SlideShare une entreprise Scribd logo
1  sur  9
Télécharger pour lire hors ligne
DESIGN AND BUILD
CONTRACTS
KEY POINTS TO CONSIDER FOR D&B CONTRACTOR & THEN PLANT
OPERATOR FOR E.G. MUNICIPAL/INDUSTRIAL CUSTOMERS
1. Liability for Design
• Employer’s Liability
• Scope:
• Amendments;
• Defective scope/design;
• Meetings to resolve defects.
• Contractor’s Liability
• Design & Build liability – with the Contractor (“DBC”), as DBC’s scope is Design +
Build (and may include the O&M phase too, e.g. availability/other obligations in a
related O&M contract);
• Defects identification and rectification measures – identification, agree with
Employer’s Representative, rectification process;
• Defect rectification certification – notifications from relevant parties - records;
• Sub-contractor’s liability – flow-down of main D&B contract provisions to sub-
contractors (duty of care deeds/collateral warranties/third party deeds).
2. Variations – Contractor-led (“CL”) versus
Employer-led (“EL”). Contractor (“C”);
Employer “E”).
• Alteration/modification of design – CL / EL:
A. Quality/quantity of work – C generally informing E if variation from originally contracted design suite requiring
additional spend according to contracted scope to increase/decrease spend according to build;
B. Imposition/alteration affecting access to works/time/method of work/order of work;
• Contractor’s right to reasonably object arising in B-instances if outwith originally agreed works-schedules appending
to original contracts, thus requiring a formal deed of variation agreeing scope of additional works, time + cost.
• Variations –
• if from E, no delays, no delay-damages: Time + Cost to be agreed;
• if due to C’s original design incomplete/fault not due to E, then delay + damages (overall program delay) + time + C
and E costs to consider (any sub-C/consultant costs) – {Scope for C to argue E’s original brief was incomplete may be
limited if 2-stage D&B, and if 1-stage D&B, incumbent on C’s design team to hold as many design briefings as
possible to get the scope precisely agreed down to as granular level as possible};
• if relevant teams on DBC project 1 expected on DBC project 2 or 3 at certain time, then this may be factored into
consideration as consequential loss/loss of anticipated future business or loss due to delay in start-up on DBC
project 2 or 3 due to E related-delay on DBC project 1 – N.B. delay in start-up insurance possible however, the excess
on any claim negotiable point re: payment by E if they are responsible for variation not C (DBC) although there
lawyers may seek to exclude this as consequential loss it is worth considering if a real possibility for DBC given
experience and examples capable of being evidenced.
3. Payment (1/2).
• Forms of award for DBC can include:
• Agreed lump-sum (one payment)/
• target-cost (share the pain or gain) with or without bill of quantities/
• cost reimbursable (actual costs of works plus additional fee)/
• measurement contracts (design can be ascertained but quantities unknown/uncertain without
further analysis): can be 2 stage D&B to allow DBC to be appointed, then second stage prior Works
Commencement, further analysis to fix price.
• Pay less/withholding payment notices under the Housing Grants Construction and Regeneration etc.
Act 1996 (as amended) (“Construction Act”).
• Pay when paid no longer competent as “outlawed” by the Construction Act.
• Dispute resolution processes for payment disagreements (e.g. negotiation by Chief Representatives ->
negotiation -> Expert Determination -> Adjudication -> Arbitration (/Technology and Construction
Court litigation).
• Advance payment from Es to DBC backed by an advance payment bond/not, reimbursable advanced
payment/not.
3. Payment (2/2).
• Interim payments.
• Security mechanisms – {“££” - relatively more expensive to put in place; “£” – a cost but less than ££}
• Retention amount withheld on payments from Es to DBC per invoice (flow-down mechanism into DBC-Subcontractor
sub-contracts) - £ (can be drip-repayment e.g. post date of PC, repaid in %-amounts of an agreed overall larger
retention sum withheld on Completion Date);
• retention bonds - ££;
• (performance-related) Liquidated and Ascertained Damages (must be a genuine pre-estimate of loss so formula for
calculation to show some method to calculate LADs in the contract, usual) – [£];
• performance on-demand bonds (call on the terms of the bond relating to failed performance under the relevant
contract/security backed by suitably well credit-rated bank/insurance company) - ££;
• parent company guarantee – if Parent-Co for DBC happy to grant this from a group-company that is ring-fenced
contractually and if the scope of the PCG limited to set amounts, could be a good option – low (time and resource to
produce)/no £, but, if group-policy not to provide PCGs, then a form .
• Collateral warranties between E and any DBC sub-contractor, and DBC with any sub-contractor-sub-
contractor/consultant (ACE/RIBA consultant appointments/MF Suite Appointments/FIDIC)
