SlideShare une entreprise Scribd logo
1  sur  35
CONSTRUCTION OF GSM BASE STATION
& TOWER FOR REGTel , CANADA
PROJECT MANAGER
SULEMAN MUHAMMED BASHIRU
PROJECT TEAM MEMBERS
OGUNYALE DAYO STEPHEN
ABOABAAKINTUNDE
ALMOTHANA DAWOUD
1
Overview
2
The Need
Map Of Regina, SK, Canada
Source: Google Earth
3
JUSTIFICATION
OPPORTUNITY
• Number of Students
and Staff on Campus
are in excess of
12,000
• About 7000 REGTel
customers currently
reside within the
campus
PROBLEM
• Experiencing
congestion at REG-03 &
REGTel -08 between 10
am – 4 pm (peak
utilisation)
• 18% Reduction in
Number Customers
since January, 2015
REVENUE
• Upon Completion, the
project can generate
$384,000 monthly ($40 x
9600 customers).
• Considering running cost
and administrative
expenses, the payback
period is expected to be two
(2) years
4
Project Objectives
● Provide competitive quality of services for
existing and potential customers within the
university and its environs.
● To decongest REGTel-03 site located west of
University of Regina and REGTel-08 located north of
University of Regina by 40% and 30% respectively.
5
Project Objectives Contd.
● Provide opportunity to justify REGTel sales drive.
Sales can be increased by at least 19 percent within
the university community.
● To serve as a hub site and back up site for REGTel-03
and REGTel-08.
6
Constraints
Bulk of the tools used will be rented
Storage of Materials
Scheduling the arrival of materials to maximise storage space
Training of Adhoc staff
7
Assumptions
Acquire licenses to build from Authorities
The project was planned & should be tracked at an activity
level
Duration estimation was done based on availability of
resources
It is the responsibility of the project manager to ensure that
progress is made per established plans
8
Acceptance Criteria
All cables from tower top to the shelter will be channelled through
cable tray
Earthing value of the site must not exceed 4.7 Ohms
Steel Reinforcement must be grade 50 deformed bars and
shall be covered with concrete overlay of minimum thickness of
75mm
The Intensity of the Aviation warning light should not be below 10
Candela
9
Acceptance Criteria Contd.
Tower should be painted with one coat of primer and two coats of
red/white enamel paint
Earth/Soil compaction ratio should be maintained during backfilling
The Shelter should have proper anti-static flooring and straps
All edges of slabs and tower base must be bevelled at 45 degrees
10
Project Organization Chart
Executive Director
{James Peters}
Engineering
Management &
Administration
Lawyers
Human Resource
Officer
Supply &
Procurement
Procurement
Officers
Project
Coordinator
Project Manager
11
Engineering
Electrical
Engineer
Civil
Engineer
Laborers
CAD
Technicians
Riggers
Rebar
Workers
Carpenters
RF
Engineer
Microwave
Engineer
Project Organization Chart
Contd.
12
Project Scope
Scope
Planning
Design
Supply of
Materials
Project
Implementation
& Control
Site Testing &
Commissioning
Procurement
13
High Level Requirements
Site
Selection
 Site Survey
 Site Purchase
 Soil Test
Civil Works
 Mobilisation to
site
 Excavation
 Reinforcement
 Formwork
 Casting
 Tower Rigging
Installation
 Electrical Installation
 Microwave Installation
 RF Installation
 Access Control
 Base Station
Commissioning
14
WBS SUMMARY
1.0 Construction
1.1 Site survey & Designs
1.1.1 Site Survey & Selection
1.1.2 Soil Test
1.1.3 Design Drawings
1.2 Civil works
1.2.1 Marking Out & Measurement
1.2.2 Excavating
1.2.3 Foundation for Tower
1.2.4 Erecting Tower
1.3 Site preparations
1.3.1 Supply of Temporary Water, Shelter, Power
2.0 Installation and Testing
2.1 Electrical Installation
2.1.1 Earthing of site
2.1.2 Aviation Warning Light
15
WBS SUMMARY Contd.
2.2 RF/ Microwave Installation
2.2.1 RF Installation
2.2.2 Microwave Instation
2.3 Acceptance Testing and Commissioning
2.3.1 Base Station Commissioning & Testing
2.3.2 Site on Air
3.0 Procurement/Supply of Materials
3.1 Procurement
3.2 Supply and Transportation of Materials
4.0 Management and Administration
4.1 Project Management
4.2 Permits
4.2.1 Building Permit
