SlideShare une entreprise Scribd logo
1  sur  33
Télécharger pour lire hors ligne
Rate of Return Analysis
Dr. Mohsin Siddique
Assistant Professor
msiddique@sharjah.ac.ae
Ext: 29431
Date:
Engineering Economics
University of Sharjah
Dept. of Civil and Env. Engg.
Outcome of Today’s Lecture
2
After completing this lecture…
The students should be able to:
Evaluate project cash flows with the internal rate of
return measure
Plot a project’s present worth against the interest rate
Use an incremental rate of return analysis to evaluate
competing alternatives
3
Part I
Techniques for Cash Flow Analysis
4
Present Worth Analysis
Annual Cash Flow Analysis
Rate of Return Analysis
Incremental Analysis
OtherTechniques:
FutureWorth Analysis
Benefit-Cost Ratio Analysis
Payback Period Analysis
Rate of Return Analysis
5
Internal Rate of Return
Calculating Rate of Return
Rate of Return Analysis
Incremental Cash Flow Analysis
Internal Rate of Return (IRR) Lender’s Viewpoint
6
The interest rate on the balance of a loan such that the
unpaid loan balance equals zero when the final payment is
made
Internal Rate of Return (IRR)
7
Simple Definition:
Given a cash flow stream, rate of return (a.k.a. IRR) is the
interest rate i* at which the benefits are equivalent to the
costs:
NPW=0
PW of benefits - PW of costs = 0
PW of benefits = PW of costs
PW of benefits / PW of costs = 1
EUAB -EUAC = 0
Internal Rate of Return (IRR)
8
Suppose you have the following cash flow stream.You invest $700,
and then receive $100, $175, $250, and $325 at the end of years 1, 2,
3 and 4 respectively.What is the IRR for your investment?
700 = 100/(1+i) + 175/(1+i)2+ 250/(1+i)3+ 325/(1+i)4
Solving for i >>> It turns out that i* = 6.09 %
Calculating Internal Rate of Return
9
Ways to find the IRR:
1. Compound InterestTables (you
may need to use interpolation)
2.Trial-and-error
3. Numerically (Excel’s IRR function,
MATLAB, or other root finding
methods)
4. Graphically
If you have a CFS with an investment
(-P) followed by benefits (non negative)
from the investment:
The graph of NPW versus i will have
the same general form.
It will decrease at a decreasing rate
and have a value 0 at some unique
value i*.
Where the graph has a value 0
defines the IRR.
Example 1: Solution Using Interest Tables
10
Given the following CFD, find i*
PWB/PWC = 1
1252(P/A,i,5)/5000 = 1
(P/A,i,5) = 5000/1252 = 3.993
From Compound Interest
Tables:
i=8%
Example 2: Solution Using Interest Tables
11
An investment resulted in the following
cash flow. Compute the rate of return.
Solve the equation by trial and error
Example 3: Graphical Solution
12
Given the following CFS, find i*
PW of costs = PW of benefits
100=20/(1+i)+30/(1+i)2+20/(1+i)3+
40/(1+i)4+40/(1+i)5
NPW=-100+20/(1+i)+30/(1+i)2+
20/(1+i)3+40/(1+i)4+40/(1+i)5
Problem: 7-1
13
$125 = $10 (P/A, i%, 6) + $10 (P/G, i%, 6)
LHS=RHS
at 12%, RHS= $10 (4.111) + $10 (8.930) = $130.4
at 15%, RHS= $10 (3.784) + $10 (7.937) = $117.2
i* = 12% + (3%) ((130.4 – 125).(130.4-117.2)) = 13.23%
$125
$10
$20
$30
$40
$50
$60
Problem 7-8
14
Try i = 7%
PWB=[$200 (3.387) - $50 (4.795)] (0.9346) = 409.03
Try i = 8%
PWB=[$200 (3.312) - $50 (4.650)] (0.9259) = $398.08
i* = 7% + (1%) [($409.03 - $400)/($409.03 - $398.04)]
= 7.82%
PWC=$400
PWB = [$200 (P/A, i%, 4) - $50 (P/G,
i%, 4)] (P/F, i%, 1)
PWC=PWB
Problem 7-10
15
PWC=$500 + $100 (P/F, i%, 1)
PWB= $300 (P/A, i%, 2) (P/F, i%, 1) + $400 (P/F, i%, 4) + $500 (P/F, i%, 5)
PWC-PWB=0
Problem 7-10
16
Try i = 30%
PWC=$500 + $100 (0.7692)= $576.92
PWB=$300 (1.361) (0.7692) + $400 (0.6501) + $500 (0.2693)=
$588.75
PWC-PWB = 11.83
Try i = 35%
PWC=$500 + $100 (0.7407)= $574.07
PWB=$300 (1.289) (0.7407) + $400 (0.3011) + $500 (0.2230) =
$518.37
PWC-PWB= 55.70
Rate of Return, i* = 30% + (5%) [11.83/55.70)= 31.06%
Exact Answer: 30.81%
17
Part II
Rate of Return (RoR) Analysis
18
Example statements about a project:
The net present worth of the project is $32,000
The equivalent uniform annual benefit is $2,800
The project will produce a 23% rate of return
The third statement is perhaps most widely understood.
Rate of return analysis is probably the most frequently
used analysis technique in industry.
Its major advantage is that it provides a figure of merit
that is readily understood.
