IBM Maximo Asset
                                                      Management
                                                      Scheduler 7.5.1
                                                      Release Date: July 27, 2012




    Pedro Solfa Spadacini - Test Software Engineer
    IBM Software Group, Tivoli
    Phone: +55-11-2927-1229
    E-mail: psolfa@br.ibm.com




1                                                                               © 2012 IBM Corporation
Agenda
      What Makes Up Scheduler 7.5.1
      Scheduler – Revised Approach to Work Management
      Introduction to Maximo Scheduler
          The Planner & Scheduler
          Graphical Assignment
          Field Work Management the Dispatcher
      Project Summary
      Customer Interaction
      Work Management
      Scheduler -Relevant Roles
      Time Phased Functional Utilization
      Dispatcher Use Cases
      Field Technician Use Cases
      Conclusion
      Questions
2
                                                   © 2012 IBM Corporation
What Makes Up Scheduler 7.5.1
    Investing in the natural evolution of our current products in a direction desired by
     our customers

    Enhancements to Scheduler
       – Graphical Assignment/Dispatching
       – Provision of standard Work Order actions
       – Additional Resources
          • Assets/Locations                                         All included as
          • Labor                                                    Maximo Scheduler
          • Tools                                                    7.5.1
          • Materials
       – Schedule Compliance

    Enhancements to Maximo
       – Service Addresses
       – Public Map UI Control
       – Crews

    Maximo Everyplace role based templates

3
                                                                 © 2012 IBM Corporation
Scheduler – Revised Approach to Work Management

     Not just a Planning & Scheduling Tool !


       It is a means for labor
       assignments to be made
       It is a Dispatching application
       where the location of Crews
       and Labor, and the progress
       of work can all be monitored
       It is Maximo Everyplace
       templates designed to make
       the job of the field technician
       all that much easier


4
                                               © 2012 IBM Corporation
Maximo Scheduler 7.5.1 - Introduction
    Extends work management in Maximo satisfying the needs of
    Planners, Schedulers, Dispatchers and Mobile Field
    Technicians.
    Target market: Utilities, oil & gas, municipal governments or
    any customers requiring EAM with work management tools.
    Key differentiator: No integration with third party products.
    EAM, Planning and Scheduling integrated in just one solution,
    reducing time to value.
    Efficient work scheduling and execution based on:
    availability of asset, tools, materials and graphical assignment.




5
                                                                    © 2012 IBM Corporation
SWG CPA DCP Template


What is Maximo Scheduler?


                                                                             Scheduler is an
                                                                             add-on product
                                                                             to Maximo
                           Maximo                                            Installed when
                                                                             Maximo 7.5 is
                                                                             installed




                    Maximo Scheduler


             • Enabled by the Scheduler license key
             • Pre-req of 7.5.0.3 fix pack
        IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template




      The Planner & Scheduler




IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Schedule Compliance
The ability to show Target, Scheduled and Actual Dates on the Gantt chart
    Allows Planners & Schedulers to get a view of how work is progressing, and the affect of the
    progress on related work




              IBM Confidential        Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Asset & Location Availability




         IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Material Availability
Other Resource Availability tab shows:
    Maintenance/Operational/Calendar availability of Asset and Location
    Material Availability for planned materials
        Shows required quantity vs available quantity
        Green bar shows materials are available, red bar shows materials are unavailable
    Planners & Schedulers know when not to schedule work based on material availability




               IBM Confidential            Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Additional Actions
Work Order Actions
  – Allow status changes on multiple
   work orders/tasks




Additional Toolbar Buttons

  – Zoom to Week
  – Go To Day
  – Constrain horizontal scrolling to the
   date range containing work
  – Filter resources based on selected
   work orders
  – Show/Hide Compliance
  – Full Screen

              IBM Confidential           Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Schedule Cost Tab
Calculate costs within schedule by week, month and year
   Illustrate Committed and Saved Estimated Labor, Materials, Services and Tools, as well
   as Actual Labor, Materials, Service and Tools
   Allows budget adherence




           IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template




           Graphical Assignment




IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Graphical Assignment
New application aimed at the process of assigning work to people
   – Similar UI to Scheduler Gantt view for consistency
   – Helps the Planner & Scheduler see non work time for a resource, as well as assignments made by other Foremen
     beyond the bounds of their schedule… eliminates duplicate labor assignments




                 IBM Confidential          Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Making an Assignment
Allows the Foreman to:
   Split Work According to Shifts, might be used if extending duration of the assignment across an
   end of shift
   Split Work, once split can drag second assignment to add a time gap
   Split Work into Three Records, creates two additional assignments
   Create Assignment
   Delete Assignment




            IBM Confidential        Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template




           Field Work Management
                The Dispatcher




IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Scheduler Features for Field Work Management




17      IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Dispatch View
Dispatcher views the map with applicable Crew or Resource routes as defined by
assignments.


