SlideShare une entreprise Scribd logo
1  sur  42
AMIT KUMAR 1303200018
ANIMESH RANJAN 1303200023








COST OF PROJECT(App) INR 1435 CRORES
COMPLETION
PERIOD(Expected)
42 MONTHS
TENDER SECURITY AMOUNT INR 14.35 CRORES
TENDERING AGENCY DMRC
TENDER GIVEN TO L&T
Quoted Price & Final Price 1265 CRORES
PROPOSED ROUTE MAP FOR CC-27
BORE
HOLE
61
BORE
HOLE
35
• VASANT VIHAR-HARD ROCK STRATA (BOTTOM-UP CONSTRUCTION APPROACH)
• HAUZ KHAS - SOFT SOIL STRATA(TOP-BOTTOM CONSTRUCTION APPROACH)
TOP VIEW – VASANT VIHAR
METHOD OF CONSTRUCTION- BOTTOM UP CONSTRUCTION
EAST
SIDE WEST SIDE
ROOF
SLAB
CONCOURSE
SLAB
BASE
SLAB
1
2
3
4
5
6
7
8
1 BLOCK WORK
2 UPE(UNDER PLATFORM EXHAUST)
3 OTE(OVER TRACK EXHAUST)
4 PLATFORM SLAB
5 FRESH AIR DUCT(ROOF SLAB)
6 SCUPPER DRAIN(BEHIND BW)
7 FALSE CEILING BELOW
CONCOURSE
8 COLUMN
9 RETAINING WALL
CROSS SECTIONAL VIEW VASANT VIHAR
9
Dimension of Block– 400*200*200
Mortar-Cement sand mortar with
ratio 1:4
Block Strength- 7.5 N/mm2
MIX –M15
Thickness of the bond-10mm
Joint Type-Basic English Bond(1 block thick)
CONCOURSE
SLAB
ROOF
SLAB
BLOCK WORK IN
FRONT OF
RETAINING WALL
RETAINING
WALL
INITIAL LAYER OF BLOCK
WORK
BASE
SLAB
UPE
CUTOUT
PLATFORM
SLAB
UNDER
PLATFROM
EXHAUST
(UNDER PLATFROM EXHAUST ) are basically cut outs provided below the platform slab
OTE LIFTING
ROOF SLAB
Area-33,706 sqm
Area- 15,533.69sqm




