Joint projects and the
governance conundrum
1
APM Governance SIG
27th January 2017
2
Agenda
 Introduction
 About APM Governance SIG
 Overview of the ‘Governance of Co-owned Projects’
 Upcoming events
Introductions
Martin Samphire – host
Andy Murray - speaker
3
Andy.murray@rsmuk.com
07776 301602
https://uk.linkedin.com/in/andymurray
Andy Murray
Andy is a chartered director and management consultant
specialising in Project, Programme and Portfolio
Management, with over 20 years of varied experience (public
sector/private sector, SME/corporate, domestic/international).
Andy has a focus on project/programme governance and the
treatment of inherent project/programme complexity. He has
worked with Axelos, HM Treasury, Cabinet Office and the
Association For Project Management (APM) in developing
guidance on delivering successful projects/programmes,
such as IUK Project Initiation Routemap, Directing Change,
Co-Directing Change, PRINCE2 and P3M3.
Andy is a sought after speaker and was cited in the Sunday
Telegraph’s business supplement as one of the most
influential people in project management.
Andy is a partner in RSM UK, responsible for the Project and
Programme service line and is also RSM’s Head of
Infrastructure sector.
About the
APM Governance SIG
5
Governance SIG
Objectives
 Be the UK focus
 Advance understanding
 Contribute to good practice
 Influence national and
international standard making
authorities
 Influence those operationally
responsible
 Develop ambassadors and
exemplars of excellence
6
….in the governance of project management (change)
Activities
 Engagement – CxO level
as well as APM members
 Conferences and Seminars
 Publications
 Influence of, and
contribution to, standards
Directing Change
2nd edition 2011
7
Governance of Co-
owned Project
2017
Sponsoring Change
2009
Free to APM members at www.apm.org.uk/memberdownloads
GovSIG Publications
Directing Agile
Change 2016
To join the SIG, please register/log into the APM website
and on the Governance page click join this group.
Overview of
the new guide
8
Governance of Co-owned Projects
 What are co-owned projects/programmes
 Why traditional governance models struggle
 Governance of co-owned projects/programmes principles
 Governance of co-owned projects/programmes health-check
 How to use the guide
 Benefits
9
Co-owned Projects: Context
 There are numerous benefits of working on joint projects
 Often organisations are participating in joint projects that are
sometimes greater in scale and complexity than they have
undertaken on their own
 By committing to a joint project the Board of each participating
organisation takes on more than usual than if they did it on their
own
 Each organisation will inevitably, in the eyes of stakeholders, be
associated with the project – whether successful or not.
 So a core concept of joint projects is that they are ‘co-owned’ by the
participating organisations.
10
Co-owned Projects: Context
11
Governance of project
management organisation
2
Governance of project
management organisation
1
Project Management of co-
owned project
Organisation 1 governance Organisation 2 governance
Governance of co-
owned project
Co-owned Projects: Issues
12
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
The challenge for organisations
who sponsor or deliver co-owned
projects is that traditional project
management frameworks and
methods are based on governance
structures that assume a single
hierarchical route for authority and
accountability.
This is rarely the case for co-owned
projects which is why organisations
are rightly challenging whether their
traditional governance
arrangements are fit for purpose.
13
Formal Arrangements
Agreements
Flexibility and change management
Benefits and rights
Co-owner to Co-owner
due diligence
Mutually accepted business cases
Co-owners’ legal and governance compatibility
Co-owners’ standing, culture and capability
Working Arrangements
Reporting
Assurance and transparency
Stakeholder relationships
Trust, collaboration and value maximisation
Co-owned Projects: Principles
Co-owned Projects: Principle 1
14
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
1. Agreements
There should be formally agreed
governance arrangements. These may
include legal contracts and agreements
among co-owners which together
ensure
• Clear processes for decision
making ensuring unified project
management and unambiguous
representation of each co-owner.
• Processes to deal with conflicts
of duty, conflicts of interest,
ambiguous accountability and
the resolution of disputes.
• Explicit commitment to
collaboration, resource
provision, mobilisation and
demobilisation.
Co-owned Projects: Principle 2
15
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
2. Flexibility and change
management
The formal arrangements should
provide for fundamental change
including change in the group of co-
owners and should define the
process to be invoked.
This includes changes as a result of
revised objectives or approach,
resolution of conflicts, co-owners
joining or leaving, or as a
consequence of material change in
control, relevant strategy or risk
appetite within co-owning
organisations.
Co-owned Projects: Principle 3
16
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
3. Benefits and rights
The formal arrangements should
define responsibility for the
realisation of benefits arising and
discharge of co-owners’ obligations
after leaving or completion.
They should include intangible
benefits and the protection of co-
owner’s confidentiality and
intellectual property, and rights to