                    Calendar View                                                 Map View




            IBM Confidential        Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Map Overview
New Map Control
 – Configurable
                                                                                       Maptip
 – Everyplace enabled



Map Providers
 – Google Maps
 – Bing Maps
 – ESRI with Maximo Spatial


                                                                                          Actions
Map tools
 – Unassigned WOs
 – Nearby labors and crews                                 Crew
 – Layer/symbology selection



Geolocation                                                                                     Work Order
 – Labor / Crew tracking

                                                                         Route




                  IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Labor & Crew Geo-location Tracking
     Browser geo-location API tracks the user

        based on Crew or Labor “Location Refresh” field
        data stored in LBSLOCATION table
        OOTB user is only tracked when in one of the Scheduler
        Everyplace applications.




                                                                                      Configurable on these system properties:

                                                                                            mxe.lbs.lastupdate.tolerance
                                                                                            mxe.lbs.maximumAccuracy


                                                          Red last update accuracy is
                                                          over the limit




      Blue when last update
      was within 60 mins                                                               Yellow last update outside
                                                                                       60 mins




20                 IBM Confidential           Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template




The Mobile Field Technician




IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Field Technician Application




                                                                              Field Technician’s
                                                                              Work Order Route




         IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Field Technician Application – My Work

                                                                             Field Technician’s
                                                                             Street Level Route



                                                                               Field Technician’s
                                                                              Material Requirements




                                                                               Field Technician’s
                                                                               Tool Requirements




        IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template


Field Technician Application – Details



                                                                              Toolbar Actions:
                                                                              • Query Tools
                                                                              • New / Follow-up Work Order
                                                                              • Status Change
                                                                              • Stop / Start Timers
                                                                              • Attach Documents



                                                                         View work order
                                                                           details




         IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template

Field Technician Application – Results
                                                                              Labor, Materials,
                                                                               Tools, Failure
                                                                             Reporting and Work
                                                                                Log results.




        IBM Confidential       Template version: SWG IPD V5.5.1 (Jul 2010)
Project Summary
     Customer Interaction with product validation

     11 customers, 5 Business Partners, ISST & GBS, Sprint demos,
     Business Partner Meetings, User Group Conferences, Hosted                                    Gaps addressed
     and on-site Beta program.
                                                                                       Map Control - GIS
     Revenue: Projected $4M in incremental Scheduler revenue over
     next 5 years, plus significant Maximo drag revenue.                               Graphical Assignment
     Pricing: Increase from $1060 to $1590 per authorized user.                        Viewing of work, route,
                                                                                       directions, by planner,
     Competitive Posture                                                               foreman, field technician
     4 gaps addressed; on par or leading in all Scheduler areas                        Schedule and resource
     except Appointment Booking and CRM integration (strategically                     optimization
     not planning to address).

     What was delivered
     Map Control                                                                    Focus on product usability
     Service Addresses
     Crews
     Mobile applications with mapping and work details (w/ Maximo Everyplace)

     Graphical Assignment
     Schedule Compliance
     Dispatching
     Asset, Location Availability
     Work order actions in Scheduler

26
                                                                                © 2012 IBM Corporation
Customers
     Customer Demand
                                                                                    Agile Client Interaction
     Maximo customers have requested advanced planning &                                      List
     scheduling tools to eliminate the need for third party product
                                                                                 City of Henderson
     integrations (CIM, Akwire, Click, Servigistics, TOA, etc.)
                                                                                 City of Cambridge
     Where customers have attempted to meet their requirements                   City of Corpus Christi
     with a true FSM product (Click, TOA), they have had to invest in
     reducing it’s functionality to meet their business requirements.            City of Lakeland
                                                                                 Baltimore Gas & Electric
                                                                                 DTE Energy
     Positioning
                                                                                 Salt River Project (SRP)
     Where a customers requirements demand a true FSM product,                   Portland General Electric
     we will defer to Click Software.
                                                                                 Deutsche Telekom
     We do not ever intend to include the FSM specific elements into             Eli Lilly
     our solution, or compete in true FSM opportunities. We have only            General Mills
     taken the steps to expand the footprint of our existing product in
     ways demanded by our customers.                                              Customer Checkpoints
                                                                                 Sprint demos
                                                                                 Dev. Partner Meetings
                                                                                 User Group Conferences
                                                                                 Beta workshops


