Revision 5.3
Power System Safety Rules
Safety Update
Why TransGrid are changing the Power System Safety Rules (PSSR)
2 /
PSSR Revision 5.3 – 2017, incorporates key changes that have
taken place since the introduction of Revision 5.2 in 2014.
The PSSRs are no different to all other elements of TransGrid’s
safety management system, in that they are subject to periodic
review frequencies and a desire for continual improvement. The
need for revision and the publication of this document, is the
culmination of a number of elements including but not limited to:
• Feedback from and consultation with frontline staff that use
the Rules on a daily basis; and
• Recommendations regarding rule changes that were
determined through the review of incidents, hazards and near
misses
Power System Safety Rules, Revision 5.3 Updates
Why TransGrid are changing the Power System Safety Rules (PSSR)
3 /
The purpose of TransGrid’s PSSR has never changed.
Safety remains our highest priority, with the PSSR being our core
document when managing electrical risks for our authorised
staff and contractors.
Power System Safety Rules, Revision 5.3 Updates
When will the changes happen?
4 /
• Revision 5.3 of the PSSR is effective from Monday 28 August
2017
• The PSSR and its associated documents can be downloaded
from transgrid.com.au
Power System Safety Rules, Revision 5.3 Updates
How do I know if there are changes
5 /
All significant new additions and alterations to Revision 5.2 have been highlighted in this version
by a vertical sidebar.
The following slides highlight the major changes
A full list of the changes can be found on page 86 of the PSSR
Power System Safety Rules, Revision 5.3 Updates
Administrative and General Rule Changes
6 /
Purpose statement updated
Power System Safety Rules, Revision 5.3 Updates
Administrative and General Rule Changes
7 /
Responsibilities updated to
reflect current organisational
structure
Training and Competency
clause updated to refer to a
broader range of pre-requisite
requirements and define a time
limit for use of instructed
persons
Power System Safety Rules, Revision 5.3 Updates
Administrative and General Rule Changes
8 /
Limited Entry Provision
updated to reflect current
businesses processes
In numerous locations within
the Rules the word ‘clearance’
has been replaced by ‘Safe
Approach Distance’
Power System Safety Rules, Revision 5.3 Updates
Administrative and General Rule Changes
9 /
Personal protective equipment
clause aligned with TransGrid’s
HSE procedures
Power System Safety Rules, Revision 5.3 Updates
Administrative and General Rule Changes
10 /
Work involving apparatus of
other organisations point (c)
updated to make the
requirements applicable to all
categories of work
Power System Safety Rules, Revision 5.3 Updates
Administrative and General Rule Changes
11 /
The Authorisations table has been revised:
• Category 1 is no longer a mandatory pre-
requisite for categories 6, 7 and 8
• Addition of category 4.0
• and removal of category 7.6 (unused)
Power System Safety Rules, Revision 5.3 Updates
Administrative and General Rule Changes
12 /
Attachment B: Safe Approach
Distances Table revised including:
• General layout
• SAD for Extra Low Voltage and
Low Voltage revised to current
work practices
• SAD for Vehicles added
NOTE: Safe Approach Distances to
High Voltage have not changed
Power System Safety Rules, Revision 5.3 Updates
SAFE APPROACH DISTANCES
Distance(m)
Persons No contact 0.25 (250mm)
Persons Insulated contact Insulated contact
Nominal Voltage (V): ELV <50V AC or <120V DC LV >ELV and <1000V AC or <1500V DC
11-33 66 132 220 275 330 500Nominal Voltage (kV):
Persons 0.7 1.0 1.2 1.8 2.3 3.0 3.9
Mobile Plant 3.0 3.0 3.0 6.0 6.0 6.0 8.0
Mobile Plant + 1.2 1.4 1.8 2.4 3.0 3.7 4.6
+
Persons
+
= Persons authorised 4.1, 4.3, 5.5, 6.5 or instructed persons directly supervised by a 4.1, 4.3 or 5.5
Mobile Plant + = Mobile plant operating with restrictive devices applied or an authorised safety observer appointed
Vehicles * 0.7 1.0 1.2 1.8 2.3 3.0 3.9
Distance(m)
Vehicles * = Includes mobile plant stowed for transit
Updates to Definitions
13 /
Definition of Extra Low Voltage
(ELV) updated
Definition of Low Voltage (LV)
updated
Definition of mobile plant updated
Power System Safety Rules, Revision 5.3 Updates
Updates to Definitions
14 /
EME Guide added, Site
Management Book removed