Rate of Return (RoR) Analysis
19
Rate of return analysis has another advantage:With NPW or
EUAB one must choose an interest rate for using in the
calculations.
This choice may possibly be difficult or controversial.
With RoR analysis no (exterior) interest rate is introduced
into the calculations.
Instead, we compute a RoR from the CFS.
Warning: Relying only on RoR is not always a good idea.
Rate of Return (RoR) Analysis
20
Example: Which of the following two investment options
would you select?
Option 1:
Invest $2,000 today. At the end of years 1, 2, and 3 get $100,
$100, and $500 profit; at the end of year 4, you get $2,200.
Option 2:
Invest $2,000 today. At the end of years 1, 2, and 3 get $100,
$100, and $100 profit; at the end of year 4, you get $2,000.
Rate of Return (RoR) Analysis
21
Find out the implicit interest rate you would be receiving; that is,
solve for the interest rate in which the PW of benefits are equal to
your payments $2,000.
Option 1:
2000 = 100/(1+i)1+ 100/(1+i)2+ 500/(1+i)3+ 2200/(1+i)4
IRR: i= 10.78%
Option 2:
2000 = 100/(1+i)1+ 100/(1+i)2+ 100/(1+i)3+ 2000/(1+i)4
IRR: i= 3.82%
Which deal would you prefer?
The Minimum Attractive Rate of Return (MARR)
22
The MARR is a minimum return the company will accept
on the money it invests
The MARR is usually calculated by financial analysts in the
company and provided to those who evaluate projects
It is the same as the interest rate used for PresentWorth
and AnnualWorth analysis.
Incremental Cash Flow Analysis (ΔCFS)
23
Suppose you must choose between projects A or B.
We can rewrite the CFS for B as B = A + (B –A).
In this representation B has two CFS components:
1. the same CFS as A, and
2. the incremental component (B –A).
B is preferred to A when the IRR on the difference (B–A)
exceeds the MARR.
Thus, to choose one between B and A, IRR analysis is done by
computing the IRR on the incremental investment (B-A)
between the projects.
Incremental Cash Flow Analysis (ΔCFS)
24
Steps to conduct ∆CFS on two CFS’s:
1. Number them CFS1and CFS2, with CFS1 having the largest initial
(year 0) cost (in absolute value)
2. Compute ∆CFS = CFS1–CFS2 (It’s year 0 entry must be negative)
3. Find the IRR for ∆CFS, say ∆IRR
4. If ∆IRR ≥ MARR, choose CFS1; if not, choose CFS2
Example:There are two cash flows: (-20,28) and (-10,15) and MARR
= 6%.
1.CFS1= (-20,28), CFS2= (-10,15)
2. ∆CFS = CFS1-CFS2=(-10,13)
3. ∆IRR = 30%.
4. ∆IRR > MARR => we choose CFS1= (-20,28)
Incremental Cash Flow Analysis (ΔCFS)
25
In summary, we compute the CFS for the difference
between the projects by subtracting the cash flow for the
lower investment-cost project (A) from that of the higher
investment-cost project (B).
Then, the decision rule is as follows:
IF ∆IRRB-A> MARR, select B
IF ∆IRRB-A= MARR, select either A or B
IF ΔIRRB-A< MARR, select A
Here, B-A is an investment increment.
Why We Use ∆IRR in IRR analysis?
26
Although the rate of return of A is higher than B, B got $8 return
from the $20 investment and A only got $5 return from $10
investment.
Project B: you put $20 in project B to get a return $8.
Project A: you put $10 in project A (and $10 in your pocket) to get a
return $5.
From this example, we know that we can’t evaluate two projects by
comparing the IRRs of the projects. Instead, we use ∆IRR and MARR
to make the decision.
Problem 7-47
27
Problem 7-47
28
Year A B (B- A)
0 -$2,000 -$2,800 -$800
1- 3 +$800 +$1,100 +$300
Computed ROR 9.7% 8.7% 6.1%
The rate of return on the increment (B - A) exceeds the
Minimum Attractive Rate of Return (MARR), therefore the
higher cost alternative B should be selected.
Problem 7-51
29
Problem 7-51
30
Year X Y X- Y
0 -$5,000 -$5,000 $0
1 -$3,000 +$2,000 -$5,000
2 +$4,000 +$2,000 +$2,000
3 +$4,000 +$2,000 +$2,000
4 +$4,000 +$2,000 +$2,000
Computed ROR 16.9% 21.9% 9.7%
Since X-Y difference between alternatives is desirable, select
Alternative X.
Summary
31
RoR analysis is often used but not always well understood
by practitioners
RoR can be computationally difficult manually; a
spreadsheet model helps reduce solution time
If an exact RoR is not necessary, use the PW or AW
methods
Use incremental analysis when using IRR
Practice Problem
32
7-49, 7-50 and 7-52
33
ThankYou
Feel Free to Contact
msiddique@sharjah.ac.ae