27
                                                                          © 2012 IBM Corporation
Work Management                                                        Logical Hands-off

      Scheduler
                   Graphical
                   Assignmen
      Schedule
      Created
                   t

      Project,     Assignments   Dispatching
      demand, &    made
      forecasted
      work         Crafts &                               Maximo
                   skills        Assigned                 Everyplace
                   validated     routes visible
                                 on a map
                                                               Field tech sees
                   Absences &                                  assigned route
                   vacation      New work may
                                 easily be                     on a map
                   respected
                                 assigned based
                                 on proximity of               See locations of
                                 labor                         neighboring
                                                               crews

                                                               Feedback on
                                                               work status &
                                                               progress




28
                                                   © 2012 IBM Corporation
Scheduler - Relevant Roles
     Define and adjust
     technician/crew availability                                                            Sequence and route work
     along with resource                                                                     assignments based on
     leveling                                                                                geography
     Capacity Planning                                                                       Monitor technician and work
     Assign work orders to                                                                   order progress and status
     technicians                                                                             Monitor the location of field
     Continuously optimize the                                                               resources compared to open
     schedule as the operational                                                             work orders
     environment changes             Planner/                 Dispatcher
                                                                                             Dispatch emergent work to
                                    Scheduler                                                the proper resource.
     Sequence and route work
     assignments based on
     geography



                                                        Receive work orders in the field
                                                        Provide real time status updates to dispatch
                                                        Request supplementary information from the
                                                        back-office
                                                        Review work orders on the mobile map, along
                                                        with optimal driving directions
                                                        Notify dispatch of potentially dangerous
                                     Mobile Workforce
                                                        situations
                                                        Complete, edit and approve work orders


29
                                                                          © 2012 IBM Corporation
Time Phased Functional Utilization


           PM                  Scheduler            Graphical         Everyplace
        Application               and              Assignment         Applications
                          Graphical Assignment




         Forecast              Schedule                Dispatch              Mobile



               PM            WO            Resource                               Field
                                                         Dispatching
            Forecasting   Scheduling      Assignment                            Technician




            Years to Months            Weeks           1-7 Days              1-3 Days




30
                                                                  © 2012 IBM Corporation
Dispatcher Use Cases
     Dispatcher
        Assignment of work for crews and labors has been completed for the following week.

        On Monday morning Bill calls in sick
        – Ford is re-assigned Bill’s work for the day

        View progress of work out in the field as it becomes completed throughout the day.

        New emergent work comes in
        – Determine who is in the area of the emergency work and is available.
        – Assign the work to a crew – it automatically becomes part of their route.




31
                                                                          © 2012 IBM Corporation
Field Technician Use Cases

     Mobile Field Technician
        View list of Work Orders assigned on a tablet device
        – View street-level route and the driving directions
        – View nearby labor/crews

        Display streamlined Work Order information along with
        start/stop timer to complete work.

        New emergent work is assigned to the field technician
        – View updates to the work list along with a new SLR
        for the day

        The work day is not going as planned
        – (a) Finished assigned work early – need to find other
        work in area to fill rest of day
        – (b) Unexpected delay in an assignment - not going to
        finish all of today’s assigned work– need to collaborate
        with dispatch to reassign the rest of work.




32
                                                                   © 2012 IBM Corporation
Future
          Schedule optimization (Integration with ILOG)
                    −    On-going work with Watson and Haifa Research teams.


          Routing optimization based on weather feeds, manual input, environment changes
                    −    Use case: when a road gets blocked by snow, route should adapt

          Linear assets and linear referencing integration

          Network Tracing (Ex: Which area is affected if I close a valve)

          GIS analytics and geo processing

     Service Area
     Ex: areas reached in 1min, 2min and 3min drive   Viewshed analysis
                                                      Ex: areas that can be seen from observation points

                                                                                                                    Linear referencing




33
                                                                                                      © 2012 IBM Corporation
DEMO

      Let's see a quick demo !


      http://ibm-931cf5a1b7d:7001/maximo/webclient/login/login.jsp




34
                                                © 2012 IBM Corporation
Conclusion
       Maximo Scheduler was created to
          Plan, Scheduling and Assign future work taking in consideration relationships, restrictions,
          availability and skills.
          Drag & Drop work assignments, quick and easy


       Visualize field crews
          Using a new map control to visualize and execute actions from the map.
          To monitor on going work
          Manage crews, work and their routes


       Improve crew and labor efficiency
          Using maps to visualize the route for the daily work
          Dynamic work list based on manual or automatic assignment (optimization)
          Improve near by labors communication
          Update work orders from the field, with mobile devices




35
                                                                       © 2012 IBM Corporation
Questions?



