The document outlines 10 top risks that international contractors face in international contracts. These risks include: 1) what law will apply to the contract and the potential consequences, 2) what technical standards or codes will apply legally and in practice, 3) what dispute resolution processes are in place to avoid arbitration, 4) whether contracts contain enforceable conditions precedent, 5) entitlement to extensions of time and concurrency issues, 6) enforceability of liquidated damages and performance damages caps, 7) caps on liability and exclusions of consequential losses, 8) payment security, interest, and termination rights for non-payment, 9) hidden design risks and approval processes, and 10) bonding requirements and repayment risks for wrongful bond calls.
Cybersecurity Awareness Training Presentation v2024.03
Werksmans Construction & Engineering Seminar - John Bishop presentation
1. The “Ten” top risks for International
Contractors
John Bishop
2. Law Clauses
• What Law will apply?
– Do we understand the consequences?
• For the effectiveness of a contract
• For the performance
• Change of Law
– Who takes the risk of a change of law?
2
3. Codes and Standards
• What technical standards or codes will apply?
– Are those stated in the contract going to be applicable
• legally
• in practice
3
4. The Disputes Process
• What procedures will keep us out of arbitration?
– DRBs/DABs/other ADR processes
• Does the local law impose a process?
– E.g. compulsory adjudication
• Are the Arbitration terms effective?
– No right to arbitrate before completion,
– Will local Courts enforce?
– Local law intervention
• Will your award be enforceable?
– The New York Convention.
4
5. Conditions Precedent
• Does the Contract Contain Conditions Precedent to
entitlement?
– Maybe hidden
• “Upon” “If”
– What is the consequence of failing to meet the
condition precedent?
• Is a bar on entitlement enforceable under local
law?
• Is a bar capable of being circumvented?
• Most international contracts require parties to pursue
their claims to maintain the economic balance
5
6. EOTs
• What events?
– What about near misses?
• Concurrency
– English Law position
– Scottish Law position
– Anti concurrency clauses
• In some countries
– the prevention principle
– overriding legal entitlement to relief
6
7. Performance Damages
• LDs (Delay and Performance)
– Enforceable?
• Under local law
• If excessive
– Different countries different results
– Capped?
– Exclusive remedy?
– Following termination
7
8. Caps and Exclusions
• Is there a cap?
– Is it effective under the local law?
– What liabilities are outside the cap?
• Exclusion of consequential losses?
– What is a consequential loss?
– What are the exclusions?
– Is the clause enforceable?
– Following termination?
8
9. Cash Risk
• Is payment secured?
– Rights when non payment
• Interest
• EOT
• Termination
• Suspension
– Retention money and the right to exchange for a
bond?
– Cash consequence of an improper bond call
– Right to evidence of financing
– Speedy dispute resolution
9
10. Design Risk
• Hidden design risks
– the selection of plant and materials
– through subcontractors
• Design approval processes
– what is the process
– is it capable of being abused?
• restrictions on comments, time and nature
• Unfair design risk
– Employer Data
– Ground conditions
– Employer’s requirements/selection of plant
10
11. Bonding
• On demand
• Conditional
• Hybrid
• Applicable law
• Repayment following a wrongful call?
11
12. Termination
• Grounds for termination
– Reasonable?
– Cure period?
– Procedure for termination
• Local Law issues
– Judicial intervention necessary?
– For convenience
12
13. Right to suspend
• Suspension
– By contract
– By Law
• Not in English Common Law
– So potentially a breach
• May be statutory right but may be conditions
• Normal in civil law jurisdictions
13
14. Currency Risk
• Price in fixed currency/currencies but cost incurred in
different split
– variations
14