Cost Engineering
Topics
> Who is Cost Engineering?

> What is Cleopatra Enterprise?

> Showcase Estimating an Industrial Plant: Class 4 to Class 2

> Questions & Answers




                           www.costengineering.eu
Added value in Cost Engineering


> Expertise

> Cost Data Development

> Education

> Professional Services

> Software solutions



                          www.costengineering.eu
Expertise


> Preparing and validating estimates during the complete project
  life cycle
> Developing and supervising contract strategies
> Benchmarking
> Asset Validation / Verification
> Location factors surveys
> Planning, cost control, quantity surveying
> Risk Assessment
> Value management




                            www.costengineering.eu
Cost Data Development

>   Standard cost data for your estimates for onshore and offshore
>   Multi-disciplinairy
>   Various industries and geographical areas
>   Based on DACE labour norms (Western Europe)
>   Based on Vendor information, historical project data
>   Well documented data qualifications
>   Yearly maintenance updates possible
>   3rd Party sources:
     > Richardson data
     > DACE Price Booklet
     > Reed business (Dutch civil)
     > Van Leeuwen Buizen Pipe & Tube


                                www.costengineering.eu
Academy


>   Based on knowledge and experience
>   Individual attention in small groups
>   Courses to suit managers as well as estimators
>   From introducing terminology to estimating and cost management
>   Company specific cost engineering programs
>   Cost engineering software tools




                          www.costengineering.eu
Cleopatra Enterprise


> The cost engineering tool for fast and accurate
  estimates for the complete project life cycle

> Thorough needs analysis

> Optimized implementation

> Customized training

> Global support




         www.costengineering.eu
References

>   Bulk storage
>   Construction industry
>   EPC(M)
>   Food and Nutrition
>   Government
>   Gas industry
>   Heavy industry
>   Pharmaceutical industry
>   Petro-/chemical industry
>   Power industry
>   Mining & Minerals




                               www.costengineering.eu
Cleopatra Enterprise




                  www.costengineering.eu
Modules


              Project
              Analysis                    Cost
                                       Estimation

Workflow




                                     Risk
Interfacing                        Analyses

                Websharing




              www.costengineering.eu
Characteristics




    www.costengineering.eu
Cost Estimation Module


> Creating solid cost estimates for various elements of a
  project from feasibility up to construction

> Allocate all types of costs: direct, allowances, indirect,
  escalation and contingencies

> Creating cost objects e.g. Assemblies

> Monitor and control estimate revisions

> Perform “What-if” analysis




                            www.costengineering.eu
Cost types




  www.costengineering.eu
Direct costs



                            Objects


                            Composites


                            Unit-Rates


                            Details




   www.costengineering.eu
Breakdown structures




       www.costengineering.eu
Breakdown structures




www.costengineering.eu
“What if” analysis




www.costengineering.eu
Project Analysis


> Learn from your past projects
> Compare multiple projects and historical data
> Analyze scope development
> Perform health checks to be more confident
> Scheduling and cash flow trending
> Benchmark your organization
> Business intelligence through regression analysis,
  pivot tables, or other methods of data mining




                          www.costengineering.eu
Workflow Module


> Control your document routing

> Monitor progress on your projects

> Quickly draw your workflow

> Personalized dashboard




                         www.costengineering.eu
Cleopatra Enterprise Software Integration
Show case:

 Example Plant




                 www.costengineering.eu
Show case: Example Plant

> Scope
   > Distillate process: raw product to middle distillate
   > By products: top and bottom
   > 28 pieces of equipment (columns, heat exchangers,
     tanks, pumps, vessels)
   > Executed in Western-Europe
   > Price level date 2010
   > Finish date: November 2011
   > Project life cycle: from feed to execution

> Plant design
   > 3D model
   > Process flow diagram
   > Equipment list



                            www.costengineering.eu
Show case: Example Plant
>   Class 4 estimate (40% accuracy):
     >   Based on Factors
     >   Parametric Equipment Models
     >   Applying Hand methodology
     >   Distribution of disciplines
>   Class 3 estimate (20% accuracy):
     >   Object re-use (Engineering Standards)
     >   Tuning for more accuracy
     >   Include allowance, indirect, escalation and contingency
     >   Disciplines: piping, mechanical, E&I, civil, etc.
     >   Parts to be estimated
>   Class 2 estimate (10% accuracy)
     > Detailed Unit-Cost
     > Bill of Quantity / Material take off input
     > Equipment Parameters


                                       www.costengineering.eu
Show case: Example Plant
> Benchmarking
   >   Compare Class 4 with Class 3 Estimate
   >   Compare Class 3 with Class 2 Estimate
   >   Analyze using Metrics
   >   View Key Quantities

> Scope Development
   > Create What-if scenario and compare alternatives
   > Show Comparison report

> Cash Flow Analysis
   > Show cash flow and schedule




                            www.costengineering.eu
Questions ?



