SlideShare une entreprise Scribd logo
1  sur  5
Télécharger pour lire hors ligne
1 | P a g e
Applying for a Contract for Difference this October
2014: the “Allocation Framework” - DECC paper
URN 14D/328 (published 1 September 2014)
General disclaimer: the following constitutes the written view of the author and in no way constitutes actual legal advice
or a legal opinion and so no reliance may be placed upon the content hereinafter contained by any reader of this document
in any way whatsoever. In the event that legal advice or opinion is sought, please contact the author of this opinion at
the contact details below. The view below is expressly confined to matters as they stand at 6 September 2014, under the
laws of England and Wales and in accordance with current publications from Her Majesty’s Department for the Energy
and Climate Change as published at https://www.gov.uk/government/publications/electricity-market-reform-contracts-
for-difference on 1 September, 2014.
Earlier this year we reported on the consultation paper URN 14D/1141
and the proposal from the
UK government to change the subsidy regime from renewable obligation certificates (ROCs) to
contracts for difference (CfDs) for large >5MW projects for solar as put simply the Levy Control
Framework does not have sufficient budget to allow for ROCs to instead phase out in 2017 as was
previously mooted by the British Government. On 1 September 2014, DECC uploaded a paper
(URN 14D/328) which outlines in greater detail the rules for the process for CfD allocation2
(“Rules”), or the “Allocation Framework” for the first round of CfDs to be issued by OfGEM with
the CfD Counterparty following the application process commencement for the 1st
round of CfD
applications on 14 October 2014.
In essence the Allocation Framework affirms that for AD, Hydro, onshore wind or solar, a
generating unit (“CfD Unit”) must be larger than 5MW for an application for a CfD to be made.
Facilities that are either already accredited for the renewable heat incentive or that are energy
from waste with CHP related3
, are expressly excluded from the process.
For each prospective project, the Allocation Framework and the 2014 CfD Contracts for Difference
(Allocation) Regulations 20144
contain the basic information that a developer will need to provide
when applying for a CfD for their project to ensure that it is a Qualifying Application5
, namely:
(a) the application should show that the relevant eligibility criteria have been satisfied, and if
there are any additional Secretary of State information required then this has been
provided (see Schedule 4 in the Allocation Framework and below in this article, – i.e. a
supply chain statement; applicable planning consent; confirmation on connection
agreement or equivalent; confirmation of non-receipt of other UK Government
1
http://www.mybusinesscounsel.com/legal-updates/page/2/
2
Contract for Difference Allocation Framework 2014 (URN 14D/328), the “Allocation Framework”:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/349370/Final_Allocation_Framew
ork.pdf
3
As defined in The Contracts for Difference (Definition of Eligible Generator) Regulations 2014:
http://www.legislation.gov.uk/uksi/2014/2010/contents/made
4
The Contracts for Difference (Allocation) Regulations 2014:
http://www.legislation.gov.uk/ukdsi/2014/9780111116777/contents
5
Regulation 17 of the draft 2014 Contract for Difference Allocation Regulations:
http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/17
2 | P a g e
subsidies for the same facility; evidence of incorporation of the generator-vehicle;
confirmation of the target commissioning window);
(b) the national system operator will determine whether an applicant is a qualifying applicant
based on their satisfaction of the criteria for application for a CfD (so regulation 17 of the
draft 2014 Allocation Regulations6
, and see (j) below in this article);
(c) the developer presenting a technology generating station should not be presenting a
generating station that is not supported in whole or part by another scheme or is sub-
5MW and as otherwise set out in draft regulation 14 of the 2014 Allocation Regulations7
;
(d) the generating station should have planning consent so a planning permission under
part 3 of the Town and Country Planning Act 1990 for an onshore generating station
such as a ground-mounted solar plant that is over 5MW in generating capacity;
(e) if there are conditions in the planning permission so it is a conditional planning consent,
then the applicant for the CfD should draft a planning consent discharge of planning
conditions plan to show that the planning conditions to the consent provided by e.g. a
local authority can be discharged;
(f) there must be evidence of a DNO connection offer or if it is a private system then
according to the Allocation Framework the connection agreement in place must secure at
least 75% of the initial installed capacity estimate of the CfD unit, or, where the
connection will be to 75% to a distribution system a connection agreement will be
required or evidence that the agreement is in place so that the CfD Counterparty (now
incorporated as: Low Carbon Contracts Company Limited – UK CRN 8818711) can know
the amount of metered electricity is estimated to be exported8
. If there will be partial or
no connection then, as per Regulation 25(4)9
, “…Where a partial connection applies or is
to apply to a relevant CFD unit, the applicant must provide a statement setting out how
data in respect of metering of electricity supply is to be provided to the CFD counterparty.
