Push Method: A method in which production of the item
begins in advance of customer needs.
Example: A buffet where food is prepared in advance.
Pull Method: A method in which customer demand activates
production of the service or item.
Example: A restaurant where food is only prepared when
orders are placed.
Lean systems use the pull method of
work flow.
KANBAN
Kanban means “card” or
“visible record” in Japanese &
refers to cards used to control the
flow of production through a
factory.
KANBAN is a PULL System .
General Operating Rules:
1. Each container must have a card.
2. The assembly line always withdraws materials from
fabrication (pull system).
3. Containers of parts must never be removed from a storage
area without a kanban being posted on the receiving post.
4. The containers should always contain the same number of
good parts. The use of nonstandard containers or irregularly
filled containers disrupts the production flow of the assembly
line.
5. Only nondefective parts should be passed along.
6. Total production should not exceed the total amount
authorized on the kanbans in the system.
–看板 Kanban cards limit excess
work in progress
• –看板 Kanban literally means
“visual card,” “signboard,” or
“billboard.”
• Toyota originally used Kanban
cards to limit the amount of
inventory tied up in “work in
progress” on a manufacturing
floor
• Not only is excess inventory
waste, time spent producing it
is time that could be expended
elsewhere
• Kanban cards act as a form of
“currency” representing how
WIP is allowed in a system.
5
“Pull” system to avoid overproduction
• Milk example – weekly batch or daily purchase?
• Next purchase triggered when you start using the only
bottle of milk you have.
• Not an example of zero-inventory, but still a pull system.
• Because of demand uncertainty and lead-times, in many
cases inventory is necessary to allow for smooth
production.
• Hence TPS follows the supermarket model or keeping a
small amount in stock. As soon as customers take
products away, they are replenished.
• Each demand instance triggers a part being pulled from
upstream.
• The triggering mechanism is called “Kanban” which
means cards, signboard or a poster.
6
Kanban system
• At Toyota, empty bin (a kanban) is send upstream after a
demand instance.
• It is a signal to refill it with a specific number of parts or send
back a card with detailed information about the part location.
• Even today, one can see Kanban cards and bins moving on the
shop-floor.
• Instead of using sophisticated computer scheduling
techniques, this is a simple, effective and visual system of
managing and ensuring the product flow and JIT production
system.
7
Kanban system
• Gas tank example.
• Toyota philosophy about kanban:
“Kanban is an organized system of inventory buffers and
as per TPS (Toyota Production System ), inventory is
waste, whether it is in pull system or push system. So
kanban is something you strive to get rid of.”
• Toyota uses kanban to force process improvements.
8
Kanban Flow
Kanban Rule: No Kanban card, no production
or movement of material
Can accommodate 10%-20% of changes in
planned production
Can easily extend to suppliers (supplier
Kanban)
Kanban card forKanban card for
product 1product 1
Kanban card forKanban card for
product 2product 2
FabricationFabrication
cellcell
OO11
OO22
OO33
OO22
StorageStorage
areaarea
Empty containersEmpty containers
Full containersFull containers
Assembly line 1Assembly line 1
Assembly line 2Assembly line 2
The Single-Card
Kanban System
Receiving postReceiving post
StorageStorage
areaarea
Empty containersEmpty containers
Full containersFull containers
Kanban card forKanban card for
product 1product 1
Kanban card forKanban card for
product 2product 2
FabricationFabrication
cellcell
OO11
OO22
OO33
OO22
Assembly line 1Assembly line 1
Assembly line 2Assembly line 2
Receiving postReceiving post
The Single-Card
Kanban System
StorageStorage
areaarea
Empty containersEmpty containers
Full containersFull containers
Kanban card forKanban card for
product 1product 1
Kanban card forKanban card for
product 2product 2
FabricationFabrication
cellcell
OO11
OO22
OO33
OO22
Assembly line 1Assembly line 1
Assembly line 2Assembly line 2
Receiving postReceiving post
The Single-Card
Kanban System
StorageStorage
areaarea
Empty containersEmpty containers
Full containersFull containers
Kanban card forKanban card for
product 1product 1
Kanban card forKanban card for
product 2product 2
FabricationFabrication
cellcell
OO11
OO22
OO33
OO22
Assembly line 1Assembly line 1
Assembly line 2Assembly line 2
Receiving postReceiving post
The Single-Card
Kanban System
StorageStorage
areaarea
Empty containersEmpty containers
Full containersFull containers
Kanban card forKanban card for
product 1product 1
Kanban card forKanban card for
product 2product 2
FabricationFabrication
cellcell
OO11
OO22
OO33
OO22
Assembly line 1Assembly line 1
Assembly line 2Assembly line 2
Receiving postReceiving post
The Single-Card
Kanban System
StorageStorage
areaarea
Empty containersEmpty containers
Full containersFull containers
Kanban card forKanban card for
product 1product 1
Kanban card forKanban card for
product 2product 2
FabricationFabrication
cellcell
OO11
OO22
OO33
OO22
Assembly line 1Assembly line 1
Assembly line 2Assembly line 2
Receiving postReceiving post
The Single-Card
Kanban System
StorageStorage
areaarea
Empty containersEmpty containers
Full containersFull containers
Kanban card forKanban card for
product 1product 1
Kanban card forKanban card for
product 2product 2
FabricationFabrication
cellcell
OO11
OO22
OO33
OO22
Assembly line 1Assembly line 1
Assembly line 2Assembly line 2
Receiving postReceiving post
The Single-Card
Kanban System
A TYPICAL KANBAN CARD
We can also modify this
Kanban card to suit our
requirement the best .
This card acts like a visual
control to replenish the
required quantity .
PARTVISUAL INSERTPHOTO HERE
PARTNO
PARTDESCRIPTION
PRODUCTION LINE
WORK STATION NO
LINESIDERACK NO
LINESIDELOAD QTY
REPLINSHMENT TRIGGER QTY
REPLINSHMENT FROMLOCATION
REPLINSHMENT QTY
KANBAN CARD
Thank you so much for viewing ………..
Let me know your feedbacks at :
industrialenggconsultancy@gmail.com

