SCHOOL OF HOUSING,BUILDING AND PIANING BUILDING TECHNOLOGY RET 565 WORK OF ROAD COMPACTION
Discussion the basic principles of field compaction. Can climatic conditions influence compaction in road construction?
Introduction Compaction increases the density of a material by expelling air from the voids in the material and, thereby, bringing the particles into more intimate contact with each other. Compaction is the cheapest and simplest method for improving the shearing resistance of soil and minimizing future settlements. Therefore, soils in embankments and subgrades in cuttings are usually compacted using special compacting equipment, such as rollers, vibrators or tampers. The result of compaction work depends primarily on the moisture content of the soil, the type of the soil, the compaction equipment used and the energy applied .
Compaction increases the density of a material. You can use rollers or other devices to expel air from the spaces in the material and force the particles closer together, making it denser.  ,[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object]
Objective of compaction for new road Nature doesn’t always provide the ideal foundation for the construction of roads: natural rock. In the majority of cases, the ground is unstable, offering insufficient bearing capacity. Earthmoving operations are therefore usually the first step in the construction of a new road. When the course has been defined and set out, the ground underlying the new road needs to be prepared.
How to achieve proper compaction In constructing roads you must compact each layer: subbase, base and surface. Depending on the type of road you are constructing, one, two or all three of these layers may be composed of the natural soils of the area. In order to compact them properly you must understand the two major factors which influence soil compaction: soil type and moisture content. Soil type dictates the relative number of passes required, the thickness of compaction layers, the type of compaction equipment, and how moisture affects compaction. And you must use different procedures and equipment to compact each soil type and still others for asphalt.
Compaction requirements Compaction requirements are commonly specified using an end-product specification. Compaction tests on the particular soil are carried out in the laboratory, and the results are used to define the required density. During construction, the densities obtained in the field are determined and compared to that required. The most common methods applied for measuring field densities are the sand cone and the nuclear density gauge. It is normally recommended that the top of an embankment, as well as the upper 500mm of the subgrade in cuttings are compacted to minimum 95 per cent of the maximum dry density obtained in the modified proctor test.
[object Object],[object Object],[object Object]
[object Object],[object Object]
The vibration imposes pulsating stresses in the soil. This reduces the friction between the soil particles and results in a highly effective and deep compaction, particularly in gravel and sand. If the vibration is turned off, the roller can be used as a traditional, static roller. This makes the vibratory steel-wheeled roller. Other types of compactor include the pneumatic-tyred roller and the sheepsfoot roller. A neumatic-tyred roller consists of rubber-tyred wheels mounted on an articulated frame, which provides a uniform load on each wheel. A sheepsfoot roller is made of a steel drum to which protruding, tamping feet have been attached. For compaction of backfill in narrow trenches and excavations for structures, a wide variety of hand-operated mechanical tampers and plate type vibrators are available.
[object Object],[object Object]
The goal of asphalt compaction is to create a pavement that offers maximum evenness and stability, while simultaneously increasing both traffic safety and riding comfort. Compaction aims at producing a road surface of maximum regularity and skid resistance, and at creating a permanent bond between the various asphalt layers. Compaction by rollers results in an extremely tight interlock between the individual particles of the mineral aggregate, which enables a high degree of stability, excellent resistance to wear, and permanent evenness to be achieved. Rollers reduce the void content in the asphalt, making it more resistant to loads and more durable.
[object Object],[object Object],[object Object],[object Object],[object Object]
Time for Asphalt Compaction For the contractor, time is the most important factor. This is how long it takes for the asphalt mixture to cool from laydown temperature to a minimum compaction temperature, usually 175° F. Below this temperature, further attempts to compact the asphalt mixture normally will not be effective and may fracture the aggregate in the mix, decreasing pavement density and frustrating the purpose of compacting.
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Climatic conditions influence compaction in road construction  Base temperature  —the temperature of the layer on which you lay the new layer—is more important than air temperature in determining time available for compaction because the layer cools downward more rapidly than upward. All other factors being equal, however,  warmer air temperature  slows the material's cooling rate, allowing more compaction time. An asphalt layer will cool more quickly in  high winds  than when it's relatively calm. Wind has more affect on the surface of the layer than its interior. A strong wind can cause the surface to cool so rapidly that a crust forms. You must break this crust down with the roller before you can begin compacting.
A mix will cool slower on a  sunny day  than on a cloudy day (other factors remaining constant). Sunshine probably affects base temperature more than mix temperature    Steps in compacting asphalt surfacing Asphalt pavements are usually compacted in three steps: breakdown rolling just behind the paving machine, intermediate rolling, and finish rolling which smooths out surface ruts and other deformities.
Rolling procedures Rollers should move at a moderate but uniform speed with the drive wheel closest to the paver. Going too fast during breakdown rolling can harm the surface. Rollers should be in good mechanical condition and able to reverse direction without backlash . ,[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Compaction Issues ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Summary Compaction is the simplest, most economical method of improving the load-carrying capability of roads. When done during construction it costs very little per ton of pavement material and can significantly reduce future maintenance costs. Compaction also gives a road greater strength for supporting heavier loads, reduces settlement over its lifetime, and reduces its permeability to water and air and its susceptibility rutting.
[object Object],[object Object],[object Object],[object Object],[object Object]

