SlideShare une entreprise Scribd logo
1  sur  17
Télécharger pour lire hors ligne
 
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
* *
U – CAD College
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
SRI LANKA
236, AL MUNAWWARA ROAD* *
AKKARAIPATTU-04
 
 
 
Training Program for
Quantity Surveying
  Practice for Quantity Surveyors (Based on SMM 7, CESMM 3, POMI & FIDIC)
 
 
M.A. Unais
B.Sc. in Architecture Engineer, Dip. in Quantity Surveyor
Contents
Practice for Quantity Surveyors (Based on SMM7, CESMM3, POMI & FIDIC)
 
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
*
1.0) The Quantity surveyor’s role 
• Post‐contract duties 
 
• Pre‐contract duties 
 
*
2.0) Contract Payments  
2‐a)  Measurements  
SMM 7   (Standard method of mea ent  uildin  works) surem of b g
(Civil En  Stand et  Measurement)
I    (Princip for  of
ent Certifica
nds 
Preparatio
Checking o
 Paper 
ent Sheet 
mary / Payment Certificate 
 Time 
a Works 
du
 
CESMM 3   gineering ard M hod of  
 
POM les of Measurement   Works  Construction) 
 
2‐b)  Interim Bill 
 
2‐c)  Paym te 
 
2‐d)  Some Important Term (Related to bill of Quantities and Payment) 
 
2‐e)  Bo
 
2‐f)  Final Bill 
 
2‐g)  n of Bill 
 
2‐h)  f Bill 
 
2‐i)  Specimen Grand Summary / Payment Certificate 
 
3.0) Annexes 
• Dimension
 
• Measurem
 
• Grand sum
 
• Extension of
 
• Schedule for Extr
 
• Schedule for SSR 
 
• Schedule for In‐Lieu Sche le 
 
• Application from for Variation Order 
4.0) Contract Document 
4‐a)  Condition of Contract (FIDIC) 
 
4‐b)  Specifications 
 
4‐c)  Drawings 
4‐d)  BOQ  
 
4‐e)  Tender with Appendix 
 
4‐f)  Letter of acceptance 
 
4‐g)  Contract agreement 
 
5.0)  Unit Pricing (Resource Cost) 
• Labour 
• Material 
• Plant 
 
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu
U
EG
E
L
LOC
D
C-S
R
A N
K
A
I
L
A
* *
 
 
1.0) The Quantity surveyor’s role 
1‐a)  Pre – Contract (QS)
Preparation of Bill of Quantity 
Quantity taker‐off 
Preparation of preliminary estimate and introduction to cost plant 
Estimating for tendering purposes 
Introduction to tender procedure and contractual arrangements  
Preparation of Tender documents for Sub Contractor and Supplier. 
Preparing comparison sheets and analyzing. 
 
1‐b)  Post‐Contract (QS)
Preparation of interim and final application for payment 
Preparing of valuations for interim and final certificate  
Variation orders, preparation of variation accounts and valuation  
Preparation, valuation, negotiation and reporting on claims. 
Preparing Sub contractors and supplier’s payment certificate and certifying. 
 
2.0) Measurements  
The term “measurement” covers two types of measurements encountered in construction work namely 
Taking off dimension by reading or scaling drawing and indicating on “Dimension Paper”  
 
This type of measurement is required either in case of proposed work or to check whether the completed 
work is in accordance with the proposed work.  
And 
The actual measurement of completed work at site and recording on “Measurement Sheets” 
 
Main classification of works related to field of civil engineering with respect to measurements. 
• Building works 
• Civil Engineering Works 
 
2‐a)  Dimension Paper 
 
1. Timesing column (Number) 
2. Dimension column 
3. Squaring column (Qty.) 
4. Description  
 
 
 
 
Form of Dimension (Units) 
 
Before going any further it is necessary to understand the asset down by the taker‐off. All dimensions are in of 
five forms 
Cubic measurements  ‐  m3
Square measurements   ‐  m2
Linear measurements  ‐  Lm / m 
Numbers    ‐  Nr / No 
Items       ‐  item 
 
 
 
 
  
  
  
  
  
  
  
  
  
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu
 
 
 
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu, Sri Lanka
2‐a.3.1)  Building Works 
• All types of building such as, 
• House or Dwelling Units 
• Flats 
• Shops 
• Hotels 
• Hospital 
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
*
• Theatres 
• Gymnasiums 
• Office 
*
• Ware house 
 
2‐a.3.2)  Civil Engineering Works 
• Water supply schemes 
chemes 
hemes 
 
 methods
dard met
thod of measurement of building works (SMM of Building Works) 
ing Standard Method of Measurement (CESMM) 
ard method of measurement of building works (SMM of Building Works) 
 been prepared by the royal Institute of Chartered surveyors (RICS) and the National 
ration of Building Trades Employers (NFBTE), UK 
a  m  
 t of ci engineers and th
 w f consu
• Surface drainage s
• Irrigation Sc
• Highway 
• Railways 
• Culverts & Bridges 
• Mass excavation filling and embankments (mass earth works) 
• Dredging
• Retaining walls 
 
2‐a.4)  Standard  of measurements 
For the purpose of providing a uniform basis for measurements, two types of “stan hod of 
measurement” have been established namely 
 
• Standard me
• Civil Engineer
 
2‐a.4.1)   Stand
This has
Fede
 
2‐a.4.2)   Civil engineering st ndard ethod of Measurement (CESMM)
This has been prepared by he institution  vil  e federation of civil engineering 
contractor, in associations ith the Association o lting Engineers, UK 
 
2‐a.4.3)  Comparison of Standard method of measurements of building works and civil 
engineering works  
• General  
Though there are two separate and distinct practices of measurements established for building and civil 
engineering works, there are common features too in between them such as  
o General approach 
o Units of measurement 
o Certain items of work which can be measured by any of the two methods  
 
• Building works 
At the time of preparing BOQ, the details available are usually in a for more precise stage, therefore items 
description can be made precisely and quantities can ascertained accurately for many items 
 