•
•
•





HEAD ATTACHMENT
FOR BREAKER
 Shot Creting is done according to IS 9012:1978(reaffirmed 2002)
 Mix- 1:3 To 1:5 is used depending upon surface . W/c is kept at .30-.35
 Plasticizer -6% wt of cement( Glenium sky 777)
 Operating temp- 5deg to 30deg Celsius
Mesh Dia- 4mm
Mesh overlap length- 300mm
Min area for applying-300mm*300mm
Mechanism for Dry- Mix shot creting
-M40 Grade Concrete was used
-Reinforcement conforming to FE500D shall be used on site.
-Water Stops –PVC water stop will be used to arrest the water leakage (at construction joints)
-Binding wire used for binding reinforcement has a core dia of 1.25mm
-Formwork ply 12mm thick coated with Formwork oil for easy removal of formwork
-Cover blocks should be used depending on clearance that needs to be provided to the
reinforcement(50mm Base slab)
-Vibrator of 60mm Dia 4nos.
Earth CompactorConcreting on site
Proper vibration should be provided in
order to avoid cold joints
• AFTER THE FINAL SET HAS TAKEN PLACE WET HESSIAN CLOTH SHALL BE PLACED AND COVERED BY POLYTHENE SHEET.
• THE HESSIAN CLOTH SHALL BE KEPT PERMANENTLY DAMP
• AFTER 24HOURS HESSIAN CLOTH AND THE POLYTHENE SHEET SHALL BE REMOVED AND THE AREA WOULD BE
• PONDED WITH WATER .
• FOR VERTICAL CURING THE HESSIAN CLOTH ALONG WITH POLYTHENE SHEET SHALL SECURE THE SURFACE FOR AT
LEASDAYS BEFORE
• NEXT VERTICAL POURING BEGINS. THE HESSIAN CLOTH SHOULD BE DAMP ALL THE TIME.
Concrtete-M40
5.25 m below roof level
Thickness- 550mm
Formwork & scaffolding for Concourse
slab
Sealing Of construction Joints
on roof slab
Cut Outs of the roof Slab( Satellite view)
Design Mix M-40
Thickness-1.8m
Roof level
MATERIAL QUANTIY(KG) TYPE
CEMENT 380 ULTRA TECH(OPC 53
GRADE)
FLYASH 80 Ashtech:IS3812(NTPC
BADARPUR)
AGGREGATE(10mm) 481 Kotpulti
AGGREGATE(20mm) 666 Kotpulti
RIVER SAND 677 Yamuna Nagar
W/C RATIO .35
ADMIXTURE @ .85% 3.91 Glenium
147,Suretec(BASF)
W/P
CAMPOunds@1%
4.6 MasterPel 760(BASF)
WATER 161 R.O Water at Batching
Plant
Following admixture were used
Masterglenium 147 provides
 Extended workability
 Providing the ultimate high strength, especially ready.
Application
Add to the mixture 80% -90% of the calculated water for the
concrete mix and then, with the remaining water
masterglenium 147 must be added to the mixture,
Water Proofing Campound used-
Masterpel 760
 Provides resistance to water penetration either under
hydrostatic pressure or capillary absorption.
 Imparts integral water tightness to structures.
Application
MasterPel 760 is a ready-to-use powder which is dispensed into
the concrete together with the cement.
M-40 has been used for 3 slabs and retaining walls
MATERIAL
QUANTIY(KG) TYPE
CEMENT 410 ULTRA TECH(OPC 53
GRADE)
MICRO SILICA 22 TAM CEM
AGGREGATE(10m
m)
457 Kotpulti
AGGREGATE(20m
m)
686 Kotpulti
RIVER SAND 765 Yamuna Nagar
W/C RATIO .37
ADMIXTURE @
.85%
2.16 Glenium sky 777
WATER 151 R.O Water at Batching
Plant
M 50 was used for concreting of columns
MasterGlenium SKY 8777
is the super plasticizer based on second generation
polycarboxylic ether polymers, developed using nano-
technology. The product has been primarily developed for
applications in high performance ready-mix concrete to
facilitate
 Capability of delivering high quality concrete at any
time to the job site in place.
Tam Cem
TamCem Micro Silica is composed of silicon dioxide
(5i02).Collected from silicon metal and ferrosilicon.
TamCem Micro Silica will react with the Calcium
Hydroxide from the cement, which will form more of the
Calcium Silicate hydrate, increasing the strength of the
concrete.
Volume-6cum but loaded up to 5-5.5cum.
Rotations –Depend upon distance and Mix
BOOM PLACER
Concrete Bucket Vol 1-1.2cum
CONCRETING THROUGH PIPES
Bulged Concrete – Bulging in concrete takes place due to displacement of
formwork.
Surface preparation: The bulged area on concrete surface shall be hacked with
chisel to required line, level. All dirt, dust shall be cleaned with brush and water.
Repairing: Hacked area will be patched up with cement: sand mortar of proportion
1:4. On the completion of patch up work, the exposed area shall be thoroughly
cured.
Grout Loss
Exposed aggregate surface created by exit of cement slurry/grout mortar from
the gaps of formwork due to excessive vibration, unsealed joint of formwork
during pouring of concrete.
Repair
-The concrete surface is cleaned and free from dust/oil/grease etc by using
broom or wire mesh by scrubbing vigorously.
-After removal of loose particles surface is washed with water.
-Patch-up is done at cleaned surface with non-shrink Grout conbextra GP2
IS DUE SEGREGATION OF AGGREGATES AND MORTAR INTO THE
CONCRETE. HONEYCOMB CREATES IN STRUCTURES DUE TO MAINLY
IMPROPER COMPACTION IN TERMS OF EXCESSIVE/INSUFFICIENT
VIBRATION AT THE TIME OF PLACING.
Minor Honey Combing
Major Honeycombing
Repairing Involves-
The loose aggregate that are exposed shall be removed by gently
tapping on it. After removal of all loose aggregate, dust, dirt etc.
by wire/Soft brush then surface will be cleaned with Water.
Patchup is done by using conbextra GP2/Rendroc which is mixed
with cement and then the paste is applied.
CHEMICALS USED FOR WATERPROOFING
-FOR PRIMING PURPOSE
MASTER SEAL M2525(PROVIDED IN TWO COMPONENT A & B)
-WATERPROOFING LAYER
MASTER SEAL M800(PROVIDED IN TWO COMPONENT A & B)
A HIGHLY ELASTIC, SOLVENT FREE, ULTRA-FAST CURING, SPRAY APPLIED POLYURETHANE COATING AND IT IS
USED IN WATERPROOFING APPLICATIONS. MASTER SEAL M800 IS A SOLVENT FREE, TWO COMPONENT
SUBSTANCE. IT IS A HIGHLY REACTIVE TWO COMPONENT MIXTURE USED FOR WATERPROOFING IN
TUNNELING AND CUT & COVER STATIONS
USES-
WATERPROOFING COMPOUND WITH A SETTING TIME OF 2-3SECONDS
STEP WISE PROCESS FOR WATERPROOFING.
-SURFACE CONDITIONS
THE RCC SURFACE SHALL BE DRY BEFORE WATERPROOFING.
ANY INGRESS FOR WATER SEEPAGE SHALL BE IDENTIFIED AND TREATED.
CONSTRUCTION JOINT SHALL BE FILLED WITH HIGH PERFORMANCE WATER STOP GROUT OF CRYSTALLINE
GROWTH.
•
MIXING OF A & B
-Thin coat of mixed primer (RESIN + HARDNER) on the surface shall be
mechanically & uniformly applied, ensuring continuous film soon after surface
preparation is complete.
-Moisture content in the substrate shall be less than 5 %.
-The drying period of primer depends on the ambient temperature and relative
humidity.
Checking moisture before application
of primer.
BASF AGGREGATES
BASF AGGREGATES are sprinkled over the primer layer
immediately after application of the primer. Aggregates
help in roughening the surface of primer for proper
bonding between the primer layer and the waterproofing
membrane layer.
Application of the water
proofing Layer with 2
component gun
Special 2 Component
gun used for applying
waterproofing
campound
-MasterSeal M800 is available with the Part A
coloured white and the Part B colored black.
-This results in a uniform grey colour of the
sprayed material thus giving the sprayer a visual
control of the quality of the mixing, and machine
faults become immediately obvious. If the
membrane colour changes, stop spraying and
check machine .
-MasterSeal M800 is normally applied at 1.5–
2.0kg/SQM this corresponds to a thickness of
1.5–2.0mm.
Ponding test
THANK
YOU!!!