Contenu connexe

Tendances

Tendances (20)

Ground improvement using jet grouting column
Ground improvement using jet grouting columnGround improvement using jet grouting column
Ground improvement using jet grouting column
 
Soil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilSoil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton Soil
 
PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES PAVEMENT DESIGN & TYPES
PAVEMENT DESIGN & TYPES
 
Pavement materials – introduction (lecture 1)
Pavement materials – introduction (lecture 1)Pavement materials – introduction (lecture 1)
Pavement materials – introduction (lecture 1)
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Foundation
FoundationFoundation
Foundation
 
4. Shallow Foundations
4. Shallow Foundations4. Shallow Foundations
4. Shallow Foundations
 
Soil stabilisation
Soil stabilisation Soil stabilisation
Soil stabilisation
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Highway engg. (road m aterial)
Highway engg. (road m aterial)Highway engg. (road m aterial)
Highway engg. (road m aterial)
 
Types of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. ITypes of pavement- Transportation Engg. I
Types of pavement- Transportation Engg. I
 
Construction of High Speed Highway and Test track
Construction of High Speed Highway and Test trackConstruction of High Speed Highway and Test track
Construction of High Speed Highway and Test track
 
Foundation Types
Foundation TypesFoundation Types
Foundation Types
 
Problems Associated with Bituminous Binders and Macadam Asphalt Mat
Problems Associated with Bituminous Binders and Macadam Asphalt MatProblems Associated with Bituminous Binders and Macadam Asphalt Mat
Problems Associated with Bituminous Binders and Macadam Asphalt Mat
 
Bituminous pavement
Bituminous pavementBituminous pavement
Bituminous pavement
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Unit 3
Unit 3Unit 3
Unit 3
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Lecture#01
Lecture#01Lecture#01
Lecture#01
 
Highway materials - soil
Highway materials - soil Highway materials - soil
Highway materials - soil
 

En vedette

Yanmar diesel generator operation manual
Yanmar  diesel generator operation manualYanmar  diesel generator operation manual
Yanmar diesel generator operation manual
Manuel Sotelo
 
Rapid compression machine_monthly meeting
Rapid compression machine_monthly meetingRapid compression machine_monthly meeting
Rapid compression machine_monthly meeting
Nathan Loveldi
 
Principle of DC Generator
Principle of DC GeneratorPrinciple of DC Generator
Principle of DC Generator
guest60b26e
 
Universal testing machines
Universal testing machinesUniversal testing machines
Universal testing machines
Shivam Tiwari
 