..”, and the CfD applicant should provide a copy of the connection agreement between
the owner of the transmission system and the generator, or a copy of the private network
use agreement between the generator and the operator of the network and a copy of the
connection agreement between the private network operator and the operator of the
transmission system10
;
(g) when applying, certain minimum sizes apply to the type of project that can obtain a CfD,
e.g. for solar it is 5MW11
;
(h) https://www.gov.uk/government/publications/electricity-market-reform-contracts-for-
difference – at this link are all of the documents that relate to completing the contract for
difference and metering agreements for an application. For the FIRST ROUND, the
Government have issued the following table:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/34820
2/The_Contracts_for_Difference__Standard_Terms__Regulations_2014_-
_CFD_Standard_Terms_Notice__29_August_2014_.pdf, which contains information on
6
Ibid.
7
http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/14
8
Rule 4 of the Allocation Framework.
9
Regulation 25 of the draft 2014 Contract for Difference Allocation Regulations:
http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/25
10
Rule 4.1 (iii) of the Allocation Framework.
11
Rule 5.1(ii) of the Allocation Framework.
3 | P a g e
e.g. the expected target commissioning window, and so it is 1 year for anaerobic digestion,
to 3 months for solar photovoltaic, as well as the total project pre-commissioning costs,
so anaerobic digestion with or without combined heat and power is £1,750,000, or, for
solar photovoltaic it is £1,000,000;
(i) Developer Asset-Co (or Developer backed by Funder – Asset-Co) supply chain
plan/development phase deliverables12
- General Project Commitments13
will need to be submitted with applications for CfDs
(including a Directors Certificate that the Generator that owns the Asset e.g.
Developer/Developer-Consortium with a funder, that the developer have financial
resources for the total project spend (‘proof of funds’), evidence that the site for the plant
is relatively unencumbered by third party property rights and where necessary
easements/other rights have been/can be obtained, and all other consents for the
installation of the PV plant have been obtained) as a part of the Project Commitments in
the CfD Agreement, together with evidence of an EPC agreement (Construction Phase)
and evidence of a framework (major kit) supply (“Material Equipment”) agreement and a
binding purchase order for the Material Equipment (so modules, inverters, frames,
switchgear). 300MW sized portfolios of solar assets being developed, require more
sophisticated responses in terms of the supply chain plan to obtain Secretary of State
approval for submission of the related application for allotment of related CfDs, and the
related guidance14
;
(j) the applicant should also be an eligible generator, in that they operate or participate in
the operation of, or intend to carry out a generating activity in relation to, an eligible
generating station, such as solar photovoltaic array that generates and supplies electricity
to the Grid15
;
12
http://www.mybusinesscounsel.com/solar-urn-14d-114-analysis-by-bhalindra-bath/
13
Annex 6 of the CfD agreement
(https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/305539/cfd_agreement.pdf
(draft CfD agreement as at April 2014): “…Delivery to the CfD Counterparty of the following:
(A) a copy of a resolution of the Generator’s board of directors (or an equivalent management committee or body) to:
(i) undertake the Project; (ii) approve the total financial commitments required to commission the
Project (the “Total Project Spend”); and (iii) approve a timetable for undertaking the Project which demonstrates that
the Facility can reasonably be expected to be commissioned no later than the Longstop Date; (B) a Directors’
Certificate certifying that: (i) the Generator has, or will have, sufficient financial resources to meet the Total Project
Spend; and (ii) any contract entered into and provided as Supporting Information pursuant to the Milestone
Requirements Notice, in the reasonable opinion of the Generator by reference to the facts and circumstances then
existing, is: (a) legal, valid and binding; and, (b) entered into with one or more counterparties who are each able to
perform their obligations under such contract; (iii) the Generator has a leasehold or freehold interest in the site
where the Facility is based (the “Facility Site”) or a contract to obtain the same; (iv) the Facility Site is not subject to
any covenants, restrictions, agreements, planning obligations, estate contracts, options, rights of way or other
encumbrances which materially inhibit the use of the Facility Site for the purposes of the Project; (v) there are
available to the Facility Site such rights, easements and services as are necessary to undertake the Project and
operate the Facility; (vi) the Generator has identified all necessary consents and planning permissions to undertake
the Project (the “Necessary Consents”); and (vii) there is a credible strategy in place to obtain the Necessary Consents
and the Necessary Consents are not subject to any condition for which there does not exist a plan approved by the
Generator’s board of directors to satisfy that condition, such that the Generator is not awareof any necessary
consents and planning permissions which cannot be obtained or complied with, ((iii) to (vii), together the “Facility
Requirements”); (C) Supporting Information evidencing (i) that the Generator has, or will have, sufficient financial