• More trades or work section are available, resulting much more detailed measurements for which rates 
have been quoted by the tenders some of them may be quite small 
 
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu, Sri Lanka
• Civil engineering works 
o In BOQ detailed description are not available therefore in pricing the BOQ and in constructing the 
work the specification drawing and other related documents are to be closely studied constantly  
o Generally temporary work and incidental labors are not measured separately therefore cost of 
which have been incorporated in related BOQ item 
o There is a great risk in pricing  
 
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
*
2‐a.4.4)  Advantage of the use of standard methods of measurement  
The following are some advantages that can be gained by studying and referring to standard 
methods of measurements and incorporating same in contract documents 
*
o Avoidance of disputes in measurements between parties 
o Gaining familiarity in the standard method  para n of bills of quantities  of pre tio
 standard of pre d
ent reque c nce
n specim
rtant ter
ization Advance 
yment made beforehand to the contractor by the employer / client before the 
ncement of the contactor work as an assistance to mobilize or get ready to start 
ctor work 
t term  an
 mad for the work
ified
o Gaining familiarity in the  method  senting item  escription in bills of quantities  
 
2‐b)  Interim bill 
Interim bill are the paym st submitted by the contractor in ac orda  with the terms & 
condition of the contract during the course of the contract 
 
2‐c)  Payment certificate 
This is the document which certificate payment the reader is referred to item 9.00 o en grand 
summary certificate 
 
2‐d)  Some impo ms related to bill of quantities and payment 
2‐d.1)    Advance payment 
These are payment made beforehand to the contractor by the employer / client either before the 
commencement of the contractor work or before the bills resubmitted are checked and certified.  
 
2‐d.1.1)  Mobil
The pa
comme
contra
 
The paymen s d the recovery of the mobilization advance will depend on the terms and 
conditions of the contract applicable to the project 
 
2‐d.1.2)  On account payment / part payment 
This can be defined as an advance payment e   already performed and effected 
before bills submitted are checked and cert . 
 
This type of payment is not incorporated in the contract but made only on mutual understanding 
and special agreement with relevant approval 
 
In this type of payment only a percentage is certified therefore they are called part payments 
 
2‐d.2)  Retention 
The amount of money to be retained from the bill payments due to the contractor is known as retention  
This is to cover any possible shortcoming of the contractor 
Release of retention is mead in accordance with the Terms and Condition of the Contract. 
 
2‐d.3)  Recoveries 
The amount of money to be recovered from the contractor are called recoveries 
Some of the recoveries to be made from the bill payments to the contractor are as follows 
o Mobilization Advance 
o Liquidated Damages 
o Material used or services offered to the contractor by the Employer / Client. 
o Cost of any losses  
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu, Sri Lanka
 
2‐d.4)  Extension of Time 
If the contract cannot be completed within the original agreed contract period due to some reason or 
reasons the contractor must request for the extension of the contract period which is termed Extension 
of time 
 
Such extension are granted if the delay is due to reasons beyond the control of the contractor otherwise 
the contractor is charged with Liquidated Damages 
  U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
*
In granting extension of time it is to be clearly stated whether the Contractor is entitlement what type of 
payment are entitled for. 
 
*
2‐d.5)  Liquidated Damages 
These are charges imposed on the contractor on the s spe ied in the contract when the extension 
of time is not granted 
 term cif
 defined a ign
e kind
cation 
nce with acts of parliament, regulation or by laws... 
 variation and valuation of variation 
es of variation recognized and practiced  
cre or  due to erro
  
 
2‐d.6)  Variations  
A variation on the work is s any alteration or modification of the des  material workmanship 
quality or quantity of the work 
 
This include any additional omission or substitution of the work or alteration of th  or standard of 
any material  
 
A variation is caused to the following reasons too 
 
o A discrepancy or divergence between the bills of quantities drawing and specifi
 
o Error or omission in the bill of quantity drawing and specification 
 
o Complia
 
2‐d.6.1)  Type of
The typ
 
o Extra works 
The variations occurred due to in ase  decrease of BOQ quantities either  r in BOQ or addition 
or omission which affects quantities in BOQ items is called extra works
 
These are valued at relevant prevailing BOQ rates 
 
The schedule to be prepared with respect to extra work is given in Annex V 
 
o SSR (Special schedule of Rates) 
The variation occurred due to addition of new items of works which is not available in the BOQ are called 
special schedule of rates 
 
These are to be valued by one of the following methods in the sequence mentioned 
o Rates of similar BOQ items executed under similar conditions 
o Rates based on similar BOQ items executed under similar conditions 
o Rates build up on day works applicable to the contract 
o Applicable rates 
o Rates build up on day works rates indicated in relevant rate book 
o Rates build up on prevailing market prices and labor rates and accepted labor and plant output 
and material requirements A specimen from for SSR is indicated in Annex VI 
 
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu, Sri Lanka
o In lieu schedule  
In lieu schedule is issued when a substitution is made for a BOQ item 
 
Eg. Fixing rubber water bars in place of PVC water bars. 
 
Annex Vll is referred for specimen from of in‐lieu schedule 
 
2‐d.7)  Provisional quantities 
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
Assumed quantities are entered against some items in BOQ of which the actual quantities cannot be 
calculated at the time of preparing BOQ since the extent of work is not known these are termed 
provisional quantities this will be apparent only once the job is done 
 
* *
This will become a variation in the contract once the variation is approved the provisional quantities are 
replaced with actual quantities and paid as per quo ates ted r
cture of a
g 
d in BOQ to d generate
asing sani ontracto
‐conditioni
tractor 
ums 
ded against some BOQ items, without quantities as “items of which either the full extent 
ctual cost involved are not known at the time of preparing BOQ 
 become variations 
 La
 t t contractor th
rial specified in
Eg:     
o item of work in sub‐stru  building 
o Excavation for pipe layin
 
2‐d.8)  Prime Cost Sums 
These are include  cover work which require, special selection an s the appointment 
of nominated sub‐contractor or nominated suppliers 
Eg:     
o Purch tary appliances from the nominated suppliers by the main c r and 
installed by the main contractor. 
o Air ng or supplying and installation of pumping equipment by nominated sub‐
con
 
Since these prime cost sums are not the actual sums these will become variation and to be dealt with 
accordingly 
 
2‐d.9)  Provisional S
These are inclu
character or a
 
These will also
Eg:   Excavation for Pipe ying on roads. 
 