Service Operation Management_Maruti
Service Operation Management_MarutiService Operation Management_Maruti
Service Operation Management_Maruti
Ankit Suneja
 
Presentation on Brick Masonry, Paint and Plastering
Presentation on Brick Masonry, Paint and PlasteringPresentation on Brick Masonry, Paint and Plastering
Presentation on Brick Masonry, Paint and Plastering
Abontee
 

En vedette (20)

Instruction manual for dhr v2.2
Instruction manual for dhr v2.2Instruction manual for dhr v2.2
Instruction manual for dhr v2.2
 
Alfanar Generator Assessment Process
Alfanar Generator Assessment ProcessAlfanar Generator Assessment Process
Alfanar Generator Assessment Process
 
2002 MAXIMA OWNER'S MANUAL
2002 MAXIMA OWNER'S MANUAL2002 MAXIMA OWNER'S MANUAL
2002 MAXIMA OWNER'S MANUAL
 
Yanmar diesel generator operation manual
Yanmar  diesel generator operation manualYanmar  diesel generator operation manual
Yanmar diesel generator operation manual
 
ICE Vibratory Hammer Owners Manual
ICE Vibratory Hammer Owners ManualICE Vibratory Hammer Owners Manual
ICE Vibratory Hammer Owners Manual
 
Field Tests of Cement
Field Tests of CementField Tests of Cement
Field Tests of Cement
 
Roller compaction machines
Roller compaction machinesRoller compaction machines
Roller compaction machines
 
construction material and technology
construction material and technologyconstruction material and technology
construction material and technology
 
Compressive strength of the concrete
Compressive strength of the concreteCompressive strength of the concrete
Compressive strength of the concrete
 
Rapid compression machine_monthly meeting
Rapid compression machine_monthly meetingRapid compression machine_monthly meeting
Rapid compression machine_monthly meeting
 
Principle of DC Generator
Principle of DC GeneratorPrinciple of DC Generator
Principle of DC Generator
 
Compressive strength in concrete test
Compressive strength in concrete testCompressive strength in concrete test
Compressive strength in concrete test
 
New Soil Investigation
New Soil InvestigationNew Soil Investigation
New Soil Investigation
 
Class 4 Soil Compaction ( Geotechnical Engineering )
Class 4    Soil Compaction ( Geotechnical Engineering )Class 4    Soil Compaction ( Geotechnical Engineering )
Class 4 Soil Compaction ( Geotechnical Engineering )
 
Building materials and construction technlogoy- FALSE CEILING & FLOORING
Building materials and construction technlogoy- FALSE CEILING & FLOORINGBuilding materials and construction technlogoy- FALSE CEILING & FLOORING
Building materials and construction technlogoy- FALSE CEILING & FLOORING
 
Universal testing machines
Universal testing machinesUniversal testing machines
Universal testing machines
 
pointing, plastering, bonding
pointing, plastering, bondingpointing, plastering, bonding
pointing, plastering, bonding
 
Service Operation Management_Maruti
Service Operation Management_MarutiService Operation Management_Maruti
Service Operation Management_Maruti
 
Presentation on Brick Masonry, Paint and Plastering
Presentation on Brick Masonry, Paint and PlasteringPresentation on Brick Masonry, Paint and Plastering
Presentation on Brick Masonry, Paint and Plastering
 
Plastering and pointing
Plastering and pointingPlastering and pointing
Plastering and pointing
 

Similaire à Final

Lecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfLecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdf
OmarAbdi39
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
SekharJ4
 

Similaire à Final (20)

Lecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdfLecture one_introffffffffffffduction.pdf
Lecture one_introffffffffffffduction.pdf
 
Rolling Resistance.pptx
Rolling Resistance.pptxRolling Resistance.pptx
Rolling Resistance.pptx
 
highway materials and desihn.pptx
highway materials and desihn.pptxhighway materials and desihn.pptx
highway materials and desihn.pptx
 
Compaction equipment
Compaction equipmentCompaction equipment
Compaction equipment
 
