2015 Africa Rail Conference
Nigeria: Country Spotlight
By
ENGR. ADESEYI SIJUWADE, FNSE, FCILT
July, 2015
MANAGING DIRECTOR
NIGERIAN RAILWAY CORPORATION
Infrastructure Development Plan
Railway Development Programme
 Opportunities for Private Sector Participation
Conclusion
Overview
Infrastructure Development Plan
 The backbone of a nation’s economy is its
stock of infrastructure
 Typically, for developed countries,
infrastructure is responsible for about 70%
of GDP, but in Nigeria, infrastructure
accounts for only 35 - 40% of GDP
 The infrastructure gap of about
USD2.9trillion is intended to be closed over
the next 30 years
 To stimulate further growth and
diversification of the Nigerian economy,
attract foreign investment and enhance job
creation, the Federal Government came up
with the Vision 20:2020 roadmap.
Infrastructure Development Plan – Cont’d
• Nigeria’s Vision 20:2020 aims to promote sustained
and inclusive economic growth, and elevate
Nigeria’s economy to be among the top 20
economies in the world by the year 2020
• Inspired by Vision 20:2020 aspirations, the
National Integrated Infrastructure Master Plan
(NIIMP) was developed as an all inclusive
approach to infrastructure delivery.
• The NIIMP is a 30 year plan that covers “core”
infrastructure – Transport, Energy, ICT and Water
and others such as Agriculture, Mining, Housing
and Social Infrastructure with priority projects
outlined for the first 5 years of the plan
Infrastructure Development Plan: Focus on Rail
Vision 20:2020 - At least 40 million tons of freight by 2020.
Action Plans
RAIL • Rehabilitation of the existing narrow gauge rail (3500km network)
• Completion of the Ajaokuta-Warri standard gauge line.
• Rehabilitation of rail links within Nigeria’s main ports.
• Construction of mass transit rail lines in Lagos and Abuja.
• Construction of rail lines to link Inland Container Depots (ICDs) to sea ports
• Concession of the rail lines from Lagos to Kano and from Port Harcourt to Maiduguri.
• Expansion of the standard gauge network by 784km
NIIMP
Targets
RAIL • To invest about USD75B over the next 30 years which will include construction of over 6,000
kilometres of new standard gauge lines
• Link all major economic centres to the rail network
• Provide adequate rail infrastructure for even economic development of the country.
• Create an enabling environment for private sector participation in the provision of rail infrastructure.
Railway Development Programme - Background
The Nigeria Railway system is about 117years
old.
Between 1898 and 1964 Nigeria had built a
network of narrow gauge rail lines totaling
3505km.
In 1986, the Federal Government of Nigeria
commenced the construction of 326 km standard
gauge rail line phase 1 from Itakpe – Ajaokuta –
Warri.
However, for over two decades, the rail system
became comatose up till 2009 when the
government commenced implementation of a 25
year Strategic Vision to revive the sector
adopting a systematic dual approach.
This entails the rehabilitation of the entire
existing narrow gauge lines simultaneously with
the development of standard gauge lines.
In February, 2011 the Federal Government of
Nigeria commenced the construction of 187.5
km Abuja – Kaduna Standard gauge rail line.
HISTORICAL DEVELOPMENT OF
RAILWAYS IN NIGERIA
GOMBE – MAIDUGURI
1963 – 1964(302km)
BAUCHI – GOMBE
1961 – 1963(166km)
KURU – BAUCHI
1958 – 1961(166km)
KADUNA JUNCTION -
KAFANCHAN 1922 –
1927(179km)
ENUGU-MAKURDI
1916 – 1924(220km)
PH - ENUGU
1914 – 1916(243km)
KANO - BARO
1907 –1911(562km)
JEBBA - MINNA
1909 -1915(225km)
IBADAN - JEBBA
1901 –1909(295km)
LAGOS - IBADAN
1898 –1901(193km)
KAF – JOS OPENED 1927
(101km)
PH – ONNE ON-
GOING 19km
AJAOKUTA – WARRI
ONGOING (277km)
Railway Development Programme – Track Rehabilitation
 The rehabilitation of over 90% of the
entire 3500km narrow gauge network
throughout the country is near
completion.
 Rehabilitation of the Lagos to Kano,
and Port Harcourt to Gombe lines is
completed and passenger services and
haulage of goods along the lines have
since commenced.
 Rehabilitation of sidings and loop lines
along the Western line, including links
to key industrial locations between
Lagos and Kano and a spur line to the
Kaduna Power Plant Complex is
expected to be completed by end of
2015.
Railway Development Programme – Update on
Rehabilitation Projects
Contract Distance Contractor Physical Progress
Track & Signalling – Western Line (Lagos –Jebba)
