SlideShare une entreprise Scribd logo
1  sur  25
Presented by:
ANURAGYADAV
Masters ofTechnology
Indian Institute ofTechnology Roorkee
An impervious layer which is provided at
the bed and sides of the canal to
increase the life, discharge and
hydraulic efficiency of the channel is
known as Lining.
Stable channels are those in which neither Silting nor Scouring
takes place.These are also known as regime channels.These are
designed on the basis that:
•Silt entering the channel should remain in suspension form.
•Flow velocity should be such that no erosion takes place
from
channel surface.
•Such channels are known as Hydraulically Efficient channels.
Prevents water seepage through surface of the canal.
Helps in preventing Water-Logging.
Increases discharge carrying capacity of the channel.
Increases channel life and reduce the maintenance cost.
Increases Gross area under cultivation.
Silting is prevented as velocity is increased.
Prevents or ReducesWeed Growth.
Increase available head for power generation due to flatter
gradient.
Heavy initial investment is required.
Difficult to shift the outlets as lining is permanent.
Difficult to repair the damaged lining.
Berm is absent in Lined channels,so safety to vehicular and
pedestrian traffic gets reduced.
THEREFORE,LINING IS DONE IFFTHE ANNUAL
BENEFITS EXCEEDSTHE ANNUAL COST.
Main types of concrete lining used in India are:
HARD SURFACETYPE LINING:
>> Cement concrete Lining
>>Shotcrete Lining
>>Precast concrete Lining
>>Cement Mortar Lining
>>Brick Lining
>>Stone blocks Lining
>>Asphaltic Lining
EARTHTYPE LINING:
>>Soil cement Lining
>>Clay puddle Lining
>>Sodium carbonate Lining
It has high initial cost so its use is limited.
It has excellent hydraulic properties.
Thickness varies from 5-10cm for M 15 concrete and 7.5 to
15cm for M 10 concrete.
A subgrade is prepared and compacted.
Subgrade is saturated to a depth of 30cm in sandy soil and
15cm in other soils.
 Lay a base coat of 1:4 cement and sand slurry on the
subgrade.
Spread oil paper/crude oil on the subgrade.
The concrete is usually laid in alternate blocks.
Shotcrete consumes large amount of cement.
Cement and Sand in the ratio (1:4) is shot at the subgrade
through a nozzle.
Thickness of this type of lining varies from 2.5 to 6.5 cm.
Shotcrete is also used for repair of old but sound concrete
lining.
This consists of precast slabs usually 90cm x 30cm in size.
Thickness of each slab varies from 5 to 6.5 cm.
Blocks are manufactured with an interlocking
arrangement.
 Slabs are laid on well prepared and compacted subgrade.
It is usually used as sandwich material between brick layers.
Thickness for this type of lining is kept from 1 to 4 cm.
A large amount of cement is consumed in this type of lining
and thus it is quite costly.
It consists of a single or double layer of brick masonry.
The size of brick is restricted to 30x15x5 cm for convenience
of handling.
This type of lining has been used in Punjab on Bhakra and
Haveli canals.
 It is hydraulically as efficient as concrete lining.
In case of failure repair can be done easily.
It is a controlled mixture of asphalt and grade aggregate
mixed and placed at high temperature of 200⁰C.
 It is covered with 30 cm layer of earth material for
protection.
The mix is placed either by hand or by an equipment similar
to that of concrete.
In this the mixture in proportion of 90 to 95% soil and 10
to 5% cement is thoroughly mixed dry and is then added
with water to raise the moisture content to optimum.
It is therefore placed on the subgrade and properly
compacted.
In U.S.A plastic soil cement has been used with a higher
consistency to get a faster rate of construction.
Clay puddle is produced from clay by first exposing clay to
weathering.
It is then mixed with water to bring it to the saturation and
is pugged thoroughly under man’s or cattle’s feet.
Lining thickness is 30 cm.
It is then protected by earth material.
The mixture consists of clayey soil and sodium carbonate
in a proportion of 10% clay and 6% sodium carbonate.
Thickness is kept as 10 cm.
This type of canal is used on small canals.
This consists of undressed stone block set in mortar and
laid over a prepared subgrade.
The lining is able to check seepage effectively but has a
considerable resistance to water flow.
Dressed stone block lining is effective but costly.
Mainly two types of lined channels are
preferred:
TRIANGULAR SECTION (Q<150 m3 / s)
TRAPEZOIDAL SECTION (Q>150 m3 / s)
There are many other sections also but we will
consider designing of only these two types of
channels.
The permissible velocity in the lined channel for different
types of materials lie in the following range.
For concrete lining: 2-2.5 m/s.
For clay lining: 1.6-1.8 m/s.
For boulder lining: 1.5 m/s.
This velocity is used to calculate the hydraulic mean
depth(R) of channel section using Manning’s equation.Surface
slope is known.
Area of flow is calculated as per the discharge.
Perimeter =Area/Hydraulic mean depth.
Side slope can be taken to be in the range of 1.25H:1V to
2H:1V.
REFERENCES
 Rolt, L.T.C. (1969). Navigable
Waterways. W & J Mackay.
Jump up^ George M. Reeves, Ian Sims,
J. C. Cripps Eds., Clay Materials Used in
Construction, p.377. Geological Society,
2006. ISBN 978-1-86239-184-0
Waterways in the Making, Edward
Paget-Tomlinson, The Landscape Press,
1996, ISBN 0-947849-03-0
The Illustrated History of Canal and
River Navigations, Edward Paget-
Tomlinson, Landmark Publishing Ltd.,
2006, ISBN 1-84306-207-0
www.nptel.ac.in
Irrigation and water power engineering-
Punmia BC.
LINING OF CHANNELS

