Calculate the Net Present Value (NPV) of the following project at 11% with the following cash flows: C0 ($600) C1 $220 C2 $500 C3 $250 Solution Statemnet showing Cash flows Particulars Time PVf@11% Amount PV Cash Outflows - 1.00 (600.00) (600.00) PV of Cash outflows (600.00) Cash inflows 1.00 0.9009 220.00 198.20 Cash inflows 2.00 0.8116 500.00 405.81 Cash inflows 3.00 0.7312 250.00 182.80 PV of Cash Inflows 786.81 NPV 186.81.