SlideShare une entreprise Scribd logo
1  sur  23
CPM (Critical Path Method)
CPM Objective
• To estimate the total project duration and to
assign starting and finishing times to all
activities involved in the project
What factors should we consider
for project scheduling?
•
•
•
•

Total completion time of the project
Earlier and latest start time of each activity
Critical activities and critical path
Float for each activity (I.e. the amount of
time by which the completion of a non
critical activity can be delayed without
delaying the total project completion time)
Important Notations
• Ei = Earliest occurrence time of an event (I.e.
The earliest time for an event to occur
immediately after al the preceding activities
have been completed without delaying the
entire project)
• Li = Latest allowable time for an event (I.e.
The latest time at which an event can occur
without causing a delay in already determined
project’s completion time)
Important Notations (contd…)
• ESij = Early starting time for an activity (i,j). It
is the earliest time an activity can possibly
start without affecting the project completion
• LSij = Late starting time for an activity (i,j) . It
is the latest possible time an activity can start
without delaying the project completion time
Important Notations (contd…)
• EFij = Early finishing time for an activity
(i,j). It is the earliest time an activity can
possibly finish without affecting the project
completion
• LFij = Late finishing time for an activity (i,j)
. It is the latest possible time an activity can
start without delaying the project
completion time
• Tij = Duration of an activity (i.j)
How to calculate earliest
occurrence and latest available
times of events?
• Forward pass method for calculating
earliest event time
• Backward pass method for latest available
event time
Forward pass method
• Start with initial event numbered 1. Earliest
occurrence time for event 1 is always zero.
I.e E1 = 0 where i = 1
• Calculate earliest start time for each activity
that begins at event ( i = 1). This is equal to
the earliest start time of event I (tail event)
(I.e) ESij = Ei for all activities (i.j) starting at
event i
Forward pass method (Contd..)
• Calculate earliest finish time of each
activity that begins at event (i) . This is
equal to the earliest start time of the activity
plus the duration of the activity
(I.e) EFij = ESij + tij = Ei + tij, for all activities
(i,j) beginning at event i.
Forward pass method (Contd..)
• Proceed to the next event j ; j > I
• Calculate the earliest occurrence time for the event
j. This is the maximum of the earliest finish times
of all activities ending into that event
Ej = Max { EFij} = Max { Ei + tij }, for all immediate
predecessor activities
 If N is the final event then earliest finish time for
the project (or) the earliest occurrence time EN for
the final event is given by
EN = Max {EFij} = Max {EN-1+ tij}, for all terminal
activities
Backward pass method (For
latest allowable event time)

• Set the latest occurrence event N equal to
its earliest occurrence time (known from
forward pass method) LN = EN , j = N
• Latest finish time of each activity which
ends at event j, LFij = Lj
• Latest start time of each activity ending at j,
LSij= LFij-tij
• Latest occurrence time for event ( i) where
i<j , L = Min {LSij}= Min {Lj-tij}
• L1=0
Sample CPM problem
Draw the network diagram and find
the critical path
A
B
C
D
E
F
G
H
I
J
K
L
M

Design new premises
Obtain tenders from the contractors
Select the contractor
Arrange details with the selected contractor
Decide which equipment to be used
Arrange storage of equipment
Arrange disposal of other equipment
Order new equipment
Take delivery of new equipment
Renovations take place
Remove old equipment
Cleaning
Return old equipment

A
B
C
A
E
E
E
H,L
K
D,F,G
J
H,L

14
4
2
1
2
3
2
4
3
12
4
2
2
Solution with critical path
E3=18
L3=18

C (2)
5

3

D(1)
E6=18
L6=21

B(4)

A (14)

E1=0
L1=0

2

E (2)

E2=14
L2=14

E7=21
L7=21
K (4)

8
J(12)

7

6

G(2)
1

E8=25
L8=25

E5=20
L5=20

F(3)
4

9

E9=37
L9=37

L(2)

