Benefits in Practice Series
Identifying and Managing Benefits
19th June 2013
The Innovation Space, BIS
Agenda
1:30 Welcome and Introductions
1:45 Setting the Context: Corporate Strategy and Benefits
2:10 Case Study Exercise 1 (groups of 3 participants)
2:30 Benefits Lifecycle
» Benefits identification and modelling
3:00 Case Study Exercise 2
» 3:30 Feedback to group (content)
» 3:50 Aligning Benefits Realisation to the wider
organisation
» Ownership, Governance and Convergence
4:25 Summary and Close
Introduction to Presenters
 Peter Glynne – Co-Chair of Benefits Management SIG
 Nick Wensley – Co-Chair of Benefits Management SIG
 Neil White
 Hugo Minney PhD
What are you going to get from this afternoon?
 Establish a strong base of practical experience
 Consider different approaches to benefits identification and
modelling
 Consider new ways of thinking and how to drive innovation
 Explore effective benefits leadership
 Network and share experience
Setting the Context
Corporate Strategy and Benefits Realisation
“A world in which all
projects succeed”
APM’s 2020 Vision
Impossibility or deliberately
aspirational?
Discussion Point:
What does Benefits realisation
mean to your organisation?
In three words or less…..
MeasurementActivists
Full Cycle Governance
A future in which all projects succeed…
 Right
Things
 Right
Way
 Done
Well
Portfolio Management
Leadership, Alignment, Value Optimisation,
Programme selection, Portfolio Adjustment
Programme
Management
Business Sponsorship, Ownership, Coordinate
complementary and interdependent projects to
realise …
Project Management
Management of budget, schedule and
resources to deliver …
Capability
Benefits
Strategic
Objectives
Getting Benefits
John Thorp
A future in which all projects succeed
 Engage the right people in the business – so they want success
 Effective cross-boundary working and decision-making at executive
level
 Incentivise organisational convergence to pull together work on
business benefits
 Recognise the need for agility and flexibility … instead of just working
to the next milestone
 A clear connection with corporate strategy. The ‘WHY’ of projects.
Case Study Exercise 1
HS2 Context and Strategic objectives
 20 minutes in groups of three
 Consider the following Nathan Coyne article:
http://www.politics.co.uk/news/2013/05/09/make-the-case-for-hs2-benefits
 Identify the top six stakeholder groups
 From the point of view of DfT: Consider six points of strategic value
for their investment in HS2
Benefits Lifecycle
Benefits Identification and Modelling
All the focus has been on the success of
Project & Programme Management……
What makes Project Management successful?
 Project Management Success Criteria
– Time / Budget / Quality
– Business Objectives and Business Benefits
 PwC 2012 – greater maturity, higher success rate
– Use an established method for project management
– Use certified practitioners (you wouldn’t trust a pilot . . )
In a nutshell: Professionalism….
Should we not apply the same
professionalism to Benefits Realisation?
The Benefits Lifecycle
A Strategic and Integrated Approach based on partnership
Benefits Mapping – Some Techniques
Considering specific aspects of HS2
 Cassandra Benefits Management model (Cranfield)
 Results Chain (DMR / Thorp)
 Benefits Dependency Map (Bradley)
 Benefits Value Mapping (Glynne)
The benefits map or model is ONLY as an aid to communication and decision making. It
must be simples, easy to understand and easy to communicate.
Too many models are only understood by the author
Key Point
Cassandra / Cranfield
ENABLERS
ENABLING
CHANGES
BUSINESS
CHANGES
BUSINESS
BENEFITS
INVESTMENT
OBJECTIVES
Treasury
guarantees
Planning
laws
Public
consultation
Investment
Routes for
line
Linked
investment
Stations
and
community
travel
High Speed
line
Journey
times
Link
economic
centres
Major
infrastructure
build
Results Chain (DMR/ Thorp)
HS2HS2
Shorter
Commute
TimesFaster
More
reliable
Shorter
Business
Meeting journey
times
Work
London, Live
in regions
Work in
Regions,
more
business
Regional
Economic
Growth
constraint
is journey
time
more
meetings
= more
business
Last
Mile
Last
Mile
PricePrice
Phase
2
Phase
2
Legislation
to
compulsory
purchase
land
Legislation
resource
release
Benefits Dependency Map (Bradley)
To Increase
Regional
Economic
Growth
To increase
jobs in
regions
To widen
labour pool
To increase
passenger
satisfaction
Reduce
commute time
Shorter
meeting
journey time
Increased
UK Trading
Improved
GDP
Increased
regional spend
More good
workers attracted
to London
HSR Bill
HS2 Hybrid
Bill
Link economic
centres (∅ 2)
Link Midlands to
London (∅ 1)
ObjectiveBenefit
Business
Changes
Enabler Disbenefit
Named New
Capability
Project, Programme or
Portfolio
NewCapabilitiesStrategicValueOperationalBenefits
Strategic
Objective
Effectiveness
Strategic
Objective
Effectiveness
Strategic
Objective
Effectiveness
Action led word
describing the
Operational
Benefit
A
Benefit Type (1 of 5)
How to Read the Benefits Value Map.....
New tangible capabilities directly
attributable to the investment in the
project, programme or portfolio. New
to the business area or organisation
e.g. What we are buying for our
investment?
Operational, functional day to day benefits
relevant to the organisation Five types of
operational benefit to enable consistency
and comparability. KEY LINK TO
OPERATIONAL PERFORMANCE
MANAGEMENT
A dashboard is developed for every
operational benefit showing key
performance indicators, priority ranking
and ownership
There must be a direct
correlation/relationship
from a capability to an
operational benefit
Five Types of Operational Benefit CRITICAL TO MEASUREMENT
1.Time – measured in hours, day, weeks etc.
2.Cost – measured in £
3.Satisfaction/Assurance – measured by a before and after
perception survey showing a measurable improvement
4.Income – measured in £
5.Disbenefit – the negative consequences of change - measured
using one of the four types described above
The colour boxes highlight the
contribution of the operational benefit to
strategic value in the bottom row. It
must reflect the organisation’s or
group’s business plan or strategy
Unique identifier for
each operational
benefit
Showing the contribution
of individual operational
benefits to the business
plan or strategy. Two
categories:
1. Efficiency
2. Effectiveness
Benefits Value Mapping
OperationalBenefits
Howwillitchangeourperformance?
StrategicValue
Howwillitcontributetostrategy?
NewCapabilities
Whatareweinvestingin?
Time Time
Income
Time
Income
Cost
Satisfaction