Contenu connexe

Tendances

Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 2 full slides to students
Chapter 2   full slides to studentsChapter 2   full slides to students
Chapter 2 full slides to studentsSaad Ul Fataah
 
Buku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blankBuku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blankAhmad Muhaimin
 
Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsBich Lien Pham
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solutionHaris Hassan
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3bAbdulaziz AlSuwaidi
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Unit no.04 project economics
Unit no.04 project economicsUnit no.04 project economics
Unit no.04 project economicsRAMCHANDRA KODAM
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methodsBich Lien Pham
 
3. eng. cost and estimation
3. eng. cost and estimation3. eng. cost and estimation
3. eng. cost and estimationMohsin Siddique
 
Engineering economics
Engineering economicsEngineering economics
Engineering economicsDeepak Kumar
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio methodAli Juma Albahrani
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisionsBich Lien Pham
 

Tendances (20)

Lecture blank - 8-9
Lecture  blank - 8-9Lecture  blank - 8-9
Lecture blank - 8-9
 
10. depreciation
10. depreciation10. depreciation
10. depreciation
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 2 full slides to students
Chapter 2   full slides to studentsChapter 2   full slides to students
Chapter 2 full slides to students
 
Buku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blankBuku enginering economi edisi ke 7 leland blank
Buku enginering economi edisi ke 7 leland blank
 
Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assets
 
Engineering Economics Paper solution
Engineering Economics Paper solutionEngineering Economics Paper solution
Engineering Economics Paper solution
 
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
Chapter 6&amp;7  annual worth analysis &amp; ror   lo3bChapter 6&amp;7  annual worth analysis &amp; ror   lo3b
Chapter 6&amp;7 annual worth analysis &amp; ror lo3b
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Unit no.04 project economics
Unit no.04 project economicsUnit no.04 project economics
Unit no.04 project economics
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
 
3. eng. cost and estimation
3. eng. cost and estimation3. eng. cost and estimation
3. eng. cost and estimation
 
Engineering economics
Engineering economicsEngineering economics
Engineering economics
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on money
 
Engineering economics (1)
Engineering economics (1)Engineering economics (1)
Engineering economics (1)
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
 

Similaire à 8 150316005531-conversion-gate01

SE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptx
SE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptxSE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptx
SE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptxYassine751298
 
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxSheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxlesleyryder69361
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Landry De Chabe
 
