August 19, 2014
Ms. Jackie Cromwell
Office of Transportation Public Private Partnerships
600 E. Main Street
Suite 2120
Richmond, VA 23219
Re: Public-Private Transportation Act of 1995 Implementation Manual and Guidelines –
Draft Update.
The American Road & Transportation Builders Association (ARTBA) offers these initial
comments on the Office of Transportation Public Private Partnerships’ (OTP3) draft update to
the Public Private Partnership Act of 1995 Implementation Manual and Guidelines (Draft
Manual). Founded in 1902, ARTBA’s membership includes private and public sector members
that are involved in the planning, designing, construction and maintenance of the nation’s
roadways, bridges, ports, airports and transit systems. Our industry generates more than $380
billion annually in U.S. economic activity and sustains more than 3.3 million American jobs.
ARTBA maintains ongoing and thorough involvement in federal legislative, policy, regulatory
and legal developments relating to transportation infrastructure development and investment.
This includes public private partnerships (P3s) in transportation, with which ARTBA has a long
history. Our P3 Division dates back more than 25 years and includes prominent concessionaires,
planning and design firms, contractors, law firms, financial entities and other experienced parties
in the P3 field. Through the reauthorization processes which have produced a series of federal
surface transportation bills in recent decades, ARTBA has advocated for provisions that have
helped make P3s a viable option for the financing and delivery of transportation improvement
projects in appropriate circumstances around the country.
ARTBA appreciates Virginia’s longtime leadership in P3 project delivery. OTP3’s public
dialogue relating to the Draft Manual is the latest instance of this leadership, and is a great
indicator by itself of the transparency VDOT is striving to achieve. Given that P3-related
developments in Virginia can carry national implications, ARTBA – an association national in
scope – carefully follows these activities and engages in the commonwealth’s policy discussion
on occasion. In fact, just last year ARTBA helped to defend Virginia’s P3 enabling legislation in
court by submitting an amicus brief in the Elizabeth River Crossings OPCO, LLC v. Meeks
litigation. We are pleased to participate in the current comment process as well.
Overall, ARTBA supports the proposed revisions to the Draft Manual and we offer the following
comments in hopes of improving further on what has been proposed.
2
On a general level, ARTBA offers comments in two areas. In regards to transparency, it is clear
the OTP3 is focused on ensuring an open and engaging public process. ARTBA strongly agrees
and supports this approach. The Draft Manual does a very good job of providing multiple
opportunities for public input. ARTBA believes that OTP3 should be vigilant in consistently
looking for additional opportunities to increase transparency with the public. This primarily
comes from holding as many public meetings as possible, at all stages of project development,
permitting, and procurement. Public meetings only improve transparency with the general public
and reduce the threat of time-consuming opposition or litigation, particularly in the latter stages
of the process.
Second, ARTBA suggests clarification as to the competing time frame for unsolicited proposals.
This does not appear to be spelled out in the Draft Manual. A prior version of the Draft Manual
stated a window for such, and that the particular time frame was dependent upon the size and
complexity of the project. Such an approach seems reasonable, as less complex projects should
have a shorter time frame while larger projects would naturally take longer, and ARTBA asks
that this concept be re-inserted into the Draft Manual.
On a more specific level, ARTBA asks OTP3 to consider the following comments on specific
sections of the Draft Manual:
 Section 1.5.3 Virginia Freedom of Information Act (VFOIA): Without sufficient
confidence that sensitive information will be kept confidential, potential project sponsors
could opt not to participate in the P3 process. In order to provide a balance between
maximizing transparency and also not unnecessarily releasing sensitive information, we
strongly suggest that this section be revised to reflect that documents should only be
subject to VFOIA when a procurement is over and the contract documents are signed. If
the project is in procurement, the documents should be treated as proprietary. Further,
the party submitting the documents should be contacted before a VFOIA request is
granted.
 Section 6.2.2 Short-Listing of Qualified Respondents: This section should specify the
number of qualified Respondents on the short-list for any project being considered. The
size of the list could vary according to the complexity of the project being considered, but
a range should be given in the policy. Also, OTP3 should consider adding a pro-rata
payment system for stipend payments on cancelled procurements to offer a level of
protection for Respondents in instances where a project is unexpectedly cancelled,
whether final proposals were submitted or not
 Section 6.3 Request for Proposals: Under this section, OTP3 reserves the right to
conduct a Best and Final Offer (BAFO) process with the short-listed Proposers.
However, there is no explanation of when or why a BAFO process would be used. In
order to provide increased transparency and give Proposers a better understanding of the
process, OTP3 should provide greater clarity in this section as to what types of scenarios
might trigger a BAFO process.
 Section 6.7 Contract Finalization and Award: Under this section, final approval is
required before the contract can be awarded to the successful Proposer. This provision
3
appears to be administrative, as opposed to legislative, in nature, as the Virginia
Department of Transportation (VDOT) would provide it. However, we are concerned
this section could be interpreted as requiring some sort of final legislative approval for P3
projects. While legislators should be involved in the P3 process, as you are aware there
should also be great care taken to ensure the process is not politicized in any way. In
order to accomplish this, ARTBA strongly recommends that legislative involvement
should be at the pre-solicitation stage, perhaps through a P3 board or panel. After the
pre-solicitation stage, legislators could be informed through frequent project status
updates. Finally, even if the final approval is purely administrative (and not legislative)
in nature, there should still be safeguards put in place to prevent politicization of the
process in its final stages. This could be done by the policy generally, yet clearly,
describing the extremely rare scenarios and/or requiring a specific set of conditions to be
met where final approval would be denied.
Again, these comments constitute initial feedback upon review of OTP3’s current Draft Manual,
and in many ways suggest areas for further discussion rather than definitive opinions on the
many details of that draft.
We appreciate OTP3’s considering these initial views and the request for more interaction as the
agency further refines the draft model contract guide. As noted previously, ARTBA and its P3
Division remain available to work with OTP3 through the remainder of this process, as well as
any other activities relating to Virginia’s P3 policy. Please contact ARTBA’s Vice President for
Regulatory Affairs and Assistant General Counsel Nick Goldstein-at any time. He can be
reached at 202-289-4434 or ngoldstein@artba.org.
Thank you for your consideration of these views and your leadership in P3 policy.
Sincerely,
T. Peter Ruane
President & C.E.O.