resources to meet the Total Project Spend and (ii) the Facility Requirements. ..”
14
https://www.gov.uk/government/publications/supply-chain-guidance (updated 1 August 2014)
15
Section 3 of The Contracts for Difference (Definition of Eligible Generator) Regulations 2014: ibid. at FN3 above.
4 | P a g e
(k) Credit Support Documents – “Collateral”
- this is referred to as “collateral” in the terms and conditions published in April and will
not include parent company guarantees, and will include a letter of credit or equivalent
on-demand liquid form of guaranteed payment security that, e.g. in the event that the
issuer loses their credit rating or folds, can be replaced within five working days with an
equivalent form of security16
- so an applicant will most probably have to provide evidence
that a standby letter of credit, on-demand bond or guarantee banked probably by a well-
rated bank or insurance company is available to secure the obligations of the generator
under the contract for difference. Despite a request for a similar form of security to be
provided by the CfD Counterparty, the counter from DECC was that the provisions in the
legislation including the ability for the Secretary of State to replace the insolvency remote
CfD Counterparty in the event of default17
(limited/no measure to terminate for CfD
Counterparty default under the terms and conditions) were sufficient, without the need
for any additional form of security.
Allocation process
 The review date for applications, called the Non-Qualification Review Request Date is 18
November 2014. Appeals against any rejected applications is 9 December 2014. The start
date for allocation of CfDs will be 22 December 2014 if no appeals, but if there are any
appeals then the allocation start date will be 23 January 2015 (Rule 8 of the Allocation
Framework).
 In the event that there is an assessment from OfGEM that there is a requirement for an
auction, then the applicants will be able to submit sealed bids18
which would include the
Applicant’s proposed Strike Price in pounds sterling that an applicant will accept for each
megawatt hour of metered output, but which, in any event must not be more than the
applicable Administrative Strike Price (e.g. for 2015/16 for solar photovoltaic this is
£120/MWh).
The applications will then be ranked and assessed according to lowest Strike Price to
highest, clearing price, cumulative value of qualifying applications, with the application
process closing when the Minimum-only cap-amount for an auction process being
reached to allow assessment and award of CfDs. A similar process will run for the Pot,
Overall Budget and Maximum only auctions.
Under Rule 18 of the Allocation Framework on “Tiebreaker Rules”, where there is a
tiebreaker-type scenario, where there are two or more Qualifying Applications with the
same strike price, then,
o the individual bids will be assessed on their own and if they would result in the
Minimum (minimum budget reserved for an allocation round as specified in a
16
Part 13 of GTAC
(https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/305536/generic_cfd_t_and_cs.pd
f).
17https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/307060/cfd_policy_drafting_upd
ate.pdf
18
Rule 11.1 of the Allocation Framework
5 | P a g e
Budget Notice19
) or Maximum (maximum budget for an allocation round specified
in a Budget Notice20
) being exceeded, then the application will fail, or,
o if a Qualifying Application or combination of Qualifying Applications comes close
to fulfilling the Minimum or Maximum without exceeding either of them, then the
Qualifying Application that comes closest to fulfilling the Minimum or Maximum
will be deemed successful, or,
o where Qualifying Applications come equally close to fulfilling the Minimum or
Maximum without exceeding it then an electronic random assignment process will
be used, or,
o a Qualifying Application subject to a Minimum (budget) can also be determined
as a Flexible Bid21
(with such a bid being made at different Strike Prices, expressed
to the nearest whole penny, with a first Delivery Year no earlier than the Delivery
Year in the application, and a capacity no greater than in the original application
before the auction was announced22
as long as it is e.g. in the case of onshore wind
or solar, as examples, over 5MW initial capacity) and will be determined as being
successful provided it is not the same as or higher than the Strike Price of another
Applicant’s sealed bid (Rule 15.1 (viii) of the Allocation Framework) – but if not
successful will then be considered against the Pot/Overall Budget.
Similar decision making methods to determine successful applications in tie-breaker
situations as above apply to the situation where the Pot/Overall Budget (but not the
Minimum or Maximum budgets) would be exceeded, and where the Pot/Overall
budget and the Minimum or Maximum budgets would be exceeded23
.
For assistance in applying for contracts for difference, advice on and actual drafting of
appropriate legal documentation for application for a contract for difference, and advice
on the draft legislation and process, email: bhalindra.bath@mybusinesscounsel.com.
London, 6 September 2014.
19
Regulation 11(2)(a) of the draft 2014 Allocation Regulations:
http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/11
20
Regulation 11(2)(b) of the draft 2014 Allocation Regulations:
http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/11
21
A bid that meets the requirements of Rule 11.6 of the Allocation Framework.
22
Rule 11.6 of the Allocation Framework.
23
Rules 18.2-18.3 of the Allocation Framework.