                                         Thank you!




      Pedro Solfa Spadacini - Test Software Engineer
      psolfa@br.ibm.com




36
                                                       © 2012 IBM Corporation

Contenu connexe

Tendances

ibm maximo training | ibm maximo training online | ibm maximo course
ibm maximo training | ibm maximo training online | ibm maximo courseibm maximo training | ibm maximo training online | ibm maximo course
ibm maximo training | ibm maximo training online | ibm maximo course
Nancy Thomas
 

Tendances (20)

Maximo Roadmap - September 2019
Maximo Roadmap - September 2019Maximo Roadmap - September 2019
Maximo Roadmap - September 2019
 
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
IBM Maximo Asset Management Training - Asset and Work Management for Chang Sh...
 
Maximo Training - Introduction
Maximo Training - IntroductionMaximo Training - Introduction
Maximo Training - Introduction
 
ibm maximo training | ibm maximo training online | ibm maximo course
ibm maximo training | ibm maximo training online | ibm maximo courseibm maximo training | ibm maximo training online | ibm maximo course
ibm maximo training | ibm maximo training online | ibm maximo course
 
Maximo overview
Maximo overviewMaximo overview
Maximo overview
 
Maximo 7.5 New Features
Maximo 7.5 New FeaturesMaximo 7.5 New Features
Maximo 7.5 New Features
 
Maximo Training - Asset Management
Maximo Training - Asset ManagementMaximo Training - Asset Management
Maximo Training - Asset Management
 
Roadmap imug Maximo product update Nov 2017
Roadmap imug Maximo product update Nov 2017Roadmap imug Maximo product update Nov 2017
Roadmap imug Maximo product update Nov 2017
 
IBM Maximo Asset Management 7.5 Add-ons
IBM Maximo Asset Management 7.5 Add-onsIBM Maximo Asset Management 7.5 Add-ons
IBM Maximo Asset Management 7.5 Add-ons
 
Agile Delivery
Agile DeliveryAgile Delivery
Agile Delivery
 
Maximo 7.6 Features
Maximo 7.6 Features Maximo 7.6 Features
Maximo 7.6 Features
 
Maximo Field Service Management
Maximo Field Service ManagementMaximo Field Service Management
Maximo Field Service Management
 
Maximo Anywhere product update Nov 2017
Maximo Anywhere product update Nov 2017Maximo Anywhere product update Nov 2017
Maximo Anywhere product update Nov 2017
 
Maximo Mobile Solutions - BPD Zenith Presentation
Maximo Mobile Solutions - BPD Zenith PresentationMaximo Mobile Solutions - BPD Zenith Presentation
Maximo Mobile Solutions - BPD Zenith Presentation
 
MaxTECH Technical Training - Maximo Custom Audit Solution
MaxTECH Technical Training - Maximo Custom Audit SolutionMaxTECH Technical Training - Maximo Custom Audit Solution
MaxTECH Technical Training - Maximo Custom Audit Solution
 
IBM Maximo Predictive Maintenance FMMUG 2018
IBM Maximo Predictive Maintenance FMMUG 2018IBM Maximo Predictive Maintenance FMMUG 2018
IBM Maximo Predictive Maintenance FMMUG 2018
 
Work Centers and Inspections
Work Centers and InspectionsWork Centers and Inspections
Work Centers and Inspections
 
ibm_maximo
ibm_maximoibm_maximo
ibm_maximo
 
Maximo 7.6.0.8
Maximo 7.6.0.8Maximo 7.6.0.8
Maximo 7.6.0.8
 
Field service management (FSM)
Field service management (FSM)Field service management (FSM)
Field service management (FSM)
 

Similaire à Maximo Scheduler 751 Workshop Pedro Solfa Sep 2012

Software app slides
Software app slidesSoftware app slides
Software app slides
ahmong4
 
Software Factories in the Real World: How an IBM WebSphere Integration Factor...
Software Factories in the Real World: How an IBM WebSphere Integration Factor...Software Factories in the Real World: How an IBM WebSphere Integration Factor...
Software Factories in the Real World: How an IBM WebSphere Integration Factor...
ghodgkinson
 

Similaire à Maximo Scheduler 751 Workshop Pedro Solfa Sep 2012 (20)

SmartCloud Control Desk Roadmap
SmartCloud Control Desk RoadmapSmartCloud Control Desk Roadmap
SmartCloud Control Desk Roadmap
 
What's new in Rational Team Concert 3.0
What's new in Rational Team Concert 3.0What's new in Rational Team Concert 3.0
What's new in Rational Team Concert 3.0
 