4.2.2 Frequency Reuse Permit
4.2.3 Public Safety Permit
4.3 Adhoc Staff recruitment
16
Project Stakeholders
 Project Sponsor, Executive Management
 Project Team
 City of Regina
 Government Agencies
 University of Regina Authorities
 Canada Transport Civil Aviation Authority
17
Risk Categories
Technical
 Nature of Soil
Human Resource
 Absenteeism &
Sick calls
 Workplace
accident/hazards
 Resignation
External
 Land litigation
 Delay in
Licensing, Permit
Approvals
 Unfavorable
Weather
condition.
18
Risk Categories
Cost
 Inflation
 Material Storage
 Delay in
Funding
Schedule
 Delay in Supply of
Material
19
Risk Assessment Matrix
Risks Impact Degree of
Impact
Probability of
Occurrence
Response
Plan and Risk
Owner
Delay in
Licensing, Permit
Approval
• Delay the
starting date.
• Delay the
schedule.
High Medium Follow up on the
licensing office to
know the updates
(PM & Legal)
Workplace
incident and
Hazards
Reduce skilled
workers
availability
High Medium • Acquire PPEs
• Train team on
those PPEs
(HSE)
Inflation Increase the
project budget
High Low Purchase critical
materials ASAP
(Procure Finance)
Delay in material
supply
Extend project
schedule and
budget
Medium Medium Always check
inventory level
(Supply Chain
Officer)
20
Project Schedule Summary
 Project duration is 217 days
 Project Start date is 18th April 2016
 Project Finish date is 14th February
2017
21
Milestones Schedule
Milestone 1
Site Survey
& Design
• August 22,
2016
Milestone 2
Permits &
Licensing
• September 14,
2016
Milestone 3
Procurement
& Payment
• October 12,
2016
Milestone 4
Adhoc Staff &
Recruitment
Milestone 5
Supply &
Transportation
of Materials
• October
21, 2016
November
3, 2016
22
Milestones Schedule Contd
Milestone 6
Civil Works
• January 2,
2017
Milestone 7
Electrical
Installation
• January 13,
2017
Milestone 8
RF &
Microwave
Installation
• January
13, 2017
Milestone 9
Testing
Milestone 10
Acceptance
Testing &
Commissionin
g
January 18,
2017
January
20 2017
23
Project Summary –Cost Estimates
Work Package Labour Cost ($) Material Cost ($)
Site Survey & Design 79,160 32,105
Permit & Licensing 7,112 12,663.6
Site Preparation 1,120 25,760
Procurement and
Payment
33,392 231,675
Adhoc Staff
Recruitment
6,360 300
Supply/Transportatio
n of materials
15,600 13,850
Civil Work 39,760 20,960
Electrical Installation 10,484 8,250
24
Project Summary – Cost
Estimates Contd.
Work Package Labour Cost ($) Material Cost ($)
RF & Microwave
Installation
3,144 58,400
Testing 2,032 3,500
Site landscaping 2,820 -
Acceptance Testing &
Commissioning Total
1,088 -
Project closing 81,680 -
Total 283,752 407,463.60
25
Project Cost Baseline
BAC = $691,215.60
Cost Baseline:
$793,215.60
Available Budget :
$950,000
Project Cost
Baseline
$793,215.60
Labor Cost
$283,752
Material Cost
$407,463.60
Contingency
Reserves
$102,000
26
Cumulative Budgeted Cost
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
Cumulative Budget Cost ($)
Cumulative Budget Cost ($)
27
Change
Management
Change Control Board,
CCB, is chaired by Project
Sponsor, James Peters
Any change to project
scope, cost or schedule
must meet CCB’s approval
28
Change
Management
Contd.
Change request will be
logged in the change
control register
The request should be
tracked through to
completion whether
approved or not
29
Change
Management
Contd.
If a change is approved
by the CCB, the project
manager will update and
re-baseline project
documentation as
necessary
Changes are
communicated to the
team and stakeholders
30
Change
Management Steps
Identify the
Need for
Change
• Any Stakeholder
Log in the
change
Register
• Project Manager
Evaluate
the
Change
• Project Manager
• Requester
• Project Team
31
Change
Management
Steps Contd.
Submit
Change
Request to,
CCB
• Project Manager
CCB
Approval
• CCB
• Project Manager
Implement
Change
• Project Manager
32
Lessons Learnt
Withdrawal of Team Member
Adopt Progressive Elaboration
Delegation of Duties
Regular Engagement of Stakeholders
33
Appendix
 Analysis of Schedule for the project
 Contact: sulemamu@uregina.ca
34
Thanks For Your Attention
35