Contenu connexe

Tendances

Tendances (20)

Reservior planning
Reservior    planningReservior    planning
Reservior planning
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion HeadworkDesign of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
 
Canal outlets
Canal outletsCanal outlets
Canal outlets
 
Irrigation Engineering
Irrigation EngineeringIrrigation Engineering
Irrigation Engineering
 
Classification of dams
Classification of damsClassification of dams
Classification of dams
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Chapter 4 seepage theories
Chapter 4 seepage theoriesChapter 4 seepage theories
Chapter 4 seepage theories
 
Irrigation Channels
Irrigation ChannelsIrrigation Channels
Irrigation Channels
 
minor and micro irrigation
 minor and micro irrigation minor and micro irrigation
minor and micro irrigation
 
Storage head works
Storage head worksStorage head works
Storage head works
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Spillway
Spillway Spillway
Spillway
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Silt excluders
Silt excludersSilt excluders
Silt excluders
 
types of canals
types of canals types of canals
types of canals
 
Canal headworks
Canal headworksCanal headworks
Canal headworks
 
L 5and l-6 sewer design
L 5and l-6 sewer designL 5and l-6 sewer design
L 5and l-6 sewer design
 

Similaire à LINING OF CHANNELS

Similaire à LINING OF CHANNELS (20)

Unit 4-canal lining
Unit 4-canal liningUnit 4-canal lining
Unit 4-canal lining
 
Presentation final
Presentation final Presentation final
Presentation final
 
Check dams
Check damsCheck dams
Check dams
 
Raod side ditches
Raod side ditchesRaod side ditches
Raod side ditches
 
Permeable pavements
Permeable pavementsPermeable pavements
Permeable pavements
 
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
IRJET- The Study of Porous Asphalt Pavement with Emphasis in Road Constructio...
 
Gangaram yadav ppt road con....
Gangaram yadav ppt road con....Gangaram yadav ppt road con....
Gangaram yadav ppt road con....
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
Grouting n gunintung
Grouting n gunintungGrouting n gunintung
Grouting n gunintung
 
Gully Control Structures.pptx
Gully Control Structures.pptxGully Control Structures.pptx
Gully Control Structures.pptx
 
Cross section of a fish pond
Cross section of a fish pondCross section of a fish pond
Cross section of a fish pond
 
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
 
Cement morter
Cement morterCement morter
Cement morter
 
ppt.pptx
ppt.pptxppt.pptx
ppt.pptx
 
N1304038490
N1304038490N1304038490
N1304038490
 
Pervious Concrete
Pervious ConcretePervious Concrete
Pervious Concrete
 
Swe l-8-earthen channels and under ground pipe line
Swe l-8-earthen channels and under ground pipe lineSwe l-8-earthen channels and under ground pipe line
Swe l-8-earthen channels and under ground pipe line
 
Sanitary sewer outlet
Sanitary sewer outletSanitary sewer outlet
Sanitary sewer outlet
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptx
 
Plastic cell filled concretepavement .pptx
Plastic cell filled concretepavement .pptxPlastic cell filled concretepavement .pptx
Plastic cell filled concretepavement .pptx
 