What's New in Rational Team Concert 3.0
What's New in Rational Team Concert 3.0What's New in Rational Team Concert 3.0
What's New in Rational Team Concert 3.0
 
GPU Support In Spark And GPU/CPU Mixed Resource Scheduling At Production Scale
GPU Support In Spark And GPU/CPU Mixed Resource Scheduling At Production ScaleGPU Support In Spark And GPU/CPU Mixed Resource Scheduling At Production Scale
GPU Support In Spark And GPU/CPU Mixed Resource Scheduling At Production Scale
 
XPages is Workflow's new best friend
XPages is Workflow's new best friendXPages is Workflow's new best friend
XPages is Workflow's new best friend
 
DevOps On Google Cloud Platform Online Training.pptx
DevOps On Google Cloud Platform Online Training.pptxDevOps On Google Cloud Platform Online Training.pptx
DevOps On Google Cloud Platform Online Training.pptx
 
What's new in designer
What's new in designerWhat's new in designer
What's new in designer
 
Compiere ERP
Compiere ERPCompiere ERP
Compiere ERP
 
Software app slides
Software app slidesSoftware app slides
Software app slides
 
Fast track RTC Innovate India 2013
Fast track  RTC Innovate India 2013Fast track  RTC Innovate India 2013
Fast track RTC Innovate India 2013
 
CVH1
CVH1CVH1
CVH1
 
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
 
Software app slides
Software app slidesSoftware app slides
Software app slides
 
DevOps in the Hybrid Cloud
DevOps in the Hybrid CloudDevOps in the Hybrid Cloud
DevOps in the Hybrid Cloud
 
Software Factories in the Real World: How an IBM WebSphere Integration Factor...
Software Factories in the Real World: How an IBM WebSphere Integration Factor...Software Factories in the Real World: How an IBM WebSphere Integration Factor...
Software Factories in the Real World: How an IBM WebSphere Integration Factor...
 
WebShare Cloud Workflow by Matt Byrd
WebShare Cloud Workflow by Matt ByrdWebShare Cloud Workflow by Matt Byrd
WebShare Cloud Workflow by Matt Byrd
 
Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...
Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...
Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...
 
Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...
Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...
Is a Monolith Standing in the Way of Your Digital Transformation? Refactor fo...
 
TenYearsCPOptimizer
TenYearsCPOptimizerTenYearsCPOptimizer
TenYearsCPOptimizer
 
Supply Planning Leadership Exchange: SAP PP/DS What You Need to Know Part 1
Supply Planning Leadership Exchange: SAP PP/DS What You Need to Know Part 1Supply Planning Leadership Exchange: SAP PP/DS What You Need to Know Part 1
Supply Planning Leadership Exchange: SAP PP/DS What You Need to Know Part 1
 

Plus de alipaiva

Workflow Workshop 2012 Sep Leucir Marin
Workflow Workshop 2012 Sep Leucir MarinWorkflow Workshop 2012 Sep Leucir Marin
Workflow Workshop 2012 Sep Leucir Marin
alipaiva
 
MIF Workshop Raquel Bortoluci Sep 2012
MIF Workshop Raquel Bortoluci Sep 2012MIF Workshop Raquel Bortoluci Sep 2012
MIF Workshop Raquel Bortoluci Sep 2012
alipaiva
 
Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012
Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012
Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012
alipaiva
 
What's New in Maximo 7 Workshop Alex Estevam Sep 2012
What's New in Maximo 7 Workshop   Alex Estevam Sep 2012What's New in Maximo 7 Workshop   Alex Estevam Sep 2012
What's New in Maximo 7 Workshop Alex Estevam Sep 2012
alipaiva
 
Caractersticas Maximo 75 Workshop Alex Estevam Sep 2012
Caractersticas Maximo 75 Workshop  Alex Estevam Sep 2012Caractersticas Maximo 75 Workshop  Alex Estevam Sep 2012
Caractersticas Maximo 75 Workshop Alex Estevam Sep 2012
alipaiva
 
Maximo Mobile Suite Workshop Regis Adamus Sep 2012
Maximo Mobile Suite Workshop   Regis Adamus Sep 2012Maximo Mobile Suite Workshop   Regis Adamus Sep 2012
Maximo Mobile Suite Workshop Regis Adamus Sep 2012
alipaiva
 
Migration Manager Workshop Leucir Marin Sep 2012
Migration Manager Workshop  Leucir Marin Sep 2012Migration Manager Workshop  Leucir Marin Sep 2012
Migration Manager Workshop Leucir Marin Sep 2012
alipaiva
 

Plus de alipaiva (7)