Contenu connexe

Tendances

Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul A'mal Mohd Hanafiah
 
EPMS5397 Elite Expansion Project Summary
EPMS5397 Elite Expansion Project SummaryEPMS5397 Elite Expansion Project Summary
EPMS5397 Elite Expansion Project Summary
Evan Montgomery
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins Resume
Rusty Adkins
 
Resume_updated 2014
Resume_updated 2014Resume_updated 2014
Resume_updated 2014
J.D. Squire
 
Greg Quinn - Resume 20150214
Greg Quinn - Resume 20150214Greg Quinn - Resume 20150214
Greg Quinn - Resume 20150214
Gregory Quinn
 
Personal_Resume_11_2013
Personal_Resume_11_2013Personal_Resume_11_2013
Personal_Resume_11_2013
Stephen Ciulla
 
RyanMoyer_FinalResume
RyanMoyer_FinalResumeRyanMoyer_FinalResume
RyanMoyer_FinalResume
Ryan Moyer PE
 
Saeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updatedSaeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updated
Abbas Saeidi
 
RyanMoyer_FinalResume
RyanMoyer_FinalResumeRyanMoyer_FinalResume
RyanMoyer_FinalResume
Ryan Moyer PE
 
Resume-ParanthamanKrishnasamy
Resume-ParanthamanKrishnasamyResume-ParanthamanKrishnasamy
Resume-ParanthamanKrishnasamy
Paran K
 

Tendances (20)

Mohammed vasil k.
Mohammed vasil k.Mohammed vasil k.
Mohammed vasil k.
 
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
Khoirul Amal Mohd Hanafiah Piping Engineering Aug 2016
 
EPMS5397 Elite Expansion Project Summary
EPMS5397 Elite Expansion Project SummaryEPMS5397 Elite Expansion Project Summary
EPMS5397 Elite Expansion Project Summary
 
Rusty Adkins Resume
Rusty Adkins ResumeRusty Adkins Resume
Rusty Adkins Resume
 
Resume_updated 2014
Resume_updated 2014Resume_updated 2014
Resume_updated 2014
 
Res414
Res414Res414
Res414
 
Greg Quinn - Resume 20150214
Greg Quinn - Resume 20150214Greg Quinn - Resume 20150214
Greg Quinn - Resume 20150214
 
Personal_Resume_11_2013
Personal_Resume_11_2013Personal_Resume_11_2013
Personal_Resume_11_2013
 
Resume Leyla Clothier
Resume Leyla ClothierResume Leyla Clothier
Resume Leyla Clothier
 
Material movement in a manufacturing plant
Material movement in a manufacturing plantMaterial movement in a manufacturing plant
Material movement in a manufacturing plant
 
Jason.Haraway, PE
Jason.Haraway, PEJason.Haraway, PE
Jason.Haraway, PE
 
Saeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer UtilitiesSaeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer Utilities
 
RyanMoyer_FinalResume
RyanMoyer_FinalResumeRyanMoyer_FinalResume
RyanMoyer_FinalResume
 
Creative Install for Data Center - Charlotte, North Carolina
Creative Install for Data Center - Charlotte, North CarolinaCreative Install for Data Center - Charlotte, North Carolina
Creative Install for Data Center - Charlotte, North Carolina
 