                 Cost Engineering
HQ - PO box 25, 3330 AA Zwijndrecht, IJsselmeer 32e, 3332
             EX Zwijndrecht, The Netherlands
        T: +31 78 620 09 10 F: +31 78 620 91 42
             E-mail: info@costengineering.eu
                 www.costengineering.eu

Contenu connexe

Tendances

construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Understanding "BOT" projects
Understanding "BOT" projectsUnderstanding "BOT" projects
Understanding "BOT" projectsPrashanth Ravada
 
PM Unit III - Project Cash Flows
PM   Unit III - Project Cash FlowsPM   Unit III - Project Cash Flows
PM Unit III - Project Cash FlowsGhaith Al Darmaki
 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysisSiladitya Bag
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract Venuri Lakshani
 
Project Financing
Project FinancingProject Financing
Project Financingkhankm
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)hoang tung
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - TransferKshitij Gupta
 
Project Finance - Session 7
Project Finance - Session 7Project Finance - Session 7
Project Finance - Session 7Bodenbr
 
Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and evaBich Lien Pham
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgeSaket Bansal
 
Bot(build operate transfer)
Bot(build operate transfer)Bot(build operate transfer)
Bot(build operate transfer)Satish Kambaliya
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniquesWissem Amara
 

Tendances (20)

construction project planing
 construction project planing construction project planing
construction project planing
 
Understanding "BOT" projects
Understanding "BOT" projectsUnderstanding "BOT" projects
Understanding "BOT" projects
 
PM Unit III - Project Cash Flows
PM   Unit III - Project Cash FlowsPM   Unit III - Project Cash Flows
PM Unit III - Project Cash Flows
 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysis
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
PROJECT CONTRACTING
PROJECT CONTRACTINGPROJECT CONTRACTING
PROJECT CONTRACTING
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Project Financing
Project FinancingProject Financing
Project Financing
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Project risk analysis
Project risk analysisProject risk analysis
Project risk analysis
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - Transfer
 
Project Finance - Session 7
Project Finance - Session 7Project Finance - Session 7
Project Finance - Session 7
 
Irr
IrrIrr
Irr
 
A lecture on CCP Certificate
A lecture on CCP CertificateA lecture on CCP Certificate
A lecture on CCP Certificate
 
Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and eva
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridgePMP : Precedence Diagram Method : Relationship Types | iZenBridge
PMP : Precedence Diagram Method : Relationship Types | iZenBridge
 
Bot(build operate transfer)
Bot(build operate transfer)Bot(build operate transfer)
Bot(build operate transfer)
 
Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 

En vedette

Cost Engineering Introduction
Cost Engineering IntroductionCost Engineering Introduction
Cost Engineering IntroductionLeendertdegeus
 
Cost Engineering Principles Of Cost Estimating
Cost Engineering Principles Of Cost EstimatingCost Engineering Principles Of Cost Estimating
Cost Engineering Principles Of Cost EstimatingMartin van Vliet
 
Operations Management - Cost Reduction Process Re-engineering
Operations Management - Cost Reduction Process Re-engineeringOperations Management - Cost Reduction Process Re-engineering
Operations Management - Cost Reduction Process Re-engineeringManohar Mani Manjula Iyer
 
The Art Of Estimation
The Art Of EstimationThe Art Of Estimation
The Art Of Estimationcodeburns
 
Agile Software Estimation
Agile Software EstimationAgile Software Estimation
Agile Software EstimationSunil Jakkaraju
 
Cost Engineering Event 2015
Cost Engineering Event 2015Cost Engineering Event 2015
Cost Engineering Event 2015CostEngineering
 
Attra Partners Prince2 Intro
Attra Partners Prince2 IntroAttra Partners Prince2 Intro
Attra Partners Prince2 Introchouha
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostYudi Setiawan
 
AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01John Blodgett
 
CCP Certification Flowchart
CCP Certification FlowchartCCP Certification Flowchart
CCP Certification Flowchartjasmin ali
 
Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...Promet Source
 
6. petróleo (oil & gas)
6. petróleo (oil & gas)6. petróleo (oil & gas)
6. petróleo (oil & gas)JorgeVilches1
 
Apresentação CME Salesopolis
Apresentação CME SalesopolisApresentação CME Salesopolis
Apresentação CME SalesopolisDiego Costa
 
Principles of flight
Principles of flightPrinciples of flight
Principles of flightdeanoson
 
Einführung in die Mediendidaktik
Einführung in die MediendidaktikEinführung in die Mediendidaktik
Einführung in die MediendidaktikJohannes Maurek
 
