PROJECT MANAGEMENT IN NOISY ENVIRONMENTS1
              ALEJANDRO DOMÍNGUEZ-TORRES, JADOMING@MAIL.UNITEC.MX, WWW.UNITEC.MX

Keywords: Bandwagon effect, Communication, Noise, Message, Project Manager, S-curve, Stakeholders.

                                                        ABSTRACT
A project always tends to breakdown an established set of rules of how work has been accomplished. Parties
involved directly or indirectly with a project may be against, be pessimistic about, be in favor of, or be optimistic
about its results. Among the several ways parties can express their feelings to others are through commentaries,
opinions, gossips, and rumors around project issues. These expressions produce interference in the transmission
and understanding of messages about how a project is managed. These are types of communication noise since
they compromise the original meaning of messages. Having as background a basic communication model, this
paper stipulates who produces noise and why it arises. It shows the effects of noise in project progress,
introduces a noise classification, and presents a set of actions to deal with noise in Project Management, as well
as project manager challenges and constraints.

BASIC COMMUNICATION MODEL IN PROJECT MANAGEMENT

As in a number of environments where human communication is present, in Project Management (PM) there is a
basic communication model (Figure 1) that is made up of senders, receivers, messages, decoders, encoders, noise
and a communication medium (PMI, p. 224). As PMBOK Guide quotes (PMI, p. 224): “the components in the
communication model need to be taken into account when discussing project communications”, a fact that
occurs in all of tasks performed during project progress.


                                                             Message
                               Encode                                                     Encode
                                                                             Noise
                               Sender                        Medium                      Receiver

                               Decode                                                     Decode
                                                       Feedback - Message
                                             Noise



                               Figure 1. Communication – Basic Model (PMI, p. 224).

In this model senders or sources of messages are primarily stakeholders (including the project manager) since
they are actively involved in the project and their interests may be positively or negatively affected by execution
or completion of it (PMI, p. 376). Thus, a stakeholder selects a message from a set of possible messages to be
transmitted to other stakeholders (the receivers).

Since a project is an endeavor undertaken to create a unique product, service, or result (PMI, p. 368), it may
generate several reactions among stakeholders and third parties depending on if they are either against or in favor
of project, or if they are either optimistic or pessimistic about project results.

In general a project tends to breakdown an established set of rules of how work has been executed in past. For
example, if parties involved directly or indirectly with a project (stakeholders or third parties; e.g., advisors,
users, work unions, etc.) are against project or are pessimistic about its results, they may feel uncertainty, show
resistance to change, and incite internal confront. In a similar way, if parties are in favor of project or are
optimistic about its results, they may incite others give support to that project. In both cases, the ways of parties


1
  This paper was presented at 17th Annual Conference of the Production and Operations Management Society "Operations Management in
the      New       World        Uncertainties"    Boston,       Massachusetts,      April    28      -      May       1,    2006.
http://www.poms.org/2006/04/poms_2006_conference_om_in_the.html#more




                                                                                                                           1 of 9
express their feelings to others parties are through of a set of commentaries, opinions, and rumors around project
issues. These expressions produce interference in the transmission and understanding of messages of how project
is managed. Such expressions are considered as noise in the sense stated by the PMBOK Guide since they
compromise the original meaning of messages. (PMI, p. 224).

There is another way in which noise is produced, this is when certain parties (stakeholders or third parties) do
not receive the corresponding project messages they expect from other parties or messages received do not
correspond to project facts. In the first case, noise is produced by a reduction of the medium of propagation
while in the second one it is due to a wrong perception of project progress.

In general, it can be said that people with vested interests on project outcomes starts noise, and that persistence
of noise is the result of sharing its anxiety, lack of information, and lack of trust (PD Webpage).

However, some care must be taken since not every message distortion is due to noise. In fact, another common
way of message distortion appears when the communication medium capacity is overloaded or exceeded; i.e.,
when the number of messages produced in a certain period exceeds the capacity to transmit them. On the other
way, message distortion also appears when it is exceeded the capacity of stakeholders to decode messages.

NOISE EFFECTS

The first reaction to noise may be often defensiveness, anger, or even counterattack. Most of these responses
differ from the best project practices. In order to be more constructive, it is necessary to understand noise
dynamics.

Since noise interferes with transmission and understanding of project messages, it may produce some changes on
decisions to be taken over project tasks. That is, at the end noise may produce changes on project development.
These changes depend on noise intensity. Thus, if noise is not comparable to project message level, its effect on
project development vanishes. On the other hand, if noise is comparable to message level and if it is not reduced
or mitigated, at certain time (threshold) there may appear one of the following effects on the project progress
trend, which is graphically represented by a typical s-curve:

        Temporary disruption or displacement in the trend (Figure 2a). This is when noise causes a time delay
         in project progress.
        Change of the rate or direction of the trend (Figure 2b). Noise causes project progress to behave in a
         slower or faster way than before.
        Displacement of the trend (Figure 2c). This is a less common (not impossible) project progress behavior
         since it implies to increase it almost instantly or in relatively short period or time.
        Trend disruption (Figure 2d). It means a non-project continuation.




                                                                                                             2 of 9
Project    (a) Temporary disruption          Project    (b) Change of rate or direction
                       progress                                     progress




                                          threshold             Time                    threshold            Time




                                  (c) Displacement                               (d) Disruption
                        Project                                      Project
                       progress                                     progress




                                          threshold             Time                    threshold            Time



                                  Figure 2. Effects of noise in project progress trend.

In order to understand when noise may change project development, consider a rumor produced around a project
(here a rumor is understood as a piece of purportedly true information that circulates without substantiating
evidence). As it is known (see www.answers.com/rumor), the information content/payload of this rumor can
range from simple gossip to advanced propaganda techniques.

Simple gossip does not have any effect on project progress since it can be mitigated by either simple
communication techniques or waiting until it vanishes. However, if rumor is propagated using propaganda
techniques, then it can influence stakeholders' opinions actively, rather than to merely communicate the facts
about project. In this last case, a “bandwagon effect” may be produced among stakeholders and third parties; that
is, parties start to behave in a certain way the others mimic them and then project progress overshoots its normal
course of events (positively or negatively) often rapidly. At this time (threshold) is when project manager has to
take actions of corrections and return to the appropriate rate to sustain growth (Figure 3).

                                    Project
                                   progress

                                                                               planned trend




                                                                                overshoots



                                                       noise




                                                              threshold                             Time



                                    Figure 3. Bandwagon effect produced by noise.