Lagos – Ibadan – Ilorin - Jebba
488km CCECC Nig. Ltd. 100%
Track & Signalling – Western Line (Jebba – Kano)
Jebba – Minna – Kaduna – Zaria - Kano
636km Costain (WA) Ltd 99.5%
Signalling & Telecoms – Eastern and Western Lines
Upgrading of Signalling Equipment
1,657km A3&O / Gear Group / Ansaldo 45%
Track– Eastern Line (PH – Makurdi)
PH – Umuahia – Enugu - Makurdi
463km Eser Contracting W. A 85%
Track – Eastern Line (Makurdi – Kuru, Plus Spur Jos &
Kafanchan)
Makurdi – Lafia – Kuru – Spur to Jos – Kafachan and Kaduna
554m CGGC 85%
Track – Eastern Line (Kuru – Maiduguri)
Kuru – Bauchi – Gombe - Maiduguri
640km Lingo 47%
Track – Zaria – Kaura Namoda
Zaria – Funtua – Gusau – Kaura Namoda
221km Duluidas 90%
Addendum to Lagos to Jebba Contract
Rehabilitation of Sidings & LoopLines from Lagos – Kano and
Lagos – Kano CCECC 65%
Railway Development Programme – Track Rehabilitation
Track Condition at Aba Before Rehabilitation
Akerri Bridge Before Rehabilitation Akerri Bridge After Rehabilitation
Track Condition at Aba After Rehabilitation
Railway Development Programme - Construction of New
Standard Gauge Lines
 Construction of the Itakpe – Ajaokuta –
Warri Standard Gauge line (277km) is in
progress and expected to be completed by
end of 2015.
 Construction of Abuja(Idu) – Kaduna
Standard gauge line (187km) is over 85%
also expected to be delivered end of 2015.
 Construction of Lagos – Ibadan Standard
Gauge (double track) 2 x 180km has been
awarded and will commence as soon as
funding arrangement is concluded with the
China Exim Bank by the Federal Ministry
of Finance.
Abuja - Kaduna
Itakpe – Ajaokuta – Warri
States Light Rail project
Various State Governments are
embarking on light rail projects to
address the urban transportation
challenges:
 Lagos State rail mass transit Blue
Line project is ongoing
 River State Mono-rail project in
Port Harcourt is about 95%
completed
 Ogun State has just award an
inter/intra state rail construction
project to the CCECC
 Abuja Light Rail project is nearing
completion
Blue Line, Lagos
Railway Development Programme - Locomotives and
Rolling Stock
FUNCTIONAL REPAIRABLE
LOCOMOTIVES
• Shunters
• Mainline
29 55
WAGONS
• Container
• Oil Tank
• Covered
• Hopper
• Wooden
250 550
COACHES
• Standard
• 1st Class
• Sleepers
• Canteen
• Inspection
• Baggage Vans
120 50
 Refurbished 250 wagons
 Refurbished 120coaches
 Procured 25Nos. 2500HP GE Locomotives
 Procured 4 Nos. 1800HP CNR Locomotives
 Procured 40Nos. Oil Tank Wagons
 Procured 2Nos. 100ton Telescopic Cranes
 Procured 4Nos. 60ton Overhead Cranes
 Procured 3 Nos. Inspection Vehicles
 Procured 5Nos. Rail Road Recovery Vehicles
 Procured 3 Nos. Wheel Lathe Machine, fully installed
 Procured 2 Sets of Diesel Multiple Units (DMU)
 Procured 11Nos. 68-Seater Air-conditioned Coaches
 Procured 18Nos. 4-Seater Motorized Rail Trolley
 Procured 2Nos. 16-Seater Rail Buses & 2Nos. Rail Cars
 Ordered 2Nos. 1800HP CNR Locomotives and 2Nos. Power Cars to be
delivered in 2015
 Ordered for 2Nos. 3,500 HP Locomotives with in-built power car and
5Nos. Air Conditioned Coaches for Standard Gauge Line to be
delivered in 2015
Railway Development Programme – Modernisation of
Locomotives & Rolling Stock
 NRC is moving towards localization and skills transfer
 Modernization of NRC’s existing, GE Transportation
U-series and other EMD series locomotives
 Modernisation of 60Nos. Flat Bed Wagons (Primarily
used for movement of bonded containers from Ports)
 Modernisation of 20Nos. Pan Xtra Goods (PXG)
Covered Wagons (Primarily used for movement of
bagged cement)
 Modernisation of 40Nos. Covered Hopper Wagon
(CHW) Primarily used for movement of Wheat
 Modernisation of 6Nos. Power Cars (Housing
generators that supply electricity for air-conditioning
and lighting in passenger coaches)
Railway Development Programme - Current Train Operations
• Passengers Service
Intra-city Mass Transit:
Lagos Mass Transit Train: 18 Trips per day,
Kaduna Intracity Mass : 10 Trips per day
Intercity Passenger Service:
Lagos – Kano –Lagos Train: twice per week,
Lagos-Ilorin-Lagos Train: thrice per week,
Offa – Kano - Offa Train: Once a week,
Minna – Kaduna – Minna Train: thrice per
week,
Kano – Nguru Train: twice per week,
Enugu – Port Harcourt – Enugu twice per week
Port Harcourt – Kafanchan once a week
Kaduna – Gombe – Kaduna once a week
Excursion Trains: Highly patronized during
festivities
Coming Soon: New Mixed Trains from Kano –