Contenu connexe

En vedette

May 29 2014 Draft Small Business Wotus Hearing Statement
May 29 2014 Draft Small Business Wotus Hearing StatementMay 29 2014 Draft Small Business Wotus Hearing Statement
May 29 2014 Draft Small Business Wotus Hearing Statementartba
 
10/31/13 – Virginia Supreme Court Decision
10/31/13 – Virginia Supreme Court Decision10/31/13 – Virginia Supreme Court Decision
10/31/13 – Virginia Supreme Court Decisionartba
 
03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letter03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letterartba
 
01/10: FTA Right of Way Guidance
01/10: FTA Right of Way Guidance01/10: FTA Right of Way Guidance
01/10: FTA Right of Way Guidanceartba
 
1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...
1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...
1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...artba
 
ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...
ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...
ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...artba
 
Impact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBA
Impact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBAImpact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBA
Impact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBAartba
 
Coalition Letter to the Senate Committee on Homeland Security and Government ...
Coalition Letter to the Senate Committee on Homeland Security and Government ...Coalition Letter to the Senate Committee on Homeland Security and Government ...
Coalition Letter to the Senate Committee on Homeland Security and Government ...artba
 
09/30/11: Amicus Brief in Sackett v. EPA
09/30/11: Amicus Brief in Sackett v. EPA09/30/11: Amicus Brief in Sackett v. EPA
09/30/11: Amicus Brief in Sackett v. EPAartba
 