Workflow Workshop 2012 Sep Leucir Marin
Workflow Workshop 2012 Sep Leucir MarinWorkflow Workshop 2012 Sep Leucir Marin
Workflow Workshop 2012 Sep Leucir Marin
 
MIF Workshop Raquel Bortoluci Sep 2012
MIF Workshop Raquel Bortoluci Sep 2012MIF Workshop Raquel Bortoluci Sep 2012
MIF Workshop Raquel Bortoluci Sep 2012
 
Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012
Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012
Oil and Gas 75 Workshop Ana Paula Brambila Sep 2012
 
What's New in Maximo 7 Workshop Alex Estevam Sep 2012
What's New in Maximo 7 Workshop   Alex Estevam Sep 2012What's New in Maximo 7 Workshop   Alex Estevam Sep 2012
What's New in Maximo 7 Workshop Alex Estevam Sep 2012
 
Caractersticas Maximo 75 Workshop Alex Estevam Sep 2012
Caractersticas Maximo 75 Workshop  Alex Estevam Sep 2012Caractersticas Maximo 75 Workshop  Alex Estevam Sep 2012
Caractersticas Maximo 75 Workshop Alex Estevam Sep 2012
 
Maximo Mobile Suite Workshop Regis Adamus Sep 2012
Maximo Mobile Suite Workshop   Regis Adamus Sep 2012Maximo Mobile Suite Workshop   Regis Adamus Sep 2012
Maximo Mobile Suite Workshop Regis Adamus Sep 2012
 
Migration Manager Workshop Leucir Marin Sep 2012
Migration Manager Workshop  Leucir Marin Sep 2012Migration Manager Workshop  Leucir Marin Sep 2012
Migration Manager Workshop Leucir Marin Sep 2012
 

Dernier

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Dernier (20)

Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Developing An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of BrazilDeveloping An App To Navigate The Roads of Brazil
Developing An App To Navigate The Roads of Brazil
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 