Contenu connexe

Tendances

Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segmentsAxay Sharma
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineeringalok0025
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. trainingRam1239
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship reportMd Mohsin Mohsin
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential buildingsuraj jha
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNeha Vivek
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elementssubbu lakshmi
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge BearingsAyushHajare
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 

Tendances (20)

Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineering
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. training
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
Metro Work
Metro WorkMetro Work
Metro Work
 
ppt on training civil report on shuttering
ppt on training civil report on shutteringppt on training civil report on shuttering
ppt on training civil report on shuttering
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
Metro Project
Metro ProjectMetro Project
Metro Project
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
Training report ON BRIDGE
Training report ON BRIDGETraining report ON BRIDGE
Training report ON BRIDGE
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
PPT OF LG
PPT OF LGPPT OF LG
PPT OF LG
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge Bearings
 
Bridge report
Bridge reportBridge report
Bridge report
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 

Similaire à Construction of metro station

Supercap tds english
Supercap tds englishSupercap tds english
Supercap tds englishweebyx
 
Supercap fast tds english
Supercap fast tds englishSupercap fast tds english
Supercap fast tds englishweebyx
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)Sukhdarshan Singh
 
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxSubgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxEricNikorido1
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD hitendra pendam
 
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)Purna Mallick
 
An introduction to steel piles
An introduction to steel piles An introduction to steel piles
An introduction to steel piles Uday Nigam
 
Curing of concrete Amit payal
Curing of concrete  Amit payalCuring of concrete  Amit payal
Curing of concrete Amit payalAMIT PAYAL
 
Terrace Waterproofing Solutions
Terrace Waterproofing SolutionsTerrace Waterproofing Solutions
Terrace Waterproofing SolutionsRaja n Raja
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concreteErankajKumar
 