Hariprasad K V R
Hariprasad K V RHariprasad K V R
Hariprasad K V R
 
Roberto Guevara-CV
Roberto Guevara-CVRoberto Guevara-CV
Roberto Guevara-CV
 
Saeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updatedSaeidi-Abbas-Resume April 2015-updated
Saeidi-Abbas-Resume April 2015-updated
 
2013 CIP executive summary 131204
2013 CIP executive summary 1312042013 CIP executive summary 131204
2013 CIP executive summary 131204
 
RyanMoyer_FinalResume
RyanMoyer_FinalResumeRyanMoyer_FinalResume
RyanMoyer_FinalResume
 
Resume-ParanthamanKrishnasamy
Resume-ParanthamanKrishnasamyResume-ParanthamanKrishnasamy
Resume-ParanthamanKrishnasamy
 

En vedette

En vedette (6)

Resume 2013 g dsm
Resume 2013 g dsmResume 2013 g dsm
Resume 2013 g dsm
 
Solar obstruction lighting solutions
Solar obstruction lighting solutionsSolar obstruction lighting solutions
Solar obstruction lighting solutions
 
Why Print Brochure
Why Print BrochureWhy Print Brochure
Why Print Brochure
 
Obstruction lights - Lentoestevalot
Obstruction lights - LentoestevalotObstruction lights - Lentoestevalot
Obstruction lights - Lentoestevalot
 
PM Certificate
PM CertificatePM Certificate
PM Certificate
 
Hype vs. Reality: The AI Explainer
Hype vs. Reality: The AI ExplainerHype vs. Reality: The AI Explainer
Hype vs. Reality: The AI Explainer
 

Similaire à Final TEAM SLIDE PRESENTATION (1)

Similaire à Final TEAM SLIDE PRESENTATION (1) (20)

Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15
 
CV QS AKHTAR RASUL
CV QS AKHTAR RASULCV QS AKHTAR RASUL
CV QS AKHTAR RASUL
 
Resume_Basavarajappa. L N
Resume_Basavarajappa. L NResume_Basavarajappa. L N
Resume_Basavarajappa. L N
 
Deepak Kumar_Project
Deepak Kumar_ProjectDeepak Kumar_Project
Deepak Kumar_Project
 
NARESH 3+
NARESH 3+NARESH 3+
NARESH 3+
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Scheme for the construction of water channels
Scheme for the construction of water channelsScheme for the construction of water channels
Scheme for the construction of water channels
 
Final Review
Final ReviewFinal Review
Final Review
 
Date Mandar ( CV )
Date Mandar ( CV ) Date Mandar ( CV )
Date Mandar ( CV )
 
Byron CV 2016v5
Byron CV 2016v5Byron CV 2016v5
Byron CV 2016v5
 
Resume updated
Resume updatedResume updated
Resume updated
 
RAJPAL @cv
RAJPAL @cvRAJPAL @cv
RAJPAL @cv
 
CV
CVCV
CV
 
number 1 Res 2013 Rod Taylor-2
number 1 Res 2013    Rod  Taylor-2number 1 Res 2013    Rod  Taylor-2
number 1 Res 2013 Rod Taylor-2
 
V.GUHAN-CV 01 link
V.GUHAN-CV 01 linkV.GUHAN-CV 01 link
V.GUHAN-CV 01 link
 
cv Rashid Tagelsir updated . -2016
cv Rashid Tagelsir   updated . -2016cv Rashid Tagelsir   updated . -2016
cv Rashid Tagelsir updated . -2016
 
GuruResume
GuruResumeGuruResume
GuruResume
 
Ici project brief2
Ici project brief2Ici project brief2
Ici project brief2
 
Construction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptxConstruction of Data Centre (Hemel Hempstead).pptx
Construction of Data Centre (Hemel Hempstead).pptx
 

Final TEAM SLIDE PRESENTATION (1)

