SlideShare une entreprise Scribd logo
1  sur  88
Télécharger pour lire hors ligne
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


                                                                      CONTENTS




        INTRODUCTION ..............................................................................................6
        EXECUTIVE SUMMARY .....................................................................................8
        PROJECT AT A GLANCE .................................................................................. 13
        1       NEED AND JUSTIFICATION FOR THE PROJECT ....................................15
         1.1     INTRODUCTION ............................................................................................................................. 15
         1.2     POWER SCENARIO IN INDIA .......................................................................................................... 16
         1.3     JUSTIFICATION FOR THE PROJECT .................................................................................................. 22
        2       DETAILS ABOUT THE PROPOSED PROJECT LOCATION IN ANANTAPUR
                DISTRICT ............................................................................................ 25
         2.1     INTRODUCTION ............................................................................................................................. 25
         2.2     AREA AND POPULATION IN ANANTAPUR DISTRICT ................................................................... 25
         2.3     RAINFALL AND CLIMATE ............................................................................................................. 26
         2.4     TEMPERATURE.............................................................................................................................. 26
         2.5     PROPOSED PROJECT LOCATION.................................................................................................. 27
         2.6     LAND REQUIREMENT AND LAYOUT OF THE PROPOSED PROJECT .............................................. 29
         2.7     LAND AVAILABILITY AND ACQUISITION FOR THE PROJECT ....................................................... 30
        3       RADIATION DATA AND PROJECTED POWER GENERATION FROM THE
                PROJECT ACTIVITY .............................................................................31
         3.1     SIMULATION REPORT OF THE POWER PLANT ............................................................................. 33
        4       SELECTION OF TECHNOLOGY ..............................................................37
         4.1     EXISTING SOLAR PHOTOVOLTAIC TECHNOLOGIES .................................................................. 37
         4.2     THIN FILM MODULES ................................................................................................................... 38
         4.3     COMPARISON BETWEEN CRYSTALLINE, THIN FILM AND CPV.................................................. 38
                 TECHNOLOGIES ........................................................................................................................... 38
         4.4     CONCLUSION ON SELECTION OF TECHNOLOGY ......................................................................... 39
        5       POWER PLANT DESIGN CRITERIA .......................................................40
         5.1     DESIGN AND SIMULATION PROJECTIONS BY PVSYST ............................................................ 40
         5.2     PV POWER PLANT ENERGY PRODUCTION ................................................................................. 41
         5.3     PV POWER PLANT CAPACITY FACTOR ......................................................................................... 41
         5.4     SELECTION OF INVERTER AND COMPONENTS ........................................................................... 42
         5.5     SELECTION OF MONITORING SYSTEM ....................................................................................... 42
         5.6     DESIGN CRITERIA FOR CABLES AND JUNCTION BOXES AND ................................................... 43
        6       DESCRIPTION OF MAJOR COMPONETS OF THE POWER PLANT ............44
         6.1     SOLAR PV MODULES ................................................................................................................... 45
         6.2     CENTRAL INVERTORS .................................................................................................................. 45
         6.1     MODULE MOUNTING SYSTEM ...................................................................................................... 47
         6.1     GRID CONNECTED EQUIPMENTS ................................................................................................. 48
         6.2     MONITORING SYSTEM ................................................................................................................ 48
         6.3     CABLES AND CONNECTORS......................................................................................................... 49
         6.4     BUILDINGS HOUSING FOR ELECTRONICS (POWER HOUSE) ..................................................... 50
         6.5     OTHER FACILITIES INCLUDING WATER ...................................................................................... 51
        7       SPECIFICATION OF MAIN PLANT AND EQUIPMENT .............................52
        8       POWER EVACUATION AND INTERFACING WITH GRID ........................58
         8.1     POWER EVACUATION SYSTEM .................................................................................................... 58
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


         8.2     TRANSFORMERS........................................................................................................................... 59
         8.3     HT, LV & 11KV METERING PANEL .......................................................................................... 60
         8.4     CABLES ........................................................................................................................................ 61
         8.5     LT POWER CABLES ..................................................................................................................... 61
         8.6     CONTROL CABLES ........................................................................................................................ 61
         8.7     POWER EVACUATION CABLE ...................................................................................................... 62
         8.8     GRID SYNCHRONIZATION SCHEME............................................................................................ 62
        9        OPERATION AND MAINTENANCE REQUIREMENTS ...............................63
         9.1     DC SIDE OF THE POWER PLANT ................................................................................................. 63
         9.2     AC SIDE OF THE POWER PLANT .................................................................................................. 63
         9.3     MODE OF OPERATION ................................................................................................................. 64
         9.4     MAINTENANCE REQUIREMENTS .................................................................................................. 65
         9.5     SPARE PARTS MANAGEMENT SYSTEM ......................................................................................... 65
         9.6     MAINTENANCE OF O & M MANUALS.......................................................................................... 66
         9.7     OPERATION & MAINTENANCE ORGANIZATION OF THE PLANT ................................................. 66
         9.8     TRAINING ..................................................................................................................................... 67
        10       ENVIRONMENTAL PROTECTION AND WASTE MANAGEMENT ...............68
        11       OPERATION & MAINTENANCE ORGANIZATION OF THE POWER PLANT… 70
         11.1    TRAINING ..................................................................................................................................... 71
         11.2    PLANT OPERATION ORGANIZATION CHART .............................................................................. 72
         11.3    PROJECT IMPLEMENTATION STRATEGY ...................................................................................... 73
         11.4    PROJECT DEVELOPMENT ............................................................................................................. 73
         11.5    FINALIZATION OF THE EQUIPMENTS AND CONTRACTS ............................................................ 73
         11.6    PROCUREMENT AND CONSTRUCTION......................................................................................... 74
         11.7    ERECTION AND COMMISSIONING PHASE .................................................................................. 75
        12       PROJECT COST ESTIMATE AND FINANCIAL ANALYSIS ........................76
         12.1    PLANT OPERATION ...................................................................................................................... 77
         12.2    SALABLE ELECTRICITY ................................................................................................................ 78
         12.3    SALE PRICE OF ELECTRICITY...................................................................................................... 78
         12.4    SALE PRICE OF CARBON CREDITS .............................................................................................. 78

      LIST OF TABLES:

      Table    1-1: Installed Capacity in MW in India at the End of 10th Plan ___________________17
      Table    1-2: Installed Capacity in MW in India as of 31 Mar 2010 _______________________17
      Table    1-3: Actual Power Supply Position _______________________________________________18
      Table    1-4: Capacity Addition during 11th Plan (As Per Planning Commission) __________18
      Table    1-5: Likely Power Supply Position at the End of 2010-12 ________________________18
      Table    1-6: Installed capacity of all states as on 31.03.2010 (in MW) __________________19
      Table    1-7: Installed Capacity in MW in Andhra Pradesh at the End of 10th Plan ________19
      Table    1-8: Installed Capacity in MW in Andhra Pradesh as of 31 Mar 2010 ____________20
      Table    1-9: Actual Power Supply Position _______________________________________________20
      Table    1-10: Projects planned for 11th Plan _____________________________________________20
      Table    1-11: Likely Power Supply Position at the End of 2010-12 _______________________21
      Table    1-12: Likely Capacity Addition During 11th Plan __________________________________21
      Table    1-13: Peak & Energy Table ______________________________________________________21
      Table    3-1: Temperature details considered for design: ________________________________32
      Table    7-1: Bill of materials _____________________________________________________________52
      Table    7-2: Technical specification of proposed solar modules at STC __________________53
      Table    7-3: Specifications of module mounting structure _______________________________53
      Table    7-4: Cables speficification _______________________________________________________54
      Table    7-5: Invertors specification ______________________________________________________54
      Table    7-6: Transformer specification at 33 kV side ____________________________________55
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      Table   7-7: Transformer specification for grid interfacing at 33/132 kV _________________56
      Table   7-8: Monitoring system specification ____________________________________________57
      Table   12-1: Project Cost Estimate _____________________________________________________76
      Table   12-2: Assumptions supporting financial projections _____________________________80
      Table   12-3: Estimation of Depreciation ________________________________________________82
      Table   12-4: Projected Profitability,Balance Sheet,CF, IRR ands WC ____________________84
      Table   12-5: Project Debt Service Coverage Ratio (DSCR) ______________________________88

      List of Figures:

      Figure   1:      Location map of Anatapur district in India: ............................................................. 28
      Figure   2:      Map showing proposed project site within Anantapur ......................................... 28
      Figure   3:      Typical module mounting structure: .......................................................................... 47
      Figure   4:      Grid-Connect equipments ............................................................................................... 48


      Annexure

          1         Project site Photographs
          2         Land ownership details of the proposed project
          3         Contour map of the project site
          4         Schematic diagram showing 5MWp Solar PV Plant Layout
          5         Schematic of Control Room Layout
          6         Schematic of earthing layout
          7         Power Evacuation Scheme 5MWp to 33/132 kV substation
          8         Incorporation certificate of Saisudhir Energy Limited
          9         Memorandum and Articles of Association of Saisudhir Energy Limited
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      ABBREVIATIONS


      General


             AB           Air Breaker

            ACB           Air Circuit Breaker

             AC           Alternate current

           ACSR           Aluminum Conductors Steel Reinforced

            BOS           Balance of the System

            CO2           Carbon Dioxide

            CIS           Copper Indium Selenium

             CT           Current Transformer

            DAS           Data Acquisition System

             DC           Direct Current

             DP           Double Pole

            DPR           Detailed Project Report

       APTRANSCO          Andhra Pradesh Transmission Corporation

             HT           High Tension

             LT           Low Tension

             LV           Low Voltage

           MNRE           Ministry of New and Renewable Energy

            kWh           Kilo Watt Hour

            NO2           Nitrous Oxide

                          Main Combiner Box / Miniature Circuit
            MCB
                          Breaker

            MFM           Multi Function Meters

             PLF          Plant Load Factor

            PFC           Power Finance Corporation

            PPA           Power Purchase Agreement

             PV           Photo Voltaic

             PT           Power Transformer

            SEB           State Electricity Board
                                                                                                          4
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



             SO2          Sulphur Dioxide

              SP          Single Pole

             VCB          Vacuum Circuit Breaker

            XLPE          Cross Linked Polyethylene


      Units


      %               Percentage

      ˚C              Degree Centigrade

      H               Hour

      Ha              Hectare

      Kg              Kilogram

      kV              Kilo-Volt

      kW              kilo Watt

      kWe             kilo Watt electrical

      kWp             kilo Watt peak

      Lt              Liter

      M               Meter

      m2              Square meter

      m3              Cubic meter

      Mg              milli gram

      Mm              milli meter

      MW              Mega Watt

      MWe             Mega Watt electrical

      Tons            Tons




                                                                                                          5
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                                               INTRODUCTION

      As the world broadens its portfolio of power options to meet growing energy

      demands and increasingly stringent environmental concerns, solar power is

      emerging as an attractive option. Of all the routes for conversion of solar into

      useful energy, direct conversion of sunlight to electricity through solar

      photovoltaic       technology       is   well    accepted.      Solar    photovoltaic       has     been

      recognized as an important route for generation of substantial quantities of grid

      quality power by utilizing the light energy of solar radiation.



      SAISUDHIR         Energy      Limited      (SSEL)      a    group     company        of   SAISUDHIR

      Infrastructures Limited is intent to develop solar photovoltaic power plant of

      (SPV) power project at Veerapuram village of Anatapur district, in the State of

      Andhra Pradesh.

      SSEL intend to setup grid interactive solar power project based on Copper

      Indium Selenium (CIS) modules also called as thin film modules. The project

      activity is to install grid connected 5 MW solar power project. The full power

      rating of the solar power plant shall be 5.0 +5% and -0% MW DC at standard

      test conditions (STC) of 1000 W/sq meter sunlight and 25 degree centigrade.

      The project is selected to install CIS modules which comply with IEC 61646 for

      quality and IEC 61730 safety standards.



      The project site proposed is in Veerapura village of Anatapur district in Andhra

      Pradesh. The total land area required for the project is about 25 acres. The

      company already acquired the land required for the project.



                                                                                                             6
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      The project envisages an investment of approx. Rs 650 million for the

      installation of 5 MW solar power plant which would provide quantity power with

      a power purchase price signed with NTPC's Vidyut Vyapar Nigam Ltd or NVVN

      which is the designated Nodal Agency under Jawaharlal Nehru National Solar

      Mission (JNNSM) for procuring the solar power by entering into a Power

      Purchase Agreement (PPA) with Solar Power Generation Project Developers. In

      addition, the Power Project would generate direct and indirect employment

      opportunities; create of civic facilities for establishment of ancillary industries.




                                                                                                          7
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                                         EXECUTIVE SUMMARY

      1.       The average per capita consumption of energy in India is around 612 kW,

               which is much lower than that of the developed countries like USA,

               Europe, Australia, Japan etc. However, this figure is expected to rise

               sharply due to high economic growth and rapid industrialization. Energy

               is a necessity and sustainable renewable energy is a vital link in

               industrialization and development of India. A transition from conventional

               energy systems to those based on renewable resources is necessary to

               meet     the    ever     increasing      demand        for   energy      and     to   address

               environmental concerns.



      2.       Thus, the present scenario needs for addition of major renewable energy

               sources of energy for overall economic development of the country.


      3.       Solar    Photovoltaic      Power plant operates on the principle of                        the

               photoelectric phenomenon - direct conversion of light to electricity. The

               solar radiation incident upon a silicon-based semiconductor photovoltaic

               cell produces direct electric current.


      4.       Photovoltaic cells are integrated into modules with a voltage of 6 - 12 V;

               the electrically interconnected modules form solar systems with an output

               voltage of 230 V.


      5.       Saisudhir Energy Limited (SSEL) is an SAISUDHIR Infrastructures group

               company. Saisudhir Infrastructures Limited is one of the fastest growing

               ISO 9000 infrastructure companies having nationwide network for its


                                                                                                           8
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


               Construction       services      in    the    field    of    Water,      Power,      Buildings

               Infrastructures, Solid Waste Management and Irrigation etc.,


      6.       SAISUDHIR builds the high-voltage electric transmission system that

               helps to keep the lights on, business running and communities strong.

               The company has played a major role in the complete preparation,

               analysis, design, construction management and inspection of energy

               structures, high voltage transmission lines and distribution systems

               across the country.


      7.       SAISUDHIR has an in-house capability for designing Transmission Line

               Towers & Switchyard Structures.


      8.       SAISUDHIR energy proposed to install a 5 MW Solar Photovoltaic (SPV)

               power plant under phase I of Jawaharlal Nehru National Solar Mission

               (JNNSM) of new grid connected projects. The generated electricity will be

               sold to NVVN with a long term Power Purchase Agreement (PPA). The

               company has already entered into a PPA agreement with NVVN.


      9.       This report highlights the details of the proposed power generation

               scheme, site facilities, solar radiation in the proposed site location and

               water, evacuation of generated power, features of main plant and

               equipment        including       the     inverter      system,        electrical     systems,

               environmental aspects, estimate of capital cost and the financial analysis

               and the schedule for project implementation.



      10.      The proposed 5 MW power plant would require about 25 acres of land.

               The company already acquired the land required for the project.
                                                                                                           9
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      11.      The plant is designed with an availability factor of 100%. The plant will

               generate about 9.63 million units per year at the module array terminals,

               after the losses in the system about 9.32 million units will be available at

               the grid terminals which will amount to a plant load factor of about

               21.28 %. The project site was selected on the basis of:

                   •   Availability of good solar insulation

                   •   Availability of uninhabited land at a reasonable cost

                   •   Availability of stable grid near to the project site

                   •   High Power Demand in the State

                   •   Availability of good infrastructural facility including road and rail

                       connection



      12.      The power generated at 11kV from the power plant will be stepped-up to

               33 kV level and connected to APPCL sub-station at Raydurg, which is

               about 10 km from the project site. The total power produced is envisaged

               as 9.63 million units at the PV array. After the losses the net available

               energy for supplying to the grid is about 9.32 million units. Thus, the net

               salable electricity to the grid works out to 9.32 million units. The plant is

               envisaged to operate 365 days at a plant load factor (PLF) of 21.28%.

               The transmission line required from the SSEL 5 MW plant site to the

               substation will be laid by the project promoters.



      13.      The power plant will comprise of IEC 61646 modules of CIS thin film

               modules with aluminum frame of 41,600 no’s , which will work out to 5

               MW +5% and -0% for accounting the DC losses (each module of 130 Wp

               capacity), 5200 nos of PV system mounting structures (strings) made out

                                                                                                          10
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


               of MS galvanized steel with 8 module structure, fixed tilt type, 80 nos of

               array junction boxes, Power conditioning unit (inverter) 10 nos of 500

               kVA, 1.25 MVA transformer 5 nos, 6.5 MVA transformer 1 no for

               interfacing with grid, LT and HT Panel and protection and metering,

               cables and earthing system set.


      14.      The net energy sales from the plant workout 9.32 million units. The

               entire energy will be sold to NVVN through APTransco grid. The financial

               analysis is made with a levelised power purchase price of Rs. 12.00 /

               kWh.


