PMI Project Management Principles
A Point of Reference
(based on the 5th Edition PMBOK® Guide)
By Tom Tiede
Agenda
• What is PMI and the PMP?
• Why PMI Project Management Principles are
Useful to Know
• A Few Basic PMI Definitions
• Five Process Groups
oInitiating o Planning o Executing
oMonitoring and Controlling
oClosing
• Ten Knowledge Areas
o Integration
o Scope
o Time
o Cost
o Quality
o Human Resources
o Communication
o Risk
o Procurement
o Stakeholders
• Project Management Terms, such as:
oTriple Constraint
oProject Charter
oProject Management Plan
oWork Breakdown Structure (WBS)
oPredecessor Relationships o Earned
Value Management o Gold Plating
oResponsibilities Assignment Matrix
oForming, Storming, Norming, Performing,
Adjourning
oCommunication Noise
oRisk Probability and Impact Matrix
oContract Type
oStakeholder Power vs. Interest Grid
• Code of Ethics and Professional Conduct
oHonor
oResponsibility
oRespect o
Fairness o
Honesty
This material will cover the following project management topics:
2
The Project Management Institute (PMI) is the world’s largest membership
association for the advocacy of Project and Program management.
•Over 400,000 current members across 180 countries
•Over 600,000 PMI certification holders
•Their most widely recognized certification is the PMP (Project Management Professional).
The PMP credential recognizes your:
o Experience,
o Education, and
o Competency to lead and manage projects
•Earning the PMP credential requires:
o A bachelor’s degree and 4,500 hours of documented project management experience, or a
secondary degree and 7,500 hours of documented project management experience
o 35 hours of certified project management training
o Passing the certification exam
•Regardless of your inclination to pursue PMP certification, PMI project management principles
apply to your role as a project leader or stakeholder
The purpose of this material is to share a few PMI project management
principles that apply to your role as a project leader or stakeholder
What is PMI and the PMP?
3
Leveraging prescribed PMI project management principles reduces the
risk and impact of costly project omissions, changes, and errors.
Cost of Resolving Project Omissions, Changes, or Errors
(Illustrative)
Why Is This Useful to Know?
Project
Initiation
Project
Planning
Project
Execution
Project
Closure
The PMI approach places great emphasis on project initiation and planning when
requirements are clearly defined and agreed upon and the full scope of the project is planned
4
Let’s Start with a Few PMI Definitions
• PMBOK ® - the Project Management Book of Knowledge from
which PMI defines terms, standards, and good practices
• Portfolio – Projects, programs, and operations managed as a
group to achieve strategic objectives
• Program - A group of projects and program activities
managed in a coordinated way
• Project – a temporary endeavor undertaken to create a
unique product, service, or result
• Project Management – the application of knowledge, skills,
tools, and techniques to project management activities to
meet project requirements
• Project Manager – the person authorized by the performing
organization to direct the team accountable for realizing
project objectives
• Project Stakeholder – includes all project team members
and anyone impacted by or impacting the project
• Triple Constraint – the foundation of project management
is balancing scope, time, and cost. Quality is at the center of
the triple constraint
Portfolio
Programs
Projects
A few basic definitions:
Quality
5
Time Cost
Scope
Initiating Planning Executing
A process group is a logical grouping of activities, inputs, tools,
techniques, and outputs required for any type of project.
Monitoring
&
Controlling
Closing
Project Management Process Groups
6
Activities
Key
Outputs
Process
Groups
Define a new project or
new phase, identify
stakeholders, and
obtain authorization
“Authorize the Work”
Develop an integrated
project management
plan to attain project
objectives
“Plan the Work”
Complete the work and
satisfy project
objectives
“Work the Plan”
Track and review
project progress and
performance; manage
variance and change
“Control the Plan”
Finalize all activities
and formally close the
project or phase
“End the Work”
• Project Charter
• Stakeholder Register
• Project Mgt. Plans &
Related Documents
- Scope
- Requirements
- Schedule
- Cost
- Quality
- Human Resources
- Communication
- Risk
- Procurement
- Change
- Stakeholders
• Project Deliverables
• Work Performance
Data
• Team Performance
Assessments
• Project
Communications (e.g.
status reports)
• Selected Suppliers &
Agreements
• Change Requests
• Issue Log
• Change Logs
• Approved Change
Requests
• Work Performance
Information
• Schedule Forecasts
• Cost Forecasts
• Updates to Project
Plan
• Quality Control
Measurements
• Verified Deliverable
• Accepted Deliverables
• Final Product, Service,
or Result (i.e. purpose
of project)
• Closed Procurement
(e.g. formal signature
of acceptance)
The five process groups overlap and follow a basic cycle of “plan, do,
check, act” until project closure.
Process Group Overlap
Executing
Planning
Applying Project Management Process Groups
Planning Executing
Change
?
Complete
?
Closing
Time
“Plan, Do, Check, Act”
Initiating
No
No
Initiating Monitoring & Controlling
Closing
Monitoring &
Controlling
Yes
7
Yes
A project manager is responsible for applying and managing the following
ten knowledge areas:
Identify, define, combine, unify and coordinate activities within the Project Management Process
Knowledge Areas
GroupsIntegration
Ensure the project includes all work required to complete the project successfullyScope
Manage the timely completion of the projectTime
Manage the planning, estimating, budgeting, financing, funding, monitoring, and controlling of
cost to enable the project to be completed within the approved budgetCost
Determine quality policies , objectives, and responsibilities so that the project will satisfy the needs
for which it was undertakenQuality
Organize, manage, and lead the project team, including the identification of roles, responsibilities,
required skills, and reporting relationshipsHuman Resources
Ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval,
management, control, monitoring and disposition of project informationCommunication
Identify and assess risks, plan responses, and control risk to increase the likelihood and impact of
positive events and decrease the likelihood and impact of negative events on the projectRisk
Purchase or acquire and control products, services, or results needed from outside the project
teamProcurement
Identify people, groups, or organizations that could impact or be impacted by the project; analyze
expectations, and develop strategies to engage stakeholders in decisions and activitiesStakeholders
8
9
Activity within each knowledge area is applied based on the appropriate
process group.
Knowledge Areas & Process Groups
Each shaded intersection has defined activities, inputs,
tools & techniques, and outputs
Process Groups
Knowledge Areas
(Below)
Initiating Planning Executing Monitoring &
Controlling
Closing
Integration Applicable Applicable Applicable Applicable Applicable
Scope Applicable Applicable
Time Applicable Applicable
Cost Applicable Applicable
Quality Applicable Applicable Applicable
Human Resources Applicable Applicable
Communication Applicable Applicable Applicable
Risk Applicable Applicable
Procurement Applicable Applicable Applicable Applicable
Stakeholders Applicable Applicable Applicable Applicable
Track, review, and report progress
to meet performance objectivesChange Requests
D e v el o p
P r o jec t C h ar te r
D e v el o p
P r o jec t M g t. P lan
D ir e ct & M a n ag e
P r o jec t W o r k
Monitor & Control
Project Work
P e rfo r m
In t eg ra te d C h an g e
C o n t ro l
U p d ate s
R e p o r ts
C h a n g e R eq u e st s
Clo se
P r o jec t o r P h as e
U p d ate s
C h a n g e L o g
A p p ro v e d C h a n g e
R e q u e sts
F in a l P ro d u c t
S e rv ic e , o r R e su lts
Project SOW
Business Case
Agreements
A p p ro v e d
C h a n g e R eq u e st s
P r o jec t M g t . P lan
P r o jec t C h ar te r
P r o jec t M an a g e m e n t
P lan U p d at es
Project Documents,
Deliverables, & Work
Performance Data
1. Integration Management - Process Activities
Integration management connects all of the knowledge areas together
from beginning (project initiation) to end (project closure).
Develop a document that formally
authorizes the project
Define, prepare,
coordinate and
integrate all
subsidiary plans into
a comprehensive
plan
Lead and perform the work to
accomplish project objectives
Review all change requests,
approve changes, and manage
changes to deliverables and the
project management plan
Finalize all activities across all
Process Groups to formally
complete the project or phase
Key: Initiating Planning
Executing
Monitoring & Controlling
Closing
Note, additional inputs, outputs, tools and techniques not depicted may apply
10
• A typical charter will identify: o Business need or
justification o Scope (high level)
o Objectives (such as the intended product, service, or result)
o Requirements (high level)
o Risks (high level)
o Assumptions and constraints
o Stakeholders (primary)
o Timing (anticipated)
o Costs (anticipated)
• The charter must be signed by someone who can invest authority for the project
(typically senior management or a sponsor)
A project charter formally authorizes the project and the project manager
to apply resources to project activities. Per PMI, without a charter, there
is no project.
Project Charter
Project Charter
11
The project management plan is the collection of all plans and related
documents pertaining to planning, executing, monitoring, controlling, and
closing the project.
Project Management Plan
Project
Management
Plan
Procurement
Change
Scope
Cost
Process
Improvement
RiskStakeholders
Configuration
Schedule
Quality
Communication
12
13
A cc e p te d D e liv e r a b le s
P la n
S c o p e M a n a g e m e n t
C o lle c t
R e q u ir e m e n ts
D e fin e
S c o p e
C r e a te
W B S
V a lid a t e
S c o p e
C o n t ro l
S c o p e
S c o p e B a s e lin e
(S c o p e B a s e lin e , W B S ,
W B S D i ct io n a r y )
P r o je c t D o cu m e n ts
U p d a te s
C h a n g e R e q u e s t s
P r o je c t S co p e
S t a te m e n t
R e q s D o c u m e n t a t io n
R e q s T ra ce a b ilit y
M a tr ix
S c o p e M g t ;. P la n
R e q s M g t. P la n
C h a n g e R e q u e s t s
P r o je c t C h a r te r
This area includes collecting requirements, defining scope, creating the
work breakdown structure (WBS), and validating and controlling scope.
2. Scope Management - Process Activities
Project Scope is the work performed to deliver a product, service,
or result that satisfies specified features and functions
Note, additional inputs, outputs, tools and techniques not depicted may apply
Determine,
document, and
manage
stakeholder
needs and
requirements to
meet objectives
Create a plan that documents how
the project scope will be defined,
validated, and controlled
Develop a
detailed
description of
the project
and product
Subdivide project
deliverables into
smaller, more
manageable
components
Gain formal
acceptance of
completed project
deliverables
Monitor
status of the
project scope
and manage
changes to
the scope
baseline
Key: Initiating Planning
Executing
Monitoring & Controlling
Closing
Scope
Workshops
Interviews
Benchmarking
Context
Diagrams
Decomposition
of Work
Inspection
The WBS is the decomposition of the work to be performed. The output is
called the Scope Baseline.
Scope Baseline:
•Scope Statement – description of project scope, major deliverables, assumptions, and
constraints
•WBS – hierarchical decomposition of the total scope of work
•WBS Dictionary – provides details regarding the deliverables, activities, and scheduling
information of each component of the WBS
Illustrative WBS
Project Title
Work Breakdown Structure (WBS)
Deliverable 1
Work
Packages
Deliverable 2
Work
Packages
Control
Account
Planning
Packages
Work
Packages
Used when
insufficient detail is
available at the
work package level
Break down the work
into the smallest
level for which cost
and time can be
assessed and
administered
14
P lan
Sc h ed u le
M a n age m en t
Define
Activities
Sequence
Activities
E stim at e
A ct ivity R es o u rc e s
E stim at e
A ctivity D u ra tio ns
D e vel o p
Sc h ed u le
C o n t ro l
Sc h ed u le
Sc h ed u le B a se lin e
P r o jec t Sch e d u le
P r o jec t C ale n d ars
Exp. Judgment Deco