2‐d.10) Escalation  
If the escalation clause is applicable o the pertinen e contractor is entitled for the 
additional payment at the rates for labor and mate  the contract 
 
2‐d.11) Day works 
There are certain items of work which cannot be measured and the cost determined beforehand until the 
work is attended to. 
 
For such items there are rate for labor materials and plant either incorporated in the contract or agreed 
in advance between the parties which are called day works labor rates day works material rates and day 
works plant rates 
 
When the said items of work are executed records are kept on the labor hour’s material used and plant 
hours involved and the valuation of the work is done applying the day work rates  
 
The items of work described above are termed day works 
Eg:    
Attending to pipe leak 
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu, Sri Lanka
2‐e)  Bonds  
In case of contracts the bonds are legal documents which bind a person for a legally accepted action 
under the terms and conditions specified 
 
In case of building and civil engineering contracts the surety undertakes to be liable for the contractor’s 
default 
 
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
*
2‐e.1)  Types of bonds 
Three types of bonds generally used in building and civil engineering contracts are as follows: 
 
*
2‐e.1.1) Bid bond or tender guarantee  
o Tender submitted should remain open for accept  for th period indicated in the Appendix to the 
form of tender. No tender is e  withdraw el or voke his tender during the staid period 
ance e 
ntitled to  canc  re
itions imp follo
nd validity orm of ten
 with th
iven to 
tender w
 of the successful tender shall be returned after he furnishes the performance bond 
 the successful tender fail to sign the contract and to submit the performance bond as 
 bid bond will be forfeited. 
on advance payment 
nt of  ob
um  the way
 by  co
ct ag
 
o According to the cond osed Bond can be furnished in one of the  wing alternative forms: 
o Cash Deposit 
o An acceptable Bank Guarantee 
o A certified cheque issued by a recognized bank 
 
o The value a  of the bond should be as indicated in the Appendix to the f der 
o This Bond should accompany the tender any tender not accompanied by bid bond e required 
value validity and terms will be disqualified and no further consideration will be g such tender 
 
o After the award has been finalized the Bid Bond will be returned to the respective  ith the 
exception of that of the successful tender 
 
o The bid bond
 
o In the event
specified the
 
2‐e.1.2) Mobilizati
Before the payme m ilization advance on the request of the contractor a bond as per the specimen 
form provided and the other doc ents specified in the contract for eg:  of expending the 
advance is to be provided  the ntractor 
 
2‐e.1.3) Performance bond  
Within the specified period on signing the contra reement the contractor should present 
performance bond for due and proper performance of the contract 
 
2‐e.2) Encashment of bonds 
In case of default of the contractor the bonds are lodged with the surety claimed encashment as per the 
terms and conditions specified 
 
2‐e.3) Points to be checked in a bond 
The points to be checked in a bond are as follows 
o The accuracy of the  
o Surety 
o Parties involved in the contract 
o Title of the contract 
o Contract price 
o Period of validity of the bond 
o Terms and conditions 
o Clause on payment on demand 
o Wording 
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying 
U – CAD College, Akkaraipattu, Sri Lanka
o Signatory 
o Signature  and 
o Official Stamp 
 
2‐f)  Final Bill 
This is the last bill submitted by the contractor with respect to the contract entered into. 
 
2‐g)  Preparation of bills 
U
EG
E
L
LOC
D
C-S
R
I
L A N
K
A
A
*
The standard practice is to prepare the bills in cumulative basis in which the total value of work done up 
to the date of measurement from the commencement of work including those already paid are 
ascertained and the balance due to the contractor is determined by subtracting the amounts already paid 
from the said total value 
*
 
Each and every time of bill preparation the join surement are done staring from the beginning 
automatically correcting an ade at pr s measurements. 
t mea
y errors m eviou
e followin f th  is 
k done on    the
bills 
Contract 
r’s signature 
ck whether the signature is available and its correctness 
s 
 of the  
escription 
em number 
ld 
ly ity b he rate 
 
Bill preparation is to be don g the same order o e BOQ and it a good practice to indicate the 
BOQ items and wor Variation Orders granted separately with  ir total values independently 
 
2‐h)  Checking of 
The points to be noted in checking of bills are as follows: 
 
2‐h.1)  Contract particulars  
• Name of the contractor 
• title 
• Contract number 
• Date of measurement 
 
2‐h.2)  Contracto
Should che
 
2‐h.3)  BOQ item
The correctness
• Item d
• BOQ it
• Quantity (this shou not exceed the BOQ quantity) 
• Unit 
• Rate 
• Amount obtained by multip ing the quant y t
• Total 
 
2‐h.4)  Items of work done on variation orders 
Only the items of work already approved are to be certified for payment the copies of approved orders 
should be available in the finance branch 
 
It is a good practice to group and total the extra works schedule of rates and in lieu schedule separately in 
the order of BOQ sections 
 