Waterproffing.pptx
Waterproffing.pptxWaterproffing.pptx
Waterproffing.pptxPrituJadhav1
 

Similaire à Construction of metro station (20)

Guniting ppt.pptx
Guniting ppt.pptxGuniting ppt.pptx
Guniting ppt.pptx
 
Supercap tds english
Supercap tds englishSupercap tds english
Supercap tds english
 
Supercap fast tds english
Supercap fast tds englishSupercap fast tds english
Supercap fast tds english
 
Unit 6..pptx
Unit 6..pptxUnit 6..pptx
Unit 6..pptx
 
Interface treatment
Interface treatmentInterface treatment
Interface treatment
 
DEVPOLYMERS SUGADEV
DEVPOLYMERS SUGADEVDEVPOLYMERS SUGADEV
DEVPOLYMERS SUGADEV
 
DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)DMRC (METRO TRAINING REPORT)
DMRC (METRO TRAINING REPORT)
 
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxSubgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
 
Tekcem supra
Tekcem supraTekcem supra
Tekcem supra
 
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
Roadconstructionequipment pptx2-130310150329-phpapp01 - copy (2)
 
An introduction to steel piles
An introduction to steel piles An introduction to steel piles
An introduction to steel piles
 
Curing of concrete Amit payal
Curing of concrete  Amit payalCuring of concrete  Amit payal
Curing of concrete Amit payal
 
Cons125
Cons125Cons125
Cons125
 
Terrace Waterproofing Solutions
Terrace Waterproofing SolutionsTerrace Waterproofing Solutions
Terrace Waterproofing Solutions
 
Surface Preparation.pptx
Surface Preparation.pptxSurface Preparation.pptx
Surface Preparation.pptx
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
Cementation
CementationCementation
Cementation
 
Waterproffing.pptx
Waterproffing.pptxWaterproffing.pptx
Waterproffing.pptx
 
Self curing-concrete-
Self curing-concrete-Self curing-concrete-
Self curing-concrete-
 

Dernier

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 

Dernier (20)

CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 

Construction of metro station

  • 1. AMIT KUMAR 1303200018 ANIMESH RANJAN 1303200023
  • 3. COST OF PROJECT(App) INR 1435 CRORES COMPLETION PERIOD(Expected) 42 MONTHS TENDER SECURITY AMOUNT INR 14.35 CRORES TENDERING AGENCY DMRC TENDER GIVEN TO L&T Quoted Price & Final Price 1265 CRORES
  • 4. PROPOSED ROUTE MAP FOR CC-27
  • 5.
  • 7.
  • 8. • VASANT VIHAR-HARD ROCK STRATA (BOTTOM-UP CONSTRUCTION APPROACH) • HAUZ KHAS - SOFT SOIL STRATA(TOP-BOTTOM CONSTRUCTION APPROACH)
  • 9. TOP VIEW – VASANT VIHAR METHOD OF CONSTRUCTION- BOTTOM UP CONSTRUCTION EAST SIDE WEST SIDE
  • 10. ROOF SLAB CONCOURSE SLAB BASE SLAB 1 2 3 4 5 6 7 8 1 BLOCK WORK 2 UPE(UNDER PLATFORM EXHAUST) 3 OTE(OVER TRACK EXHAUST) 4 PLATFORM SLAB 5 FRESH AIR DUCT(ROOF SLAB) 6 SCUPPER DRAIN(BEHIND BW) 7 FALSE CEILING BELOW CONCOURSE 8 COLUMN 9 RETAINING WALL CROSS SECTIONAL VIEW VASANT VIHAR 9
  • 11. Dimension of Block– 400*200*200 Mortar-Cement sand mortar with ratio 1:4 Block Strength- 7.5 N/mm2 MIX –M15 Thickness of the bond-10mm Joint Type-Basic English Bond(1 block thick) CONCOURSE SLAB ROOF SLAB BLOCK WORK IN FRONT OF RETAINING WALL RETAINING WALL INITIAL LAYER OF BLOCK WORK
  • 12. BASE SLAB UPE CUTOUT PLATFORM SLAB UNDER PLATFROM EXHAUST (UNDER PLATFROM EXHAUST ) are basically cut outs provided below the platform slab
  • 13.
  • 16.
  • 17.
  • 23.
  • 24.  Shot Creting is done according to IS 9012:1978(reaffirmed 2002)  Mix- 1:3 To 1:5 is used depending upon surface . W/c is kept at .30-.35  Plasticizer -6% wt of cement( Glenium sky 777)  Operating temp- 5deg to 30deg Celsius Mesh Dia- 4mm Mesh overlap length- 300mm Min area for applying-300mm*300mm
  • 25. Mechanism for Dry- Mix shot creting
  • 26. -M40 Grade Concrete was used -Reinforcement conforming to FE500D shall be used on site. -Water Stops –PVC water stop will be used to arrest the water leakage (at construction joints) -Binding wire used for binding reinforcement has a core dia of 1.25mm -Formwork ply 12mm thick coated with Formwork oil for easy removal of formwork -Cover blocks should be used depending on clearance that needs to be provided to the reinforcement(50mm Base slab) -Vibrator of 60mm Dia 4nos.
  • 27. Earth CompactorConcreting on site Proper vibration should be provided in order to avoid cold joints
  • 28. • AFTER THE FINAL SET HAS TAKEN PLACE WET HESSIAN CLOTH SHALL BE PLACED AND COVERED BY POLYTHENE SHEET. • THE HESSIAN CLOTH SHALL BE KEPT PERMANENTLY DAMP • AFTER 24HOURS HESSIAN CLOTH AND THE POLYTHENE SHEET SHALL BE REMOVED AND THE AREA WOULD BE • PONDED WITH WATER . • FOR VERTICAL CURING THE HESSIAN CLOTH ALONG WITH POLYTHENE SHEET SHALL SECURE THE SURFACE FOR AT LEASDAYS BEFORE • NEXT VERTICAL POURING BEGINS. THE HESSIAN CLOTH SHOULD BE DAMP ALL THE TIME.
  • 29. Concrtete-M40 5.25 m below roof level Thickness- 550mm Formwork & scaffolding for Concourse slab
  • 30. Sealing Of construction Joints on roof slab Cut Outs of the roof Slab( Satellite view) Design Mix M-40 Thickness-1.8m Roof level
  • 31. MATERIAL QUANTIY(KG) TYPE CEMENT 380 ULTRA TECH(OPC 53 GRADE) FLYASH 80 Ashtech:IS3812(NTPC BADARPUR) AGGREGATE(10mm) 481 Kotpulti AGGREGATE(20mm) 666 Kotpulti RIVER SAND 677 Yamuna Nagar W/C RATIO .35 ADMIXTURE @ .85% 3.91 Glenium 147,Suretec(BASF) W/P CAMPOunds@1% 4.6 MasterPel 760(BASF) WATER 161 R.O Water at Batching Plant Following admixture were used Masterglenium 147 provides  Extended workability  Providing the ultimate high strength, especially ready. Application Add to the mixture 80% -90% of the calculated water for the concrete mix and then, with the remaining water masterglenium 147 must be added to the mixture, Water Proofing Campound used- Masterpel 760  Provides resistance to water penetration either under hydrostatic pressure or capillary absorption.  Imparts integral water tightness to structures. Application MasterPel 760 is a ready-to-use powder which is dispensed into the concrete together with the cement. M-40 has been used for 3 slabs and retaining walls
