SlideShare une entreprise Scribd logo
1  sur  31
Télécharger pour lire hors ligne
Lecture by: Andualem Endris (M.Sc)
andu0117@yahoo.com
Chapter Two
Madawalabu
University
College of Engineering
Construction Technology and Management Department
Procurement Management and Contract Administration
CoTM 4242
1
COTM 4242 2
• Procurement is the acquisition of goods,
works, consultancy or other services through
purchasing, hiring or obtaining by any other
contractual means.
• Tendering is a stage in the procurement
process extending from advertisement
(invitation to bid) up to signing of contract.
• Tender is an offer which incorporates the sum
of money, time and other conditions required to
carry out the contract obligations in order to
complete a project or a part of it consisting of
specified works.
COTM 4242 3
 Stage 1: Inception & Feasibility study –
identifying project objectives / set up project brief
 Stage 2: Design – develop further project brief /
develop concept & schematic design / Undertake
detailed design & detailing / prepare cost plan & budget
 Stage 3: Tendering – issue tender documents /
prepare & submit tender / evaluation of tender / award
tenders / prepare contract documents
COTM 4242 4
 Stage 4: Construction – site possession &
mobilization / undertake procurement fabrication,
installation, construction / carry out contract
administration
 Stage 5: Handover & Maintenance –
undertake all testing, commissioning & training /
handover project to owner /carry out necessary
maintenance / Defect rectification / etc
COTM 4242 5
Tendering will be started after the design completed
and project budget is approved
The process that is used to obtain offers leading to a
contract between:
client contractor
client consultant
main contractor sub-contractor
COTM 4242 6
 A tender formally means an invitation
to trade under the terms of offer.
 A contract is the term used for when
the parties have reached agreement.
COTM 4242 7
COTM 4242 8
SELECTION
CRITERIA
In this process we look at the ways to
choose between different tenderers,
reviewing the specific Criteria for
tender evaluation:
•Pre-qualification
•Technical evaluation
•Financial Evaluation
•Relationship between Technical and
Financial
COTM 4242 9
Pre-
Qualification
Technical
Evaluation
Financial
Evaluation
Interested firms or consortia,
submit experience and financial
capacity details
Contracting Authority assesses
these details
Short list the firms
Only short-listed firms can
submit a proposal
Bidders submit proposals
COTM 4242 10
Pre-
Qualification
Bidders submit Technical Proposals,
showing how they would run the contract
Bidders provide information on Financial
and technical ability
Proposals assessed using ‘technical
evaluation criteria
Bidders have to pass a ‘technical
threshold’ to be eligible for selection (e.g.
scoring at least 70 percent on technical
evaluation criteria in our country)
Technical
Qualification
Financial
Evaluation
COTM 4242 11
Pre-
Qualification
Financial proposals of only technically
acceptable bids should be opened and
evaluated.
Financial Criteria can be very simple, as
following examples:
Bidder asking for lowest tariff
Bidder asking for Lowest Fee (Least Bidder)
Bidder with best financial proposal awarded
the contract
Financial
Qualification
Technical
Evaluation
COTM 4242 12
 To select a suitable contractor at a time
appropriate to the situation of the project.
 To obtain from the contractor selected at the
proper time, an acceptable tender or offer
upon which a contract can be let.
COTM 4242 13
COTM 4242 14
Stage 2:
APPROVAL TO
TENDER
Stage 1:
PREPARATION
Stage 3:
DOCUMENTATION
Stage 4:
INVITATION
Stage 5:
PROCESSING
Stage 6:
AWARD
CONTRACT
 Final completion of drawings, specification,
measurement / take-off process.
 Choose conditions of contract.
 Parties involved: architects, engineers, QS,
client
COTM 4242 15
 Discussion and decision on type of
tender to be used.
 Selection of tender:
 Open
 Selective
 Negotiate
 Parties involved: CLIENT, CONSULTANT,
and CONTRACTOR
COTM 4242 16
Short-listed
tenderers
Contract Document
 Letter of invitation
 Checklist for submission of tender
 Articles of agreement
 Form of tender
 Specifications
 Bills of quantities
 Drawings
 Letter of acceptance form
 Schedule of day work rates
COTM 4242 17
 Based on selection of tendering methods
 Open / competitive / bid tender – produce tender
notice
 Selective – short listed contractors will be invited to
tender if they wish
 Negotiated – only one contractor is approached-
direct entry to project
COTM 4242 18
 The Tender Notice is a brief
description of the job being tendered
which is to be published in
Newspapers and on the Internet.
 The Internet is a very cost effective
way of publishing the tenders.
COTM 4242 19
a. Name of the Project.
b. Name & Address of the
Company floating the tender.
c. Name of work, materials or
services.
d. Place of work location.
e. Approximate estimated cost
of work.
f. Earnest Money.
g. Period of completion.
h. Date on which the Tender
Document sale commences.
i. Date and time up to which
tender documents can be
obtained.
j. The cost of tender
documents.
k. The date and time up to
which the tenders to be
submitted and are to be
opened.
l. Specification.
m. Eligibility Criterion.
COTM 4242 20
 Receive tender submitted by contractor
 Tender assessment / evaluation
 Completed tenders are received
 Arithmetical check
 Reasonable tender sum
 Reasonable completion time
 Capabilities of renderers' under considerations
 Tender recommendation / report – tender board
COTM 4242 21
 Pre-award meeting with contractors – validation of
lowest complying bid
 Validate lowest bid - Pre-contract meeting with
contractor for contract signing
 Approval by tender board / treasury
COTM 4242 22
COTM 4242 23
COTM 4242 24
Stage 2:
Determine
basis of
tender
Stage 1:
Decision to
tender
Stage 3:
Preparation of
cost estimates
Stage 4:
Commercial
appreciation
Stage 5:
Conversion of
estimate to
tender
Stage 6:
Submission
of tender
 Receipt of tender documents
 Pre-tender data sheet
 Decision to tender
 Consider implications of:
 Bonds
 Warranties
 Parent company
 Guarantees
 Funding
COTM 4242 25
 Abstract materials and subcontractors
 Sent out enquiries
 Consider construction methods / prepare method
statement
 Design temporary works / consider alternatives
 Prepare outline program
 Check major quantities
 Identify restrictions
 Visit site and compile site report
 Campaigning meeting (designating areas
responsibilities)
COTM 4242 26
 Calculate current rates using:
 Materials
 Equipments and
 Labour costs
 Analyze and check subcontractors’ quotations
 Price prelims / general items (in association with
members of the team
 Prepare summary sheets
COTM 4242 27
 Tender committee meeting part 1:
 Review:
 Method
 Program
 Technical and commercial risks
 Cash flow and finance
 Use of own plant
 Competition
 Commercial opportunities
 Economic climate
 Check prelims against historical cost data
COTM 4242 28
 Tender committee meeting – part 2:
 Calculate ‘spread’ and add to estimate
COTM 4242 29
 Submit in format required (Bid
submission format)
 Organize delivery.
COTM 4242 30
31COTM 4242