Port Harcourt , and Gombe to PH to commence in
July, 2015
• Freight Service
Flour Mills (Wheat) Traffic: Lagos to Kano,
carrying about 3,000 tons per month
Lafarge Cement Traffic, Lagos to Kano, carrying
about 3,000 tons monthly
Movement of containers for ICNL: Lagos to Kano
about 2,000 tons monthly
Track Materials for Eastern Line Contractors, about
9,000 tons monthly
Movement of Petroleum Products for NRC and
Connect rail: Lagos to Kano
Coming Soon – Container Traffic for APM, Lagos
to Kano
0
1 000 000
2 000 000
3 000 000
4 000 000
5 000 000
6 000 000
2009 2010 2011 2012 2013 2014
OPERATIONAL PERFORMANCE – PASSENGER SERVICES
Opportunities for Private Sector Participation - Projection Of
Train Services Over The Next 10 Years
Route 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Narrow Gauge
Eastern Line (PortHarcourt - Maiduguri)
Western Line (Lagos - Kano)
Standard Gauge
Itakpe - Ajaokuta - Warri
Abuja - Kaduna
Lagos - Ibadan
Zaria –Kaura Namoda- Birnin Konni
Ajaokuta(Eganyi) - Obajana - Abuja
Ajaokuta - Oturkpo - Onitsha
Eganyi(Near Ajaokuta) - Lokoja - Abaji -
Abuja
Lagos - Abuja (High Speed)
Opportunities for Private Sector Participation - Projected
Rolling Stock Requirement For The Next 10 Years
Rolling Stock 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 total
Locomotives
20 25 20 25 230 37 42 44 42 50 535
Coaches 100 100 100 100 846 200 200 100 100 200 2,046
Wagons 350 250 250 200 3,100 1,250 200 200 200 200 9,300
Opportunities for Private Sector Participation – PPP Initiatives
 Finance, Supply, and jointly manage with
NRC, utilization of wagons to enhance
freight haulage capacity
 Finance, Supply, and jointly manage with
NRC, utilization of coaches to enhance
passenger carriage capacity
 Design, Build, Maintain, Operate, and
Transfer (DBMOT) of Warehousing to
provide suitable, safe and secure storage
space for goods
 Finance, Supply, and Operate modern
facilities and provide services for loading
and offloading of goods
1) Logistics Services
Remodelling and Redevelopment of 9 Major Railway
Stations to incorporate Commercial Outlet
2) Station Remodelling and Redevelopment
 Development of 8Nos. Railway Landed Properties at
Prime locations for Residential, Hotel and other
Commercial purposes
3) Development of Railway Landed Properties
Outline Business Cases (OBC) for the 3 PPP
initiatives are being finalised by our
Transaction Advisers following which
Procurement Process for PPP Consortiums
will commence
S/N FEASIBILITY STUDIES COMPLETED
1 Lagos - Abuja (High Speed 550km)
2 Ajaokuta (Eganyi)-Obajana-Jakura-Baro-Abuja with additional line from Ajaokuta - Otukpo - to include the
Anyigba - Ejule - Idah - Adoru - Nsukka - Adani - Omor - Anaku - Aguleri - Nsugbe - Onitsha Rail Line (821km)
3 Zaria-Kaura Namoda-Sokoto- Illela -Birnin Konni (Niger Republic - 520km)
4 Benin-Agbor-Onitsha-Nnewi-Owerri-Aba with additional line from Onitsha-Enugu-Abakaliki (500km)
5 Eganyi(Near Ajaokuta) - Lokoja - Abaji - Abuja (280km)
FEASIBILITY STUDIES ON-GOING
6 Kano – Bichi - Katsina – Jibiya (354km)
7 Sokoto – Birnin Kebbi - Jega – Yauri - Makera with a branch line to Kontagora (408km)
8 Aba – Ikot Ekpene - Ibiono - Itu (Spur Uyo) Odukpani Calabar (340km)
9 Port Harcourt – Aba – Umuahia – Enugu – Makurdi – Lafia - Jos – Bauchi – Gombe- Biu - Maiduguri (1,552km)
10 Calabar -Ikom – Obudu – Ogoja – KatsinaAla – Wukari – Jalingo – Yola – Maiduguri (1,069km)
11 Kano – Nguru – Gashua – Damaturu – Maiduguri – Gamboru Ngala (707km)
Opportunities for Private Sector Participation – Greenfield Projects
20
Conclusion
Nigeria is making appreciable efforts to address its infrastructure challenges
The Federal Government has demonstrated great commitment towards
Revitalization and Modernization of the rail system
However, Government cannot fully address the Railway infrastructural challenges
without significant involvement of the private sector
The Government is making efforts to provide the enabling environment for
effective Private sector participation in the country’s rail sector - The Nigerian
Railway Corporation Act of 1955 is in the process of being repealed and re-
enacted. The draft Bill has been forwarded to the National Assembly.
Nigeria’s investment climate is currently very attractive hence the increase in the
FDI inflow in recent times
Now is the time to take advantage of the enormous opportunities in Nigeria Rail
Sector.
Thank you for Listening