Contenu connexe

Tendances

CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]
Aditi Tulpule
 
RET Review Solution
RET Review SolutionRET Review Solution
RET Review Solution
Simon Mathis
 
HYDRO_POLICY_UK_2015
HYDRO_POLICY_UK_2015HYDRO_POLICY_UK_2015
HYDRO_POLICY_UK_2015
Anil Khadka
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
Sanman Rajput
 

Tendances (18)

CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]CATOs-Opportunities-for-Onshore-Tranmission-final[1]
CATOs-Opportunities-for-Onshore-Tranmission-final[1]
 
Tariff policy of India: Salient Points
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
 
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
Notice for Energy Storage Project by Neyveli Lignite Corporation (NLC)
 
Tariff policy
Tariff policyTariff policy
Tariff policy
 
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in PunjabScheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
Scheme for Allocation of Solar Power Projects to Land Owning Farmers in Punjab
 
Draft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmersDraft scheme for allocation of solar power projects for land owning farmers
Draft scheme for allocation of solar power projects for land owning farmers
 
Rfp 250 mw fy16 17
Rfp 250 mw fy16 17Rfp 250 mw fy16 17
Rfp 250 mw fy16 17
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Transnational Trade of Electricity
Transnational Trade of ElectricityTransnational Trade of Electricity
Transnational Trade of Electricity
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Forecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling forForecasting, scheduling and im balance handling for
Forecasting, scheduling and im balance handling for
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015
 
140617 zeewind risk_analysis_eng
140617 zeewind risk_analysis_eng140617 zeewind risk_analysis_eng
140617 zeewind risk_analysis_eng
 
RET Review Solution
RET Review SolutionRET Review Solution
RET Review Solution
 
Bihar policy for promotion of new and renewable energy sources 2011
Bihar policy for promotion of new and renewable energy sources 2011Bihar policy for promotion of new and renewable energy sources 2011
Bihar policy for promotion of new and renewable energy sources 2011
 
HYDRO_POLICY_UK_2015
HYDRO_POLICY_UK_2015HYDRO_POLICY_UK_2015
HYDRO_POLICY_UK_2015
 
RFP for Solar Power Plant in Punjab
RFP for Solar Power Plant in PunjabRFP for Solar Power Plant in Punjab
RFP for Solar Power Plant in Punjab
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 

Similaire à URN 14D 328 - applying for a Contract for Difference this October 2014 under the Allocation Framework and draft Regulations

UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
Iaroslav GREGIRCHAK
 
Power supply regulation_28.9
Power supply regulation_28.9Power supply regulation_28.9
Power supply regulation_28.9
Manoj kumar Rana
 

Similaire à URN 14D 328 - applying for a Contract for Difference this October 2014 under the Allocation Framework and draft Regulations (20)

Forecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind EnergyForecasting, scheduling and imbalance handling for Solar Wind Energy
Forecasting, scheduling and imbalance handling for Solar Wind Energy
 
CERC Regulations_latest policy and rules.pptx
CERC Regulations_latest policy and rules.pptxCERC Regulations_latest policy and rules.pptx
CERC Regulations_latest policy and rules.pptx
 
38700 716 13
38700 716 1338700 716 13
38700 716 13
 
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 1 Guidelines - Draft
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
The Contracts for Difference – Strike Back (with a cameo appearance by...Ener...
 
Procedure for implementation of short term open access (stoa)
Procedure for implementation of short term open access (stoa)Procedure for implementation of short term open access (stoa)
Procedure for implementation of short term open access (stoa)
 
Procedure for-distribution-open-access, Tata Power
Procedure for-distribution-open-access, Tata PowerProcedure for-distribution-open-access, Tata Power
Procedure for-distribution-open-access, Tata Power
 
Session 16 contract structure & agreement
Session 16   contract structure & agreementSession 16   contract structure & agreement
Session 16 contract structure & agreement
 
UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
UKRAINE - BOC - GETTING ACCESS TO ELECTRICITY - e-report_on_systemic_problem_...
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...
 
td_arr.pdf
td_arr.pdftd_arr.pdf
td_arr.pdf
 
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsTariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
 
PPA_NDMC
PPA_NDMCPPA_NDMC
PPA_NDMC
 
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
5.6.14 UK Infrastructure Bill - potential impact on private sector businesses...
 