M(2)
12

10
I (3)

H (4)
E4=16
L4=18

11

E11=41
L11=42

E10=39
L10=39

E12=42
L12=42
From the earlier example what is
the critical path?
• The critical path is the sequence of critical
activities that form a continuous path
between the start of a project & its
completion
• It is the longest path
• Critical events : where E = L
• Critical activities float is 0.
Floats
• Calculated for non critical activity or non
critical event
• The length of time to which a non critical
activity and/or an event can be delayed or
extended without delaying the total project
completion time
• Float can be called as slack or free time also
Float on event
• Float slack of an event is the difference
between its latest occurrence time and its
earliest occurrence time
• Event float = Li-Ei
• Event float is 0 for critical events (I.e. L = E)
Float on activities
• The length of free time available within the
estimated times of non-critical activities
• 3 types of float for non-critical activities
– Total float
– Free float
– Independent float
Total float
• Length of time by which an activity can be
delayed if all its predecessor activities are
completed at its earliest possible time and
all successor activities can be delayed until
their latest permissible time
• Total float TFij= (Lj-tij)-Ei
Free float
• Time by which the completion of an
activity can be delayed without causing any
delay in its immediate succeeding activities
• Free float FFij= (Ej-Ei)-tij
Independent float
• Amount of time available when preceding
activities are completed at their latest
permissible times and the following
activities can still be completed at their
earliest possible times
• Independent float IFij=(Ej-Li)-tij
• Negative value of independent float is
considered as 0
Further on floats
• Latest occurrence time of an event is always
greater than or equal to its earliest occurrence
time. This implies
Independent float < Free float < Total float
• Floats help in identifying underutilized
resources,flexibility in the total schedule and
possibilities of redeployment of resources
• Once a float of an activity is disturbed, float for
all other activities of the project is changed and
should be recalculated
What does a float value mean?
• If float value is negative, it means project
completion is behind the schedule data.
Resources are not adequate and activity may
not finish in time
• Float = 0. Just enough resources, no
possibility for delay
• Float is positive means resources are surplus
and can be deployed elsewhere as required

Contenu connexe

Tendances

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Short Comings of Bar Chart and Remidial Measures
Short Comings of Bar Chart and Remidial MeasuresShort Comings of Bar Chart and Remidial Measures
Short Comings of Bar Chart and Remidial Measuressudheerkumar_nitw
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Project monitoring and control &amp; planning for monitoring
Project monitoring and control &amp; planning for monitoringProject monitoring and control &amp; planning for monitoring
Project monitoring and control &amp; planning for monitoringSandeep Kumar
 
Road Project Schedule M S Project.ppt
Road Project Schedule M S Project.pptRoad Project Schedule M S Project.ppt
Road Project Schedule M S Project.pptkilldudeMohan
 
Rules for Network Construction
Rules for Network ConstructionRules for Network Construction
Rules for Network ConstructionRaja Adapa
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)El Moro
 

Tendances (20)

Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Short Comings of Bar Chart and Remidial Measures
Short Comings of Bar Chart and Remidial MeasuresShort Comings of Bar Chart and Remidial Measures
Short Comings of Bar Chart and Remidial Measures
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Project monitoring and control &amp; planning for monitoring
Project monitoring and control &amp; planning for monitoringProject monitoring and control &amp; planning for monitoring
Project monitoring and control &amp; planning for monitoring
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
CPM NETWORK
CPM NETWORKCPM NETWORK
CPM NETWORK
 
Road Project Schedule M S Project.ppt
Road Project Schedule M S Project.pptRoad Project Schedule M S Project.ppt
Road Project Schedule M S Project.ppt
 
Rules for Network Construction
Rules for Network ConstructionRules for Network Construction
Rules for Network Construction
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 

En vedette

Critical path method
Critical path methodCritical path method
Critical path methodNicola2903
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 
Advantages of swot analysis
Advantages of swot analysisAdvantages of swot analysis
Advantages of swot analysisDhivya S Dhvi
 
Internal Auditing - Performance Standards
Internal Auditing - Performance StandardsInternal Auditing - Performance Standards
Internal Auditing - Performance Standardsaldenmae
 
Establishing performance standards
Establishing performance standardsEstablishing performance standards
Establishing performance standardsRajendra Nabar
 
Eindtermen en leerplannen wo natuur - Walter Dons
Eindtermen en leerplannen wo natuur - Walter DonsEindtermen en leerplannen wo natuur - Walter Dons
Eindtermen en leerplannen wo natuur - Walter DonsPIME
 
Swot analysis , its importance and limitations
Swot analysis , its importance and limitationsSwot analysis , its importance and limitations
Swot analysis , its importance and limitationsSuleyman Ally
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applicationsAmrit Mty
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Management and it's functions
Management and it's functionsManagement and it's functions
Management and it's functionsGeorge Cherian
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review TechniqueRaymund Sanchez
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 

En vedette (20)

Critical path method
Critical path methodCritical path method
Critical path method
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Advantages of swot analysis
Advantages of swot analysisAdvantages of swot analysis
Advantages of swot analysis
 
Critical Path Method presentation.
Critical Path Method presentation.Critical Path Method presentation.
Critical Path Method presentation.
 