publicise outcomes or represent
other co-owners.
Co-owned Projects: Principle 4
17
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
4. Mutually-accepted business
cases
Each co-owner should assure itself
that each co-owner’s organisation
has a stable basis of internal
approval of its business case for the
project and is committed to maximum
openness about its nature and
relevant changes as they may occur.
Critical aspects of the business
cases include clear definitions of
project objectives, the role of each
co-owner, their incentives and
rewards, risk allocation, commitments
and responsibilities.
Co-owned Projects: Principle 5
18
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
5. Co-owners’ legal and
governance compatibility
Each co-owner should assure itself of
the legal competence and relevant
obligations of co-owners, and that
internal governance arrangements of
co-owners and any project delivery
structure created are compatible with
standards of governance acceptable
to it.
Co-owned Projects: Principle 6
19
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
6. Co-owners’ standing, culture
and capability
Each co-owner should assure itself
that co-owners’ cultures, knowledge,
capabilities and reputation are
appropriate to co-ownership of the
project and also that co-owners’
policies and practices on ethics and
sustainability are acceptable to it.
Co-owned Projects: Principle 7
20
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
7. Reporting
The depth, breadth and transparency
of reporting should be fair, balanced
and suitable for the audience to
understand.
Reports should provide the
information needed for co-owners to
make decisions, report onward to
stakeholders and to trigger previously
agreed independent review and
corrective actions when they have
legitimate concerns about the
achievement of project objectives or
viability.
Co-owned Projects: Principle 8
21
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
8. Assurance and transparency
Projects should incorporate
arrangements for access to
information necessary for co-owners'
internal control or audit functions, for
conformity with disclosure and
transparency obligations, for
independent assurance and also
include channels for whistleblowing.
Co-owned Projects: Principle 9
22
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
9. Stakeholder relationships
There should be arrangements in
place to ensure that the execution of
projects takes account of co-owners'
shareholder and other stakeholder
relationships and to deal with
reputational risk and potential
conflicts of interest.
Co-owned Projects: Principle 10
23
Governance of
project management
organisation
2
Governance of
project management
organisation 1
Project Management of
co-owned project
Organisation 1 governance Organisation 2 governance
Governance of
co-owned
project
10. Trust, collaboration and value
maximisation
There should be arrangements in
place to build and maintain trust,
collaboration and collaborative
behaviour including identifying
opportunities for improving the value
of the project to co-owners.
Governance of Co-owned Projects:
Checklists
24
A set of questions to probe current and
planned arrangements
Categories
 Alignment and compatibility
 Reward, risk and opportunity
 Leadership and sponsorship
 Project management capability
 Disclosure and reporting
The checklists are designed to uncover
gaps and prompt action. Surveys,
workshops or interviews can be used to
explore how well the organisation or project
is set up for co-ownership.
Leadership and Sponsorship
Governance of Co-owned Projects:
How to use the guide
25
Organisational Governance Project Governance
What to assess Reasons why any of the principles is not accepted
– comply or explain.
Validate using a sample of co-owned projects
across the organisation.
The specific project in question only.
Identify gaps and departures from the principles.
Identify relevant key questions not satisfactorily
answered.
Scope of
assessment
The specific organisation only.
Reviewing different types of co-owned projects
experienced or likely to be considered.
Governance of the project by all the co-owners
(and potential co-owners if desired).
How to use the
results
Identify the corporate arrangements that need
enhancing based on gaps identified.
Gaps may originate from:
 exceptions and variability across the sample;
 weak/absent organisational policies,
guidance, capabilities, or behaviours.
Identify the specific arrangements for the project
that need enhancing based on gaps identified.
Gaps may originate from:
• weak/absent arrangements within the project;
• weak/absent corporate arrangements within the
co-owning organisations.
Governance of Co-owned Projects:
Benefits
 Helps inform when not to do a joint project
 Makes explicit downstream issues
 Certainty of decision-making process
 Robust decisions
 Timely decision-making
 Reduces admin burden (e.g. reporting)
 Stronger stakeholder relationships
 Greater visibility of threats and opportunities and how to
minimise/optimise them
26
Governance of Co-owned Projects:
Order it now!
27
APM members can get 10% off the price by calling +44 (0)1767 604951
Thank you. Questions?
APM Governance SIG
28
Getting Involved with GovSIG
 APM GovSIG on website
 Development events
 Conference
 Blogging
 Research
 Committee
29
To join the SIG, please register/log into the APM website and on
the Governance page click join this group.
This presentation was delivered
at an APM webinar
To find out more about
upcoming webinars please visit
our website
www.apm.org.uk/events