The following are the points to be noted 
• Variation order number 
• Item description  
• Quantity 
• Unit 
• Rate 
• Amount 
• Total 
U – CAD College, Akkaraipattu, Sri Lanka
DATE:___________________
PROJECT: PAGE:___________________
Time/
NO.
DIM.
SQU /
QTY.
DESCRIPTION
Time/
NO.
DIM.
SQU /
QTY.
DESCRIPTION
QUANTITY TAKE-OFF SHEET
(BS 3327-statinery for Quantity Surveyours)
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying
U – CAD College, Akkaraipattu, Sri LankaContrector Name : …… Project :- ………….
Contrect No : …… Date :- …………….
Description
BOQ
Item No.
No. Length Breadth Depth Quantity Total
Measurement Sheet
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying
U – CAD College, Akkaraipattu, Sri Lanka
U – CAD College, Akkaraipattu, Sri Lanka
TITLE OF CONTRACT : …………………………..
CONTRACT NO. : …………………………..
CONTRACTOR : …………………………..
CONTRACT VALUE : …………………………..
BILL NO : …………………………..
1.00 Value of work executed (Excluding Variations) 5,461,190.00
2.00 Value of work executed on Variation Orders 1,177,493.40
Sub Total - A 6,638,683.40
3.00 80% of Valvue of Matrial on site 1,071,600.00
Sub Total - B 7,710,283.40
4.00 Add Advance Payment 5,875,513.18
Sub Total - C 13,585,796.58
Less
5.00 Retention (10 % of B) (771,028.34)
6.00 Recovery of Mobilization Advance (20% of B) (1,542,056.68)
7.00 Other Recoveries
7.10 Water provided by
the board (15,907.50)
7.20 Power provided by
the board (2,328.00)
7.30 Non provision of services as per
contract (23,453.75)
7.40 For utilization of Board Building (4,500.00)
7.50 Recovery of preliminaries due to use of
pre mixed concrete (45,426.00)
7.60 Item not recovered from (3,010.00)
(2,407,710.27)
Less Previous payments 11,178,086.31
Certificate No. 1 (Mob. Advance) (5,875,513.18)
Certificate No. 2 (Bill No.-2) (1,914,225.24)
Certificate No. 3 (Bill No.-3) (453,008.67)
Certificate No. 4 (Bill No.-4) (394,065.26) (8,636,812.35)
Balance due to the Contractor 2,541,273.96
Project Manager ……………………….
Date ……………………….
we recommend the payment of Rs. Two Million, Five Hunderd Forty One Thousand, Two Hundred and
Seventy Three and Cents Ninety Six
GRAND SUMMARY / CERTIFICATE NO
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying
U – CAD College, Akkaraipattu, Sri Lanka
U – CAD College, Akkaraipattu, Sri LankaScheme ……………………….
Project : ……………………….
Contractor Name : ……………………….
Contract No : ………………………. Date :- ……………
Variation Order No. ………………………. Page :- ……………
Serial
No.
BOQ
Item No.
Item Description Unit
Actual
Qty.
BOQ
Qty
Excess
Qty
Rate Amount
Remarks /
Reasons
Schedule for extra works
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying
U – CAD College, Akkaraipattu, Sri Lanka
U – CAD College, Akkaraipattu, Sri Lanka
Scheme ……………………….
Project : ……………………….
Contractor Name : ……………………….
Contract No : ………………………. Date :- ……………
Variation Order No. ………………………. Page :- ……………
Serial
No.
Unit Qty. Rate Amount
Reasons
for
Variation
Justification
for Rate
Special Schdule of Rates
Item Description
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying
U – CAD College, Akkaraipattu, Sri Lanka
U – CAD College, Akkaraipattu, Sri Lanka
Scheme ……………………….
Project : ……………………….
Contractor Name : ……………………….
Contract No : ………………………. Date :- ……………
Variation Order No. ………………………. Page :- ……………
Unit Qty. Rate Amount Description Unit Qty. Rate AmountItem Description
Serial
No.
BOQ Item In Lieu Item
Saving Excess
Reasons for
Variation
In Lieu Schdule
Variation Order No
M.A. UNAIS
B.Sc. in Architecture Engineering, Dip in Quantity Surveying
U – CAD College, Akkaraipattu, Sri Lanka

Contenu connexe

Tendances

MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDFIDHAMUKI
 
Principles Of Measurement International
Principles Of Measurement International Principles Of Measurement International
Principles Of Measurement International Sorab Mishra
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qumes manandhar
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 
An introduction to taking off building quantities
An introduction to taking off building quantities An introduction to taking off building quantities
An introduction to taking off building quantities Arshad Mohanut
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2ArunRavi43
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Introduction to civil engineering
Introduction to  civil engineeringIntroduction to  civil engineering
Introduction to civil engineeringSavitha Pradeep
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line methodmalang1214
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of RatesRaj Shah
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 

Tendances (20)

MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
 
Principles Of Measurement International
Principles Of Measurement International Principles Of Measurement International
Principles Of Measurement International
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
An introduction to taking off building quantities
An introduction to taking off building quantities An introduction to taking off building quantities
An introduction to taking off building quantities
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Introduction to civil engineering
Introduction to  civil engineeringIntroduction to  civil engineering
Introduction to civil engineering
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 

En vedette

Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of QuantitiesNatalie Reid
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantityhlksd
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
ITD Presentation Slides
ITD Presentation SlidesITD Presentation Slides
ITD Presentation SlidesHappy Phiphi
 
M3 EG BQ for timber panel door
M3 EG BQ for timber panel doorM3 EG BQ for timber panel door
M3 EG BQ for timber panel doorEst
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Charity drive report 2
Charity drive report 2Charity drive report 2
Charity drive report 2Lin Hui
 
Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bmLin Hui
 
Measurement4
Measurement4Measurement4
Measurement4kohwenqi
 
Measurement Assignment 2
Measurement Assignment 2 Measurement Assignment 2
Measurement Assignment 2 Wan Nee
 
M3 EG BQ timber windows
M3 EG BQ timber windowsM3 EG BQ timber windows
M3 EG BQ timber windowsEst
 
M3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answerM3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answerEst
 
M3 Lecture 7 notes aluminium door
M3 Lecture 7 notes aluminium doorM3 Lecture 7 notes aluminium door
M3 Lecture 7 notes aluminium doorEst
 
Design project one full
Design project one full   Design project one full
Design project one full Lin Hui
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof coveringEst
 
Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster Lin Hui
 
Integrated project report
Integrated project reportIntegrated project report
Integrated project reportLin Hui
 

En vedette (20)

Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
ITD Presentation Slides
ITD Presentation SlidesITD Presentation Slides
ITD Presentation Slides
 