      15.      The total cost of generation includes the insurance cost, repairs and

               maintenance, cost of administration, salaries and wages, cost of utilities.


      16.      The total installed project cost including civil, mechanical and electrical,

               preoperative expenses and the contingency works out to Rs 650 million.


      17.      The solar power plant reduces contribution to atmospheric carbon-di-

               oxide vis-à-vis fossil fuel generation. The project helps solar radiation

               into useful electricity, adding to the sustainability of the project and the

               local environment. Thus, the project meets the UNFCCC norms set to

               qualify for obtaining CDM benefits. The project is envisaged to register

               with UNFCCC for availing the CDM benefits.


      18.      The term loan requirement from the financial institution works out to

               455.00 (70% of the project cost) million. It is assumed that the term

               loan will be repaid in 13 years in quarterly installments, with an initial



                                                                                                          11
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


               moratorium period of 1 year. The equity from SSIL will be Rs 195.00

               million. The interest rate for the term loan is considered as 11.50 %.



      19.      The depreciation computed is on straight line basis.



      20.      Income tax at the rate of 32.45% % is considered in the financial

               analysis. The benefits available under Section 80 IA, for power projects

               have been taken into consideration in the financial analysis while

               calculating the income tax liability. The post tax Project Internal Rate of

               Return (IRR) works out to 13.63% and Post tax Equity IRR works out to

               18.89%.


      21.      The project also generates Clean Development Mechanism (CDM)

               revenue with reduction at 1% in the subsequent years. If we consider the

               revenue from sale of carbon credits with a minimum price of € 12 per

               CER, the project generates additional revenue of about INR 7.5 million,

               which will add to the profitability of the project.


      22.      Minimum Project Debt Service Coverage Ratio (DSCR) will work out to

               1.35 and average DSCR will work out to 1.65.




                                                                                                          12
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                                        PROJECT AT A GLANCE

   1     Project Authority                                     SAISUDHIR Energy Limited

                                                               5 MW +5% and –0% Solar Photovoltaic
   2     Project Installed Capacity
                                                               Power Plant
                                                               T.Veerapuram   Village, Anantapur
   3     Selected Location
                                                               District.

   4     Nearest Major Towns                                   Anantapur

   5     Seismic Zone                                          Zone-4 as per IS 1893-1984.
                                                               Well Connected, buses are Operated by
   6     Access by Bus                                         Andhrapradesh State Road Transport
                                                               Corporation (APSRTC)
   7     Nearest Airport                                       Bangalore International Airport (BIAL)

                                                               Anantapur Railway Station is on the
   8     Access by Rail
                                                               Bangalore-Hydrabad line.
                                                               Copper Indium Selenium (CIS) Thin film
   9     Solar module type
                                                               modules

  10     Capacity of each module                               130 Wp

  11     No. of modules                                        41,600 Nos

  12     PV System Mounting Structure type                     MS Galvanised(> 70 micron)

  13     Module mounting structure type                        8 Module mounting structure

  14     No. of module mounting structures                     5,200 Nos.

  15     No. of Array junction boxes                           80 Nos.

         Power conditioning Unit (Invertor)
  16                                                           500 kVA
         capacity
  17     Power conditioning Unit specifications                Input voltage range 450-900V

  18     No. of invertors                                      10 Nos.

  19     Invertors make                                        AEG or equivalent

  20     1.25 MVA Transformer                                  5 Nos

  21     6.5 MVA Transformer                                   1 No.


                                                                                                          13
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



  22     LT Panel with protection & metering                   5 Nos.

  23     LT Panel with protection & metering                   2 Nos

  24     Cables and earthing systems                           1 set

  25     Gross Power Generation (kW)                           5000 +5% and -0%

         Net exportable power at 33 kV to
  27                                                           9.32 million units
         nearest grid substation(kW)

  28     Power Purchase tariff with NVVN in `                  12.00

  29     Plant Load Factor                                     21.28%

  30     Total Project cost (Rs. In millions)                  650
         Preliminary       and    pre-operative
  31                                            30.00
         expenses (Rs. In millions)
         Equity from Promoters
  32                                            195.00
         (Rs. In millions)
         Term loan from Financial Institutions
  33                                            455.00
         (Rs in millions)
  34     Interest on term loan                                  11.50%

  35     Project IRR (post tax)                                 13.63 %

  36     Equity IRR (post tax)                                  18.89 %

  37     Plant Commissioning Date                               Dec 2011
         Land requirement                                      25 Acres
  38
                  • Module area                                51,089 m2
                                                               The entire station will be laid at a
  39     Land Development
                                                               uniform level.
 TECHNICAL FEATURES
                                                               Through 33/132kV Transmission lines
  40     Power Evacuation                                      Raydurg substation located 10km from
                                                               project site.
 OTHER FACILITIES
                                                               Through EPC (Engineering, Procurement
  41     Mode of Implementation
                                                               and Construction) or thru split contracts.
                                                               Twelve (12) months from the date of
  42     Project Time Frame
                                                               signing PPA with NVVN
 PROJECT COST
                                                               Present day cost including, financing
         Project Cost                                          charges and margin money.
  43
                                                                Rs.650 million.

                                                                                                          14
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




      1 NEED AND JUSTIFICATION FOR THE PROJECT


      1.1 Introduction


      India with 17 percent of the world population and just 0.8 per cent of the

      world’s known oil and natural gas resources is going to face serious energy

      challenges       in   the    coming      decades.      Besides      energy      independence,       the

      devastating impact of climate change has become an issue of critical

      importance. Energy production using fossil fuels is the major contributor to

      greenhouse gas emissions. Hence, transition to a low-carbon energy economy is

      the real solution for mitigating the impact of climate change.



      India has huge potential for producing electricity from renewable sources. The

      achievement so far is about 17,222 (as on 31.03.2010) MW, as against global

      installed capacity of approximately 2,00,000 MW of renewable electricity

      generation. While India’s achievement is commendable, it is necessary for us to

      keep pace with the fast growth in developed countries.



      There are three imperatives that necessitate a transition to a sustainable energy

      system in the 21st century: They are Climate change and its potentially

      disastrous consequences. Peaking of production, depletion and extinction of

      fossil fuels and Energy Autonomy and Independence.



      The single biggest reason for global warming is the burning of fossil fuels. So

      the solution lies in effecting an accelerated transition to a low carbon energy

      economy,       which means           large scale development of                 renewable       energy.

      Fortunately there are several emerging technologies that will facilitate this.
                                                                                                          15
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      Peaking of production of all fossil fuels (viz. oil, gas and coal) in the next two

      decades and gradual extinction of these resources is an accepted scientific fact.

      Even assuming that they would be available, India, which is already dependent

      on their import, would become more and more import dependent. The financial

      implications of large scale imports would destroy our economy and necessitate

      strategies to move towards energy autonomy or independence.


      The conversion of solar energy to electricity displaces an equivalent amount of

      grid power, which would otherwise be produced by grid connected fossil fuel

      dominated power plants. Grid power is comprised of a large share of fossil fuel

      based generation systems.


      1.2 Power Scenario in India

      As per Section73(a) of the Indian Electricity Act-2003, CEA has been carrying

      out periodic electric power survey to project state-wise and region-wise power

      plans together with assessment of peaking power and energy surpluses /

      deficits. The estimate prepared by the CEA is revised and updated from time to

      time taking into account the actual growth rates achieved. The Reports and

      National Electricity Plan prepared by CEA i.e. Report on (17th) Electric Power

      Survey of India published in August 2007, Draft National Electricity Plan-

      Transmission published in 2005 and Power Scenario at a glance published in

      April 2010 have been referred for carrying out demand analysis of the State of

      Andhra Pradesh and other regions.


      Load forecast/Availability of power for 2003-2012 for the State of Eastern,

      Northern, Western, Southern and North-Eastern region have been given below

      which shows that surplus amount of power will be available for the North-East
                                                                                                          16
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      region while other regions i.e. Northern, Western and Southern will expect a

      shortage of power at the end of 11th Plan i.e. 2011-12. Actual power scenario

      of are as follows in terms of:

                   •      Installed Capacity

                   •      Actual Supply/Generation.

                   •      Likely capacity addition.

                       Table 1-: Installed Capacity in MW in India at the End of 10th Plan

                            INSTALLED CAPACITY (AT THE END OF 10TH PLAN) (FIGURES IN MW)
       Sector              Hydro                                                 Thermal    Nuclear     R.E.S. Total
                                   Coal                     Gas      Diesel         Total              (MNRE)
       STATE            26,005.7     41,731.6        3,729.8         604.6         46,066       0.0     975.7 73,047.4
       PRIVATE           1,230.0      4,241.4        4,183.0         597.1        9,021.5       0.0    6,784.8 17,036.3
       CENTRAL             7,418     25,118.3        5,809.0              0.0   30,927.3    3,900.0        0.0 42,245.3
       TOTAL            34,653.7     71,091.3      13,721.8        1,201.8      86,014.8    3,900.0    7,760.5 1,32,329

                         Table 1-: Installed Capacity in MW in India as of 31 Mar 2010

                                          INSTALLED CAPACITY AS ON 31.03.2010 (FIGURES IN MW)
          Sector         Hydro                   Thermal                                     Nuclear      R.E.S        Total
                                       Coal         Gas          Diesel           Total                  (MNRE)
       STATE           27,065.00   44,977.00    4,046.12      602.61       49,625.73        0.00       2,701.12          79,391.85
       PRIVATE         1,233.00    8,056.38     6,307.50      597.14       14,961.02        0.00       12,819.99         29,014.01
       CENTRAL         8,565.40    31,165.00    6,702.23      0.00         37,867.23        4,560.00   0.00              50,992.63
       TOTAL           36,863.40   84,198.38    17,055.85     1,199.75     1,02,453.98      4,560.00   15,521.11       1,59,398.49




                                                                                                                          17
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


                                         Table 1-: Actual Power Supply Position

                                             ACTUAL POWER SUPPLY POSITION
       9 Period        Peak          Peak Met     Peak         Peak       Energy      Energy Avail-Energy     Energy
                       Demand        (MW)         Deficit/     Deficit/   Requi-      ability (MU) Deficit/   Deficit/
                       (MW)                       Surplus      Surplus    rment                    Surplus    Surplus
                                                  (MW)         (%)        (MU)                     (MU)       (%)
       9TH PLAN END    78,441        69,189       -9,252       -11.8      5,22,537    4,83,350     -39,187    -7.5
       2002-03         81,492        71,547       -9,945       -12.2      5,45,983    4,97,890     -48,093    -8.8
       2003-04         84,574        75,066       -9,508       -11.2      5,59,264    5,19,398     -39,866    -7.1
       2004-05         87,906        77,652       -10,254      -11.7      5,91,373    5,48,115     -43,258    -7.3
       2005-06         93,255        81,792       -11,463      -12.3      6,31,757    5,78,819     -52,938    -8.4
       2006-07         1,00,715      86,818       -13,897      -13.8      6,90,587    6,24,495     -66,092    -9.6
       2007-08         1,08,866      90,793       -18,073      -16.6      7,39,345    6,66,007     -73,338    -9.9
       2008-09         1,09,809      96,685       -13,124      -12        7,74,324    6,89,021     -85,303    -11
       APR,09          1,18,472      1,02,725     -15,748      -13.3      8,30,300    7,46,493     -83,807    -10.1
       MAR ,2010       1,18,472      1,02,725     -15,748      -13.3      76,493      67,513       -8,980     -11.7

      NOTE :- PEAK DEMAND - 121891 MW , ENERGY REQUIREMENT - 794561 MU FOR THE YEAR
      2008-2009(AS PER 17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY
      POSITION IN THE MONTH(S) - MARCH & OCTOBER

      SOURCE:- DMLF DIVISION



                  Table 1-: Capacity Addition during 11th Plan (As Per Planning Commission)

            CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET)
       Sector     Hydro    Thermal                             Nuclear Wind Total
                           Coal      Gas      Diesel Total
       STATE        3,482.0       19,985.0      3,316.4      0.0      23,301.4       0.0        0.0      26,783.4
       PRIVATE      3,491.0       9,515.0       2,037.0      0.0      11,552.0       0.0        0.0      15,043.0
       CENTRAL      8,654.0       23,350.0      1,490.0      0.0      24,840.0       3,380.0    0.0      36,874.0
       TOTAL        15,627.0      52,850.0      6,843.4      0.0      59,693.4       3,380.0    0.0      78700.4*
      NOTE :- * AS PER ACTUAL ORDERS , THE CAPACITY COMES TO 78900.4 MW


                           Table 1-: Likely Power Supply Position at the End of 2010-12

              LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12 (DEMAND AS PER 17TH EPS)


        Period     Peak           Peak      Peak     Peak    Energy Requi- Energy                  Energy      Energy
                  Demand           Met     Deficit/ Deficit/  rment (MU)     Avail-                Deficit/    Deficit/
                   (MW)           (MW)     Surplus Surplus                   ability              Surplus      Surplus
                                            (MW)     (%)                     (MU)                   (MU)        (%)
       2011-12      1,52,746      1,42,765   -9,981     -6.5 9,68,659     9,48,836               -19,823      -2.0




                                                                                                                     18
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                            Table 1-: Installed capacity of all states as on 31.03.2010 (in MW)

                     S.No          STATES   HYDRO                         THERMAL                           NUCLEAR           R.E.S      TOTAL
                     .                                    COAL         GAS     DIESEL           TOTAL
                      1     CHANDIGARH            46.74      27.09        15.32          0.00      42.41         8.84             0.00       97.99
                      2     DELHI             581.62       2,602.96      808.01          0.00    3,410.97      122.08             0.00    4,114.67
                      3     HARYANA         1,327.68       3,017.99      535.29          3.92    3,557.20      109.16            76.50    5,070.54
                      4     H.P.            1,539.94        118.30        61.88          0.13     180.31        34.08           275.83    2,030.16
                      5     J&K             1,480.53        263.70       304.14          8.94     576.78        77.00           129.33    2,263.64
                      6     PUNJAB          2,962.89       3,208.19      263.92          0.00    3,472.11      208.04           278.90    6,921.94
                      7     RAJASTHAN       1,454.80       4,149.48      665.03          0.00    4,814.51      573.00           926.15    7,768.46
                      8     U.P.            1,597.42       6,912.84      549.97          0.00    7,462.81      335.72           587.70    9,983.65
                      9 UTTRAKHAND          1,919.18         261.26       69.35          0.00      330.61       22.28           132.92    2,404.99
                      10 CHATTISGARH          120.00       4,383.00        0.00          0.00    4,383.00       47.52           218.95    4,769.47
                      11 GUJARAT              772.00       7,008.89    3,894.49         17.48   10,920.86      559.32         1,655.91   13,908.09
                      12 M.P.               3,223.66       4,282.10      257.18          0.00    4,539.28      273.24           287.86    8,324.04
                      13 MAHARASHTRA        3,331.84      11,203.05    3,715.93          0.00   14,918.98      690.14         2,437.97   21,378.93
                      14 GOA                       0.00     277.03        48.00          0.00     325.03        25.80            30.05      380.88
                      15 D&D                       0.00      19.04         4.20          0.00      23.24         7.38             0.00       30.62
                      16 D&N HAVAILI            0.00          22.04       27.10          0.00       49.14        8.46             0.00       57.60
                      17 A.P.               3,617.53       6,259.88    2,580.40         36.80    8,877.08      214.28           700.51   13,409.40
                      18 KARNATAKA          3,599.80       3,902.67      220.00     234.42       4,357.09      195.36         2,234.09   10,386.34
                      19 KERALA             1,781.50         765.38      533.58     256.44       1,555.40       78.10           138.76    3,553.76
                      20 T.N                2,108.20       5,519.81    1,026.30     411.66       6,957.77      478.50         4,865.51   14,409.98
                      21 P.CHURY                0.00         207.01       32.50          0.00      239.51       16.28             0.00      255.79
                      22 D.V.C                193.26       3,563.10       90.00          0.00    3,653.10        0.00             0.00    3,846.36
                      23 BIHAR                129.43       1,661.70        0.00          0.00    1,661.70        0.00            54.60    1,845.73
                      24 JHARKHAND            200.93       1,737.88        0.00          0.00    1,737.88        0.00             4.05    1,942.86
                      25 ORISSA             2,166.93       1,828.10        0.00          0.00    1,828.10        0.00            64.30    4,059.33
                      26 SIKKIM                75.27          68.10        0.00          5.00       73.10        0.00            47.11      195.48
                      27 W.BENGAL           1,116.30       6,756.34      100.00         12.20    6,868.54        0.00           164.70    8,149.54
                      28 ARP.P.                97.57          0.00        21.05         15.88      36.93         0.00            67.42      201.92
                      29 ASSAM                429.72         60.00       441.32         20.69     522.01         0.00            27.11      978.84
                      30 MANIPUR               80.98           0.00       25.96         45.41      71.37         0.00             5.45      157.80
                      31 MEGHALYA             230.58           0.00       25.96          2.05      28.01         0.00            31.03      289.62
                      32 MIZORAM                  34.31        0.00       16.28         51.86      68.14         0.00            28.47      130.92
                      33 NAGALAND                 53.32        0.00       19.19          2.00      21.19         0.00            28.67      103.18
                      34 TRIPURA                  62.37        0.00      160.84          4.85     165.69         0.00            16.01      244.07
                      35 A&N ISLAND                0.00        0.00        0.00         60.05      60.05         0.00             5.25       65.30
                      36 LAKSHDEEP                 0.00        0.00        0.00          9.97       9.97         0.00             0.00        9.97