Contenu connexe

Tendances

Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
Fakhar-un -Nisa
 

Tendances (20)

Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Contract Management in Civil Engineering Works
Contract Management in Civil Engineering WorksContract Management in Civil Engineering Works
Contract Management in Civil Engineering Works
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
Subcontract Agreement of Concrete/Earth Works (Purchase this doc, Text: 08118...
Subcontract Agreement of Concrete/Earth Works (Purchase this doc, Text: 08118...Subcontract Agreement of Concrete/Earth Works (Purchase this doc, Text: 08118...
Subcontract Agreement of Concrete/Earth Works (Purchase this doc, Text: 08118...
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Construction contract
Construction contract Construction contract
Construction contract
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Sample construction contract
Sample construction contractSample construction contract
Sample construction contract
 
#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi#FIDIC Understanding Basics# By SN Panigrahi
#FIDIC Understanding Basics# By SN Panigrahi
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
 

En vedette (7)

RIBA plan of work
RIBA plan of workRIBA plan of work
RIBA plan of work
 
14102008 - Nordic Ppp Forum Presentation Pja Peekel Final
14102008 - Nordic Ppp Forum   Presentation Pja Peekel   Final14102008 - Nordic Ppp Forum   Presentation Pja Peekel   Final
14102008 - Nordic Ppp Forum Presentation Pja Peekel Final
 
Tender writing – point of difference – important in wining tenders?
Tender writing – point of difference – important in wining tenders?Tender writing – point of difference – important in wining tenders?
Tender writing – point of difference – important in wining tenders?
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Tender procedure slide
Tender procedure slideTender procedure slide
Tender procedure slide
 

Similaire à Chapter 2 [compatibility mode]

Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
Muneesh Methwani
 

Similaire à Chapter 2 [compatibility mode] (20)

Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Tenders.ppt
 Tenders.ppt Tenders.ppt
Tenders.ppt
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Contract monitoring & evaluation
Contract monitoring & evaluationContract monitoring & evaluation
Contract monitoring & evaluation
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Tendering process for traditional contracts by eng. mohammed fadlalla
Tendering process for traditional contracts  by eng. mohammed fadlallaTendering process for traditional contracts  by eng. mohammed fadlalla
Tendering process for traditional contracts by eng. mohammed fadlalla
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
CH-3-Introduction.pptx
CH-3-Introduction.pptxCH-3-Introduction.pptx
CH-3-Introduction.pptx
 
procurement overview
procurement overviewprocurement overview
procurement overview
 
Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014Arunkumar_Proc & Contr_25.12.2014
Arunkumar_Proc & Contr_25.12.2014
 
Tendering
TenderingTendering
Tendering
 
Tender
TenderTender
Tender
 

Plus de Delhi Technological University

Plus de Delhi Technological University (20)

Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 
Chapter 4- Contract Management
Chapter 4- Contract ManagementChapter 4- Contract Management
Chapter 4- Contract Management
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Chapter 2- Construction Law
Chapter 2- Construction Law Chapter 2- Construction Law
Chapter 2- Construction Law
 
Chapter 1-Construction Law
Chapter 1-Construction Law Chapter 1-Construction Law
Chapter 1-Construction Law
 
Chapter 5- Lecture
Chapter 5- LectureChapter 5- Lecture
Chapter 5- Lecture
 
Chapter 4- Lecture
Chapter 4- LectureChapter 4- Lecture
Chapter 4- Lecture
 
Chapter 3- Lecture
Chapter 3- LectureChapter 3- Lecture
Chapter 3- Lecture
 
Chapter 2- Lecture
Chapter 2- LectureChapter 2- Lecture
Chapter 2- Lecture
 
Chapter 1- Lecture
Chapter 1- LectureChapter 1- Lecture
Chapter 1- Lecture
 
Construction equipment management chapter 5
Construction equipment management chapter 5Construction equipment management chapter 5
Construction equipment management chapter 5
 
Construction equipment management chapter 4
Construction equipment management chapter 4Construction equipment management chapter 4
Construction equipment management chapter 4
 
Construction equipment management chapter 3
Construction equipment management chapter 3Construction equipment management chapter 3
Construction equipment management chapter 3
 
Construction equipment management chapter 2
Construction equipment management chapter 2Construction equipment management chapter 2
Construction equipment management chapter 2
 
Construction equipment management chapter 1pdf
Construction equipment management chapter 1pdfConstruction equipment management chapter 1pdf
Construction equipment management chapter 1pdf
 
Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]Chapter 5 [compatibility mode]
Chapter 5 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 

Dernier

Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 

Dernier (20)

Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 

Chapter 2 [compatibility mode]