Comments FWS Critical Habitat Proposals
Comments FWS Critical Habitat ProposalsComments FWS Critical Habitat Proposals
Comments FWS Critical Habitat Proposalsartba
 
ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...
ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...
ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...artba
 
Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...
Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...
Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...artba
 
03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipelineartba
 
Comments Opposing ESA protections for the Long-Eared Bat
 Comments Opposing ESA protections for the Long-Eared Bat Comments Opposing ESA protections for the Long-Eared Bat
Comments Opposing ESA protections for the Long-Eared Batartba
 
FHWA MOU with the State of Texas Regarding Environmental Reviews.
FHWA MOU with the State of Texas Regarding Environmental Reviews.FHWA MOU with the State of Texas Regarding Environmental Reviews.
FHWA MOU with the State of Texas Regarding Environmental Reviews.artba
 

En vedette (15)

May 29 2014 Draft Small Business Wotus Hearing Statement
May 29 2014 Draft Small Business Wotus Hearing StatementMay 29 2014 Draft Small Business Wotus Hearing Statement
May 29 2014 Draft Small Business Wotus Hearing Statement
 
10/31/13 – Virginia Supreme Court Decision
10/31/13 – Virginia Supreme Court Decision10/31/13 – Virginia Supreme Court Decision
10/31/13 – Virginia Supreme Court Decision
 
03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letter03/05: Multi-Industry Permit Streamlining Letter
03/05: Multi-Industry Permit Streamlining Letter
 
01/10: FTA Right of Way Guidance
01/10: FTA Right of Way Guidance01/10: FTA Right of Way Guidance
01/10: FTA Right of Way Guidance
 
1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...
1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...
1/12 – Industry Letter Supporting Passage H.R. 185, the “Regulatory Accountab...
 
ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...
ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...
ARTBA Comments on the Federal Accounting Standard Board’s Disclosure Requirem...
 
Impact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBA
Impact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBAImpact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBA
Impact of Propsed Cafe Standards on HTF Revenues- William Buencher ARTBA
 
Coalition Letter to the Senate Committee on Homeland Security and Government ...
Coalition Letter to the Senate Committee on Homeland Security and Government ...Coalition Letter to the Senate Committee on Homeland Security and Government ...
Coalition Letter to the Senate Committee on Homeland Security and Government ...
 
09/30/11: Amicus Brief in Sackett v. EPA
09/30/11: Amicus Brief in Sackett v. EPA09/30/11: Amicus Brief in Sackett v. EPA
09/30/11: Amicus Brief in Sackett v. EPA
 
Comments FWS Critical Habitat Proposals
Comments FWS Critical Habitat ProposalsComments FWS Critical Habitat Proposals
Comments FWS Critical Habitat Proposals
 
ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...
ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...
ARTBA Comments Supporting FHWA’s Draft Availability Payments Concessions Publ...
 
Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...
Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...
Coalition Letter to Senate on Failure to Advance S. 1140, the “Federal Water ...
 
03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline03/05: State Department Approval of Keystone XL Pipeline
03/05: State Department Approval of Keystone XL Pipeline
 
Comments Opposing ESA protections for the Long-Eared Bat
 Comments Opposing ESA protections for the Long-Eared Bat Comments Opposing ESA protections for the Long-Eared Bat
Comments Opposing ESA protections for the Long-Eared Bat
 
FHWA MOU with the State of Texas Regarding Environmental Reviews.
FHWA MOU with the State of Texas Regarding Environmental Reviews.FHWA MOU with the State of Texas Regarding Environmental Reviews.
FHWA MOU with the State of Texas Regarding Environmental Reviews.
 