Assurance
INCREASED
ECONOMIC
INVESTMENT IN
REGIONS
Effectiveness
INCREASED
PASSENGER
SATISFACTION
WITH SERVICES
Effectiveness
?
Effectiveness
?
Effectiveness
A
B
C
D
E
F
G
H
I
J
Focus on change, business performance
and measurement
Exercise 2 – HS2 Benefits at
operational level
 30 minutes in threes
 Partially completed template – fill in the
gaps
 Share from your group – please nominate
spokesperson (1 minute feedback time)
– Results of discussion on HS2
Aligning Benefits Realisation to
the Wider Organisation
Ownership, Governance and Convergence
Benefits Realisation
Common Behaviours across organisations
And there’s always the impact of the media.....
CONVERGENCE
What are the Opportunities for
collaboration?
Operational
Performance
Management Financial
Forecasting/
Budgeting
Strategic
Planning and
Evaluation
Benefits
Realisation
PMO
Change
Management
Ever increasing professionalism in the management of change within organisations
Communications
(internal and
external)
Benefits Realisation: Effective Partnership Working
Likely degree of engagement across the Change Journey within a typical organisation.
Typical Professional Group Strategy / Policy Delivery Embedding
of Change
Project/Programme Management
Finance Profession
Sponsors of Change
Economists
Strategists
Business Change Managers
External Relations/Communications
Human Resources
Operational Management
Procurement
Contract Management
Organisation Executive Board
Internal Audit
Understanding Behaviours, Governance and
Convergence
What to look out for across your organisation?
Process Obsessed Benefits Realisation
We MUST follow the prescribed process/manual
People looking to find a problem for a
waiting benefits solution....
My favourite solution will solve any ill...........
Limiting the focus to only the Project or
Programme.......
We don’t want to INVOLVE other areas of the business.. too political
Believing that lack of success is other
people’s issue for not understanding how
important something is..........
They won’t listen and they don’t want to understand
Groupthink on the approach to benefits
realisation......
We all agree so it must be the right approach.....???
Governance of Benefits
 Governance is one of the most important factors in the successful realisation of
benefits. Not just at Portfolio level which is critical to success!!
 Governance needs to be a ‘partnership approach’ between the project/
programme and wider business organisation (operational/business as usual)
 The wider business organisation should always own the benefits. Align director
level and operational ownership. Two level ownership.....portfolio level and
operations
 The project/ programme should facilitate the benefits on behalf of the business
organisation – not own the benefits……….
Governance is closely linked to leadership and organisation culture – arguably the
most important aspect of successful benefits realisation. GET IT WRONG AT YOUR
PERIL as governance can be difficult to change once implemented
Key Point
Challenges in Implementing a Robust Governance Model
• Getting senior executives to take responsibility for
individual or collective benefits, especially if there
is a history of project/programme failure within the
organisation
• Jargon/technical language trap
• Ensuring that there is a clear understanding of
roles and responsibilities for benefits realisation.
Communication, Communication, Communication
• Maintaining momentum – if the governance model
becomes ineffective, senior managers will very
quickly lose confidence in it.
An example Governance Model for a Single Organisation
An actual model used within a UK public sector organisation
An Example Governance Model for Multiple Organisations
During Implementation
An actual model used within a UK public sector organisation
An Example Governance Model for Multiple Organisations
Post-implementation
An actual model used within a UK public sector organisation
Pushing the Boundaries of Change
Benefits Realisation across Local Government
Thought Leadership: Six Action Points:
1.Incentivise organisation wide convergence in
benefits realisation
1.Move beyond an over reliance on isolated
process, low-value templates and certification
driven technical knowledge
2.Establish appropriate benefits leadership at the
portfolio level
3.Greater external partnership working to deliver
change and benefits
4.Greater integration of the cost reduction
agenda and benefits realisation
5.Invest in professionalism; innovation and
collaboration
Summary and Close
Conclusions – where to go from here
 Recap
– Benefits Mapping in context
– Benefits Lifecycle
– Ownership and Governance
– Conclusions from exercises
 What would people like to see next?
Some Examples of Approaches
Org 5
Customer
Group 1
Customer
Group 2
Customer
Group 3
Org 6
A
B
C
D
E
F
G
Example Stakeholder and Benefits Impact Matrix
High Low
H
The above table illustrates the impact of each benefit on the each stakeholder group. Benefits are in order of sequence only
Org 4Org 3Org 2Org 1
Greater assurance in the quality and
integrity of returns
Main Organisation Other Stakeholders
Reduced staff costs on administration of
customer's hard copy financial accounts
Increased assurance in the accuracy of
returns and statements being filed
Increased customer satisfaction with the
filing of financial accounts
Increased assurance in debt management
in Collector Generals
Increased satisfaction with the quality and
access to information on financial
accounts
Increased confidence in the targeting of
interventions based on risk profile
Increased confidence in the targeting of
interventions based on risk profile
Operational Benefit
Source: Glynne
Sample Operational Benefit Dashboard
Ref: BenefitA Description Impact Summary
Measurement
Question
Method and Unit of
Measurement
Baseline
Value
Target Value Actual Values
Measurement to
be done by
Priority
Likelihood of
Failure
Dependency on other
Benefits
Benefit
Category
Actions Required to Realise the Benefit Ownership
Start
Date
End
Date
Risks Impacting Realisation of the Benefit Impact Probability Mitigation
Director Owner
Operational Owner
Current RAG Status
Exposure Rating 16
AN Other
AN Other
Question to be asked to measure the benefit
How will the benefits be measured and what is the unit of
measurement. Alignment with organisational performance
management including relevant KPIs
Measurement
Dates
? ?
Baseline
Actual(s)
Time ?
Cost?
Satisfaction ?
Income ?
Profitability ?
4 4
Owner
End date to be realised TBC
Source: Glynne