Power supply regulation_28.9
Power supply regulation_28.9Power supply regulation_28.9
Power supply regulation_28.9
 
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
Exploiting deep geothermal energy and oil in the UK, building CO2 reduction c...
 
Tariff based competitive bidding for intra state trans. projects
Tariff based competitive bidding for intra state trans. projectsTariff based competitive bidding for intra state trans. projects
Tariff based competitive bidding for intra state trans. projects
 
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-IIIRfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
RfS for 35 MW in Puducherry under NSM Ph-II, Batch-III
 

Plus de Bhalindra Bath - projects & M&A law

Plus de Bhalindra Bath - projects & M&A law (6)

Summary
SummarySummary
Summary
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT - 03.2015
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT -  03.2015MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT -  03.2015
MBC ENGINEERING, INFRASTRUCTURE & PROCUREMENT - 03.2015
 
MBC W2F W2E BIOFUEL BIOMASS AD - 03.2015
MBC W2F W2E BIOFUEL BIOMASS AD -  03.2015MBC W2F W2E BIOFUEL BIOMASS AD -  03.2015
MBC W2F W2E BIOFUEL BIOMASS AD - 03.2015
 
MBC SOLAR
MBC SOLAR MBC SOLAR
MBC SOLAR
 
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
De-risking and enabling uk shale gas and deep heat geothermal projects; &, ri...
 

Dernier

Appeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdfAppeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdf
PoojaGadiya1
 
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
anilsa9823
 
一比一原版西澳大学毕业证学位证书
 一比一原版西澳大学毕业证学位证书 一比一原版西澳大学毕业证学位证书
一比一原版西澳大学毕业证学位证书
SS A
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
RRR Chambers
 
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Call Girls In Delhi Whatsup 9873940964 Enjoy Unlimited Pleasure
 
一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书
E LSS
 
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
mayurchatre90
 

Dernier (20)

Appeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdfAppeal and Revision in Income Tax Act.pdf
Appeal and Revision in Income Tax Act.pdf
 
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Singar Nagar Lucknow best sexual service
 
一比一原版西澳大学毕业证学位证书
 一比一原版西澳大学毕业证学位证书 一比一原版西澳大学毕业证学位证书
一比一原版西澳大学毕业证学位证书
 
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
8. SECURITY GUARD CREED, CODE OF CONDUCT, COPE.pptx
 
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Nangli Wazidpur Sector 135 ( Noida)
 
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptxCOPYRIGHTS - PPT 01.12.2023 part- 2.pptx
COPYRIGHTS - PPT 01.12.2023 part- 2.pptx
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm
 
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueAndrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
BPA GROUP 7 - DARIO VS. MISON REPORTING.pdf
BPA GROUP 7 - DARIO VS. MISON REPORTING.pdfBPA GROUP 7 - DARIO VS. MISON REPORTING.pdf
BPA GROUP 7 - DARIO VS. MISON REPORTING.pdf
 
Introduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusionIntroduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusion
 
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptxpnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
pnp FIRST-RESPONDER-IN-CRIME-SCENEs.pptx
 
一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书一比一原版利兹大学毕业证学位证书
一比一原版利兹大学毕业证学位证书
 
THE FACTORIES ACT,1948 (2).pptx labour
THE FACTORIES ACT,1948 (2).pptx   labourTHE FACTORIES ACT,1948 (2).pptx   labour
THE FACTORIES ACT,1948 (2).pptx labour
 
Relationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdfRelationship Between International Law and Municipal Law MIR.pdf
Relationship Between International Law and Municipal Law MIR.pdf
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
Negotiable Instruments Act 1881.UNDERSTAND THE LAW OF 1881
 
589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptx
 

URN 14D 328 - applying for a Contract for Difference this October 2014 under the Allocation Framework and draft Regulations