Accounting 2 Chapter 8 Jamelli
Accounting 2 Chapter 8 JamelliAccounting 2 Chapter 8 Jamelli
Accounting 2 Chapter 8 JamelliMax Jamelli
 
Software Project Estimation Survival Guide
Software Project Estimation Survival GuideSoftware Project Estimation Survival Guide
Software Project Estimation Survival Guidemichaelcummings
 

En vedette (20)

Cost Engineering Introduction
Cost Engineering IntroductionCost Engineering Introduction
Cost Engineering Introduction
 
Introduction of cost engineering
Introduction of cost engineeringIntroduction of cost engineering
Introduction of cost engineering
 
Cost Engineering Principles Of Cost Estimating
Cost Engineering Principles Of Cost EstimatingCost Engineering Principles Of Cost Estimating
Cost Engineering Principles Of Cost Estimating
 
Operations Management - Cost Reduction Process Re-engineering
Operations Management - Cost Reduction Process Re-engineeringOperations Management - Cost Reduction Process Re-engineering
Operations Management - Cost Reduction Process Re-engineering
 
The Art Of Estimation
The Art Of EstimationThe Art Of Estimation
The Art Of Estimation
 
Agile Software Estimation
Agile Software EstimationAgile Software Estimation
Agile Software Estimation
 
Cost Engineering Event 2015
Cost Engineering Event 2015Cost Engineering Event 2015
Cost Engineering Event 2015
 
Attra Partners Prince2 Intro
Attra Partners Prince2 IntroAttra Partners Prince2 Intro
Attra Partners Prince2 Intro
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total Cost
 
AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01AACE Cost Engineering Journal ce15-01
AACE Cost Engineering Journal ce15-01
 
CCP Certification Flowchart
CCP Certification FlowchartCCP Certification Flowchart
CCP Certification Flowchart
 
Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...Project Estimation Presentation - Donte's 8th level of estimating level of ef...
Project Estimation Presentation - Donte's 8th level of estimating level of ef...
 
6. petróleo (oil & gas)
6. petróleo (oil & gas)6. petróleo (oil & gas)
6. petróleo (oil & gas)
 
Apresentação CME Salesopolis
Apresentação CME SalesopolisApresentação CME Salesopolis
Apresentação CME Salesopolis
 
Principles of flight
Principles of flightPrinciples of flight
Principles of flight
 
Einführung in die Mediendidaktik
Einführung in die MediendidaktikEinführung in die Mediendidaktik
Einführung in die Mediendidaktik
 
F
FF
F
 
Lista numerada de participantes
Lista numerada de participantes Lista numerada de participantes
Lista numerada de participantes
 
Accounting 2 Chapter 8 Jamelli
Accounting 2 Chapter 8 JamelliAccounting 2 Chapter 8 Jamelli
Accounting 2 Chapter 8 Jamelli
 
Software Project Estimation Survival Guide
Software Project Estimation Survival GuideSoftware Project Estimation Survival Guide
Software Project Estimation Survival Guide
 

Similaire à Cost Engineering for Projects

Cost Engineering for Turn Arounds
Cost Engineering for Turn AroundsCost Engineering for Turn Arounds
Cost Engineering for Turn AroundsMartin van Vliet
 
Cost Engineering for Tendering & Contracting
Cost Engineering for Tendering & ContractingCost Engineering for Tendering & Contracting
Cost Engineering for Tendering & ContractingMartin van Vliet
 
Cleopatra Enterprise Tendering And Contract Strategies
Cleopatra Enterprise Tendering And Contract StrategiesCleopatra Enterprise Tendering And Contract Strategies
Cleopatra Enterprise Tendering And Contract StrategiesLeendertdegeus
 
Cleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueCleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueLeendertdegeus
 
Cleopatra Enterprise and DACE Labour Norms
Cleopatra Enterprise and DACE Labour NormsCleopatra Enterprise and DACE Labour Norms
Cleopatra Enterprise and DACE Labour NormsMartin van Vliet
 
Powerdale Presentation En
Powerdale Presentation EnPowerdale Presentation En
Powerdale Presentation Enstephanzarzecki
 
Building Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSBuilding Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSLeonardo ENERGY
 
Mechanical Engineer-Mohammed Omer
Mechanical Engineer-Mohammed OmerMechanical Engineer-Mohammed Omer
Mechanical Engineer-Mohammed OmerOmer Mohammed
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsMartin van Vliet
 
Stork Crane Integrity
Stork Crane IntegrityStork Crane Integrity
Stork Crane IntegrityGH_Wijnants
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyorSyafiq Deen
 
Amr Said_CV_2017cn
Amr Said_CV_2017cnAmr Said_CV_2017cn
Amr Said_CV_2017cnAmr elmasry
 

Similaire à Cost Engineering for Projects (20)

