SlideShare une entreprise Scribd logo
1  sur  16
Télécharger pour lire hors ligne
HS 228
Environmental Clearance procedure in India
Ajay Shankar Bidyarthy
Mathematics and Computing
Department of Mathematics
INTRODUCTION
- Environmental clearance process is required
for 39 types of projects; main purpose is to
assess the impact of the planned project on
environment and people
In India till 1980 most projects were
cleared without any environmental
clearance
Introduction
 National committee on environment planning was
setup in 4th five year plan (1969 – 1978). Before 1980, all
issues related to environmental clearance were dealt by
Department of Science and Technology.
=> 1980, Department of Environment setup to deal with such issues.
=> Department of Environment upgraded to Ministry of
Environment and Forest in 1985.
=> In 1994 MOEF issued guidelines for EIA
MOEF
Ministry of Environment and
Forest
EIA
Environmental impact
assessment
Steps in Clearance

Start
Site Selection
Apply for NOC
EIA Study
Public Hearing
After NOC, Proponent applies for final clearance with
MOEF/State Govt.
Review by Environment Appraisal Committee
Conduct EIA
Change
suggested
Accepted Rejected
Process of Clearance
 Project proponent has to submit a report that assesses
the impact of project on environment called EIA to
SPCB, for which it hires a consultant.
 This report is then assessed by SPCB in the following
Steps :-
1. Screening
- It is the most preliminary step of assessment.
- SPCB has record and data of impacts that have been
caused by projects in the past based on which it
develops threshold levels
- If the projects impact is less than these threshold,
the project is given clearance straight away.
Otherwise the proponent has to go to the next level
: Preliminary assessment
State Pollution Control Board
Process of Clearance
2. Preliminary Assessment
- Involves more research and review of the EIA data
based on which clearance is given.
** Drawback in Indian System :-
1. Law investment projects are given clearance straight
away.
2. Consultants hired by proponents are under pressure
to get clearance
3. False data in EIA
4. Corruption
5. Lack of Expertise amongst consultant
e.g.
Reliance
refinery
in Orissa
Process of Clearance
3. Formation of EIA Team
- If the project fails screening and preliminary
assessment, EIA report is sent to a team of experts
hired by SPCB for detailed review.
** Drawback :-
- Team members lack expertise in social and wildlife
impact studies in INDIA
Process of Clearance
4. Identification and Scoping
- In scoping, the expert team tries to estimate which
sections of society, environment and economy would be
affected.
- It does so by holding discussions with people of respective
fields.
- Based on scoping and results of preliminary study, the
team identifies the issues of conflict which need to be
studies.
** Drawbacks :-
- Local peoples opinion not taken at this initial level.
- Experts study only direct impacts in INDIA
Process of Clearance
5. Prediction and Evaluation
- Use of Mathematical and Physical models to predict
impacts and evaluating the prediction : whether
they will be significant or not.
** Drawbacks :-
- Because of narrow scoping, all impacts are not
predicted.
- Detail of Method of prediction, evaluation never
disclosed.
- Inaccurate prediction in many case.
Process of Clearance
6. Mitigation
- Suggesting alternative measures to proponent like
paying concessions to people, offering restoration of
resourses, use of cleaner technology
** Drawbacks :-
- Lack of transparency
- People not informed about preparedness measure
Process of Clearance
7. Public Hearing
- Public hearing involves a discussion between the
project proponent and the representatives of society.
- It is done to include the concerns of all sections of the
society in the decision making process.
- It involves :-
=> SPCB representatives
=> District Collector
=> State Govt. representatives
=> 3 representative of Gram Panchayat
=> 3 senior citizen nominated by collector
Process of Clearance
** Drawbacks :-
- Many projects exempted from public hearing.
- Public opinion not given much importance.
- Illiterate people can not defend themselves.
- Corruption :
- Public hearing notice not given 30 days before as per
nomination.
- People are not given access to EIA documents as per
norms.
Proponent, Govt. nexus
Process of Clearance
8. Environment Appraisal Committee
- After NOC from SPCB, proponent approaches state or MOEF
for clearance which forms a committee of experts to analyze
the project. Committee has to give clearance within 90 days.
** Drawbacks :-
- State NOC which is assumed to be environment clearance by
the proponents and project is started before EAC clearance
- Decision making is not transparent. No reason or
explanation is given to people.
- Information regarding govt. decision making is not
dissipated among citizens.
Environmental appraisal committee
Suggestions Regarding Process of
Clearance
 Independent regulatory body of experts instead
of SPCB.
 Report quality improvement
 Proper format of report having segments like
- Impact on biodiversity
- Impact on plans for animal
- Impact on aquatic life
 Use of format which makes EIA report conclusive and less
bulky.
 Centralized data bank.
 Appointment of consultants by regulatory body.
Suggestions Regarding Process of
Clearance
 Transparency
 Main EIA
Info desk to reach out to masses
Decision making should be transparent
Updated website
More professional experts needed so that study
and prediction are accurate
People’s opinion should be taken at the stage of
scoping
Evaluation and mitigation to be transparent
Suggestions Regarding Process of
Clearance
 Public hearing
Scope of public hearing should be widened
EIA document should be available in local languages to
people
Video recording of hearing
Thank you