Defined terms ‘Prohibited Access
Zone’ and ‘Radio Frequency
Worker Access Zones’ replaced by
terms ‘Exclusion Zone – Red’ and
‘Exclusion Zone – Yellow’
Power System Safety Rules, Revision 5.3 Updates
Category specific changes
Power System Safety Rules, Revision 5.3 Updates15 /
There are no changes to Categories 1 and 2
Category 3 specific changes
16 /
Opening paragraph of Work in
Substations – General updated to
clarify that: High Voltage Areas are
included in the scope of category 3
Opening paragraph of 3.1 updated
to confirm this category is only for
work not affecting substation
apparatus
Power System Safety Rules, Revision 5.3 Updates
Category 3 specific changes
17 /
Wording of Substation Hazard 4
updated
Wording of Substation Hazard 7
updated
Wording of Substation Hazard 15
updated
Power System Safety Rules, Revision 5.3 Updates
Category 3 specific changes
18 /
Rule 3.2 updated to specifically
exclude category 3.2 people from
supervising instructed persons
Rule 3.3.3 updated to clarify that
only unplanned earth grid
breakages need to be repaired on
the same day
Power System Safety Rules, Revision 5.3 Updates
Category 4 specific changes
19 /
Title of Rule 4.3.2 (a) updated to
provide clarity on its purpose
Rule 4.3.2 (b) updated with
additional requirements
Power System Safety Rules, Revision 5.3 Updates
Category 5 specific changes
20 /
Rule 5.1.3 Updated to reinforce the
requirement to enter and leave a
Designated Work Area using the
approved entrance
Power System Safety Rules, Revision 5.3 Updates
Do Not Opertate
Do
Not
Ope
rtate
Do Not Opertate
Do
Not
Ope
rtate
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Access
Authority
Do Not Opertate
Do Not Opertate
All persons working
under a HV Access
Authority shall:
(a) Participate in a pre-
work risk assessment;
(b) At the start of each
day or shift, or upon
returning after leaving
site, sign on the HV
Access Authority
to indicate that they
understand the
warnings/
demonstrations given
and their responsibilities
under
the HV Access
Authority;
Category 5 specific changes
21 /
Rule 5.2 (n) revised to remove the
discretionary use of bonding leads
Power System Safety Rules, Revision 5.3 Updates
Category 5 specific changes
22 /
Rule 5.5.5 (b) updated with the
requirement for earth bridging
leads to be locked
Power System Safety Rules, Revision 5.3 Updates
Category 5 specific changes
23 /
Rule 5.6.3 revised and approved
earthing methods are now
included in the supporting
document
Rules 5.6.8 and 5.6.9 reworded to
improve clarity and the approval
requirements for defeating
interlocks changed to reflect
business processes
Power System Safety Rules, Revision 5.3 Updates
Category 6 specific changes
24 /
Rule 6.1 updated to allow category
6.1 people to supervise instructed
persons
Rule 6.1.2 updated with reference
to Dial before you Dig
Power System Safety Rules, Revision 5.3 Updates
Category 6 specific changes
25 /
New Rule 6.1.4 added ‘Work on
earthing systems’
Power System Safety Rules, Revision 5.3 Updates
Category 6 specific changes
26 /
Rule 6.3 (k) revised to remove the
discretionary use of bonding leads
Rule 6.3 (m) revised to include
multiple work locations
Rule 6.4.1 (c) ii ‘aerial conductor’
wording changed to ‘HV
conductor’
Power System Safety Rules, Revision 5.3 Updates
Category 6 specific changes
27 /
New Rule 6.3.6 added for Bridging
of Earthing Systems
Power System Safety Rules, Revision 5.3 Updates
Category 7 specific changes
28 /
Rule 7.1.2 removed and
requirements for Dial before you
Dig added to Cables Hazard 2
Rule 7.3 (k) revised to remove the
discretionary use of bonding leads
All references to Rule 7.6 have
been removed
Power System Safety Rules, Revision 5.3 Updates
E.L. 80.0m
E.L. 76.0m
E.L. 40.0m
E.L. 20.0m
E.L. 30.0m
E.L. 0.0m
OPTUS A1
TELSTRA A2
TELSTRA A3
TELSTRA A1
OPTUS A2
OPTUS A3
TELSTRA A4
TELSTRA A5
TELSTRA A6
TRANSGRID 1
TRANSGRID 2
TRANSGRID YAGI
Category 8 specific changes
29 /
‘Prohibited Access Zone’ and
‘Radio Frequency Worker Access
Zones’ replaced by terms
‘Exclusion Zone – Red’ and
‘Exclusion Zone – Yellow’
plus
References to ‘Site Management
Book’ replaced by references to
‘EME Guide’
Power System Safety Rules, Revision 5.3 Updates
Where to from here?
30 /
• Revision 5.3 of the PSSR comes into effect on 28 August 2017
and can be downloaded from transgrid.com.au
Power System Safety Rules, Revision 5.3 Updates