Contenu connexe

Tendances

world-class-manufacturing
world-class-manufacturingworld-class-manufacturing
world-class-manufacturing
Prasad Bidwai
 

Tendances (20)

Akshay kanban
Akshay kanbanAkshay kanban
Akshay kanban
 
SMED Setup & Lead Time Reduction
SMED Setup & Lead Time ReductionSMED Setup & Lead Time Reduction
SMED Setup & Lead Time Reduction
 
Just in time manufacturing ppt
Just in time manufacturing pptJust in time manufacturing ppt
Just in time manufacturing ppt
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
Lean manufacturing overview
Lean manufacturing overviewLean manufacturing overview
Lean manufacturing overview
 
Material requirement planning, MRP.
Material requirement planning, MRP. Material requirement planning, MRP.
Material requirement planning, MRP.
 
Line balancing
Line balancingLine balancing
Line balancing
 
Poka Yoke Final Ppt
Poka Yoke  Final PptPoka Yoke  Final Ppt
Poka Yoke Final Ppt
 
Production Planning and Control
Production Planning and ControlProduction Planning and Control
Production Planning and Control
 
Kanban Systems
Kanban SystemsKanban Systems
Kanban Systems
 
WCM (World Class Manufacturing)
WCM (World Class Manufacturing)WCM (World Class Manufacturing)
WCM (World Class Manufacturing)
 
Lean manufacturing ppt
Lean manufacturing pptLean manufacturing ppt
Lean manufacturing ppt
 
JIT- JUST IN TIME PPT
JIT- JUST IN TIME PPTJIT- JUST IN TIME PPT
JIT- JUST IN TIME PPT
 
Jit
JitJit
Jit
 
Lean ppt
Lean pptLean ppt
Lean ppt
 
Lean Manufacturing - An Overview
Lean Manufacturing - An OverviewLean Manufacturing - An Overview
Lean Manufacturing - An Overview
 
world-class-manufacturing
world-class-manufacturingworld-class-manufacturing
world-class-manufacturing
 
MRP I and MRP II
MRP I and MRP IIMRP I and MRP II
MRP I and MRP II
 
Just In Time & Kanban
Just In Time & KanbanJust In Time & Kanban
Just In Time & Kanban
 
Kanban (1)
Kanban (1)Kanban (1)
Kanban (1)
 

En vedette

Vt2014 kanban presentation
Vt2014 kanban presentationVt2014 kanban presentation
Vt2014 kanban presentation
plog99
 
Toyota Production System
Toyota Production SystemToyota Production System
Toyota Production System
shekhar67
 
Lean manufacturing concepts and tools and quality management1
Lean manufacturing concepts and tools and quality management1Lean manufacturing concepts and tools and quality management1
Lean manufacturing concepts and tools and quality management1
hgalinova
 