Internal Auditing - Performance Standards
Internal Auditing - Performance StandardsInternal Auditing - Performance Standards
Internal Auditing - Performance Standards
 
Establishing performance standards
Establishing performance standardsEstablishing performance standards
Establishing performance standards
 
Eindtermen en leerplannen wo natuur - Walter Dons
Eindtermen en leerplannen wo natuur - Walter DonsEindtermen en leerplannen wo natuur - Walter Dons
Eindtermen en leerplannen wo natuur - Walter Dons
 
P E R T
P E R TP E R T
P E R T
 
Swot analysis , its importance and limitations
Swot analysis , its importance and limitationsSwot analysis , its importance and limitations
Swot analysis , its importance and limitations
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Management and it's functions
Management and it's functionsManagement and it's functions
Management and it's functions
 
Posdcorb
PosdcorbPosdcorb
Posdcorb
 
Posdcorb
PosdcorbPosdcorb
Posdcorb
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 

Similaire à Cpm (critical path method)

Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementAKSHAYA0000
 
Unit2 network optimization
Unit2 network optimizationUnit2 network optimization
Unit2 network optimizationDevaKumari Vijay
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjlicpn03
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfSalahudin Babar
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptxLJay7
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project ManagementIshan Gandhi
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.pptNitin137794
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxmohammad_bilal
 

Similaire à Cpm (critical path method) (20)

Project management
Project managementProject management
Project management
 
Chapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
 
Unit2 network optimization
Unit2 network optimizationUnit2 network optimization
Unit2 network optimization
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Critical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdjCritical path lecture by EDP.pptxbdhshsjjdj
Critical path lecture by EDP.pptxbdhshsjjdj
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Pert_CPM.pptx
Pert_CPM.pptxPert_CPM.pptx
Pert_CPM.pptx
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Cpmpert
CpmpertCpmpert
Cpmpert
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
 
Networktechniques
NetworktechniquesNetworktechniques
Networktechniques
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
 

Plus de Areef Khan

1 making of textilefutyfuyuy
1 making of textilefutyfuyuy1 making of textilefutyfuyuy
1 making of textilefutyfuyuyAreef Khan
 
162160659 satyam-shrey-shahityrr
162160659 satyam-shrey-shahityrr162160659 satyam-shrey-shahityrr
162160659 satyam-shrey-shahityrrAreef Khan
 
Jobportal 130815001657-phpapp01
Jobportal 130815001657-phpapp01Jobportal 130815001657-phpapp01
Jobportal 130815001657-phpapp01Areef Khan
 
2 pulleys and belt drives
2 pulleys and belt drives2 pulleys and belt drives
2 pulleys and belt drivesAreef Khan
 

Plus de Areef Khan (6)

1 making of textilefutyfuyuy
1 making of textilefutyfuyuy1 making of textilefutyfuyuy
1 making of textilefutyfuyuy
 
162160659 satyam-shrey-shahityrr
162160659 satyam-shrey-shahityrr162160659 satyam-shrey-shahityrr
162160659 satyam-shrey-shahityrr
 
Jobportal 130815001657-phpapp01
Jobportal 130815001657-phpapp01Jobportal 130815001657-phpapp01
Jobportal 130815001657-phpapp01
 
Download
DownloadDownload
Download
 
3 gear drives
3 gear drives3 gear drives
3 gear drives
 
2 pulleys and belt drives
2 pulleys and belt drives2 pulleys and belt drives
2 pulleys and belt drives
 

Dernier

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Dernier (20)

Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

Cpm (critical path method)