                Table 1-: Installed Capacity in MW in Andhra Pradesh at the End of 10th Plan


                              INSTALLED CAPACITY (AT THE END OF 10th PLAN (FIGURES IN MW)
       Sector             Hydro     Thermal                               Nuclear   R.E.S.                                                           Total
                                    Coal      Gas     Diesel   Total                (MNRE)
       STATE              3,582.6           3,132.5              272.3            0.0             3,404.8               0.0              103.0       7,090.3
       PRIVATE            3.8               0.0                  1,603.4          36.8            1,640.2               0.0              283.4       1,927.4
       CENTRAL            0.0               2,378.0              0.0              0.0             2,378.0               152.5            0.0         2,530.5
       TOTAL              3,586.3           5,510.5              1,875.7          36.8            7,423.0               152.5            386.4       11,548.2




                                                                                                                                                        19
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


                 Table 1-: Installed Capacity in MW in Andhra Pradesh as of 31 Mar 2010

           Sector           Hydro                                  Thermal                                         Nuclear       R.E.S.         Total
                                                Coal             Gas    Diesel                   Total                          (MNRE)
       STATE             3,617.53          3,882.50           0.00         0.00             3,882.50         0.00                    188.43      7,688.46
       PRIVATE           0.00              0.00               2,580.40     36.80            2,617.20         0.00                    512.08      3,129.28
       CENTRAL           0.00              2,377.38           0.00         0.00             2,377.38         214.28                    0.00      2,591.66
       TOTAL             3,617.53          6,259.88           2,580.40     36.80            8,877.08         214.28                  700.51     13,409.40

                                                    Table 1-: Actual Power Supply Position

                                             Peak             Peak        Peak           Peak            Energy      Energy    Energy   Energy
                         Period             Demand             Met       deficit/       Deficit/         Requi-      Avail-    Deficit/ Deficit/
                                             (MW)             (MW)       Surplus       Surplus (         rment       ability   Surplus Surplus (
                                                                          (MW)           %)               (MU)        (MU)      (MU)      %)
                 9TH PLAN END                    8,585         6,873       -1,712           -19.9         48,394      44,302    -4,092         -8.5
                 2002-03                         8,491         6,858       -1,633           -19.2         47,258      44,049    -3,209         -6.8
                 2003-04                         8,679         7,769         -910           -10.5         48,080      46,680    -1,400         -2.9
                 2004-05                         8,093         7,903         -190            -2.3         50,416      50,061      -355         -0.7
                 2005-06                         8,999         8,542         -457            -5.1         53,030      52,332      -698         -1.3
                 2006-07                       10,208          8,641       -1,567           -15.4         60,964      58,280    -2,684         -4.4
                 2007-08                       10,048          9,162         -886            -8.8         64,139      61,511    -2,628         -4.1
                 2008-2009                     10,823          9,997         -826            -7.6         71,592      66,754    -4,838         -6.8
                 APR,09-MAR10                  12,135         10,880       -1,255           -10.3         79,014      73,784    -5,230         -6.6
                 MAR 2010                      12,135         10,880       -1,255           -10.3          7,929       7,040      -889        -11.2

                                                   Table 1-: Projects planned for 11th Plan

                          PROJECTS PLANNED FOR XITH PLAN (STATE/PRIVATE/CENTRAL SECTOR) INCLUDING BEST
                                                                                                                       CAPACITY LIKELY YEAR /
                 EFFORT           PROJECT                        AGENCY             STATUS                 TYPE        (MW)     DATE OF
                 PROJECTS                                                                                                       COMMISSIONIN
                                                                                                                                G
                     1            SIMHADRI-EXT U-3,4             NTPC               Under Construction     COAL        1,000     2010-12
                     2            SUB TOTAL –Central sector                                                            1,000
                     3            JURALA PRIYA      U1,2         APGENCO            Commissioned           HYDRO       78        31.08.2008
                     4            JURALA PRIYA      U,3          APGENCO            Commissioned           HYDRO       39        07.06.2009
                     5            JURALA PRIYA      U 4-6        APGENCO            Under Construction     HYDRO       117       2010-11
                     6            NAGARJUNA SAGAR TR             APGENCO            Under Construction     HYDRO       50        2010-12
                     7            PULICHINTALA                   APID               Under Construction     HYDRO       120       2010-12
                     8            RAYALSEEMA U4                  APGENCO            Commissioned           COAL        210       2007-08
                     9            RAYALSEEMA ST III U5           APGENCO            Under Construction     COAL        210       2010-11
                     10           VIJAYWADA TPP ST-IV,U1         APGENCO            Commissioned           COAL        500       8.10.2009
                     11           KOTHAGUDEM ST-V                APGENCO            Under Construction     COAL        500       2011-12
                     12           KAKTIYA TPP                    APGENCO            Under Construction     COAL        500       2010-11
                     13           SUB TOTAL –state sector                                                              2,324
                     14           KONASEEMA                      OAKWELL            Commissioned           GAS/LNG     280       3.5.2009
                     15           KONASEEMA                      OAKWELL            Under Construction     GAS/LNG     165       2010-11
                     16           GAUTAMI                        GAUTAMI POW        Commissioned           GAS/LNG     464       3.5.2009
                     17           KONDAPALLI PH II               LANCO              Commissioned           GAS         233       5.12.2009
                     18           KONDAPALLI PH II               LANCO              Under Construction     LNG         133       2010-11
                     19           SUB TOTAL -private sector                                                            1,275
                     20           TOTAL (AP)                                                                           4,719




                                                                                                                                                20
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                           Table 1-: Likely Power Supply Position at the End of 2010-12

                       LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS)
                      Period    Peak    Peak    Peak     Peak     Energy   Energy  Energy    Energy
                      2011-   Demand 12,357 -2,364 Deficit/
                               14,721   Met     eficit/  -16.1    Requi-
                                                                 89,032     Avail-
                                                                           80,338  Deficit/
                                                                                    -8,694   Deficit/
                                                                                               -9.8
                        12


                             Table 1-: Likely Capacity Addition During 11th Plan

                                  LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS
                            FOR THE STATE : -  Ty St Installed  Capacity  Benefits  Commissioned Last Unit
                            ANDHRA PRADESH
                            CENTRAL-SECTOR     pe at Capacity   Addition  Shares of /            Commissioning
                            *SIMHADRI ST-II     T   U   1,000.00   1,000.00   384.00                  (2010-2012)
                            *ENNORE JV COST     T   U   1,000.00   1,000.00   129.00                 (20110-2012)
                            KAIGA U-3 & 4       N   U   440.00     440.00     123.00     COMM 220.00 11.04.2007
                            *KALPAKKAM PFBR   N U       500.00     500.00     142.00                  (2010-2011)
                            CENTRAL-SECTOR TOTAL:-                            778.00
                            STATE-SECTOR
                            NAGAR SAGAR TR      H   U   50.00      50.00      50.00                  (2010-2012)
                            VIJAYWADA TPP       T   U   500.00     500.00     500.00     COMM 500.00 ( 8.10.2009 )
                            KOTHAGUDEM ST-V     T   U   500.00     500.00     500.00                   (2011-2012)
                            JURALA PRIYA        H   U   234.00     234.00     234.00     COMM          27.06.2009
                            RAYALSEEMA 4&5      T   U   420.00     420.00     420.00     117.00 210.00 20.11.2007
                                                                                         COMM
                            PULICHINTALA        H   U   120.00     120.00     120.00                   (2011-2012)
                            KAKTIYA TPP        T U      500.00     500.00     500.00                  (2010-2011)
                            STATE - SECTOR TOTAL:-                            1,824.00
                            PRIVATE-SECTOR
                            KONASEEMA CCGT      G   U   445.00     445.00     445.00     COMM 280.00 (3.5.2009)
                            GAUTAMI CCGT        G   C   464.00     464.00     464.00     COMM 464.00 (3.5.2009)
                            KONDAPALLI CCPP     G   U   233.00     233..00    233.00     COMM 233.00 (5.12.2009)
                            KONDAPALLI CCPP     T   U   366.00     366.00     133.00                 (2010-2011)

                            PRIVATE-SECTOR TOTAL:-                            1,275.00
                            GRAND-TOTAL:-                                     3,757.00



      Note:            U-Under Construction Project;
                       C-Commissioned
                       * Share from Central Sectors Projects for which M.O.P. Orders are
                       yet to be issued is tentative.

                                              Table 1-: Peak & Energy Table

                                      PEAK AND ENERGY TABLE
                        YEAR (As per 17th EPS Report vs Actual achieved)
                                          PEAK                   ENERGY
                                  Requirment    Actual   Requirement      Actual
                     2004-05      as per 17th 8,093
                                 8,168         Demand 48,928 17th
                                                          as Per         Require
                                                                          50,416
                     2005-06     8,810        8,999     54,683            53,030
                     2006-07     9,597        10,208    59,311            60,964
                     2007-08     10,454       10,048    64,331            64,139
                     2008-09     11,388       10,823    69,775            71,592
                     2009-10     12,406                 75,680
                     2010-11     13,514                 82,085
                     2011-12     14,721                 89,032




                                                                                                                     21
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      From the above tables i.e. Actual power Supply position for the state of Andhra

      Pradesh, it clearly indicates the consistent power deficit of around 8.5 % at the

      end of 9th Plan continuing till 2009-10 up to 11.2%.


      1.3 Justification for the project


      For the state of Andhra Pradesh the projected peak load is 13,514 MW (2010-

      11). Table above shows Installed capacity as on 31 Mar 2010 for the state of

      Andhra Pradesh, actual power supply position and capacity addition during 11th

      Plan for the state of Andhra Pradesh. As per present power scenario for the

      state of Andhra Pradesh the peak deficit during 2006-07 is around 4.4 %. As

      per table above power deficit for the state of Andhra Pradesh during 2011-12

      will be around 1,255 MW (March 2010). Thus Considering projected power

      demand for the state of Andhra Pradesh, power generated from the proposed

      power plant may be utilized for the state of Andhra Pradesh.



      The proposed solar photovoltaic power plant (SPV) will contribute to bridge the

      gap between the demand and availability of power.



      As per the proposed transmission evacuation plan, the proposed power station

      shall be connected to APTransco 33/132 kV substation at Raydurng, in

      Anantapur district. Therefore it is considered that the proposed power plant will

      be able to contribute to the power requirement of the Andhra Pradesh, hence it

      is justified for construction of the Proposed 5 MW Power Plant at Veerapuram

      village, Anantapur district, Andhra Pradesh.




                                                                                                          22
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      The project activity will result in an annual average reduction of about 8000

      tCO2e per year by replacing electricity generated from fossil fuel fired power

      plants. The project activity has been essentially conceived to generate GHG

      emission free electricity by making use of available Solar PV in the project area.

      The project - being a renewable energy project - leads to sustainable

      development through efficient utilization of naturally available sunlight and

      generation of additional employment for the local stakeholders.



      The Government of India in its Interim Approval Guidelines for CDM Projects

      has stipulated a set of indicators for describing the sustainable development of

      a project. According to these indicators, the sustainability of the described

      project is as follows:



      Social well being:

      The project activity is generating employment opportunities for professional,

      skilled    and    unskilled      labour    for    development,        engineering,       procurement

      operation and maintenance of the project activity. The development of project

      specific infrastructure will result in employment and income generation activities

      for local personnel. In addition various kinds of maintenance work would

      generate employment opportunities for local contractor on regular and



      Economic well being:


          •     The project activities will bring an additional permanent basis. The project

                activity would promote the application of solar energy based power

                generation investment to the tune of INR 650 million, which is a

                significant investment in a green field project in the region.
                                                                                                          23
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




          •    The project activities will act as a nucleus for other economic activities

               such as setting up of cottage industries, shops, hotels etc. around the

               area, contributing to the economic development around the project area.


          •    Proposed power plant will use solar radiation as resource for generation

               of power helps conserve foreign exchange by reducing the need to import

               fossil fuels to meet the country’s growing energy demand.



      Environmental well being:


      Solar energy based power generation system will be a robust clean technology

      involving latest state of the art renewable energy options to be used for the

      purpose of electricity generation. The project implementation will lead to

      reduction of SOx, NOx and particulate matter (PM) emissions. It therefore

      results in an improvement in air quality and human health.




                                                                                                          24
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




      2 DETAILS ABOUT THE PROPOSED PROJECT LOCATION
        IN ANANTAPUR DISTRICT


      2.1 Introduction

      Anantapur district is situated in 13'-40'' and 15’-15'' Northern Latitude and 76'-

      50'' and 78'-30'' Eastern Longitude. It is bounded by Bellary, Kurnool District

      on the North, Cuddapah and Kolar Districts of Karnataka on South East and

      North respectively. The District is roughly oblong in shape, the longer side

      running North to South with a portion of Chitradurg District of Karnataka State

      intruding into it from west between Kundurpi and Amarapuram Mandals.The

      Distance of State capital Hyderabad from the district is of ~300 Kms. The

      District of Anantapur has a fairly good elevation which provides the District with

      tolerable climate throughout the year. It has a gradual fall from the South

      North towards the valley of the Pennar in Peddavadugur, Peddapappur and

       Tadipatri Mandals. There is a gradual rise in Hindupur, Parigi,                             Lepakshi,

      Chilamathur, Agali, Rolla and Madakasira Mandals in the South to join the

      Karnataka Plateau where the average elevation is about 2000 feet is above the

      mean sea level.


      2.2 Area and population in Anantapur District


      There are 929 inhabited villages, out of 964 total Revenue villages of the

      District. The number of villages in size group of 500 to 1999 forms 36.71% of

      the total inhabited villages . The size group of 2000 to 4999 forms 38.64% and

      the size group of 5000 to 9999 forms 12.81% only out of total villages, while 84

      villages ( 9.04%) of total inhabited villages are having population less than 500.

      There are 26 villages with more than 10,000 population excluding Towns.
                                                                                                          25
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



      2.3 Rainfall and Climate


      Anatapur district being far from the East coast, it does not enjoy the full

      benefits of North East Monsoons and being cut off by the high western Ghats,

      the South West Monsoon are also prevented from penetrating and punching

      the thirst of these parched soils. It is therefore seen, the district is deprived of

      both the monsoons and subjected to droughts due to bad seasons. The normal

       rainfall of the district is 553.0 MMs. by which it secures least rainfall when

      compared to Rayalaseema and other parts of Andhra Pradesh. The normal

      rainfall for the South West Monsoon period is 338.0 MMs. which forms about

      61.2% of the total rainfall for the year. The failure of the rains in this South

      West monsoon period of June to September will lead the District to drought by

      failure of crops. The rainfall for North East monsoon period is 156.0 M.Ms. only,

      which forms 28.3%              M.Ms. of      the total rainfall for the year (October to

       December).


      2.4 Temperature


      March, April and May are warm months when the normal daily maximum

      temperature ranges between 29.1 C to 40.3 C. November, December and

      January      are cooler       months       when the temperature              falls   about     15.7 C,

      Hindupur, Parigi, Lepakshi, Chilamathur, Agali, Rolla and Madakasira Mandals

      being at High Elevation are more cooler than the rest of the Mandals in the

      District.




                                                                                                          26
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



      2.5 Proposed Project location

      The Proposed project site T Veerapuram is located in Raydurg Taluk of

      Anantapur district. Below figure shows the project location. The site selection

      for a Solar Power Plant is pre-dominantly determined by solar insulation

      availability & grid connectivity for exporting power. Equally important are other

      essential factors/considerations such as:



      •   Availability of adequate land for Power Plant and green belt development

      •   Soil condition like soil bearing capacity etc.

      •   Proximity to State Electricity Grid enabling economic evacuation of power

          generated

      •   Availability of water and power during construction

      •   Availability of local work force in the proximity

      •   Availability of load centres (towns) within vicinity

      •   Easy accessibility of the site



      The proposed project site in Veerapuram village, Anatapur district of Andhra

      Pradesh State is found favoring all the above factors to a reasonable extent.




                                                                                                          27
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                       Figure :         Location map of Anatapur district in India:




                Figure :          Map showing proposed project site within Anantapur




                                                                                   Proposed
                                                                                   Project site for
                                                                                   5 MW SPV
                                                                                   Power Project
                                                                                   at Veerapura




                                                                                                          28
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



      2.6 Land requirement and layout of the proposed Project


      The Power Plant will be located in the proposed site in Veerapuram village. The

      total land area required for the project is about 25 acres. The Power Plant

      layout can be divided into two sections as:


          1. Module mounting area and

          2. Control room



      The major portion of the site will be used for module mounting. As described in

      the Power Plant Scheme the module will be mounted in a steel structure which

      will be installed facing South direction for best efficiency & optimal power

      output. The steel structure will be grouted using RCC foundation. The proposed

      structure is designed to hold 8 modules per structure and which can withstand

      wind speed up to 100km/hr. The structure is designed in such a way that it will

      occupy minimum required space without sacrificing the performance.