Bandwagon effect does not represent the way parties behave individually. In general, at threshold, the behavior
of a particular person is random in the sense that it does not show a specific pattern and it does not seem to have
any purpose and objective. This randomness also occurs in time since in most cases the occurrence of noise
cannot be accurately predicted with any precision. Thus, noise may be considered as a random and persistent
disturbance that obscures or reduces the clarity of the message.

Therefore, it may be concluded at least that (Brenner 2002):




                                                                                                                    3 of 9
    Noise may become more damaging with time.
        Noise may be credible.
        Packaged noise may spread more rapidly.

CATEGORIZING NOISE

When a project is in progress and noise exists, project manager may consider four options: address it, do not
detect it, neglect it, or have an inaccurate perception of it. The last one is perhaps the most dangerous option to
project management.

In order to help solve the problem of noise inaccurate perception, theory of knowledge is invoked: the best way
of knowing something is trying to categorize it. Two types of categorization there exist for human
communication in literature. The first one is according to noise sources in the area of general communication
(Yang), while the second one is according to rumor intentions taking place on public diplomacy (PD Webpage).

Both categorizations can be easily extrapolated to noise occurring on project management communications.
Thus, following Yang, it can be said there exists:

        Environmental noise: Outside interference that prevents project manager from gaining project
         messages;
        Physiological-impairment noise: Interference caused by parties‟ physical problems that can block
         his/her effective sending or receiving of project messages;
        Syntactical noise: Interference caused by parties‟ incorrect use of communication language rules (e.g.,
         grammar);
        Psychological noise: Interference produced by parties‟ stress, frustration, irritation, etc.,
        Intellectual noise: Interference caused by parties‟ great amount of opinions and points of view about
         project messages;
        Cultural noise (influence): Interference produced by parties‟ preconceived, unyielding attitudes due to
         cultural group belonging. Being “closed-minded”;
        Organizational noise (confusion): Interference caused by the way messages arranged in order;
        Semantic noise: Interference caused by words meaning, such as project management or project
         technical jargon, dialect, etc.

Having in mind this categorization, a good exercise could be to relate each project process to certain types of
noise. The result of this exercise can be used as a guideline to project manager to know what kind of noise is
expected when a particular project process is being executed.

On the other hand, extrapolating ideas stated on PD Webpage, noise could take one of the following forms:

        Intentional noise. It is generated to achieve a purpose; e.g., „you might follow PMBOK Guide if you
         want to be successful in managing projects‟.
        Premature noise. It is an early version of what will eventually become the truth; e.g., an in-house noise
         about pending personnel, procedural, and infrastructural changes.
        Malicious noise. It is generated to damage project manager, some stakeholders, or to tend relations
         among them.
        Outrageous noise. It is composed of stories so unbelievable that most parties think they cannot have
         been made up.
        Nearly true noise. It is built around a kernel of truth.
        „Birthday‟ noise. It comes around as regularly as birthdays; e.g., legends around projects developed in
         the past.

Malicious noise is perhaps the most dangerous type of noise in this categorization. If this is the case, project
manager should understand and accept what (s)he can and cannot change about the situation. In fact, project
manager has some control over his/her reputation and his/her relationship with stakeholders and he has little if
any control over what other people choose to say about him/her.




                                                                                                             4 of 9
As in signal processing theory, some terminology may be given. Based on a specific categorization, each one of
the aforementioned noise types could be called “colored noise”, where one type of noise defines one and only
one color. Similarly, noise is called “white noise” if it is made up of all of colored noise types. However, because
of parties‟ bandwagon effect around noise, most of the times it is not easy to determine if a specific colored noise
or even if white noise is occurring.

Noise may occur at any moment during project life cycle phases, however since stakeholders or other third
parties have a high influence at the start of project and this influence gets progressively lower as the project
continues (PMI, p.21), the attention of project manager to predict noise must behave similarly as parties‟
influence, as it is shown in Figure 4.

                                         Project manager
                                        attention to noise
                                 High




                                  Low
                                                   Project time


                            Figure 4. Project manager attention to noise over time.

DEALING WITH NOISE

Noise is always present in any project and cannot be avoided, cannot be eliminated, or even cannot be wished
away; it can only be controlled. Thus noise cannot be mitigated at all. In fact, its elimination requires an endless
effort by the project manager and to use countless resources. However, noise may be considered as project gifts
since it can open lines of communications among stakeholders and third parties, can be viewed as symptoms of
larger project environment problems, and can let the project manager address issues before they become
problems.

Extrapolating the ideas stated on PD Webpage, sometimes it is easier to discourage noise than it is to stop it. The
way to discourage noise is to engage in open and honest communication with important stakeholder and party
groups, and to respond to stakeholder concerns before they become a source of anxiety and speculation.

PD Webpage states some additional ideas, such that in some particular cases where noise is composed of jokes
the best response is to do nothing. Responding to noise can backfire by giving it more credibility than it had to
begin with. The key to judging when, and how forcefully, to respond to noise lies in understanding how
concerned stakeholders are by the claims. When noise starts to threaten project management relationship with a
stakeholder, it is time to the project management speaks up.

A strategy to control noise consists of defining and applying a set of preventive and corrective actions. In
literature, it has been reported the successful application of preventive and corrective actions to manage and
control rumors in environments different to project management (Brenner 2003, Brenner 2004, Burgess and
Maiese, Daniel, DiFonzo and Bordia). Some of these actions has been extrapolated and successfully applied by
the author to noisy project management environments. Of course, the responsibility of implementing these
actions entirely belongs to the project manager; so action effectiveness depends on the value given to it.

PREVENTIVE ACTIONS

Preventive actions are based on the fact that credibility is the most powerful tool the project manager possesses.
In fact, credibility can suppress noise and even limit their formation. Thus, the project manager must be clear, be
early, and be right in applying the following preventive actions.

        Preventive action 1: Anticipate noise. This action must be the standard in any project. Prevention and
         not correction must be the rule adopted by any project manager.