Soil compaction
Soil compactionSoil compaction
Soil compaction
 
Field control of compaction and compaction Equipment
Field control of compaction and compaction EquipmentField control of compaction and compaction Equipment
Field control of compaction and compaction Equipment
 
Highway materials and tests
Highway materials and testsHighway materials and tests
Highway materials and tests
 
Shamsudin masoud PPT (Principle of Soil and Soil Compaction.ppt
Shamsudin masoud PPT (Principle of Soil  and Soil Compaction.pptShamsudin masoud PPT (Principle of Soil  and Soil Compaction.ppt
Shamsudin masoud PPT (Principle of Soil and Soil Compaction.ppt
 
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
HIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICEHIGHWAY  CONSTRUCTION  MATERIAL  &  PRACTICE
HIGHWAY CONSTRUCTION MATERIAL & PRACTICE
 
Compaction Of Soil
Compaction Of SoilCompaction Of Soil
Compaction Of Soil
 
Pavement Analysis and Design.pptx
Pavement Analysis and Design.pptxPavement Analysis and Design.pptx
Pavement Analysis and Design.pptx
 
Rubcrete
RubcreteRubcrete
Rubcrete
 
C 4
C   4C   4
C 4
 
Compaction of soil (for civil engineering)
Compaction of soil (for civil engineering)Compaction of soil (for civil engineering)
Compaction of soil (for civil engineering)
 
Glossary tire-rubber-terminology
Glossary tire-rubber-terminologyGlossary tire-rubber-terminology
Glossary tire-rubber-terminology
 
Typesoftyres auto.system by prashant yadav (iu1241010063,indus university))
Typesoftyres auto.system by prashant yadav (iu1241010063,indus university))Typesoftyres auto.system by prashant yadav (iu1241010063,indus university))
Typesoftyres auto.system by prashant yadav (iu1241010063,indus university))
 
Chapter 3 compaction and consolidation
Chapter 3 compaction and consolidationChapter 3 compaction and consolidation
Chapter 3 compaction and consolidation
 
seminar-Airless tyres.pptx
seminar-Airless tyres.pptxseminar-Airless tyres.pptx
seminar-Airless tyres.pptx
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
Good Applications of Foam Cement in Geothermal Wells and Deepwater Environments
Good Applications of Foam Cement in Geothermal Wells and Deepwater EnvironmentsGood Applications of Foam Cement in Geothermal Wells and Deepwater Environments
Good Applications of Foam Cement in Geothermal Wells and Deepwater Environments
 

Plus de M. Arkam C. Munaaim Adj. Prof, PhD, PEPC, IntPE.

Plus de M. Arkam C. Munaaim Adj. Prof, PhD, PEPC, IntPE. (20)

POTENTIAL OF MICRO HYDRO EMBEDDED AT EFFLUENT DISCHARGE POINT OF SEWERAGE TRE...
POTENTIAL OF MICRO HYDRO EMBEDDED AT EFFLUENT DISCHARGE POINT OF SEWERAGE TRE...POTENTIAL OF MICRO HYDRO EMBEDDED AT EFFLUENT DISCHARGE POINT OF SEWERAGE TRE...
POTENTIAL OF MICRO HYDRO EMBEDDED AT EFFLUENT DISCHARGE POINT OF SEWERAGE TRE...
 
MJA-TVET MALAYSIA PROGRAM 2020
MJA-TVET MALAYSIA PROGRAM 2020MJA-TVET MALAYSIA PROGRAM 2020
MJA-TVET MALAYSIA PROGRAM 2020
 
MJA-TVET PROGRAM INTRODUCTION
MJA-TVET PROGRAM INTRODUCTIONMJA-TVET PROGRAM INTRODUCTION
MJA-TVET PROGRAM INTRODUCTION
 
Mega Jati ACADEMY Introduction 2020
Mega Jati ACADEMY Introduction 2020Mega Jati ACADEMY Introduction 2020
Mega Jati ACADEMY Introduction 2020
 
