in a small
increase in electricity use compared to the
base case
Alternative 3 has highest natural gas use,
but less than base case
48
49. Minimize Greenhouse Gas (GHG) Emissions
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
Base Case - Current MH
Incineration
Alt 1 - Fluidized Bed
Incineration
Alt 2 - Haul Biosolids Off-
Site
Alt 3 - Pelletization
Annual GHG (tonne CO2 equiv. per year)
Annual GHG (t CO2 eqiv. Per year)
49
• All alternatives represent less than 0.1% of
typical per capita greenhouse gas emissions
(based on a service area of 500,000) and less
than 0.04% of the City’s reduction goal
• For Alternative 2 and 3, additional CO2 from
land application or further processing is offset
by fertilizer credits (less fertilizer production)
(BEAM)
50. Other Environmental Criteria
+ Minimize risk of
environmental impacts due
to spills
- None of the materials (ash,
biosolids or pellets) would cause
a significant environmental
impact if spilled
- Alternative 2 has most potential
for spills of material and/or fuel
due to number of trucks
+ Minimize environmental
impacts due to construction
- All of the alternatives require
construction on-site with equal
potential for impacts
- Normal construction measures
would be used to mitigate
impacts
50
52. Community Criteria
Community opinion
Biosolids management staff working conditions
Nuisance impacts (noise, odour, traffic, mud)
Community impacts during construction
52
53. Public Opinion – Who commented?
No. of Attendees
(Signed In)
Number of
Comments
Received
Public Information
Centre No. 1
70 31
Public Information
Centre No. 2
62 53
53
54. Summary of Public Input from PIC No. 2
0
5
10
15
20
25
30
35
40
45
In favour of
Incineration
Opposed to
Incineration
Opposed to
Additional Truck
Traffic
In favour of
benefical use
(land application)
Opposed to
beneficial use
(land application)
Number of
Comments
54
55. General Feedback
Most frequent comments:
- Strong support for incineration (Alternative 1)
- Strong opposition to additional truck traffic through
community (Alternatives 2 and 3)
- Concerns about the health impacts of land application
of biosolids or pellets (Alternatives 2 and 3)
55
56. Biosolids Management Staff Working Conditions
Alternative Working Conditions Overall
Alternative 1 – Fluidized
Bed Incineration
Biosolids management trains are
enclosed, with minimal odour potential
Ash is inert and odourless
Least impact to HCTP staff, no
change from existing
Alternative 2 – Haul
biosolids off-site
Biosolids truck loading facility odours
within facility, with little potential for
mitigation; however, facility would not
need full time attendance
Some impact to HCTP staff
working conditions due to odour
Alternative 3 –
Pelletization and Pellet
management
Pelletizer facility has significant odours
inside facility with little potential for
mitigation
Biosolids truck loading facility odours,
similar to Alternative 2
Worst working conditions for
staff inside pelletizer facilities
due to odours
56
57. Other Community Impacts
+ Nuisance impacts (noise, traffic,
odour, mud) (not health related)
- Associated with trucks -
• Alternative 2 – most potential impact
• Alternative 3 – some impact
- In general, all impacts will be
short duration and infrequent
+ Community Impacts during
construction
- All require construction at HCTP,
similar impacts
- Mitigation measures will be used
57
59. Biosolids Management Costs
Criteria
Alternative 1:
On-site Fluidized
Bed Incineration
Alternative 2:
Biosolids and
Haulage
Off-site for
Management
Alternative 3:
Pelletization and
Haulage Off-site of
Fertilizer Product*
Capital $107 million $112 million $109 million
25 Year Life-Cycle Cost $273 million $400 million $295 million
Note:
* Does not include additional digester capacity to provide 100% beneficial use if
pelletizer is not available. Additional cost of $37 million for digester capacity.