Contenu connexe

Tendances

Impact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaImpact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaMizanur R. Shohel
 
Public Participation in Environmental Decision-Making
Public Participation in Environmental Decision-Making Public Participation in Environmental Decision-Making
Public Participation in Environmental Decision-Making Ashwani Kumar
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrithvi Ghag
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
Environmental Management Plan
Environmental Management PlanEnvironmental Management Plan
Environmental Management PlanShehab Sajeeb
 
Eia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationEia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationMizanur R. Shohel
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentSamanth kumar
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentKashmeera N.A.
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5Bibhabasu Mohanty
 
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIAENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIASakthivel R
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIAbishal sapkota
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentSonikaPawar
 
13 environmental impact assessment
13 environmental impact assessment13 environmental impact assessment
13 environmental impact assessmentPrabha Panth
 
Environment impact assessment.ppt
Environment impact assessment.pptEnvironment impact assessment.ppt
Environment impact assessment.pptApoorva Mathur
 
Baseline study for EIA
Baseline study for EIABaseline study for EIA
Baseline study for EIAJenson Samraj
 

Tendances (20)

Impact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eiaImpact prediction, evaluation and mitigation in eia
Impact prediction, evaluation and mitigation in eia
 
Public Participation in Environmental Decision-Making
Public Participation in Environmental Decision-Making Public Participation in Environmental Decision-Making
Public Participation in Environmental Decision-Making
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
Environmental Management Plan
Environmental Management PlanEnvironmental Management Plan
Environmental Management Plan
 
Eia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigrationEia prediction, evaluation & mitigration
Eia prediction, evaluation & mitigration
 
EIA
EIAEIA
EIA
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
EIA
EIAEIA
EIA
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5
 
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIAENVIRONMENTAL IMPACT ASSESSMENT - EIA
ENVIRONMENTAL IMPACT ASSESSMENT - EIA
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIA
 
Environmental Audit
Environmental AuditEnvironmental Audit
Environmental Audit
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
13 environmental impact assessment
13 environmental impact assessment13 environmental impact assessment
13 environmental impact assessment
 
Environment impact assessment.ppt
Environment impact assessment.pptEnvironment impact assessment.ppt
Environment impact assessment.ppt
 
Baseline study for EIA
Baseline study for EIABaseline study for EIA
Baseline study for EIA
 
Environmental Audit
Environmental AuditEnvironmental Audit
Environmental Audit
 

En vedette

En vedette (20)

Environmental clearance
Environmental clearanceEnvironmental clearance
Environmental clearance
 
Environmental Clearance
Environmental ClearanceEnvironmental Clearance
Environmental Clearance
 
Environmental clearance from moef
Environmental clearance from moefEnvironmental clearance from moef
Environmental clearance from moef
 
Clearance required for setting up thermal power plant
Clearance required for setting up thermal power plantClearance required for setting up thermal power plant
Clearance required for setting up thermal power plant
 
ENVIRONMENTAL CLEARANCE
ENVIRONMENTAL CLEARANCEENVIRONMENTAL CLEARANCE
ENVIRONMENTAL CLEARANCE
 
VNTR and RFLP
VNTR and RFLPVNTR and RFLP
VNTR and RFLP
 
Environmental audit
Environmental auditEnvironmental audit
Environmental audit
 
Rflp
RflpRflp
Rflp
 
Restriction fragment length polymorphism
Restriction fragment length polymorphismRestriction fragment length polymorphism
Restriction fragment length polymorphism
 