M3 EG BQ for timber panel door
M3 EG BQ for timber panel doorM3 EG BQ for timber panel door
M3 EG BQ for timber panel door
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Charity drive report 2
Charity drive report 2Charity drive report 2
Charity drive report 2
 
Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bm
 
Measurement4
Measurement4Measurement4
Measurement4
 
Measurement Assignment 2
Measurement Assignment 2 Measurement Assignment 2
Measurement Assignment 2
 
M3 EG BQ timber windows
M3 EG BQ timber windowsM3 EG BQ timber windows
M3 EG BQ timber windows
 
M3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answerM3 Lecture 10 timber roof structure answer
M3 Lecture 10 timber roof structure answer
 
M3 Lecture 7 notes aluminium door
M3 Lecture 7 notes aluminium doorM3 Lecture 7 notes aluminium door
M3 Lecture 7 notes aluminium door
 
Design project one full
Design project one full   Design project one full
Design project one full
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof covering
 
Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster Ipoh railway station - Scientific Poster
Ipoh railway station - Scientific Poster
 
Integrated project report
Integrated project reportIntegrated project report
Integrated project report
 

Similaire à Practice for Quantity Surveyors

Similaire à Practice for Quantity Surveyors (20)

Curriculum Vitae (Muzzafar)
Curriculum Vitae (Muzzafar)Curriculum Vitae (Muzzafar)
Curriculum Vitae (Muzzafar)
 
CV of engr. Ghulam Azhar with 14 years exp (1)
CV of engr. Ghulam Azhar with 14 years exp (1)CV of engr. Ghulam Azhar with 14 years exp (1)
CV of engr. Ghulam Azhar with 14 years exp (1)
 
OSAS CV
OSAS CVOSAS CV
OSAS CV
 
OSAS CV
OSAS CVOSAS CV
OSAS CV
 
resume frfcf murgi
resume frfcf murgiresume frfcf murgi
resume frfcf murgi
 
Edmund Changngi (Current CV's Rev. 1 )
Edmund Changngi (Current CV's Rev. 1 )Edmund Changngi (Current CV's Rev. 1 )
Edmund Changngi (Current CV's Rev. 1 )
 
Kaushik Patel Resume
Kaushik Patel ResumeKaushik Patel Resume
Kaushik Patel Resume
 
Scope of work
Scope of workScope of work
Scope of work
 
ANALYSIS, MODELLING AND ESTIMATION OF SUSPENSION BRIDGE
ANALYSIS, MODELLING AND ESTIMATION OF SUSPENSION BRIDGEANALYSIS, MODELLING AND ESTIMATION OF SUSPENSION BRIDGE
ANALYSIS, MODELLING AND ESTIMATION OF SUSPENSION BRIDGE
 
Ajesh Resume
Ajesh ResumeAjesh Resume
Ajesh Resume
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013
 
CSCM @Qlassic
CSCM @QlassicCSCM @Qlassic
CSCM @Qlassic
 
Naveed Asif C.V Updated
Naveed Asif C.V UpdatedNaveed Asif C.V Updated
Naveed Asif C.V Updated
 
Civil Consultant Resume
Civil Consultant ResumeCivil Consultant Resume
Civil Consultant Resume
 
OSAS-CV5
OSAS-CV5OSAS-CV5
OSAS-CV5
 
Vadali_Srinivas[1]
Vadali_Srinivas[1]Vadali_Srinivas[1]
Vadali_Srinivas[1]
 
Shiraz nawaz cv.
Shiraz nawaz cv.Shiraz nawaz cv.
Shiraz nawaz cv.
 
Mohammed vasil k.
Mohammed vasil k.Mohammed vasil k.
Mohammed vasil k.
 
CV M.Ilyas - 1
CV M.Ilyas - 1CV M.Ilyas - 1
CV M.Ilyas - 1
 
Adeel Shaikh CV
Adeel Shaikh CVAdeel Shaikh CV
Adeel Shaikh CV
 

Dernier

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Dernier (20)

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Practice for Quantity Surveyors