• Construction Industry Scheme tax rules – any sub-contractor’s must register under these rules with Her
Majesty’s Revenue and Customs (if in the UK/check local jurisdiction for any equivalent scheme) to have 20%
deducted from payments by DBC to them (unless DBC Accounts can verify with HMRC that a relevant sub-
contractor is not registered, whereupon 30% may be deducted from a relevant payment under the CIS
rules). This applies to businesses averaging a spend of £1m/more per year.
4. Practical Completion
• Practical Completion
• Independent Technical Assessment for DBC (“ITA”);
• Employer’s Agent monitoring works for DBC and providing ITA;
• Certifying works as complete (commissioning & performance testing ->
acceptance & final certificate);
• Snag List – i.e. items that are less than a sum of money e.g. £1000 to
complete but not more than £15,000-£20,000 that can be rectified in e.g. 6
weeks;
• Warranty Period insurance;
• Handover list of documents, HSA file, designs, drawings, O&M user manual,
training for O&M staff for DBC sub-contractor group-co (if not the same
company as provided the D&B works).
5. DBC Patent/intellectual property
• Restricted non-assignable licensing of certain DBC-IP conveyed with
the built plant to ultimate-Employer/customer (“Purchaser”).
• Breaches/infringement of DBC-IP to be sanctioned heavily in relevant
clauses on DBC-IP.
• DBC-IP to be informed of any IP-infringement claim and to be able to
manage any such claim with relevant Purchaser’s in-house legal
team/external counsel.
• Purchaser to pay for fees, royalties or other charges under the term of
operation and use of any built plant/DBC-works: insofar as not
already included in the overall Contract Price.
6. Ways to Limit DBC-liability
• Health & Safety:
• HSA co-ordinator, manual and monitoring throughout DBO.
• Spot inspections/audits from DBC base-staff on relevant projects.
• Construction Design Management regulations:
• CDM Co-ordinator to be appointed and to manage CDM construction and design obligations with staff during D&B phase, and to hand over manual and documents to
O&M on date of final acceptance of plant/date of practical completion of civil works.
• Limitation of liability clause: e.g. for consequential losses. N.B. cannot limit liability under English law for death or personal injury caused by negligence (test for professional
negligence claim (“PNC”) in law: existence in law of a duty of care; behaviour that falls below the standard of care imposed by law; causal connection between the defendant’s
conduct and the damage; and, damage falling within the scope of the duty; PNC in tort: (a) foreseeability: was it reasonably foreseeable that the claimant would suffer the kind
of damage which occurred; (2) proximity: was there sufficient proximity between the parties; (3) was it was just and reasonable that the defendant should owe a duty of care of
the scope alleged), or for fraudulent misrepresentation (there must be a representation, which is false, the defendant knew that the representation was false or was reckless as
to whether it was true, the defendant intended that the claimant act in reliance on the representation, and the claimant relied on the representation to its detriment).
• Insurances:
• up to date, comprehensive, regularly checked (in main contractor-co, in sub-contractors and any consultants, and with Employer/purchaser).
• Termination due to Employer’s fault/Contractor’s fault:
• to be tightly drafted, e.g. for material breach, direct/indirect change of ownership, or for a insolvency-related event.
• Suspension for non-payment: if E late in paying against a key performance indicator/milestone date, then DBC should have the ability to suspend works without liability for delay
damages/non-performance liquidated and ascertained damages.
• Set-off: DBC able to set off any damages claims for delay/performance if E responsible in any objectively verifiable and capable of being evidenced way – best to get independent
assessment report.
• Site conditions: full due diligence (e.g. geotechnical surveys) to be carried out prior to works-commencement and to be either at E or C risk (if at C risk, then prior to entering into
contract, thorough analysis recommended, and cost to rectify site e.g. asbestosised waste etc. to be factored into pricing).
• Employment: ensure that if any employees to be engaged that relevant employment law considerations factored into consideration, including EU Working Time Directive, TUPE,
or other contract/legislative requirements in collaboration with DBC-HR.
• Change Control provisions: if third party investors, and if any “step-in” provisions drafted into a relevant contract, ensure that work completed by DBC up to any Change-Over
Date, if a relevant change-control trigger-event arises, that is capable of being certified as complete, is paid for up to and including the Change-Over Date.
ANY QUESTIONS? SEND AN EMAIL.
Produced by:
Bhalindra Bath
Email: bhalindra.bath@mybusinesscounsel.com
Date: 26 March, 2015