  • 1. CONSTRUCTION OF GSM BASE STATION & TOWER FOR REGTel , CANADA PROJECT MANAGER SULEMAN MUHAMMED BASHIRU PROJECT TEAM MEMBERS OGUNYALE DAYO STEPHEN ABOABAAKINTUNDE ALMOTHANA DAWOUD 1
  • 3. The Need Map Of Regina, SK, Canada Source: Google Earth 3
  • 4. JUSTIFICATION OPPORTUNITY • Number of Students and Staff on Campus are in excess of 12,000 • About 7000 REGTel customers currently reside within the campus PROBLEM • Experiencing congestion at REG-03 & REGTel -08 between 10 am – 4 pm (peak utilisation) • 18% Reduction in Number Customers since January, 2015 REVENUE • Upon Completion, the project can generate $384,000 monthly ($40 x 9600 customers). • Considering running cost and administrative expenses, the payback period is expected to be two (2) years 4
  • 5. Project Objectives ● Provide competitive quality of services for existing and potential customers within the university and its environs. ● To decongest REGTel-03 site located west of University of Regina and REGTel-08 located north of University of Regina by 40% and 30% respectively. 5
  • 6. Project Objectives Contd. ● Provide opportunity to justify REGTel sales drive. Sales can be increased by at least 19 percent within the university community. ● To serve as a hub site and back up site for REGTel-03 and REGTel-08. 6
  • 7. Constraints Bulk of the tools used will be rented Storage of Materials Scheduling the arrival of materials to maximise storage space Training of Adhoc staff 7
  • 8. Assumptions Acquire licenses to build from Authorities The project was planned & should be tracked at an activity level Duration estimation was done based on availability of resources It is the responsibility of the project manager to ensure that progress is made per established plans 8
  • 9. Acceptance Criteria All cables from tower top to the shelter will be channelled through cable tray Earthing value of the site must not exceed 4.7 Ohms Steel Reinforcement must be grade 50 deformed bars and shall be covered with concrete overlay of minimum thickness of 75mm The Intensity of the Aviation warning light should not be below 10 Candela 9
  • 10. Acceptance Criteria Contd. Tower should be painted with one coat of primer and two coats of red/white enamel paint Earth/Soil compaction ratio should be maintained during backfilling The Shelter should have proper anti-static flooring and straps All edges of slabs and tower base must be bevelled at 45 degrees 10
  • 11. Project Organization Chart Executive Director {James Peters} Engineering Management & Administration Lawyers Human Resource Officer Supply & Procurement Procurement Officers Project Coordinator Project Manager 11
  • 13. Project Scope Scope Planning Design Supply of Materials Project Implementation & Control Site Testing & Commissioning Procurement 13
  • 14. High Level Requirements Site Selection  Site Survey  Site Purchase  Soil Test Civil Works  Mobilisation to site  Excavation  Reinforcement  Formwork  Casting  Tower Rigging Installation  Electrical Installation  Microwave Installation  RF Installation  Access Control  Base Station Commissioning 14
  • 15. WBS SUMMARY 1.0 Construction 1.1 Site survey & Designs 1.1.1 Site Survey & Selection 1.1.2 Soil Test 1.1.3 Design Drawings 1.2 Civil works 1.2.1 Marking Out & Measurement 1.2.2 Excavating 1.2.3 Foundation for Tower 1.2.4 Erecting Tower 1.3 Site preparations 1.3.1 Supply of Temporary Water, Shelter, Power 2.0 Installation and Testing 2.1 Electrical Installation 2.1.1 Earthing of site 2.1.2 Aviation Warning Light 15
  • 16. WBS SUMMARY Contd. 2.2 RF/ Microwave Installation 2.2.1 RF Installation 2.2.2 Microwave Instation 2.3 Acceptance Testing and Commissioning 2.3.1 Base Station Commissioning & Testing 2.3.2 Site on Air 3.0 Procurement/Supply of Materials 3.1 Procurement 3.2 Supply and Transportation of Materials 4.0 Management and Administration 4.1 Project Management 4.2 Permits 4.2.1 Building Permit 4.2.2 Frequency Reuse Permit 4.2.3 Public Safety Permit 4.3 Adhoc Staff recruitment 16
