2. Agenda
• Project Location and Alignment
• Easements, Constraints, and
Construction Sequencing
• Community Benefits and Restoration
• Project Clean Lake and CSO Benefits
once completed
2
3. About us
• Created by Court Order in 1972
• Servicing all or part of 62
member communities
• 1 million customers
• 90+ billion gallons wastewater
treated each year
3
4. What We Do
• Three wastewater treatment plants
• Interceptor sewer operation,
maintenance
• Combined Sewer Overflow control
• Regional Stormwater Management
4
5. Street Catch WWTP
Basins
Domestic Industrial
Wastewater Wastewater Storm Water
Outlet (SWO)
Regulator
Lake Erie
Combined
Sewer
Combined
Dry weather
Sewer Overflow
outlet (DWO)
Flow to WWTP
Combined Sewer System
6. How they work:
Regulating structures
allow excess stormwater
to overflow
Overflow pipe
Side-spill weir
6
11. Project background
• Control CSO overflows
• Consolidate existing regulators
• Provide relief for up to a 5-year, 6-hour
storm event
• Convey flow to current interceptor, future
tunnel
• Prepare for future 17’ Doan Valley Tunnel
11
12. By the numbers
• 11,000 feet
3’ to 6’ sewers in tunnel
• 2,700 feet
15” to 7’ sewers in open-cut
• Plus structures, regulators, and
modifications
13. DWIRS Location
DWIRS location related to
Dugway West Brook and Dugway
West Culvert
Existing local sewer system
Existing CSO Regulators
Proximity to Dugway East Brook
and Dugway Storage Tunnel
Proximity to Easterly Interceptor
on the North End
Proximity to Doan Valley Tunnel
on the South End
13
14. Open Streams, Brooks ORIGINAL
Nine Mile
Nine Mile
Creek/Culvert
Creek/Culvert
Dugway West
Dugway West
Brook /Culvert
Brook /Culvert
Dugway East
Dugway East
Brook/Culvert
Brook/Culvert
Doan Brook/
Doan Brook/
Culvert
Culvert
15. Open Streams, Buried Culverts CURRENT
Nine Mile
Nine Mile
Creek/Culvert
Creek/Culvert
Dugway West
Dugway West
Brook /Culvert
Brook /Culvert
Dugway East
Dugway East
Brook/Culvert
Brook/Culvert
Doan Brook/
Doan Brook/
Culvert
Culvert
16. Bidding, Construction Schedule
1. DWIRS Project Bidding May 2013
2. Construction Start Sept. 2013
3. Substantial Completion May 2016
(32 months)
4. Final Completion Sept. 2016
(36 Months)
16
17. Easements, property
acquisition
• Ongoing discussions
• Negotiations: TranSystems
• Land Bank acquisitions, demolition:
NEORSD
• 8 properties to be demolished
• Demolition work will occur in the first 5
months
17
18. Project Constraints
• Focus: Northern half, then southern
– Utility relocation by other agencies may
occur anywhere along alignment
• Limit active shafts, work sites
• Restore work zones shortly after
completion
18
19. Project Constraints
• Coordinate with schools to maintain
access to all driveways
• Limit haul routes
• Complete work within St. Clair within
12 months
19
20. Project Constraints
• Complete Durant sewer in final 12
months
• Demolish eight structures within first
five months
• Work hours: 7 a.m. – 7 p.m.
Monday – Saturday per the City
20
37. Provisions and
monitoring
• Inspections: Contractors will video
and photograph structures’ exterior
• Markers: Contractor will install
Geotechnical instrumentation and
survey markers on structures
• Vibration monitoring
37
41. What is Project Clean Lake?
• Consent decree with EPA
• $3 billion 25-year program to address
water quality issues caused by sewage
overflows (CSOs)