Contenu connexe

Tendances

Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)
Gurparvesh kaur
 
Ppt on mono rail by rahul
Ppt on mono rail by rahulPpt on mono rail by rahul
Ppt on mono rail by rahul
Vikas Gupta
 

Tendances (20)

Summer training report rdso ajju
Summer training report rdso ajjuSummer training report rdso ajju
Summer training report rdso ajju
 
Bangladeshi Rail (by Robin)
Bangladeshi Rail (by Robin)Bangladeshi Rail (by Robin)
Bangladeshi Rail (by Robin)
 
Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)
 
Level of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation MethodLevel of Service(LOS) of a road with Calculation Method
Level of Service(LOS) of a road with Calculation Method
 
Green roads for healthy environment
Green roads for healthy environment Green roads for healthy environment
Green roads for healthy environment
 
Rajkot BRTS
Rajkot BRTSRajkot BRTS
Rajkot BRTS
 
Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)Kanchrapara Railway workshop Project(Short)
Kanchrapara Railway workshop Project(Short)
 
Cmrl ppt
Cmrl pptCmrl ppt
Cmrl ppt
 
Rake maintenance (C&W Depot AGC ) Indian Railways
Rake maintenance (C&W Depot AGC )  Indian RailwaysRake maintenance (C&W Depot AGC )  Indian Railways
Rake maintenance (C&W Depot AGC ) Indian Railways
 
Traffic & transportation – ii
Traffic & transportation – iiTraffic & transportation – ii
Traffic & transportation – ii
 
Ppt on mono rail by rahul
Ppt on mono rail by rahulPpt on mono rail by rahul
Ppt on mono rail by rahul
 
Indian Freight Trains
Indian Freight TrainsIndian Freight Trains
Indian Freight Trains
 
Land use transportation relation
Land use  transportation relationLand use  transportation relation
Land use transportation relation
 
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
IMPACT  OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA IMPACT  OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
 
Public Transport Systems, Intermediate Public Transport Systems and their Cha...
Public Transport Systems, Intermediate Public Transport Systems and their Cha...Public Transport Systems, Intermediate Public Transport Systems and their Cha...
Public Transport Systems, Intermediate Public Transport Systems and their Cha...
 
Intelligent Transportation System Modified
Intelligent Transportation System ModifiedIntelligent Transportation System Modified
Intelligent Transportation System Modified
 
The Motor Vehicle (Amendment) Bill 2016
The Motor Vehicle (Amendment) Bill 2016The Motor Vehicle (Amendment) Bill 2016
The Motor Vehicle (Amendment) Bill 2016
 
Dedicated Freight corridor
Dedicated Freight corridorDedicated Freight corridor
Dedicated Freight corridor
 
BRT Chennai
BRT ChennaiBRT Chennai
BRT Chennai
 
Lesson 4 national transport policy
Lesson 4 national transport policyLesson 4 national transport policy
Lesson 4 national transport policy
 

En vedette

En vedette (6)

Nigerija
NigerijaNigerija
Nigerija
 
The NN2020 group high speed railway for Nigeria
The NN2020 group high speed railway for NigeriaThe NN2020 group high speed railway for Nigeria
The NN2020 group high speed railway for Nigeria
 
The Strategic Importance of Railways in Africa. Overview of the Present Syste...
The Strategic Importance of Railways in Africa. Overview of the Present Syste...The Strategic Importance of Railways in Africa. Overview of the Present Syste...
The Strategic Importance of Railways in Africa. Overview of the Present Syste...
 
Growth through corridor and port development
Growth through corridor and port developmentGrowth through corridor and port development
Growth through corridor and port development
 
FEDERAL MINISTRY OF WORKS: TRANSFORMING NIGERIA ROADS, ACHIEVEMENTS AND CHALL...
FEDERAL MINISTRY OF WORKS: TRANSFORMING NIGERIA ROADS, ACHIEVEMENTS AND CHALL...FEDERAL MINISTRY OF WORKS: TRANSFORMING NIGERIA ROADS, ACHIEVEMENTS AND CHALL...
FEDERAL MINISTRY OF WORKS: TRANSFORMING NIGERIA ROADS, ACHIEVEMENTS AND CHALL...
 
SUSTAINABLE Biofuels INDUSTRY in Nigeria
SUSTAINABLE Biofuels INDUSTRY in NigeriaSUSTAINABLE Biofuels INDUSTRY in Nigeria
SUSTAINABLE Biofuels INDUSTRY in Nigeria
 

Similaire à Nigeria rail industry

Rail budget highlights2011-12
Rail budget highlights2011-12Rail budget highlights2011-12
Rail budget highlights2011-12
Nil Wahulkar
 

Similaire à Nigeria rail industry (20)

Ministry of Transport Report
Ministry of Transport ReportMinistry of Transport Report
Ministry of Transport Report
 
#MP2013 Presentation of the Hon. Minister of Transport, Senator Idris Umar
#MP2013 Presentation of the Hon. Minister of Transport, Senator Idris Umar #MP2013 Presentation of the Hon. Minister of Transport, Senator Idris Umar
#MP2013 Presentation of the Hon. Minister of Transport, Senator Idris Umar
 
Mooc project -adeolu oketayo--23rd february 2022
Mooc project -adeolu oketayo--23rd february 2022Mooc project -adeolu oketayo--23rd february 2022
Mooc project -adeolu oketayo--23rd february 2022
 
Transpot system in India
Transpot system in IndiaTranspot system in India
Transpot system in India
 
Dfc
DfcDfc
Dfc
 
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
THE EAST AND CENTRAL AFRICA REGIONAL DEVELOPMENT. Why Kenya remain the hegemo...
 