Environmental Certification | enviroshutters.co
Environmental Certification | enviroshutters.coEnvironmental Certification | enviroshutters.co
Environmental Certification | enviroshutters.co
 
Clearance Certificate
Clearance CertificateClearance Certificate
Clearance Certificate
 
Environmental clearance for construction projects optima
Environmental clearance for construction projects optimaEnvironmental clearance for construction projects optima
Environmental clearance for construction projects optima
 
What is eia
What is eiaWhat is eia
What is eia
 
Ever Green Eco Audit
Ever Green Eco AuditEver Green Eco Audit
Ever Green Eco Audit
 
Google servicios y productos
Google servicios y productosGoogle servicios y productos
Google servicios y productos
 
ISO-certification
ISO-certificationISO-certification
ISO-certification
 
PEISS
PEISSPEISS
PEISS
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Green audit
Green auditGreen audit
Green audit
 
Documents required for exports in India
Documents required for exports in IndiaDocuments required for exports in India
Documents required for exports in India
 

Similaire à Environmental clearance procedure in India: Principal of Governance

Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfHajiraThabasum
 
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, ECENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, ECB. BHASKAR
 
EIA of Yamuna Riverfront (2022).pptx
EIA of Yamuna Riverfront (2022).pptxEIA of Yamuna Riverfront (2022).pptx
EIA of Yamuna Riverfront (2022).pptxIrshadrazvi
 
EIA SCREENING presentation
EIA SCREENING  presentationEIA SCREENING  presentation
EIA SCREENING presentationSyeda Fatima
 
Developing Guidelines for Public Participation on Environmental Impact Assess...
Developing Guidelines for Public Participation on Environmental Impact Assess...Developing Guidelines for Public Participation on Environmental Impact Assess...
Developing Guidelines for Public Participation on Environmental Impact Assess...Ethical Sector
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentPramoda Raj
 
Environmental Audits
Environmental AuditsEnvironmental Audits
Environmental AuditsYajush Sonar
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentVinod Burdak
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)Angom Baleshwor
 
Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentArunAngadi5
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentIntan Ayuna
 
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...Semakula Allan Kinene
 
What is environmental impact assessment and its type_.pdf
What is environmental impact assessment and its type_.pdfWhat is environmental impact assessment and its type_.pdf
What is environmental impact assessment and its type_.pdfJagriti Agarwal
 
4. Outline Public Participation Guidelines - Baird
4. Outline Public Participation Guidelines - Baird4. Outline Public Participation Guidelines - Baird
4. Outline Public Participation Guidelines - BairdEthical Sector
 
15020243019_NiharicaOgale_Final_Report
15020243019_NiharicaOgale_Final_Report15020243019_NiharicaOgale_Final_Report
15020243019_NiharicaOgale_Final_ReportNiharica Ogale
 

Similaire à Environmental clearance procedure in India: Principal of Governance (20)

Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdfBeige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
 
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, ECENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
 
EIA;- EC
EIA;- ECEIA;- EC
EIA;- EC
 
EIA of Yamuna Riverfront (2022).pptx
EIA of Yamuna Riverfront (2022).pptxEIA of Yamuna Riverfront (2022).pptx
EIA of Yamuna Riverfront (2022).pptx
 
EIA SCREENING presentation
EIA SCREENING  presentationEIA SCREENING  presentation
EIA SCREENING presentation
 
Environmental management
Environmental managementEnvironmental management
Environmental management
 
Developing Guidelines for Public Participation on Environmental Impact Assess...
Developing Guidelines for Public Participation on Environmental Impact Assess...Developing Guidelines for Public Participation on Environmental Impact Assess...
Developing Guidelines for Public Participation on Environmental Impact Assess...
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Environmental Audits
Environmental AuditsEnvironmental Audits
Environmental Audits
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
 
Eia sem 40_02
Eia sem 40_02Eia sem 40_02
Eia sem 40_02
 
Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessment
 
Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
ENSURING SUSTAINABLE DEVELOPMENT: THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSM...
 