Contenu connexe

Tendances

Benefits management and organisational change
Benefits management and organisational changeBenefits management and organisational change
Benefits management and organisational change
Association for Project Management
 
Deploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive WeaponDeploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive Weapon
Grant Crow
 

Tendances (20)

Benefits Management to enable change, Tuesday 27th January 2015
Benefits Management to enable change, Tuesday 27th January 2015Benefits Management to enable change, Tuesday 27th January 2015
Benefits Management to enable change, Tuesday 27th January 2015
 
Implementing Balance Scorecard
Implementing Balance ScorecardImplementing Balance Scorecard
Implementing Balance Scorecard
 
Target Operating Model Research
Target Operating Model ResearchTarget Operating Model Research
Target Operating Model Research
 
Benefits management and organisational change
Benefits management and organisational changeBenefits management and organisational change
Benefits management and organisational change
 
Deploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive WeaponDeploying Hoshin Kanri as a Competitive Weapon
Deploying Hoshin Kanri as a Competitive Weapon
 
Delivering Value with Financial Performance: Leading FP&A Practices of High-G...
Delivering Value with Financial Performance: Leading FP&A Practices of High-G...Delivering Value with Financial Performance: Leading FP&A Practices of High-G...
Delivering Value with Financial Performance: Leading FP&A Practices of High-G...
 
LSS - 5 Year Strategy
LSS -  5 Year StrategyLSS -  5 Year Strategy
LSS - 5 Year Strategy
 
Project Benefits Realisation General Presentation 7 Actions G Byatt
Project Benefits Realisation   General Presentation   7 Actions   G ByattProject Benefits Realisation   General Presentation   7 Actions   G Byatt
Project Benefits Realisation General Presentation 7 Actions G Byatt
 
PMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMOPMO Handbook - How to Plan, Build, and Run a PMO
PMO Handbook - How to Plan, Build, and Run a PMO
 
Best Practices in Financial Planning and Analysis | 2013 Business Analytics S...
Best Practices in Financial Planning and Analysis | 2013 Business Analytics S...Best Practices in Financial Planning and Analysis | 2013 Business Analytics S...
Best Practices in Financial Planning and Analysis | 2013 Business Analytics S...
 
Benefits realisation management, third sector forum, 13th May 2015
Benefits realisation management, third sector forum, 13th May 2015Benefits realisation management, third sector forum, 13th May 2015
Benefits realisation management, third sector forum, 13th May 2015
 
The One Page Strategic Planning process
The One Page Strategic Planning processThe One Page Strategic Planning process
The One Page Strategic Planning process
 
Benefit Realisation Management
Benefit Realisation ManagementBenefit Realisation Management
Benefit Realisation Management
 
Balance scorecard kpi
Balance scorecard kpiBalance scorecard kpi
Balance scorecard kpi
 
PMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsPMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 Questions
 
Business case Template
Business case TemplateBusiness case Template
Business case Template
 
Business Process Management Tools & Framework. By ex-Deloitte
Business Process Management Tools & Framework. By ex-DeloitteBusiness Process Management Tools & Framework. By ex-Deloitte
Business Process Management Tools & Framework. By ex-Deloitte
 
The Project Management Office - Effectiveness and Delivering Value
The Project Management Office - Effectiveness and Delivering ValueThe Project Management Office - Effectiveness and Delivering Value
The Project Management Office - Effectiveness and Delivering Value
 
Mergers and Acquisitions Toolkit - Framework, Best Practices and Templates
Mergers and Acquisitions Toolkit - Framework, Best Practices and TemplatesMergers and Acquisitions Toolkit - Framework, Best Practices and Templates
Mergers and Acquisitions Toolkit - Framework, Best Practices and Templates
 