  • 17. Project Stakeholders  Project Sponsor, Executive Management  Project Team  City of Regina  Government Agencies  University of Regina Authorities  Canada Transport Civil Aviation Authority 17
  • 18. Risk Categories Technical  Nature of Soil Human Resource  Absenteeism & Sick calls  Workplace accident/hazards  Resignation External  Land litigation  Delay in Licensing, Permit Approvals  Unfavorable Weather condition. 18
  • 19. Risk Categories Cost  Inflation  Material Storage  Delay in Funding Schedule  Delay in Supply of Material 19
  • 20. Risk Assessment Matrix Risks Impact Degree of Impact Probability of Occurrence Response Plan and Risk Owner Delay in Licensing, Permit Approval • Delay the starting date. • Delay the schedule. High Medium Follow up on the licensing office to know the updates (PM & Legal) Workplace incident and Hazards Reduce skilled workers availability High Medium • Acquire PPEs • Train team on those PPEs (HSE) Inflation Increase the project budget High Low Purchase critical materials ASAP (Procure Finance) Delay in material supply Extend project schedule and budget Medium Medium Always check inventory level (Supply Chain Officer) 20
  • 21. Project Schedule Summary  Project duration is 217 days  Project Start date is 18th April 2016  Project Finish date is 14th February 2017 21
  • 22. Milestones Schedule Milestone 1 Site Survey & Design • August 22, 2016 Milestone 2 Permits & Licensing • September 14, 2016 Milestone 3 Procurement & Payment • October 12, 2016 Milestone 4 Adhoc Staff & Recruitment Milestone 5 Supply & Transportation of Materials • October 21, 2016 November 3, 2016 22
  • 23. Milestones Schedule Contd Milestone 6 Civil Works • January 2, 2017 Milestone 7 Electrical Installation • January 13, 2017 Milestone 8 RF & Microwave Installation • January 13, 2017 Milestone 9 Testing Milestone 10 Acceptance Testing & Commissionin g January 18, 2017 January 20 2017 23
  • 24. Project Summary –Cost Estimates Work Package Labour Cost ($) Material Cost ($) Site Survey & Design 79,160 32,105 Permit & Licensing 7,112 12,663.6 Site Preparation 1,120 25,760 Procurement and Payment 33,392 231,675 Adhoc Staff Recruitment 6,360 300 Supply/Transportatio n of materials 15,600 13,850 Civil Work 39,760 20,960 Electrical Installation 10,484 8,250 24
  • 25. Project Summary – Cost Estimates Contd. Work Package Labour Cost ($) Material Cost ($) RF & Microwave Installation 3,144 58,400 Testing 2,032 3,500 Site landscaping 2,820 - Acceptance Testing & Commissioning Total 1,088 - Project closing 81,680 - Total 283,752 407,463.60 25
  • 26. Project Cost Baseline BAC = $691,215.60 Cost Baseline: $793,215.60 Available Budget : $950,000 Project Cost Baseline $793,215.60 Labor Cost $283,752 Material Cost $407,463.60 Contingency Reserves $102,000 26
  • 28. Change Management Change Control Board, CCB, is chaired by Project Sponsor, James Peters Any change to project scope, cost or schedule must meet CCB’s approval 28
  • 29. Change Management Contd. Change request will be logged in the change control register The request should be tracked through to completion whether approved or not 29
  • 30. Change Management Contd. If a change is approved by the CCB, the project manager will update and re-baseline project documentation as necessary Changes are communicated to the team and stakeholders 30
  • 31. Change Management Steps Identify the Need for Change • Any Stakeholder Log in the change Register • Project Manager Evaluate the Change • Project Manager • Requester • Project Team 31
  • 32. Change Management Steps Contd. Submit Change Request to, CCB • Project Manager CCB Approval • CCB • Project Manager Implement Change • Project Manager 32
  • 33. Lessons Learnt Withdrawal of Team Member Adopt Progressive Elaboration Delegation of Duties Regular Engagement of Stakeholders 33
  • 34. Appendix  Analysis of Schedule for the project  Contact: sulemamu@uregina.ca 34
  • 35. Thanks For Your Attention 35