      The interconnection cables are routed within the structure and the output cables

      from the modules are taken through proper size conduit to the smart connect

      box. The output cables from the junction boxes are routed under the ground

      through conduits or cable trenches. Man holes for regular maintenance and

      inspection will be provided at equal distances as required. Earthing for all the

      module mounting structures will be done using copper or GI conductors. The

      earth pits for module area will be provided as the electrical standards. In order

      to protect the modules from lightning, lightning protection will be provided in

      the module mounting area. Sufficient number of lightning arrestor will be



                                                                                                          29
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      provided in this area alone for protection of modules. The proposed power plant

      layout is enclosed as annexure 5.


      2.7 Land availability and acquisition for the project

      As mentioned in the previous section, solar power plant of 5 MW capacity

      requires about 25 acres of land. The land required by the project is already

      acquired on lease basis.




                                                                                                          30
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      RADIATION DATA AND PROJECTED POWER GENERATION FROM THE PROJECT

      ACTIVITY



      Actual site of installation is T. Veerapuram village, Raydurg taluka, located in

      Anatapur district. The latitude and longitude of this site is 14.36 0N and 76.56
      0
          E respectively. Solar radiation available is for Anatapur in Andhra Pradesh is

      considered for simulation of project parameters.



      Latitude         : 14.70 ºN

      Longitude        : 77.60 ºE



      Below is the weather data for Anatapur district. The data is taken from surface

      metrology and solar energy data NASA earth science enterprise programme and

      is based on 22 years of yield data analysis.



      The irradiation and temperature details considered for the design purpose are

      as below:




                                                                                                          31
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


                            Table -: Temperature details considered for design:




      Average annual solar insulation at horizontal angle taken for Anantapur based

      on the above chart: 5.34 KWh/m²/day.




                                                                                                          32
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



      2.8 Simulation report of the power plant




                                                                                                          33
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                                                                                                          34
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




                                                                                                          35
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      The above simulation analysis is carried out based on the fixed structures.

      Saisudhir energy and NVVN has entered into a power purchase agreement for

      the capacity of 5 MW +5% and -0% power plant capacity. The entire generated

      energy will be sold to NVVN on a long term basis. With this arrangement to

      optimize the power generation potential, it was envisaged to install PV modules

      of 5.250 MW capacity to take care of the DC side energy losses in the system.




                                                                                                          36
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




      3 SELECTION OF TECHNOLOGY


      The key components of a photovoltaic power system are the photovoltaic cells

      (sometimes also called solar cells) interconnected and encapsulated to form a

      photovoltaic module (the commercial product), the mounting structure for the

      module or array, the inverter (essential for grid-connected systems and) and

      charge controller (for off-grid systems only).


      3.1 Existing Solar Photovoltaic Technologies


      Crystalline silicon technologies currently account for most of the overall cell

      production in the IEA PVPS countries. Single crystal PV cells are manufactured

      using a single-crystal growth method and have commercial efficiencies between

      15 % and 18 %. Multicrystalline cells, usually manufactured from a melting and

      solidification process, are less expensive to produce but are marginally less

      efficient, with conversion efficiencies around 14 %.


      PV cells made from ribbons demonstrate an average efficiency around 14 %.

      Thin film cells, constructed by depositing extremely thin layers of photovoltaic

      semi-conductor materials onto a backing material such as glass, stainless steel

      or plastic, show stable efficiencies in the range of 7 % to 13 %. Thin film

      materials commercially used are amorphous silicon (a-Si), cadmium telluride

      (CdTe), and copper-indium-gallium-diselenide (CIGS) and Copper Indium

      Selenium (CIS) Thin film modules.




                                                                                                          37
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



      3.2 Thin film modules

      Thin film modules are potentially cheaper to manufacture than crystalline cells

      have a wider customer appeal as design elements due to their homogeneous

      appearance present. Disadvantages, such as low-conversion efficiencies and

      requiring larger areas of PV arrays and more material (cables, support

      structures) to produce the same amount of electricity.



      3.3       Comparison between Crystalline, Thin film and CPV
                Technologies
                 S.No.      Parameter            Crystalline                       Thin Film                               CPV
                         Types of Materials Mono/ Polycrystalline         Amorphous Silicon, CdS,             Triple Junction GaAs Cell &
                                                                          CdTe, CIGS, CIS etc.                lens , tracker

                   1     Handling               Better protec tion against Not Guaranteed                     Installation would be at site.
                                                breakage                                                      Not Guaranteed
                   2     Power Efficiency    12-16%                       6-8%                                20-25%
                   3     Technology          Well Developed               Under development                   Under development
                   4     Module Weight       Light weight modules         Heavier modules                     Heaviest System
                   5     Area utilization    Higher power generated       Less power per unit area            Highest power per unit area
                                             per unit area due to high
                                             efficiency
                   6     Temperature Effects Temperature variations       Lesser impact of Temperature        High variation
                                             affect output                variations
                   7     Irradiance          Used particularly for        Better performance with Diffuse     Works only for Normal
                                             Normal radiations            radiations                          radiations
                   8     Module quantity     Lesser nos required due      More modules required               Lowest nos. of modules
                                             to high efficienc y                                              required
                   9     Output per MW       High                         Varies as per sunlight condtion     Very High(due to tracking)
                         installed                                        and various locations
                  10     Transportation Cost Lower Transportation         Higher cost                         High cost
                                             cost
                  11     Mounting Structure Fewer Mounting structure      More Mounting structures            Sophisticated mounting
                                             required per KW power        required                            required

                  12     Land Requirement       Lesser space required per Largest space requirement           Lowest spac e required
                                                MW


                  13     Inverter            High inverter flexibility    Limited inverter flexibility        Limited inverter flexibility
                  14     Cost                High c ost per Watt          Lower cost per Watt                 Highest cost per Watt
                  14     Environment Effects Less Sensitive               Sensitive                           Sensitive

                  15     Stabilization          Stable power output from Stability achieved after 4-6         Unknown
                                                at initial stages        months
                  16     Availability           Easily available         Limited supply                       Limited supply
                  17     Health hazards         Made from non toxic      Toxic materials used for thin        Unknown
                                                material (Si)            films (CdS, CdTe)
                  18     Power Degradation      Less degradation         Highest degradation for initial 5-   High Degradation
                                                                         7 years



                  19     Plant Maintenance   Less maintenance            Highest maintenanc e required,       High maintenanc e required, so
                                             required after installation so highest maintenance c ost         high maintenance cost
                                             so lower cost
                  20     Repair              Relatively easy             Diffic ult due to complex          Difficult due to complex
                                                                         structure                          struc ture
                  21     Cooling Requirement Not required                Not required                       Requires active or passive
                                                                                                            cooling which could increase
                                                                                                            cost
                  22     Cabling                Well known, and lower     Well Understood but yet difficult Complex and under
                                                cabling losses            due to higher number of arrays, development. Cabling losses
                                                                          along with high cabling losses    expected to be high

                  23     Suitability for Grid   Good                      Good                                Good
                         Technology

                                                                                                                                               38
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



      3.4       Conclusion on selection of technology


      Each of the above technologies has their own particular strengths and

      weaknesses which have played a role in our decision making. We have decided

      to use Copper Indium Selenium (CIS) Thin film modules as our

      preferred technology. These advantages and disadvantages in addition with

      their market availability and costing are the key parameters on basis of which

      we have taken our technological decision.


      In the section 4.3 we have compared various technologies, and justification of

      why we have chosen a particular technology. In the below section we have

      compared the CIS, vis a vis Crystalline, Amorphous technologies.


      Characteristic              CIS      Crystalline    Amorphous        Remarks



      Module efficiency           ++       +++            -                cSi still higher than CIS, but the difference
                                                                           is getting narrow

      Appearance                  ++       -              ++               CIS modules are all black, and therefore
                                                                           very compatible with roof settings

      High Temperature            -        -              ++               CIS and cSi do not have anneal effect

      Light soaking effect        ++       -              -                CIS has light soaking effect. Higher than
                                                                           nominal power output is expected.

      Degradation                 ++       ++             -                Degradation rate is almost same as
                                                                           Crystalline.

      Production cost             ++       +              ++               Unit production cost of CIS modules
                                                                           expected to decrease by mass production
                                                                           but not in the case of crystalline module.

      Manufacturing process       +        -              +                Simple processes allow a smooth and
                                                                           efficient production overall

      Environmental               +        -              +                Environmentally friendly - CIS modules do
      contribution                                                         not include toxic or pollutant elements

      Energy payback time         ++       +              ++               Manufacture of CIS modules require only a
                                                                           small amount of energy

      Issue of raw materials      ++       -              +                CIS products do not use silicon, thus less
                                                                           affected by market volatility




                                                                                                                39
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh




      4 POWER PLANT DESIGN CRITERIA


      The Power Plant is sized on the following major criteria:

          •    Solar Power (average insulation available)

          •    Power evacuation facility in the vicinity of the proposed site along with

               Grid availability on 24 Hours a day basis.



      Details of the design process and are presented in the below sections.



      4.1       Design and Simulation projections by PVSYST

      PVSYST tool is one of the most accepted design tool for the study, sizing,

      simulation and data analysis of complete PV systems. We have used this tool to

      generate the most realistic energy yield simulation results which are detailed in

      this report. Main features of PVSYST:



          1) Detailed computation of the used components (modules, inverters, etc)

          2) Simulation on hourly basis and detailed evaluation and consideration of

               different loss factors.

          3) Calculation of arbitrary orientated module planes (fixed and tracking

               systems)

          4) Most accepted and used tool to generate simulation results for big PV

               power plants, as the results are based on systematic and refined

               approach.

          5) Program with the most accurate results and functions at the market.




                                                                                                          40
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh



      4.2       PV Power Plant Energy Production


      The system lifetime energy production is calculated by determining the first-

      year energy generation as expressed in kWh (AC)/kWp (AC), then degrading

      output over the system life based on an annual performance degradation rate.

      System degradation (largely a function of PV panel type and manufacturing

      quality) and its predictability are important factors in lifecycle costs since they

      determine the probable level of future cash flows. This stream of energy

      produced is then discounted to derive a present value of the energy generated

      to make a levelized cost calculation. The first year kWh/kWp is a function of

      the:

          •    The amount of sunshine the project site receives in a year.

          •    The mounting and orientation of the system (i.e., flat, fixed-tilt, tracking,

               etc.).

          •    The spacing between PV panels as expressed in terms of system ground

               coverage ratio (GCR).

          •    The energy harvest of the PV panel (i.e., performance sensitivity to high

               temperatures, sensitivity to low or diffuse light, etc.).

          •    System      losses     from     soiling,     transformers,       inverters,      and       wiring

               inefficiencies.

          •    System availability largely driven by inverter downtime.


      4.3       PV power plant capacity factor


      The capacity factor, a standard methodology used in the utility industry to

      measure the productivity of energy generating assets, is a key driver of a solar

      power plant’s economics.

                                                                                                             41
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


      A PV power plant’s capacity factor is a function of the insulation at the project

      location, the performance of the PV panel (primarily as it relates to high-

      temperature performance), and the orientation of the PV panel to the sun, the

      system electrical efficiencies, and the availability of the power plant to produce

      power.


      4.4       Selection of Inverter and Components


      For a complete reliable system and to ensure high energy yield from the plant,

      innovative components with latest technology are selected. The inverter that is

      selected is of very high efficiency over a wide range of load. The inverter

      operates in excess of 95.0% efficiency in comparison with the requested of 93%

      efficiency.

      Design lifetime of the inverter is at 35,000 hours with rated power at 40°C. This

      is approximately 4.8 hours at full load per day to estimate the lifetime of 20

      years.


      4.5       Selection of Monitoring System


      Monitoring system requirement for a large power plant like 5 MW with state of

      the art technology, monitoring and analysis of is carried out. Few features are

      of the monitoring system are presented as follows:

          •    Monitors the performance of the entire power plant                              (string wise

               monitoring, junction boxes, inverters, etc)

          •    Evaluates (strings, inverter, nominal/actual value), quantity of DC Power

               & AC Power produced.

          •    Measures instantaneous irradiation level and temperature at site. It also

               measures the module back surface temperature.

                                                                                                          42
Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh


          •    Alerts in case of error (discrepancy in normal operation of components,

               like module string/ diodes/ inverter/ junction box / loose contacts/ etc,)

               to facilitate recognition and correction of the fault with minimum

               downtime.

          •    Visualizes nominal status of the connected components via Control

               Center PC Software (diagnosis on site or remote)

          •    Logs system data and error messages for further processing or storing

          •    Stores and visualizes energy yield data (for life of the plant) in the Portal

               from where the data can be accessed remotely.



      4.6       Design criteria for Cables and Junction boxes and


      The power plant will adopt the best engineering practice for complete cable

      routing in the power plant by using minimal cable length while connecting in

      series string, using optimal size cables to ensure the entire plant cable losses

      are minimum.



      The junction boxes proposed are completely pre-wired to ensure ease of

      installation, maintenance and eliminates any installation hassles. These junction

      boxes not only combine the DC power from strings but also monitor each string

      performance and feed the same data to the central monitoring system.




                                                                                                          43
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr
59582162 dpr

Contenu connexe

Tendances

Solar tracking system
Solar tracking systemSolar tracking system
Solar tracking systemParviz Bora
 
The bat hat
The bat hatThe bat hat
The bat hatslmnsvn
 
CHK Power Quality products & services catalogue 22 sep 14 release
CHK Power Quality products & services catalogue 22 sep 14 releaseCHK Power Quality products & services catalogue 22 sep 14 release
CHK Power Quality products & services catalogue 22 sep 14 releaseAjeesh Joseph
 
Energy star-v5-implementation-paper
Energy star-v5-implementation-paperEnergy star-v5-implementation-paper
Energy star-v5-implementation-paperCyber Spacio
 
Democratic Republic of the Congo - Energy Outlook
Democratic Republic of the Congo - Energy OutlookDemocratic Republic of the Congo - Energy Outlook
Democratic Republic of the Congo - Energy OutlookRachit Kansal
 
Study: LNG and Coal Life Cycle Assessment of Greenhouse Gas Emissions
Study: LNG and Coal Life Cycle Assessment of Greenhouse Gas EmissionsStudy: LNG and Coal Life Cycle Assessment of Greenhouse Gas Emissions
Study: LNG and Coal Life Cycle Assessment of Greenhouse Gas EmissionsMarcellus Drilling News
 
Combined solar power and desalination plants
Combined solar power and desalination plantsCombined solar power and desalination plants
Combined solar power and desalination plantsParti Djibouti
 
Performance investigation and blade analysis of a small horizontal axis wind ...
Performance investigation and blade analysis of a small horizontal axis wind ...Performance investigation and blade analysis of a small horizontal axis wind ...
Performance investigation and blade analysis of a small horizontal axis wind ...Petronillo Peligro
 
Solar Desalination With Trough Design
Solar Desalination With Trough DesignSolar Desalination With Trough Design
Solar Desalination With Trough DesignWaleed Alyafie
 
Economics of wind_energy__march_2009_
Economics of wind_energy__march_2009_Economics of wind_energy__march_2009_
Economics of wind_energy__march_2009_Dr Lendy Spires
 
Best practice manual hvac chillers
Best practice manual hvac chillersBest practice manual hvac chillers
Best practice manual hvac chillersMohan Ningegowda
 
Logistics Feasibility Study for Ultra Mega Power Plant (UMPP)
Logistics Feasibility Study for Ultra Mega Power Plant  (UMPP)Logistics Feasibility Study for Ultra Mega Power Plant  (UMPP)
Logistics Feasibility Study for Ultra Mega Power Plant (UMPP)Genex Logistics
 
INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...
INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...
INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...Eloo Okoye
 
Ip model code of safe practice part 19 2nd ed. jan. 2007 part1
Ip   model code of safe practice part 19 2nd ed. jan. 2007 part1Ip   model code of safe practice part 19 2nd ed. jan. 2007 part1
Ip model code of safe practice part 19 2nd ed. jan. 2007 part1Varadaraj Ck
 
End of-life management solar photovoltaic panels 2016 irena
End of-life management  solar photovoltaic panels 2016 irenaEnd of-life management  solar photovoltaic panels 2016 irena
End of-life management solar photovoltaic panels 2016 irenaAlpha
 
Heating & Cooling of Building
Heating & Cooling of BuildingHeating & Cooling of Building
Heating & Cooling of BuildingMudasSir Rahim
 
Design of Power Plant for House
Design of Power Plant for HouseDesign of Power Plant for House
Design of Power Plant for HouseMalik Zaid
 

Tendances (20)

Solar tracking system
Solar tracking systemSolar tracking system
Solar tracking system
 
The bat hat
The bat hatThe bat hat
The bat hat
 
CHK Power Quality products & services catalogue 22 sep 14 release
CHK Power Quality products & services catalogue 22 sep 14 releaseCHK Power Quality products & services catalogue 22 sep 14 release
CHK Power Quality products & services catalogue 22 sep 14 release
 
Energy star-v5-implementation-paper
Energy star-v5-implementation-paperEnergy star-v5-implementation-paper
Energy star-v5-implementation-paper
 
Democratic Republic of the Congo - Energy Outlook
Democratic Republic of the Congo - Energy OutlookDemocratic Republic of the Congo - Energy Outlook
Democratic Republic of the Congo - Energy Outlook
 
Study: LNG and Coal Life Cycle Assessment of Greenhouse Gas Emissions
Study: LNG and Coal Life Cycle Assessment of Greenhouse Gas EmissionsStudy: LNG and Coal Life Cycle Assessment of Greenhouse Gas Emissions
Study: LNG and Coal Life Cycle Assessment of Greenhouse Gas Emissions
 
Combined solar power and desalination plants
Combined solar power and desalination plantsCombined solar power and desalination plants
Combined solar power and desalination plants
 
S E I Passive House
S E I Passive HouseS E I Passive House
S E I Passive House
 
Performance investigation and blade analysis of a small horizontal axis wind ...
Performance investigation and blade analysis of a small horizontal axis wind ...Performance investigation and blade analysis of a small horizontal axis wind ...
Performance investigation and blade analysis of a small horizontal axis wind ...
 