Maximo Scheduler 751 Workshop Pedro Solfa Sep 2012

  • 1. IBM Maximo Asset Management Scheduler 7.5.1 Release Date: July 27, 2012 Pedro Solfa Spadacini - Test Software Engineer IBM Software Group, Tivoli Phone: +55-11-2927-1229 E-mail: psolfa@br.ibm.com 1 © 2012 IBM Corporation
  • 2. Agenda What Makes Up Scheduler 7.5.1 Scheduler – Revised Approach to Work Management Introduction to Maximo Scheduler The Planner & Scheduler Graphical Assignment Field Work Management the Dispatcher Project Summary Customer Interaction Work Management Scheduler -Relevant Roles Time Phased Functional Utilization Dispatcher Use Cases Field Technician Use Cases Conclusion Questions 2 © 2012 IBM Corporation
  • 3. What Makes Up Scheduler 7.5.1 Investing in the natural evolution of our current products in a direction desired by our customers Enhancements to Scheduler – Graphical Assignment/Dispatching – Provision of standard Work Order actions – Additional Resources • Assets/Locations All included as • Labor Maximo Scheduler • Tools 7.5.1 • Materials – Schedule Compliance Enhancements to Maximo – Service Addresses – Public Map UI Control – Crews Maximo Everyplace role based templates 3 © 2012 IBM Corporation
  • 4. Scheduler – Revised Approach to Work Management Not just a Planning & Scheduling Tool ! It is a means for labor assignments to be made It is a Dispatching application where the location of Crews and Labor, and the progress of work can all be monitored It is Maximo Everyplace templates designed to make the job of the field technician all that much easier 4 © 2012 IBM Corporation
  • 5. Maximo Scheduler 7.5.1 - Introduction Extends work management in Maximo satisfying the needs of Planners, Schedulers, Dispatchers and Mobile Field Technicians. Target market: Utilities, oil & gas, municipal governments or any customers requiring EAM with work management tools. Key differentiator: No integration with third party products. EAM, Planning and Scheduling integrated in just one solution, reducing time to value. Efficient work scheduling and execution based on: availability of asset, tools, materials and graphical assignment. 5 © 2012 IBM Corporation
  • 6. SWG CPA DCP Template What is Maximo Scheduler? Scheduler is an add-on product to Maximo Maximo Installed when Maximo 7.5 is installed Maximo Scheduler • Enabled by the Scheduler license key • Pre-req of 7.5.0.3 fix pack IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 7. SWG CPA DCP Template The Planner & Scheduler IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 8. SWG CPA DCP Template Schedule Compliance The ability to show Target, Scheduled and Actual Dates on the Gantt chart Allows Planners & Schedulers to get a view of how work is progressing, and the affect of the progress on related work IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 9. SWG CPA DCP Template Asset & Location Availability IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 10. SWG CPA DCP Template Material Availability Other Resource Availability tab shows: Maintenance/Operational/Calendar availability of Asset and Location Material Availability for planned materials Shows required quantity vs available quantity Green bar shows materials are available, red bar shows materials are unavailable Planners & Schedulers know when not to schedule work based on material availability IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 11. SWG CPA DCP Template Additional Actions Work Order Actions – Allow status changes on multiple work orders/tasks Additional Toolbar Buttons – Zoom to Week – Go To Day – Constrain horizontal scrolling to the date range containing work – Filter resources based on selected work orders – Show/Hide Compliance – Full Screen IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 12. SWG CPA DCP Template Schedule Cost Tab Calculate costs within schedule by week, month and year Illustrate Committed and Saved Estimated Labor, Materials, Services and Tools, as well as Actual Labor, Materials, Service and Tools Allows budget adherence IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 13. SWG CPA DCP Template Graphical Assignment IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 14. SWG CPA DCP Template Graphical Assignment New application aimed at the process of assigning work to people – Similar UI to Scheduler Gantt view for consistency – Helps the Planner & Scheduler see non work time for a resource, as well as assignments made by other Foremen beyond the bounds of their schedule… eliminates duplicate labor assignments IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 15. SWG CPA DCP Template Making an Assignment Allows the Foreman to: Split Work According to Shifts, might be used if extending duration of the assignment across an end of shift Split Work, once split can drag second assignment to add a time gap Split Work into Three Records, creates two additional assignments Create Assignment Delete Assignment IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 16. SWG CPA DCP Template Field Work Management The Dispatcher IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 17. SWG CPA DCP Template Scheduler Features for Field Work Management 17 IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 18. SWG CPA DCP Template Dispatch View Dispatcher views the map with applicable Crew or Resource routes as defined by assignments. Calendar View Map View IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 19. SWG CPA DCP Template Map Overview New Map Control – Configurable Maptip – Everyplace enabled Map Providers – Google Maps – Bing Maps – ESRI with Maximo Spatial Actions Map tools – Unassigned WOs – Nearby labors and crews Crew – Layer/symbology selection Geolocation Work Order – Labor / Crew tracking Route IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 20. SWG CPA DCP Template Labor & Crew Geo-location Tracking Browser geo-location API tracks the user based on Crew or Labor “Location Refresh” field data stored in LBSLOCATION table OOTB user is only tracked when in one of the Scheduler Everyplace applications. Configurable on these system properties: mxe.lbs.lastupdate.tolerance mxe.lbs.maximumAccuracy Red last update accuracy is over the limit Blue when last update was within 60 mins Yellow last update outside 60 mins 20 IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 21. SWG CPA DCP Template The Mobile Field Technician IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 22. SWG CPA DCP Template Field Technician Application Field Technician’s Work Order Route IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 23. SWG CPA DCP Template Field Technician Application – My Work Field Technician’s Street Level Route Field Technician’s Material Requirements Field Technician’s Tool Requirements IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 24. SWG CPA DCP Template Field Technician Application – Details Toolbar Actions: • Query Tools • New / Follow-up Work Order • Status Change • Stop / Start Timers • Attach Documents View work order details IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 25. SWG CPA DCP Template Field Technician Application – Results Labor, Materials, Tools, Failure Reporting and Work Log results. IBM Confidential Template version: SWG IPD V5.5.1 (Jul 2010)