  • 1.   U EG E L LOC D C-S R I L A N K A A * * U – CAD College U EG E L LOC D C-S R I L A N K A A SRI LANKA 236, AL MUNAWWARA ROAD* * AKKARAIPATTU-04       Training Program for Quantity Surveying   Practice for Quantity Surveyors (Based on SMM 7, CESMM 3, POMI & FIDIC)     M.A. Unais B.Sc. in Architecture Engineer, Dip. in Quantity Surveyor
  • 2. Contents Practice for Quantity Surveyors (Based on SMM7, CESMM3, POMI & FIDIC)   U EG E L LOC D C-S R I L A N K A A * 1.0) The Quantity surveyor’s role  • Post‐contract duties    • Pre‐contract duties    * 2.0) Contract Payments   2‐a)  Measurements   SMM 7   (Standard method of mea ent  uildin  works) surem of b g (Civil En  Stand et  Measurement) I    (Princip for  of ent Certifica nds  Preparatio Checking o  Paper  ent Sheet  mary / Payment Certificate   Time  a Works  du   CESMM 3   gineering ard M hod of     POM les of Measurement   Works  Construction)    2‐b)  Interim Bill    2‐c)  Paym te    2‐d)  Some Important Term (Related to bill of Quantities and Payment)    2‐e)  Bo   2‐f)  Final Bill    2‐g)  n of Bill    2‐h)  f Bill    2‐i)  Specimen Grand Summary / Payment Certificate    3.0) Annexes  • Dimension   • Measurem   • Grand sum   • Extension of   • Schedule for Extr   • Schedule for SSR    • Schedule for In‐Lieu Sche le    • Application from for Variation Order  4.0) Contract Document  4‐a)  Condition of Contract (FIDIC)    4‐b)  Specifications    4‐c)  Drawings  4‐d)  BOQ     4‐e)  Tender with Appendix    4‐f)  Letter of acceptance    4‐g)  Contract agreement    5.0)  Unit Pricing (Resource Cost)  • Labour  • Material  • Plant    M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu
  • 3. M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu U EG E L LOC D C-S R A N K A I L A * *     1.0) The Quantity surveyor’s role  1‐a)  Pre – Contract (QS) Preparation of Bill of Quantity  Quantity taker‐off  Preparation of preliminary estimate and introduction to cost plant  Estimating for tendering purposes  Introduction to tender procedure and contractual arrangements   Preparation of Tender documents for Sub Contractor and Supplier.  Preparing comparison sheets and analyzing.    1‐b)  Post‐Contract (QS) Preparation of interim and final application for payment  Preparing of valuations for interim and final certificate   Variation orders, preparation of variation accounts and valuation   Preparation, valuation, negotiation and reporting on claims.  Preparing Sub contractors and supplier’s payment certificate and certifying.    2.0) Measurements   The term “measurement” covers two types of measurements encountered in construction work namely  Taking off dimension by reading or scaling drawing and indicating on “Dimension Paper”     This type of measurement is required either in case of proposed work or to check whether the completed  work is in accordance with the proposed work.   And  The actual measurement of completed work at site and recording on “Measurement Sheets”    Main classification of works related to field of civil engineering with respect to measurements.  • Building works  • Civil Engineering Works    2‐a)  Dimension Paper    1. Timesing column (Number)  2. Dimension column  3. Squaring column (Qty.)  4. Description           Form of Dimension (Units)    Before going any further it is necessary to understand the asset down by the taker‐off. All dimensions are in of  five forms  Cubic measurements  ‐  m3 Square measurements   ‐  m2 Linear measurements  ‐  Lm / m  Numbers    ‐  Nr / No  Items       ‐  item         
  • 4.                            M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu  
  • 6. M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu, Sri Lanka 2‐a.3.1)  Building Works  • All types of building such as,  • House or Dwelling Units  • Flats  • Shops  • Hotels  • Hospital  U EG E L LOC D C-S R I L A N K A A * • Theatres  • Gymnasiums  • Office  * • Ware house    2‐a.3.2)  Civil Engineering Works  • Water supply schemes  chemes  hemes     methods dard met thod of measurement of building works (SMM of Building Works)  ing Standard Method of Measurement (CESMM)  ard method of measurement of building works (SMM of Building Works)   been prepared by the royal Institute of Chartered surveyors (RICS) and the National  ration of Building Trades Employers (NFBTE), UK  a  m    t of ci engineers and th  w f consu • Surface drainage s • Irrigation Sc • Highway  • Railways  • Culverts & Bridges  • Mass excavation filling and embankments (mass earth works)  • Dredging • Retaining walls    2‐a.4)  Standard  of measurements  For the purpose of providing a uniform basis for measurements, two types of “stan hod of  measurement” have been established namely    • Standard me • Civil Engineer   2‐a.4.1)   Stand This has Fede   2‐a.4.2)   Civil engineering st ndard ethod of Measurement (CESMM) This has been prepared by he institution  vil  e federation of civil engineering  contractor, in associations ith the Association o lting Engineers, UK    2‐a.4.3)  Comparison of Standard method of measurements of building works and civil  engineering works   • General   Though there are two separate and distinct practices of measurements established for building and civil  engineering works, there are common features too in between them such as   o General approach  o Units of measurement  o Certain items of work which can be measured by any of the two methods     • Building works  At the time of preparing BOQ, the details available are usually in a for more precise stage, therefore items  description can be made precisely and quantities can ascertained accurately for many items    • More trades or work section are available, resulting much more detailed measurements for which rates  have been quoted by the tenders some of them may be quite small   
  • 7. M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu, Sri Lanka • Civil engineering works  o In BOQ detailed description are not available therefore in pricing the BOQ and in constructing the  work the specification drawing and other related documents are to be closely studied constantly   o Generally temporary work and incidental labors are not measured separately therefore cost of  which have been incorporated in related BOQ item  o There is a great risk in pricing     U EG E L LOC D C-S R I L A N K A A * 2‐a.4.4)  Advantage of the use of standard methods of measurement   The following are some advantages that can be gained by studying and referring to standard  methods of measurements and incorporating same in contract documents  * o Avoidance of disputes in measurements between parties  o Gaining familiarity in the standard method  para n of bills of quantities  of pre tio  standard of pre d ent reque c nce n specim rtant ter ization Advance  yment made beforehand to the contractor by the employer / client before the  ncement of the contactor work as an assistance to mobilize or get ready to start  ctor work  t term  an  mad for the work ified o Gaining familiarity in the  method  senting item  escription in bills of quantities     2‐b)  Interim bill  Interim bill are the paym st submitted by the contractor in ac orda  with the terms &  condition of the contract during the course of the contract    2‐c)  Payment certificate  This is the document which certificate payment the reader is referred to item 9.00 o en grand  summary certificate    2‐d)  Some impo ms related to bill of quantities and payment  2‐d.1)    Advance payment  These are payment made beforehand to the contractor by the employer / client either before the  commencement of the contractor work or before the bills resubmitted are checked and certified.     