  • 1. 1 | P a g e Applying for a Contract for Difference this October 2014: the “Allocation Framework” - DECC paper URN 14D/328 (published 1 September 2014) General disclaimer: the following constitutes the written view of the author and in no way constitutes actual legal advice or a legal opinion and so no reliance may be placed upon the content hereinafter contained by any reader of this document in any way whatsoever. In the event that legal advice or opinion is sought, please contact the author of this opinion at the contact details below. The view below is expressly confined to matters as they stand at 6 September 2014, under the laws of England and Wales and in accordance with current publications from Her Majesty’s Department for the Energy and Climate Change as published at https://www.gov.uk/government/publications/electricity-market-reform-contracts- for-difference on 1 September, 2014. Earlier this year we reported on the consultation paper URN 14D/1141 and the proposal from the UK government to change the subsidy regime from renewable obligation certificates (ROCs) to contracts for difference (CfDs) for large >5MW projects for solar as put simply the Levy Control Framework does not have sufficient budget to allow for ROCs to instead phase out in 2017 as was previously mooted by the British Government. On 1 September 2014, DECC uploaded a paper (URN 14D/328) which outlines in greater detail the rules for the process for CfD allocation2 (“Rules”), or the “Allocation Framework” for the first round of CfDs to be issued by OfGEM with the CfD Counterparty following the application process commencement for the 1st round of CfD applications on 14 October 2014. In essence the Allocation Framework affirms that for AD, Hydro, onshore wind or solar, a generating unit (“CfD Unit”) must be larger than 5MW for an application for a CfD to be made. Facilities that are either already accredited for the renewable heat incentive or that are energy from waste with CHP related3 , are expressly excluded from the process. For each prospective project, the Allocation Framework and the 2014 CfD Contracts for Difference (Allocation) Regulations 20144 contain the basic information that a developer will need to provide when applying for a CfD for their project to ensure that it is a Qualifying Application5 , namely: (a) the application should show that the relevant eligibility criteria have been satisfied, and if there are any additional Secretary of State information required then this has been provided (see Schedule 4 in the Allocation Framework and below in this article, – i.e. a supply chain statement; applicable planning consent; confirmation on connection agreement or equivalent; confirmation of non-receipt of other UK Government 1 http://www.mybusinesscounsel.com/legal-updates/page/2/ 2 Contract for Difference Allocation Framework 2014 (URN 14D/328), the “Allocation Framework”: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/349370/Final_Allocation_Framew ork.pdf 3 As defined in The Contracts for Difference (Definition of Eligible Generator) Regulations 2014: http://www.legislation.gov.uk/uksi/2014/2010/contents/made 4 The Contracts for Difference (Allocation) Regulations 2014: http://www.legislation.gov.uk/ukdsi/2014/9780111116777/contents 5 Regulation 17 of the draft 2014 Contract for Difference Allocation Regulations: http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/17
  • 2. 2 | P a g e subsidies for the same facility; evidence of incorporation of the generator-vehicle; confirmation of the target commissioning window); (b) the national system operator will determine whether an applicant is a qualifying applicant based on their satisfaction of the criteria for application for a CfD (so regulation 17 of the draft 2014 Allocation Regulations6 , and see (j) below in this article); (c) the developer presenting a technology generating station should not be presenting a generating station that is not supported in whole or part by another scheme or is sub- 5MW and as otherwise set out in draft regulation 14 of the 2014 Allocation Regulations7 ; (d) the generating station should have planning consent so a planning permission under part 3 of the Town and Country Planning Act 1990 for an onshore generating station such as a ground-mounted solar plant that is over 5MW in generating capacity; (e) if there are conditions in the planning permission so it is a conditional planning consent, then the applicant for the CfD should draft a planning consent discharge of planning conditions plan to show that the planning conditions to the consent provided by e.g. a local authority can be discharged; (f) there must be evidence of a DNO connection offer or if it is a private system then according to the Allocation Framework the connection agreement in place must secure at least 75% of the initial installed capacity estimate of the CfD unit, or, where the connection will be to 75% to a distribution system a connection agreement will be required or evidence that the agreement is in place so that the CfD Counterparty (now incorporated as: Low Carbon Contracts Company Limited – UK CRN 8818711) can know the amount of metered electricity is estimated to be exported8 . If there will be partial or no connection then, as per Regulation 25(4)9 , “…Where a partial connection applies or is to apply to a relevant CFD unit, the applicant must provide a statement setting out how data in respect of metering of electricity supply is to be provided to the CFD counterparty. ..”, and the CfD applicant should provide a copy of the connection agreement between the