What is environmental impact assessment and its type_.pdf
What is environmental impact assessment and its type_.pdfWhat is environmental impact assessment and its type_.pdf
What is environmental impact assessment and its type_.pdf
 
PEISS
PEISSPEISS
PEISS
 
4. Outline Public Participation Guidelines - Baird
4. Outline Public Participation Guidelines - Baird4. Outline Public Participation Guidelines - Baird
4. Outline Public Participation Guidelines - Baird
 
15020243019_NiharicaOgale_Final_Report
15020243019_NiharicaOgale_Final_Report15020243019_NiharicaOgale_Final_Report
15020243019_NiharicaOgale_Final_Report
 
Ecw 579 week 13
Ecw 579 week 13Ecw 579 week 13
Ecw 579 week 13
 

Plus de Ajay Bidyarthy

Student Database Management System
Student Database Management SystemStudent Database Management System
Student Database Management SystemAjay Bidyarthy
 
Some real life data analysis on stationary and non-stationary Time Series
Some real life data analysis on stationary and non-stationary Time SeriesSome real life data analysis on stationary and non-stationary Time Series
Some real life data analysis on stationary and non-stationary Time SeriesAjay Bidyarthy
 
Solving Quadratic Assignment Problems (QAP) using Ant Colony System
Solving Quadratic Assignment Problems (QAP) using Ant Colony SystemSolving Quadratic Assignment Problems (QAP) using Ant Colony System
Solving Quadratic Assignment Problems (QAP) using Ant Colony SystemAjay Bidyarthy
 
Skip Graphs and its Applications
Skip Graphs and its ApplicationsSkip Graphs and its Applications
Skip Graphs and its ApplicationsAjay Bidyarthy
 
Implementation of parallel randomized algorithm for skew-symmetric matrix game
Implementation of parallel randomized algorithm for skew-symmetric matrix gameImplementation of parallel randomized algorithm for skew-symmetric matrix game
Implementation of parallel randomized algorithm for skew-symmetric matrix gameAjay Bidyarthy
 
DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...
DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...
DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...Ajay Bidyarthy
 
Design and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation AlgorithmsDesign and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation AlgorithmsAjay Bidyarthy
 
Design and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation AlgorithmsDesign and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation AlgorithmsAjay Bidyarthy
 
Optimization Techniques
Optimization TechniquesOptimization Techniques
Optimization TechniquesAjay Bidyarthy
 

Plus de Ajay Bidyarthy (9)

Student Database Management System
Student Database Management SystemStudent Database Management System
Student Database Management System
 
Some real life data analysis on stationary and non-stationary Time Series
Some real life data analysis on stationary and non-stationary Time SeriesSome real life data analysis on stationary and non-stationary Time Series
Some real life data analysis on stationary and non-stationary Time Series
 
Solving Quadratic Assignment Problems (QAP) using Ant Colony System
Solving Quadratic Assignment Problems (QAP) using Ant Colony SystemSolving Quadratic Assignment Problems (QAP) using Ant Colony System
Solving Quadratic Assignment Problems (QAP) using Ant Colony System
 
Skip Graphs and its Applications
Skip Graphs and its ApplicationsSkip Graphs and its Applications
Skip Graphs and its Applications
 
Implementation of parallel randomized algorithm for skew-symmetric matrix game
Implementation of parallel randomized algorithm for skew-symmetric matrix gameImplementation of parallel randomized algorithm for skew-symmetric matrix game
Implementation of parallel randomized algorithm for skew-symmetric matrix game
 
DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...
DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...
DOW JONES INDUSTRIAL AVERAGE Time series Data Analysis: Analysis and Results ...
 
Design and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation AlgorithmsDesign and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation Algorithms
 
Design and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation AlgorithmsDesign and Implementation of Parallel and Randomized Approximation Algorithms
Design and Implementation of Parallel and Randomized Approximation Algorithms
 
Optimization Techniques
Optimization TechniquesOptimization Techniques
Optimization Techniques
 

Dernier

CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Call Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Call Girls in Nagpur High Profile
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...tanu pandey
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Dernier (20)

CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 37 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 