mposition Rolling
Wave Planning
P D M
D e p en d e n c ies
L ea d s/L ags
Exp. Judgment
Bottom Up PMIS
Exp. Judgment
Analogous
Parametric
3 Point
Reserve Anal.
P r o jec t Sch e d u le
N et w o r k D ia gr am s
A ctivity R es o u rc e
R e q u ir em e nts
R B S
A ct ivity D u ra tio n
E stim ates
Sc h ed u le M gt. P lan
A ct ivity L ist
M il est o n e List
Sc h ed u le Fo r e ca sts
P r o jec t C h ar te r
Sc o p e Ba se lin e
Time management includes all activity related to developing and
managing the project schedule.
3. Time Management – Process Activities
Establish the policies,
procedures, and
documentation for planning,
developing, managing,
executing, and controlling
the project schedule
Define and document specific
actions to be performed to
produce project deliverables
Identify and document
relationships among project
activities
Estimate the type and quantities of
material, human resources, or suppliers
required to perform each activity
Estimate the number of work periods
needed to complete individual activities
with estimated resources
Analyze activity sequences, durations,
resource requirements, and schedule
constraints to create the project schedule
Monitor the
status of project
activities to
update project
progress and
manage
changes to the
schedule
baseline to
achieve the plan
Key:
Initiating
Planning
Executing
Monitoring & Controlling
Closing
Note, additional inputs, outputs, tools and techniques not depicted may apply
15
Critical Path
Compression
Resource
Optimization PMIS
Below are a few of many terms project managers should know when
developing and managing a project schedule.
PMI Terms Descriptions
3-Pt. Estimating Based on estimated Pessimistic (P), Optimistic (O), and Most Likely (M) durations
Analogous Estimating High level, top down estimate based on similar projects (usually by a SME - subject matter expert) Bottom-Up
Estimating Estimate at the lowest level of the WBS (level 3) and then roll up for the total project estimate Parametric EstimatingBased on an
existing, comparable parameter (e.g. $/ft. in the same neighborhood)
Reserve Analysis Contingency (buffer based on known risk) & include in project budget or Managerial (buffer based on unknown
risks) Rolling Wave Planning An iterative technique used when future details aren't known; near term is planned in detail; future is higher level
Finish to Start (FS) Finish to Finish (FF) Start to Start (SS) Start to Finish (SF)
Time (Schedule) Management Terms
Predecessor
Relationships
Default relationship; B cannot
start until A is finished
B cannot finish until A is
finished
B cannot start until A starts
Rare, A starts before B
finishes (e.g. when replacing
an old system B with a new
system A)
Free Slack The latest an activity can start without delaying next activities
Total Slack The latest an activity can start without delaying project finish date
Float Often referred to as the same as Slack
Lag Lag (a delay) = the successor must wait due to some delay after the predecessor is complete
Lead Lead (an accelerant) = the successor can begin before the predecessor is complete
Schedule Compression Crashing or fast tracking the schedule to adjust the schedule to align with the plan
Fast Tracking Compression technique based on overlapping sequential activities (risky)
Resource Leveling Adjusting peaks and valleys to create a level usage of resources
Resource Smoothing Adjusting peaks and valleys to create a level usage of resources AND also accounts for individual resource limitations
A B
A
B
A
B
A
B
16
Plan
Cost Managem ent
Estimate
Costs
Determine
Budget
Control
Costs
Cost Baseline
Project Funding
Requirem ents
W ork Performance Info
Cost Forecasts
Change Requests
Updates
Exp. Judgment
Aggregation
Reserve Analysis
Funding LImits
Cost Mgt. Plan
Activity C ost Estimates
Basis of Estimates
This area includes defining how project costs will be managed, estimating
activity costs, determining the budget, and controlling costs.
4. Cost Management – Process Activities
Establish the
policies,
procedures, and
documentation
for planning,
managing,
expending, and
controlling
project costs
Develop an approximation
of the monetary resources
needed to complete
project activities
Aggregate estimated costs of
individual activities or work
packages to establish an
authorized cost baseline
Monitor the status of the
project to update project
costs and manage changes to
the cost baseline
Key: Initiating Planning
Executing
Monitoring & Controlling
Closing
Note, additional inputs, outputs, tools and techniques not depicted may apply
17
Analogous
Parametric
Bottom Up 3
Point Reserve
Earned Value
TCPI
Forecasting
PMIS
Reserve Anal.
IRR NPV ROI
Opportunity
$ Payback
EVM is a means of measuring project cost and schedule vs. the plan.
Earned Value Management (EVM)
Time
Dollars
Cost Baseline (“S” Curve)
Approved Time-Phased Budget
BAC
Budget at Completion (BAC) = total
project budget
ETC
Estimate to Complete (ETC) = cost to complete
the project based on current spending efficiency
EAC
Estimate at Completion (EAC) =
current projected final cost based on
current spending efficiency
Variance at Completion (VAC)
Cost Variance
(CV)
Cost Performance (CPI) = EV/AC
Schedule Performance (SPI) = EV/PV
Schedule Variance
(SV)
EV
Earned Value (EV) = budgeted cost for work actually completed
Planned Value (PV) = budgeted cost for work scheduled
18
Actual Cost (AC)
at point in time
AC
PV
Point in Time
Plan
Quality
Managem
ent
Perform Quality
Assurance
urements
Control
Quality
Quality Mgt. Plan
Process Improvement
Plan
Quality Metrics
Quality Checklists
Updates
Verified Deliverables
QC Measures
Validated Changes
Quality management includes identifying quality requirements and
standards, auditing requirements and control measurements, assessing
quality performance, and recommending changes, when needed.
5. Quality Management – Process Activities
Identify quality requirements
and/or standards for the
project and its deliverables,
and document how the project
will demonstrate compliance
Audit the quality requirements
and the results from quality
control measurements to ensure
appropriate standards and
operational definitions are used
Monitor and record results of
quality activities to assess
performance and recommend
necessary changes
Key: Initiating Planning
Executing
Monitoring & Controlling
Closing
19
Cost/Benefit
Cost of Quality
7 Basic Tools
Benchmarking
Sampling
Mea
s
Quality Audits
Controls
Charts
Process
Analysis
Quality Management Philosophies and Principles
Quality Philosophies:
• Total Quality Management (Deming) –
proactive approach with statistical analysis
• Zero Defects (Crosby) – Do it right the first time
• Fitness for Use (Juran) – Satisfy customer needs
• Continuous Improvement (Kaizen) – proactive
approach to process improvement
• Gold Plating – unacceptable practice of providing
more than requested
• Cost of Quality – cost of conforming is less than
cost of non-conforming
• Design of Experiments – isolate factors that
influence results
• 6 Sigma – strive for 99.9997% error free
• ISO 9000 – document what you do; do what you
document
Quality Principles:
• Define and satisfy customer needs
• Prevent rather than inspect
• Be proactive rather reactive
• Validate project processes
• Measure against approved
standards
• Continually improve
• Take accountability
PMI quality management principles are based on a few popular
philosophies.
20
Project managers should be familiar with common quality management
tools and terms.
Quality Management Tools and Terms
21
Tools Description
1. Cause and Effect Diagrams Fishbone (Ishikawa) diagram
2. Flowcharts Basic flow chart or GERT diagram with feedback loop
3. Checksheets Check list (e.g. pre-flight list to ensure you are "cockpit ready" before taking flight)
4. Pareto Diagrams Cumulative histogram (e.g. 80/20 rule)
5. Histograms Depiction of volume or frequency of occurrences of several events
6. Control Charts Depiction of process output over time with UCL & LCL at 3 sigma from mean
7. Scatter Diagrams Depicts pattern of results across two variables
Terms Description
Benchmarking Comparing actual or planned processes to comparable projects to identify best practices
Design of Experiments Variable based analysis (freeze all variables but one and assess outcome)
Statistical Sampling Using a % of the population and extrapolating the results within an acceptable confidence level
Quality Audits Identify best practices; identify gaps; share best practices; offer assistance to improve; highlight lessons learned
Process Analysis Assess process, identify root causes, alleviate root causes
Inspection Examination of work product and comparison to documented standards (e.g. reviews, audits)
85/15 Rule 85% of quality relates to mgt.; 15% is worker related
80/20 Rule 80% of problems come from 20% of the issues
Rule of 7 Must have 7 consecutive data points above or below mean to consider process "out of control"
Mean Time Before Failure MTBF, example quality metric
Mean Time to Repair MTTR, example quality metric
Grade vs. Quality Not the same; you can have a lower grade product with high quality and vice versa (e.g. automobile models)
Upper Control Limit UCL = 3 sigma above mean (average)
Lower Control Limit LCL = 3 sigma below mean (average)
Upper Specification Limit USL is customer established and can be above or below UCL
Lower Specification Limit USL is customer established and can be above or below LCL
Plan
HR Management
Acquire
Project Team
Develop
Project Team
Manage
Project Team
Change Requests
Updates
Org Charts
Job Descriptions
Org. Theory
Pre-
Assignment
Acquisition
Negotiation
Training
Team Building
Ground Rules
Recognition
Rewards
HR Mgt. Plan
Project Staff
Assignments
Resource Calendars
Team Performance
Assessments
Human resource management consists of planning, acquiring, developing,
and managing the project team.
6. Human Resource Management - Process Activities
Define roles,
responsibilities,
required skills,
and reporting
relationships
Confirm availability
and obtain the
necessary team
Improve competencies,
team interaction, the
team environment, and
enhance project team
performance
Track team member
performance, provide
feedback, resolve issues,
and manage changes to
the team to optimize team
performance
Key: Initiating Planning
Executing
Monitoring & Controlling
Closing
Note, additional inputs, outputs, tools and techniques not depicted may apply
22
Observations
Conversations
Conflict Mgt.
Performance
Appraisals
Responsibility assignment matrix (RAM) charts such as a “RACI” let each
team member know who is responsible for each activity and deliverable.
Roles and Responsibilities
• (R) Responsible - those who do the work
• (A) Accountable - The one who:
o Is ultimately answerable for the completion of the deliverable
o Delegates the work to those responsible
o Approves the work that the responsible person provides
• (C) Consulted – those whose opinions are sought (typically subject matter experts); typically this is a two
way communication
• (I) Informed – those who are kept up-to-date on progress; typically this is a one way communication
23
RACI Person
Activity Ann Ben Carlos Denny
Develop Schedule A R I I
Collect Requirements I A R C
Develop Test Plan I A R C
Develop Training Plan A C I R
Project Life Cycle - Team Building & Leadership Styles
Team Building Stages
• Forming – creating the team
• Storming – team chaos as people start
working with one another
• Norming – team behavior starts to
normalize
• Performing – team performs as a unit
• Adjourning – team completes work
and disbands
Situational Leadership Styles
• Directing – provide specific, clear
instructions and closely supervise
• Coaching – solicit input, offer rationale
and examples
• Facilitating –maintain team progress;
delegate day-to-day control
• Supporting – support and motivate the
team to complete objectives
Project managers should be aware of typical team building dynamics and
situational leadership styles across a project life cycle.
Time
24
Team Building:
Leadership Style:
Forming
Directing
Storming Norming Performing Adjourning
SupportingCoaching Facilitating
Project Life Cycle
Initiating Closing
Conflict Management
• Scheduling Priorities
• Scarce Resources
• Personal Work Styles
• Methodology/Details
• Cost/Budget
• Personalities
Recommended:
1. Collaborate/Problem Solve
2. Compromise/Reconcile
3. Force/Direct
Not Recommended:
1. Smooth/Accommodate
2. Withdraw/Avoid
Conflict is inevitable. A project manager should be aware of typical