Contenu connexe

Similaire à Power Safety System Rules: Revisions effective in version 5.3

The Saudi Arabian Grid Code
The Saudi Arabian Grid CodeThe Saudi Arabian Grid Code
The Saudi Arabian Grid Code
Power System Operation
 
2013 Electrical Safety awareness training team brief 19_2
2013 Electrical Safety awareness training team brief 19_22013 Electrical Safety awareness training team brief 19_2
2013 Electrical Safety awareness training team brief 19_2
David King
 
Simple robust autotuning rules for 2-DoF PI controllers
Simple robust autotuning rules for 2-DoF PI controllersSimple robust autotuning rules for 2-DoF PI controllers
Simple robust autotuning rules for 2-DoF PI controllers
ISA Interchange
 
Application of Quantitative Feedback Theory for Wind Turbine Controller Design
Application of Quantitative Feedback Theory for Wind Turbine Controller DesignApplication of Quantitative Feedback Theory for Wind Turbine Controller Design
Application of Quantitative Feedback Theory for Wind Turbine Controller Design
Goran Bencic
 

Similaire à Power Safety System Rules: Revisions effective in version 5.3 (20)

8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
8.1.1_PAR 2030.7_Bower_EPRI/SNL Microgrid Symposium
 
Pre commissioning
Pre commissioningPre commissioning
Pre commissioning
 
cable testing and intallation
cable testing and intallationcable testing and intallation
cable testing and intallation
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transition
 
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
COMPARATIVE STUDY OF CLOSED LOOP CONTROL DFIG BY USING FUZZY LOGIC AND PI CON...
 
The Saudi Arabian Grid Code
The Saudi Arabian Grid CodeThe Saudi Arabian Grid Code
The Saudi Arabian Grid Code
 
2013 Electrical Safety awareness training team brief 19_2
2013 Electrical Safety awareness training team brief 19_22013 Electrical Safety awareness training team brief 19_2
2013 Electrical Safety awareness training team brief 19_2
 
Tes p-122.01-r0 (2)
Tes p-122.01-r0 (2)Tes p-122.01-r0 (2)
Tes p-122.01-r0 (2)
 
Saudi Arabian Power Distribution Code 2020
Saudi Arabian Power Distribution Code 2020Saudi Arabian Power Distribution Code 2020
Saudi Arabian Power Distribution Code 2020
 
Arai crash test facility at chakan
Arai crash test facility at chakanArai crash test facility at chakan
Arai crash test facility at chakan
 
Simple robust autotuning rules for 2-DoF PI controllers
Simple robust autotuning rules for 2-DoF PI controllersSimple robust autotuning rules for 2-DoF PI controllers
Simple robust autotuning rules for 2-DoF PI controllers
 
IRJET- Solar Radiation Tracking using Pneumatic System to Increase the Effici...
IRJET- Solar Radiation Tracking using Pneumatic System to Increase the Effici...IRJET- Solar Radiation Tracking using Pneumatic System to Increase the Effici...
IRJET- Solar Radiation Tracking using Pneumatic System to Increase the Effici...
 
NIGERIA GRID CODE
NIGERIA GRID CODE NIGERIA GRID CODE
NIGERIA GRID CODE
 
Grid code 2014
Grid code 2014Grid code 2014
Grid code 2014
 
Application of Quantitative Feedback Theory for Wind Turbine Controller Design
Application of Quantitative Feedback Theory for Wind Turbine Controller DesignApplication of Quantitative Feedback Theory for Wind Turbine Controller Design
Application of Quantitative Feedback Theory for Wind Turbine Controller Design
 
itu-t recommendation g671, g703
itu-t recommendation g671, g703itu-t recommendation g671, g703
itu-t recommendation g671, g703
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation Switchgear
 
078 switchgear install 1.0
078 switchgear install 1.0078 switchgear install 1.0
078 switchgear install 1.0
 
NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011
NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011
NERC CIP Compliance 101 Workshop - Smart Grid Security East 2011
 
IRJET- Pneumatic Conveyer with Bottle Filling and Placing Machine
IRJET-  	  Pneumatic Conveyer with Bottle Filling and Placing MachineIRJET-  	  Pneumatic Conveyer with Bottle Filling and Placing Machine
IRJET- Pneumatic Conveyer with Bottle Filling and Placing Machine
 

Plus de TransGrid AU

Powering sydneys future workshop
Powering sydneys future workshopPowering sydneys future workshop
Powering sydneys future workshop
TransGrid AU
 

Plus de TransGrid AU (20)

Unlocking Australia's Renewable Energy Future
Unlocking Australia's Renewable Energy Future Unlocking Australia's Renewable Energy Future
Unlocking Australia's Renewable Energy Future
 
All Energy 2017_TransGrid
All Energy 2017_TransGridAll Energy 2017_TransGrid
All Energy 2017_TransGrid
 
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
Smart Regulation for a 21st Century Energy System_Australian Clean Energy Sum...
 
New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017New regulation for a new energy system: Australian Clean Energy Summit 2017
New regulation for a new energy system: Australian Clean Energy Summit 2017
 
Powering sydneys future workshop
Powering sydneys future workshopPowering sydneys future workshop
Powering sydneys future workshop
 
Local Energy & Microgrids Conference 2016
Local Energy & Microgrids Conference  2016 Local Energy & Microgrids Conference  2016
Local Energy & Microgrids Conference 2016
 
CommsDay 2016 Sydney Summit
CommsDay 2016 Sydney SummitCommsDay 2016 Sydney Summit
CommsDay 2016 Sydney Summit
 
TransGrid's Renewable Energy Hub
TransGrid's Renewable Energy Hub TransGrid's Renewable Energy Hub
TransGrid's Renewable Energy Hub
 
Electricity Storage Forum 2016
Electricity Storage Forum 2016Electricity Storage Forum 2016
Electricity Storage Forum 2016
 
150819 Reliability Webinar presentation
150819 Reliability Webinar presentation150819 Reliability Webinar presentation
150819 Reliability Webinar presentation
 
TransGrid Energy Storage Australia 2015
TransGrid Energy Storage Australia 2015TransGrid Energy Storage Australia 2015
TransGrid Energy Storage Australia 2015
 
2015 TAPR Forum Presentation
2015 TAPR Forum Presentation2015 TAPR Forum Presentation
2015 TAPR Forum Presentation
 
Webinar - December Revenue Proposal Update
Webinar - December Revenue Proposal UpdateWebinar - December Revenue Proposal Update
Webinar - December Revenue Proposal Update
 
Powering Sydney's Future - end of year briefing
Powering Sydney's Future - end of year briefing Powering Sydney's Future - end of year briefing
Powering Sydney's Future - end of year briefing
 
TransGrid's December 2014 Engagement Workshop
TransGrid's December 2014 Engagement WorkshopTransGrid's December 2014 Engagement Workshop
TransGrid's December 2014 Engagement Workshop
 
141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue Proposal141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue Proposal
 
Network Planning Workshop - Powering Sydney
Network Planning Workshop - Powering SydneyNetwork Planning Workshop - Powering Sydney
Network Planning Workshop - Powering Sydney
 
Local Generation Workshop - Powering Sydney
Local Generation Workshop - Powering SydneyLocal Generation Workshop - Powering Sydney
Local Generation Workshop - Powering Sydney
 
Energy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering SydneyEnergy Efficiency Workshop - Powering Sydney
Energy Efficiency Workshop - Powering Sydney
 
Demand Response workshop - Powering Sydney
Demand Response workshop - Powering SydneyDemand Response workshop - Powering Sydney
Demand Response workshop - Powering Sydney
 

Dernier

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 

Dernier (20)