Managing Benefits - Foundation
Managing Benefits - FoundationManaging Benefits - Foundation
Managing Benefits - Foundation
 

En vedette

Chapter 14 Managing Employee Benefits
Chapter 14 Managing Employee BenefitsChapter 14 Managing Employee Benefits
Chapter 14 Managing Employee Benefits
Rayman Soe
 
Business Cases And Benefits Management
Business Cases And Benefits ManagementBusiness Cases And Benefits Management
Business Cases And Benefits Management
Alan McSweeney
 
Business Process Re-engineering
Business Process Re-engineeringBusiness Process Re-engineering
Business Process Re-engineering
rinkimusaddi
 

En vedette (20)

Workshop A: Pragmatic benefits realisation management
Workshop A: Pragmatic benefits realisation managementWorkshop A: Pragmatic benefits realisation management
Workshop A: Pragmatic benefits realisation management
 
EA Benefits
EA BenefitsEA Benefits
EA Benefits
 
Integrating risk and benefits management
Integrating risk and benefits managementIntegrating risk and benefits management
Integrating risk and benefits management
 
Benefits realization
Benefits realizationBenefits realization
Benefits realization
 
Managing benefits from projects, Benefits management to enable change, Tuesda...
Managing benefits from projects, Benefits management to enable change, Tuesda...Managing benefits from projects, Benefits management to enable change, Tuesda...
Managing benefits from projects, Benefits management to enable change, Tuesda...
 
Pereira Diamond benefits model webinar 10th June 2015
Pereira Diamond benefits model webinar 10th June 2015Pereira Diamond benefits model webinar 10th June 2015
Pereira Diamond benefits model webinar 10th June 2015
 
Measuring and reporting non-financial benefits using the social return on inv...
Measuring and reporting non-financial benefits using the social return on inv...Measuring and reporting non-financial benefits using the social return on inv...
Measuring and reporting non-financial benefits using the social return on inv...
 
Outcome Relationship Models, presentation, Ned Newton, London, 23 June 2016
Outcome Relationship Models, presentation, Ned Newton, London, 23 June 2016Outcome Relationship Models, presentation, Ned Newton, London, 23 June 2016
Outcome Relationship Models, presentation, Ned Newton, London, 23 June 2016
 
E-Business: Chapter 1: Intro to E-B
E-Business: Chapter 1: Intro to E-BE-Business: Chapter 1: Intro to E-B
E-Business: Chapter 1: Intro to E-B
 
20 Tips to implement and rollout Organisational Change Projects
20 Tips to implement and rollout Organisational Change Projects20 Tips to implement and rollout Organisational Change Projects
20 Tips to implement and rollout Organisational Change Projects
 
The new path to organisational change - London Business School Review
The new path to organisational change - London Business School ReviewThe new path to organisational change - London Business School Review
The new path to organisational change - London Business School Review
 
Chapter 14 Managing Employee Benefits
Chapter 14 Managing Employee BenefitsChapter 14 Managing Employee Benefits
Chapter 14 Managing Employee Benefits
 
Agility and Organisational Change
Agility and Organisational ChangeAgility and Organisational Change
Agility and Organisational Change
 
Business Cases And Benefits Management
Business Cases And Benefits ManagementBusiness Cases And Benefits Management
Business Cases And Benefits Management
 
OpenStrategies: A simple system for Strategic Planning and Benefits Realisation
OpenStrategies: A simple system for Strategic Planning and Benefits RealisationOpenStrategies: A simple system for Strategic Planning and Benefits Realisation
OpenStrategies: A simple system for Strategic Planning and Benefits Realisation
 
Addressing the common challenges of benefits realisation management, workshop...
Addressing the common challenges of benefits realisation management, workshop...Addressing the common challenges of benefits realisation management, workshop...
Addressing the common challenges of benefits realisation management, workshop...
 
Business Process Re-engineering
Business Process Re-engineeringBusiness Process Re-engineering
Business Process Re-engineering
 
Bolman & Deal's Four Frames for Organisational Analysis
Bolman & Deal's Four Frames for Organisational AnalysisBolman & Deal's Four Frames for Organisational Analysis
Bolman & Deal's Four Frames for Organisational Analysis
 
South East Branch Knowledge cafe
South East Branch Knowledge cafe South East Branch Knowledge cafe
South East Branch Knowledge cafe
 
Who dares bims or handling bim risk in Hong Kong
Who dares bims or handling bim risk in Hong KongWho dares bims or handling bim risk in Hong Kong
Who dares bims or handling bim risk in Hong Kong
 

Similaire à Identifying and managing benefits masterclass

The strategy focused organization
The strategy focused organizationThe strategy focused organization
The strategy focused organization
herkick
 
Strategic Thinking For PM
Strategic Thinking For PMStrategic Thinking For PM
Strategic Thinking For PM
Arabella Jones
 
Im1013 Chapter 7
Im1013 Chapter 7Im1013 Chapter 7
Im1013 Chapter 7
Chanpohlai
 
Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)
LAXMI VIDYAPEETH
 
Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)
SAMIN-SAM
 
Strategic Thinking and Repositioning Day1
Strategic Thinking and Repositioning Day1Strategic Thinking and Repositioning Day1
Strategic Thinking and Repositioning Day1
Timothy Wooi
 