sources of project conflict and recommended techniques to resolve them.
Sources of Conflict Conflict Resolution Techniques
25
Higher
Lower
Probability
of Conflict
Plan
Communication
Management
Manage
Communications
Communciation
Mgt. Plan
Control
Communications
Project Communications
Work Performance
Information
Change Requests
Roughly 90% of a project manager’s job is communication.
7. Communication Management - Process Activities
Develop a
communication
approach based
on stakeholder’s
informational
needs
Create, collect,
distribute, store,
and retrieve
information
Monitor and control
communication
throughout the entire
project life cycle
Key: Initiating Planning Executing
Monitoring & Controlling Closing
Note, additional inputs, outputs, tools and techniques not depicted may
apply
26
Req. Analysis
Technology
Models
Methods
Meetings
Models
Method
Systems
Reporting
Exp. Judgment
Systems
Meetings
Communication Paths
N
N N
N
•# of Communication Paths
equals [N x (N-1)]/2
•N equals # of Stakeholders
• Example: [4 x (4-1)]/2 = 6
Communication Methods
• Interactive – between two people
• Push – send to specific recipients
• Pull – recipient actively seeks information
Communication Management
Communication Types
• Active listening – receiver verifies correct
interpretation
• Effective listening – receiver observes visual
and vocal cues
• Feedback – sender receives feedback from
receiver
• Nonverbal - ~55% of communication (e.g.
body and facial language)
• Para-lingual – Voice characteristics
Project managers should be aware of the basics of effective
communication across the broad stakeholder community.
Sender/Encode Decode/Receiver
Transmit
Acknowledgement
Response
Communication Model
Noise
27
Noise
28
Plan
Risk Management
Identify
Risks
Perform
Qualitative Analysis
Perform
Quantitative
Analysis
Plan
Risk Response
Control
Risks
Updates
U pdates
Project Docum ents
Risk Register
(Risks & Triggers)
Risk Mgt. Plan
Updates
U pdates
8. Risk Management – Process Activities
Risks are possible events that could impact the project in a positive (an
opportunity) or negative (a threat) way.
Define how to
conduct risk
management
activities
Determine and document the
characteristics of risk which
may affect the project
Prioritize risks for further analysis or
action by assessing their probability of
occurrence and impact
Analyze the effect of
identified risks on overall
project objectives
Develop options
and actions to
enhance
opportunities and
reduce threats to
project objectives
Implement risk response plans, track identified
risks, monitor residual risks, identify new risks,
and evaluate risk process effectiveness
Key: Initiating Planning
Executing
Monitoring & Controlling
Closing
Note, additional inputs, outputs, tools and
techniques not depicted may apply
Risk Probability and Impact Matrix
High
Level of Impact
A probability and impact matrix can be used to evaluate the impact of a
risk and the probability of its occurrence.
Probability and Impact Matrix
Low
High
Moderate
Moderate
Probability of
Occurrence
Positive Risk Responses
•Share – split the responsibility
and benefit to maximize the
opportunity
•Exploit – take steps to ensure
success
•Enhance – improve the size of
the risk event and impact
•Accept – do nothing
Negative Risk Responses
•Avoid – get rid of the potential
problem
•Transfer – re-assign to another
party
•Mitigate – minimize the bad
characteristics of the risk
•Accept – do nothing
The higher the combined probability and impact of the risk
event the greater the need to develop a risk response plan
29
Project managers should be aware of risk management terms.
Risk Management Terms
•Monte Carlo – simulation of possible outcomes
•Risk Breakdown Structure – breakdown by category (e.g. internal, external, technology, organizational,
etc.)
•Risk Trigger – an indicator that an event “could” occur
•SWOT Analysis – strengths, weaknesses, opportunities, and threats
•Expected Monetary Value (EMV) – summation of probability x impact of alternative decisions (…not
to be confused with EVM – earned value management)
•Contingency Reserves – for known risks (include in budget and schedule)
•Management Reserves – for unknown risks (excluded from baselines for budget and schedule)
•Residual Risk – risk remaining after risk response
•Secondary Risk – potential risk as a result of risk response
•Workaround – “wing it” response when other risk response plans don’t work
•Types of Risk Tolerance
o Averse – Avoids risk
o Seeker – Seeks risk
o Neutral – Middle ground
30
Risk Management
Procurement
Mgt. Plan
Plan
Procurement Mgt.
Conduct
Procurements
Control
Procurements
Close
Procurements
Work Performance Info
Updates
Change Requests
Procurement Mgt. Plan
SOW
RFPs
Selection Criteria
Make Buy Decision
Selected Suppliers
Agreements
Resource Calendars
Exp. Judgment
Make Buy
Analysis
Seller Proposals
Closed Procurements
OPA Udpates
Procurement management includes planning, selecting, contracting,
controlling, and closing outsourced products and services.
9. Procurement Management – Process Activities
Document
project
procurement
decisions,
specify the
approach, and
identify
potential sellers
Obtain seller response,
select a seller, and
award a contract
Manage procurement
relationship, monitor contract
performance, and make changes
and corrections as appropriate
Complete each project
procurement, including
finalizing open claims,
updating records to
reflect final results, and
archiving information
Key:
Initiating
Planning
Executing
Monitoring & Controlling Closing
Note, additional inputs, outputs, tools and techniques not depicted may
apply
31
Exp. Judgment
Bidder Conf.
Ind. Estimates
Advertising
Inspect/Audits
Reporting A/P
Systems
Claims Admin.
Records Mgt.
Audits
Negotiations
Record Mgt.
Project managers should be aware of the benefits and risks of different
contract types from a buyer’s perspective and a seller’s perspective.
Contract Types
Buyer’s Risk
Seller’s Risk
Low High
High Low
• (FFP) Firm Fixed Price – allows buyer to budget fixed price; requires seller to detail scope and accurately
estimate price; very common
• (FFIF) Fixed Price Incentive Fee – includes incentive to motivate seller to produce at greater speed
• (FF EPA) Fixed Price Economic Price Adjustment – compensates for year to year economic changes
• (T&M) Time and Materials – typically used for smaller initiatives
• (PO) Purchase Order – typically used for commodity items
• (CPFF) Cost Plus Fixed Fee – typically variable costs are cost-plus and predictable costs are fixed fee
• (CPIF) Cost Plus Incentive Fee – actual costs plus incentive to motivate seller to produce at greater speed
• (CPAF) Cost Plus Award Fee – actual costs plus award based on customer satisfaction with agreed criteria
• (CPPC) Cost Plus Percent of Cost – actual cost plus % of actual; the higher the cost, the higher the fees
32
FFP FPIF FP EPA T&M PO CPFF CPIF CPAF CPPC
Project managers should be familiar with additional procurement terms
in the table below:
Procurement Terms
33
Terms Description
Make or Buy Analysis Is it more practical to insource or outsource (based on a cost comparison between the two)?
Bidder Conference Prior to bid submission, offers opportunities for prospective sellers to obtain requirements clarification from buyer
Independent Estimates Used to validate proposal information
Contract (CCOLA) Must have 5 Components: Capacity, Consideration, Offer, Legal Purpose, Acceptance
Point of Total Assumption Point at which seller is responsible for all cost overruns; PTA = (Ceiling Price - Target Price)/Buyer Share + Target Cost
Ceiling Price % of Target Cost (e.g. Ceiling = 140% of target cost)
Target Cost Expected cost of work in the contract
Target Price Equals Target Cost + Target Profit
Share Ratio Ratio of split between buyer and seller of cost savings or overruns (e.g. 70/30)
RFP Request for Proposal, typically used for higher priced, customized services or products
RFQ Request for Quote, typically used for small dollar commodity type products
IFB Invitation to Bid, used for government sealed bids (similar to RFP)
Design Scope of Work (SOW) Buyer provides exact details; generally results in fixed price contract
Functional Scope of Work (SOW) Buyer provides functionality needed; generally results in cost plus contract
Sole Source Go direct to a supplier without any available competition (e.g. supplier holds the patent)
Single Source Go direct to a supplier although competitors are available (e.g. "preferred supplier")
Negotiation PMI prefers "win/win" negotiation approach
Standard Terms & Conditions Typical common (non-negotiable) contract items with a tight range or parameters
Special Provisions Typically added to account for changes to standard terms and conditions
Claims Administration Means of administering contested changes or disagreements regarding compensation
ADR Alternative dispute resolution (e.g. arbitration) used when claims cannot be negotiated between buyer and seller
Identify
Stakeholders
Plan
Stakeholder
Management
Manage
Stakeholder
Engagement
Stakeholder Register
Stakeholder Mgt. Plan
Control
Stakeholder
Engagement
Issue Log
Change Requests
Updates
Work Performance Info
Change Requests
Updates
Stakeholder
Engagement Matrix
(Unaware, Neutral,
Resistance, Leading)
It is critical to project success to identify stakeholders, address their
requirements, meet their expectations, and foster their engagement.
10. Stakeholder Management – Process Activities
Identify the people,
groups, or
organizations that
could impact or be
impacted by the
decision, activity, or
outcome of the
project.
Develop appropriate management
strategies to effectively engage
stakeholders throughout the project
life cycle based on their needs and
potential impact on project success
Communicate and work with stakeholders to meet
their needs and expectations, address issues as
they occur, and foster appropriate stakeholder
engagement throughout the project life cycle
Monitor overall
project stakeholder
relationships and
adjust strategies and
plans for engaging
stakeholders
Key: Initiating Planning
Executing
Monitoring & Controlling
Closing
Note, additional inputs, outputs, tools and techniques not depicted may apply
34
Exp. Judgment
Stakeholder
Analysis (Power/
Interest)
Interpersonal
Skills
Management
Skills
All stakeholders are different and, therefore, need to be managed
differently based on their relative authority (power) and level of concern
(interest).
Stakeholder
Stakeholder Power vs. Interest Grid
Low High
High
Moderate
Moderate
Power
Interest
Power vs. Interest Grid
35
Keep Satisfied Manage Closely
Monitor Keep Informed
All PMI members must agree to adhere to a high personal standard of
ethical and professional behavior.
Tenets of Code:
1.Honor
o Do what is right and honorable
o Set high standards for yourself and aspire to meet those standards is all aspects of life
2.Responsibility – Take ownership of:
o The decisions you make or fail to make
o The actions you take or fail to take
o The consequences that result
3.Respect
o Show high regard for yourself, others, and the resources (e.g. people, money, reputation, safety)
entrusted to you
o Engender trust confidence, performance excellence, and mutual cooperation in an environment
of diverse perspectives and views
4.Fairness
o Make decisions and act impartially and objectively
o Conduct yourself in a way free from competing self interest, prejudice, and favoritism
5.Honesty
o Understand the truth
o Act in a truthful manner both in your communication and in your conduct
PMI Code of Ethics and Professional Conduct
36
37
Summary
• What is PMI and the PMP?
• Why PMI Project Management Principles are
Useful to Know
• A Few Basic PMI Definitions
• Five Process Groups
oInitiating o Planning o Executing
oMonitoring and Controlling
oClosing
• Ten Knowledge Areas
o Integration
o Scope
o Time
o Cost
o Quality
o Human Resources
o Communication
o Risk
o Procurement
o Stakeholders
• Project Management Terms, such as:
oTriple Constraint
oProject Charter
oProject Management Plan
oWork Breakdown Structure (WBS)
oPredecessor Relationships o Earned
Value Management o Gold Plating
oResponsibilities Assignment Matrix
oForming, Storming, Norming, Performing,
Adjourning
oCommunication Noise
oRisk Probability and Impact Matrix
oContract Type
oStakeholder Power vs. Interest Grid
• Code of Ethics and Professional Conduct
oHonor
oResponsibility
oRespect o
Fairness o
Honesty
This material covered the following project management topics:
Thank you for taking the time to review this material!