WCDSB_EnergyPlan
WCDSB_EnergyPlanWCDSB_EnergyPlan
WCDSB_EnergyPlan
 
Solar Desalination With Trough Design
Solar Desalination With Trough DesignSolar Desalination With Trough Design
Solar Desalination With Trough Design
 
Economics of wind_energy__march_2009_
Economics of wind_energy__march_2009_Economics of wind_energy__march_2009_
Economics of wind_energy__march_2009_
 
Best practice manual hvac chillers
Best practice manual hvac chillersBest practice manual hvac chillers
Best practice manual hvac chillers
 
FinalReport-1
FinalReport-1FinalReport-1
FinalReport-1
 
Logistics Feasibility Study for Ultra Mega Power Plant (UMPP)
Logistics Feasibility Study for Ultra Mega Power Plant  (UMPP)Logistics Feasibility Study for Ultra Mega Power Plant  (UMPP)
Logistics Feasibility Study for Ultra Mega Power Plant (UMPP)
 
INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...
INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...
INVESTMENT ANALYSIS OF SMALL SCALE WIND TURBINE INSTALLATIONS IN URBAN AREAS ...
 
Ip model code of safe practice part 19 2nd ed. jan. 2007 part1
Ip   model code of safe practice part 19 2nd ed. jan. 2007 part1Ip   model code of safe practice part 19 2nd ed. jan. 2007 part1
Ip model code of safe practice part 19 2nd ed. jan. 2007 part1
 
End of-life management solar photovoltaic panels 2016 irena
End of-life management  solar photovoltaic panels 2016 irenaEnd of-life management  solar photovoltaic panels 2016 irena
End of-life management solar photovoltaic panels 2016 irena
 
Heating & Cooling of Building
Heating & Cooling of BuildingHeating & Cooling of Building
Heating & Cooling of Building
 
Design of Power Plant for House
Design of Power Plant for HouseDesign of Power Plant for House
Design of Power Plant for House
 

En vedette

Solar photovoltaic system
Solar photovoltaic systemSolar photovoltaic system
Solar photovoltaic systemMAYANK PATEL
 
A three phase grid tied spv system with adaptive dc link voltage for cpi volt...
A three phase grid tied spv system with adaptive dc link voltage for cpi volt...A three phase grid tied spv system with adaptive dc link voltage for cpi volt...
A three phase grid tied spv system with adaptive dc link voltage for cpi volt...Asoka Technologies
 
physiology and mecanism of labour
physiology and mecanism of labourphysiology and mecanism of labour
physiology and mecanism of labourManu Aravind
 
Market Research India - Solar Energy Market in India 2009
Market Research India - Solar Energy Market in India 2009Market Research India - Solar Energy Market in India 2009
Market Research India - Solar Energy Market in India 2009Netscribes, Inc.
 
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCProject report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCGirish Gupta
 
Physiology of labor
Physiology of laborPhysiology of labor
Physiology of laborsarahracal
 
Physiology of normal labour
Physiology of normal labourPhysiology of normal labour
Physiology of normal labourrajeev sood
 
W7 info policy
W7 info policyW7 info policy
W7 info policylyonka02
 
Top 4 reasons to use informational text in
Top 4 reasons to use informational text inTop 4 reasons to use informational text in
Top 4 reasons to use informational text inthatcher1217
 
Foss in-e gov-august-2014
Foss in-e gov-august-2014Foss in-e gov-august-2014
Foss in-e gov-august-2014nghia le trung
 
Гид Российского Покупателя. Том I
Гид Российского Покупателя. Том IГид Российского Покупателя. Том I
Гид Российского Покупателя. Том IAsti Group Exhibition Company
 

En vedette (20)

Solar photovoltaic system
Solar photovoltaic systemSolar photovoltaic system
Solar photovoltaic system
 
A three phase grid tied spv system with adaptive dc link voltage for cpi volt...
A three phase grid tied spv system with adaptive dc link voltage for cpi volt...A three phase grid tied spv system with adaptive dc link voltage for cpi volt...
A three phase grid tied spv system with adaptive dc link voltage for cpi volt...
 
Physiology and Homeostasis
Physiology and HomeostasisPhysiology and Homeostasis
Physiology and Homeostasis
 
physiology and mecanism of labour
physiology and mecanism of labourphysiology and mecanism of labour
physiology and mecanism of labour
 
Market Research India - Solar Energy Market in India 2009
Market Research India - Solar Energy Market in India 2009Market Research India - Solar Energy Market in India 2009
Market Research India - Solar Energy Market in India 2009
 
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGCProject report on 33kv Substation and Automatic Power Factor Controller in ONGC
Project report on 33kv Substation and Automatic Power Factor Controller in ONGC
 
Physiology of labor
Physiology of laborPhysiology of labor
Physiology of labor
 
Solar pv systems
Solar pv systemsSolar pv systems
Solar pv systems
 
Physiology of normal labour
Physiology of normal labourPhysiology of normal labour
Physiology of normal labour
 
Az én hobbijaim
Az én hobbijaimAz én hobbijaim
Az én hobbijaim
 
Sta 217
Sta 217Sta 217
Sta 217
 
Tom Jones
Tom JonesTom Jones
Tom Jones
 
The human brain
The human brainThe human brain
The human brain
 
W7 info policy
W7 info policyW7 info policy
W7 info policy
 
Top 4 reasons to use informational text in
Top 4 reasons to use informational text inTop 4 reasons to use informational text in
Top 4 reasons to use informational text in
 
Tom jones
Tom jonesTom jones
Tom jones
 
Весна в японском стиле
Весна в японском стилеВесна в японском стиле
Весна в японском стиле
 
Foss in-e gov-august-2014
Foss in-e gov-august-2014Foss in-e gov-august-2014
Foss in-e gov-august-2014
 
Support Anna
Support AnnaSupport Anna
Support Anna
 
Гид Российского Покупателя. Том I
Гид Российского Покупателя. Том IГид Российского Покупателя. Том I
Гид Российского Покупателя. Том I
 

Similaire à 59582162 dpr

EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House mrconroy
 
Energy Systems Optimization Of A Shopping Mall
Energy Systems Optimization Of A Shopping MallEnergy Systems Optimization Of A Shopping Mall
Energy Systems Optimization Of A Shopping MallAristotelisGiannopoulos
 
Protective Device Coordination
Protective Device CoordinationProtective Device Coordination
Protective Device Coordinationjoeengi
 
bosch_shi_shu_shv_dishwasher_1998.pdf
bosch_shi_shu_shv_dishwasher_1998.pdfbosch_shi_shu_shv_dishwasher_1998.pdf
bosch_shi_shu_shv_dishwasher_1998.pdfAntonioVerduAlfonso1
 
exfo_book_guide-wdm_en.pdf
exfo_book_guide-wdm_en.pdfexfo_book_guide-wdm_en.pdf
exfo_book_guide-wdm_en.pdfMohamedshabana38
 
Catalog hitachi 50 hitachi-tr-series_dienhathe.org
Catalog hitachi 50 hitachi-tr-series_dienhathe.orgCatalog hitachi 50 hitachi-tr-series_dienhathe.org
Catalog hitachi 50 hitachi-tr-series_dienhathe.orgDien Ha The
 
New holland td90 tractor service repair manual
New holland td90 tractor service repair manualNew holland td90 tractor service repair manual
New holland td90 tractor service repair manualiekkdmmem
 
New holland td60 tractor service repair manual
New holland td60 tractor service repair manualNew holland td60 tractor service repair manual
New holland td60 tractor service repair manualfjjsekekskmdm
 

Similaire à 59582162 dpr (12)

DNV Liquified Gas Terminal
DNV Liquified Gas TerminalDNV Liquified Gas Terminal
DNV Liquified Gas Terminal
 
EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House
 
Energy Systems Optimization Of A Shopping Mall
Energy Systems Optimization Of A Shopping MallEnergy Systems Optimization Of A Shopping Mall
Energy Systems Optimization Of A Shopping Mall
 
Protective Device Coordination
Protective Device CoordinationProtective Device Coordination
Protective Device Coordination
 
bosch_shi_shu_shv_dishwasher_1998.pdf
bosch_shi_shu_shv_dishwasher_1998.pdfbosch_shi_shu_shv_dishwasher_1998.pdf
bosch_shi_shu_shv_dishwasher_1998.pdf
 
Alnor hvac handbook
Alnor hvac handbookAlnor hvac handbook
Alnor hvac handbook
 
Jerome 431 manual
Jerome 431 manualJerome 431 manual
Jerome 431 manual
 
exfo_book_guide-wdm_en.pdf
exfo_book_guide-wdm_en.pdfexfo_book_guide-wdm_en.pdf
exfo_book_guide-wdm_en.pdf
 
Bucher lift control guide
Bucher lift control guideBucher lift control guide
Bucher lift control guide
 
Catalog hitachi 50 hitachi-tr-series_dienhathe.org
Catalog hitachi 50 hitachi-tr-series_dienhathe.orgCatalog hitachi 50 hitachi-tr-series_dienhathe.org
Catalog hitachi 50 hitachi-tr-series_dienhathe.org
 
New holland td90 tractor service repair manual
New holland td90 tractor service repair manualNew holland td90 tractor service repair manual
New holland td90 tractor service repair manual
 
New holland td60 tractor service repair manual
New holland td60 tractor service repair manualNew holland td60 tractor service repair manual
New holland td60 tractor service repair manual
 

Dernier

Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 

Dernier (20)

Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 

59582162 dpr

  • 1. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh CONTENTS INTRODUCTION ..............................................................................................6 EXECUTIVE SUMMARY .....................................................................................8 PROJECT AT A GLANCE .................................................................................. 13 1 NEED AND JUSTIFICATION FOR THE PROJECT ....................................15 1.1 INTRODUCTION ............................................................................................................................. 15 1.2 POWER SCENARIO IN INDIA .......................................................................................................... 16 1.3 JUSTIFICATION FOR THE PROJECT .................................................................................................. 22 2 DETAILS ABOUT THE PROPOSED PROJECT LOCATION IN ANANTAPUR DISTRICT ............................................................................................ 25 2.1 INTRODUCTION ............................................................................................................................. 25 2.2 AREA AND POPULATION IN ANANTAPUR DISTRICT ................................................................... 25 2.3 RAINFALL AND CLIMATE ............................................................................................................. 26 2.4 TEMPERATURE.............................................................................................................................. 26 2.5 PROPOSED PROJECT LOCATION.................................................................................................. 27 2.6 LAND REQUIREMENT AND LAYOUT OF THE PROPOSED PROJECT .............................................. 29 2.7 LAND AVAILABILITY AND ACQUISITION FOR THE PROJECT ....................................................... 30 3 RADIATION DATA AND PROJECTED POWER GENERATION FROM THE PROJECT ACTIVITY .............................................................................31 3.1 SIMULATION REPORT OF THE POWER PLANT ............................................................................. 33 4 SELECTION OF TECHNOLOGY ..............................................................37 4.1 EXISTING SOLAR PHOTOVOLTAIC TECHNOLOGIES .................................................................. 37 4.2 THIN FILM MODULES ................................................................................................................... 38 4.3 COMPARISON BETWEEN CRYSTALLINE, THIN FILM AND CPV.................................................. 38 TECHNOLOGIES ........................................................................................................................... 38 4.4 CONCLUSION ON SELECTION OF TECHNOLOGY ......................................................................... 39 5 POWER PLANT DESIGN CRITERIA .......................................................40 5.1 DESIGN AND SIMULATION PROJECTIONS BY PVSYST ............................................................ 40 5.2 PV POWER PLANT ENERGY PRODUCTION ................................................................................. 41 5.3 PV POWER PLANT CAPACITY FACTOR ......................................................................................... 41 5.4 SELECTION OF INVERTER AND COMPONENTS ........................................................................... 42 5.5 SELECTION OF MONITORING SYSTEM ....................................................................................... 42 5.6 DESIGN CRITERIA FOR CABLES AND JUNCTION BOXES AND ................................................... 43 6 DESCRIPTION OF MAJOR COMPONETS OF THE POWER PLANT ............44 6.1 SOLAR PV MODULES ................................................................................................................... 45 6.2 CENTRAL INVERTORS .................................................................................................................. 45 6.1 MODULE MOUNTING SYSTEM ...................................................................................................... 47 6.1 GRID CONNECTED EQUIPMENTS ................................................................................................. 48 6.2 MONITORING SYSTEM ................................................................................................................ 48 6.3 CABLES AND CONNECTORS......................................................................................................... 49 6.4 BUILDINGS HOUSING FOR ELECTRONICS (POWER HOUSE) ..................................................... 50 6.5 OTHER FACILITIES INCLUDING WATER ...................................................................................... 51 7 SPECIFICATION OF MAIN PLANT AND EQUIPMENT .............................52 8 POWER EVACUATION AND INTERFACING WITH GRID ........................58 8.1 POWER EVACUATION SYSTEM .................................................................................................... 58
  • 2. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 8.2 TRANSFORMERS........................................................................................................................... 59 8.3 HT, LV & 11KV METERING PANEL .......................................................................................... 60 8.4 CABLES ........................................................................................................................................ 61 8.5 LT POWER CABLES ..................................................................................................................... 61 8.6 CONTROL CABLES ........................................................................................................................ 61 8.7 POWER EVACUATION CABLE ...................................................................................................... 62 8.8 GRID SYNCHRONIZATION SCHEME............................................................................................ 62 9 OPERATION AND MAINTENANCE REQUIREMENTS ...............................63 9.1 DC SIDE OF THE POWER PLANT ................................................................................................. 63 9.2 AC SIDE OF THE POWER PLANT .................................................................................................. 63 9.3 MODE OF OPERATION ................................................................................................................. 64 9.4 MAINTENANCE REQUIREMENTS .................................................................................................. 65 9.5 SPARE PARTS MANAGEMENT SYSTEM ......................................................................................... 65 9.6 MAINTENANCE OF O & M MANUALS.......................................................................................... 66 9.7 OPERATION & MAINTENANCE ORGANIZATION OF THE PLANT ................................................. 66 9.8 TRAINING ..................................................................................................................................... 67 10 ENVIRONMENTAL PROTECTION AND WASTE MANAGEMENT ...............68 11 OPERATION & MAINTENANCE ORGANIZATION OF THE POWER PLANT… 70 11.1 TRAINING ..................................................................................................................................... 71 11.2 PLANT OPERATION ORGANIZATION CHART .............................................................................. 72 11.3 PROJECT IMPLEMENTATION STRATEGY ...................................................................................... 73 11.4 PROJECT DEVELOPMENT ............................................................................................................. 73 11.5 FINALIZATION OF THE EQUIPMENTS AND CONTRACTS ............................................................ 73 11.6 PROCUREMENT AND CONSTRUCTION......................................................................................... 74 11.7 ERECTION AND COMMISSIONING PHASE .................................................................................. 75 12 PROJECT COST ESTIMATE AND FINANCIAL ANALYSIS ........................76 12.1 PLANT OPERATION ...................................................................................................................... 77 12.2 SALABLE ELECTRICITY ................................................................................................................ 78 12.3 SALE PRICE OF ELECTRICITY...................................................................................................... 78 12.4 SALE PRICE OF CARBON CREDITS .............................................................................................. 78 LIST OF TABLES: Table 1-1: Installed Capacity in MW in India at the End of 10th Plan ___________________17 Table 1-2: Installed Capacity in MW in India as of 31 Mar 2010 _______________________17 Table 1-3: Actual Power Supply Position _______________________________________________18 Table 1-4: Capacity Addition during 11th Plan (As Per Planning Commission) __________18 Table 1-5: Likely Power Supply Position at the End of 2010-12 ________________________18 Table 1-6: Installed capacity of all states as on 31.03.2010 (in MW) __________________19 Table 1-7: Installed Capacity in MW in Andhra Pradesh at the End of 10th Plan ________19 Table 1-8: Installed Capacity in MW in Andhra Pradesh as of 31 Mar 2010 ____________20 Table 1-9: Actual Power Supply Position _______________________________________________20 Table 1-10: Projects planned for 11th Plan _____________________________________________20 Table 1-11: Likely Power Supply Position at the End of 2010-12 _______________________21 Table 1-12: Likely Capacity Addition During 11th Plan __________________________________21 Table 1-13: Peak & Energy Table ______________________________________________________21 Table 3-1: Temperature details considered for design: ________________________________32 Table 7-1: Bill of materials _____________________________________________________________52 Table 7-2: Technical specification of proposed solar modules at STC __________________53 Table 7-3: Specifications of module mounting structure _______________________________53 Table 7-4: Cables speficification _______________________________________________________54 Table 7-5: Invertors specification ______________________________________________________54 Table 7-6: Transformer specification at 33 kV side ____________________________________55
  • 3. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Table 7-7: Transformer specification for grid interfacing at 33/132 kV _________________56 Table 7-8: Monitoring system specification ____________________________________________57 Table 12-1: Project Cost Estimate _____________________________________________________76 Table 12-2: Assumptions supporting financial projections _____________________________80 Table 12-3: Estimation of Depreciation ________________________________________________82 Table 12-4: Projected Profitability,Balance Sheet,CF, IRR ands WC ____________________84 Table 12-5: Project Debt Service Coverage Ratio (DSCR) ______________________________88 List of Figures: Figure 1: Location map of Anatapur district in India: ............................................................. 28 Figure 2: Map showing proposed project site within Anantapur ......................................... 28 Figure 3: Typical module mounting structure: .......................................................................... 47 Figure 4: Grid-Connect equipments ............................................................................................... 48 Annexure 1 Project site Photographs 2 Land ownership details of the proposed project 3 Contour map of the project site 4 Schematic diagram showing 5MWp Solar PV Plant Layout 5 Schematic of Control Room Layout 6 Schematic of earthing layout 7 Power Evacuation Scheme 5MWp to 33/132 kV substation 8 Incorporation certificate of Saisudhir Energy Limited 9 Memorandum and Articles of Association of Saisudhir Energy Limited
  • 4. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh ABBREVIATIONS General AB Air Breaker ACB Air Circuit Breaker AC Alternate current ACSR Aluminum Conductors Steel Reinforced BOS Balance of the System CO2 Carbon Dioxide CIS Copper Indium Selenium CT Current Transformer DAS Data Acquisition System DC Direct Current DP Double Pole DPR Detailed Project Report APTRANSCO Andhra Pradesh Transmission Corporation HT High Tension LT Low Tension LV Low Voltage MNRE Ministry of New and Renewable Energy kWh Kilo Watt Hour NO2 Nitrous Oxide Main Combiner Box / Miniature Circuit MCB Breaker MFM Multi Function Meters PLF Plant Load Factor PFC Power Finance Corporation PPA Power Purchase Agreement PV Photo Voltaic PT Power Transformer SEB State Electricity Board 4
  • 5. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh SO2 Sulphur Dioxide SP Single Pole VCB Vacuum Circuit Breaker XLPE Cross Linked Polyethylene Units % Percentage ˚C Degree Centigrade H Hour Ha Hectare Kg Kilogram kV Kilo-Volt kW kilo Watt kWe kilo Watt electrical kWp kilo Watt peak Lt Liter M Meter m2 Square meter m3 Cubic meter Mg milli gram Mm milli meter MW Mega Watt MWe Mega Watt electrical Tons Tons 5
  • 6. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh INTRODUCTION As the world broadens its portfolio of power options to meet growing energy demands and increasingly stringent environmental concerns, solar power is emerging as an attractive option. Of all the routes for conversion of solar into useful energy, direct conversion of sunlight to electricity through solar photovoltaic technology is well accepted. Solar photovoltaic has been recognized as an important route for generation of substantial quantities of grid quality power by utilizing the light energy of solar radiation. SAISUDHIR Energy Limited (SSEL) a group company of SAISUDHIR Infrastructures Limited is intent to develop solar photovoltaic power plant of (SPV) power project at Veerapuram village of Anatapur district, in the State of Andhra Pradesh. SSEL intend to setup grid interactive solar power project based on Copper Indium Selenium (CIS) modules also called as thin film modules. The project activity is to install grid connected 5 MW solar power project. The full power rating of the solar power plant shall be 5.0 +5% and -0% MW DC at standard test conditions (STC) of 1000 W/sq meter sunlight and 25 degree centigrade. The project is selected to install CIS modules which comply with IEC 61646 for quality and IEC 61730 safety standards. The project site proposed is in Veerapura village of Anatapur district in Andhra Pradesh. The total land area required for the project is about 25 acres. The company already acquired the land required for the project. 6
  • 7. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh The project envisages an investment of approx. Rs 650 million for the installation of 5 MW solar power plant which would provide quantity power with a power purchase price signed with NTPC's Vidyut Vyapar Nigam Ltd or NVVN which is the designated Nodal Agency under Jawaharlal Nehru National Solar Mission (JNNSM) for procuring the solar power by entering into a Power Purchase Agreement (PPA) with Solar Power Generation Project Developers. In addition, the Power Project would generate direct and indirect employment opportunities; create of civic facilities for establishment of ancillary industries. 7
  • 8. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh EXECUTIVE SUMMARY 1. The average per capita consumption of energy in India is around 612 kW, which is much lower than that of the developed countries like USA, Europe, Australia, Japan etc. However, this figure is expected to rise sharply due to high economic growth and rapid industrialization. Energy is a necessity and sustainable renewable energy is a vital link in industrialization and development of India. A transition from conventional energy systems to those based on renewable resources is necessary to meet the ever increasing demand for energy and to address environmental concerns. 2. Thus, the present scenario needs for addition of major renewable energy sources of energy for overall economic development of the country. 3. Solar Photovoltaic Power plant operates on the principle of the photoelectric phenomenon - direct conversion of light to electricity. The solar radiation incident upon a silicon-based semiconductor photovoltaic cell produces direct electric current. 4. Photovoltaic cells are integrated into modules with a voltage of 6 - 12 V; the electrically interconnected modules form solar systems with an output voltage of 230 V. 5. Saisudhir Energy Limited (SSEL) is an SAISUDHIR Infrastructures group company. Saisudhir Infrastructures Limited is one of the fastest growing ISO 9000 infrastructure companies having nationwide network for its 8
  • 9. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Construction services in the field of Water, Power, Buildings Infrastructures, Solid Waste Management and Irrigation etc., 6. SAISUDHIR builds the high-voltage electric transmission system that helps to keep the lights on, business running and communities strong. The company has played a major role in the complete preparation, analysis, design, construction management and inspection of energy structures, high voltage transmission lines and distribution systems across the country. 7. SAISUDHIR has an in-house capability for designing Transmission Line Towers & Switchyard Structures. 8. SAISUDHIR energy proposed to install a 5 MW Solar Photovoltaic (SPV) power plant under phase I of Jawaharlal Nehru National Solar Mission (JNNSM) of new grid connected projects. The generated electricity will be sold to NVVN with a long term Power Purchase Agreement (PPA). The company has already entered into a PPA agreement with NVVN. 9. This report highlights the details of the proposed power generation scheme, site facilities, solar radiation in the proposed site location and water, evacuation of generated power, features of main plant and equipment including the inverter system, electrical systems, environmental aspects, estimate of capital cost and the financial analysis and the schedule for project implementation. 10. The proposed 5 MW power plant would require about 25 acres of land. The company already acquired the land required for the project. 9
  • 10. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 11. The plant is designed with an availability factor of 100%. The plant will generate about 9.63 million units per year at the module array terminals, after the losses in the system about 9.32 million units will be available at the grid terminals which will amount to a plant load factor of about 21.28 %. The project site was selected on the basis of: • Availability of good solar insulation • Availability of uninhabited land at a reasonable cost • Availability of stable grid near to the project site • High Power Demand in the State • Availability of good infrastructural facility including road and rail connection 12. The power generated at 11kV from the power plant will be stepped-up to 33 kV level and connected to APPCL sub-station at Raydurg, which is about 10 km from the project site. The total power produced is envisaged as 9.63 million units at the PV array. After the losses the net available energy for supplying to the grid is about 9.32 million units. Thus, the net salable electricity to the grid works out to 9.32 million units. The plant is envisaged to operate 365 days at a plant load factor (PLF) of 21.28%. The transmission line required from the SSEL 5 MW plant site to the substation will be laid by the project promoters. 13. The power plant will comprise of IEC 61646 modules of CIS thin film modules with aluminum frame of 41,600 no’s , which will work out to 5 MW +5% and -0% for accounting the DC losses (each module of 130 Wp capacity), 5200 nos of PV system mounting structures (strings) made out 10
  • 11. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh of MS galvanized steel with 8 module structure, fixed tilt type, 80 nos of array junction boxes, Power conditioning unit (inverter) 10 nos of 500 kVA, 1.25 MVA transformer 5 nos, 6.5 MVA transformer 1 no for interfacing with grid, LT and HT Panel and protection and metering, cables and earthing system set. 14. The net energy sales from the plant workout 9.32 million units. The entire energy will be sold to NVVN through APTransco grid. The financial analysis is made with a levelised power purchase price of Rs. 12.00 / kWh. 15. The total cost of generation includes the insurance cost, repairs and maintenance, cost of administration, salaries and wages, cost of utilities. 16. The total installed project cost including civil, mechanical and electrical, preoperative expenses and the contingency works out to Rs 650 million. 17. The solar power plant reduces contribution to atmospheric carbon-di- oxide vis-à-vis fossil fuel generation. The project helps solar radiation into useful electricity, adding to the sustainability of the project and the local environment. Thus, the project meets the UNFCCC norms set to qualify for obtaining CDM benefits. The project is envisaged to register with UNFCCC for availing the CDM benefits. 18. The term loan requirement from the financial institution works out to 455.00 (70% of the project cost) million. It is assumed that the term loan will be repaid in 13 years in quarterly installments, with an initial 11