Environmental clearance procedure in India: Principal of Governance

  • 1. HS 228 Environmental Clearance procedure in India Ajay Shankar Bidyarthy Mathematics and Computing Department of Mathematics
  • 2. INTRODUCTION - Environmental clearance process is required for 39 types of projects; main purpose is to assess the impact of the planned project on environment and people In India till 1980 most projects were cleared without any environmental clearance
  • 3. Introduction  National committee on environment planning was setup in 4th five year plan (1969 – 1978). Before 1980, all issues related to environmental clearance were dealt by Department of Science and Technology. => 1980, Department of Environment setup to deal with such issues. => Department of Environment upgraded to Ministry of Environment and Forest in 1985. => In 1994 MOEF issued guidelines for EIA MOEF Ministry of Environment and Forest EIA Environmental impact assessment
  • 4. Steps in Clearance  Start Site Selection Apply for NOC EIA Study Public Hearing After NOC, Proponent applies for final clearance with MOEF/State Govt. Review by Environment Appraisal Committee Conduct EIA Change suggested Accepted Rejected
  • 5. Process of Clearance  Project proponent has to submit a report that assesses the impact of project on environment called EIA to SPCB, for which it hires a consultant.  This report is then assessed by SPCB in the following Steps :- 1. Screening - It is the most preliminary step of assessment. - SPCB has record and data of impacts that have been caused by projects in the past based on which it develops threshold levels - If the projects impact is less than these threshold, the project is given clearance straight away. Otherwise the proponent has to go to the next level : Preliminary assessment State Pollution Control Board
  • 6. Process of Clearance 2. Preliminary Assessment - Involves more research and review of the EIA data based on which clearance is given. ** Drawback in Indian System :- 1. Law investment projects are given clearance straight away. 2. Consultants hired by proponents are under pressure to get clearance 3. False data in EIA 4. Corruption 5. Lack of Expertise amongst consultant e.g. Reliance refinery in Orissa
  • 7. Process of Clearance 3. Formation of EIA Team - If the project fails screening and preliminary assessment, EIA report is sent to a team of experts hired by SPCB for detailed review. ** Drawback :- - Team members lack expertise in social and wildlife impact studies in INDIA
  • 8. Process of Clearance 4. Identification and Scoping - In scoping, the expert team tries to estimate which sections of society, environment and economy would be affected. - It does so by holding discussions with people of respective fields. - Based on scoping and results of preliminary study, the team identifies the issues of conflict which need to be studies. ** Drawbacks :- - Local peoples opinion not taken at this initial level. - Experts study only direct impacts in INDIA
  • 9. Process of Clearance 5. Prediction and Evaluation - Use of Mathematical and Physical models to predict impacts and evaluating the prediction : whether they will be significant or not. ** Drawbacks :- - Because of narrow scoping, all impacts are not predicted. - Detail of Method of prediction, evaluation never disclosed. - Inaccurate prediction in many case.
  • 10. Process of Clearance 6. Mitigation - Suggesting alternative measures to proponent like paying concessions to people, offering restoration of resourses, use of cleaner technology ** Drawbacks :- - Lack of transparency - People not informed about preparedness measure
  • 11. Process of Clearance 7. Public Hearing - Public hearing involves a discussion between the project proponent and the representatives of society. - It is done to include the concerns of all sections of the society in the decision making process. - It involves :- => SPCB representatives => District Collector => State Govt. representatives => 3 representative of Gram Panchayat => 3 senior citizen nominated by collector
  • 12. Process of Clearance ** Drawbacks :- - Many projects exempted from public hearing. - Public opinion not given much importance. - Illiterate people can not defend themselves. - Corruption : - Public hearing notice not given 30 days before as per nomination. - People are not given access to EIA documents as per norms. Proponent, Govt. nexus
  • 13. Process of Clearance 8. Environment Appraisal Committee - After NOC from SPCB, proponent approaches state or MOEF for clearance which forms a committee of experts to analyze the project. Committee has to give clearance within 90 days. ** Drawbacks :- - State NOC which is assumed to be environment clearance by the proponents and project is started before EAC clearance - Decision making is not transparent. No reason or explanation is given to people. - Information regarding govt. decision making is not dissipated among citizens. Environmental appraisal committee
  • 14. Suggestions Regarding Process of Clearance  Independent regulatory body of experts instead of SPCB.  Report quality improvement  Proper format of report having segments like - Impact on biodiversity - Impact on plans for animal - Impact on aquatic life  Use of format which makes EIA report conclusive and less bulky.  Centralized data bank.  Appointment of consultants by regulatory body.
  • 15. Suggestions Regarding Process of Clearance  Transparency  Main EIA Info desk to reach out to masses Decision making should be transparent Updated website More professional experts needed so that study and prediction are accurate People’s opinion should be taken at the stage of scoping Evaluation and mitigation to be transparent
  • 16. Suggestions Regarding Process of Clearance  Public hearing Scope of public hearing should be widened EIA document should be available in local languages to people Video recording of hearing Thank you