Contenu connexe

Tendances

5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Amr Miqdadi
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
PMI Project Management Model Overview (PMBOK 4th Edition)
PMI Project Management Model Overview (PMBOK 4th Edition)PMI Project Management Model Overview (PMBOK 4th Edition)
PMI Project Management Model Overview (PMBOK 4th Edition)Sandro Pasini, MBA, PMP
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Amr Miqdadi
 
Pre planning for large ERP/CRM initiative
Pre planning for large ERP/CRM  initiativePre planning for large ERP/CRM  initiative
Pre planning for large ERP/CRM initiativesureshgk
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management areaZaur Ahmadov, PMP
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management Yesica Adicondro
 
Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...Megha Kotak, PMP
 
PMP PMBok 5th Project management processes
PMP PMBok 5th Project management processesPMP PMBok 5th Project management processes
PMP PMBok 5th Project management processesAbdullah Ahmed, PMP, RMP
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Managementchaitanyakrsk
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project portfolio formation framework
Project portfolio formation frameworkProject portfolio formation framework
Project portfolio formation frameworkReza Masoumi
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI ApproachZaur Ahmadov, PMP
 
14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT ProjectsBhuWan Khadka
 

Tendances (20)

5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4Undestand PMBok 5th, Section 4
Undestand PMBok 5th, Section 4
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
PMI Project Management Model Overview (PMBOK 4th Edition)
PMI Project Management Model Overview (PMBOK 4th Edition)PMI Project Management Model Overview (PMBOK 4th Edition)
PMI Project Management Model Overview (PMBOK 4th Edition)
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2
 
Pre planning for large ERP/CRM initiative
Pre planning for large ERP/CRM  initiativePre planning for large ERP/CRM  initiative
Pre planning for large ERP/CRM initiative
 
PMP-Integration Management area
PMP-Integration Management  areaPMP-Integration Management  area
PMP-Integration Management area
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...Project lifecycle management @ Pharma Project Management Conference - 2014, M...
Project lifecycle management @ Pharma Project Management Conference - 2014, M...
 