Capital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptxCapital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptxRachanaSingh78
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04rajeevgupta
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingpremarhea
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...Aquamarine Emerald
 
economy Chapter5_by louy Al hami
economy Chapter5_by louy Al hami economy Chapter5_by louy Al hami
economy Chapter5_by louy Al hami Louy Alhamy
 
INVESTMENT DECISION AND RELATED PROBLEM
INVESTMENT DECISION AND RELATED PROBLEMINVESTMENT DECISION AND RELATED PROBLEM
INVESTMENT DECISION AND RELATED PROBLEMMohammed Jasir PV
 
Business Finance Chapter 8
Business Finance Chapter 8Business Finance Chapter 8
Business Finance Chapter 8Tinku Kumar
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation newBsgr Planmin
 
Chapter 09 Capital Budgeting
Chapter 09 Capital BudgetingChapter 09 Capital Budgeting
Chapter 09 Capital BudgetingAlamgir Alwani
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternativesBich Lien Pham
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.pptSanthoshK757191
 
Capital Budgeting- Q.pptx
Capital Budgeting- Q.pptxCapital Budgeting- Q.pptx
Capital Budgeting- Q.pptxMohd Sarim
 

Similaire à 8 150316005531-conversion-gate01 (20)

SE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptx
SE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptxSE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptx
SE 307-CHAPTER_7_RATE_OF_RETURN_ANALYSIS_new.pptx
 
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docxSheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
Sheet4Assignment 1 LASA # 2—Capital Budgeting TechniquesSheet1So.docx
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1
 
Capital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptxCapital_Budgeting.Chp 4 Unit2.pptx
Capital_Budgeting.Chp 4 Unit2.pptx
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Capital Budgeting Rules 04
Capital Budgeting Rules 04Capital Budgeting Rules 04
Capital Budgeting Rules 04
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
 
economy Chapter5_by louy Al hami
economy Chapter5_by louy Al hami economy Chapter5_by louy Al hami
economy Chapter5_by louy Al hami
 
INVESTMENT DECISION AND RELATED PROBLEM
INVESTMENT DECISION AND RELATED PROBLEMINVESTMENT DECISION AND RELATED PROBLEM
INVESTMENT DECISION AND RELATED PROBLEM
 
Evaluation
EvaluationEvaluation
Evaluation
 
Business Finance Chapter 8
Business Finance Chapter 8Business Finance Chapter 8
Business Finance Chapter 8
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Lecture cash flow evaluation new
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
 
Chapter 09 Capital Budgeting
Chapter 09 Capital BudgetingChapter 09 Capital Budgeting
Chapter 09 Capital Budgeting
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.ppt
 
Capital Budgeting- Q.pptx
Capital Budgeting- Q.pptxCapital Budgeting- Q.pptx
Capital Budgeting- Q.pptx
 
Capital budgeting unit_2
Capital budgeting unit_2Capital budgeting unit_2
Capital budgeting unit_2
 

Plus de abidiqbal55

Network theorems chapter 9
Network theorems chapter 9Network theorems chapter 9
Network theorems chapter 9abidiqbal55
 
Method of analysis chapter 8
Method of analysis chapter 8Method of analysis chapter 8
Method of analysis chapter 8abidiqbal55
 
Method of analysis chapter 8 final
Method of analysis chapter 8 finalMethod of analysis chapter 8 final
Method of analysis chapter 8 finalabidiqbal55
 
Inductors chapter 11
Inductors chapter 11Inductors chapter 11
Inductors chapter 11abidiqbal55
 
Capacitor chapter 10
Capacitor chapter 10Capacitor chapter 10
Capacitor chapter 10abidiqbal55
 
Ac series parallel chapter 13
Ac series parallel chapter 13Ac series parallel chapter 13
Ac series parallel chapter 13abidiqbal55
 
10 150316005543-conversion-gate01
10 150316005543-conversion-gate0110 150316005543-conversion-gate01
10 150316005543-conversion-gate01abidiqbal55
 
9 150316005537-conversion-gate01
9 150316005537-conversion-gate019 150316005537-conversion-gate01
9 150316005537-conversion-gate01abidiqbal55
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01abidiqbal55
 
6 150316005521-conversion-gate01
6 150316005521-conversion-gate016 150316005521-conversion-gate01
6 150316005521-conversion-gate01abidiqbal55
 
5moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate015moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate01abidiqbal55
 