Effective Implementation Of Strategic Initiatives Nov 2009
Effective Implementation Of Strategic Initiatives Nov 2009Effective Implementation Of Strategic Initiatives Nov 2009
Effective Implementation Of Strategic Initiatives Nov 2009
giseke
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
Sitco
 

Similaire à Identifying and managing benefits masterclass (20)

Strategic management theories
Strategic management theoriesStrategic management theories
Strategic management theories
 
The strategy focused organization
The strategy focused organizationThe strategy focused organization
The strategy focused organization
 
pappu mgmt
pappu mgmtpappu mgmt
pappu mgmt
 
Edited on point_and_strategic_performance_assurance
Edited on point_and_strategic_performance_assuranceEdited on point_and_strategic_performance_assurance
Edited on point_and_strategic_performance_assurance
 
Strategy as Transformation
Strategy as TransformationStrategy as Transformation
Strategy as Transformation
 
Strategic Thinking For PM
Strategic Thinking For PMStrategic Thinking For PM
Strategic Thinking For PM
 
Enkkhancing Our Strategic Execution Culture (EOSEC)_Facilitator Guide_V1.0_20...
Enkkhancing Our Strategic Execution Culture (EOSEC)_Facilitator Guide_V1.0_20...Enkkhancing Our Strategic Execution Culture (EOSEC)_Facilitator Guide_V1.0_20...
Enkkhancing Our Strategic Execution Culture (EOSEC)_Facilitator Guide_V1.0_20...
 
Im1013 Chapter 7
Im1013 Chapter 7Im1013 Chapter 7
Im1013 Chapter 7
 
Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)
 
Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)Chapter 1 conceptual framework for strategic management (2)
Chapter 1 conceptual framework for strategic management (2)
 
Strategic Thinking and Repositioning Day1
Strategic Thinking and Repositioning Day1Strategic Thinking and Repositioning Day1
Strategic Thinking and Repositioning Day1
 
PDSA Cycle
PDSA CyclePDSA Cycle
PDSA Cycle
 
م.47-#تواصل_تطوير-م.محمد العربى-إستخدام مفاهيم الرشاقة للتحول الإستراتيجي للم...
م.47-#تواصل_تطوير-م.محمد العربى-إستخدام مفاهيم الرشاقة للتحول الإستراتيجي للم...م.47-#تواصل_تطوير-م.محمد العربى-إستخدام مفاهيم الرشاقة للتحول الإستراتيجي للم...
م.47-#تواصل_تطوير-م.محمد العربى-إستخدام مفاهيم الرشاقة للتحول الإستراتيجي للم...
 
Effective Implementation Of Strategic Initiatives Nov 2009
Effective Implementation Of Strategic Initiatives Nov 2009Effective Implementation Of Strategic Initiatives Nov 2009
Effective Implementation Of Strategic Initiatives Nov 2009
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
 
Foundations of business strategy - Lec 1.pdf
Foundations of business strategy - Lec 1.pdfFoundations of business strategy - Lec 1.pdf
Foundations of business strategy - Lec 1.pdf
 
Introduction To Strategy
Introduction To StrategyIntroduction To Strategy
Introduction To Strategy
 
Stretigic Management
Stretigic ManagementStretigic Management
Stretigic Management
 
management
management management
management
 
How To Balance Long-term Strategic Goals With Immediate Operating Concerns, R...
How To Balance Long-term Strategic Goals With Immediate Operating Concerns, R...How To Balance Long-term Strategic Goals With Immediate Operating Concerns, R...
How To Balance Long-term Strategic Goals With Immediate Operating Concerns, R...
 

Plus de Association for Project Management

Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Association for Project Management
 

Plus de Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Dernier

Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
instagramfab782445
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
laloo_007
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
ZurliaSoop
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Dernier (20)

Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in OmanMifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
Mifepristone Available in Muscat +918761049707^^ €€ Buy Abortion Pills in Oman
 
Buy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From SeosmmearthBuy Verified TransferWise Accounts From Seosmmearth
Buy Verified TransferWise Accounts From Seosmmearth
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
Cracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' SlideshareCracking the 'Career Pathing' Slideshare
Cracking the 'Career Pathing' Slideshare
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Cannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 UpdatedCannabis Legalization World Map: 2024 Updated
Cannabis Legalization World Map: 2024 Updated
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 