PMP PMBok 5th Project management processes
PMP PMBok 5th Project management processesPMP PMBok 5th Project management processes
PMP PMBok 5th Project management processes
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
 
1. introduction
1. introduction1. introduction
1. introduction
 
Chap04 project integration management
Chap04 project integration managementChap04 project integration management
Chap04 project integration management
 
Project Management
Project ManagementProject Management
Project Management
 
Project portfolio formation framework
Project portfolio formation frameworkProject portfolio formation framework
Project portfolio formation framework
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
 
14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects14. Developing Custom Processes For IT Projects
14. Developing Custom Processes For IT Projects
 

Similaire à PmiprojectmanagementprinciplesAmit Payal

PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
pmi project management principles.pptx
pmi project management principles.pptxpmi project management principles.pptx
pmi project management principles.pptxssusere01f83
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...Chandrasen Sharma
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management FundamentalsInsaf Ali Soomro PMP
 
1. Introduction to Project Management and the Project Management Framework
1. Introduction to Project Management and the Project Management Framework1. Introduction to Project Management and the Project Management Framework
1. Introduction to Project Management and the Project Management FrameworkMeshack Shack
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdfMUST
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsJacobs Engineering
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxSabrinaScott22
 
Top Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars
 

Similaire à PmiprojectmanagementprinciplesAmit Payal (20)

PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
pmi project management principles.pptx
pmi project management principles.pptxpmi project management principles.pptx
pmi project management principles.pptx
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals12 Terms You Should Know Project Management Fundamentals
12 Terms You Should Know Project Management Fundamentals
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
Ibm projectmgmt-1
Ibm  projectmgmt-1Ibm  projectmgmt-1
Ibm projectmgmt-1
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
1. Introduction to Project Management and the Project Management Framework
1. Introduction to Project Management and the Project Management Framework1. Introduction to Project Management and the Project Management Framework
1. Introduction to Project Management and the Project Management Framework
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
INTRO.pptx
INTRO.pptxINTRO.pptx
INTRO.pptx
 
L1-Project Integration Management.pdf
L1-Project Integration Management.pdfL1-Project Integration Management.pdf
L1-Project Integration Management.pdf
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
PM & PM LC.pptx
PM & PM LC.pptxPM & PM LC.pptx
PM & PM LC.pptx
 
6396901
63969016396901
6396901
 
PPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptxPPT1-PROJECT-_-Project-Management.pptx
PPT1-PROJECT-_-Project-Management.pptx
 
Top Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad Thalji
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
Session 1 PMP 4th edition
Session 1 PMP 4th editionSession 1 PMP 4th edition
Session 1 PMP 4th edition
 

Plus de AMIT PAYAL

Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)AMIT PAYAL
 
Projectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit PayalProjectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit PayalAMIT PAYAL
 
Projectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit PayalProjectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit PayalAMIT PAYAL
 
Wonderful dream home r 1-Amit Payal
Wonderful dream home r 1-Amit PayalWonderful dream home r 1-Amit Payal
Wonderful dream home r 1-Amit PayalAMIT PAYAL
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalAMIT PAYAL
 
Maintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit PayalMaintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit PayalAMIT PAYAL
 
Expert for construction-Amit Payal
Expert for construction-Amit PayalExpert for construction-Amit Payal
Expert for construction-Amit PayalAMIT PAYAL
 
Cracksanushakdv Amit Payal
Cracksanushakdv Amit PayalCracksanushakdv Amit Payal
Cracksanushakdv Amit PayalAMIT PAYAL
 
Contractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit PayalContractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit PayalAMIT PAYAL
 
Wonder cement & concrete-Amit Payal
Wonder cement & concrete-Amit PayalWonder cement & concrete-Amit Payal
Wonder cement & concrete-Amit PayalAMIT PAYAL
 
Contractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit PayalContractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit PayalAMIT PAYAL
 
Constructionprojectmanagement Amit Payal
Constructionprojectmanagement Amit PayalConstructionprojectmanagement Amit Payal
Constructionprojectmanagement Amit PayalAMIT PAYAL
 
Wonder cement & concrete ppt april '2020(Amit Payal)
Wonder cement & concrete ppt april '2020(Amit Payal)Wonder cement & concrete ppt april '2020(Amit Payal)
Wonder cement & concrete ppt april '2020(Amit Payal)AMIT PAYAL
 
Technical services cptp-Amit Payal
Technical services   cptp-Amit PayalTechnical services   cptp-Amit Payal
Technical services cptp-Amit PayalAMIT PAYAL
 
Building cracks causes & remedies byAmit Payal
Building cracks causes & remedies byAmit PayalBuilding cracks causes & remedies byAmit Payal
Building cracks causes & remedies byAmit PayalAMIT PAYAL
 
Sikarmktgamit-Amit Payal
Sikarmktgamit-Amit PayalSikarmktgamit-Amit Payal
Sikarmktgamit-Amit PayalAMIT PAYAL
 
Saathi profile diary-Amit Payal
Saathi profile diary-Amit PayalSaathi profile diary-Amit Payal
Saathi profile diary-Amit PayalAMIT PAYAL
 
Typesofcracks Amit Payal
Typesofcracks Amit PayalTypesofcracks Amit Payal
Typesofcracks Amit PayalAMIT PAYAL
 
Typesofcracks 180101221007-AmitPayal
Typesofcracks 180101221007-AmitPayalTypesofcracks 180101221007-AmitPayal
Typesofcracks 180101221007-AmitPayalAMIT PAYAL
 

Plus de AMIT PAYAL (20)

Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
Projectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit PayalProjectplanningandprojectworkplan Amit Payal
Projectplanningandprojectworkplan Amit Payal
 
Projectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit PayalProjectmanagementconceptscases Amit Payal
Projectmanagementconceptscases Amit Payal
 
Wonderful dream home r 1-Amit Payal
Wonderful dream home r 1-Amit PayalWonderful dream home r 1-Amit Payal
Wonderful dream home r 1-Amit Payal
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
 
Maintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit PayalMaintenanceandrepairofbuildings Amit Payal
Maintenanceandrepairofbuildings Amit Payal
 
Expert for construction-Amit Payal
Expert for construction-Amit PayalExpert for construction-Amit Payal
Expert for construction-Amit Payal
 
Cracksanushakdv Amit Payal
Cracksanushakdv Amit PayalCracksanushakdv Amit Payal
Cracksanushakdv Amit Payal
 
Contractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit PayalContractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit Payal
 
Wonder cement & concrete-Amit Payal
Wonder cement & concrete-Amit PayalWonder cement & concrete-Amit Payal
Wonder cement & concrete-Amit Payal
 
Contractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit PayalContractor meet ppt slides Amit Payal
Contractor meet ppt slides Amit Payal
 
Constructionprojectmanagement Amit Payal
Constructionprojectmanagement Amit PayalConstructionprojectmanagement Amit Payal
Constructionprojectmanagement Amit Payal
 
Wonder cement & concrete ppt april '2020(Amit Payal)
Wonder cement & concrete ppt april '2020(Amit Payal)Wonder cement & concrete ppt april '2020(Amit Payal)
Wonder cement & concrete ppt april '2020(Amit Payal)
 
Technical services cptp-Amit Payal
Technical services   cptp-Amit PayalTechnical services   cptp-Amit Payal
Technical services cptp-Amit Payal
 
Building cracks causes & remedies byAmit Payal
Building cracks causes & remedies byAmit PayalBuilding cracks causes & remedies byAmit Payal
Building cracks causes & remedies byAmit Payal
 
Sikarmktgamit-Amit Payal
Sikarmktgamit-Amit PayalSikarmktgamit-Amit Payal
Sikarmktgamit-Amit Payal
 
Saathi profile diary-Amit Payal
Saathi profile diary-Amit PayalSaathi profile diary-Amit Payal
Saathi profile diary-Amit Payal
 
Typesofcracks Amit Payal
Typesofcracks Amit PayalTypesofcracks Amit Payal
Typesofcracks Amit Payal
 
Typesofcracks 180101221007-AmitPayal
Typesofcracks 180101221007-AmitPayalTypesofcracks 180101221007-AmitPayal
Typesofcracks 180101221007-AmitPayal
 

Dernier

Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 

Dernier (20)

Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 

PmiprojectmanagementprinciplesAmit Payal

  • 1. PMI Project Management Principles A Point of Reference (based on the 5th Edition PMBOK® Guide) By Tom Tiede
  • 2. Agenda • What is PMI and the PMP? • Why PMI Project Management Principles are Useful to Know • A Few Basic PMI Definitions • Five Process Groups oInitiating o Planning o Executing oMonitoring and Controlling oClosing • Ten Knowledge Areas o Integration o Scope o Time o Cost o Quality o Human Resources o Communication o Risk o Procurement o Stakeholders • Project Management Terms, such as: oTriple Constraint oProject Charter oProject Management Plan oWork Breakdown Structure (WBS) oPredecessor Relationships o Earned Value Management o Gold Plating oResponsibilities Assignment Matrix oForming, Storming, Norming, Performing, Adjourning oCommunication Noise oRisk Probability and Impact Matrix oContract Type oStakeholder Power vs. Interest Grid • Code of Ethics and Professional Conduct oHonor oResponsibility oRespect o Fairness o Honesty This material will cover the following project management topics: 2
  • 3. The Project Management Institute (PMI) is the world’s largest membership association for the advocacy of Project and Program management. •Over 400,000 current members across 180 countries •Over 600,000 PMI certification holders •Their most widely recognized certification is the PMP (Project Management Professional). The PMP credential recognizes your: o Experience, o Education, and o Competency to lead and manage projects •Earning the PMP credential requires: o A bachelor’s degree and 4,500 hours of documented project management experience, or a secondary degree and 7,500 hours of documented project management experience o 35 hours of certified project management training o Passing the certification exam •Regardless of your inclination to pursue PMP certification, PMI project management principles apply to your role as a project leader or stakeholder The purpose of this material is to share a few PMI project management principles that apply to your role as a project leader or stakeholder What is PMI and the PMP? 3
  • 4. Leveraging prescribed PMI project management principles reduces the risk and impact of costly project omissions, changes, and errors. Cost of Resolving Project Omissions, Changes, or Errors (Illustrative) Why Is This Useful to Know? Project Initiation Project Planning Project Execution Project Closure The PMI approach places great emphasis on project initiation and planning when requirements are clearly defined and agreed upon and the full scope of the project is planned 4
  • 5. Let’s Start with a Few PMI Definitions • PMBOK ® - the Project Management Book of Knowledge from which PMI defines terms, standards, and good practices • Portfolio – Projects, programs, and operations managed as a group to achieve strategic objectives • Program - A group of projects and program activities managed in a coordinated way • Project – a temporary endeavor undertaken to create a unique product, service, or result • Project Management – the application of knowledge, skills, tools, and techniques to project management activities to meet project requirements • Project Manager – the person authorized by the performing organization to direct the team accountable for realizing project objectives • Project Stakeholder – includes all project team members and anyone impacted by or impacting the project • Triple Constraint – the foundation of project management is balancing scope, time, and cost. Quality is at the center of the triple constraint Portfolio Programs Projects A few basic definitions: Quality 5 Time Cost Scope
  • 6. Initiating Planning Executing A process group is a logical grouping of activities, inputs, tools, techniques, and outputs required for any type of project. Monitoring & Controlling Closing Project Management Process Groups 6 Activities Key Outputs Process Groups Define a new project or new phase, identify stakeholders, and obtain authorization “Authorize the Work” Develop an integrated project management plan to attain project objectives “Plan the Work” Complete the work and satisfy project objectives “Work the Plan” Track and review project progress and performance; manage variance and change “Control the Plan” Finalize all activities and formally close the project or phase “End the Work” • Project Charter • Stakeholder Register • Project Mgt. Plans & Related Documents - Scope - Requirements - Schedule - Cost - Quality - Human Resources - Communication - Risk - Procurement - Change - Stakeholders • Project Deliverables • Work Performance Data • Team Performance Assessments • Project Communications (e.g. status reports) • Selected Suppliers & Agreements • Change Requests • Issue Log • Change Logs • Approved Change Requests • Work Performance Information • Schedule Forecasts • Cost Forecasts • Updates to Project Plan • Quality Control Measurements • Verified Deliverable • Accepted Deliverables • Final Product, Service, or Result (i.e. purpose of project) • Closed Procurement (e.g. formal signature of acceptance)
  • 7. The five process groups overlap and follow a basic cycle of “plan, do, check, act” until project closure. Process Group Overlap Executing Planning Applying Project Management Process Groups Planning Executing Change ? Complete ? Closing Time “Plan, Do, Check, Act” Initiating No No Initiating Monitoring & Controlling Closing Monitoring & Controlling Yes 7 Yes
  • 8. A project manager is responsible for applying and managing the following ten knowledge areas: Identify, define, combine, unify and coordinate activities within the Project Management Process Knowledge Areas GroupsIntegration Ensure the project includes all work required to complete the project successfullyScope Manage the timely completion of the projectTime Manage the planning, estimating, budgeting, financing, funding, monitoring, and controlling of cost to enable the project to be completed within the approved budgetCost Determine quality policies , objectives, and responsibilities so that the project will satisfy the needs for which it was undertakenQuality Organize, manage, and lead the project team, including the identification of roles, responsibilities, required skills, and reporting relationshipsHuman Resources Ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring and disposition of project informationCommunication Identify and assess risks, plan responses, and control risk to increase the likelihood and impact of positive events and decrease the likelihood and impact of negative events on the projectRisk Purchase or acquire and control products, services, or results needed from outside the project teamProcurement Identify people, groups, or organizations that could impact or be impacted by the project; analyze expectations, and develop strategies to engage stakeholders in decisions and activitiesStakeholders 8
  • 9. 9 Activity within each knowledge area is applied based on the appropriate process group. Knowledge Areas & Process Groups Each shaded intersection has defined activities, inputs, tools & techniques, and outputs Process Groups Knowledge Areas (Below) Initiating Planning Executing Monitoring & Controlling Closing Integration Applicable Applicable Applicable Applicable Applicable Scope Applicable Applicable Time Applicable Applicable Cost Applicable Applicable Quality Applicable Applicable Applicable Human Resources Applicable Applicable Communication Applicable Applicable Applicable Risk Applicable Applicable Procurement Applicable Applicable Applicable Applicable Stakeholders Applicable Applicable Applicable Applicable
  • 10. Track, review, and report progress to meet performance objectivesChange Requests D e v el o p P r o jec t C h ar te r D e v el o p P r o jec t M g t. P lan D ir e ct & M a n ag e P r o jec t W o r k Monitor & Control Project Work P e rfo r m In t eg ra te d C h an g e C o n t ro l U p d ate s R e p o r ts C h a n g e R eq u e st s Clo se P r o jec t o r P h as e U p d ate s C h a n g e L o g A p p ro v e d C h a n g e R e q u e sts F in a l P ro d u c t S e rv ic e , o r R e su lts Project SOW Business Case Agreements A p p ro v e d C h a n g e R eq u e st s P r o jec t M g t . P lan P r o jec t C h ar te r P r o jec t M an a g e m e n t P lan U p d at es Project Documents, Deliverables, & Work Performance Data 1. Integration Management - Process Activities Integration management connects all of the knowledge areas together from beginning (project initiation) to end (project closure). Develop a document that formally authorizes the project Define, prepare, coordinate and integrate all subsidiary plans into a comprehensive plan Lead and perform the work to accomplish project objectives Review all change requests, approve changes, and manage changes to deliverables and the project management plan Finalize all activities across all Process Groups to formally complete the project or phase Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply 10
  • 11. • A typical charter will identify: o Business need or justification o Scope (high level) o Objectives (such as the intended product, service, or result) o Requirements (high level) o Risks (high level) o Assumptions and constraints o Stakeholders (primary) o Timing (anticipated) o Costs (anticipated) • The charter must be signed by someone who can invest authority for the project (typically senior management or a sponsor) A project charter formally authorizes the project and the project manager to apply resources to project activities. Per PMI, without a charter, there is no project. Project Charter Project Charter 11
  • 12. The project management plan is the collection of all plans and related documents pertaining to planning, executing, monitoring, controlling, and closing the project. Project Management Plan Project Management Plan Procurement Change Scope Cost Process Improvement RiskStakeholders Configuration Schedule Quality Communication 12
  • 13. 13 A cc e p te d D e liv e r a b le s P la n S c o p e M a n a g e m e n t C o lle c t R e q u ir e m e n ts D e fin e S c o p e C r e a te W B S V a lid a t e S c o p e C o n t ro l S c o p e S c o p e B a s e lin e (S c o p e B a s e lin e , W B S , W B S D i ct io n a r y ) P r o je c t D o cu m e n ts U p d a te s C h a n g e R e q u e s t s P r o je c t S co p e S t a te m e n t R e q s D o c u m e n t a t io n R e q s T ra ce a b ilit y M a tr ix S c o p e M g t ;. P la n R e q s M g t. P la n C h a n g e R e q u e s t s P r o je c t C h a r te r This area includes collecting requirements, defining scope, creating the work breakdown structure (WBS), and validating and controlling scope. 2. Scope Management - Process Activities Project Scope is the work performed to deliver a product, service, or result that satisfies specified features and functions Note, additional inputs, outputs, tools and techniques not depicted may apply Determine, document, and manage stakeholder needs and requirements to meet objectives Create a plan that documents how the project scope will be defined, validated, and controlled Develop a detailed description of the project and product Subdivide project deliverables into smaller, more manageable components Gain formal acceptance of completed project deliverables Monitor status of the project scope and manage changes to the scope baseline Key: Initiating Planning Executing Monitoring & Controlling Closing Scope Workshops Interviews Benchmarking Context Diagrams Decomposition of Work Inspection
  • 14. The WBS is the decomposition of the work to be performed. The output is called the Scope Baseline. Scope Baseline: •Scope Statement – description of project scope, major deliverables, assumptions, and constraints •WBS – hierarchical decomposition of the total scope of work •WBS Dictionary – provides details regarding the deliverables, activities, and scheduling information of each component of the WBS Illustrative WBS Project Title Work Breakdown Structure (WBS) Deliverable 1 Work Packages Deliverable 2 Work Packages Control Account Planning Packages Work Packages Used when insufficient detail is available at the work package level Break down the work into the smallest level for which cost and time can be assessed and administered 14