5 150316005456-conversion-gate01
5 150316005456-conversion-gate015 150316005456-conversion-gate01
5 150316005456-conversion-gate01abidiqbal55
 
4 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate014 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate01abidiqbal55
 
3 150316005311-conversion-gate01
3 150316005311-conversion-gate013 150316005311-conversion-gate01
3 150316005311-conversion-gate01abidiqbal55
 
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate012 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01abidiqbal55
 
1 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate011 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate01abidiqbal55
 

Plus de abidiqbal55 (18)

Lecture 1
Lecture 1Lecture 1
Lecture 1
 
Network theorems chapter 9
Network theorems chapter 9Network theorems chapter 9
Network theorems chapter 9
 
Method of analysis chapter 8
Method of analysis chapter 8Method of analysis chapter 8
Method of analysis chapter 8
 
Method of analysis chapter 8 final
Method of analysis chapter 8 finalMethod of analysis chapter 8 final
Method of analysis chapter 8 final
 
Inductors chapter 11
Inductors chapter 11Inductors chapter 11
Inductors chapter 11
 
Capacitor chapter 10
Capacitor chapter 10Capacitor chapter 10
Capacitor chapter 10
 
Ac series parallel chapter 13
Ac series parallel chapter 13Ac series parallel chapter 13
Ac series parallel chapter 13
 
Chap5 engeco
Chap5 engecoChap5 engeco
Chap5 engeco
 
10 150316005543-conversion-gate01
10 150316005543-conversion-gate0110 150316005543-conversion-gate01
10 150316005543-conversion-gate01
 
9 150316005537-conversion-gate01
9 150316005537-conversion-gate019 150316005537-conversion-gate01
9 150316005537-conversion-gate01
 
7 150316005526-conversion-gate01
7 150316005526-conversion-gate017 150316005526-conversion-gate01
7 150316005526-conversion-gate01
 
6 150316005521-conversion-gate01
6 150316005521-conversion-gate016 150316005521-conversion-gate01
6 150316005521-conversion-gate01
 
5moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate015moreinterestformulas 150316005456-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate01
 
5 150316005456-conversion-gate01
5 150316005456-conversion-gate015 150316005456-conversion-gate01
5 150316005456-conversion-gate01
 
4 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate014 interestandequivalence-150316005410-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate01
 
3 150316005311-conversion-gate01
3 150316005311-conversion-gate013 150316005311-conversion-gate01
3 150316005311-conversion-gate01
 
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate012 decisionmakingandprofessionalethics-150316005212-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
 
1 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate011 introductiontoengineeringeconomics-150316005104-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate01
 

Dernier

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 

Dernier (20)