59
61. Criteria with Equivalent and Negligible Impacts for All Alternatives
- All Health criteria
- Environmental criteria
• Protect air quality – minimize emissions to environment
• Minimize greenhouse gas emissions
• Minimize environmental impacts during construction
- Community criteria
• Minimize community impacts during construction
These criteria could not be used to distinguish
between the alternatives
61
62. Relative Impacts of Other Criteria
Criterion Alternative 1:
On-site Fluidized
Bed Incineration
Alternative 2:
Biosolids and Haulage
Off-site for Management
Alternative 3: Pelletization
and Haulage Off-site of
Fertilizer Product
Provide a reliable and
sustainable biosolids
management solution
Most reliable Least reliable Good reliability
Recover soil and
fertilizer value
Lowest opportunity Good opportunity
(however, potential for
landfilling)
Recovery of fertilizer
value
Minimize use of energy
and other resources
Lowest diesel fuel and
natural gas use, lower
electricity than Alt. 3
Highest diesel fuel use,
very low electricity and
natural gas use
Moderate diesel fuel,
high natural gas and
electricity
Community Opinion Strong community
support
Strong community
opposition
Strong community
opposition
Quality of life – odours,
noise, traffic
Least impact – no
change from current
Most impact from traffic
and odours
Lower impacts than Alt. 2
Biosolids Management
Staff Working Conditions
Best staff working
conditions
Less favourable staff
working conditions
Least favourable staff
working conditions
Life-Cycle Cost $273 million $400 million $295 million*
* Plus potential $37 million for digester capacity
62
63. Findings (Page 1 of 2)
Factors Supporting Alternative 1 - Fluidized Bed
Incineration:
- Most reliable biosolids management alternative (least
dependent on third party contractor)
- Lowest use of diesel fuel, no natural gas use
- Most supported alternative by members of the community
who have submit comments to date
- Lowest truck traffic (no change from current) and lowest risk
of spills
- Lowest greenhouse gas generation
- Least odourous and least impact to HCTP management staff
working conditions
- Lowest capital and life-cycle cost
63
64. Findings (Page 2 of 2)
Factors Supporting Alternative 2 - Off-Site
Haulage and Management:
- Recovery of soil conditioning and fertilizer value
- No added use of electricity or natural gas at HCTP
Factors Supporting Alternative 3 – Pelletization:
- Recovery of fertilizer value
- Lower truck traffic than Alternative 2
- Lower use of diesel fuel than Alternative 2
64
66. Next Steps
December/January
- Completion of Technical Memoranda
- Consolidation of comments and responses
February/March
- Report to Works Committee and Council
April
- Completion of Class EA Report
- Filing of Class EA Report for 30-day public review period
66
Notes de l'éditeur
The Highland Creek Treatment Plant (HCTP) is located in southern Scarborough in an industrial area, close to the waterfront trail, parkland, and residential areas.
As part of the wastewater treatment process, biosolids are currently being managed by two 38-year old multiple hearth incinerators; however, the incinerators are coming to the end of their service life. To support the decision to replace the incinerators, Toronto Water initiated a Schedule "B" Municipal Class Environmental Assessment (Class EA) to identify the best approach for biosolids management that will replace the multiple hearth incinerators.
This process is required by the Ontario Ministry of the Environment and Climate Change.
Due to the significant community concern in the area about the various options to manage biosolids, Toronto Water requested Toronto Public Health (TPH) to lead a Health Impact Assessment (HIA) as part of the EA process.
This HIA supplements the Rapid HIA done in 2011 by providing a more in-depth assessment of the potential health impacts of biosolids management alternatives for HCTP. It also enhances the Class EA by providing a thorough review of the alternatives from a health and health equity perspective.
I will highlight the most important findings of the HIA.
The HIA examined the potential for the proposed biosolids management alternatives to affect a number of health determinants in the study area.
The health areas are:
air quality;
traffic safety;
multi-media exposure risk (air, soil, dust and backyard produce);
stress and risk perception (namely, odours and noise);
neighbourhood characteristics (namely, access to transportation, green space and leisure, property values, community and social cohesion).
Climate change and job opportunities were also studied as secondary health areas of concern.
TPH’s 2008 HIA framework was adapted for the needs of the project.
An in-depth HIA was conducted, incorporating input from an HIA Stakeholder Group made up of stakeholders from the study area and input from the Class EA stakeholder consultation. Key experts also reviewed the draft HIA reports.
The in-depth HIA found that the health impacts of associated with the alternatives are very small and the differences among the alternatives do not result in appreciable differences in health impacts.
All three alternatives evaluated will result in significant reductions in air emissions compared to the current multiple hearth incinerators.