  • 15. P lan Sc h ed u le M a n age m en t Define Activities Sequence Activities E stim at e A ct ivity R es o u rc e s E stim at e A ctivity D u ra tio ns D e vel o p Sc h ed u le C o n t ro l Sc h ed u le Sc h ed u le B a se lin e P r o jec t Sch e d u le P r o jec t C ale n d ars Exp. Judgment Deco mposition Rolling Wave Planning P D M D e p en d e n c ies L ea d s/L ags Exp. Judgment Bottom Up PMIS Exp. Judgment Analogous Parametric 3 Point Reserve Anal. P r o jec t Sch e d u le N et w o r k D ia gr am s A ctivity R es o u rc e R e q u ir em e nts R B S A ct ivity D u ra tio n E stim ates Sc h ed u le M gt. P lan A ct ivity L ist M il est o n e List Sc h ed u le Fo r e ca sts P r o jec t C h ar te r Sc o p e Ba se lin e Time management includes all activity related to developing and managing the project schedule. 3. Time Management – Process Activities Establish the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule Define and document specific actions to be performed to produce project deliverables Identify and document relationships among project activities Estimate the type and quantities of material, human resources, or suppliers required to perform each activity Estimate the number of work periods needed to complete individual activities with estimated resources Analyze activity sequences, durations, resource requirements, and schedule constraints to create the project schedule Monitor the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply 15 Critical Path Compression Resource Optimization PMIS
  • 16. Below are a few of many terms project managers should know when developing and managing a project schedule. PMI Terms Descriptions 3-Pt. Estimating Based on estimated Pessimistic (P), Optimistic (O), and Most Likely (M) durations Analogous Estimating High level, top down estimate based on similar projects (usually by a SME - subject matter expert) Bottom-Up Estimating Estimate at the lowest level of the WBS (level 3) and then roll up for the total project estimate Parametric EstimatingBased on an existing, comparable parameter (e.g. $/ft. in the same neighborhood) Reserve Analysis Contingency (buffer based on known risk) & include in project budget or Managerial (buffer based on unknown risks) Rolling Wave Planning An iterative technique used when future details aren't known; near term is planned in detail; future is higher level Finish to Start (FS) Finish to Finish (FF) Start to Start (SS) Start to Finish (SF) Time (Schedule) Management Terms Predecessor Relationships Default relationship; B cannot start until A is finished B cannot finish until A is finished B cannot start until A starts Rare, A starts before B finishes (e.g. when replacing an old system B with a new system A) Free Slack The latest an activity can start without delaying next activities Total Slack The latest an activity can start without delaying project finish date Float Often referred to as the same as Slack Lag Lag (a delay) = the successor must wait due to some delay after the predecessor is complete Lead Lead (an accelerant) = the successor can begin before the predecessor is complete Schedule Compression Crashing or fast tracking the schedule to adjust the schedule to align with the plan Fast Tracking Compression technique based on overlapping sequential activities (risky) Resource Leveling Adjusting peaks and valleys to create a level usage of resources Resource Smoothing Adjusting peaks and valleys to create a level usage of resources AND also accounts for individual resource limitations A B A B A B A B 16
  • 17. Plan Cost Managem ent Estimate Costs Determine Budget Control Costs Cost Baseline Project Funding Requirem ents W ork Performance Info Cost Forecasts Change Requests Updates Exp. Judgment Aggregation Reserve Analysis Funding LImits Cost Mgt. Plan Activity C ost Estimates Basis of Estimates This area includes defining how project costs will be managed, estimating activity costs, determining the budget, and controlling costs. 4. Cost Management – Process Activities Establish the policies, procedures, and documentation for planning, managing, expending, and controlling project costs Develop an approximation of the monetary resources needed to complete project activities Aggregate estimated costs of individual activities or work packages to establish an authorized cost baseline Monitor the status of the project to update project costs and manage changes to the cost baseline Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply 17 Analogous Parametric Bottom Up 3 Point Reserve Earned Value TCPI Forecasting PMIS Reserve Anal. IRR NPV ROI Opportunity $ Payback
  • 18. EVM is a means of measuring project cost and schedule vs. the plan. Earned Value Management (EVM) Time Dollars Cost Baseline (“S” Curve) Approved Time-Phased Budget BAC Budget at Completion (BAC) = total project budget ETC Estimate to Complete (ETC) = cost to complete the project based on current spending efficiency EAC Estimate at Completion (EAC) = current projected final cost based on current spending efficiency Variance at Completion (VAC) Cost Variance (CV) Cost Performance (CPI) = EV/AC Schedule Performance (SPI) = EV/PV Schedule Variance (SV) EV Earned Value (EV) = budgeted cost for work actually completed Planned Value (PV) = budgeted cost for work scheduled 18 Actual Cost (AC) at point in time AC PV Point in Time
  • 19. Plan Quality Managem ent Perform Quality Assurance urements Control Quality Quality Mgt. Plan Process Improvement Plan Quality Metrics Quality Checklists Updates Verified Deliverables QC Measures Validated Changes Quality management includes identifying quality requirements and standards, auditing requirements and control measurements, assessing quality performance, and recommending changes, when needed. 5. Quality Management – Process Activities Identify quality requirements and/or standards for the project and its deliverables, and document how the project will demonstrate compliance Audit the quality requirements and the results from quality control measurements to ensure appropriate standards and operational definitions are used Monitor and record results of quality activities to assess performance and recommend necessary changes Key: Initiating Planning Executing Monitoring & Controlling Closing 19 Cost/Benefit Cost of Quality 7 Basic Tools Benchmarking Sampling Mea s Quality Audits Controls Charts Process Analysis
  • 20. Quality Management Philosophies and Principles Quality Philosophies: • Total Quality Management (Deming) – proactive approach with statistical analysis • Zero Defects (Crosby) – Do it right the first time • Fitness for Use (Juran) – Satisfy customer needs • Continuous Improvement (Kaizen) – proactive approach to process improvement • Gold Plating – unacceptable practice of providing more than requested • Cost of Quality – cost of conforming is less than cost of non-conforming • Design of Experiments – isolate factors that influence results • 6 Sigma – strive for 99.9997% error free • ISO 9000 – document what you do; do what you document Quality Principles: • Define and satisfy customer needs • Prevent rather than inspect • Be proactive rather reactive • Validate project processes • Measure against approved standards • Continually improve • Take accountability PMI quality management principles are based on a few popular philosophies. 20
  • 21. Project managers should be familiar with common quality management tools and terms. Quality Management Tools and Terms 21 Tools Description 1. Cause and Effect Diagrams Fishbone (Ishikawa) diagram 2. Flowcharts Basic flow chart or GERT diagram with feedback loop 3. Checksheets Check list (e.g. pre-flight list to ensure you are "cockpit ready" before taking flight) 4. Pareto Diagrams Cumulative histogram (e.g. 80/20 rule) 5. Histograms Depiction of volume or frequency of occurrences of several events 6. Control Charts Depiction of process output over time with UCL & LCL at 3 sigma from mean 7. Scatter Diagrams Depicts pattern of results across two variables Terms Description Benchmarking Comparing actual or planned processes to comparable projects to identify best practices Design of Experiments Variable based analysis (freeze all variables but one and assess outcome) Statistical Sampling Using a % of the population and extrapolating the results within an acceptable confidence level Quality Audits Identify best practices; identify gaps; share best practices; offer assistance to improve; highlight lessons learned Process Analysis Assess process, identify root causes, alleviate root causes Inspection Examination of work product and comparison to documented standards (e.g. reviews, audits) 85/15 Rule 85% of quality relates to mgt.; 15% is worker related 80/20 Rule 80% of problems come from 20% of the issues Rule of 7 Must have 7 consecutive data points above or below mean to consider process "out of control" Mean Time Before Failure MTBF, example quality metric Mean Time to Repair MTTR, example quality metric Grade vs. Quality Not the same; you can have a lower grade product with high quality and vice versa (e.g. automobile models) Upper Control Limit UCL = 3 sigma above mean (average) Lower Control Limit LCL = 3 sigma below mean (average) Upper Specification Limit USL is customer established and can be above or below UCL Lower Specification Limit USL is customer established and can be above or below LCL
  • 22. Plan HR Management Acquire Project Team Develop Project Team Manage Project Team Change Requests Updates Org Charts Job Descriptions Org. Theory Pre- Assignment Acquisition Negotiation Training Team Building Ground Rules Recognition Rewards HR Mgt. Plan Project Staff Assignments Resource Calendars Team Performance Assessments Human resource management consists of planning, acquiring, developing, and managing the project team. 6. Human Resource Management - Process Activities Define roles, responsibilities, required skills, and reporting relationships Confirm availability and obtain the necessary team Improve competencies, team interaction, the team environment, and enhance project team performance Track team member performance, provide feedback, resolve issues, and manage changes to the team to optimize team performance Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply 22 Observations Conversations Conflict Mgt. Performance Appraisals
  • 23. Responsibility assignment matrix (RAM) charts such as a “RACI” let each team member know who is responsible for each activity and deliverable. Roles and Responsibilities • (R) Responsible - those who do the work • (A) Accountable - The one who: o Is ultimately answerable for the completion of the deliverable o Delegates the work to those responsible o Approves the work that the responsible person provides • (C) Consulted – those whose opinions are sought (typically subject matter experts); typically this is a two way communication • (I) Informed – those who are kept up-to-date on progress; typically this is a one way communication 23 RACI Person Activity Ann Ben Carlos Denny Develop Schedule A R I I Collect Requirements I A R C Develop Test Plan I A R C Develop Training Plan A C I R
  • 24. Project Life Cycle - Team Building & Leadership Styles Team Building Stages • Forming – creating the team • Storming – team chaos as people start working with one another • Norming – team behavior starts to normalize • Performing – team performs as a unit • Adjourning – team completes work and disbands Situational Leadership Styles • Directing – provide specific, clear instructions and closely supervise • Coaching – solicit input, offer rationale and examples • Facilitating –maintain team progress; delegate day-to-day control • Supporting – support and motivate the team to complete objectives Project managers should be aware of typical team building dynamics and situational leadership styles across a project life cycle. Time 24 Team Building: Leadership Style: Forming Directing Storming Norming Performing Adjourning SupportingCoaching Facilitating Project Life Cycle Initiating Closing
