Construction of Data Centre (Hemel Hempstead).pptx
Final TEAM SLIDE PRESENTATION (1)
1. CONSTRUCTION OF GSM BASE STATION
& TOWER FOR REGTel , CANADA
PROJECT MANAGER
SULEMAN MUHAMMED BASHIRU
PROJECT TEAM MEMBERS
OGUNYALE DAYO STEPHEN
ABOABAAKINTUNDE
ALMOTHANA DAWOUD
1
4. JUSTIFICATION
OPPORTUNITY
• Number of Students
and Staff on Campus
are in excess of
12,000
• About 7000 REGTel
customers currently
reside within the
campus
PROBLEM
• Experiencing
congestion at REG-03 &
REGTel -08 between 10
am – 4 pm (peak
utilisation)
• 18% Reduction in
Number Customers
since January, 2015
REVENUE
• Upon Completion, the
project can generate
$384,000 monthly ($40 x
9600 customers).
• Considering running cost
and administrative
expenses, the payback
period is expected to be two
(2) years
4
5. Project Objectives
● Provide competitive quality of services for
existing and potential customers within the
university and its environs.
● To decongest REGTel-03 site located west of
University of Regina and REGTel-08 located north of
University of Regina by 40% and 30% respectively.
5
6. Project Objectives Contd.
● Provide opportunity to justify REGTel sales drive.
Sales can be increased by at least 19 percent within
the university community.
● To serve as a hub site and back up site for REGTel-03
and REGTel-08.
6
7. Constraints
Bulk of the tools used will be rented
Storage of Materials
Scheduling the arrival of materials to maximise storage space
Training of Adhoc staff
7
8. Assumptions
Acquire licenses to build from Authorities
The project was planned & should be tracked at an activity
level
Duration estimation was done based on availability of
resources
It is the responsibility of the project manager to ensure that
progress is made per established plans
8
9. Acceptance Criteria
All cables from tower top to the shelter will be channelled through
cable tray
Earthing value of the site must not exceed 4.7 Ohms
Steel Reinforcement must be grade 50 deformed bars and
shall be covered with concrete overlay of minimum thickness of
75mm
The Intensity of the Aviation warning light should not be below 10
Candela
9
10. Acceptance Criteria Contd.
Tower should be painted with one coat of primer and two coats of
red/white enamel paint
Earth/Soil compaction ratio should be maintained during backfilling
The Shelter should have proper anti-static flooring and straps
All edges of slabs and tower base must be bevelled at 45 degrees
10
14. High Level Requirements
Site
Selection
Site Survey
Site Purchase
Soil Test
Civil Works
Mobilisation to
site
Excavation
Reinforcement
Formwork
Casting
Tower Rigging
Installation
Electrical Installation
Microwave Installation
RF Installation
Access Control
Base Station
Commissioning
14
15. WBS SUMMARY
1.0 Construction
1.1 Site survey & Designs
1.1.1 Site Survey & Selection
1.1.2 Soil Test
1.1.3 Design Drawings
1.2 Civil works
1.2.1 Marking Out & Measurement
1.2.2 Excavating
1.2.3 Foundation for Tower
1.2.4 Erecting Tower
1.3 Site preparations
1.3.1 Supply of Temporary Water, Shelter, Power
2.0 Installation and Testing
2.1 Electrical Installation
2.1.1 Earthing of site
2.1.2 Aviation Warning Light
15
16. WBS SUMMARY Contd.
2.2 RF/ Microwave Installation
2.2.1 RF Installation
2.2.2 Microwave Instation
2.3 Acceptance Testing and Commissioning
2.3.1 Base Station Commissioning & Testing
2.3.2 Site on Air
3.0 Procurement/Supply of Materials
3.1 Procurement
3.2 Supply and Transportation of Materials
4.0 Management and Administration
4.1 Project Management
4.2 Permits
4.2.1 Building Permit
4.2.2 Frequency Reuse Permit
4.2.3 Public Safety Permit
4.3 Adhoc Staff recruitment
16
17. Project Stakeholders
Project Sponsor, Executive Management
Project Team
City of Regina
Government Agencies
University of Regina Authorities
Canada Transport Civil Aviation Authority
17
18. Risk Categories
Technical
Nature of Soil
Human Resource
Absenteeism &
Sick calls
Workplace
accident/hazards
Resignation
External
Land litigation
Delay in
Licensing, Permit
Approvals
Unfavorable
Weather
condition.
18
20. Risk Assessment Matrix
Risks Impact Degree of
Impact
Probability of
Occurrence
Response
Plan and Risk
Owner
Delay in
Licensing, Permit
Approval
• Delay the
starting date.
• Delay the
schedule.
High Medium Follow up on the
licensing office to
know the updates
(PM & Legal)
Workplace
incident and
Hazards
Reduce skilled
workers
availability
High Medium • Acquire PPEs
• Train team on
those PPEs
(HSE)
Inflation Increase the
project budget
High Low Purchase critical
materials ASAP
(Procure Finance)
Delay in material
supply
Extend project
schedule and
budget
Medium Medium Always check
inventory level
(Supply Chain
Officer)
20
21. Project Schedule Summary
Project duration is 217 days
Project Start date is 18th April 2016
Project Finish date is 14th February
2017
21
22. Milestones Schedule
Milestone 1
Site Survey
& Design
• August 22,
2016
Milestone 2
Permits &
Licensing
• September 14,
2016
Milestone 3
Procurement
& Payment
• October 12,
2016
Milestone 4
Adhoc Staff &
Recruitment
Milestone 5
Supply &
Transportation
of Materials
• October
21, 2016
November
3, 2016
22
23. Milestones Schedule Contd
Milestone 6
Civil Works
• January 2,
2017
Milestone 7
Electrical
Installation
• January 13,
2017
Milestone 8
RF &
Microwave
Installation
• January
13, 2017
Milestone 9
Testing
Milestone 10
Acceptance
Testing &
Commissionin
g
January 18,
2017
January
20 2017
23
24. Project Summary –Cost Estimates
Work Package Labour Cost ($) Material Cost ($)
Site Survey & Design 79,160 32,105
Permit & Licensing 7,112 12,663.6
Site Preparation 1,120 25,760
Procurement and
Payment
33,392 231,675
Adhoc Staff
Recruitment
6,360 300
Supply/Transportatio
n of materials
15,600 13,850
Civil Work 39,760 20,960
Electrical Installation 10,484 8,250
24
25. Project Summary – Cost
Estimates Contd.
Work Package Labour Cost ($) Material Cost ($)
RF & Microwave
Installation
3,144 58,400
Testing 2,032 3,500
Site landscaping 2,820 -
Acceptance Testing &
Commissioning Total
1,088 -
Project closing 81,680 -
Total 283,752 407,463.60
25
30. Change
Management
Contd.
If a change is approved
by the CCB, the project
manager will update and
re-baseline project
documentation as
necessary
Changes are
communicated to the
team and stakeholders
30
31. Change
Management Steps
Identify the
Need for
Change
• Any Stakeholder
Log in the
change
Register
• Project Manager
Evaluate
the
Change
• Project Manager
• Requester
• Project Team
31