Contenu connexe

Tendances

Collaboration, sharing knowledge & improving delivery within the public sector
Collaboration, sharing knowledge & improving delivery within the public sectorCollaboration, sharing knowledge & improving delivery within the public sector
Collaboration, sharing knowledge & improving delivery within the public sector
Association for Project Management
 

Tendances (6)

Collaboration, sharing knowledge & improving delivery within the public sector
Collaboration, sharing knowledge & improving delivery within the public sectorCollaboration, sharing knowledge & improving delivery within the public sector
Collaboration, sharing knowledge & improving delivery within the public sector
 
Directing Agile Change, 14th October 2015, London
Directing Agile Change, 14th October 2015, LondonDirecting Agile Change, 14th October 2015, London
Directing Agile Change, 14th October 2015, London
 
APM Presents - Introducing Portfolio Management
APM Presents - Introducing Portfolio ManagementAPM Presents - Introducing Portfolio Management
APM Presents - Introducing Portfolio Management
 
New developments in program management
New developments in program managementNew developments in program management
New developments in program management
 
Overview of developments in project management - ICE MPL Proceedings
Overview of developments in project management - ICE MPL ProceedingsOverview of developments in project management - ICE MPL Proceedings
Overview of developments in project management - ICE MPL Proceedings
 
APM North West conference 9 October 2018
APM North West conference 9 October 2018APM North West conference 9 October 2018
APM North West conference 9 October 2018
 

Similaire à Joint projects and the governance conundrum webinar, 27 January 2017

2015 PMI SCC GreenPM in the process groups - Alison C Holder
2015 PMI SCC GreenPM in the process groups - Alison C Holder2015 PMI SCC GreenPM in the process groups - Alison C Holder
2015 PMI SCC GreenPM in the process groups - Alison C Holder
alisoncholder
 

Similaire à Joint projects and the governance conundrum webinar, 27 January 2017 (20)

Good governance of the project portfolio
Good governance of the project portfolioGood governance of the project portfolio
Good governance of the project portfolio
 
Sponsorship presentation
Sponsorship presentationSponsorship presentation
Sponsorship presentation
 
Project governanc
Project governancProject governanc
Project governanc
 
North West branch Annual General Meeting & "Lessons on Governance"
North West branch Annual General Meeting & "Lessons on Governance"North West branch Annual General Meeting & "Lessons on Governance"
North West branch Annual General Meeting & "Lessons on Governance"
 
0. Foundations of project management (2).ppt
0. Foundations of project management (2).ppt0. Foundations of project management (2).ppt
0. Foundations of project management (2).ppt
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2
 
APM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challengesAPM Presents - Why project governance and its key principles and challenges
APM Presents - Why project governance and its key principles and challenges
 
13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview
 
1. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV0110151. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV011015
 
Project Management
Project ManagementProject Management
Project Management
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOK
 
Project governance
Project governanceProject governance
Project governance
 
Ethics in project management.pdf
Ethics in project management.pdfEthics in project management.pdf
Ethics in project management.pdf
 
Project management frame work part 1
Project management frame work part 1Project management frame work part 1
Project management frame work part 1
 
Effective governance
Effective governanceEffective governance
Effective governance
 
Project Planning Managment {Chapter One}.pptx
Project Planning Managment {Chapter One}.pptxProject Planning Managment {Chapter One}.pptx
Project Planning Managment {Chapter One}.pptx
 
It's not Big Brother - governance in the construction industry - RICS Article
It's not Big Brother - governance in the construction industry - RICS ArticleIt's not Big Brother - governance in the construction industry - RICS Article
It's not Big Brother - governance in the construction industry - RICS Article
 
Untitled document.pdf
Untitled document.pdfUntitled document.pdf
Untitled document.pdf
 
2015 PMI SCC GreenPM in the process groups - Alison C Holder
2015 PMI SCC GreenPM in the process groups - Alison C Holder2015 PMI SCC GreenPM in the process groups - Alison C Holder
2015 PMI SCC GreenPM in the process groups - Alison C Holder
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 

Plus de Association for Project Management

Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Association for Project Management
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
Association for Project Management
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Association for Project Management
 