HOW TO BE A PE (2019)
HOW TO BE A PE (2019)HOW TO BE A PE (2019)
HOW TO BE A PE (2019)
 
INTRODUCTION TO INDUSTRIAL REVOLUTION 4.0
INTRODUCTION TO INDUSTRIAL REVOLUTION 4.0 INTRODUCTION TO INDUSTRIAL REVOLUTION 4.0
INTRODUCTION TO INDUSTRIAL REVOLUTION 4.0
 
Lestari Library UniMAP
Lestari Library UniMAPLestari Library UniMAP
Lestari Library UniMAP
 
Eat 105 Chapter 3
Eat 105  Chapter 3Eat 105  Chapter 3
Eat 105 Chapter 3
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2
Eat105 chapter 2
 
Eat105 Chapter 1
Eat105 Chapter 1Eat105 Chapter 1
Eat105 Chapter 1
 
Parans Installation Malaysia
Parans Installation MalaysiaParans Installation Malaysia
Parans Installation Malaysia
 
USM_Mechanical and Electrical Engineers in Land Development Projects
USM_Mechanical and Electrical Engineers in Land Development Projects USM_Mechanical and Electrical Engineers in Land Development Projects
USM_Mechanical and Electrical Engineers in Land Development Projects
 
IEM on PCE Slideshow
IEM on PCE SlideshowIEM on PCE Slideshow
IEM on PCE Slideshow
 
SPAN-PPKAS Meeting 19Oct2015
SPAN-PPKAS Meeting 19Oct2015SPAN-PPKAS Meeting 19Oct2015
SPAN-PPKAS Meeting 19Oct2015
 
Registered Energy Manager Slide: Energy Audit
Registered Energy Manager Slide: Energy AuditRegistered Energy Manager Slide: Energy Audit
Registered Energy Manager Slide: Energy Audit
 
Tea Talk IEM 2015: The Development of Solar Power Plant in Malaysia
Tea Talk IEM 2015: The Development of Solar Power Plant in MalaysiaTea Talk IEM 2015: The Development of Solar Power Plant in Malaysia
Tea Talk IEM 2015: The Development of Solar Power Plant in Malaysia
 
Arkam ViVa
Arkam ViVaArkam ViVa
Arkam ViVa
 
SHEFFIELD HALLAM
SHEFFIELD HALLAMSHEFFIELD HALLAM
SHEFFIELD HALLAM
 
The Development of Solar Power Plant in Malaysia
The Development of Solar Power Plant in MalaysiaThe Development of Solar Power Plant in Malaysia
The Development of Solar Power Plant in Malaysia
 
EUT440 LAW 3 (Negligence)
EUT440 LAW 3 (Negligence)EUT440 LAW 3 (Negligence)
EUT440 LAW 3 (Negligence)
 

Dernier

Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
amitlee9823
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
Abortion pills in Kuwait Cytotec pills in Kuwait
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
lizamodels9
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Dernier (20)