                                                                                                              5 of 9
    Preventive action 2: Strive to increase and maintain trust and credibility. The project manager must
         reliably pair your words with matching activities. When information is provided, the project manager
         must always tell the truth and do not exaggerate or lie for short-term benefit; e.g., (s)he does not talk
         falsely, this is another way that noise starts in the first place.
        Preventive action 3: Keep stakeholders informed. The project manager must periodically inform
         stakeholders about project progress and related events.
        Preventive action 4. Tailor each communication. Information given to stakeholders must satisfy
         particular information needs. Newsletters, memos and briefings are excellent methods to provide
         information. They can become the “official” words on the project and prevent noise from starting.
        Preventive action 5: Set up a “hotline” communication channel. This is to be in permanent
         communication firstly with stakeholders and then with other parties if possible. This action helps
         provide factual responses when needed and at any time. Internet instant messengers can help achieve
         this action.
        Preventive action 6. Be judicious about communication openness. Many people believe that
         implementing a broadband communication channel with parties prevents noise. This is not certain at all;
         in fact, while secrecy does stimulate noise, openness limits it only if it reduces anxiety. In other words,
         openness can even make things worse, if it adds to anxiety.
        Preventive action 7. Anticipate parties‟ anxiety. If it is known of a probable source of anxiety or
         worry, get out in front of it. Do not wait for noise to form. Take corrective actions early, and make
         those actions known (see corrective actions below).
        Preventive action 8. Fill voids by complementing and repeating information given. When parties
         worry, they make up what they do not know. When it is said nothing about a topic, parties are worrying
         about, then it is leaved a void to be filled by noise. Before occurrence of this, it is better that project
         manager fills voids by complementing and repeating information given.
        Preventive action 9. Monitor possible effects of noise with respect external events, stakeholder
         attitudes, and parties´ behavior. This is in order to interventions can be enacted early in the life of noise.

CORRECTIVE ACTIONS

Corrective actions must be considered as the last ones to be taken by the project manager since they are based on
repairing project manager credibility when it gets tattered. If this occurs and before the project manager responds
to noise, (s)he must address the following questions (PD Webpage):

        What type of noise is this?
        Is this any truth to it? Does it point to a problem I need to fix?
        Is the issue important to stakeholders? Which ones? Why?
        Are stakeholders paying attention to noise? If so, what is their response to it? Do they want to hear
         something from me about it?
        Can I provide information that might dispel noise? Do I need to be more open with information in
         general?
        What is the underlying concern or anxiety expressed by noise? Can I do anything constructive to
         address it?
        What is the state of my relationship with parties influenced by noise? Could or should I do anything to
         improve the quality of that relationship?
        Are there credible third parties who might help dispel noise?

Answering these questions is not an easy task. In fact, repairing credibility indicates that something has been
wrong in managing project. In order to help give answers, it is recommended the project manager implement the
following actions.

        Corrective action 1. Avoid a “no comment” response. Do not be a project manager advocating a “no
         comment” posture in response to noise. In any event, explain why it is given.
        Corrective action 2: Determine what colored noise is actually circulating. It requires the support of
         some “noise reporters” (some of them could be stakeholders or third parties) who are in a position to
         hear circulating noise. In general, these reporters should be very active in the environment and be
         interested in being beneficed from project product. It is also important that these individuals to be
         widely trusted by stakeholders.




                                                                                                                6 of 9
    Corrective action 3: Determine which part of noise content is due to either true or false information.
         There are at least two ways of implementing this action,

        o    A naïve way is that once noise begins to cause problems in project progress, it is helpful talk to
             some stakeholders and to ask the source of the problem according to them and their knowledge of
             the situation. This will diminish stakeholders‟ fears and uncertainties.
        o    A more sophisticated way again requires the support of “noise investigators” (who may be the same
             people as the "noise reporters" or others). These reporters can help determine, from their
             perspective, the accuracy of information pertaining to their group that produces noise. While there
             will certainly be cases were the practices of secrecy and deception make reliable information
             checking impossible, there will also be many cases in which some noise can be partially reduced.
             This noise investigation action may be structured at least in two ways, as long as it provides
             information that is widely regarded as trustworthy and reliable:

             -   The first way is that “noise reporters” might be organized into a committee made up of people
                 from both or all sides that meet periodically to exchange information about current noise and
                 then organize efforts to determine noise‟s source accuracy. These committees should also
                 involve people with access to the information needed to conduct effective investigations.
             -   The second way involves widely trusted neutral intermediaries who systematically contact key
                 parties involved in a conflict to identify and investigate the latest noise. When these
                 intermediaries hear a story that they think is likely to be untrue, they initiate an investigation to
                 try to determine whether or not the story is accurate. Also needed is a plan for handling
                 inconclusive investigations. This means that the investigators have to clearly acknowledge
                 cases in which they are unable to determine the reliability of noise‟s source.

        Corrective action 4: Determine mechanisms for diminishing noise contents and replacing it with
         reliable information. In order to be successful in implementing these mechanisms, project manager must
         take into account that:

        o    “Noise investigators” need some reliable procedure for promptly reporting their findings to project
             managers and stakeholders (again, e-mail and instant messengers could help). In cases were there is
             no agreement on what has happened, they should report what is known, what is not known, and
             what is still being investigated. They should also report differing interpretations of available facts.
        o    There must be a plan for reducing noise. Since noise becomes stronger and more difficult to stop
             over time (bandwagon effect), it is very important to act quickly before the false information is
             repeated so many times that it becomes accepted as truth. In this case, project manager must
             consider in his/her plan the following points:

             -   Refute noise via an appropriate level source. For example, instrument refutation via a
                 stakeholder leader or a sponsor.
             -   Refute noise via a trusted outside source. For example, consult and disseminate the opinion of
                 experts in the corresponding topic.
             -   Refute noise with a clear, strong, concise, and memorable message based on results obtained so
                 far and on previous experience.
             -   Refute noise based upon the truth.
             -   Refute noise with consistent messages. Do not provide contradictory information and always
                 complete facts without repeating the false information itself.

If after applying these corrective actions noise persists and has developed in such a way it is comparable to
project messages, then the project manager must change the rules for managing the project  for example,
publicly delegate responsibility to a new high-visibility stakeholder. Care must be taken since all of the project
processes are interdependent; change of rules implies a change in the whole rules used to manage the project.
Thus, uncertainty and ambiguity will apply since stakeholders will be unsure how to proceed.

Under extreme conditions, the project manager must not try to apply the old rules of project management faster
or better. Rather, project manager must start challenging assumptions in order to drive strategic process change.
In these circumstances, the project manager will succeed if he can read the way of managing the project, and
master its rules, quickly and successfully.



                                                                                                               7 of 9
Project management mismatches occur when the project manager retain the old rules to manage the project after
appearing of noise comparable to messages. Frequently project management mismatches can lead to complete
project breakdown. Moreover, failure to capture the potential of using new project management rules stifles the
process of project management innovation.

The project manager must remember that stakeholders are like chorus: each one has a different accent, tone, and
voice. Thus, (s)he must try to harmonize and synchronize stakeholders‟ work styles.