Plus de artba

2017 media kit
2017 media kit2017 media kit
2017 media kitartba
 
September October tb_2016
September October tb_2016September October tb_2016
September October tb_2016artba
 
Transportation Builder July/August 2016
Transportation Builder July/August 2016Transportation Builder July/August 2016
Transportation Builder July/August 2016artba
 
The National Work Zone Management Conference Agenda 2016
The National Work Zone Management Conference Agenda 2016The National Work Zone Management Conference Agenda 2016
The National Work Zone Management Conference Agenda 2016artba
 
ARTBA 2016 National Convention Program
ARTBA 2016 National Convention ProgramARTBA 2016 National Convention Program
ARTBA 2016 National Convention Programartba
 
May/June Transportation Builder
May/June Transportation BuilderMay/June Transportation Builder
May/June Transportation Builderartba
 
Northeastern regional meeting
Northeastern regional meetingNortheastern regional meeting
Northeastern regional meetingartba
 
Southern regional meeting
Southern regional meetingSouthern regional meeting
Southern regional meetingartba
 
Central regional meeting
Central regional meetingCentral regional meeting
Central regional meetingartba
 
Western regional meeting
Western regional meetingWestern regional meeting
Western regional meetingartba
 
Western regional meeting
Western regional meetingWestern regional meeting
Western regional meetingartba
 
July/August 2015 TB magazine
July/August 2015 TB magazineJuly/August 2015 TB magazine
July/August 2015 TB magazineartba
 
September/October 2015 TB magazine
September/October 2015 TB magazineSeptember/October 2015 TB magazine
September/October 2015 TB magazineartba
 
November/December 2015 TB
November/December 2015 TBNovember/December 2015 TB
November/December 2015 TBartba
 
January/February 2016 TB
January/February 2016 TBJanuary/February 2016 TB
January/February 2016 TBartba
 
March/April 2016 TB
March/April 2016 TBMarch/April 2016 TB
March/April 2016 TBartba
 
2016 ­ARTBA FIP Schedule
2016 ­ARTBA FIP Schedule2016 ­ARTBA FIP Schedule
2016 ­ARTBA FIP Scheduleartba
 
2016 ARTBA FIP Program
2016 ARTBA FIP Program2016 ARTBA FIP Program
2016 ARTBA FIP Programartba
 
2016 ILDP Agenda
2016 ILDP Agenda2016 ILDP Agenda
2016 ILDP Agendaartba
 
P3 Agenda 2016
P3 Agenda 2016P3 Agenda 2016
P3 Agenda 2016artba
 

Plus de artba (20)

2017 media kit
2017 media kit2017 media kit
2017 media kit
 
September October tb_2016
September October tb_2016September October tb_2016
September October tb_2016
 
Transportation Builder July/August 2016
Transportation Builder July/August 2016Transportation Builder July/August 2016
Transportation Builder July/August 2016
 
The National Work Zone Management Conference Agenda 2016
The National Work Zone Management Conference Agenda 2016The National Work Zone Management Conference Agenda 2016
The National Work Zone Management Conference Agenda 2016
 
ARTBA 2016 National Convention Program
ARTBA 2016 National Convention ProgramARTBA 2016 National Convention Program
ARTBA 2016 National Convention Program
 
May/June Transportation Builder
May/June Transportation BuilderMay/June Transportation Builder
May/June Transportation Builder
 
Northeastern regional meeting
Northeastern regional meetingNortheastern regional meeting
Northeastern regional meeting
 
Southern regional meeting
Southern regional meetingSouthern regional meeting
Southern regional meeting
 
Central regional meeting
Central regional meetingCentral regional meeting
Central regional meeting
 
Western regional meeting
Western regional meetingWestern regional meeting
Western regional meeting
 
Western regional meeting
Western regional meetingWestern regional meeting
Western regional meeting
 
July/August 2015 TB magazine
July/August 2015 TB magazineJuly/August 2015 TB magazine
July/August 2015 TB magazine
 
September/October 2015 TB magazine
September/October 2015 TB magazineSeptember/October 2015 TB magazine
September/October 2015 TB magazine
 
November/December 2015 TB
November/December 2015 TBNovember/December 2015 TB
November/December 2015 TB
 