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 

Power Safety System Rules: Revisions effective in version 5.3

  • 1. Revision 5.3 Power System Safety Rules Safety Update
  • 2. Why TransGrid are changing the Power System Safety Rules (PSSR) 2 / PSSR Revision 5.3 – 2017, incorporates key changes that have taken place since the introduction of Revision 5.2 in 2014. The PSSRs are no different to all other elements of TransGrid’s safety management system, in that they are subject to periodic review frequencies and a desire for continual improvement. The need for revision and the publication of this document, is the culmination of a number of elements including but not limited to: • Feedback from and consultation with frontline staff that use the Rules on a daily basis; and • Recommendations regarding rule changes that were determined through the review of incidents, hazards and near misses Power System Safety Rules, Revision 5.3 Updates
  • 3. Why TransGrid are changing the Power System Safety Rules (PSSR) 3 / The purpose of TransGrid’s PSSR has never changed. Safety remains our highest priority, with the PSSR being our core document when managing electrical risks for our authorised staff and contractors. Power System Safety Rules, Revision 5.3 Updates
  • 4. When will the changes happen? 4 / • Revision 5.3 of the PSSR is effective from Monday 28 August 2017 • The PSSR and its associated documents can be downloaded from transgrid.com.au Power System Safety Rules, Revision 5.3 Updates
  • 5. How do I know if there are changes 5 / All significant new additions and alterations to Revision 5.2 have been highlighted in this version by a vertical sidebar. The following slides highlight the major changes A full list of the changes can be found on page 86 of the PSSR Power System Safety Rules, Revision 5.3 Updates
  • 6. Administrative and General Rule Changes 6 / Purpose statement updated Power System Safety Rules, Revision 5.3 Updates
  • 7. Administrative and General Rule Changes 7 / Responsibilities updated to reflect current organisational structure Training and Competency clause updated to refer to a broader range of pre-requisite requirements and define a time limit for use of instructed persons Power System Safety Rules, Revision 5.3 Updates
  • 8. Administrative and General Rule Changes 8 / Limited Entry Provision updated to reflect current businesses processes In numerous locations within the Rules the word ‘clearance’ has been replaced by ‘Safe Approach Distance’ Power System Safety Rules, Revision 5.3 Updates
  • 9. Administrative and General Rule Changes 9 / Personal protective equipment clause aligned with TransGrid’s HSE procedures Power System Safety Rules, Revision 5.3 Updates
  • 10. Administrative and General Rule Changes 10 / Work involving apparatus of other organisations point (c) updated to make the requirements applicable to all categories of work Power System Safety Rules, Revision 5.3 Updates
  • 11. Administrative and General Rule Changes 11 / The Authorisations table has been revised: • Category 1 is no longer a mandatory pre- requisite for categories 6, 7 and 8 • Addition of category 4.0 • and removal of category 7.6 (unused) Power System Safety Rules, Revision 5.3 Updates
  • 12. Administrative and General Rule Changes 12 / Attachment B: Safe Approach Distances Table revised including: • General layout • SAD for Extra Low Voltage and Low Voltage revised to current work practices • SAD for Vehicles added NOTE: Safe Approach Distances to High Voltage have not changed Power System Safety Rules, Revision 5.3 Updates SAFE APPROACH DISTANCES Distance(m) Persons No contact 0.25 (250mm) Persons Insulated contact Insulated contact Nominal Voltage (V): ELV <50V AC or <120V DC LV >ELV and <1000V AC or <1500V DC 11-33 66 132 220 275 330 500Nominal Voltage (kV): Persons 0.7 1.0 1.2 1.8 2.3 3.0 3.9 Mobile Plant 3.0 3.0 3.0 6.0 6.0 6.0 8.0 Mobile Plant + 1.2 1.4 1.8 2.4 3.0 3.7 4.6 + Persons + = Persons authorised 4.1, 4.3, 5.5, 6.5 or instructed persons directly supervised by a 4.1, 4.3 or 5.5 Mobile Plant + = Mobile plant operating with restrictive devices applied or an authorised safety observer appointed Vehicles * 0.7 1.0 1.2 1.8 2.3 3.0 3.9 Distance(m) Vehicles * = Includes mobile plant stowed for transit
  • 13. Updates to Definitions 13 / Definition of Extra Low Voltage (ELV) updated Definition of Low Voltage (LV) updated Definition of mobile plant updated Power System Safety Rules, Revision 5.3 Updates