(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 

Final

  • 1. SCHOOL OF HOUSING,BUILDING AND PIANING BUILDING TECHNOLOGY RET 565 WORK OF ROAD COMPACTION
  • 2. Discussion the basic principles of field compaction. Can climatic conditions influence compaction in road construction?
  • 3. Introduction Compaction increases the density of a material by expelling air from the voids in the material and, thereby, bringing the particles into more intimate contact with each other. Compaction is the cheapest and simplest method for improving the shearing resistance of soil and minimizing future settlements. Therefore, soils in embankments and subgrades in cuttings are usually compacted using special compacting equipment, such as rollers, vibrators or tampers. The result of compaction work depends primarily on the moisture content of the soil, the type of the soil, the compaction equipment used and the energy applied .
  • 4.
  • 5.
  • 6. Objective of compaction for new road Nature doesn’t always provide the ideal foundation for the construction of roads: natural rock. In the majority of cases, the ground is unstable, offering insufficient bearing capacity. Earthmoving operations are therefore usually the first step in the construction of a new road. When the course has been defined and set out, the ground underlying the new road needs to be prepared.
  • 7. How to achieve proper compaction In constructing roads you must compact each layer: subbase, base and surface. Depending on the type of road you are constructing, one, two or all three of these layers may be composed of the natural soils of the area. In order to compact them properly you must understand the two major factors which influence soil compaction: soil type and moisture content. Soil type dictates the relative number of passes required, the thickness of compaction layers, the type of compaction equipment, and how moisture affects compaction. And you must use different procedures and equipment to compact each soil type and still others for asphalt.
  • 8. Compaction requirements Compaction requirements are commonly specified using an end-product specification. Compaction tests on the particular soil are carried out in the laboratory, and the results are used to define the required density. During construction, the densities obtained in the field are determined and compared to that required. The most common methods applied for measuring field densities are the sand cone and the nuclear density gauge. It is normally recommended that the top of an embankment, as well as the upper 500mm of the subgrade in cuttings are compacted to minimum 95 per cent of the maximum dry density obtained in the modified proctor test.
  • 9.
  • 10.
  • 11. The vibration imposes pulsating stresses in the soil. This reduces the friction between the soil particles and results in a highly effective and deep compaction, particularly in gravel and sand. If the vibration is turned off, the roller can be used as a traditional, static roller. This makes the vibratory steel-wheeled roller. Other types of compactor include the pneumatic-tyred roller and the sheepsfoot roller. A neumatic-tyred roller consists of rubber-tyred wheels mounted on an articulated frame, which provides a uniform load on each wheel. A sheepsfoot roller is made of a steel drum to which protruding, tamping feet have been attached. For compaction of backfill in narrow trenches and excavations for structures, a wide variety of hand-operated mechanical tampers and plate type vibrators are available.
  • 12.
  • 13. The goal of asphalt compaction is to create a pavement that offers maximum evenness and stability, while simultaneously increasing both traffic safety and riding comfort. Compaction aims at producing a road surface of maximum regularity and skid resistance, and at creating a permanent bond between the various asphalt layers. Compaction by rollers results in an extremely tight interlock between the individual particles of the mineral aggregate, which enables a high degree of stability, excellent resistance to wear, and permanent evenness to be achieved. Rollers reduce the void content in the asphalt, making it more resistant to loads and more durable.
  • 14.
  • 15. Time for Asphalt Compaction For the contractor, time is the most important factor. This is how long it takes for the asphalt mixture to cool from laydown temperature to a minimum compaction temperature, usually 175° F. Below this temperature, further attempts to compact the asphalt mixture normally will not be effective and may fracture the aggregate in the mix, decreasing pavement density and frustrating the purpose of compacting.
  • 16.
  • 17. Climatic conditions influence compaction in road construction Base temperature —the temperature of the layer on which you lay the new layer—is more important than air temperature in determining time available for compaction because the layer cools downward more rapidly than upward. All other factors being equal, however, warmer air temperature slows the material's cooling rate, allowing more compaction time. An asphalt layer will cool more quickly in high winds than when it's relatively calm. Wind has more affect on the surface of the layer than its interior. A strong wind can cause the surface to cool so rapidly that a crust forms. You must break this crust down with the roller before you can begin compacting.
  • 18. A mix will cool slower on a sunny day than on a cloudy day (other factors remaining constant). Sunshine probably affects base temperature more than mix temperature   Steps in compacting asphalt surfacing Asphalt pavements are usually compacted in three steps: breakdown rolling just behind the paving machine, intermediate rolling, and finish rolling which smooths out surface ruts and other deformities.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24. Summary Compaction is the simplest, most economical method of improving the load-carrying capability of roads. When done during construction it costs very little per ton of pavement material and can significantly reduce future maintenance costs. Compaction also gives a road greater strength for supporting heavier loads, reduces settlement over its lifetime, and reduces its permeability to water and air and its susceptibility rutting.