41
42. What is Project Clean Lake?
• 772 communities have similar
mandates
43. What is Project Clean Lake?
• Reduce combined sewer overflow volume
10
9
8
7
Billions of gallons
6
5
4
3
2
1
0
1972 TODAY 2035
43
45. 7 tunnels to control CSO
• 21 total miles
• 17’ to 24’ diameters
• 100’ to 200’ underground
• Three Deep Tunnel Pump Stations
• Drop Structures, Near Surface Sewers
and Structures
45
47. Other CSO Project
Coordination
SST
SST
DST Overlap (DST)
E140
E140
DST-4 Forest Hills Park
DST-5 St. Clair/E 109th
DST-7 Lakeview and Ada
DST-8 Lakeview and Superior
East 140 th Relief Sewer
(E140)
Doan Valley Tunnel (DVT)
DST
DST Lakeview and Ada
Superior Ave
Shoreline Storage Tunnel
(SST)
DWIRS
DWIRS
Forest Hills Park Mining Site
47
DVT
DVT
49. CSO Reduction Benefits
Year of Annual
Project Title Completio CSO capture
n
Dugway East Relief Sewer (DEIRS) 2012 85 Million Gallons
Euclid Creek Storage Tunnel (ECT) 2015 344 Million Gallons
Dugway West Relief Sewer (DWIRS) 2016 110 Million Gallons
Dugway Storage Tunnel/E 140th
2020 411 Million Gallons
(DST/E140)
Doan Valley Tunnel (DVT) 2021 348 Million Gallons
Shoreline Storage Tunnel (SST) 2027 502 Million Gallons
Total CSO 1,800 Million
Capture Gallons
Northeast Ohio Regional Sewer District neorsd.org/cleanlake | cleanlake@neorsd.org neorsd.org/cleanlake | cleanlake@neorsd.org Northeast Ohio Regional Sewer District
Northeast Ohio Regional Sewer District neorsd.org/cleanlake | cleanlake@neorsd.org neorsd.org/cleanlake | cleanlake@neorsd.org Northeast Ohio Regional Sewer District
11,000 feet of 36”-72” sewers in tunnel Approximately 2,700 feet of 15”-84” sewers in open-cut 2 diversion structures to future DST and Dugway West/East Culverts (DWD-1 & DWD-2) 2 regulator structures to Dugway West Culvert (DWR-1 & DWR-2) Flow Divider (DWF-1) Modifications to 39 existing regulators
Ongoing Temporary and Permanent Easement Negotiations TranSystems is Consultant handling the Negotiations NEORSD is processing Land Bank Acquisitions and Demo 8 Properties will be demolished for the project and demo work will occur in the first 5 months.
Contractor to focus efforts on Northern Half before Southern (Utility relocation work by other agencies may occur anywhere along alignment) Limit the number of active shafts and work sites Work zone restoration following shortly after completion Coordinate with schools to maintain access to all driveways. Limit Construction Haul Routes Work within St. Clair shall be completed within 12 months Durant sewer shall be done in the final 12 months Demo 8 Structures within first 5 months Work Hours are 700am to 700pm Mon– Sat per the City
Contractor to focus efforts on Northern Half before Southern (Utility relocation work by other agencies may occur anywhere along alignment) Limit the number of active shafts and work sites Work zone restoration following shortly after completion Coordinate with schools to maintain access to all driveways. Limit Construction Haul Routes Work within St. Clair shall be completed within 12 months Durant sewer shall be done in the final 12 months Demo 8 Structures within first 5 months Work Hours are 700am to 700pm Mon– Sat per the City
Contractor to focus efforts on Northern Half before Southern (Utility relocation work by other agencies may occur anywhere along alignment) Limit the number of active shafts and work sites Work zone restoration following shortly after completion Coordinate with schools to maintain access to all driveways. Limit Construction Haul Routes Work within St. Clair shall be completed within 12 months Durant sewer shall be done in the final 12 months Demo 8 Structures within first 5 months Work Hours are 700am to 700pm Mon– Sat per the City
Contractors will perform external video and photographic inspection of Structures. Contractor will install Geotechnical instrumentation and survey markers on structures. Vibration Monitoring. Surface Settlement Monitoring over tunnel. Post Construction Inspection. Restoration as needed.
Contractors will perform external video and photographic inspection of Structures. Contractor will install Geotechnical instrumentation and survey markers on structures. Vibration Monitoring. Surface Settlement Monitoring over tunnel. Post Construction Inspection. Restoration as needed.
Aspects of the Restoration are open to Community input. Final Roadway restoration will include new pavement. Additional Demo will be considered. NEORSD is considering additional community benefits as opportunities are presented.
Aspects of the Restoration are open to Community input. Final Roadway restoration will include new pavement. Additional Demo will be considered. NEORSD is considering additional community benefits as opportunities are presented.
Northeast Ohio Regional Sewer District neorsd.org/cleanlake | cleanlake@neorsd.org neorsd.org/cleanlake | cleanlake@neorsd.org Northeast Ohio Regional Sewer District
Northeast Ohio Regional Sewer District neorsd.org/cleanlake | cleanlake@neorsd.org neorsd.org/cleanlake | cleanlake@neorsd.org Northeast Ohio Regional Sewer District
21 Miles in Length 17’ to 24’ in Diameter 100’ to 200’ in Depth Five Rock Tunnels in Chagrin Shale Two Soft ground Tunnels in Buried Cuyahoga River Valley Three Deep Tunnel Pump Stations Drop Structures Near Surface Sewers and Structures
Northeast Ohio Regional Sewer District neorsd.org/cleanlake | cleanlake@neorsd.org neorsd.org/cleanlake | cleanlake@neorsd.org Northeast Ohio Regional Sewer District
Northeast Ohio Regional Sewer District neorsd.org/cleanlake | cleanlake@neorsd.org neorsd.org/cleanlake | cleanlake@neorsd.org Northeast Ohio Regional Sewer District