Identifying and managing benefits masterclass

  • 1. Benefits in Practice Series Identifying and Managing Benefits 19th June 2013 The Innovation Space, BIS
  • 2. Agenda 1:30 Welcome and Introductions 1:45 Setting the Context: Corporate Strategy and Benefits 2:10 Case Study Exercise 1 (groups of 3 participants) 2:30 Benefits Lifecycle » Benefits identification and modelling 3:00 Case Study Exercise 2 » 3:30 Feedback to group (content) » 3:50 Aligning Benefits Realisation to the wider organisation » Ownership, Governance and Convergence 4:25 Summary and Close
  • 3. Introduction to Presenters  Peter Glynne – Co-Chair of Benefits Management SIG  Nick Wensley – Co-Chair of Benefits Management SIG  Neil White  Hugo Minney PhD
  • 4. What are you going to get from this afternoon?  Establish a strong base of practical experience  Consider different approaches to benefits identification and modelling  Consider new ways of thinking and how to drive innovation  Explore effective benefits leadership  Network and share experience
  • 5. Setting the Context Corporate Strategy and Benefits Realisation “A world in which all projects succeed” APM’s 2020 Vision Impossibility or deliberately aspirational?
  • 6. Discussion Point: What does Benefits realisation mean to your organisation? In three words or less…..
  • 7. MeasurementActivists Full Cycle Governance A future in which all projects succeed…  Right Things  Right Way  Done Well Portfolio Management Leadership, Alignment, Value Optimisation, Programme selection, Portfolio Adjustment Programme Management Business Sponsorship, Ownership, Coordinate complementary and interdependent projects to realise … Project Management Management of budget, schedule and resources to deliver … Capability Benefits Strategic Objectives Getting Benefits John Thorp
  • 8. A future in which all projects succeed  Engage the right people in the business – so they want success  Effective cross-boundary working and decision-making at executive level  Incentivise organisational convergence to pull together work on business benefits  Recognise the need for agility and flexibility … instead of just working to the next milestone  A clear connection with corporate strategy. The ‘WHY’ of projects.
  • 9. Case Study Exercise 1 HS2 Context and Strategic objectives  20 minutes in groups of three  Consider the following Nathan Coyne article: http://www.politics.co.uk/news/2013/05/09/make-the-case-for-hs2-benefits  Identify the top six stakeholder groups  From the point of view of DfT: Consider six points of strategic value for their investment in HS2
  • 11. All the focus has been on the success of Project & Programme Management……
  • 12. What makes Project Management successful?  Project Management Success Criteria – Time / Budget / Quality – Business Objectives and Business Benefits  PwC 2012 – greater maturity, higher success rate – Use an established method for project management – Use certified practitioners (you wouldn’t trust a pilot . . ) In a nutshell: Professionalism….
  • 13. Should we not apply the same professionalism to Benefits Realisation?
  • 14. The Benefits Lifecycle A Strategic and Integrated Approach based on partnership
  • 15. Benefits Mapping – Some Techniques Considering specific aspects of HS2  Cassandra Benefits Management model (Cranfield)  Results Chain (DMR / Thorp)  Benefits Dependency Map (Bradley)  Benefits Value Mapping (Glynne) The benefits map or model is ONLY as an aid to communication and decision making. It must be simples, easy to understand and easy to communicate. Too many models are only understood by the author Key Point
  • 16. Cassandra / Cranfield ENABLERS ENABLING CHANGES BUSINESS CHANGES BUSINESS BENEFITS INVESTMENT OBJECTIVES Treasury guarantees Planning laws Public consultation Investment Routes for line Linked investment Stations and community travel High Speed line Journey times Link economic centres Major infrastructure build
  • 17. Results Chain (DMR/ Thorp) HS2HS2 Shorter Commute TimesFaster More reliable Shorter Business Meeting journey times Work London, Live in regions Work in Regions, more business Regional Economic Growth constraint is journey time more meetings = more business Last Mile Last Mile PricePrice Phase 2 Phase 2 Legislation to compulsory purchase land Legislation resource release
  • 18. Benefits Dependency Map (Bradley) To Increase Regional Economic Growth To increase jobs in regions To widen labour pool To increase passenger satisfaction Reduce commute time Shorter meeting journey time Increased UK Trading Improved GDP Increased regional spend More good workers attracted to London HSR Bill HS2 Hybrid Bill Link economic centres (∅ 2) Link Midlands to London (∅ 1) ObjectiveBenefit Business Changes Enabler Disbenefit
  • 19. Named New Capability Project, Programme or Portfolio NewCapabilitiesStrategicValueOperationalBenefits Strategic Objective Effectiveness Strategic Objective Effectiveness Strategic Objective Effectiveness Action led word describing the Operational Benefit A Benefit Type (1 of 5) How to Read the Benefits Value Map..... New tangible capabilities directly attributable to the investment in the project, programme or portfolio. New to the business area or organisation e.g. What we are buying for our investment? Operational, functional day to day benefits relevant to the organisation Five types of operational benefit to enable consistency and comparability. KEY LINK TO OPERATIONAL PERFORMANCE MANAGEMENT A dashboard is developed for every operational benefit showing key performance indicators, priority ranking and ownership There must be a direct correlation/relationship from a capability to an operational benefit Five Types of Operational Benefit CRITICAL TO MEASUREMENT 1.Time – measured in hours, day, weeks etc. 2.Cost – measured in £ 3.Satisfaction/Assurance – measured by a before and after perception survey showing a measurable improvement 4.Income – measured in £ 5.Disbenefit – the negative consequences of change - measured using one of the four types described above The colour boxes highlight the contribution of the operational benefit to strategic value in the bottom row. It must reflect the organisation’s or group’s business plan or strategy Unique identifier for each operational benefit Showing the contribution of individual operational benefits to the business plan or strategy. Two categories: 1. Efficiency 2. Effectiveness