January/February 2016 TB
January/February 2016 TBJanuary/February 2016 TB
January/February 2016 TB
 
March/April 2016 TB
March/April 2016 TBMarch/April 2016 TB
March/April 2016 TB
 
2016 ­ARTBA FIP Schedule
2016 ­ARTBA FIP Schedule2016 ­ARTBA FIP Schedule
2016 ­ARTBA FIP Schedule
 
2016 ARTBA FIP Program
2016 ARTBA FIP Program2016 ARTBA FIP Program
2016 ARTBA FIP Program
 
2016 ILDP Agenda
2016 ILDP Agenda2016 ILDP Agenda
2016 ILDP Agenda
 
P3 Agenda 2016
P3 Agenda 2016P3 Agenda 2016
P3 Agenda 2016
 

Dernier

Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfauroraaudrey4826
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victoryanjanibaddipudi1
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoSABC News
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationReyMonsales
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerOmarCabrera39
 

Dernier (13)

Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
Top 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdfTop 10 Wealthiest People In The World.pdf
Top 10 Wealthiest People In The World.pdf
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep VictoryAP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
AP Election Survey 2024: TDP-Janasena-BJP Alliance Set To Sweep Victory
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 
Referendum Party 2024 Election Manifesto
Referendum Party 2024 Election ManifestoReferendum Party 2024 Election Manifesto
Referendum Party 2024 Election Manifesto
 
Opportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and informationOpportunities, challenges, and power of media and information
Opportunities, challenges, and power of media and information
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
Brief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert OppenheimerBrief biography of Julius Robert Oppenheimer
Brief biography of Julius Robert Oppenheimer
 