Globalization and indian railways
Globalization and indian railwaysGlobalization and indian railways
Globalization and indian railways
 
Fmt
FmtFmt
Fmt
 
project.pptx
project.pptxproject.pptx
project.pptx
 
INDIAN RAILWAYS PRESENTATION BY BHAVIK KHAKHKHAR
INDIAN RAILWAYS PRESENTATION BY BHAVIK KHAKHKHARINDIAN RAILWAYS PRESENTATION BY BHAVIK KHAKHKHAR
INDIAN RAILWAYS PRESENTATION BY BHAVIK KHAKHKHAR
 
Development of Transport Infrastructure in Afghanistan
Development of Transport Infrastructure in AfghanistanDevelopment of Transport Infrastructure in Afghanistan
Development of Transport Infrastructure in Afghanistan
 
INDIA - SURGING AHEAD
INDIA - SURGING AHEAD INDIA - SURGING AHEAD
INDIA - SURGING AHEAD
 
logistics
logisticslogistics
logistics
 
project.pptx
project.pptxproject.pptx
project.pptx
 
Rail budget highlights2011-12
Rail budget highlights2011-12Rail budget highlights2011-12
Rail budget highlights2011-12
 
Pakistan railways
Pakistan railwaysPakistan railways
Pakistan railways
 
09.02.1012 Sustaining the coal sector with the road and transportation policy...
09.02.1012 Sustaining the coal sector with the road and transportation policy...09.02.1012 Sustaining the coal sector with the road and transportation policy...
09.02.1012 Sustaining the coal sector with the road and transportation policy...
 
Investment outlook: what investors are looking for - John Meyer, SP Angel
Investment outlook: what investors are looking for - John Meyer, SP AngelInvestment outlook: what investors are looking for - John Meyer, SP Angel
Investment outlook: what investors are looking for - John Meyer, SP Angel
 
Infrastructure
InfrastructureInfrastructure
Infrastructure
 
Railways Sector Report - July 2018
Railways Sector Report - July 2018Railways Sector Report - July 2018
Railways Sector Report - July 2018
 

Plus de Tristan Wiggill

Plus de Tristan Wiggill (20)

Business Fleet Africa May 2023.pdf
Business Fleet Africa May 2023.pdfBusiness Fleet Africa May 2023.pdf
Business Fleet Africa May 2023.pdf
 
Business Fleet Africa April 2023.pdf
Business Fleet Africa April 2023.pdfBusiness Fleet Africa April 2023.pdf
Business Fleet Africa April 2023.pdf
 
Business Fleet Africa March 2023.pdf
Business Fleet Africa March 2023.pdfBusiness Fleet Africa March 2023.pdf
Business Fleet Africa March 2023.pdf
 
Business Fleet Africa January 2023.pdf
Business Fleet Africa January 2023.pdfBusiness Fleet Africa January 2023.pdf
Business Fleet Africa January 2023.pdf
 
Business Fleet Africa December 2022.pdf
Business Fleet Africa December 2022.pdfBusiness Fleet Africa December 2022.pdf
Business Fleet Africa December 2022.pdf
 
Business Fleet Africa November 2022.pdf
Business Fleet Africa November 2022.pdfBusiness Fleet Africa November 2022.pdf
Business Fleet Africa November 2022.pdf
 
Business Fleet Africa October 2022.pdf
Business Fleet Africa October 2022.pdfBusiness Fleet Africa October 2022.pdf
Business Fleet Africa October 2022.pdf
 
How do we keep Gauteng moving?
How do we keep Gauteng moving?How do we keep Gauteng moving?
How do we keep Gauteng moving?
 
Gauteng Transport Authority update
Gauteng Transport Authority updateGauteng Transport Authority update
Gauteng Transport Authority update
 
Road Funding in South Africa
Road Funding in South AfricaRoad Funding in South Africa
Road Funding in South Africa
 
Self regulation and road funding perspectives from the road transport managem...
Self regulation and road funding perspectives from the road transport managem...Self regulation and road funding perspectives from the road transport managem...
Self regulation and road funding perspectives from the road transport managem...
 
Roads: So how do we pay for them?
Roads: So how do we pay for them?Roads: So how do we pay for them?
Roads: So how do we pay for them?
 
Road funding from a freight forwarding and logistics perspective
Road funding from a freight forwarding and logistics perspectiveRoad funding from a freight forwarding and logistics perspective
Road funding from a freight forwarding and logistics perspective
 
Feedback on DRiVE: Distance-based Road user charge Voluntary Experiment
Feedback on DRiVE: Distance-based Road user charge Voluntary ExperimentFeedback on DRiVE: Distance-based Road user charge Voluntary Experiment
Feedback on DRiVE: Distance-based Road user charge Voluntary Experiment
 
E-tolls: The Impact on Development in Gauteng
E-tolls: The Impact on Development in GautengE-tolls: The Impact on Development in Gauteng
E-tolls: The Impact on Development in Gauteng
 
Transport and the economy: Understanding the relationship...and the dangers
Transport and the economy: Understanding the relationship...and the dangersTransport and the economy: Understanding the relationship...and the dangers
Transport and the economy: Understanding the relationship...and the dangers
 
Sout Africa's fuel price
Sout Africa's fuel priceSout Africa's fuel price
Sout Africa's fuel price
 
The Future of National Roads: The 2030 Roads Plan and a Sustainable Funding M...
The Future of National Roads: The 2030 Roads Plan and a Sustainable Funding M...The Future of National Roads: The 2030 Roads Plan and a Sustainable Funding M...
The Future of National Roads: The 2030 Roads Plan and a Sustainable Funding M...
 