  • 20. Benefits Value Mapping OperationalBenefits Howwillitchangeourperformance? StrategicValue Howwillitcontributetostrategy? NewCapabilities Whatareweinvestingin? Time Time Income Time Income Cost Satisfaction Assurance INCREASED ECONOMIC INVESTMENT IN REGIONS Effectiveness INCREASED PASSENGER SATISFACTION WITH SERVICES Effectiveness ? Effectiveness ? Effectiveness A B C D E F G H I J Focus on change, business performance and measurement
  • 21. Exercise 2 – HS2 Benefits at operational level  30 minutes in threes  Partially completed template – fill in the gaps  Share from your group – please nominate spokesperson (1 minute feedback time) – Results of discussion on HS2
  • 22. Aligning Benefits Realisation to the Wider Organisation Ownership, Governance and Convergence
  • 23. Benefits Realisation Common Behaviours across organisations And there’s always the impact of the media.....
  • 24. CONVERGENCE What are the Opportunities for collaboration? Operational Performance Management Financial Forecasting/ Budgeting Strategic Planning and Evaluation Benefits Realisation PMO Change Management Ever increasing professionalism in the management of change within organisations Communications (internal and external)
  • 25. Benefits Realisation: Effective Partnership Working Likely degree of engagement across the Change Journey within a typical organisation. Typical Professional Group Strategy / Policy Delivery Embedding of Change Project/Programme Management Finance Profession Sponsors of Change Economists Strategists Business Change Managers External Relations/Communications Human Resources Operational Management Procurement Contract Management Organisation Executive Board Internal Audit
  • 26. Understanding Behaviours, Governance and Convergence What to look out for across your organisation?
  • 27. Process Obsessed Benefits Realisation We MUST follow the prescribed process/manual
  • 28. People looking to find a problem for a waiting benefits solution.... My favourite solution will solve any ill...........
  • 29. Limiting the focus to only the Project or Programme....... We don’t want to INVOLVE other areas of the business.. too political
  • 30. Believing that lack of success is other people’s issue for not understanding how important something is.......... They won’t listen and they don’t want to understand
  • 31. Groupthink on the approach to benefits realisation...... We all agree so it must be the right approach.....???
  • 32. Governance of Benefits  Governance is one of the most important factors in the successful realisation of benefits. Not just at Portfolio level which is critical to success!!  Governance needs to be a ‘partnership approach’ between the project/ programme and wider business organisation (operational/business as usual)  The wider business organisation should always own the benefits. Align director level and operational ownership. Two level ownership.....portfolio level and operations  The project/ programme should facilitate the benefits on behalf of the business organisation – not own the benefits………. Governance is closely linked to leadership and organisation culture – arguably the most important aspect of successful benefits realisation. GET IT WRONG AT YOUR PERIL as governance can be difficult to change once implemented Key Point
  • 33. Challenges in Implementing a Robust Governance Model • Getting senior executives to take responsibility for individual or collective benefits, especially if there is a history of project/programme failure within the organisation • Jargon/technical language trap • Ensuring that there is a clear understanding of roles and responsibilities for benefits realisation. Communication, Communication, Communication • Maintaining momentum – if the governance model becomes ineffective, senior managers will very quickly lose confidence in it.
  • 34. An example Governance Model for a Single Organisation An actual model used within a UK public sector organisation
  • 35. An Example Governance Model for Multiple Organisations During Implementation An actual model used within a UK public sector organisation
  • 36. An Example Governance Model for Multiple Organisations Post-implementation An actual model used within a UK public sector organisation
  • 37. Pushing the Boundaries of Change Benefits Realisation across Local Government Thought Leadership: Six Action Points: 1.Incentivise organisation wide convergence in benefits realisation 1.Move beyond an over reliance on isolated process, low-value templates and certification driven technical knowledge 2.Establish appropriate benefits leadership at the portfolio level 3.Greater external partnership working to deliver change and benefits 4.Greater integration of the cost reduction agenda and benefits realisation 5.Invest in professionalism; innovation and collaboration
  • 39. Conclusions – where to go from here  Recap – Benefits Mapping in context – Benefits Lifecycle – Ownership and Governance – Conclusions from exercises  What would people like to see next?
  • 40. Some Examples of Approaches
  • 41. Org 5 Customer Group 1 Customer Group 2 Customer Group 3 Org 6 A B C D E F G Example Stakeholder and Benefits Impact Matrix High Low H The above table illustrates the impact of each benefit on the each stakeholder group. Benefits are in order of sequence only Org 4Org 3Org 2Org 1 Greater assurance in the quality and integrity of returns Main Organisation Other Stakeholders Reduced staff costs on administration of customer's hard copy financial accounts Increased assurance in the accuracy of returns and statements being filed Increased customer satisfaction with the filing of financial accounts Increased assurance in debt management in Collector Generals Increased satisfaction with the quality and access to information on financial accounts Increased confidence in the targeting of interventions based on risk profile Increased confidence in the targeting of interventions based on risk profile Operational Benefit Source: Glynne
  • 42. Sample Operational Benefit Dashboard Ref: BenefitA Description Impact Summary Measurement Question Method and Unit of Measurement Baseline Value Target Value Actual Values Measurement to be done by Priority Likelihood of Failure Dependency on other Benefits Benefit Category Actions Required to Realise the Benefit Ownership Start Date End Date Risks Impacting Realisation of the Benefit Impact Probability Mitigation Director Owner Operational Owner Current RAG Status Exposure Rating 16 AN Other AN Other Question to be asked to measure the benefit How will the benefits be measured and what is the unit of measurement. Alignment with organisational performance management including relevant KPIs Measurement Dates ? ? Baseline Actual(s) Time ? Cost? Satisfaction ? Income ? Profitability ? 4 4 Owner End date to be realised TBC Source: Glynne