Summary of estimated burden of illness for each alternative
Pre-mortality Alterative 1 Alternative 2 Alterative 3
Estimated air related morality per 100 years 0.336 0.123 0.098
Estimated traffic related mortality per 100 0.00011 0.00172 0.00013
years (Route 4)
Total 0.33611 0.12472 0.09813
Morbidity Alterative 1 Alternative 2 Alterative 3
Estimated air related hospitalisations
per 100 years 0.918 0.336 0.269
Estimated traffic related injuries 0.033 0.510 0.170
per 100 years
Total 0.951 0.846 0.439
While air quality has improved, it is still an important contributor to cardiovascular and respiratory disease in Toronto.
The HIA modelled the contribution of the alternatives to criteria air contaminants to the study area’s airshed, namely nitrogen oxides, sulphur oxides, ozone, carbon monoxide, and particulate matter.
The HIA followed the approach taken for the local air quality studies done in South Riverdale and the Beach and South Etobicoke to estimate health impacts related to cumulative exposures and the contribution of emissions from Highland Creek Treatment Plant.
While there are differences, the contribution from the alternatives to respiratory and cardiovascular induced hospitalizations and mortality is very small. All three of the alternatives is expected to result in a decrease in average levels of criteria air contaminants in the study area.
[Note for MOH]:
Respiratory and cardiovascular induced hospitalizations and mortality
Existing Air Quality: 7%
Base Case: 0.0056%
Alternative 1: 0.00041%
Alternative 2: 0.00015%
Alternative 3: 0.00012%
The HIA also examined the emissions and health impact from chronic exposure to carcinogenic air toxics.
All three of the alternatives are expected to result in a significant decrease in risks when compared to the current base case.
While there are differences in risk among the alternatives, they are not important from the point of view of health. The predicted exposures from the alternatives for all the carcinogens examined are below 1-in-million excess cancer risk benchmark.
[Note for MOH]:
Incremental Lifetime Cancer Risk
Existing Air Quality: 76 in one million
Base Case: 0.25 in one million
Alternative 1: 0.024 in one million
Alternative 2: 0.011 in one million
Alternative 3: 0.011 in one million
The HIA also examined the emissions and health impact from chronic exposure to non-carcinogenic air toxics.
All three of the alternatives are expected to result in a significant decrease in risks when compared to the current base case.
While there are differences among the alternatives, they are not important from the point of view of health. The predicted exposures from the alternatives for all the non-carcinogens assessed are well below any level of concern for health.
The HIA also examined the risks from exposure to soil, dust, and backyard produce in the study area impacted by emissions from the alternatives. These results follow the same trends as the air quality findings: the risks are very low and there is a significant improvement when compared to the current base case.
[Note for MOH]:
Concentration Ratio Long term non-cancer risks
Existing Air Quality: 2.1
Base Case: 0.0042
Alternative 1: 0.00090
Alternative 2: 0.0023
Alternative 3: 0.00088
Route 1 and Route 4 have some similarities (bike routes, left turns, truck restrictions); however, they also differ in some ways (manoeverability, pedestrian exposure, distance through residential area, impact score ratings)
Route 1 had a high impact score for schools, libraries and other community facilities (7 facilities); on-street parking (on narrow Manse road); number of traffic signals (11); vertical alignment (road grade); number of transit stops (12)
Data on background traffic in the area and injury and fatality rates for Toronto were used to estimate the potential increase in risk to health from collisions with trucks travelling to and from HCTP.
Alternative 2, the alternative that would require the greatest number of trucks, results in the highest increase in truck traffic at less than 1 percent. It is estimated that even this alternative would result in a very small increase in risk, estimated to be additional less than 1 percent injuries and fatalities over a 100 year period.
The HIA examined the potential for additional noise and odours to impact health and to result in increased stress and perceived risk for those living in the study area, and in particular along the proposed truck haulage routes.
Alternative 2 and 3 have a higher potential to result in stress from odour and noise, as these two alternatives involved higher truck traffic and transport of biosolids products through the study area.
Any increase in odour or noise is very small and does not constitute a health risk.
The HIA also examined neighbourhood characteristics, impacts on climate change and jobs. The HIA did not find any evidence of health impacts related to these factors, nor were any appreciable differences between the alternatives found.