Beneficiaries of an optimally designed transportation system
Beneficiaries of an optimally designed transportation system Beneficiaries of an optimally designed transportation system
Beneficiaries of an optimally designed transportation system
 
Road Funds and Road User Charging in SADC
Road Funds and Road User Charging in SADC Road Funds and Road User Charging in SADC
Road Funds and Road User Charging in SADC
 

Dernier

Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Abortion pills in Kuwait Cytotec pills in Kuwait
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
laloo_007
 

Dernier (20)

Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' Slideshare
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 

Nigeria rail industry

  • 1. 2015 Africa Rail Conference Nigeria: Country Spotlight By ENGR. ADESEYI SIJUWADE, FNSE, FCILT July, 2015 MANAGING DIRECTOR NIGERIAN RAILWAY CORPORATION
  • 2. Infrastructure Development Plan Railway Development Programme  Opportunities for Private Sector Participation Conclusion Overview
  • 3. Infrastructure Development Plan  The backbone of a nation’s economy is its stock of infrastructure  Typically, for developed countries, infrastructure is responsible for about 70% of GDP, but in Nigeria, infrastructure accounts for only 35 - 40% of GDP  The infrastructure gap of about USD2.9trillion is intended to be closed over the next 30 years  To stimulate further growth and diversification of the Nigerian economy, attract foreign investment and enhance job creation, the Federal Government came up with the Vision 20:2020 roadmap.
  • 4. Infrastructure Development Plan – Cont’d • Nigeria’s Vision 20:2020 aims to promote sustained and inclusive economic growth, and elevate Nigeria’s economy to be among the top 20 economies in the world by the year 2020 • Inspired by Vision 20:2020 aspirations, the National Integrated Infrastructure Master Plan (NIIMP) was developed as an all inclusive approach to infrastructure delivery. • The NIIMP is a 30 year plan that covers “core” infrastructure – Transport, Energy, ICT and Water and others such as Agriculture, Mining, Housing and Social Infrastructure with priority projects outlined for the first 5 years of the plan
  • 5. Infrastructure Development Plan: Focus on Rail Vision 20:2020 - At least 40 million tons of freight by 2020. Action Plans RAIL • Rehabilitation of the existing narrow gauge rail (3500km network) • Completion of the Ajaokuta-Warri standard gauge line. • Rehabilitation of rail links within Nigeria’s main ports. • Construction of mass transit rail lines in Lagos and Abuja. • Construction of rail lines to link Inland Container Depots (ICDs) to sea ports • Concession of the rail lines from Lagos to Kano and from Port Harcourt to Maiduguri. • Expansion of the standard gauge network by 784km NIIMP Targets RAIL • To invest about USD75B over the next 30 years which will include construction of over 6,000 kilometres of new standard gauge lines • Link all major economic centres to the rail network • Provide adequate rail infrastructure for even economic development of the country. • Create an enabling environment for private sector participation in the provision of rail infrastructure.
  • 6. Railway Development Programme - Background The Nigeria Railway system is about 117years old. Between 1898 and 1964 Nigeria had built a network of narrow gauge rail lines totaling 3505km. In 1986, the Federal Government of Nigeria commenced the construction of 326 km standard gauge rail line phase 1 from Itakpe – Ajaokuta – Warri. However, for over two decades, the rail system became comatose up till 2009 when the government commenced implementation of a 25 year Strategic Vision to revive the sector adopting a systematic dual approach. This entails the rehabilitation of the entire existing narrow gauge lines simultaneously with the development of standard gauge lines. In February, 2011 the Federal Government of Nigeria commenced the construction of 187.5 km Abuja – Kaduna Standard gauge rail line.
  • 7. HISTORICAL DEVELOPMENT OF RAILWAYS IN NIGERIA GOMBE – MAIDUGURI 1963 – 1964(302km) BAUCHI – GOMBE 1961 – 1963(166km) KURU – BAUCHI 1958 – 1961(166km) KADUNA JUNCTION - KAFANCHAN 1922 – 1927(179km) ENUGU-MAKURDI 1916 – 1924(220km) PH - ENUGU 1914 – 1916(243km) KANO - BARO 1907 –1911(562km) JEBBA - MINNA 1909 -1915(225km) IBADAN - JEBBA 1901 –1909(295km) LAGOS - IBADAN 1898 –1901(193km) KAF – JOS OPENED 1927 (101km) PH – ONNE ON- GOING 19km AJAOKUTA – WARRI ONGOING (277km)