CHALLENGES AND CONSTRAINTS

Managing projects in noise environments is not an easy task. The project manager must be aware of noise and its
effects on stakeholders, parties, and project management and results. In fact, project manager should challenge
the following situations (Clements and Drake, DiFonzo and Bordia):

            Expect to encounter harmful noise during all of the project management phases.
            Take into account that noise often starts from the very first conception of project.
            Be alert to the possible negative effects of noise within three main domains: consequences to
             project and project management, stakeholder attitudes, and third party behaviors.
            Formulate a pro-active plan to prevent and correct noise.
            Inhibit noise activity and its associated effects by reducing and/or placing bounds upon uncertainty
             and by reducing belief in noise through effective formal communications.

These challenges are more difficult in implementation than they appear. In fact, project manager actions may be
limited to the following constraints (Clements and Drake, DiFonzo and Bordia):

            Resources for rapid response to noise are rarely budgeted; this is certain if project is managed with
             limit resources.
            Stakeholders and sponsors pay insufficient attention to communication versus attention to
             “technical priorities”.
            Rapid respond to noise is not always possible if project is decentralized.

REFERENCES

Brenner, R (2002). Responding to Rumors. www.chacocanyon.com/pointlookout/020424.shtml. Visited
November 2005.

Brenner, R (2003). There is no Rumor Mill. http://www.chacocanyon.com/pointlookout/030326.shtml. Visited
November 2005.

Burgess, H. and M. Maiese. Rumor Control. www.beyondintractability.org/m/rumor_control.jsp. Visited
November 2005.

Clements, J. and C. Drake. Dealing with Rumors. www.comminit.com/strategicthinking/stepicom/sld-1681.html.
Visited November 2005.

Daniel, M. Rumor Management Strategy.
http://faculty.kfupm.edu.sa/mgm/danielm/Rumor%20Management%20Strategy.htm. Visited November 2005

DiFonzo, N. and P. Bordia. How Top PR Professionals Handle Hot Air: Types of Corporate Rumors, Their
Effects, and Strategies to Manage Them: A study to the Institute for Public Relations.
www.instituteforpr.com/pdf/1999_rumor-study.pdf. Visited November 2005.

PD Webapge. Rumors/Urban Legends. http://home.att.net/~eccentricstar/cs_rumors.html. Visited November
2005.




                                                                                                            8 of 9
PMI. A Guide to the Project Management Body of Knowledge: PMBOK Guide. Third Edition. Project
Management Institute. 2004

Yang, S. The Human Communication Process. www.wam.umd.edu/~suyang/Ch%201_Spring05.ppt. Visited
July 2005.




                                                                                         9 of 9

Contenu connexe

Similaire à Managing Projects in Noisy Environments

Generalized Analysis Value Behavior
Generalized Analysis Value BehaviorGeneralized Analysis Value Behavior
Generalized Analysis Value BehaviorBob Prieto
 
Program tetrahedron further development
Program tetrahedron further developmentProgram tetrahedron further development
Program tetrahedron further developmentBob Prieto
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultantsbfitzsimons1974
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
[Report] Who's protecting your blindside? Construction Management: Protectin...
[Report] Who's protecting your blindside?  Construction Management: Protectin...[Report] Who's protecting your blindside?  Construction Management: Protectin...
[Report] Who's protecting your blindside? Construction Management: Protectin...JLL
 
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docxRunning head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docxcowinhelen
 
Assignment 1. Project Success And How It Is Defined
Assignment 1. Project Success And How It Is DefinedAssignment 1. Project Success And How It Is Defined
Assignment 1. Project Success And How It Is DefinedJeff Brooks
 
1 This document was originally created on 26th May 2009 .docx
1 This document was originally created on 26th May 2009 .docx1 This document was originally created on 26th May 2009 .docx
1 This document was originally created on 26th May 2009 .docxkarisariddell
 
Project PlanProject ManagementSher.docx
Project PlanProject ManagementSher.docxProject PlanProject ManagementSher.docx
Project PlanProject ManagementSher.docxLynellBull52
 
03.stakeholders and communication PMI-RMP Risk Management Professional
03.stakeholders and communication  PMI-RMP Risk Management Professional03.stakeholders and communication  PMI-RMP Risk Management Professional
03.stakeholders and communication PMI-RMP Risk Management Professionalnanacyrah
 
Projects in Contemporary Organizations The past several decades ha.docx
Projects in Contemporary Organizations The past several decades ha.docxProjects in Contemporary Organizations The past several decades ha.docx
Projects in Contemporary Organizations The past several decades ha.docxbriancrawford30935
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road ConstructionHeidi Owens
 
Not all projects are the same: One size does not fit all for managing projects
Not all projects are the same: One size does not fit all for managing projectsNot all projects are the same: One size does not fit all for managing projects
Not all projects are the same: One size does not fit all for managing projectsImprovement Skills Consulting Ltd.
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...Harish Rajmane
 
Research Paper On Primavera
Research Paper On PrimaveraResearch Paper On Primavera
Research Paper On PrimaveraGina Buck
 
2 project management 3
2 project management 32 project management 3
2 project management 3Narayan Mane
 

Similaire à Managing Projects in Noisy Environments (20)

Pm in noisy environments
Pm in noisy environmentsPm in noisy environments
Pm in noisy environments
 
Pm in noisy envronments
Pm in noisy envronmentsPm in noisy envronments
Pm in noisy envronments
 
Generalized Analysis Value Behavior
Generalized Analysis Value BehaviorGeneralized Analysis Value Behavior
Generalized Analysis Value Behavior
 
Program tetrahedron further development
Program tetrahedron further developmentProgram tetrahedron further development
Program tetrahedron further development
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultants
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
Project Management
Project ManagementProject Management
Project Management
 
[Report] Who's protecting your blindside? Construction Management: Protectin...
[Report] Who's protecting your blindside?  Construction Management: Protectin...[Report] Who's protecting your blindside?  Construction Management: Protectin...
[Report] Who's protecting your blindside? Construction Management: Protectin...
 