owner of the transmission system and the generator, or a copy of the private network use agreement between the generator and the operator of the network and a copy of the connection agreement between the private network operator and the operator of the transmission system10 ; (g) when applying, certain minimum sizes apply to the type of project that can obtain a CfD, e.g. for solar it is 5MW11 ; (h) https://www.gov.uk/government/publications/electricity-market-reform-contracts-for- difference – at this link are all of the documents that relate to completing the contract for difference and metering agreements for an application. For the FIRST ROUND, the Government have issued the following table: https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/34820 2/The_Contracts_for_Difference__Standard_Terms__Regulations_2014_- _CFD_Standard_Terms_Notice__29_August_2014_.pdf, which contains information on 6 Ibid. 7 http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/14 8 Rule 4 of the Allocation Framework. 9 Regulation 25 of the draft 2014 Contract for Difference Allocation Regulations: http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/25 10 Rule 4.1 (iii) of the Allocation Framework. 11 Rule 5.1(ii) of the Allocation Framework.
  • 3. 3 | P a g e e.g. the expected target commissioning window, and so it is 1 year for anaerobic digestion, to 3 months for solar photovoltaic, as well as the total project pre-commissioning costs, so anaerobic digestion with or without combined heat and power is £1,750,000, or, for solar photovoltaic it is £1,000,000; (i) Developer Asset-Co (or Developer backed by Funder – Asset-Co) supply chain plan/development phase deliverables12 - General Project Commitments13 will need to be submitted with applications for CfDs (including a Directors Certificate that the Generator that owns the Asset e.g. Developer/Developer-Consortium with a funder, that the developer have financial resources for the total project spend (‘proof of funds’), evidence that the site for the plant is relatively unencumbered by third party property rights and where necessary easements/other rights have been/can be obtained, and all other consents for the installation of the PV plant have been obtained) as a part of the Project Commitments in the CfD Agreement, together with evidence of an EPC agreement (Construction Phase) and evidence of a framework (major kit) supply (“Material Equipment”) agreement and a binding purchase order for the Material Equipment (so modules, inverters, frames, switchgear). 300MW sized portfolios of solar assets being developed, require more sophisticated responses in terms of the supply chain plan to obtain Secretary of State approval for submission of the related application for allotment of related CfDs, and the related guidance14 ; (j) the applicant should also be an eligible generator, in that they operate or participate in the operation of, or intend to carry out a generating activity in relation to, an eligible generating station, such as solar photovoltaic array that generates and supplies electricity to the Grid15 ; 12 http://www.mybusinesscounsel.com/solar-urn-14d-114-analysis-by-bhalindra-bath/ 13 Annex 6 of the CfD agreement (https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/305539/cfd_agreement.pdf (draft CfD agreement as at April 2014): “…Delivery to the CfD Counterparty of the following: (A) a copy of a resolution of the Generator’s board of directors (or an equivalent management committee or body) to: (i) undertake the Project; (ii) approve the total financial commitments required to commission the Project (the “Total Project Spend”); and (iii) approve a timetable for undertaking the Project which demonstrates that the Facility can reasonably be expected to be commissioned no later than the Longstop Date; (B) a Directors’ Certificate certifying that: (i) the Generator has, or will have, sufficient financial resources to meet the Total Project Spend; and (ii) any contract entered into and provided as Supporting Information pursuant to the Milestone Requirements Notice, in the reasonable opinion of the Generator by reference to the facts and circumstances then existing, is: (a) legal, valid and binding; and, (b) entered into with one or more counterparties who are each able to perform their obligations under such contract; (iii) the Generator has a leasehold or freehold interest in the site where the Facility is based (the “Facility Site”) or a contract to obtain the same; (iv) the Facility Site is not subject to any covenants, restrictions, agreements, planning obligations, estate contracts, options, rights of way or other encumbrances which materially inhibit the use of the Facility Site for the purposes of the Project; (v) there are available to the Facility Site such rights, easements and services as are necessary to undertake the Project and operate the Facility; (vi) the Generator has identified all necessary consents and planning permissions to undertake the Project (the “Necessary Consents”); and (vii) there is a credible strategy in place to obtain the Necessary Consents and the Necessary Consents are not subject to any condition for which there does not exist a plan approved by the Generator’s board of directors to satisfy that condition, such that the Generator is not awareof any necessary consents and planning permissions which cannot be obtained or complied with, ((iii) to (vii), together the “Facility Requirements”); (C) Supporting Information evidencing (i) that the Generator has, or will have, sufficient financial resources to meet the Total Project Spend and (ii) the Facility Requirements. ..” 14 https://www.gov.uk/government/publications/supply-chain-guidance (updated 1 August 2014) 15 Section 3 of The Contracts for Difference (Definition of Eligible Generator) Regulations 2014: ibid. at FN3 above.