Visual Management: Leading with what you can see
Visual Management: Leading with what you can seeVisual Management: Leading with what you can see
Visual Management: Leading with what you can see
Renee Troughton
 

En vedette (20)

Vt2014 kanban presentation
Vt2014 kanban presentationVt2014 kanban presentation
Vt2014 kanban presentation
 
Jidoka Sample
Jidoka SampleJidoka Sample
Jidoka Sample
 
Introduction to jidoka november 2016
Introduction to jidoka   november 2016Introduction to jidoka   november 2016
Introduction to jidoka november 2016
 
Toyota Production System
Toyota Production SystemToyota Production System
Toyota Production System
 
Standardized Work
Standardized WorkStandardized Work
Standardized Work
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Kanban Board Examples
Kanban Board ExamplesKanban Board Examples
Kanban Board Examples
 
POKA-YOKE - A Lean Strategy to Mistake Proofing
POKA-YOKE - A Lean Strategy to Mistake ProofingPOKA-YOKE - A Lean Strategy to Mistake Proofing
POKA-YOKE - A Lean Strategy to Mistake Proofing
 
5 S Sample
5 S Sample5 S Sample
5 S Sample
 
Kanban Pull System
Kanban Pull SystemKanban Pull System
Kanban Pull System
 
Lean manufacturing concepts and tools and quality management1
Lean manufacturing concepts and tools and quality management1Lean manufacturing concepts and tools and quality management1
Lean manufacturing concepts and tools and quality management1
 
Visual Factory
Visual FactoryVisual Factory
Visual Factory
 
Kanban Explained in 11 Slides
Kanban Explained in 11 SlidesKanban Explained in 11 Slides
Kanban Explained in 11 Slides
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Visual Control and Management : Manufacturing Management
Visual Control and Management : Manufacturing ManagementVisual Control and Management : Manufacturing Management
Visual Control and Management : Manufacturing Management
 
Visual Controls - Mieruka
Visual Controls - MierukaVisual Controls - Mieruka
Visual Controls - Mieruka
 
Visual Management: Leading with what you can see
Visual Management: Leading with what you can seeVisual Management: Leading with what you can see
Visual Management: Leading with what you can see
 
Implementing Kanban Pull Systems in Office & Service Environments
Implementing Kanban Pull Systems in Office & Service EnvironmentsImplementing Kanban Pull Systems in Office & Service Environments
Implementing Kanban Pull Systems in Office & Service Environments
 
Kanban in 4 easy steps
Kanban in 4 easy steps Kanban in 4 easy steps
Kanban in 4 easy steps
 
Total Productive Maintenance
Total Productive MaintenanceTotal Productive Maintenance
Total Productive Maintenance
 

Similaire à Kanban system presentation

Kanban system in fast food industry
Kanban system in fast food industryKanban system in fast food industry
Kanban system in fast food industry
Jessica Allison
 
Presentation kanban
Presentation kanbanPresentation kanban
Presentation kanban
Nasir Shakil
 

Similaire à Kanban system presentation (20)

Kanban System .pdf
Kanban System .pdfKanban System .pdf
Kanban System .pdf
 
Kanban system (presentation for blog ) 2003
Kanban system (presentation for blog ) 2003Kanban system (presentation for blog ) 2003
Kanban system (presentation for blog ) 2003
 
Kanban system (presentation for blog )
Kanban system (presentation for blog )Kanban system (presentation for blog )
Kanban system (presentation for blog )
 
kanban1-140329054118-phpapp02.ppt
kanban1-140329054118-phpapp02.pptkanban1-140329054118-phpapp02.ppt
kanban1-140329054118-phpapp02.ppt
 
KANBAN
KANBANKANBAN
KANBAN
 
Kanban
KanbanKanban
Kanban
 
Kanban
KanbanKanban
Kanban
 
Kanban
KanbanKanban
Kanban
 
Kanban systems
Kanban systemsKanban systems
Kanban systems
 
Intro to pull kan ban
Intro to pull kan banIntro to pull kan ban
Intro to pull kan ban
 
Kanban presentation
Kanban presentationKanban presentation
Kanban presentation
 
Connectivity Solutions SAP Kanban Training
Connectivity Solutions SAP Kanban Training Connectivity Solutions SAP Kanban Training
Connectivity Solutions SAP Kanban Training
 
Lean, Just-in-time, and Toyota Production System
Lean, Just-in-time,and Toyota Production SystemLean, Just-in-time,and Toyota Production System
Lean, Just-in-time, and Toyota Production System
 