2‐d.1.1)  Mobil The pa comme contra   The paymen s d the recovery of the mobilization advance will depend on the terms and  conditions of the contract applicable to the project    2‐d.1.2)  On account payment / part payment  This can be defined as an advance payment e   already performed and effected  before bills submitted are checked and cert .    This type of payment is not incorporated in the contract but made only on mutual understanding  and special agreement with relevant approval    In this type of payment only a percentage is certified therefore they are called part payments    2‐d.2)  Retention  The amount of money to be retained from the bill payments due to the contractor is known as retention   This is to cover any possible shortcoming of the contractor  Release of retention is mead in accordance with the Terms and Condition of the Contract.    2‐d.3)  Recoveries  The amount of money to be recovered from the contractor are called recoveries  Some of the recoveries to be made from the bill payments to the contractor are as follows  o Mobilization Advance  o Liquidated Damages  o Material used or services offered to the contractor by the Employer / Client.  o Cost of any losses  
  • 8. M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu, Sri Lanka   2‐d.4)  Extension of Time  If the contract cannot be completed within the original agreed contract period due to some reason or  reasons the contractor must request for the extension of the contract period which is termed Extension  of time    Such extension are granted if the delay is due to reasons beyond the control of the contractor otherwise  the contractor is charged with Liquidated Damages    U EG E L LOC D C-S R I L A N K A A * In granting extension of time it is to be clearly stated whether the Contractor is entitlement what type of  payment are entitled for.    * 2‐d.5)  Liquidated Damages  These are charges imposed on the contractor on the s spe ied in the contract when the extension  of time is not granted   term cif  defined a ign e kind cation  nce with acts of parliament, regulation or by laws...   variation and valuation of variation  es of variation recognized and practiced   cre or  due to erro      2‐d.6)  Variations   A variation on the work is s any alteration or modification of the des  material workmanship  quality or quantity of the work    This include any additional omission or substitution of the work or alteration of th  or standard of  any material     A variation is caused to the following reasons too    o A discrepancy or divergence between the bills of quantities drawing and specifi   o Error or omission in the bill of quantity drawing and specification    o Complia   2‐d.6.1)  Type of The typ   o Extra works  The variations occurred due to in ase  decrease of BOQ quantities either  r in BOQ or addition  or omission which affects quantities in BOQ items is called extra works   These are valued at relevant prevailing BOQ rates    The schedule to be prepared with respect to extra work is given in Annex V    o SSR (Special schedule of Rates)  The variation occurred due to addition of new items of works which is not available in the BOQ are called  special schedule of rates    These are to be valued by one of the following methods in the sequence mentioned  o Rates of similar BOQ items executed under similar conditions  o Rates based on similar BOQ items executed under similar conditions  o Rates build up on day works applicable to the contract  o Applicable rates  o Rates build up on day works rates indicated in relevant rate book  o Rates build up on prevailing market prices and labor rates and accepted labor and plant output  and material requirements A specimen from for SSR is indicated in Annex VI   
  • 9. M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu, Sri Lanka o In lieu schedule   In lieu schedule is issued when a substitution is made for a BOQ item    Eg. Fixing rubber water bars in place of PVC water bars.    Annex Vll is referred for specimen from of in‐lieu schedule    2‐d.7)  Provisional quantities  U EG E L LOC D C-S R I L A N K A A Assumed quantities are entered against some items in BOQ of which the actual quantities cannot be  calculated at the time of preparing BOQ since the extent of work is not known these are termed  provisional quantities this will be apparent only once the job is done    * * This will become a variation in the contract once the variation is approved the provisional quantities are  replaced with actual quantities and paid as per quo ates ted r cture of a g  d in BOQ to d generate asing sani ontracto ‐conditioni tractor  ums  ded against some BOQ items, without quantities as “items of which either the full extent  ctual cost involved are not known at the time of preparing BOQ   become variations   La  t t contractor th rial specified in Eg:      o item of work in sub‐stru  building  o Excavation for pipe layin   2‐d.8)  Prime Cost Sums  These are include  cover work which require, special selection an s the appointment  of nominated sub‐contractor or nominated suppliers  Eg:      o Purch tary appliances from the nominated suppliers by the main c r and  installed by the main contractor.  o Air ng or supplying and installation of pumping equipment by nominated sub‐ con   Since these prime cost sums are not the actual sums these will become variation and to be dealt with  accordingly    2‐d.9)  Provisional S These are inclu character or a   These will also Eg:   Excavation for Pipe ying on roads.    2‐d.10) Escalation   If the escalation clause is applicable o the pertinen e contractor is entitled for the  additional payment at the rates for labor and mate  the contract    2‐d.11) Day works  There are certain items of work which cannot be measured and the cost determined beforehand until the  work is attended to.    For such items there are rate for labor materials and plant either incorporated in the contract or agreed  in advance between the parties which are called day works labor rates day works material rates and day  works plant rates    When the said items of work are executed records are kept on the labor hour’s material used and plant  hours involved and the valuation of the work is done applying the day work rates     The items of work described above are termed day works  Eg:     Attending to pipe leak 