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docxRunning head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
Running head IMPLEMENTATION STRATEGIESIMPLEMENTATION STRATEGIES.docx
 
Finance 1.pdf
Finance 1.pdfFinance 1.pdf
Finance 1.pdf
 
Assignment 1. Project Success And How It Is Defined
Assignment 1. Project Success And How It Is DefinedAssignment 1. Project Success And How It Is Defined
Assignment 1. Project Success And How It Is Defined
 
1 This document was originally created on 26th May 2009 .docx
1 This document was originally created on 26th May 2009 .docx1 This document was originally created on 26th May 2009 .docx
1 This document was originally created on 26th May 2009 .docx
 
Project PlanProject ManagementSher.docx
Project PlanProject ManagementSher.docxProject PlanProject ManagementSher.docx
Project PlanProject ManagementSher.docx
 
03.stakeholders and communication PMI-RMP Risk Management Professional
03.stakeholders and communication  PMI-RMP Risk Management Professional03.stakeholders and communication  PMI-RMP Risk Management Professional
03.stakeholders and communication PMI-RMP Risk Management Professional
 
Projects in Contemporary Organizations The past several decades ha.docx
Projects in Contemporary Organizations The past several decades ha.docxProjects in Contemporary Organizations The past several decades ha.docx
Projects in Contemporary Organizations The past several decades ha.docx
 
M6 Toll Road Construction
M6 Toll Road ConstructionM6 Toll Road Construction
M6 Toll Road Construction
 
Not all projects are the same: One size does not fit all for managing projects
Not all projects are the same: One size does not fit all for managing projectsNot all projects are the same: One size does not fit all for managing projects
Not all projects are the same: One size does not fit all for managing projects
 
To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
Research Paper On Primavera
Research Paper On PrimaveraResearch Paper On Primavera
Research Paper On Primavera
 
2 project management 3
2 project management 32 project management 3
2 project management 3
 

Plus de Universidad Tecnológica de México - UNITEC

Plus de Universidad Tecnológica de México - UNITEC (20)

5 cosas que no sabías acerca de la cofia de una enfermera
5 cosas que no sabías acerca de la cofia de una enfermera5 cosas que no sabías acerca de la cofia de una enfermera
5 cosas que no sabías acerca de la cofia de una enfermera
 
Ventajas de titularte por maestria
Ventajas de titularte por maestriaVentajas de titularte por maestria
Ventajas de titularte por maestria
 
Infografía: Oportunidades en el Turismo de Reuniones UNITEC
Infografía: Oportunidades en el Turismo de Reuniones UNITECInfografía: Oportunidades en el Turismo de Reuniones UNITEC
Infografía: Oportunidades en el Turismo de Reuniones UNITEC
 
Gastronomía UNITEC: El chef bajo la lupa
Gastronomía UNITEC: El chef bajo la lupaGastronomía UNITEC: El chef bajo la lupa
Gastronomía UNITEC: El chef bajo la lupa
 
Actitud, la clave para el éxito laboral (webinar)
Actitud, la clave para el éxito laboral (webinar)Actitud, la clave para el éxito laboral (webinar)
Actitud, la clave para el éxito laboral (webinar)
 
Claves del Nuevo Sistema Penal
Claves del Nuevo Sistema PenalClaves del Nuevo Sistema Penal
Claves del Nuevo Sistema Penal
 
UNITEC en un 2X3 Los pasos para tu inscripción (webinar)
UNITEC en un 2X3 Los pasos para tu inscripción (webinar)UNITEC en un 2X3 Los pasos para tu inscripción (webinar)
UNITEC en un 2X3 Los pasos para tu inscripción (webinar)
 
Conoce el mundo de la Educación en Línea
Conoce el mundo de la Educación en LíneaConoce el mundo de la Educación en Línea
Conoce el mundo de la Educación en Línea
 
Creando Multimedia
Creando MultimediaCreando Multimedia
Creando Multimedia
 
Con vocación de Ingeniero (webinar)
Con vocación de Ingeniero (webinar)Con vocación de Ingeniero (webinar)
Con vocación de Ingeniero (webinar)
 
Mi empleo, mi desarrollo (webinar)
Mi empleo, mi desarrollo (webinar)Mi empleo, mi desarrollo (webinar)
Mi empleo, mi desarrollo (webinar)
 
Estudia con Financiamientos
Estudia con FinanciamientosEstudia con Financiamientos
Estudia con Financiamientos
 
Cuidando la salud de los mexicanos
Cuidando la salud de los mexicanosCuidando la salud de los mexicanos
Cuidando la salud de los mexicanos
 
Trade Marketing y Administración de Ventas (webinar)
Trade Marketing y Administración de Ventas (webinar)Trade Marketing y Administración de Ventas (webinar)
Trade Marketing y Administración de Ventas (webinar)
 
Tus estudios cuentan
Tus estudios cuentanTus estudios cuentan
Tus estudios cuentan
 
La Realidad Virtual en Cine y Video
La Realidad Virtual en Cine y VideoLa Realidad Virtual en Cine y Video
La Realidad Virtual en Cine y Video
 
Aduanas las puertas del comercio exterior
Aduanas las puertas del comercio exteriorAduanas las puertas del comercio exterior
Aduanas las puertas del comercio exterior
 
Talentos que buscan las organizaciones en las personas (webinar)
Talentos que buscan las organizaciones en las personas (webinar)Talentos que buscan las organizaciones en las personas (webinar)
Talentos que buscan las organizaciones en las personas (webinar)
 
Importancia del turismo de reuniones (webinar)
Importancia del turismo de reuniones (webinar)Importancia del turismo de reuniones (webinar)
Importancia del turismo de reuniones (webinar)
 
Sigue tu camino con más posibilidades
Sigue tu camino con más posibilidadesSigue tu camino con más posibilidades
Sigue tu camino con más posibilidades
 