Plus de Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Dernier

Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
amitlee9823
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
dlhescort
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
amitlee9823
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 

Dernier (20)

Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 

Joint projects and the governance conundrum webinar, 27 January 2017

  • 1. Joint projects and the governance conundrum 1 APM Governance SIG 27th January 2017
  • 2. 2 Agenda  Introduction  About APM Governance SIG  Overview of the ‘Governance of Co-owned Projects’  Upcoming events
  • 3. Introductions Martin Samphire – host Andy Murray - speaker 3
  • 4. Andy.murray@rsmuk.com 07776 301602 https://uk.linkedin.com/in/andymurray Andy Murray Andy is a chartered director and management consultant specialising in Project, Programme and Portfolio Management, with over 20 years of varied experience (public sector/private sector, SME/corporate, domestic/international). Andy has a focus on project/programme governance and the treatment of inherent project/programme complexity. He has worked with Axelos, HM Treasury, Cabinet Office and the Association For Project Management (APM) in developing guidance on delivering successful projects/programmes, such as IUK Project Initiation Routemap, Directing Change, Co-Directing Change, PRINCE2 and P3M3. Andy is a sought after speaker and was cited in the Sunday Telegraph’s business supplement as one of the most influential people in project management. Andy is a partner in RSM UK, responsible for the Project and Programme service line and is also RSM’s Head of Infrastructure sector.
  • 6. Governance SIG Objectives  Be the UK focus  Advance understanding  Contribute to good practice  Influence national and international standard making authorities  Influence those operationally responsible  Develop ambassadors and exemplars of excellence 6 ….in the governance of project management (change) Activities  Engagement – CxO level as well as APM members  Conferences and Seminars  Publications  Influence of, and contribution to, standards
  • 7. Directing Change 2nd edition 2011 7 Governance of Co- owned Project 2017 Sponsoring Change 2009 Free to APM members at www.apm.org.uk/memberdownloads GovSIG Publications Directing Agile Change 2016 To join the SIG, please register/log into the APM website and on the Governance page click join this group.
  • 9. Governance of Co-owned Projects  What are co-owned projects/programmes  Why traditional governance models struggle  Governance of co-owned projects/programmes principles  Governance of co-owned projects/programmes health-check  How to use the guide  Benefits 9
  • 10. Co-owned Projects: Context  There are numerous benefits of working on joint projects  Often organisations are participating in joint projects that are sometimes greater in scale and complexity than they have undertaken on their own  By committing to a joint project the Board of each participating organisation takes on more than usual than if they did it on their own  Each organisation will inevitably, in the eyes of stakeholders, be associated with the project – whether successful or not.  So a core concept of joint projects is that they are ‘co-owned’ by the participating organisations. 10
  • 11. Co-owned Projects: Context 11 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co- owned project Organisation 1 governance Organisation 2 governance Governance of co- owned project
  • 12. Co-owned Projects: Issues 12 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project The challenge for organisations who sponsor or deliver co-owned projects is that traditional project management frameworks and methods are based on governance structures that assume a single hierarchical route for authority and accountability. This is rarely the case for co-owned projects which is why organisations are rightly challenging whether their traditional governance arrangements are fit for purpose.
  • 13. 13 Formal Arrangements Agreements Flexibility and change management Benefits and rights Co-owner to Co-owner due diligence Mutually accepted business cases Co-owners’ legal and governance compatibility Co-owners’ standing, culture and capability Working Arrangements Reporting Assurance and transparency Stakeholder relationships Trust, collaboration and value maximisation Co-owned Projects: Principles
  • 14. Co-owned Projects: Principle 1 14 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 1. Agreements There should be formally agreed governance arrangements. These may include legal contracts and agreements among co-owners which together ensure • Clear processes for decision making ensuring unified project management and unambiguous representation of each co-owner. • Processes to deal with conflicts of duty, conflicts of interest, ambiguous accountability and the resolution of disputes. • Explicit commitment to collaboration, resource provision, mobilisation and demobilisation.
  • 15. Co-owned Projects: Principle 2 15 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 2. Flexibility and change management The formal arrangements should provide for fundamental change including change in the group of co- owners and should define the process to be invoked. This includes changes as a result of revised objectives or approach, resolution of conflicts, co-owners joining or leaving, or as a consequence of material change in control, relevant strategy or risk appetite within co-owning organisations.
  • 16. Co-owned Projects: Principle 3 16 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 3. Benefits and rights The formal arrangements should define responsibility for the realisation of benefits arising and discharge of co-owners’ obligations after leaving or completion. They should include intangible benefits and the protection of co- owner’s confidentiality and intellectual property, and rights to publicise outcomes or represent other co-owners.