  • 26. Project Summary Customer Interaction with product validation 11 customers, 5 Business Partners, ISST & GBS, Sprint demos, Business Partner Meetings, User Group Conferences, Hosted Gaps addressed and on-site Beta program. Map Control - GIS Revenue: Projected $4M in incremental Scheduler revenue over next 5 years, plus significant Maximo drag revenue. Graphical Assignment Pricing: Increase from $1060 to $1590 per authorized user. Viewing of work, route, directions, by planner, Competitive Posture foreman, field technician 4 gaps addressed; on par or leading in all Scheduler areas Schedule and resource except Appointment Booking and CRM integration (strategically optimization not planning to address). What was delivered Map Control Focus on product usability Service Addresses Crews Mobile applications with mapping and work details (w/ Maximo Everyplace) Graphical Assignment Schedule Compliance Dispatching Asset, Location Availability Work order actions in Scheduler 26 © 2012 IBM Corporation
  • 27. Customers Customer Demand Agile Client Interaction Maximo customers have requested advanced planning & List scheduling tools to eliminate the need for third party product City of Henderson integrations (CIM, Akwire, Click, Servigistics, TOA, etc.) City of Cambridge Where customers have attempted to meet their requirements City of Corpus Christi with a true FSM product (Click, TOA), they have had to invest in reducing it’s functionality to meet their business requirements. City of Lakeland Baltimore Gas & Electric DTE Energy Positioning Salt River Project (SRP) Where a customers requirements demand a true FSM product, Portland General Electric we will defer to Click Software. Deutsche Telekom We do not ever intend to include the FSM specific elements into Eli Lilly our solution, or compete in true FSM opportunities. We have only General Mills taken the steps to expand the footprint of our existing product in ways demanded by our customers. Customer Checkpoints Sprint demos Dev. Partner Meetings User Group Conferences Beta workshops 27 © 2012 IBM Corporation
  • 28. Work Management Logical Hands-off Scheduler Graphical Assignmen Schedule Created t Project, Assignments Dispatching demand, & made forecasted work Crafts & Maximo skills Assigned Everyplace validated routes visible on a map Field tech sees Absences & assigned route vacation New work may easily be on a map respected assigned based on proximity of See locations of labor neighboring crews Feedback on work status & progress 28 © 2012 IBM Corporation
  • 29. Scheduler - Relevant Roles Define and adjust technician/crew availability Sequence and route work along with resource assignments based on leveling geography Capacity Planning Monitor technician and work Assign work orders to order progress and status technicians Monitor the location of field Continuously optimize the resources compared to open schedule as the operational work orders environment changes Planner/ Dispatcher Dispatch emergent work to Scheduler the proper resource. Sequence and route work assignments based on geography Receive work orders in the field Provide real time status updates to dispatch Request supplementary information from the back-office Review work orders on the mobile map, along with optimal driving directions Notify dispatch of potentially dangerous Mobile Workforce situations Complete, edit and approve work orders 29 © 2012 IBM Corporation
  • 30. Time Phased Functional Utilization PM Scheduler Graphical Everyplace Application and Assignment Applications Graphical Assignment Forecast Schedule Dispatch Mobile PM WO Resource Field Dispatching Forecasting Scheduling Assignment Technician Years to Months Weeks 1-7 Days 1-3 Days 30 © 2012 IBM Corporation
  • 31. Dispatcher Use Cases Dispatcher Assignment of work for crews and labors has been completed for the following week. On Monday morning Bill calls in sick – Ford is re-assigned Bill’s work for the day View progress of work out in the field as it becomes completed throughout the day. New emergent work comes in – Determine who is in the area of the emergency work and is available. – Assign the work to a crew – it automatically becomes part of their route. 31 © 2012 IBM Corporation
  • 32. Field Technician Use Cases Mobile Field Technician View list of Work Orders assigned on a tablet device – View street-level route and the driving directions – View nearby labor/crews Display streamlined Work Order information along with start/stop timer to complete work. New emergent work is assigned to the field technician – View updates to the work list along with a new SLR for the day The work day is not going as planned – (a) Finished assigned work early – need to find other work in area to fill rest of day – (b) Unexpected delay in an assignment - not going to finish all of today’s assigned work– need to collaborate with dispatch to reassign the rest of work. 32 © 2012 IBM Corporation
  • 33. Future Schedule optimization (Integration with ILOG) − On-going work with Watson and Haifa Research teams. Routing optimization based on weather feeds, manual input, environment changes − Use case: when a road gets blocked by snow, route should adapt Linear assets and linear referencing integration Network Tracing (Ex: Which area is affected if I close a valve) GIS analytics and geo processing Service Area Ex: areas reached in 1min, 2min and 3min drive Viewshed analysis Ex: areas that can be seen from observation points Linear referencing 33 © 2012 IBM Corporation
  • 34. DEMO Let's see a quick demo ! http://ibm-931cf5a1b7d:7001/maximo/webclient/login/login.jsp 34 © 2012 IBM Corporation
  • 35. Conclusion Maximo Scheduler was created to Plan, Scheduling and Assign future work taking in consideration relationships, restrictions, availability and skills. Drag & Drop work assignments, quick and easy Visualize field crews Using a new map control to visualize and execute actions from the map. To monitor on going work Manage crews, work and their routes Improve crew and labor efficiency Using maps to visualize the route for the daily work Dynamic work list based on manual or automatic assignment (optimization) Improve near by labors communication Update work orders from the field, with mobile devices 35 © 2012 IBM Corporation
  • 36. Questions? Thank you! Pedro Solfa Spadacini - Test Software Engineer psolfa@br.ibm.com 36 © 2012 IBM Corporation