Managing Projects in Noisy Environments

  • 1. PROJECT MANAGEMENT IN NOISY ENVIRONMENTS1 ALEJANDRO DOMÍNGUEZ-TORRES, JADOMING@MAIL.UNITEC.MX, WWW.UNITEC.MX Keywords: Bandwagon effect, Communication, Noise, Message, Project Manager, S-curve, Stakeholders. ABSTRACT A project always tends to breakdown an established set of rules of how work has been accomplished. Parties involved directly or indirectly with a project may be against, be pessimistic about, be in favor of, or be optimistic about its results. Among the several ways parties can express their feelings to others are through commentaries, opinions, gossips, and rumors around project issues. These expressions produce interference in the transmission and understanding of messages about how a project is managed. These are types of communication noise since they compromise the original meaning of messages. Having as background a basic communication model, this paper stipulates who produces noise and why it arises. It shows the effects of noise in project progress, introduces a noise classification, and presents a set of actions to deal with noise in Project Management, as well as project manager challenges and constraints. BASIC COMMUNICATION MODEL IN PROJECT MANAGEMENT As in a number of environments where human communication is present, in Project Management (PM) there is a basic communication model (Figure 1) that is made up of senders, receivers, messages, decoders, encoders, noise and a communication medium (PMI, p. 224). As PMBOK Guide quotes (PMI, p. 224): “the components in the communication model need to be taken into account when discussing project communications”, a fact that occurs in all of tasks performed during project progress. Message Encode Encode Noise Sender Medium Receiver Decode Decode Feedback - Message Noise Figure 1. Communication – Basic Model (PMI, p. 224). In this model senders or sources of messages are primarily stakeholders (including the project manager) since they are actively involved in the project and their interests may be positively or negatively affected by execution or completion of it (PMI, p. 376). Thus, a stakeholder selects a message from a set of possible messages to be transmitted to other stakeholders (the receivers). Since a project is an endeavor undertaken to create a unique product, service, or result (PMI, p. 368), it may generate several reactions among stakeholders and third parties depending on if they are either against or in favor of project, or if they are either optimistic or pessimistic about project results. In general a project tends to breakdown an established set of rules of how work has been executed in past. For example, if parties involved directly or indirectly with a project (stakeholders or third parties; e.g., advisors, users, work unions, etc.) are against project or are pessimistic about its results, they may feel uncertainty, show resistance to change, and incite internal confront. In a similar way, if parties are in favor of project or are optimistic about its results, they may incite others give support to that project. In both cases, the ways of parties 1 This paper was presented at 17th Annual Conference of the Production and Operations Management Society "Operations Management in the New World Uncertainties" Boston, Massachusetts, April 28 - May 1, 2006. http://www.poms.org/2006/04/poms_2006_conference_om_in_the.html#more 1 of 9
  • 2. express their feelings to others parties are through of a set of commentaries, opinions, and rumors around project issues. These expressions produce interference in the transmission and understanding of messages of how project is managed. Such expressions are considered as noise in the sense stated by the PMBOK Guide since they compromise the original meaning of messages. (PMI, p. 224). There is another way in which noise is produced, this is when certain parties (stakeholders or third parties) do not receive the corresponding project messages they expect from other parties or messages received do not correspond to project facts. In the first case, noise is produced by a reduction of the medium of propagation while in the second one it is due to a wrong perception of project progress. In general, it can be said that people with vested interests on project outcomes starts noise, and that persistence of noise is the result of sharing its anxiety, lack of information, and lack of trust (PD Webpage). However, some care must be taken since not every message distortion is due to noise. In fact, another common way of message distortion appears when the communication medium capacity is overloaded or exceeded; i.e., when the number of messages produced in a certain period exceeds the capacity to transmit them. On the other way, message distortion also appears when it is exceeded the capacity of stakeholders to decode messages. NOISE EFFECTS The first reaction to noise may be often defensiveness, anger, or even counterattack. Most of these responses differ from the best project practices. In order to be more constructive, it is necessary to understand noise dynamics. Since noise interferes with transmission and understanding of project messages, it may produce some changes on decisions to be taken over project tasks. That is, at the end noise may produce changes on project development. These changes depend on noise intensity. Thus, if noise is not comparable to project message level, its effect on project development vanishes. On the other hand, if noise is comparable to message level and if it is not reduced or mitigated, at certain time (threshold) there may appear one of the following effects on the project progress trend, which is graphically represented by a typical s-curve:  Temporary disruption or displacement in the trend (Figure 2a). This is when noise causes a time delay in project progress.  Change of the rate or direction of the trend (Figure 2b). Noise causes project progress to behave in a slower or faster way than before.  Displacement of the trend (Figure 2c). This is a less common (not impossible) project progress behavior since it implies to increase it almost instantly or in relatively short period or time.  Trend disruption (Figure 2d). It means a non-project continuation. 2 of 9
  • 3. Project (a) Temporary disruption Project (b) Change of rate or direction progress progress threshold Time threshold Time (c) Displacement (d) Disruption Project Project progress progress threshold Time threshold Time Figure 2. Effects of noise in project progress trend. In order to understand when noise may change project development, consider a rumor produced around a project (here a rumor is understood as a piece of purportedly true information that circulates without substantiating evidence). As it is known (see www.answers.com/rumor), the information content/payload of this rumor can range from simple gossip to advanced propaganda techniques. Simple gossip does not have any effect on project progress since it can be mitigated by either simple communication techniques or waiting until it vanishes. However, if rumor is propagated using propaganda techniques, then it can influence stakeholders' opinions actively, rather than to merely communicate the facts about project. In this last case, a “bandwagon effect” may be produced among stakeholders and third parties; that is, parties start to behave in a certain way the others mimic them and then project progress overshoots its normal course of events (positively or negatively) often rapidly. At this time (threshold) is when project manager has to take actions of corrections and return to the appropriate rate to sustain growth (Figure 3). Project progress planned trend overshoots noise threshold Time Figure 3. Bandwagon effect produced by noise. Bandwagon effect does not represent the way parties behave individually. In general, at threshold, the behavior of a particular person is random in the sense that it does not show a specific pattern and it does not seem to have any purpose and objective. This randomness also occurs in time since in most cases the occurrence of noise cannot be accurately predicted with any precision. Thus, noise may be considered as a random and persistent disturbance that obscures or reduces the clarity of the message. Therefore, it may be concluded at least that (Brenner 2002): 3 of 9