Artba comments re va p3 implementation manual and guidelines update

  • 1. August 19, 2014 Ms. Jackie Cromwell Office of Transportation Public Private Partnerships 600 E. Main Street Suite 2120 Richmond, VA 23219 Re: Public-Private Transportation Act of 1995 Implementation Manual and Guidelines – Draft Update. The American Road & Transportation Builders Association (ARTBA) offers these initial comments on the Office of Transportation Public Private Partnerships’ (OTP3) draft update to the Public Private Partnership Act of 1995 Implementation Manual and Guidelines (Draft Manual). Founded in 1902, ARTBA’s membership includes private and public sector members that are involved in the planning, designing, construction and maintenance of the nation’s roadways, bridges, ports, airports and transit systems. Our industry generates more than $380 billion annually in U.S. economic activity and sustains more than 3.3 million American jobs. ARTBA maintains ongoing and thorough involvement in federal legislative, policy, regulatory and legal developments relating to transportation infrastructure development and investment. This includes public private partnerships (P3s) in transportation, with which ARTBA has a long history. Our P3 Division dates back more than 25 years and includes prominent concessionaires, planning and design firms, contractors, law firms, financial entities and other experienced parties in the P3 field. Through the reauthorization processes which have produced a series of federal surface transportation bills in recent decades, ARTBA has advocated for provisions that have helped make P3s a viable option for the financing and delivery of transportation improvement projects in appropriate circumstances around the country. ARTBA appreciates Virginia’s longtime leadership in P3 project delivery. OTP3’s public dialogue relating to the Draft Manual is the latest instance of this leadership, and is a great indicator by itself of the transparency VDOT is striving to achieve. Given that P3-related developments in Virginia can carry national implications, ARTBA – an association national in scope – carefully follows these activities and engages in the commonwealth’s policy discussion on occasion. In fact, just last year ARTBA helped to defend Virginia’s P3 enabling legislation in court by submitting an amicus brief in the Elizabeth River Crossings OPCO, LLC v. Meeks litigation. We are pleased to participate in the current comment process as well. Overall, ARTBA supports the proposed revisions to the Draft Manual and we offer the following comments in hopes of improving further on what has been proposed.
  • 2. 2 On a general level, ARTBA offers comments in two areas. In regards to transparency, it is clear the OTP3 is focused on ensuring an open and engaging public process. ARTBA strongly agrees and supports this approach. The Draft Manual does a very good job of providing multiple opportunities for public input. ARTBA believes that OTP3 should be vigilant in consistently looking for additional opportunities to increase transparency with the public. This primarily comes from holding as many public meetings as possible, at all stages of project development, permitting, and procurement. Public meetings only improve transparency with the general public and reduce the threat of time-consuming opposition or litigation, particularly in the latter stages of the process. Second, ARTBA suggests clarification as to the competing time frame for unsolicited proposals. This does not appear to be spelled out in the Draft Manual. A prior version of the Draft Manual stated a window for such, and that the particular time frame was dependent upon the size and complexity of the project. Such an approach seems reasonable, as less complex projects should have a shorter time frame while larger projects would naturally take longer, and ARTBA asks that this concept be re-inserted into the Draft Manual. On a more specific level, ARTBA asks OTP3 to consider the following comments on specific sections of the Draft Manual:  Section 1.5.3 Virginia Freedom of Information Act (VFOIA): Without sufficient confidence that sensitive information will be kept confidential, potential project sponsors could opt not to participate in the P3 process. In order to provide a balance between maximizing transparency and also not unnecessarily releasing sensitive information, we strongly suggest that this section be revised to reflect that documents should only be subject to VFOIA when a procurement is over and the contract documents are signed. If the project is in procurement, the documents should be treated as proprietary. Further, the party submitting the documents should be contacted before a VFOIA request is granted.  Section 6.2.2 Short-Listing of Qualified Respondents: This section should specify the number of qualified Respondents on the short-list for any project being considered. The size of the list could vary according to the complexity of the project being considered, but a range should be given in the policy. Also, OTP3 should consider adding a pro-rata payment system for stipend payments on cancelled procurements to offer a level of protection for Respondents in instances where a project is unexpectedly cancelled, whether final proposals were submitted or not  Section 6.3 Request for Proposals: Under this section, OTP3 reserves the right to conduct a Best and Final Offer (BAFO) process with the short-listed Proposers. However, there is no explanation of when or why a BAFO process would be used. In order to provide increased transparency and give Proposers a better understanding of the process, OTP3 should provide greater clarity in this section as to what types of scenarios might trigger a BAFO process.  Section 6.7 Contract Finalization and Award: Under this section, final approval is required before the contract can be awarded to the successful Proposer. This provision
  • 3. 3 appears to be administrative, as opposed to legislative, in nature, as the Virginia Department of Transportation (VDOT) would provide it. However, we are concerned this section could be interpreted as requiring some sort of final legislative approval for P3 projects. While legislators should be involved in the P3 process, as you are aware there should also be great care taken to ensure the process is not politicized in any way. In order to accomplish this, ARTBA strongly recommends that legislative involvement should be at the pre-solicitation stage, perhaps through a P3 board or panel. After the pre-solicitation stage, legislators could be informed through frequent project status updates. Finally, even if the final approval is purely administrative (and not legislative) in nature, there should still be safeguards put in place to prevent politicization of the process in its final stages. This could be done by the policy generally, yet clearly, describing the extremely rare scenarios and/or requiring a specific set of conditions to be met where final approval would be denied. Again, these comments constitute initial feedback upon review of OTP3’s current Draft Manual, and in many ways suggest areas for further discussion rather than definitive opinions on the many details of that draft. We appreciate OTP3’s considering these initial views and the request for more interaction as the agency further refines the draft model contract guide. As noted previously, ARTBA and its P3 Division remain available to work with OTP3 through the remainder of this process, as well as any other activities relating to Virginia’s P3 policy. Please contact ARTBA’s Vice President for Regulatory Affairs and Assistant General Counsel Nick Goldstein-at any time. He can be reached at 202-289-4434 or ngoldstein@artba.org. Thank you for your consideration of these views and your leadership in P3 policy. Sincerely, T. Peter Ruane President & C.E.O.