Contenu connexe

Tendances

Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCT
Julian Swindell
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
AMILA GAYAN
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 

Tendances (20)

FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Fidic
FidicFidic
Fidic
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Construction contract
Construction contract Construction contract
Construction contract
 
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.pptDisputes and Claims in Engineering Contracts - 18.07.07.ppt
Disputes and Claims in Engineering Contracts - 18.07.07.ppt
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Building contracts and the JCT
Building contracts and the JCTBuilding contracts and the JCT
Building contracts and the JCT
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
FIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdfFIDIC Red Book (PEC 2019).pdf
FIDIC Red Book (PEC 2019).pdf
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
 
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBETalk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 

En vedette

FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
Adrias TAN
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
Adrias TAN
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 

En vedette (12)

Presentation_Public Procurement in International Construction and Infrastruct...
Presentation_Public Procurement in International Construction and Infrastruct...Presentation_Public Procurement in International Construction and Infrastruct...
Presentation_Public Procurement in International Construction and Infrastruct...
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Contract Administrators Treading The Thin Blue Line
Contract Administrators   Treading The Thin Blue LineContract Administrators   Treading The Thin Blue Line
Contract Administrators Treading The Thin Blue Line
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
Commentary on fidic iv clauses
Commentary on fidic iv clausesCommentary on fidic iv clauses
Commentary on fidic iv clauses
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
 
FIDIC & Dispute Boards
FIDIC & Dispute BoardsFIDIC & Dispute Boards
FIDIC & Dispute Boards
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 

Similaire à Design & Build contracts - key points for a main contractor with technology also providing the O&M.

Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
Maatla Moadi
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
Melvin Lim
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlow
Jeff Dixon
 

Similaire à Design & Build contracts - key points for a main contractor with technology also providing the O&M. (20)

Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
How to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and DevelopersHow to Build Successful Projects: A Guide for Owners and Developers
How to Build Successful Projects: A Guide for Owners and Developers
 
Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)Seminar Presentation Slides (Chapter 2)
Seminar Presentation Slides (Chapter 2)
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
01.15+Audit-Success.pdf
01.15+Audit-Success.pdf01.15+Audit-Success.pdf
01.15+Audit-Success.pdf
 
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendmentsKey terms to consider when negotiating cm at-risk agreements + gmp amendments
Key terms to consider when negotiating cm at-risk agreements + gmp amendments
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlow
 

Plus de Bhalindra Bath - projects & M&A law

Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Bhalindra Bath - projects & M&A law
 

Plus de Bhalindra Bath - projects & M&A law (12)

The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
 
Summary
SummarySummary
Summary
 
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT - 03.2015
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT -  03.2015MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT -  03.2015
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT - 03.2015
 
MBC W2F W2E BIOFUEL BIOMASS AD - 03.2015
MBC W2F W2E BIOFUEL BIOMASS AD -  03.2015MBC W2F W2E BIOFUEL BIOMASS AD -  03.2015
MBC W2F W2E BIOFUEL BIOMASS AD - 03.2015
 
MBC SOLAR
MBC SOLAR MBC SOLAR
MBC SOLAR
 
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
 
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
DECC decision on ROCs CfDs Grace Periods Grandfathering of ROCs and degressio...
 
URN 14D 328 - applying for a Contract for Difference this October 2014 under ...
URN 14D 328 - applying for a Contract for Difference this October 2014 under ...URN 14D 328 - applying for a Contract for Difference this October 2014 under ...
URN 14D 328 - applying for a Contract for Difference this October 2014 under ...
 
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
 
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
 
Potential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passedPotential next steps for developers if URD 14D/114 is passed
Potential next steps for developers if URD 14D/114 is passed
 
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
Impact of CfDs for 5+MW solar installations in the UK post 1.4.15 - URN 14D/114
 

Dernier

一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
Airst S
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
Airst S
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
JosephCanama
 
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
ShashankKumar441258
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
RRR Chambers
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
A AA
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
bd2c5966a56d
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
mahikaanand16
 

Dernier (20)

一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
一比一原版(CQU毕业证书)中央昆士兰大学毕业证如何办理
 
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam TakersPhilippine FIRE CODE REVIEWER for Architecture Board Exam Takers
Philippine FIRE CODE REVIEWER for Architecture Board Exam Takers
 
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdfNavigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
Navigating the Legal and Ethical Landscape of Blockchain Investigation.pdf
 
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
 
一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理一比一原版赫尔大学毕业证如何办理
一比一原版赫尔大学毕业证如何办理
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
 
Code_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.pptCode_Ethics of_Mechanical_Engineering.ppt
Code_Ethics of_Mechanical_Engineering.ppt
 
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
6th sem cpc notes for 6th semester students samjhe. Padhlo bhai
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...
 
Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdf
 
3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
 

Design & Build contracts - key points for a main contractor with technology also providing the O&M.

  • 1. DESIGN AND BUILD CONTRACTS KEY POINTS TO CONSIDER FOR D&B CONTRACTOR & THEN PLANT OPERATOR FOR E.G. MUNICIPAL/INDUSTRIAL CUSTOMERS
  • 2. 1. Liability for Design • Employer’s Liability • Scope: • Amendments; • Defective scope/design; • Meetings to resolve defects. • Contractor’s Liability • Design & Build liability – with the Contractor (“DBC”), as DBC’s scope is Design + Build (and may include the O&M phase too, e.g. availability/other obligations in a related O&M contract); • Defects identification and rectification measures – identification, agree with Employer’s Representative, rectification process; • Defect rectification certification – notifications from relevant parties - records; • Sub-contractor’s liability – flow-down of main D&B contract provisions to sub- contractors (duty of care deeds/collateral warranties/third party deeds).
  • 3. 2. Variations – Contractor-led (“CL”) versus Employer-led (“EL”). Contractor (“C”); Employer “E”). • Alteration/modification of design – CL / EL: A. Quality/quantity of work – C generally informing E if variation from originally contracted design suite requiring additional spend according to contracted scope to increase/decrease spend according to build; B. Imposition/alteration affecting access to works/time/method of work/order of work; • Contractor’s right to reasonably object arising in B-instances if outwith originally agreed works-schedules appending to original contracts, thus requiring a formal deed of variation agreeing scope of additional works, time + cost. • Variations – • if from E, no delays, no delay-damages: Time + Cost to be agreed; • if due to C’s original design incomplete/fault not due to E, then delay + damages (overall program delay) + time + C and E costs to consider (any sub-C/consultant costs) – {Scope for C to argue E’s original brief was incomplete may be limited if 2-stage D&B, and if 1-stage D&B, incumbent on C’s design team to hold as many design briefings as possible to get the scope precisely agreed down to as granular level as possible}; • if relevant teams on DBC project 1 expected on DBC project 2 or 3 at certain time, then this may be factored into consideration as consequential loss/loss of anticipated future business or loss due to delay in start-up on DBC project 2 or 3 due to E related-delay on DBC project 1 – N.B. delay in start-up insurance possible however, the excess on any claim negotiable point re: payment by E if they are responsible for variation not C (DBC) although there lawyers may seek to exclude this as consequential loss it is worth considering if a real possibility for DBC given experience and examples capable of being evidenced.
  • 4. 3. Payment (1/2). • Forms of award for DBC can include: • Agreed lump-sum (one payment)/ • target-cost (share the pain or gain) with or without bill of quantities/ • cost reimbursable (actual costs of works plus additional fee)/ • measurement contracts (design can be ascertained but quantities unknown/uncertain without further analysis): can be 2 stage D&B to allow DBC to be appointed, then second stage prior Works Commencement, further analysis to fix price. • Pay less/withholding payment notices under the Housing Grants Construction and Regeneration etc. Act 1996 (as amended) (“Construction Act”). • Pay when paid no longer competent as “outlawed” by the Construction Act. • Dispute resolution processes for payment disagreements (e.g. negotiation by Chief Representatives -> negotiation -> Expert Determination -> Adjudication -> Arbitration (/Technology and Construction Court litigation). • Advance payment from Es to DBC backed by an advance payment bond/not, reimbursable advanced payment/not.
  • 5. 3. Payment (2/2). • Interim payments. • Security mechanisms – {“££” - relatively more expensive to put in place; “£” – a cost but less than ££} • Retention amount withheld on payments from Es to DBC per invoice (flow-down mechanism into DBC-Subcontractor sub-contracts) - £ (can be drip-repayment e.g. post date of PC, repaid in %-amounts of an agreed overall larger retention sum withheld on Completion Date); • retention bonds - ££; • (performance-related) Liquidated and Ascertained Damages (must be a genuine pre-estimate of loss so formula for calculation to show some method to calculate LADs in the contract, usual) – [£]; • performance on-demand bonds (call on the terms of the bond relating to failed performance under the relevant contract/security backed by suitably well credit-rated bank/insurance company) - ££; • parent company guarantee – if Parent-Co for DBC happy to grant this from a group-company that is ring-fenced contractually and if the scope of the PCG limited to set amounts, could be a good option – low (time and resource to produce)/no £, but, if group-policy not to provide PCGs, then a form . • Collateral warranties between E and any DBC sub-contractor, and DBC with any sub-contractor-sub- contractor/consultant (ACE/RIBA consultant appointments/MF Suite Appointments/FIDIC) • Construction Industry Scheme tax rules – any sub-contractor’s must register under these rules with Her Majesty’s Revenue and Customs (if in the UK/check local jurisdiction for any equivalent scheme) to have 20% deducted from payments by DBC to them (unless DBC Accounts can verify with HMRC that a relevant sub- contractor is not registered, whereupon 30% may be deducted from a relevant payment under the CIS rules). This applies to businesses averaging a spend of £1m/more per year.