  • 4. Noise may become more damaging with time.  Noise may be credible.  Packaged noise may spread more rapidly. CATEGORIZING NOISE When a project is in progress and noise exists, project manager may consider four options: address it, do not detect it, neglect it, or have an inaccurate perception of it. The last one is perhaps the most dangerous option to project management. In order to help solve the problem of noise inaccurate perception, theory of knowledge is invoked: the best way of knowing something is trying to categorize it. Two types of categorization there exist for human communication in literature. The first one is according to noise sources in the area of general communication (Yang), while the second one is according to rumor intentions taking place on public diplomacy (PD Webpage). Both categorizations can be easily extrapolated to noise occurring on project management communications. Thus, following Yang, it can be said there exists:  Environmental noise: Outside interference that prevents project manager from gaining project messages;  Physiological-impairment noise: Interference caused by parties‟ physical problems that can block his/her effective sending or receiving of project messages;  Syntactical noise: Interference caused by parties‟ incorrect use of communication language rules (e.g., grammar);  Psychological noise: Interference produced by parties‟ stress, frustration, irritation, etc.,  Intellectual noise: Interference caused by parties‟ great amount of opinions and points of view about project messages;  Cultural noise (influence): Interference produced by parties‟ preconceived, unyielding attitudes due to cultural group belonging. Being “closed-minded”;  Organizational noise (confusion): Interference caused by the way messages arranged in order;  Semantic noise: Interference caused by words meaning, such as project management or project technical jargon, dialect, etc. Having in mind this categorization, a good exercise could be to relate each project process to certain types of noise. The result of this exercise can be used as a guideline to project manager to know what kind of noise is expected when a particular project process is being executed. On the other hand, extrapolating ideas stated on PD Webpage, noise could take one of the following forms:  Intentional noise. It is generated to achieve a purpose; e.g., „you might follow PMBOK Guide if you want to be successful in managing projects‟.  Premature noise. It is an early version of what will eventually become the truth; e.g., an in-house noise about pending personnel, procedural, and infrastructural changes.  Malicious noise. It is generated to damage project manager, some stakeholders, or to tend relations among them.  Outrageous noise. It is composed of stories so unbelievable that most parties think they cannot have been made up.  Nearly true noise. It is built around a kernel of truth.  „Birthday‟ noise. It comes around as regularly as birthdays; e.g., legends around projects developed in the past. Malicious noise is perhaps the most dangerous type of noise in this categorization. If this is the case, project manager should understand and accept what (s)he can and cannot change about the situation. In fact, project manager has some control over his/her reputation and his/her relationship with stakeholders and he has little if any control over what other people choose to say about him/her. 4 of 9
  • 5. As in signal processing theory, some terminology may be given. Based on a specific categorization, each one of the aforementioned noise types could be called “colored noise”, where one type of noise defines one and only one color. Similarly, noise is called “white noise” if it is made up of all of colored noise types. However, because of parties‟ bandwagon effect around noise, most of the times it is not easy to determine if a specific colored noise or even if white noise is occurring. Noise may occur at any moment during project life cycle phases, however since stakeholders or other third parties have a high influence at the start of project and this influence gets progressively lower as the project continues (PMI, p.21), the attention of project manager to predict noise must behave similarly as parties‟ influence, as it is shown in Figure 4. Project manager attention to noise High Low Project time Figure 4. Project manager attention to noise over time. DEALING WITH NOISE Noise is always present in any project and cannot be avoided, cannot be eliminated, or even cannot be wished away; it can only be controlled. Thus noise cannot be mitigated at all. In fact, its elimination requires an endless effort by the project manager and to use countless resources. However, noise may be considered as project gifts since it can open lines of communications among stakeholders and third parties, can be viewed as symptoms of larger project environment problems, and can let the project manager address issues before they become problems. Extrapolating the ideas stated on PD Webpage, sometimes it is easier to discourage noise than it is to stop it. The way to discourage noise is to engage in open and honest communication with important stakeholder and party groups, and to respond to stakeholder concerns before they become a source of anxiety and speculation. PD Webpage states some additional ideas, such that in some particular cases where noise is composed of jokes the best response is to do nothing. Responding to noise can backfire by giving it more credibility than it had to begin with. The key to judging when, and how forcefully, to respond to noise lies in understanding how concerned stakeholders are by the claims. When noise starts to threaten project management relationship with a stakeholder, it is time to the project management speaks up. A strategy to control noise consists of defining and applying a set of preventive and corrective actions. In literature, it has been reported the successful application of preventive and corrective actions to manage and control rumors in environments different to project management (Brenner 2003, Brenner 2004, Burgess and Maiese, Daniel, DiFonzo and Bordia). Some of these actions has been extrapolated and successfully applied by the author to noisy project management environments. Of course, the responsibility of implementing these actions entirely belongs to the project manager; so action effectiveness depends on the value given to it. PREVENTIVE ACTIONS Preventive actions are based on the fact that credibility is the most powerful tool the project manager possesses. In fact, credibility can suppress noise and even limit their formation. Thus, the project manager must be clear, be early, and be right in applying the following preventive actions.  Preventive action 1: Anticipate noise. This action must be the standard in any project. Prevention and not correction must be the rule adopted by any project manager. 5 of 9
  • 6. Preventive action 2: Strive to increase and maintain trust and credibility. The project manager must reliably pair your words with matching activities. When information is provided, the project manager must always tell the truth and do not exaggerate or lie for short-term benefit; e.g., (s)he does not talk falsely, this is another way that noise starts in the first place.  Preventive action 3: Keep stakeholders informed. The project manager must periodically inform stakeholders about project progress and related events.  Preventive action 4. Tailor each communication. Information given to stakeholders must satisfy particular information needs. Newsletters, memos and briefings are excellent methods to provide information. They can become the “official” words on the project and prevent noise from starting.  Preventive action 5: Set up a “hotline” communication channel. This is to be in permanent communication firstly with stakeholders and then with other parties if possible. This action helps provide factual responses when needed and at any time. Internet instant messengers can help achieve this action.  Preventive action 6. Be judicious about communication openness. Many people believe that implementing a broadband communication channel with parties prevents noise. This is not certain at all; in fact, while secrecy does stimulate noise, openness limits it only if it reduces anxiety. In other words, openness can even make things worse, if it adds to anxiety.  Preventive action 7. Anticipate parties‟ anxiety. If it is known of a probable source of anxiety or worry, get out in front of it. Do not wait for noise to form. Take corrective actions early, and make those actions known (see corrective actions below).  Preventive action 8. Fill voids by complementing and repeating information given. When parties worry, they make up what they do not know. When it is said nothing about a topic, parties are worrying about, then it is leaved a void to be filled by noise. Before occurrence of this, it is better that project manager fills voids by complementing and repeating information given.  Preventive action 9. Monitor possible effects of noise with respect external events, stakeholder attitudes, and parties´ behavior. This is in order to interventions can be enacted early in the life of noise. CORRECTIVE ACTIONS Corrective actions must be considered as the last ones to be taken by the project manager since they are based on repairing project manager credibility when it gets tattered. If this occurs and before the project manager responds to noise, (s)he must address the following questions (PD Webpage):  What type of noise is this?  Is this any truth to it? Does it point to a problem I need to fix?  Is the issue important to stakeholders? Which ones? Why?  