  • 8. Railway Development Programme – Track Rehabilitation  The rehabilitation of over 90% of the entire 3500km narrow gauge network throughout the country is near completion.  Rehabilitation of the Lagos to Kano, and Port Harcourt to Gombe lines is completed and passenger services and haulage of goods along the lines have since commenced.  Rehabilitation of sidings and loop lines along the Western line, including links to key industrial locations between Lagos and Kano and a spur line to the Kaduna Power Plant Complex is expected to be completed by end of 2015.
  • 9. Railway Development Programme – Update on Rehabilitation Projects Contract Distance Contractor Physical Progress Track & Signalling – Western Line (Lagos –Jebba) Lagos – Ibadan – Ilorin - Jebba 488km CCECC Nig. Ltd. 100% Track & Signalling – Western Line (Jebba – Kano) Jebba – Minna – Kaduna – Zaria - Kano 636km Costain (WA) Ltd 99.5% Signalling & Telecoms – Eastern and Western Lines Upgrading of Signalling Equipment 1,657km A3&O / Gear Group / Ansaldo 45% Track– Eastern Line (PH – Makurdi) PH – Umuahia – Enugu - Makurdi 463km Eser Contracting W. A 85% Track – Eastern Line (Makurdi – Kuru, Plus Spur Jos & Kafanchan) Makurdi – Lafia – Kuru – Spur to Jos – Kafachan and Kaduna 554m CGGC 85% Track – Eastern Line (Kuru – Maiduguri) Kuru – Bauchi – Gombe - Maiduguri 640km Lingo 47% Track – Zaria – Kaura Namoda Zaria – Funtua – Gusau – Kaura Namoda 221km Duluidas 90% Addendum to Lagos to Jebba Contract Rehabilitation of Sidings & LoopLines from Lagos – Kano and Lagos – Kano CCECC 65%
  • 10. Railway Development Programme – Track Rehabilitation Track Condition at Aba Before Rehabilitation Akerri Bridge Before Rehabilitation Akerri Bridge After Rehabilitation Track Condition at Aba After Rehabilitation
  • 11. Railway Development Programme - Construction of New Standard Gauge Lines  Construction of the Itakpe – Ajaokuta – Warri Standard Gauge line (277km) is in progress and expected to be completed by end of 2015.  Construction of Abuja(Idu) – Kaduna Standard gauge line (187km) is over 85% also expected to be delivered end of 2015.  Construction of Lagos – Ibadan Standard Gauge (double track) 2 x 180km has been awarded and will commence as soon as funding arrangement is concluded with the China Exim Bank by the Federal Ministry of Finance. Abuja - Kaduna Itakpe – Ajaokuta – Warri
  • 12. States Light Rail project Various State Governments are embarking on light rail projects to address the urban transportation challenges:  Lagos State rail mass transit Blue Line project is ongoing  River State Mono-rail project in Port Harcourt is about 95% completed  Ogun State has just award an inter/intra state rail construction project to the CCECC  Abuja Light Rail project is nearing completion Blue Line, Lagos
  • 13. Railway Development Programme - Locomotives and Rolling Stock FUNCTIONAL REPAIRABLE LOCOMOTIVES • Shunters • Mainline 29 55 WAGONS • Container • Oil Tank • Covered • Hopper • Wooden 250 550 COACHES • Standard • 1st Class • Sleepers • Canteen • Inspection • Baggage Vans 120 50  Refurbished 250 wagons  Refurbished 120coaches  Procured 25Nos. 2500HP GE Locomotives  Procured 4 Nos. 1800HP CNR Locomotives  Procured 40Nos. Oil Tank Wagons  Procured 2Nos. 100ton Telescopic Cranes  Procured 4Nos. 60ton Overhead Cranes  Procured 3 Nos. Inspection Vehicles  Procured 5Nos. Rail Road Recovery Vehicles  Procured 3 Nos. Wheel Lathe Machine, fully installed  Procured 2 Sets of Diesel Multiple Units (DMU)  Procured 11Nos. 68-Seater Air-conditioned Coaches  Procured 18Nos. 4-Seater Motorized Rail Trolley  Procured 2Nos. 16-Seater Rail Buses & 2Nos. Rail Cars  Ordered 2Nos. 1800HP CNR Locomotives and 2Nos. Power Cars to be delivered in 2015  Ordered for 2Nos. 3,500 HP Locomotives with in-built power car and 5Nos. Air Conditioned Coaches for Standard Gauge Line to be delivered in 2015
  • 14. Railway Development Programme – Modernisation of Locomotives & Rolling Stock  NRC is moving towards localization and skills transfer  Modernization of NRC’s existing, GE Transportation U-series and other EMD series locomotives  Modernisation of 60Nos. Flat Bed Wagons (Primarily used for movement of bonded containers from Ports)  Modernisation of 20Nos. Pan Xtra Goods (PXG) Covered Wagons (Primarily used for movement of bagged cement)  Modernisation of 40Nos. Covered Hopper Wagon (CHW) Primarily used for movement of Wheat  Modernisation of 6Nos. Power Cars (Housing generators that supply electricity for air-conditioning and lighting in passenger coaches)