  • 6. 4. Practical Completion • Practical Completion • Independent Technical Assessment for DBC (“ITA”); • Employer’s Agent monitoring works for DBC and providing ITA; • Certifying works as complete (commissioning & performance testing -> acceptance & final certificate); • Snag List – i.e. items that are less than a sum of money e.g. £1000 to complete but not more than £15,000-£20,000 that can be rectified in e.g. 6 weeks; • Warranty Period insurance; • Handover list of documents, HSA file, designs, drawings, O&M user manual, training for O&M staff for DBC sub-contractor group-co (if not the same company as provided the D&B works).
  • 7. 5. DBC Patent/intellectual property • Restricted non-assignable licensing of certain DBC-IP conveyed with the built plant to ultimate-Employer/customer (“Purchaser”). • Breaches/infringement of DBC-IP to be sanctioned heavily in relevant clauses on DBC-IP. • DBC-IP to be informed of any IP-infringement claim and to be able to manage any such claim with relevant Purchaser’s in-house legal team/external counsel. • Purchaser to pay for fees, royalties or other charges under the term of operation and use of any built plant/DBC-works: insofar as not already included in the overall Contract Price.
  • 8. 6. Ways to Limit DBC-liability • Health & Safety: • HSA co-ordinator, manual and monitoring throughout DBO. • Spot inspections/audits from DBC base-staff on relevant projects. • Construction Design Management regulations: • CDM Co-ordinator to be appointed and to manage CDM construction and design obligations with staff during D&B phase, and to hand over manual and documents to O&M on date of final acceptance of plant/date of practical completion of civil works. • Limitation of liability clause: e.g. for consequential losses. N.B. cannot limit liability under English law for death or personal injury caused by negligence (test for professional negligence claim (“PNC”) in law: existence in law of a duty of care; behaviour that falls below the standard of care imposed by law; causal connection between the defendant’s conduct and the damage; and, damage falling within the scope of the duty; PNC in tort: (a) foreseeability: was it reasonably foreseeable that the claimant would suffer the kind of damage which occurred; (2) proximity: was there sufficient proximity between the parties; (3) was it was just and reasonable that the defendant should owe a duty of care of the scope alleged), or for fraudulent misrepresentation (there must be a representation, which is false, the defendant knew that the representation was false or was reckless as to whether it was true, the defendant intended that the claimant act in reliance on the representation, and the claimant relied on the representation to its detriment). • Insurances: • up to date, comprehensive, regularly checked (in main contractor-co, in sub-contractors and any consultants, and with Employer/purchaser). • Termination due to Employer’s fault/Contractor’s fault: • to be tightly drafted, e.g. for material breach, direct/indirect change of ownership, or for a insolvency-related event. • Suspension for non-payment: if E late in paying against a key performance indicator/milestone date, then DBC should have the ability to suspend works without liability for delay damages/non-performance liquidated and ascertained damages. • Set-off: DBC able to set off any damages claims for delay/performance if E responsible in any objectively verifiable and capable of being evidenced way – best to get independent assessment report. • Site conditions: full due diligence (e.g. geotechnical surveys) to be carried out prior to works-commencement and to be either at E or C risk (if at C risk, then prior to entering into contract, thorough analysis recommended, and cost to rectify site e.g. asbestosised waste etc. to be factored into pricing). • Employment: ensure that if any employees to be engaged that relevant employment law considerations factored into consideration, including EU Working Time Directive, TUPE, or other contract/legislative requirements in collaboration with DBC-HR. • Change Control provisions: if third party investors, and if any “step-in” provisions drafted into a relevant contract, ensure that work completed by DBC up to any Change-Over Date, if a relevant change-control trigger-event arises, that is capable of being certified as complete, is paid for up to and including the Change-Over Date.
  • 9. ANY QUESTIONS? SEND AN EMAIL. Produced by: Bhalindra Bath Email: bhalindra.bath@mybusinesscounsel.com Date: 26 March, 2015