  • 12. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh moratorium period of 1 year. The equity from SSIL will be Rs 195.00 million. The interest rate for the term loan is considered as 11.50 %. 19. The depreciation computed is on straight line basis. 20. Income tax at the rate of 32.45% % is considered in the financial analysis. The benefits available under Section 80 IA, for power projects have been taken into consideration in the financial analysis while calculating the income tax liability. The post tax Project Internal Rate of Return (IRR) works out to 13.63% and Post tax Equity IRR works out to 18.89%. 21. The project also generates Clean Development Mechanism (CDM) revenue with reduction at 1% in the subsequent years. If we consider the revenue from sale of carbon credits with a minimum price of € 12 per CER, the project generates additional revenue of about INR 7.5 million, which will add to the profitability of the project. 22. Minimum Project Debt Service Coverage Ratio (DSCR) will work out to 1.35 and average DSCR will work out to 1.65. 12
  • 13. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh PROJECT AT A GLANCE 1 Project Authority SAISUDHIR Energy Limited 5 MW +5% and –0% Solar Photovoltaic 2 Project Installed Capacity Power Plant T.Veerapuram Village, Anantapur 3 Selected Location District. 4 Nearest Major Towns Anantapur 5 Seismic Zone Zone-4 as per IS 1893-1984. Well Connected, buses are Operated by 6 Access by Bus Andhrapradesh State Road Transport Corporation (APSRTC) 7 Nearest Airport Bangalore International Airport (BIAL) Anantapur Railway Station is on the 8 Access by Rail Bangalore-Hydrabad line. Copper Indium Selenium (CIS) Thin film 9 Solar module type modules 10 Capacity of each module 130 Wp 11 No. of modules 41,600 Nos 12 PV System Mounting Structure type MS Galvanised(> 70 micron) 13 Module mounting structure type 8 Module mounting structure 14 No. of module mounting structures 5,200 Nos. 15 No. of Array junction boxes 80 Nos. Power conditioning Unit (Invertor) 16 500 kVA capacity 17 Power conditioning Unit specifications Input voltage range 450-900V 18 No. of invertors 10 Nos. 19 Invertors make AEG or equivalent 20 1.25 MVA Transformer 5 Nos 21 6.5 MVA Transformer 1 No. 13
  • 14. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 22 LT Panel with protection & metering 5 Nos. 23 LT Panel with protection & metering 2 Nos 24 Cables and earthing systems 1 set 25 Gross Power Generation (kW) 5000 +5% and -0% Net exportable power at 33 kV to 27 9.32 million units nearest grid substation(kW) 28 Power Purchase tariff with NVVN in ` 12.00 29 Plant Load Factor 21.28% 30 Total Project cost (Rs. In millions) 650 Preliminary and pre-operative 31 30.00 expenses (Rs. In millions) Equity from Promoters 32 195.00 (Rs. In millions) Term loan from Financial Institutions 33 455.00 (Rs in millions) 34 Interest on term loan 11.50% 35 Project IRR (post tax) 13.63 % 36 Equity IRR (post tax) 18.89 % 37 Plant Commissioning Date Dec 2011 Land requirement 25 Acres 38 • Module area 51,089 m2 The entire station will be laid at a 39 Land Development uniform level. TECHNICAL FEATURES Through 33/132kV Transmission lines 40 Power Evacuation Raydurg substation located 10km from project site. OTHER FACILITIES Through EPC (Engineering, Procurement 41 Mode of Implementation and Construction) or thru split contracts. Twelve (12) months from the date of 42 Project Time Frame signing PPA with NVVN PROJECT COST Present day cost including, financing Project Cost charges and margin money. 43 Rs.650 million. 14
  • 15. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 1 NEED AND JUSTIFICATION FOR THE PROJECT 1.1 Introduction India with 17 percent of the world population and just 0.8 per cent of the world’s known oil and natural gas resources is going to face serious energy challenges in the coming decades. Besides energy independence, the devastating impact of climate change has become an issue of critical importance. Energy production using fossil fuels is the major contributor to greenhouse gas emissions. Hence, transition to a low-carbon energy economy is the real solution for mitigating the impact of climate change. India has huge potential for producing electricity from renewable sources. The achievement so far is about 17,222 (as on 31.03.2010) MW, as against global installed capacity of approximately 2,00,000 MW of renewable electricity generation. While India’s achievement is commendable, it is necessary for us to keep pace with the fast growth in developed countries. There are three imperatives that necessitate a transition to a sustainable energy system in the 21st century: They are Climate change and its potentially disastrous consequences. Peaking of production, depletion and extinction of fossil fuels and Energy Autonomy and Independence. The single biggest reason for global warming is the burning of fossil fuels. So the solution lies in effecting an accelerated transition to a low carbon energy economy, which means large scale development of renewable energy. Fortunately there are several emerging technologies that will facilitate this. 15
  • 16. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Peaking of production of all fossil fuels (viz. oil, gas and coal) in the next two decades and gradual extinction of these resources is an accepted scientific fact. Even assuming that they would be available, India, which is already dependent on their import, would become more and more import dependent. The financial implications of large scale imports would destroy our economy and necessitate strategies to move towards energy autonomy or independence. The conversion of solar energy to electricity displaces an equivalent amount of grid power, which would otherwise be produced by grid connected fossil fuel dominated power plants. Grid power is comprised of a large share of fossil fuel based generation systems. 1.2 Power Scenario in India As per Section73(a) of the Indian Electricity Act-2003, CEA has been carrying out periodic electric power survey to project state-wise and region-wise power plans together with assessment of peaking power and energy surpluses / deficits. The estimate prepared by the CEA is revised and updated from time to time taking into account the actual growth rates achieved. The Reports and National Electricity Plan prepared by CEA i.e. Report on (17th) Electric Power Survey of India published in August 2007, Draft National Electricity Plan- Transmission published in 2005 and Power Scenario at a glance published in April 2010 have been referred for carrying out demand analysis of the State of Andhra Pradesh and other regions. Load forecast/Availability of power for 2003-2012 for the State of Eastern, Northern, Western, Southern and North-Eastern region have been given below which shows that surplus amount of power will be available for the North-East 16
  • 17. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh region while other regions i.e. Northern, Western and Southern will expect a shortage of power at the end of 11th Plan i.e. 2011-12. Actual power scenario of are as follows in terms of: • Installed Capacity • Actual Supply/Generation. • Likely capacity addition. Table 1-: Installed Capacity in MW in India at the End of 10th Plan INSTALLED CAPACITY (AT THE END OF 10TH PLAN) (FIGURES IN MW) Sector Hydro Thermal Nuclear R.E.S. Total Coal Gas Diesel Total (MNRE) STATE 26,005.7 41,731.6 3,729.8 604.6 46,066 0.0 975.7 73,047.4 PRIVATE 1,230.0 4,241.4 4,183.0 597.1 9,021.5 0.0 6,784.8 17,036.3 CENTRAL 7,418 25,118.3 5,809.0 0.0 30,927.3 3,900.0 0.0 42,245.3 TOTAL 34,653.7 71,091.3 13,721.8 1,201.8 86,014.8 3,900.0 7,760.5 1,32,329 Table 1-: Installed Capacity in MW in India as of 31 Mar 2010 INSTALLED CAPACITY AS ON 31.03.2010 (FIGURES IN MW) Sector Hydro Thermal Nuclear R.E.S Total Coal Gas Diesel Total (MNRE) STATE 27,065.00 44,977.00 4,046.12 602.61 49,625.73 0.00 2,701.12 79,391.85 PRIVATE 1,233.00 8,056.38 6,307.50 597.14 14,961.02 0.00 12,819.99 29,014.01 CENTRAL 8,565.40 31,165.00 6,702.23 0.00 37,867.23 4,560.00 0.00 50,992.63 TOTAL 36,863.40 84,198.38 17,055.85 1,199.75 1,02,453.98 4,560.00 15,521.11 1,59,398.49 17
  • 18. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Table 1-: Actual Power Supply Position ACTUAL POWER SUPPLY POSITION 9 Period Peak Peak Met Peak Peak Energy Energy Avail-Energy Energy Demand (MW) Deficit/ Deficit/ Requi- ability (MU) Deficit/ Deficit/ (MW) Surplus Surplus rment Surplus Surplus (MW) (%) (MU) (MU) (%) 9TH PLAN END 78,441 69,189 -9,252 -11.8 5,22,537 4,83,350 -39,187 -7.5 2002-03 81,492 71,547 -9,945 -12.2 5,45,983 4,97,890 -48,093 -8.8 2003-04 84,574 75,066 -9,508 -11.2 5,59,264 5,19,398 -39,866 -7.1 2004-05 87,906 77,652 -10,254 -11.7 5,91,373 5,48,115 -43,258 -7.3 2005-06 93,255 81,792 -11,463 -12.3 6,31,757 5,78,819 -52,938 -8.4 2006-07 1,00,715 86,818 -13,897 -13.8 6,90,587 6,24,495 -66,092 -9.6 2007-08 1,08,866 90,793 -18,073 -16.6 7,39,345 6,66,007 -73,338 -9.9 2008-09 1,09,809 96,685 -13,124 -12 7,74,324 6,89,021 -85,303 -11 APR,09 1,18,472 1,02,725 -15,748 -13.3 8,30,300 7,46,493 -83,807 -10.1 MAR ,2010 1,18,472 1,02,725 -15,748 -13.3 76,493 67,513 -8,980 -11.7 NOTE :- PEAK DEMAND - 121891 MW , ENERGY REQUIREMENT - 794561 MU FOR THE YEAR 2008-2009(AS PER 17TH EPS REPORT),OCCURENCE OF PEAK AS PER ACTUAL POWER SUPPLY POSITION IN THE MONTH(S) - MARCH & OCTOBER SOURCE:- DMLF DIVISION Table 1-: Capacity Addition during 11th Plan (As Per Planning Commission) CAPACITY ADDITION DURING 11TH PLAN (AS PER PLANNING COMMISSION TARGET) Sector Hydro Thermal Nuclear Wind Total Coal Gas Diesel Total STATE 3,482.0 19,985.0 3,316.4 0.0 23,301.4 0.0 0.0 26,783.4 PRIVATE 3,491.0 9,515.0 2,037.0 0.0 11,552.0 0.0 0.0 15,043.0 CENTRAL 8,654.0 23,350.0 1,490.0 0.0 24,840.0 3,380.0 0.0 36,874.0 TOTAL 15,627.0 52,850.0 6,843.4 0.0 59,693.4 3,380.0 0.0 78700.4* NOTE :- * AS PER ACTUAL ORDERS , THE CAPACITY COMES TO 78900.4 MW Table 1-: Likely Power Supply Position at the End of 2010-12 LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12 (DEMAND AS PER 17TH EPS) Period Peak Peak Peak Peak Energy Requi- Energy Energy Energy Demand Met Deficit/ Deficit/ rment (MU) Avail- Deficit/ Deficit/ (MW) (MW) Surplus Surplus ability Surplus Surplus (MW) (%) (MU) (MU) (%) 2011-12 1,52,746 1,42,765 -9,981 -6.5 9,68,659 9,48,836 -19,823 -2.0 18
  • 19. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Table 1-: Installed capacity of all states as on 31.03.2010 (in MW) S.No STATES HYDRO THERMAL NUCLEAR R.E.S TOTAL . COAL GAS DIESEL TOTAL 1 CHANDIGARH 46.74 27.09 15.32 0.00 42.41 8.84 0.00 97.99 2 DELHI 581.62 2,602.96 808.01 0.00 3,410.97 122.08 0.00 4,114.67 3 HARYANA 1,327.68 3,017.99 535.29 3.92 3,557.20 109.16 76.50 5,070.54 4 H.P. 1,539.94 118.30 61.88 0.13 180.31 34.08 275.83 2,030.16 5 J&K 1,480.53 263.70 304.14 8.94 576.78 77.00 129.33 2,263.64 6 PUNJAB 2,962.89 3,208.19 263.92 0.00 3,472.11 208.04 278.90 6,921.94 7 RAJASTHAN 1,454.80 4,149.48 665.03 0.00 4,814.51 573.00 926.15 7,768.46 8 U.P. 1,597.42 6,912.84 549.97 0.00 7,462.81 335.72 587.70 9,983.65 9 UTTRAKHAND 1,919.18 261.26 69.35 0.00 330.61 22.28 132.92 2,404.99 10 CHATTISGARH 120.00 4,383.00 0.00 0.00 4,383.00 47.52 218.95 4,769.47 11 GUJARAT 772.00 7,008.89 3,894.49 17.48 10,920.86 559.32 1,655.91 13,908.09 12 M.P. 3,223.66 4,282.10 257.18 0.00 4,539.28 273.24 287.86 8,324.04 13 MAHARASHTRA 3,331.84 11,203.05 3,715.93 0.00 14,918.98 690.14 2,437.97 21,378.93 14 GOA 0.00 277.03 48.00 0.00 325.03 25.80 30.05 380.88 15 D&D 0.00 19.04 4.20 0.00 23.24 7.38 0.00 30.62 16 D&N HAVAILI 0.00 22.04 27.10 0.00 49.14 8.46 0.00 57.60 17 A.P. 3,617.53 6,259.88 2,580.40 36.80 8,877.08 214.28 700.51 13,409.40 18 KARNATAKA 3,599.80 3,902.67 220.00 234.42 4,357.09 195.36 2,234.09 10,386.34 19 KERALA 1,781.50 765.38 533.58 256.44 1,555.40 78.10 138.76 3,553.76 20 T.N 2,108.20 5,519.81 1,026.30 411.66 6,957.77 478.50 4,865.51 14,409.98 21 P.CHURY 0.00 207.01 32.50 0.00 239.51 16.28 0.00 255.79 22 D.V.C 193.26 3,563.10 90.00 0.00 3,653.10 0.00 0.00 3,846.36 23 BIHAR 129.43 1,661.70 0.00 0.00 1,661.70 0.00 54.60 1,845.73 24 JHARKHAND 200.93 1,737.88 0.00 0.00 1,737.88 0.00 4.05 1,942.86 25 ORISSA 2,166.93 1,828.10 0.00 0.00 1,828.10 0.00 64.30 4,059.33 26 SIKKIM 75.27 68.10 0.00 5.00 73.10 0.00 47.11 195.48 27 W.BENGAL 1,116.30 6,756.34 100.00 12.20 6,868.54 0.00 164.70 8,149.54 28 ARP.P. 97.57 0.00 21.05 15.88 36.93 0.00 67.42 201.92 29 ASSAM 429.72 60.00 441.32 20.69 522.01 0.00 27.11 978.84 30 MANIPUR 80.98 0.00 25.96 45.41 71.37 0.00 5.45 157.80 31 MEGHALYA 230.58 0.00 25.96 2.05 28.01 0.00 31.03 289.62 32 MIZORAM 34.31 0.00 16.28 51.86 68.14 0.00 28.47 130.92 33 NAGALAND 53.32 0.00 19.19 2.00 21.19 0.00 28.67 103.18 34 TRIPURA 62.37 0.00 160.84 4.85 165.69 0.00 16.01 244.07 35 A&N ISLAND 0.00 0.00 0.00 60.05 60.05 0.00 5.25 65.30 36 LAKSHDEEP 0.00 0.00 0.00 9.97 9.97 0.00 0.00 9.97 Table 1-: Installed Capacity in MW in Andhra Pradesh at the End of 10th Plan INSTALLED CAPACITY (AT THE END OF 10th PLAN (FIGURES IN MW) Sector Hydro Thermal Nuclear R.E.S. Total Coal Gas Diesel Total (MNRE) STATE 3,582.6 3,132.5 272.3 0.0 3,404.8 0.0 103.0 7,090.3 PRIVATE 3.8 0.0 1,603.4 36.8 1,640.2 0.0 283.4 1,927.4 CENTRAL 0.0 2,378.0 0.0 0.0 2,378.0 152.5 0.0 2,530.5 TOTAL 3,586.3 5,510.5 1,875.7 36.8 7,423.0 152.5 386.4 11,548.2 19
  • 20. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Table 1-: Installed Capacity in MW in Andhra Pradesh as of 31 Mar 2010 Sector Hydro Thermal Nuclear R.E.S. Total Coal Gas Diesel Total (MNRE) STATE 3,617.53 3,882.50 0.00 0.00 3,882.50 0.00 188.43 7,688.46 PRIVATE 0.00 0.00 2,580.40 36.80 2,617.20 0.00 512.08 3,129.28 CENTRAL 0.00 2,377.38 0.00 0.00 2,377.38 214.28 0.00 2,591.66 TOTAL 3,617.53 6,259.88 2,580.40 36.80 8,877.08 214.28 700.51 13,409.40 Table 1-: Actual Power Supply Position Peak Peak Peak Peak Energy Energy Energy Energy Period Demand Met deficit/ Deficit/ Requi- Avail- Deficit/ Deficit/ (MW) (MW) Surplus Surplus ( rment ability Surplus Surplus ( (MW) %) (MU) (MU) (MU) %) 9TH PLAN END 8,585 6,873 -1,712 -19.9 48,394 44,302 -4,092 -8.5 2002-03 8,491 6,858 -1,633 -19.2 47,258 44,049 -3,209 -6.8 2003-04 8,679 7,769 -910 -10.5 48,080 46,680 -1,400 -2.9 2004-05 8,093 7,903 -190 -2.3 50,416 50,061 -355 -0.7 2005-06 8,999 8,542 -457 -5.1 53,030 52,332 -698 -1.3 2006-07 10,208 8,641 -1,567 -15.4 60,964 58,280 -2,684 -4.4 2007-08 10,048 9,162 -886 -8.8 64,139 61,511 -2,628 -4.1 2008-2009 10,823 9,997 -826 -7.6 71,592 66,754 -4,838 -6.8 APR,09-MAR10 12,135 10,880 -1,255 -10.3 79,014 73,784 -5,230 -6.6 MAR 2010 12,135 10,880 -1,255 -10.3 7,929 7,040 -889 -11.2 Table 1-: Projects planned for 11th Plan PROJECTS PLANNED FOR XITH PLAN (STATE/PRIVATE/CENTRAL SECTOR) INCLUDING BEST CAPACITY LIKELY YEAR / EFFORT PROJECT AGENCY STATUS TYPE (MW) DATE OF PROJECTS COMMISSIONIN G 1 SIMHADRI-EXT U-3,4 NTPC Under Construction COAL 1,000 2010-12 2 SUB TOTAL –Central sector 1,000 3 JURALA PRIYA U1,2 APGENCO Commissioned HYDRO 78 31.08.2008 4 JURALA PRIYA U,3 APGENCO Commissioned HYDRO 39 07.06.2009 5 JURALA PRIYA U 4-6 APGENCO Under Construction HYDRO 117 2010-11 6 NAGARJUNA SAGAR TR APGENCO Under Construction HYDRO 50 2010-12 7 PULICHINTALA APID Under Construction HYDRO 120 2010-12 8 RAYALSEEMA U4 APGENCO Commissioned COAL 210 2007-08 9 RAYALSEEMA ST III U5 APGENCO Under Construction COAL 210 2010-11 10 VIJAYWADA TPP ST-IV,U1 APGENCO Commissioned COAL 500 8.10.2009 11 KOTHAGUDEM ST-V APGENCO Under Construction COAL 500 2011-12 12 KAKTIYA TPP APGENCO Under Construction COAL 500 2010-11 13 SUB TOTAL –state sector 2,324 14 KONASEEMA OAKWELL Commissioned GAS/LNG 280 3.5.2009 15 KONASEEMA OAKWELL Under Construction GAS/LNG 165 2010-11 16 GAUTAMI GAUTAMI POW Commissioned GAS/LNG 464 3.5.2009 17 KONDAPALLI PH II LANCO Commissioned GAS 233 5.12.2009 18 KONDAPALLI PH II LANCO Under Construction LNG 133 2010-11 19 SUB TOTAL -private sector 1,275 20 TOTAL (AP) 4,719 20
  • 21. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Table 1-: Likely Power Supply Position at the End of 2010-12 LIKELY POWER SUPPLY POSITION AT THE END OF 2011-12* (DEMAND AS PER 17TH EPS) Period Peak Peak Peak Peak Energy Energy Energy Energy 2011- Demand 12,357 -2,364 Deficit/ 14,721 Met eficit/ -16.1 Requi- 89,032 Avail- 80,338 Deficit/ -8,694 Deficit/ -9.8 12 Table 1-: Likely Capacity Addition During 11th Plan LIKELY CAPACITY ADDITION DURING 11TH PLAN INCLUDING BEST EFFORT PROJECTS FOR THE STATE : - Ty St Installed Capacity Benefits Commissioned Last Unit ANDHRA PRADESH CENTRAL-SECTOR pe at Capacity Addition Shares of / Commissioning *SIMHADRI ST-II T U 1,000.00 1,000.00 384.00 (2010-2012) *ENNORE JV COST T U 1,000.00 1,000.00 129.00 (20110-2012) KAIGA U-3 & 4 N U 440.00 440.00 123.00 COMM 220.00 11.04.2007 *KALPAKKAM PFBR N U 500.00 500.00 142.00 (2010-2011) CENTRAL-SECTOR TOTAL:- 778.00 STATE-SECTOR NAGAR SAGAR TR H U 50.00 50.00 50.00 (2010-2012) VIJAYWADA TPP T U 500.00 500.00 500.00 COMM 500.00 ( 8.10.2009 ) KOTHAGUDEM ST-V T U 500.00 500.00 500.00 (2011-2012) JURALA PRIYA H U 234.00 234.00 234.00 COMM 27.06.2009 RAYALSEEMA 4&5 T U 420.00 420.00 420.00 117.00 210.00 20.11.2007 COMM PULICHINTALA H U 120.00 120.00 120.00 (2011-2012) KAKTIYA TPP T U 500.00 500.00 500.00 (2010-2011) STATE - SECTOR TOTAL:- 1,824.00 PRIVATE-SECTOR KONASEEMA CCGT G U 445.00 445.00 445.00 COMM 280.00 (3.5.2009) GAUTAMI CCGT G C 464.00 464.00 464.00 COMM 464.00 (3.5.2009) KONDAPALLI CCPP G U 233.00 233..00 233.00 COMM 233.00 (5.12.2009) KONDAPALLI CCPP T U 366.00 366.00 133.00 (2010-2011) PRIVATE-SECTOR TOTAL:- 1,275.00 GRAND-TOTAL:- 3,757.00 Note: U-Under Construction Project; C-Commissioned * Share from Central Sectors Projects for which M.O.P. Orders are yet to be issued is tentative. Table 1-: Peak & Energy Table PEAK AND ENERGY TABLE YEAR (As per 17th EPS Report vs Actual achieved) PEAK ENERGY Requirment Actual Requirement Actual 2004-05 as per 17th 8,093 8,168 Demand 48,928 17th as Per Require 50,416 2005-06 8,810 8,999 54,683 53,030 2006-07 9,597 10,208 59,311 60,964 2007-08 10,454 10,048 64,331 64,139 2008-09 11,388 10,823 69,775 71,592 2009-10 12,406 75,680 2010-11 13,514 82,085 2011-12 14,721 89,032 21
  • 22. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh From the above tables i.e. Actual power Supply position for the state of Andhra Pradesh, it clearly indicates the consistent power deficit of around 8.5 % at the end of 9th Plan continuing till 2009-10 up to 11.2%. 1.3 Justification for the project For the state of Andhra Pradesh the projected peak load is 13,514 MW (2010- 11). Table above shows Installed capacity as on 31 Mar 2010 for the state of Andhra Pradesh, actual power supply position and capacity addition during 11th Plan for the state of Andhra Pradesh. As per present power scenario for the state of Andhra Pradesh the peak deficit during 2006-07 is around 4.4 %. As per table above power deficit for the state of Andhra Pradesh during 2011-12 will be around 1,255 MW (March 2010). Thus Considering projected power demand for the state of Andhra Pradesh, power generated from the proposed power plant may be utilized for the state of Andhra Pradesh. The proposed solar photovoltaic power plant (SPV) will contribute to bridge the gap between the demand and availability of power. As per the proposed transmission evacuation plan, the proposed power station shall be connected to APTransco 33/132 kV substation at Raydurng, in Anantapur district. Therefore it is considered that the proposed power plant will be able to contribute to the power requirement of the Andhra Pradesh, hence it is justified for construction of the Proposed 5 MW Power Plant at Veerapuram village, Anantapur district, Andhra Pradesh. 22
  • 23. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh The project activity will result in an annual average reduction of about 8000 tCO2e per year by replacing electricity generated from fossil fuel fired power plants. The project activity has been essentially conceived to generate GHG emission free electricity by making use of available Solar PV in the project area. The project - being a renewable energy project - leads to sustainable development through efficient utilization of naturally available sunlight and generation of additional employment for the local stakeholders. The Government of India in its Interim Approval Guidelines for CDM Projects has stipulated a set of indicators for describing the sustainable development of a project. According to these indicators, the sustainability of the described project is as follows: Social well being: The project activity is generating employment opportunities for professional, skilled and unskilled labour for development, engineering, procurement operation and maintenance of the project activity. The development of project specific infrastructure will result in employment and income generation activities for local personnel. In addition various kinds of maintenance work would generate employment opportunities for local contractor on regular and Economic well being: • The project activities will bring an additional permanent basis. The project activity would promote the application of solar energy based power generation investment to the tune of INR 650 million, which is a significant investment in a green field project in the region. 23