LINING OF CHANNELS

  • 2. An impervious layer which is provided at the bed and sides of the canal to increase the life, discharge and hydraulic efficiency of the channel is known as Lining.
  • 3. Stable channels are those in which neither Silting nor Scouring takes place.These are also known as regime channels.These are designed on the basis that: •Silt entering the channel should remain in suspension form. •Flow velocity should be such that no erosion takes place from channel surface. •Such channels are known as Hydraulically Efficient channels.
  • 4. Prevents water seepage through surface of the canal. Helps in preventing Water-Logging. Increases discharge carrying capacity of the channel. Increases channel life and reduce the maintenance cost. Increases Gross area under cultivation. Silting is prevented as velocity is increased. Prevents or ReducesWeed Growth. Increase available head for power generation due to flatter gradient.
  • 5. Heavy initial investment is required. Difficult to shift the outlets as lining is permanent. Difficult to repair the damaged lining. Berm is absent in Lined channels,so safety to vehicular and pedestrian traffic gets reduced. THEREFORE,LINING IS DONE IFFTHE ANNUAL BENEFITS EXCEEDSTHE ANNUAL COST.
  • 6. Main types of concrete lining used in India are: HARD SURFACETYPE LINING: >> Cement concrete Lining >>Shotcrete Lining >>Precast concrete Lining >>Cement Mortar Lining >>Brick Lining >>Stone blocks Lining >>Asphaltic Lining EARTHTYPE LINING: >>Soil cement Lining >>Clay puddle Lining >>Sodium carbonate Lining
  • 7. It has high initial cost so its use is limited. It has excellent hydraulic properties. Thickness varies from 5-10cm for M 15 concrete and 7.5 to 15cm for M 10 concrete. A subgrade is prepared and compacted. Subgrade is saturated to a depth of 30cm in sandy soil and 15cm in other soils.  Lay a base coat of 1:4 cement and sand slurry on the subgrade. Spread oil paper/crude oil on the subgrade. The concrete is usually laid in alternate blocks.
  • 8. Shotcrete consumes large amount of cement. Cement and Sand in the ratio (1:4) is shot at the subgrade through a nozzle. Thickness of this type of lining varies from 2.5 to 6.5 cm. Shotcrete is also used for repair of old but sound concrete lining.
  • 9. This consists of precast slabs usually 90cm x 30cm in size. Thickness of each slab varies from 5 to 6.5 cm. Blocks are manufactured with an interlocking arrangement.  Slabs are laid on well prepared and compacted subgrade.
  • 10. It is usually used as sandwich material between brick layers. Thickness for this type of lining is kept from 1 to 4 cm. A large amount of cement is consumed in this type of lining and thus it is quite costly.
  • 11. It consists of a single or double layer of brick masonry. The size of brick is restricted to 30x15x5 cm for convenience of handling. This type of lining has been used in Punjab on Bhakra and Haveli canals.  It is hydraulically as efficient as concrete lining. In case of failure repair can be done easily.
  • 12. It is a controlled mixture of asphalt and grade aggregate mixed and placed at high temperature of 200⁰C.  It is covered with 30 cm layer of earth material for protection. The mix is placed either by hand or by an equipment similar to that of concrete.
  • 13. In this the mixture in proportion of 90 to 95% soil and 10 to 5% cement is thoroughly mixed dry and is then added with water to raise the moisture content to optimum. It is therefore placed on the subgrade and properly compacted. In U.S.A plastic soil cement has been used with a higher consistency to get a faster rate of construction.
  • 14. Clay puddle is produced from clay by first exposing clay to weathering. It is then mixed with water to bring it to the saturation and is pugged thoroughly under man’s or cattle’s feet. Lining thickness is 30 cm. It is then protected by earth material.
  • 15. The mixture consists of clayey soil and sodium carbonate in a proportion of 10% clay and 6% sodium carbonate. Thickness is kept as 10 cm. This type of canal is used on small canals.
  • 16. This consists of undressed stone block set in mortar and laid over a prepared subgrade. The lining is able to check seepage effectively but has a considerable resistance to water flow. Dressed stone block lining is effective but costly.
  • 17. Mainly two types of lined channels are preferred: TRIANGULAR SECTION (Q<150 m3 / s) TRAPEZOIDAL SECTION (Q>150 m3 / s) There are many other sections also but we will consider designing of only these two types of channels.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22. The permissible velocity in the lined channel for different types of materials lie in the following range. For concrete lining: 2-2.5 m/s. For clay lining: 1.6-1.8 m/s. For boulder lining: 1.5 m/s. This velocity is used to calculate the hydraulic mean depth(R) of channel section using Manning’s equation.Surface slope is known. Area of flow is calculated as per the discharge. Perimeter =Area/Hydraulic mean depth. Side slope can be taken to be in the range of 1.25H:1V to 2H:1V.
  • 23.
  • 24. REFERENCES  Rolt, L.T.C. (1969). Navigable Waterways. W & J Mackay. Jump up^ George M. Reeves, Ian Sims, J. C. Cripps Eds., Clay Materials Used in Construction, p.377. Geological Society, 2006. ISBN 978-1-86239-184-0 Waterways in the Making, Edward Paget-Tomlinson, The Landscape Press, 1996, ISBN 0-947849-03-0 The Illustrated History of Canal and River Navigations, Edward Paget- Tomlinson, Landmark Publishing Ltd., 2006, ISBN 1-84306-207-0 www.nptel.ac.in Irrigation and water power engineering- Punmia BC.