  • 32. MATERIAL QUANTIY(KG) TYPE CEMENT 410 ULTRA TECH(OPC 53 GRADE) MICRO SILICA 22 TAM CEM AGGREGATE(10m m) 457 Kotpulti AGGREGATE(20m m) 686 Kotpulti RIVER SAND 765 Yamuna Nagar W/C RATIO .37 ADMIXTURE @ .85% 2.16 Glenium sky 777 WATER 151 R.O Water at Batching Plant M 50 was used for concreting of columns MasterGlenium SKY 8777 is the super plasticizer based on second generation polycarboxylic ether polymers, developed using nano- technology. The product has been primarily developed for applications in high performance ready-mix concrete to facilitate  Capability of delivering high quality concrete at any time to the job site in place. Tam Cem TamCem Micro Silica is composed of silicon dioxide (5i02).Collected from silicon metal and ferrosilicon. TamCem Micro Silica will react with the Calcium Hydroxide from the cement, which will form more of the Calcium Silicate hydrate, increasing the strength of the concrete.
  • 33. Volume-6cum but loaded up to 5-5.5cum. Rotations –Depend upon distance and Mix BOOM PLACER Concrete Bucket Vol 1-1.2cum CONCRETING THROUGH PIPES
  • 34. Bulged Concrete – Bulging in concrete takes place due to displacement of formwork. Surface preparation: The bulged area on concrete surface shall be hacked with chisel to required line, level. All dirt, dust shall be cleaned with brush and water. Repairing: Hacked area will be patched up with cement: sand mortar of proportion 1:4. On the completion of patch up work, the exposed area shall be thoroughly cured. Grout Loss Exposed aggregate surface created by exit of cement slurry/grout mortar from the gaps of formwork due to excessive vibration, unsealed joint of formwork during pouring of concrete. Repair -The concrete surface is cleaned and free from dust/oil/grease etc by using broom or wire mesh by scrubbing vigorously. -After removal of loose particles surface is washed with water. -Patch-up is done at cleaned surface with non-shrink Grout conbextra GP2
  • 35. IS DUE SEGREGATION OF AGGREGATES AND MORTAR INTO THE CONCRETE. HONEYCOMB CREATES IN STRUCTURES DUE TO MAINLY IMPROPER COMPACTION IN TERMS OF EXCESSIVE/INSUFFICIENT VIBRATION AT THE TIME OF PLACING. Minor Honey Combing Major Honeycombing Repairing Involves- The loose aggregate that are exposed shall be removed by gently tapping on it. After removal of all loose aggregate, dust, dirt etc. by wire/Soft brush then surface will be cleaned with Water. Patchup is done by using conbextra GP2/Rendroc which is mixed with cement and then the paste is applied.
  • 36. CHEMICALS USED FOR WATERPROOFING -FOR PRIMING PURPOSE MASTER SEAL M2525(PROVIDED IN TWO COMPONENT A & B) -WATERPROOFING LAYER MASTER SEAL M800(PROVIDED IN TWO COMPONENT A & B)
  • 37. A HIGHLY ELASTIC, SOLVENT FREE, ULTRA-FAST CURING, SPRAY APPLIED POLYURETHANE COATING AND IT IS USED IN WATERPROOFING APPLICATIONS. MASTER SEAL M800 IS A SOLVENT FREE, TWO COMPONENT SUBSTANCE. IT IS A HIGHLY REACTIVE TWO COMPONENT MIXTURE USED FOR WATERPROOFING IN TUNNELING AND CUT & COVER STATIONS USES- WATERPROOFING COMPOUND WITH A SETTING TIME OF 2-3SECONDS STEP WISE PROCESS FOR WATERPROOFING. -SURFACE CONDITIONS THE RCC SURFACE SHALL BE DRY BEFORE WATERPROOFING. ANY INGRESS FOR WATER SEEPAGE SHALL BE IDENTIFIED AND TREATED. CONSTRUCTION JOINT SHALL BE FILLED WITH HIGH PERFORMANCE WATER STOP GROUT OF CRYSTALLINE GROWTH.
  • 38. • MIXING OF A & B -Thin coat of mixed primer (RESIN + HARDNER) on the surface shall be mechanically & uniformly applied, ensuring continuous film soon after surface preparation is complete. -Moisture content in the substrate shall be less than 5 %. -The drying period of primer depends on the ambient temperature and relative humidity.
  • 39. Checking moisture before application of primer. BASF AGGREGATES BASF AGGREGATES are sprinkled over the primer layer immediately after application of the primer. Aggregates help in roughening the surface of primer for proper bonding between the primer layer and the waterproofing membrane layer.
  • 40. Application of the water proofing Layer with 2 component gun Special 2 Component gun used for applying waterproofing campound -MasterSeal M800 is available with the Part A coloured white and the Part B colored black. -This results in a uniform grey colour of the sprayed material thus giving the sprayer a visual control of the quality of the mixing, and machine faults become immediately obvious. If the membrane colour changes, stop spraying and check machine . -MasterSeal M800 is normally applied at 1.5– 2.0kg/SQM this corresponds to a thickness of 1.5–2.0mm. Ponding test
  • 41.