  • 10. M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu, Sri Lanka 2‐e)  Bonds   In case of contracts the bonds are legal documents which bind a person for a legally accepted action  under the terms and conditions specified    In case of building and civil engineering contracts the surety undertakes to be liable for the contractor’s  default    U EG E L LOC D C-S R I L A N K A A * 2‐e.1)  Types of bonds  Three types of bonds generally used in building and civil engineering contracts are as follows:    * 2‐e.1.1) Bid bond or tender guarantee   o Tender submitted should remain open for accept  for th period indicated in the Appendix to the  form of tender. No tender is e  withdraw el or voke his tender during the staid period  ance e  ntitled to  canc  re itions imp follo nd validity orm of ten  with th iven to  tender w  of the successful tender shall be returned after he furnishes the performance bond   the successful tender fail to sign the contract and to submit the performance bond as   bid bond will be forfeited.  on advance payment  nt of  ob um  the way  by  co ct ag   o According to the cond osed Bond can be furnished in one of the  wing alternative forms:  o Cash Deposit  o An acceptable Bank Guarantee  o A certified cheque issued by a recognized bank    o The value a  of the bond should be as indicated in the Appendix to the f der  o This Bond should accompany the tender any tender not accompanied by bid bond e required  value validity and terms will be disqualified and no further consideration will be g such tender    o After the award has been finalized the Bid Bond will be returned to the respective  ith the  exception of that of the successful tender    o The bid bond   o In the event specified the   2‐e.1.2) Mobilizati Before the payme m ilization advance on the request of the contractor a bond as per the specimen  form provided and the other doc ents specified in the contract for eg:  of expending the  advance is to be provided  the ntractor    2‐e.1.3) Performance bond   Within the specified period on signing the contra reement the contractor should present  performance bond for due and proper performance of the contract    2‐e.2) Encashment of bonds  In case of default of the contractor the bonds are lodged with the surety claimed encashment as per the  terms and conditions specified    2‐e.3) Points to be checked in a bond  The points to be checked in a bond are as follows  o The accuracy of the   o Surety  o Parties involved in the contract  o Title of the contract  o Contract price  o Period of validity of the bond  o Terms and conditions  o Clause on payment on demand  o Wording 
  • 11. M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying  U – CAD College, Akkaraipattu, Sri Lanka o Signatory  o Signature  and  o Official Stamp    2‐f)  Final Bill  This is the last bill submitted by the contractor with respect to the contract entered into.    2‐g)  Preparation of bills  U EG E L LOC D C-S R I L A N K A A * The standard practice is to prepare the bills in cumulative basis in which the total value of work done up  to the date of measurement from the commencement of work including those already paid are  ascertained and the balance due to the contractor is determined by subtracting the amounts already paid  from the said total value  *   Each and every time of bill preparation the join surement are done staring from the beginning  automatically correcting an ade at pr s measurements.  t mea y errors m eviou e followin f th  is  k done on    the bills  Contract  r’s signature  ck whether the signature is available and its correctness  s   of the   escription  em number  ld  ly ity b he rate    Bill preparation is to be don g the same order o e BOQ and it a good practice to indicate the  BOQ items and wor Variation Orders granted separately with  ir total values independently    2‐h)  Checking of  The points to be noted in checking of bills are as follows:    2‐h.1)  Contract particulars   • Name of the contractor  • title  • Contract number  • Date of measurement    2‐h.2)  Contracto Should che   2‐h.3)  BOQ item The correctness • Item d • BOQ it • Quantity (this shou not exceed the BOQ quantity)  • Unit  • Rate  • Amount obtained by multip ing the quant y t • Total    2‐h.4)  Items of work done on variation orders  Only the items of work already approved are to be certified for payment the copies of approved orders  should be available in the finance branch    It is a good practice to group and total the extra works schedule of rates and in lieu schedule separately in  the order of BOQ sections    The following are the points to be noted  • Variation order number  • Item description   • Quantity  • Unit  • Rate  • Amount  • Total 
  • 12. U – CAD College, Akkaraipattu, Sri Lanka DATE:___________________ PROJECT: PAGE:___________________ Time/ NO. DIM. SQU / QTY. DESCRIPTION Time/ NO. DIM. SQU / QTY. DESCRIPTION QUANTITY TAKE-OFF SHEET (BS 3327-statinery for Quantity Surveyours) M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying
  • 13. U – CAD College, Akkaraipattu, Sri LankaContrector Name : …… Project :- …………. Contrect No : …… Date :- ……………. Description BOQ Item No. No. Length Breadth Depth Quantity Total Measurement Sheet M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying U – CAD College, Akkaraipattu, Sri Lanka
  • 14. U – CAD College, Akkaraipattu, Sri Lanka TITLE OF CONTRACT : ………………………….. CONTRACT NO. : ………………………….. CONTRACTOR : ………………………….. CONTRACT VALUE : ………………………….. BILL NO : ………………………….. 1.00 Value of work executed (Excluding Variations) 5,461,190.00 2.00 Value of work executed on Variation Orders 1,177,493.40 Sub Total - A 6,638,683.40 3.00 80% of Valvue of Matrial on site 1,071,600.00 Sub Total - B 7,710,283.40 4.00 Add Advance Payment 5,875,513.18 Sub Total - C 13,585,796.58 Less 5.00 Retention (10 % of B) (771,028.34) 6.00 Recovery of Mobilization Advance (20% of B) (1,542,056.68) 7.00 Other Recoveries 7.10 Water provided by the board (15,907.50) 7.20 Power provided by the board (2,328.00) 7.30 Non provision of services as per contract (23,453.75) 7.40 For utilization of Board Building (4,500.00) 7.50 Recovery of preliminaries due to use of pre mixed concrete (45,426.00) 7.60 Item not recovered from (3,010.00) (2,407,710.27) Less Previous payments 11,178,086.31 Certificate No. 1 (Mob. Advance) (5,875,513.18) Certificate No. 2 (Bill No.-2) (1,914,225.24) Certificate No. 3 (Bill No.-3) (453,008.67) Certificate No. 4 (Bill No.-4) (394,065.26) (8,636,812.35) Balance due to the Contractor 2,541,273.96 Project Manager ………………………. Date ………………………. we recommend the payment of Rs. Two Million, Five Hunderd Forty One Thousand, Two Hundred and Seventy Three and Cents Ninety Six GRAND SUMMARY / CERTIFICATE NO M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying U – CAD College, Akkaraipattu, Sri Lanka
  • 15. U – CAD College, Akkaraipattu, Sri LankaScheme ………………………. Project : ………………………. Contractor Name : ………………………. Contract No : ………………………. Date :- …………… Variation Order No. ………………………. Page :- …………… Serial No. BOQ Item No. Item Description Unit Actual Qty. BOQ Qty Excess Qty Rate Amount Remarks / Reasons Schedule for extra works M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying U – CAD College, Akkaraipattu, Sri Lanka
  • 16. U – CAD College, Akkaraipattu, Sri Lanka Scheme ………………………. Project : ………………………. Contractor Name : ………………………. Contract No : ………………………. Date :- …………… Variation Order No. ………………………. Page :- …………… Serial No. Unit Qty. Rate Amount Reasons for Variation Justification for Rate Special Schdule of Rates Item Description M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying U – CAD College, Akkaraipattu, Sri Lanka
  • 17. U – CAD College, Akkaraipattu, Sri Lanka Scheme ………………………. Project : ………………………. Contractor Name : ………………………. Contract No : ………………………. Date :- …………… Variation Order No. ………………………. Page :- …………… Unit Qty. Rate Amount Description Unit Qty. Rate AmountItem Description Serial No. BOQ Item In Lieu Item Saving Excess Reasons for Variation In Lieu Schdule Variation Order No M.A. UNAIS B.Sc. in Architecture Engineering, Dip in Quantity Surveying U – CAD College, Akkaraipattu, Sri Lanka