  • 1. Lecture by: Andualem Endris (M.Sc) andu0117@yahoo.com Chapter Two Madawalabu University College of Engineering Construction Technology and Management Department Procurement Management and Contract Administration CoTM 4242 1
  • 3. • Procurement is the acquisition of goods, works, consultancy or other services through purchasing, hiring or obtaining by any other contractual means. • Tendering is a stage in the procurement process extending from advertisement (invitation to bid) up to signing of contract. • Tender is an offer which incorporates the sum of money, time and other conditions required to carry out the contract obligations in order to complete a project or a part of it consisting of specified works. COTM 4242 3
  • 4.  Stage 1: Inception & Feasibility study – identifying project objectives / set up project brief  Stage 2: Design – develop further project brief / develop concept & schematic design / Undertake detailed design & detailing / prepare cost plan & budget  Stage 3: Tendering – issue tender documents / prepare & submit tender / evaluation of tender / award tenders / prepare contract documents COTM 4242 4
  • 5.  Stage 4: Construction – site possession & mobilization / undertake procurement fabrication, installation, construction / carry out contract administration  Stage 5: Handover & Maintenance – undertake all testing, commissioning & training / handover project to owner /carry out necessary maintenance / Defect rectification / etc COTM 4242 5
  • 6. Tendering will be started after the design completed and project budget is approved The process that is used to obtain offers leading to a contract between: client contractor client consultant main contractor sub-contractor COTM 4242 6
  • 7.  A tender formally means an invitation to trade under the terms of offer.  A contract is the term used for when the parties have reached agreement. COTM 4242 7
  • 8. COTM 4242 8 SELECTION CRITERIA In this process we look at the ways to choose between different tenderers, reviewing the specific Criteria for tender evaluation: •Pre-qualification •Technical evaluation •Financial Evaluation •Relationship between Technical and Financial
  • 9. COTM 4242 9 Pre- Qualification Technical Evaluation Financial Evaluation Interested firms or consortia, submit experience and financial capacity details Contracting Authority assesses these details Short list the firms Only short-listed firms can submit a proposal Bidders submit proposals
  • 10. COTM 4242 10 Pre- Qualification Bidders submit Technical Proposals, showing how they would run the contract Bidders provide information on Financial and technical ability Proposals assessed using ‘technical evaluation criteria Bidders have to pass a ‘technical threshold’ to be eligible for selection (e.g. scoring at least 70 percent on technical evaluation criteria in our country) Technical Qualification Financial Evaluation
  • 11. COTM 4242 11 Pre- Qualification Financial proposals of only technically acceptable bids should be opened and evaluated. Financial Criteria can be very simple, as following examples: Bidder asking for lowest tariff Bidder asking for Lowest Fee (Least Bidder) Bidder with best financial proposal awarded the contract Financial Qualification Technical Evaluation
  • 13.  To select a suitable contractor at a time appropriate to the situation of the project.  To obtain from the contractor selected at the proper time, an acceptable tender or offer upon which a contract can be let. COTM 4242 13
  • 14. COTM 4242 14 Stage 2: APPROVAL TO TENDER Stage 1: PREPARATION Stage 3: DOCUMENTATION Stage 4: INVITATION Stage 5: PROCESSING Stage 6: AWARD CONTRACT
  • 15.  Final completion of drawings, specification, measurement / take-off process.  Choose conditions of contract.  Parties involved: architects, engineers, QS, client COTM 4242 15
  • 16.  Discussion and decision on type of tender to be used.  Selection of tender:  Open  Selective  Negotiate  Parties involved: CLIENT, CONSULTANT, and CONTRACTOR COTM 4242 16 Short-listed tenderers
  • 17. Contract Document  Letter of invitation  Checklist for submission of tender  Articles of agreement  Form of tender  Specifications  Bills of quantities  Drawings  Letter of acceptance form  Schedule of day work rates COTM 4242 17
  • 18.  Based on selection of tendering methods  Open / competitive / bid tender – produce tender notice  Selective – short listed contractors will be invited to tender if they wish  Negotiated – only one contractor is approached- direct entry to project COTM 4242 18
  • 19.  The Tender Notice is a brief description of the job being tendered which is to be published in Newspapers and on the Internet.  The Internet is a very cost effective way of publishing the tenders. COTM 4242 19
  • 20. a. Name of the Project. b. Name & Address of the Company floating the tender. c. Name of work, materials or services. d. Place of work location. e. Approximate estimated cost of work. f. Earnest Money. g. Period of completion. h. Date on which the Tender Document sale commences. i. Date and time up to which tender documents can be obtained. j. The cost of tender documents. k. The date and time up to which the tenders to be submitted and are to be opened. l. Specification. m. Eligibility Criterion. COTM 4242 20
  • 21.  Receive tender submitted by contractor  Tender assessment / evaluation  Completed tenders are received  Arithmetical check  Reasonable tender sum  Reasonable completion time  Capabilities of renderers' under considerations  Tender recommendation / report – tender board COTM 4242 21
  • 22.  Pre-award meeting with contractors – validation of lowest complying bid  Validate lowest bid - Pre-contract meeting with contractor for contract signing  Approval by tender board / treasury COTM 4242 22
  • 24. COTM 4242 24 Stage 2: Determine basis of tender Stage 1: Decision to tender Stage 3: Preparation of cost estimates Stage 4: Commercial appreciation Stage 5: Conversion of estimate to tender Stage 6: Submission of tender
  • 25.  Receipt of tender documents  Pre-tender data sheet  Decision to tender  Consider implications of:  Bonds  Warranties  Parent company  Guarantees  Funding COTM 4242 25
  • 26.  Abstract materials and subcontractors  Sent out enquiries  Consider construction methods / prepare method statement  Design temporary works / consider alternatives  Prepare outline program  Check major quantities  Identify restrictions  Visit site and compile site report  Campaigning meeting (designating areas responsibilities) COTM 4242 26
  • 27.  Calculate current rates using:  Materials  Equipments and  Labour costs  Analyze and check subcontractors’ quotations  Price prelims / general items (in association with members of the team  Prepare summary sheets COTM 4242 27
  • 28.  Tender committee meeting part 1:  Review:  Method  Program  Technical and commercial risks  Cash flow and finance  Use of own plant  Competition  Commercial opportunities  Economic climate  Check prelims against historical cost data COTM 4242 28
  • 29.  Tender committee meeting – part 2:  Calculate ‘spread’ and add to estimate COTM 4242 29
  • 30.  Submit in format required (Bid submission format)  Organize delivery. COTM 4242 30