  • 24. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh • The project activities will act as a nucleus for other economic activities such as setting up of cottage industries, shops, hotels etc. around the area, contributing to the economic development around the project area. • Proposed power plant will use solar radiation as resource for generation of power helps conserve foreign exchange by reducing the need to import fossil fuels to meet the country’s growing energy demand. Environmental well being: Solar energy based power generation system will be a robust clean technology involving latest state of the art renewable energy options to be used for the purpose of electricity generation. The project implementation will lead to reduction of SOx, NOx and particulate matter (PM) emissions. It therefore results in an improvement in air quality and human health. 24
  • 25. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 2 DETAILS ABOUT THE PROPOSED PROJECT LOCATION IN ANANTAPUR DISTRICT 2.1 Introduction Anantapur district is situated in 13'-40'' and 15’-15'' Northern Latitude and 76'- 50'' and 78'-30'' Eastern Longitude. It is bounded by Bellary, Kurnool District on the North, Cuddapah and Kolar Districts of Karnataka on South East and North respectively. The District is roughly oblong in shape, the longer side running North to South with a portion of Chitradurg District of Karnataka State intruding into it from west between Kundurpi and Amarapuram Mandals.The Distance of State capital Hyderabad from the district is of ~300 Kms. The District of Anantapur has a fairly good elevation which provides the District with tolerable climate throughout the year. It has a gradual fall from the South North towards the valley of the Pennar in Peddavadugur, Peddapappur and Tadipatri Mandals. There is a gradual rise in Hindupur, Parigi, Lepakshi, Chilamathur, Agali, Rolla and Madakasira Mandals in the South to join the Karnataka Plateau where the average elevation is about 2000 feet is above the mean sea level. 2.2 Area and population in Anantapur District There are 929 inhabited villages, out of 964 total Revenue villages of the District. The number of villages in size group of 500 to 1999 forms 36.71% of the total inhabited villages . The size group of 2000 to 4999 forms 38.64% and the size group of 5000 to 9999 forms 12.81% only out of total villages, while 84 villages ( 9.04%) of total inhabited villages are having population less than 500. There are 26 villages with more than 10,000 population excluding Towns. 25
  • 26. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 2.3 Rainfall and Climate Anatapur district being far from the East coast, it does not enjoy the full benefits of North East Monsoons and being cut off by the high western Ghats, the South West Monsoon are also prevented from penetrating and punching the thirst of these parched soils. It is therefore seen, the district is deprived of both the monsoons and subjected to droughts due to bad seasons. The normal rainfall of the district is 553.0 MMs. by which it secures least rainfall when compared to Rayalaseema and other parts of Andhra Pradesh. The normal rainfall for the South West Monsoon period is 338.0 MMs. which forms about 61.2% of the total rainfall for the year. The failure of the rains in this South West monsoon period of June to September will lead the District to drought by failure of crops. The rainfall for North East monsoon period is 156.0 M.Ms. only, which forms 28.3% M.Ms. of the total rainfall for the year (October to December). 2.4 Temperature March, April and May are warm months when the normal daily maximum temperature ranges between 29.1 C to 40.3 C. November, December and January are cooler months when the temperature falls about 15.7 C, Hindupur, Parigi, Lepakshi, Chilamathur, Agali, Rolla and Madakasira Mandals being at High Elevation are more cooler than the rest of the Mandals in the District. 26
  • 27. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 2.5 Proposed Project location The Proposed project site T Veerapuram is located in Raydurg Taluk of Anantapur district. Below figure shows the project location. The site selection for a Solar Power Plant is pre-dominantly determined by solar insulation availability & grid connectivity for exporting power. Equally important are other essential factors/considerations such as: • Availability of adequate land for Power Plant and green belt development • Soil condition like soil bearing capacity etc. • Proximity to State Electricity Grid enabling economic evacuation of power generated • Availability of water and power during construction • Availability of local work force in the proximity • Availability of load centres (towns) within vicinity • Easy accessibility of the site The proposed project site in Veerapuram village, Anatapur district of Andhra Pradesh State is found favoring all the above factors to a reasonable extent. 27
  • 28. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Figure : Location map of Anatapur district in India: Figure : Map showing proposed project site within Anantapur Proposed Project site for 5 MW SPV Power Project at Veerapura 28
  • 29. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 2.6 Land requirement and layout of the proposed Project The Power Plant will be located in the proposed site in Veerapuram village. The total land area required for the project is about 25 acres. The Power Plant layout can be divided into two sections as: 1. Module mounting area and 2. Control room The major portion of the site will be used for module mounting. As described in the Power Plant Scheme the module will be mounted in a steel structure which will be installed facing South direction for best efficiency & optimal power output. The steel structure will be grouted using RCC foundation. The proposed structure is designed to hold 8 modules per structure and which can withstand wind speed up to 100km/hr. The structure is designed in such a way that it will occupy minimum required space without sacrificing the performance. The interconnection cables are routed within the structure and the output cables from the modules are taken through proper size conduit to the smart connect box. The output cables from the junction boxes are routed under the ground through conduits or cable trenches. Man holes for regular maintenance and inspection will be provided at equal distances as required. Earthing for all the module mounting structures will be done using copper or GI conductors. The earth pits for module area will be provided as the electrical standards. In order to protect the modules from lightning, lightning protection will be provided in the module mounting area. Sufficient number of lightning arrestor will be 29
  • 30. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh provided in this area alone for protection of modules. The proposed power plant layout is enclosed as annexure 5. 2.7 Land availability and acquisition for the project As mentioned in the previous section, solar power plant of 5 MW capacity requires about 25 acres of land. The land required by the project is already acquired on lease basis. 30
  • 31. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh RADIATION DATA AND PROJECTED POWER GENERATION FROM THE PROJECT ACTIVITY Actual site of installation is T. Veerapuram village, Raydurg taluka, located in Anatapur district. The latitude and longitude of this site is 14.36 0N and 76.56 0 E respectively. Solar radiation available is for Anatapur in Andhra Pradesh is considered for simulation of project parameters. Latitude : 14.70 ºN Longitude : 77.60 ºE Below is the weather data for Anatapur district. The data is taken from surface metrology and solar energy data NASA earth science enterprise programme and is based on 22 years of yield data analysis. The irradiation and temperature details considered for the design purpose are as below: 31
  • 32. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh Table -: Temperature details considered for design: Average annual solar insulation at horizontal angle taken for Anantapur based on the above chart: 5.34 KWh/m²/day. 32
  • 33. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 2.8 Simulation report of the power plant 33
  • 34. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 34
  • 35. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 35
  • 36. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh The above simulation analysis is carried out based on the fixed structures. Saisudhir energy and NVVN has entered into a power purchase agreement for the capacity of 5 MW +5% and -0% power plant capacity. The entire generated energy will be sold to NVVN on a long term basis. With this arrangement to optimize the power generation potential, it was envisaged to install PV modules of 5.250 MW capacity to take care of the DC side energy losses in the system. 36
  • 37. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 3 SELECTION OF TECHNOLOGY The key components of a photovoltaic power system are the photovoltaic cells (sometimes also called solar cells) interconnected and encapsulated to form a photovoltaic module (the commercial product), the mounting structure for the module or array, the inverter (essential for grid-connected systems and) and charge controller (for off-grid systems only). 3.1 Existing Solar Photovoltaic Technologies Crystalline silicon technologies currently account for most of the overall cell production in the IEA PVPS countries. Single crystal PV cells are manufactured using a single-crystal growth method and have commercial efficiencies between 15 % and 18 %. Multicrystalline cells, usually manufactured from a melting and solidification process, are less expensive to produce but are marginally less efficient, with conversion efficiencies around 14 %. PV cells made from ribbons demonstrate an average efficiency around 14 %. Thin film cells, constructed by depositing extremely thin layers of photovoltaic semi-conductor materials onto a backing material such as glass, stainless steel or plastic, show stable efficiencies in the range of 7 % to 13 %. Thin film materials commercially used are amorphous silicon (a-Si), cadmium telluride (CdTe), and copper-indium-gallium-diselenide (CIGS) and Copper Indium Selenium (CIS) Thin film modules. 37
  • 38. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 3.2 Thin film modules Thin film modules are potentially cheaper to manufacture than crystalline cells have a wider customer appeal as design elements due to their homogeneous appearance present. Disadvantages, such as low-conversion efficiencies and requiring larger areas of PV arrays and more material (cables, support structures) to produce the same amount of electricity. 3.3 Comparison between Crystalline, Thin film and CPV Technologies S.No. Parameter Crystalline Thin Film CPV Types of Materials Mono/ Polycrystalline Amorphous Silicon, CdS, Triple Junction GaAs Cell & CdTe, CIGS, CIS etc. lens , tracker 1 Handling Better protec tion against Not Guaranteed Installation would be at site. breakage Not Guaranteed 2 Power Efficiency 12-16% 6-8% 20-25% 3 Technology Well Developed Under development Under development 4 Module Weight Light weight modules Heavier modules Heaviest System 5 Area utilization Higher power generated Less power per unit area Highest power per unit area per unit area due to high efficiency 6 Temperature Effects Temperature variations Lesser impact of Temperature High variation affect output variations 7 Irradiance Used particularly for Better performance with Diffuse Works only for Normal Normal radiations radiations radiations 8 Module quantity Lesser nos required due More modules required Lowest nos. of modules to high efficienc y required 9 Output per MW High Varies as per sunlight condtion Very High(due to tracking) installed and various locations 10 Transportation Cost Lower Transportation Higher cost High cost cost 11 Mounting Structure Fewer Mounting structure More Mounting structures Sophisticated mounting required per KW power required required 12 Land Requirement Lesser space required per Largest space requirement Lowest spac e required MW 13 Inverter High inverter flexibility Limited inverter flexibility Limited inverter flexibility 14 Cost High c ost per Watt Lower cost per Watt Highest cost per Watt 14 Environment Effects Less Sensitive Sensitive Sensitive 15 Stabilization Stable power output from Stability achieved after 4-6 Unknown at initial stages months 16 Availability Easily available Limited supply Limited supply 17 Health hazards Made from non toxic Toxic materials used for thin Unknown material (Si) films (CdS, CdTe) 18 Power Degradation Less degradation Highest degradation for initial 5- High Degradation 7 years 19 Plant Maintenance Less maintenance Highest maintenanc e required, High maintenanc e required, so required after installation so highest maintenance c ost high maintenance cost so lower cost 20 Repair Relatively easy Diffic ult due to complex Difficult due to complex structure struc ture 21 Cooling Requirement Not required Not required Requires active or passive cooling which could increase cost 22 Cabling Well known, and lower Well Understood but yet difficult Complex and under cabling losses due to higher number of arrays, development. Cabling losses along with high cabling losses expected to be high 23 Suitability for Grid Good Good Good Technology 38
  • 39. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 3.4 Conclusion on selection of technology Each of the above technologies has their own particular strengths and weaknesses which have played a role in our decision making. We have decided to use Copper Indium Selenium (CIS) Thin film modules as our preferred technology. These advantages and disadvantages in addition with their market availability and costing are the key parameters on basis of which we have taken our technological decision. In the section 4.3 we have compared various technologies, and justification of why we have chosen a particular technology. In the below section we have compared the CIS, vis a vis Crystalline, Amorphous technologies. Characteristic CIS Crystalline Amorphous Remarks Module efficiency ++ +++ - cSi still higher than CIS, but the difference is getting narrow Appearance ++ - ++ CIS modules are all black, and therefore very compatible with roof settings High Temperature - - ++ CIS and cSi do not have anneal effect Light soaking effect ++ - - CIS has light soaking effect. Higher than nominal power output is expected. Degradation ++ ++ - Degradation rate is almost same as Crystalline. Production cost ++ + ++ Unit production cost of CIS modules expected to decrease by mass production but not in the case of crystalline module. Manufacturing process + - + Simple processes allow a smooth and efficient production overall Environmental + - + Environmentally friendly - CIS modules do contribution not include toxic or pollutant elements Energy payback time ++ + ++ Manufacture of CIS modules require only a small amount of energy Issue of raw materials ++ - + CIS products do not use silicon, thus less affected by market volatility 39
  • 40. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 4 POWER PLANT DESIGN CRITERIA The Power Plant is sized on the following major criteria: • Solar Power (average insulation available) • Power evacuation facility in the vicinity of the proposed site along with Grid availability on 24 Hours a day basis. Details of the design process and are presented in the below sections. 4.1 Design and Simulation projections by PVSYST PVSYST tool is one of the most accepted design tool for the study, sizing, simulation and data analysis of complete PV systems. We have used this tool to generate the most realistic energy yield simulation results which are detailed in this report. Main features of PVSYST: 1) Detailed computation of the used components (modules, inverters, etc) 2) Simulation on hourly basis and detailed evaluation and consideration of different loss factors. 3) Calculation of arbitrary orientated module planes (fixed and tracking systems) 4) Most accepted and used tool to generate simulation results for big PV power plants, as the results are based on systematic and refined approach. 5) Program with the most accurate results and functions at the market. 40
  • 41. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh 4.2 PV Power Plant Energy Production The system lifetime energy production is calculated by determining the first- year energy generation as expressed in kWh (AC)/kWp (AC), then degrading output over the system life based on an annual performance degradation rate. System degradation (largely a function of PV panel type and manufacturing quality) and its predictability are important factors in lifecycle costs since they determine the probable level of future cash flows. This stream of energy produced is then discounted to derive a present value of the energy generated to make a levelized cost calculation. The first year kWh/kWp is a function of the: • The amount of sunshine the project site receives in a year. • The mounting and orientation of the system (i.e., flat, fixed-tilt, tracking, etc.). • The spacing between PV panels as expressed in terms of system ground coverage ratio (GCR). • The energy harvest of the PV panel (i.e., performance sensitivity to high temperatures, sensitivity to low or diffuse light, etc.). • System losses from soiling, transformers, inverters, and wiring inefficiencies. • System availability largely driven by inverter downtime. 4.3 PV power plant capacity factor The capacity factor, a standard methodology used in the utility industry to measure the productivity of energy generating assets, is a key driver of a solar power plant’s economics. 41
  • 42. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh A PV power plant’s capacity factor is a function of the insulation at the project location, the performance of the PV panel (primarily as it relates to high- temperature performance), and the orientation of the PV panel to the sun, the system electrical efficiencies, and the availability of the power plant to produce power. 4.4 Selection of Inverter and Components For a complete reliable system and to ensure high energy yield from the plant, innovative components with latest technology are selected. The inverter that is selected is of very high efficiency over a wide range of load. The inverter operates in excess of 95.0% efficiency in comparison with the requested of 93% efficiency. Design lifetime of the inverter is at 35,000 hours with rated power at 40°C. This is approximately 4.8 hours at full load per day to estimate the lifetime of 20 years. 4.5 Selection of Monitoring System Monitoring system requirement for a large power plant like 5 MW with state of the art technology, monitoring and analysis of is carried out. Few features are of the monitoring system are presented as follows: • Monitors the performance of the entire power plant (string wise monitoring, junction boxes, inverters, etc) • Evaluates (strings, inverter, nominal/actual value), quantity of DC Power & AC Power produced. • Measures instantaneous irradiation level and temperature at site. It also measures the module back surface temperature. 42
  • 43. Detailed Project Report on 5 MW SPV based power plant at Veerapuram, Anantapur district. Andhra Pradesh • Alerts in case of error (discrepancy in normal operation of components, like module string/ diodes/ inverter/ junction box / loose contacts/ etc,) to facilitate recognition and correction of the fault with minimum downtime. • Visualizes nominal status of the connected components via Control Center PC Software (diagnosis on site or remote) • Logs system data and error messages for further processing or storing • Stores and visualizes energy yield data (for life of the plant) in the Portal from where the data can be accessed remotely. 4.6 Design criteria for Cables and Junction boxes and The power plant will adopt the best engineering practice for complete cable routing in the power plant by using minimal cable length while connecting in series string, using optimal size cables to ensure the entire plant cable losses are minimum. The junction boxes proposed are completely pre-wired to ensure ease of installation, maintenance and eliminates any installation hassles. These junction boxes not only combine the DC power from strings but also monitor each string performance and feed the same data to the central monitoring system. 43