Kanban system in fast food industry
Kanban system in fast food industryKanban system in fast food industry
Kanban system in fast food industry
 
Kanban presentation
Kanban presentationKanban presentation
Kanban presentation
 
Lean Management and Kanban System
Lean Management and Kanban SystemLean Management and Kanban System
Lean Management and Kanban System
 
Presentation kanban
Presentation kanbanPresentation kanban
Presentation kanban
 
Supermarket delivery system
Supermarket delivery systemSupermarket delivery system
Supermarket delivery system
 
PPC Chapter 8.pdf
PPC Chapter 8.pdfPPC Chapter 8.pdf
PPC Chapter 8.pdf
 
Kanban Lean Thinking - Fakeeh quality week
Kanban Lean Thinking - Fakeeh quality weekKanban Lean Thinking - Fakeeh quality week
Kanban Lean Thinking - Fakeeh quality week
 

Plus de Ãbhîläşh Mãňü

Plus de Ãbhîläşh Mãňü (20)

When you want to make voucher entries in tally
When you want to make voucher entries in tallyWhen you want to make voucher entries in tally
When you want to make voucher entries in tally
 
Fii and-fdi-in-india
Fii and-fdi-in-indiaFii and-fdi-in-india
Fii and-fdi-in-india
 
Human resource accounting
Human resource accountingHuman resource accounting
Human resource accounting
 
Fund flow statement
Fund flow statementFund flow statement
Fund flow statement
 
Accounting for price level changes
Accounting for price level changesAccounting for price level changes
Accounting for price level changes
 
Value chain analysis
Value chain analysisValue chain analysis
Value chain analysis
 
sales and distribution
sales and distribution sales and distribution
sales and distribution
 
sales and distribution
sales and distribution sales and distribution
sales and distribution
 
Salesand distribution
Salesand distributionSalesand distribution
Salesand distribution
 
sales management
sales managementsales management
sales management
 
Distribution stratergies
Distribution stratergiesDistribution stratergies
Distribution stratergies
 
venture capital
venture capitalventure capital
venture capital
 
Maintenance managemant
Maintenance managemantMaintenance managemant
Maintenance managemant
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Just in-time
Just in-timeJust in-time
Just in-time
 
Inventory management
Inventory managementInventory management
Inventory management
 
Entrepreneurship process
Entrepreneurship processEntrepreneurship process
Entrepreneurship process
 
business data processing
business data processingbusiness data processing
business data processing
 
Business law
Business lawBusiness law
Business law
 
Trial balance and errors
Trial balance and errorsTrial balance and errors
Trial balance and errors
 

Dernier

Dernier (20)

Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 

Kanban system presentation

  • 2. Push and Pull method of Work Flow Push Method: A method in which production of the item begins in advance of customer needs. Example: A buffet where food is prepared in advance. Pull Method: A method in which customer demand activates production of the service or item. Example: A restaurant where food is only prepared when orders are placed. Lean systems use the pull method of work flow.
  • 3. KANBAN Kanban means “card” or “visible record” in Japanese & refers to cards used to control the flow of production through a factory. KANBAN is a PULL System .
  • 4. General Operating Rules: 1. Each container must have a card. 2. The assembly line always withdraws materials from fabrication (pull system). 3. Containers of parts must never be removed from a storage area without a kanban being posted on the receiving post. 4. The containers should always contain the same number of good parts. The use of nonstandard containers or irregularly filled containers disrupts the production flow of the assembly line. 5. Only nondefective parts should be passed along. 6. Total production should not exceed the total amount authorized on the kanbans in the system.
  • 5. –看板 Kanban cards limit excess work in progress • –看板 Kanban literally means “visual card,” “signboard,” or “billboard.” • Toyota originally used Kanban cards to limit the amount of inventory tied up in “work in progress” on a manufacturing floor • Not only is excess inventory waste, time spent producing it is time that could be expended elsewhere • Kanban cards act as a form of “currency” representing how WIP is allowed in a system. 5
  • 6. “Pull” system to avoid overproduction • Milk example – weekly batch or daily purchase? • Next purchase triggered when you start using the only bottle of milk you have. • Not an example of zero-inventory, but still a pull system. • Because of demand uncertainty and lead-times, in many cases inventory is necessary to allow for smooth production. • Hence TPS follows the supermarket model or keeping a small amount in stock. As soon as customers take products away, they are replenished. • Each demand instance triggers a part being pulled from upstream. • The triggering mechanism is called “Kanban” which means cards, signboard or a poster. 6
  • 7. Kanban system • At Toyota, empty bin (a kanban) is send upstream after a demand instance. • It is a signal to refill it with a specific number of parts or send back a card with detailed information about the part location. • Even today, one can see Kanban cards and bins moving on the shop-floor. • Instead of using sophisticated computer scheduling techniques, this is a simple, effective and visual system of managing and ensuring the product flow and JIT production system. 7
  • 8. Kanban system • Gas tank example. • Toyota philosophy about kanban: “Kanban is an organized system of inventory buffers and as per TPS (Toyota Production System ), inventory is waste, whether it is in pull system or push system. So kanban is something you strive to get rid of.” • Toyota uses kanban to force process improvements. 8
  • 9. Kanban Flow Kanban Rule: No Kanban card, no production or movement of material Can accommodate 10%-20% of changes in planned production Can easily extend to suppliers (supplier Kanban)
  • 10. Kanban card forKanban card for product 1product 1 Kanban card forKanban card for product 2product 2 FabricationFabrication cellcell OO11 OO22 OO33 OO22 StorageStorage areaarea Empty containersEmpty containers Full containersFull containers Assembly line 1Assembly line 1 Assembly line 2Assembly line 2 The Single-Card Kanban System Receiving postReceiving post
  • 11. StorageStorage areaarea Empty containersEmpty containers Full containersFull containers Kanban card forKanban card for product 1product 1 Kanban card forKanban card for product 2product 2 FabricationFabrication cellcell OO11 OO22 OO33 OO22 Assembly line 1Assembly line 1 Assembly line 2Assembly line 2 Receiving postReceiving post The Single-Card Kanban System
  • 12. StorageStorage areaarea Empty containersEmpty containers Full containersFull containers Kanban card forKanban card for product 1product 1 Kanban card forKanban card for product 2product 2 FabricationFabrication cellcell OO11 OO22 OO33 OO22 Assembly line 1Assembly line 1 Assembly line 2Assembly line 2 Receiving postReceiving post The Single-Card Kanban System
  • 13. StorageStorage areaarea Empty containersEmpty containers Full containersFull containers Kanban card forKanban card for product 1product 1 Kanban card forKanban card for product 2product 2 FabricationFabrication cellcell OO11 OO22 OO33 OO22 Assembly line 1Assembly line 1 Assembly line 2Assembly line 2 Receiving postReceiving post The Single-Card Kanban System
  • 14. StorageStorage areaarea Empty containersEmpty containers Full containersFull containers Kanban card forKanban card for product 1product 1 Kanban card forKanban card for product 2product 2 FabricationFabrication cellcell OO11 OO22 OO33 OO22 Assembly line 1Assembly line 1 Assembly line 2Assembly line 2 Receiving postReceiving post The Single-Card Kanban System
  • 15. StorageStorage areaarea Empty containersEmpty containers Full containersFull containers Kanban card forKanban card for product 1product 1 Kanban card forKanban card for product 2product 2 FabricationFabrication cellcell OO11 OO22 OO33 OO22 Assembly line 1Assembly line 1 Assembly line 2Assembly line 2 Receiving postReceiving post The Single-Card Kanban System
  • 16. StorageStorage areaarea Empty containersEmpty containers Full containersFull containers Kanban card forKanban card for product 1product 1 Kanban card forKanban card for product 2product 2 FabricationFabrication cellcell OO11 OO22 OO33 OO22 Assembly line 1Assembly line 1 Assembly line 2Assembly line 2 Receiving postReceiving post The Single-Card Kanban System
  • 17. A TYPICAL KANBAN CARD We can also modify this Kanban card to suit our requirement the best . This card acts like a visual control to replenish the required quantity . PARTVISUAL INSERTPHOTO HERE PARTNO PARTDESCRIPTION PRODUCTION LINE WORK STATION NO LINESIDERACK NO LINESIDELOAD QTY REPLINSHMENT TRIGGER QTY REPLINSHMENT FROMLOCATION REPLINSHMENT QTY KANBAN CARD
  • 18. Thank you so much for viewing ……….. Let me know your feedbacks at : industrialenggconsultancy@gmail.com

Notes de l'éditeur

  1. The process starts with a card for the first product.
  2. The fabricated product moves to full container storage.
  3. Full containers are moved to final assembly.
  4. The same process is followed for product 2.