Are stakeholders paying attention to noise? If so, what is their response to it? Do they want to hear something from me about it?  Can I provide information that might dispel noise? Do I need to be more open with information in general?  What is the underlying concern or anxiety expressed by noise? Can I do anything constructive to address it?  What is the state of my relationship with parties influenced by noise? Could or should I do anything to improve the quality of that relationship?  Are there credible third parties who might help dispel noise? Answering these questions is not an easy task. In fact, repairing credibility indicates that something has been wrong in managing project. In order to help give answers, it is recommended the project manager implement the following actions.  Corrective action 1. Avoid a “no comment” response. Do not be a project manager advocating a “no comment” posture in response to noise. In any event, explain why it is given.  Corrective action 2: Determine what colored noise is actually circulating. It requires the support of some “noise reporters” (some of them could be stakeholders or third parties) who are in a position to hear circulating noise. In general, these reporters should be very active in the environment and be interested in being beneficed from project product. It is also important that these individuals to be widely trusted by stakeholders. 6 of 9
  • 7. Corrective action 3: Determine which part of noise content is due to either true or false information. There are at least two ways of implementing this action, o A naïve way is that once noise begins to cause problems in project progress, it is helpful talk to some stakeholders and to ask the source of the problem according to them and their knowledge of the situation. This will diminish stakeholders‟ fears and uncertainties. o A more sophisticated way again requires the support of “noise investigators” (who may be the same people as the "noise reporters" or others). These reporters can help determine, from their perspective, the accuracy of information pertaining to their group that produces noise. While there will certainly be cases were the practices of secrecy and deception make reliable information checking impossible, there will also be many cases in which some noise can be partially reduced. This noise investigation action may be structured at least in two ways, as long as it provides information that is widely regarded as trustworthy and reliable: - The first way is that “noise reporters” might be organized into a committee made up of people from both or all sides that meet periodically to exchange information about current noise and then organize efforts to determine noise‟s source accuracy. These committees should also involve people with access to the information needed to conduct effective investigations. - The second way involves widely trusted neutral intermediaries who systematically contact key parties involved in a conflict to identify and investigate the latest noise. When these intermediaries hear a story that they think is likely to be untrue, they initiate an investigation to try to determine whether or not the story is accurate. Also needed is a plan for handling inconclusive investigations. This means that the investigators have to clearly acknowledge cases in which they are unable to determine the reliability of noise‟s source.  Corrective action 4: Determine mechanisms for diminishing noise contents and replacing it with reliable information. In order to be successful in implementing these mechanisms, project manager must take into account that: o “Noise investigators” need some reliable procedure for promptly reporting their findings to project managers and stakeholders (again, e-mail and instant messengers could help). In cases were there is no agreement on what has happened, they should report what is known, what is not known, and what is still being investigated. They should also report differing interpretations of available facts. o There must be a plan for reducing noise. Since noise becomes stronger and more difficult to stop over time (bandwagon effect), it is very important to act quickly before the false information is repeated so many times that it becomes accepted as truth. In this case, project manager must consider in his/her plan the following points: - Refute noise via an appropriate level source. For example, instrument refutation via a stakeholder leader or a sponsor. - Refute noise via a trusted outside source. For example, consult and disseminate the opinion of experts in the corresponding topic. - Refute noise with a clear, strong, concise, and memorable message based on results obtained so far and on previous experience. - Refute noise based upon the truth. - Refute noise with consistent messages. Do not provide contradictory information and always complete facts without repeating the false information itself. If after applying these corrective actions noise persists and has developed in such a way it is comparable to project messages, then the project manager must change the rules for managing the project  for example, publicly delegate responsibility to a new high-visibility stakeholder. Care must be taken since all of the project processes are interdependent; change of rules implies a change in the whole rules used to manage the project. Thus, uncertainty and ambiguity will apply since stakeholders will be unsure how to proceed. Under extreme conditions, the project manager must not try to apply the old rules of project management faster or better. Rather, project manager must start challenging assumptions in order to drive strategic process change. In these circumstances, the project manager will succeed if he can read the way of managing the project, and master its rules, quickly and successfully. 7 of 9
  • 8. Project management mismatches occur when the project manager retain the old rules to manage the project after appearing of noise comparable to messages. Frequently project management mismatches can lead to complete project breakdown. Moreover, failure to capture the potential of using new project management rules stifles the process of project management innovation. The project manager must remember that stakeholders are like chorus: each one has a different accent, tone, and voice. Thus, (s)he must try to harmonize and synchronize stakeholders‟ work styles. CHALLENGES AND CONSTRAINTS Managing projects in noise environments is not an easy task. The project manager must be aware of noise and its effects on stakeholders, parties, and project management and results. In fact, project manager should challenge the following situations (Clements and Drake, DiFonzo and Bordia):  Expect to encounter harmful noise during all of the project management phases.  Take into account that noise often starts from the very first conception of project.  Be alert to the possible negative effects of noise within three main domains: consequences to project and project management, stakeholder attitudes, and third party behaviors.  Formulate a pro-active plan to prevent and correct noise.  Inhibit noise activity and its associated effects by reducing and/or placing bounds upon uncertainty and by reducing belief in noise through effective formal communications. These challenges are more difficult in implementation than they appear. In fact, project manager actions may be limited to the following constraints (Clements and Drake, DiFonzo and Bordia):  Resources for rapid response to noise are rarely budgeted; this is certain if project is managed with limit resources.  Stakeholders and sponsors pay insufficient attention to communication versus attention to “technical priorities”.  Rapid respond to noise is not always possible if project is decentralized. REFERENCES Brenner, R (2002). Responding to Rumors. www.chacocanyon.com/pointlookout/020424.shtml. Visited November 2005. Brenner, R (2003). There is no Rumor Mill. http://www.chacocanyon.com/pointlookout/030326.shtml. Visited November 2005. Burgess, H. and M. Maiese. Rumor Control. www.beyondintractability.org/m/rumor_control.jsp. Visited November 2005. Clements, J. and C. Drake. Dealing with Rumors. www.comminit.com/strategicthinking/stepicom/sld-1681.html. Visited November 2005. Daniel, M. Rumor Management Strategy. http://faculty.kfupm.edu.sa/mgm/danielm/Rumor%20Management%20Strategy.htm. Visited November 2005 DiFonzo, N. and P. Bordia. How Top PR Professionals Handle Hot Air: Types of Corporate Rumors, Their Effects, and Strategies to Manage Them: A study to the Institute for Public Relations. www.instituteforpr.com/pdf/1999_rumor-study.pdf. Visited November 2005. PD Webapge. Rumors/Urban Legends. http://home.att.net/~eccentricstar/cs_rumors.html. Visited November 2005. 8 of 9
  • 9. PMI. A Guide to the Project Management Body of Knowledge: PMBOK Guide. Third Edition. Project Management Institute. 2004 Yang, S. The Human Communication Process. www.wam.umd.edu/~suyang/Ch%201_Spring05.ppt. Visited July 2005. 9 of 9