  • 17. Co-owned Projects: Principle 4 17 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 4. Mutually-accepted business cases Each co-owner should assure itself that each co-owner’s organisation has a stable basis of internal approval of its business case for the project and is committed to maximum openness about its nature and relevant changes as they may occur. Critical aspects of the business cases include clear definitions of project objectives, the role of each co-owner, their incentives and rewards, risk allocation, commitments and responsibilities.
  • 18. Co-owned Projects: Principle 5 18 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 5. Co-owners’ legal and governance compatibility Each co-owner should assure itself of the legal competence and relevant obligations of co-owners, and that internal governance arrangements of co-owners and any project delivery structure created are compatible with standards of governance acceptable to it.
  • 19. Co-owned Projects: Principle 6 19 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 6. Co-owners’ standing, culture and capability Each co-owner should assure itself that co-owners’ cultures, knowledge, capabilities and reputation are appropriate to co-ownership of the project and also that co-owners’ policies and practices on ethics and sustainability are acceptable to it.
  • 20. Co-owned Projects: Principle 7 20 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 7. Reporting The depth, breadth and transparency of reporting should be fair, balanced and suitable for the audience to understand. Reports should provide the information needed for co-owners to make decisions, report onward to stakeholders and to trigger previously agreed independent review and corrective actions when they have legitimate concerns about the achievement of project objectives or viability.
  • 21. Co-owned Projects: Principle 8 21 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 8. Assurance and transparency Projects should incorporate arrangements for access to information necessary for co-owners' internal control or audit functions, for conformity with disclosure and transparency obligations, for independent assurance and also include channels for whistleblowing.
  • 22. Co-owned Projects: Principle 9 22 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 9. Stakeholder relationships There should be arrangements in place to ensure that the execution of projects takes account of co-owners' shareholder and other stakeholder relationships and to deal with reputational risk and potential conflicts of interest.
  • 23. Co-owned Projects: Principle 10 23 Governance of project management organisation 2 Governance of project management organisation 1 Project Management of co-owned project Organisation 1 governance Organisation 2 governance Governance of co-owned project 10. Trust, collaboration and value maximisation There should be arrangements in place to build and maintain trust, collaboration and collaborative behaviour including identifying opportunities for improving the value of the project to co-owners.
  • 24. Governance of Co-owned Projects: Checklists 24 A set of questions to probe current and planned arrangements Categories  Alignment and compatibility  Reward, risk and opportunity  Leadership and sponsorship  Project management capability  Disclosure and reporting The checklists are designed to uncover gaps and prompt action. Surveys, workshops or interviews can be used to explore how well the organisation or project is set up for co-ownership. Leadership and Sponsorship
  • 25. Governance of Co-owned Projects: How to use the guide 25 Organisational Governance Project Governance What to assess Reasons why any of the principles is not accepted – comply or explain. Validate using a sample of co-owned projects across the organisation. The specific project in question only. Identify gaps and departures from the principles. Identify relevant key questions not satisfactorily answered. Scope of assessment The specific organisation only. Reviewing different types of co-owned projects experienced or likely to be considered. Governance of the project by all the co-owners (and potential co-owners if desired). How to use the results Identify the corporate arrangements that need enhancing based on gaps identified. Gaps may originate from:  exceptions and variability across the sample;  weak/absent organisational policies, guidance, capabilities, or behaviours. Identify the specific arrangements for the project that need enhancing based on gaps identified. Gaps may originate from: • weak/absent arrangements within the project; • weak/absent corporate arrangements within the co-owning organisations.
  • 26. Governance of Co-owned Projects: Benefits  Helps inform when not to do a joint project  Makes explicit downstream issues  Certainty of decision-making process  Robust decisions  Timely decision-making  Reduces admin burden (e.g. reporting)  Stronger stakeholder relationships  Greater visibility of threats and opportunities and how to minimise/optimise them 26
  • 27. Governance of Co-owned Projects: Order it now! 27 APM members can get 10% off the price by calling +44 (0)1767 604951 Thank you. Questions?
  • 29. Getting Involved with GovSIG  APM GovSIG on website  Development events  Conference  Blogging  Research  Committee 29 To join the SIG, please register/log into the APM website and on the Governance page click join this group.
  • 30. This presentation was delivered at an APM webinar To find out more about upcoming webinars please visit our website www.apm.org.uk/events