  • 15. Railway Development Programme - Current Train Operations • Passengers Service Intra-city Mass Transit: Lagos Mass Transit Train: 18 Trips per day, Kaduna Intracity Mass : 10 Trips per day Intercity Passenger Service: Lagos – Kano –Lagos Train: twice per week, Lagos-Ilorin-Lagos Train: thrice per week, Offa – Kano - Offa Train: Once a week, Minna – Kaduna – Minna Train: thrice per week, Kano – Nguru Train: twice per week, Enugu – Port Harcourt – Enugu twice per week Port Harcourt – Kafanchan once a week Kaduna – Gombe – Kaduna once a week Excursion Trains: Highly patronized during festivities Coming Soon: New Mixed Trains from Kano – Port Harcourt , and Gombe to PH to commence in July, 2015 • Freight Service Flour Mills (Wheat) Traffic: Lagos to Kano, carrying about 3,000 tons per month Lafarge Cement Traffic, Lagos to Kano, carrying about 3,000 tons monthly Movement of containers for ICNL: Lagos to Kano about 2,000 tons monthly Track Materials for Eastern Line Contractors, about 9,000 tons monthly Movement of Petroleum Products for NRC and Connect rail: Lagos to Kano Coming Soon – Container Traffic for APM, Lagos to Kano
  • 16. 0 1 000 000 2 000 000 3 000 000 4 000 000 5 000 000 6 000 000 2009 2010 2011 2012 2013 2014 OPERATIONAL PERFORMANCE – PASSENGER SERVICES
  • 17. Opportunities for Private Sector Participation - Projection Of Train Services Over The Next 10 Years Route 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Narrow Gauge Eastern Line (PortHarcourt - Maiduguri) Western Line (Lagos - Kano) Standard Gauge Itakpe - Ajaokuta - Warri Abuja - Kaduna Lagos - Ibadan Zaria –Kaura Namoda- Birnin Konni Ajaokuta(Eganyi) - Obajana - Abuja Ajaokuta - Oturkpo - Onitsha Eganyi(Near Ajaokuta) - Lokoja - Abaji - Abuja Lagos - Abuja (High Speed)
  • 18. Opportunities for Private Sector Participation - Projected Rolling Stock Requirement For The Next 10 Years Rolling Stock 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 total Locomotives 20 25 20 25 230 37 42 44 42 50 535 Coaches 100 100 100 100 846 200 200 100 100 200 2,046 Wagons 350 250 250 200 3,100 1,250 200 200 200 200 9,300
  • 19. Opportunities for Private Sector Participation – PPP Initiatives  Finance, Supply, and jointly manage with NRC, utilization of wagons to enhance freight haulage capacity  Finance, Supply, and jointly manage with NRC, utilization of coaches to enhance passenger carriage capacity  Design, Build, Maintain, Operate, and Transfer (DBMOT) of Warehousing to provide suitable, safe and secure storage space for goods  Finance, Supply, and Operate modern facilities and provide services for loading and offloading of goods 1) Logistics Services Remodelling and Redevelopment of 9 Major Railway Stations to incorporate Commercial Outlet 2) Station Remodelling and Redevelopment  Development of 8Nos. Railway Landed Properties at Prime locations for Residential, Hotel and other Commercial purposes 3) Development of Railway Landed Properties Outline Business Cases (OBC) for the 3 PPP initiatives are being finalised by our Transaction Advisers following which Procurement Process for PPP Consortiums will commence
  • 20. S/N FEASIBILITY STUDIES COMPLETED 1 Lagos - Abuja (High Speed 550km) 2 Ajaokuta (Eganyi)-Obajana-Jakura-Baro-Abuja with additional line from Ajaokuta - Otukpo - to include the Anyigba - Ejule - Idah - Adoru - Nsukka - Adani - Omor - Anaku - Aguleri - Nsugbe - Onitsha Rail Line (821km) 3 Zaria-Kaura Namoda-Sokoto- Illela -Birnin Konni (Niger Republic - 520km) 4 Benin-Agbor-Onitsha-Nnewi-Owerri-Aba with additional line from Onitsha-Enugu-Abakaliki (500km) 5 Eganyi(Near Ajaokuta) - Lokoja - Abaji - Abuja (280km) FEASIBILITY STUDIES ON-GOING 6 Kano – Bichi - Katsina – Jibiya (354km) 7 Sokoto – Birnin Kebbi - Jega – Yauri - Makera with a branch line to Kontagora (408km) 8 Aba – Ikot Ekpene - Ibiono - Itu (Spur Uyo) Odukpani Calabar (340km) 9 Port Harcourt – Aba – Umuahia – Enugu – Makurdi – Lafia - Jos – Bauchi – Gombe- Biu - Maiduguri (1,552km) 10 Calabar -Ikom – Obudu – Ogoja – KatsinaAla – Wukari – Jalingo – Yola – Maiduguri (1,069km) 11 Kano – Nguru – Gashua – Damaturu – Maiduguri – Gamboru Ngala (707km) Opportunities for Private Sector Participation – Greenfield Projects 20
  • 21. Conclusion Nigeria is making appreciable efforts to address its infrastructure challenges The Federal Government has demonstrated great commitment towards Revitalization and Modernization of the rail system However, Government cannot fully address the Railway infrastructural challenges without significant involvement of the private sector The Government is making efforts to provide the enabling environment for effective Private sector participation in the country’s rail sector - The Nigerian Railway Corporation Act of 1955 is in the process of being repealed and re- enacted. The draft Bill has been forwarded to the National Assembly. Nigeria’s investment climate is currently very attractive hence the increase in the FDI inflow in recent times Now is the time to take advantage of the enormous opportunities in Nigeria Rail Sector.
  • 22. Thank you for Listening