  • 14. Updates to Definitions 14 / EME Guide added, Site Management Book removed Defined terms ‘Prohibited Access Zone’ and ‘Radio Frequency Worker Access Zones’ replaced by terms ‘Exclusion Zone – Red’ and ‘Exclusion Zone – Yellow’ Power System Safety Rules, Revision 5.3 Updates
  • 15. Category specific changes Power System Safety Rules, Revision 5.3 Updates15 / There are no changes to Categories 1 and 2
  • 16. Category 3 specific changes 16 / Opening paragraph of Work in Substations – General updated to clarify that: High Voltage Areas are included in the scope of category 3 Opening paragraph of 3.1 updated to confirm this category is only for work not affecting substation apparatus Power System Safety Rules, Revision 5.3 Updates
  • 17. Category 3 specific changes 17 / Wording of Substation Hazard 4 updated Wording of Substation Hazard 7 updated Wording of Substation Hazard 15 updated Power System Safety Rules, Revision 5.3 Updates
  • 18. Category 3 specific changes 18 / Rule 3.2 updated to specifically exclude category 3.2 people from supervising instructed persons Rule 3.3.3 updated to clarify that only unplanned earth grid breakages need to be repaired on the same day Power System Safety Rules, Revision 5.3 Updates
  • 19. Category 4 specific changes 19 / Title of Rule 4.3.2 (a) updated to provide clarity on its purpose Rule 4.3.2 (b) updated with additional requirements Power System Safety Rules, Revision 5.3 Updates
  • 20. Category 5 specific changes 20 / Rule 5.1.3 Updated to reinforce the requirement to enter and leave a Designated Work Area using the approved entrance Power System Safety Rules, Revision 5.3 Updates Do Not Opertate Do Not Ope rtate Do Not Opertate Do Not Ope rtate Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority Access Authority
  • 21. Do Not Opertate Do Not Opertate All persons working under a HV Access Authority shall: (a) Participate in a pre- work risk assessment; (b) At the start of each day or shift, or upon returning after leaving site, sign on the HV Access Authority to indicate that they understand the warnings/ demonstrations given and their responsibilities under the HV Access Authority; Category 5 specific changes 21 / Rule 5.2 (n) revised to remove the discretionary use of bonding leads Power System Safety Rules, Revision 5.3 Updates
  • 22. Category 5 specific changes 22 / Rule 5.5.5 (b) updated with the requirement for earth bridging leads to be locked Power System Safety Rules, Revision 5.3 Updates
  • 23. Category 5 specific changes 23 / Rule 5.6.3 revised and approved earthing methods are now included in the supporting document Rules 5.6.8 and 5.6.9 reworded to improve clarity and the approval requirements for defeating interlocks changed to reflect business processes Power System Safety Rules, Revision 5.3 Updates
  • 24. Category 6 specific changes 24 / Rule 6.1 updated to allow category 6.1 people to supervise instructed persons Rule 6.1.2 updated with reference to Dial before you Dig Power System Safety Rules, Revision 5.3 Updates
  • 25. Category 6 specific changes 25 / New Rule 6.1.4 added ‘Work on earthing systems’ Power System Safety Rules, Revision 5.3 Updates
  • 26. Category 6 specific changes 26 / Rule 6.3 (k) revised to remove the discretionary use of bonding leads Rule 6.3 (m) revised to include multiple work locations Rule 6.4.1 (c) ii ‘aerial conductor’ wording changed to ‘HV conductor’ Power System Safety Rules, Revision 5.3 Updates
  • 27. Category 6 specific changes 27 / New Rule 6.3.6 added for Bridging of Earthing Systems Power System Safety Rules, Revision 5.3 Updates
  • 28. Category 7 specific changes 28 / Rule 7.1.2 removed and requirements for Dial before you Dig added to Cables Hazard 2 Rule 7.3 (k) revised to remove the discretionary use of bonding leads All references to Rule 7.6 have been removed Power System Safety Rules, Revision 5.3 Updates
  • 29. E.L. 80.0m E.L. 76.0m E.L. 40.0m E.L. 20.0m E.L. 30.0m E.L. 0.0m OPTUS A1 TELSTRA A2 TELSTRA A3 TELSTRA A1 OPTUS A2 OPTUS A3 TELSTRA A4 TELSTRA A5 TELSTRA A6 TRANSGRID 1 TRANSGRID 2 TRANSGRID YAGI Category 8 specific changes 29 / ‘Prohibited Access Zone’ and ‘Radio Frequency Worker Access Zones’ replaced by terms ‘Exclusion Zone – Red’ and ‘Exclusion Zone – Yellow’ plus References to ‘Site Management Book’ replaced by references to ‘EME Guide’ Power System Safety Rules, Revision 5.3 Updates
  • 30. Where to from here? 30 / • Revision 5.3 of the PSSR comes into effect on 28 August 2017 and can be downloaded from transgrid.com.au Power System Safety Rules, Revision 5.3 Updates