  • 2. CPM Objective • To estimate the total project duration and to assign starting and finishing times to all activities involved in the project
  • 3. What factors should we consider for project scheduling? • • • • Total completion time of the project Earlier and latest start time of each activity Critical activities and critical path Float for each activity (I.e. the amount of time by which the completion of a non critical activity can be delayed without delaying the total project completion time)
  • 4. Important Notations • Ei = Earliest occurrence time of an event (I.e. The earliest time for an event to occur immediately after al the preceding activities have been completed without delaying the entire project) • Li = Latest allowable time for an event (I.e. The latest time at which an event can occur without causing a delay in already determined project’s completion time)
  • 5. Important Notations (contd…) • ESij = Early starting time for an activity (i,j). It is the earliest time an activity can possibly start without affecting the project completion • LSij = Late starting time for an activity (i,j) . It is the latest possible time an activity can start without delaying the project completion time
  • 6. Important Notations (contd…) • EFij = Early finishing time for an activity (i,j). It is the earliest time an activity can possibly finish without affecting the project completion • LFij = Late finishing time for an activity (i,j) . It is the latest possible time an activity can start without delaying the project completion time • Tij = Duration of an activity (i.j)
  • 7. How to calculate earliest occurrence and latest available times of events? • Forward pass method for calculating earliest event time • Backward pass method for latest available event time
  • 8. Forward pass method • Start with initial event numbered 1. Earliest occurrence time for event 1 is always zero. I.e E1 = 0 where i = 1 • Calculate earliest start time for each activity that begins at event ( i = 1). This is equal to the earliest start time of event I (tail event) (I.e) ESij = Ei for all activities (i.j) starting at event i
  • 9. Forward pass method (Contd..) • Calculate earliest finish time of each activity that begins at event (i) . This is equal to the earliest start time of the activity plus the duration of the activity (I.e) EFij = ESij + tij = Ei + tij, for all activities (i,j) beginning at event i.
  • 10. Forward pass method (Contd..) • Proceed to the next event j ; j > I • Calculate the earliest occurrence time for the event j. This is the maximum of the earliest finish times of all activities ending into that event Ej = Max { EFij} = Max { Ei + tij }, for all immediate predecessor activities  If N is the final event then earliest finish time for the project (or) the earliest occurrence time EN for the final event is given by EN = Max {EFij} = Max {EN-1+ tij}, for all terminal activities
  • 11. Backward pass method (For latest allowable event time) • Set the latest occurrence event N equal to its earliest occurrence time (known from forward pass method) LN = EN , j = N • Latest finish time of each activity which ends at event j, LFij = Lj • Latest start time of each activity ending at j, LSij= LFij-tij • Latest occurrence time for event ( i) where i<j , L = Min {LSij}= Min {Lj-tij} • L1=0
  • 12. Sample CPM problem Draw the network diagram and find the critical path
  • 13. A B C D E F G H I J K L M Design new premises Obtain tenders from the contractors Select the contractor Arrange details with the selected contractor Decide which equipment to be used Arrange storage of equipment Arrange disposal of other equipment Order new equipment Take delivery of new equipment Renovations take place Remove old equipment Cleaning Return old equipment A B C A E E E H,L K D,F,G J H,L 14 4 2 1 2 3 2 4 3 12 4 2 2
  • 14. Solution with critical path E3=18 L3=18 C (2) 5 3 D(1) E6=18 L6=21 B(4) A (14) E1=0 L1=0 2 E (2) E2=14 L2=14 E7=21 L7=21 K (4) 8 J(12) 7 6 G(2) 1 E8=25 L8=25 E5=20 L5=20 F(3) 4 9 E9=37 L9=37 L(2) M(2) 12 10 I (3) H (4) E4=16 L4=18 11 E11=41 L11=42 E10=39 L10=39 E12=42 L12=42
  • 15. From the earlier example what is the critical path? • The critical path is the sequence of critical activities that form a continuous path between the start of a project & its completion • It is the longest path • Critical events : where E = L • Critical activities float is 0.
  • 16. Floats • Calculated for non critical activity or non critical event • The length of time to which a non critical activity and/or an event can be delayed or extended without delaying the total project completion time • Float can be called as slack or free time also
  • 17. Float on event • Float slack of an event is the difference between its latest occurrence time and its earliest occurrence time • Event float = Li-Ei • Event float is 0 for critical events (I.e. L = E)
  • 18. Float on activities • The length of free time available within the estimated times of non-critical activities • 3 types of float for non-critical activities – Total float – Free float – Independent float
  • 19. Total float • Length of time by which an activity can be delayed if all its predecessor activities are completed at its earliest possible time and all successor activities can be delayed until their latest permissible time • Total float TFij= (Lj-tij)-Ei
  • 20. Free float • Time by which the completion of an activity can be delayed without causing any delay in its immediate succeeding activities • Free float FFij= (Ej-Ei)-tij
  • 21. Independent float • Amount of time available when preceding activities are completed at their latest permissible times and the following activities can still be completed at their earliest possible times • Independent float IFij=(Ej-Li)-tij • Negative value of independent float is considered as 0
  • 22. Further on floats • Latest occurrence time of an event is always greater than or equal to its earliest occurrence time. This implies Independent float < Free float < Total float • Floats help in identifying underutilized resources,flexibility in the total schedule and possibilities of redeployment of resources • Once a float of an activity is disturbed, float for all other activities of the project is changed and should be recalculated
  • 23. What does a float value mean? • If float value is negative, it means project completion is behind the schedule data. Resources are not adequate and activity may not finish in time • Float = 0. Just enough resources, no possibility for delay • Float is positive means resources are surplus and can be deployed elsewhere as required