Notes de l'éditeur

  1. Importance of Portfolio, aligning the Strategic Objectives and constraining to Corporate Governance. Everything within constraint of a single portfolio – avoid double-counting by defining measurement and collecting results at Portfolio level Not getting into discussion on definition of Programme and Project Motivating people (activists) Analogy with flying an aeroplane
  2. We’ll come on to this in the Benefits Lifecycle section
  3. You have the whole of the space in The Innovation Space, but please don’t go outside Please be back in time for 2:30 start on Benefits Lifecycle This forms the foundation for the next exercise so feedback will be after the next exercise
  4. 2:30 start
  5. Lots of reports on Project Management, you will probably recognise a lot of them including Standish Chaos reports
  6. 5 criteria for success used by PwC – Iron triangle Business Objectives On this basis 68% fail. 60% of failure is due to internal problems in particular failure to plan. You wouldn’t trust a pilot to fly you across the Atlantic who had just completed an online course and got a certificate – you’d want to see ability and experience. Do you let novices loose on your big project investment?
  7. Some reports where PAC and MPA are asking to see benefits, or align delivery with benefits
  8. Strategy dictates what are the gaps that need filling, whether Opportunity Response to legislation change (what would it have cost to comply without change?) Cost improvement Benefits the WHY of projects Four stages of Benefits Management, starting with the idea and proposal to start an OBC and BC. Benefits Planning will influence decisions during project/ programme delivery, to optimise benefits Not constrained by tolerance on the upside, although on downside always consider changes in the environment (cost of finance, key skills etc) which might pull rug from business case Handover and commitment by frontline staff to realise benefits Benefits Review leading to further optimisation, perhaps without a new project
  9. Note: MSP Benefits Map (p62), Benefits Logic Map (p65) or Investment Logic Map (p32) not used. Some factors to help decide when each of these methods should be used: Where are you in the process? If change are underway then the value to gained through stakeholder inclusion is lost. Use value mapping or results chain. If at beginning or cycle then those techniques that major on drivers and objectives could be favoured. Is consensus desirable or sought? Bradley BDN enables stakeholder participation. How large is the programme? Value Mapping favours large initiatives. Objective and benefits relational maps may get unwieldy. Benefits Management Capability maturity of organisation? Choice of mapping technique could be made to favour existing capabilities of personnel.
  10. Cassandra / Cranfield Benefits Dependency Network (developed 2006) Given understanding of prevailing change drivers: Work to right to identify strategic objectives. Objectives are analysed and mapped to benefits to be realised on meeting of objectives. Each benefits is now mapped (right to left) to the changes needed to realise it. This approach recognises the fact that some business changes themselves required to be enabled by upstream changes e.g. IS/IT  Working from Right (the Future) to Left What we want What we have to become to get what we want What we have to do to become what we need Working from Left (what we’re doing) to Right Justify a previous decision Find a return for the investment Strengths Simple – can be done in 15-30 minutes Clear linkage between change in the environment and change in the project Collaboration and group working is easy Weaknesses Without good facilitation can become unnecessarily complicated Confusion over definitions and failure to align in neat columns (this project leads to this benefit which leads to this project …)
  11. Results Chain (DMR/Thorp) Provides a graphical representation of the vents and conditions required to achieve stated business outcomes. Four components: Outcomes (benefits) – circles Initiatives – squares Contributions – shown as arrows Assumptions – hexagons Strengths Impact of change in environment or programme/project delivery easy to follow Tasks associated with benefits Promotes discussion Consensus building Shared agreement of how changes will add value Use of Assumptions makes implicit thinking explicit and therefore open to debate Weaknesses Typically maps from the activity to find outcomes Unlikely to unearth new information – usually done by Project Team rather than all stakeholders From single project, benefits may multiply (leading to double-counting)
  12. Gerald Bradley’s Benefits Dependency Map - Neil Dependency path from required enabling changes through to objectives. Three stages: 1 - Building a Strategy Map of linked objectives ( maybe 10 to 16) to explore objectively what the changes must achieve – arrive at 2 to 4 ‘bounding objectives’ to scope the programme 2 - Creating a Benefits Map for each ‘bounding objective: For each bounding objective a Benefits Map is developed. This is developed by working from right to left from the objective, identifying, at each stage, a set of directly contributing benefits. The test for each set is that they are: Collectively sufficient Individually necessary Mutually independent Likely to lead to different kind of change needs 3 - Transforming the resulting Benefits Map into a Benefit Dependency Map : Add the business and enabling changes needed to enable the delivery of the benefits. Strengths Provides a clear line of sight from changes through to objectives - a logical flow Particularly effective in engaging and gaining buy-in from Stakeholders Cane be used to depict progress being made in achieving objectives – benefits can be weighted to show contribution to objectives/ Weaknesses Maps can get complicated – this can be reduced by depicting only bounding and end benefits
  13. What is point regarding explicit and implicit objectives? * VERY IMPORTANT AND USUALLY MISSED I think that the context should explicitly position the people factor. * TOO EARLY – IT COMES UP LATER
  14. UNCLASSIFIED
  15. UNCLASSIFIED
  16. UNCLASSIFIED
  17. UNCLASSIFIED
  18. UNCLASSIFIED
  19. What is point regarding explicit and implicit objectives? * VERY IMPORTANT AND USUALLY MISSED I think that the context should explicitly position the people factor. * TOO EARLY – IT COMES UP LATER
  20. What is point regarding explicit and implicit objectives? * VERY IMPORTANT AND USUALLY MISSED I think that the context should explicitly position the people factor. * TOO EARLY – IT COMES UP LATER