  • 4. 4 | P a g e (k) Credit Support Documents – “Collateral” - this is referred to as “collateral” in the terms and conditions published in April and will not include parent company guarantees, and will include a letter of credit or equivalent on-demand liquid form of guaranteed payment security that, e.g. in the event that the issuer loses their credit rating or folds, can be replaced within five working days with an equivalent form of security16 - so an applicant will most probably have to provide evidence that a standby letter of credit, on-demand bond or guarantee banked probably by a well- rated bank or insurance company is available to secure the obligations of the generator under the contract for difference. Despite a request for a similar form of security to be provided by the CfD Counterparty, the counter from DECC was that the provisions in the legislation including the ability for the Secretary of State to replace the insolvency remote CfD Counterparty in the event of default17 (limited/no measure to terminate for CfD Counterparty default under the terms and conditions) were sufficient, without the need for any additional form of security. Allocation process  The review date for applications, called the Non-Qualification Review Request Date is 18 November 2014. Appeals against any rejected applications is 9 December 2014. The start date for allocation of CfDs will be 22 December 2014 if no appeals, but if there are any appeals then the allocation start date will be 23 January 2015 (Rule 8 of the Allocation Framework).  In the event that there is an assessment from OfGEM that there is a requirement for an auction, then the applicants will be able to submit sealed bids18 which would include the Applicant’s proposed Strike Price in pounds sterling that an applicant will accept for each megawatt hour of metered output, but which, in any event must not be more than the applicable Administrative Strike Price (e.g. for 2015/16 for solar photovoltaic this is £120/MWh). The applications will then be ranked and assessed according to lowest Strike Price to highest, clearing price, cumulative value of qualifying applications, with the application process closing when the Minimum-only cap-amount for an auction process being reached to allow assessment and award of CfDs. A similar process will run for the Pot, Overall Budget and Maximum only auctions. Under Rule 18 of the Allocation Framework on “Tiebreaker Rules”, where there is a tiebreaker-type scenario, where there are two or more Qualifying Applications with the same strike price, then, o the individual bids will be assessed on their own and if they would result in the Minimum (minimum budget reserved for an allocation round as specified in a 16 Part 13 of GTAC (https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/305536/generic_cfd_t_and_cs.pd f). 17https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/307060/cfd_policy_drafting_upd ate.pdf 18 Rule 11.1 of the Allocation Framework
  • 5. 5 | P a g e Budget Notice19 ) or Maximum (maximum budget for an allocation round specified in a Budget Notice20 ) being exceeded, then the application will fail, or, o if a Qualifying Application or combination of Qualifying Applications comes close to fulfilling the Minimum or Maximum without exceeding either of them, then the Qualifying Application that comes closest to fulfilling the Minimum or Maximum will be deemed successful, or, o where Qualifying Applications come equally close to fulfilling the Minimum or Maximum without exceeding it then an electronic random assignment process will be used, or, o a Qualifying Application subject to a Minimum (budget) can also be determined as a Flexible Bid21 (with such a bid being made at different Strike Prices, expressed to the nearest whole penny, with a first Delivery Year no earlier than the Delivery Year in the application, and a capacity no greater than in the original application before the auction was announced22 as long as it is e.g. in the case of onshore wind or solar, as examples, over 5MW initial capacity) and will be determined as being successful provided it is not the same as or higher than the Strike Price of another Applicant’s sealed bid (Rule 15.1 (viii) of the Allocation Framework) – but if not successful will then be considered against the Pot/Overall Budget. Similar decision making methods to determine successful applications in tie-breaker situations as above apply to the situation where the Pot/Overall Budget (but not the Minimum or Maximum budgets) would be exceeded, and where the Pot/Overall budget and the Minimum or Maximum budgets would be exceeded23 . For assistance in applying for contracts for difference, advice on and actual drafting of appropriate legal documentation for application for a contract for difference, and advice on the draft legislation and process, email: bhalindra.bath@mybusinesscounsel.com. London, 6 September 2014. 19 Regulation 11(2)(a) of the draft 2014 Allocation Regulations: http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/11 20 Regulation 11(2)(b) of the draft 2014 Allocation Regulations: http://www.legislation.gov.uk/ukdsi/2014/9780111116777/regulation/11 21 A bid that meets the requirements of Rule 11.6 of the Allocation Framework. 22 Rule 11.6 of the Allocation Framework. 23 Rules 18.2-18.3 of the Allocation Framework.