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 

8 150316005531-conversion-gate01

  • 1. Rate of Return Analysis Dr. Mohsin Siddique Assistant Professor msiddique@sharjah.ac.ae Ext: 29431 Date: Engineering Economics University of Sharjah Dept. of Civil and Env. Engg.
  • 2. Outcome of Today’s Lecture 2 After completing this lecture… The students should be able to: Evaluate project cash flows with the internal rate of return measure Plot a project’s present worth against the interest rate Use an incremental rate of return analysis to evaluate competing alternatives
  • 4. Techniques for Cash Flow Analysis 4 Present Worth Analysis Annual Cash Flow Analysis Rate of Return Analysis Incremental Analysis OtherTechniques: FutureWorth Analysis Benefit-Cost Ratio Analysis Payback Period Analysis
  • 5. Rate of Return Analysis 5 Internal Rate of Return Calculating Rate of Return Rate of Return Analysis Incremental Cash Flow Analysis
  • 6. Internal Rate of Return (IRR) Lender’s Viewpoint 6 The interest rate on the balance of a loan such that the unpaid loan balance equals zero when the final payment is made
  • 7. Internal Rate of Return (IRR) 7 Simple Definition: Given a cash flow stream, rate of return (a.k.a. IRR) is the interest rate i* at which the benefits are equivalent to the costs: NPW=0 PW of benefits - PW of costs = 0 PW of benefits = PW of costs PW of benefits / PW of costs = 1 EUAB -EUAC = 0
  • 8. Internal Rate of Return (IRR) 8 Suppose you have the following cash flow stream.You invest $700, and then receive $100, $175, $250, and $325 at the end of years 1, 2, 3 and 4 respectively.What is the IRR for your investment? 700 = 100/(1+i) + 175/(1+i)2+ 250/(1+i)3+ 325/(1+i)4 Solving for i >>> It turns out that i* = 6.09 %
  • 9. Calculating Internal Rate of Return 9 Ways to find the IRR: 1. Compound InterestTables (you may need to use interpolation) 2.Trial-and-error 3. Numerically (Excel’s IRR function, MATLAB, or other root finding methods) 4. Graphically If you have a CFS with an investment (-P) followed by benefits (non negative) from the investment: The graph of NPW versus i will have the same general form. It will decrease at a decreasing rate and have a value 0 at some unique value i*. Where the graph has a value 0 defines the IRR.
  • 10. Example 1: Solution Using Interest Tables 10 Given the following CFD, find i* PWB/PWC = 1 1252(P/A,i,5)/5000 = 1 (P/A,i,5) = 5000/1252 = 3.993 From Compound Interest Tables: i=8%
  • 11. Example 2: Solution Using Interest Tables 11 An investment resulted in the following cash flow. Compute the rate of return. Solve the equation by trial and error
  • 12. Example 3: Graphical Solution 12 Given the following CFS, find i* PW of costs = PW of benefits 100=20/(1+i)+30/(1+i)2+20/(1+i)3+ 40/(1+i)4+40/(1+i)5 NPW=-100+20/(1+i)+30/(1+i)2+ 20/(1+i)3+40/(1+i)4+40/(1+i)5
  • 13. Problem: 7-1 13 $125 = $10 (P/A, i%, 6) + $10 (P/G, i%, 6) LHS=RHS at 12%, RHS= $10 (4.111) + $10 (8.930) = $130.4 at 15%, RHS= $10 (3.784) + $10 (7.937) = $117.2 i* = 12% + (3%) ((130.4 – 125).(130.4-117.2)) = 13.23% $125 $10 $20 $30 $40 $50 $60
  • 14. Problem 7-8 14 Try i = 7% PWB=[$200 (3.387) - $50 (4.795)] (0.9346) = 409.03 Try i = 8% PWB=[$200 (3.312) - $50 (4.650)] (0.9259) = $398.08 i* = 7% + (1%) [($409.03 - $400)/($409.03 - $398.04)] = 7.82% PWC=$400 PWB = [$200 (P/A, i%, 4) - $50 (P/G, i%, 4)] (P/F, i%, 1) PWC=PWB
  • 15. Problem 7-10 15 PWC=$500 + $100 (P/F, i%, 1) PWB= $300 (P/A, i%, 2) (P/F, i%, 1) + $400 (P/F, i%, 4) + $500 (P/F, i%, 5) PWC-PWB=0
  • 16. Problem 7-10 16 Try i = 30% PWC=$500 + $100 (0.7692)= $576.92 PWB=$300 (1.361) (0.7692) + $400 (0.6501) + $500 (0.2693)= $588.75 PWC-PWB = 11.83 Try i = 35% PWC=$500 + $100 (0.7407)= $574.07 PWB=$300 (1.289) (0.7407) + $400 (0.3011) + $500 (0.2230) = $518.37 PWC-PWB= 55.70 Rate of Return, i* = 30% + (5%) [11.83/55.70)= 31.06% Exact Answer: 30.81%
  • 18. Rate of Return (RoR) Analysis 18 Example statements about a project: The net present worth of the project is $32,000 The equivalent uniform annual benefit is $2,800 The project will produce a 23% rate of return The third statement is perhaps most widely understood. Rate of return analysis is probably the most frequently used analysis technique in industry. Its major advantage is that it provides a figure of merit that is readily understood.