  • 25. Conflict Management • Scheduling Priorities • Scarce Resources • Personal Work Styles • Methodology/Details • Cost/Budget • Personalities Recommended: 1. Collaborate/Problem Solve 2. Compromise/Reconcile 3. Force/Direct Not Recommended: 1. Smooth/Accommodate 2. Withdraw/Avoid Conflict is inevitable. A project manager should be aware of typical sources of project conflict and recommended techniques to resolve them. Sources of Conflict Conflict Resolution Techniques 25 Higher Lower Probability of Conflict
  • 26. Plan Communication Management Manage Communications Communciation Mgt. Plan Control Communications Project Communications Work Performance Information Change Requests Roughly 90% of a project manager’s job is communication. 7. Communication Management - Process Activities Develop a communication approach based on stakeholder’s informational needs Create, collect, distribute, store, and retrieve information Monitor and control communication throughout the entire project life cycle Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply 26 Req. Analysis Technology Models Methods Meetings Models Method Systems Reporting Exp. Judgment Systems Meetings
  • 27. Communication Paths N N N N •# of Communication Paths equals [N x (N-1)]/2 •N equals # of Stakeholders • Example: [4 x (4-1)]/2 = 6 Communication Methods • Interactive – between two people • Push – send to specific recipients • Pull – recipient actively seeks information Communication Management Communication Types • Active listening – receiver verifies correct interpretation • Effective listening – receiver observes visual and vocal cues • Feedback – sender receives feedback from receiver • Nonverbal - ~55% of communication (e.g. body and facial language) • Para-lingual – Voice characteristics Project managers should be aware of the basics of effective communication across the broad stakeholder community. Sender/Encode Decode/Receiver Transmit Acknowledgement Response Communication Model Noise 27 Noise
  • 28. 28 Plan Risk Management Identify Risks Perform Qualitative Analysis Perform Quantitative Analysis Plan Risk Response Control Risks Updates U pdates Project Docum ents Risk Register (Risks & Triggers) Risk Mgt. Plan Updates U pdates 8. Risk Management – Process Activities Risks are possible events that could impact the project in a positive (an opportunity) or negative (a threat) way. Define how to conduct risk management activities Determine and document the characteristics of risk which may affect the project Prioritize risks for further analysis or action by assessing their probability of occurrence and impact Analyze the effect of identified risks on overall project objectives Develop options and actions to enhance opportunities and reduce threats to project objectives Implement risk response plans, track identified risks, monitor residual risks, identify new risks, and evaluate risk process effectiveness Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 29. Risk Probability and Impact Matrix High Level of Impact A probability and impact matrix can be used to evaluate the impact of a risk and the probability of its occurrence. Probability and Impact Matrix Low High Moderate Moderate Probability of Occurrence Positive Risk Responses •Share – split the responsibility and benefit to maximize the opportunity •Exploit – take steps to ensure success •Enhance – improve the size of the risk event and impact •Accept – do nothing Negative Risk Responses •Avoid – get rid of the potential problem •Transfer – re-assign to another party •Mitigate – minimize the bad characteristics of the risk •Accept – do nothing The higher the combined probability and impact of the risk event the greater the need to develop a risk response plan 29
  • 30. Project managers should be aware of risk management terms. Risk Management Terms •Monte Carlo – simulation of possible outcomes •Risk Breakdown Structure – breakdown by category (e.g. internal, external, technology, organizational, etc.) •Risk Trigger – an indicator that an event “could” occur •SWOT Analysis – strengths, weaknesses, opportunities, and threats •Expected Monetary Value (EMV) – summation of probability x impact of alternative decisions (…not to be confused with EVM – earned value management) •Contingency Reserves – for known risks (include in budget and schedule) •Management Reserves – for unknown risks (excluded from baselines for budget and schedule) •Residual Risk – risk remaining after risk response •Secondary Risk – potential risk as a result of risk response •Workaround – “wing it” response when other risk response plans don’t work •Types of Risk Tolerance o Averse – Avoids risk o Seeker – Seeks risk o Neutral – Middle ground 30 Risk Management
  • 31. Procurement Mgt. Plan Plan Procurement Mgt. Conduct Procurements Control Procurements Close Procurements Work Performance Info Updates Change Requests Procurement Mgt. Plan SOW RFPs Selection Criteria Make Buy Decision Selected Suppliers Agreements Resource Calendars Exp. Judgment Make Buy Analysis Seller Proposals Closed Procurements OPA Udpates Procurement management includes planning, selecting, contracting, controlling, and closing outsourced products and services. 9. Procurement Management – Process Activities Document project procurement decisions, specify the approach, and identify potential sellers Obtain seller response, select a seller, and award a contract Manage procurement relationship, monitor contract performance, and make changes and corrections as appropriate Complete each project procurement, including finalizing open claims, updating records to reflect final results, and archiving information Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply 31 Exp. Judgment Bidder Conf. Ind. Estimates Advertising Inspect/Audits Reporting A/P Systems Claims Admin. Records Mgt. Audits Negotiations Record Mgt.
  • 32. Project managers should be aware of the benefits and risks of different contract types from a buyer’s perspective and a seller’s perspective. Contract Types Buyer’s Risk Seller’s Risk Low High High Low • (FFP) Firm Fixed Price – allows buyer to budget fixed price; requires seller to detail scope and accurately estimate price; very common • (FFIF) Fixed Price Incentive Fee – includes incentive to motivate seller to produce at greater speed • (FF EPA) Fixed Price Economic Price Adjustment – compensates for year to year economic changes • (T&M) Time and Materials – typically used for smaller initiatives • (PO) Purchase Order – typically used for commodity items • (CPFF) Cost Plus Fixed Fee – typically variable costs are cost-plus and predictable costs are fixed fee • (CPIF) Cost Plus Incentive Fee – actual costs plus incentive to motivate seller to produce at greater speed • (CPAF) Cost Plus Award Fee – actual costs plus award based on customer satisfaction with agreed criteria • (CPPC) Cost Plus Percent of Cost – actual cost plus % of actual; the higher the cost, the higher the fees 32 FFP FPIF FP EPA T&M PO CPFF CPIF CPAF CPPC
  • 33. Project managers should be familiar with additional procurement terms in the table below: Procurement Terms 33 Terms Description Make or Buy Analysis Is it more practical to insource or outsource (based on a cost comparison between the two)? Bidder Conference Prior to bid submission, offers opportunities for prospective sellers to obtain requirements clarification from buyer Independent Estimates Used to validate proposal information Contract (CCOLA) Must have 5 Components: Capacity, Consideration, Offer, Legal Purpose, Acceptance Point of Total Assumption Point at which seller is responsible for all cost overruns; PTA = (Ceiling Price - Target Price)/Buyer Share + Target Cost Ceiling Price % of Target Cost (e.g. Ceiling = 140% of target cost) Target Cost Expected cost of work in the contract Target Price Equals Target Cost + Target Profit Share Ratio Ratio of split between buyer and seller of cost savings or overruns (e.g. 70/30) RFP Request for Proposal, typically used for higher priced, customized services or products RFQ Request for Quote, typically used for small dollar commodity type products IFB Invitation to Bid, used for government sealed bids (similar to RFP) Design Scope of Work (SOW) Buyer provides exact details; generally results in fixed price contract Functional Scope of Work (SOW) Buyer provides functionality needed; generally results in cost plus contract Sole Source Go direct to a supplier without any available competition (e.g. supplier holds the patent) Single Source Go direct to a supplier although competitors are available (e.g. "preferred supplier") Negotiation PMI prefers "win/win" negotiation approach Standard Terms & Conditions Typical common (non-negotiable) contract items with a tight range or parameters Special Provisions Typically added to account for changes to standard terms and conditions Claims Administration Means of administering contested changes or disagreements regarding compensation ADR Alternative dispute resolution (e.g. arbitration) used when claims cannot be negotiated between buyer and seller
  • 34. Identify Stakeholders Plan Stakeholder Management Manage Stakeholder Engagement Stakeholder Register Stakeholder Mgt. Plan Control Stakeholder Engagement Issue Log Change Requests Updates Work Performance Info Change Requests Updates Stakeholder Engagement Matrix (Unaware, Neutral, Resistance, Leading) It is critical to project success to identify stakeholders, address their requirements, meet their expectations, and foster their engagement. 10. Stakeholder Management – Process Activities Identify the people, groups, or organizations that could impact or be impacted by the decision, activity, or outcome of the project. Develop appropriate management strategies to effectively engage stakeholders throughout the project life cycle based on their needs and potential impact on project success Communicate and work with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder engagement throughout the project life cycle Monitor overall project stakeholder relationships and adjust strategies and plans for engaging stakeholders Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply 34 Exp. Judgment Stakeholder Analysis (Power/ Interest) Interpersonal Skills Management Skills
  • 35. All stakeholders are different and, therefore, need to be managed differently based on their relative authority (power) and level of concern (interest). Stakeholder Stakeholder Power vs. Interest Grid Low High High Moderate Moderate Power Interest Power vs. Interest Grid 35 Keep Satisfied Manage Closely Monitor Keep Informed
  • 36. All PMI members must agree to adhere to a high personal standard of ethical and professional behavior. Tenets of Code: 1.Honor o Do what is right and honorable o Set high standards for yourself and aspire to meet those standards is all aspects of life 2.Responsibility – Take ownership of: o The decisions you make or fail to make o The actions you take or fail to take o The consequences that result 3.Respect o Show high regard for yourself, others, and the resources (e.g. people, money, reputation, safety) entrusted to you o Engender trust confidence, performance excellence, and mutual cooperation in an environment of diverse perspectives and views 4.Fairness o Make decisions and act impartially and objectively o Conduct yourself in a way free from competing self interest, prejudice, and favoritism 5.Honesty o Understand the truth o Act in a truthful manner both in your communication and in your conduct PMI Code of Ethics and Professional Conduct 36
  • 37. 37 Summary • What is PMI and the PMP? • Why PMI Project Management Principles are Useful to Know • A Few Basic PMI Definitions • Five Process Groups oInitiating o Planning o Executing oMonitoring and Controlling oClosing • Ten Knowledge Areas o Integration o Scope o Time o Cost o Quality o Human Resources o Communication o Risk o Procurement o Stakeholders • Project Management Terms, such as: oTriple Constraint oProject Charter oProject Management Plan oWork Breakdown Structure (WBS) oPredecessor Relationships o Earned Value Management o Gold Plating oResponsibilities Assignment Matrix oForming, Storming, Norming, Performing, Adjourning oCommunication Noise oRisk Probability and Impact Matrix oContract Type oStakeholder Power vs. Interest Grid • Code of Ethics and Professional Conduct oHonor oResponsibility oRespect o Fairness o Honesty This material covered the following project management topics: Thank you for taking the time to review this material!