  • 19. Rate of Return (RoR) Analysis 19 Rate of return analysis has another advantage:With NPW or EUAB one must choose an interest rate for using in the calculations. This choice may possibly be difficult or controversial. With RoR analysis no (exterior) interest rate is introduced into the calculations. Instead, we compute a RoR from the CFS. Warning: Relying only on RoR is not always a good idea.
  • 20. Rate of Return (RoR) Analysis 20 Example: Which of the following two investment options would you select? Option 1: Invest $2,000 today. At the end of years 1, 2, and 3 get $100, $100, and $500 profit; at the end of year 4, you get $2,200. Option 2: Invest $2,000 today. At the end of years 1, 2, and 3 get $100, $100, and $100 profit; at the end of year 4, you get $2,000.
  • 21. Rate of Return (RoR) Analysis 21 Find out the implicit interest rate you would be receiving; that is, solve for the interest rate in which the PW of benefits are equal to your payments $2,000. Option 1: 2000 = 100/(1+i)1+ 100/(1+i)2+ 500/(1+i)3+ 2200/(1+i)4 IRR: i= 10.78% Option 2: 2000 = 100/(1+i)1+ 100/(1+i)2+ 100/(1+i)3+ 2000/(1+i)4 IRR: i= 3.82% Which deal would you prefer?
  • 22. The Minimum Attractive Rate of Return (MARR) 22 The MARR is a minimum return the company will accept on the money it invests The MARR is usually calculated by financial analysts in the company and provided to those who evaluate projects It is the same as the interest rate used for PresentWorth and AnnualWorth analysis.
  • 23. Incremental Cash Flow Analysis (ΔCFS) 23 Suppose you must choose between projects A or B. We can rewrite the CFS for B as B = A + (B –A). In this representation B has two CFS components: 1. the same CFS as A, and 2. the incremental component (B –A). B is preferred to A when the IRR on the difference (B–A) exceeds the MARR. Thus, to choose one between B and A, IRR analysis is done by computing the IRR on the incremental investment (B-A) between the projects.
  • 24. Incremental Cash Flow Analysis (ΔCFS) 24 Steps to conduct ∆CFS on two CFS’s: 1. Number them CFS1and CFS2, with CFS1 having the largest initial (year 0) cost (in absolute value) 2. Compute ∆CFS = CFS1–CFS2 (It’s year 0 entry must be negative) 3. Find the IRR for ∆CFS, say ∆IRR 4. If ∆IRR ≥ MARR, choose CFS1; if not, choose CFS2 Example:There are two cash flows: (-20,28) and (-10,15) and MARR = 6%. 1.CFS1= (-20,28), CFS2= (-10,15) 2. ∆CFS = CFS1-CFS2=(-10,13) 3. ∆IRR = 30%. 4. ∆IRR > MARR => we choose CFS1= (-20,28)
  • 25. Incremental Cash Flow Analysis (ΔCFS) 25 In summary, we compute the CFS for the difference between the projects by subtracting the cash flow for the lower investment-cost project (A) from that of the higher investment-cost project (B). Then, the decision rule is as follows: IF ∆IRRB-A> MARR, select B IF ∆IRRB-A= MARR, select either A or B IF ΔIRRB-A< MARR, select A Here, B-A is an investment increment.
  • 26. Why We Use ∆IRR in IRR analysis? 26 Although the rate of return of A is higher than B, B got $8 return from the $20 investment and A only got $5 return from $10 investment. Project B: you put $20 in project B to get a return $8. Project A: you put $10 in project A (and $10 in your pocket) to get a return $5. From this example, we know that we can’t evaluate two projects by comparing the IRRs of the projects. Instead, we use ∆IRR and MARR to make the decision.
  • 28. Problem 7-47 28 Year A B (B- A) 0 -$2,000 -$2,800 -$800 1- 3 +$800 +$1,100 +$300 Computed ROR 9.7% 8.7% 6.1% The rate of return on the increment (B - A) exceeds the Minimum Attractive Rate of Return (MARR), therefore the higher cost alternative B should be selected.
  • 30. Problem 7-51 30 Year X Y X- Y 0 -$5,000 -$5,000 $0 1 -$3,000 +$2,000 -$5,000 2 +$4,000 +$2,000 +$2,000 3 +$4,000 +$2,000 +$2,000 4 +$4,000 +$2,000 +$2,000 Computed ROR 16.9% 21.9% 9.7% Since X-Y difference between alternatives is desirable, select Alternative X.
  • 31. Summary 31 RoR analysis is often used but not always well understood by practitioners RoR can be computationally difficult manually; a spreadsheet model helps reduce solution time If an exact RoR is not necessary, use the PW or AW methods Use incremental analysis when using IRR
  • 33. 33 ThankYou Feel Free to Contact msiddique@sharjah.ac.ae