Cost Engineering for Turn Arounds
Cost Engineering for Turn AroundsCost Engineering for Turn Arounds
Cost Engineering for Turn Arounds
 
Cost Engineering for Tendering & Contracting
Cost Engineering for Tendering & ContractingCost Engineering for Tendering & Contracting
Cost Engineering for Tendering & Contracting
 
Cleopatra Enterprise Tendering And Contract Strategies
Cleopatra Enterprise Tendering And Contract StrategiesCleopatra Enterprise Tendering And Contract Strategies
Cleopatra Enterprise Tendering And Contract Strategies
 
Cleopatra Enterprise Added Value
Cleopatra Enterprise Added ValueCleopatra Enterprise Added Value
Cleopatra Enterprise Added Value
 
Ahmed El-sheikha C Vjune
Ahmed El-sheikha C VjuneAhmed El-sheikha C Vjune
Ahmed El-sheikha C Vjune
 
Cleopatra Enterprise and DACE Labour Norms
Cleopatra Enterprise and DACE Labour NormsCleopatra Enterprise and DACE Labour Norms
Cleopatra Enterprise and DACE Labour Norms
 
Powerdale Presentation En
Powerdale Presentation EnPowerdale Presentation En
Powerdale Presentation En
 
Building Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACSBuilding Commissioning, Ongoing Commissioning and quality management using BACS
Building Commissioning, Ongoing Commissioning and quality management using BACS
 
Virtual Design and Construction
Virtual Design and ConstructionVirtual Design and Construction
Virtual Design and Construction
 
Genisision – Sales – 012 – Capability Statement Expanded
Genisision – Sales – 012 – Capability Statement ExpandedGenisision – Sales – 012 – Capability Statement Expanded
Genisision – Sales – 012 – Capability Statement Expanded
 
Mechanical Engineer-Mohammed Omer
Mechanical Engineer-Mohammed OmerMechanical Engineer-Mohammed Omer
Mechanical Engineer-Mohammed Omer
 
RESUME 06.01.2016......
RESUME  06.01.2016......RESUME  06.01.2016......
RESUME 06.01.2016......
 
CV
CVCV
CV
 
Senior Mechanical Engineer CV
Senior Mechanical Engineer CVSenior Mechanical Engineer CV
Senior Mechanical Engineer CV
 
Total Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project ControlsTotal Cost Management - Synergy between Cost Estimating and Project Controls
Total Cost Management - Synergy between Cost Estimating and Project Controls
 
Stork Crane Integrity
Stork Crane IntegrityStork Crane Integrity
Stork Crane Integrity
 
Quantity surveyor
Quantity surveyorQuantity surveyor
Quantity surveyor
 
khushbu cv
khushbu cvkhushbu cv
khushbu cv
 
Fabio_CV 2014n
Fabio_CV 2014nFabio_CV 2014n
Fabio_CV 2014n
 
Amr Said_CV_2017cn
Amr Said_CV_2017cnAmr Said_CV_2017cn
Amr Said_CV_2017cn
 

Dernier

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Dernier (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 

Cost Engineering for Projects

  • 2. Topics > Who is Cost Engineering? > What is Cleopatra Enterprise? > Showcase Estimating an Industrial Plant: Class 4 to Class 2 > Questions & Answers www.costengineering.eu
  • 3. Added value in Cost Engineering > Expertise > Cost Data Development > Education > Professional Services > Software solutions www.costengineering.eu
  • 4. Expertise > Preparing and validating estimates during the complete project life cycle > Developing and supervising contract strategies > Benchmarking > Asset Validation / Verification > Location factors surveys > Planning, cost control, quantity surveying > Risk Assessment > Value management www.costengineering.eu
  • 5. Cost Data Development > Standard cost data for your estimates for onshore and offshore > Multi-disciplinairy > Various industries and geographical areas > Based on DACE labour norms (Western Europe) > Based on Vendor information, historical project data > Well documented data qualifications > Yearly maintenance updates possible > 3rd Party sources: > Richardson data > DACE Price Booklet > Reed business (Dutch civil) > Van Leeuwen Buizen Pipe & Tube www.costengineering.eu
  • 6. Academy > Based on knowledge and experience > Individual attention in small groups > Courses to suit managers as well as estimators > From introducing terminology to estimating and cost management > Company specific cost engineering programs > Cost engineering software tools www.costengineering.eu
  • 7. Cleopatra Enterprise > The cost engineering tool for fast and accurate estimates for the complete project life cycle > Thorough needs analysis > Optimized implementation > Customized training > Global support www.costengineering.eu
  • 8. References > Bulk storage > Construction industry > EPC(M) > Food and Nutrition > Government > Gas industry > Heavy industry > Pharmaceutical industry > Petro-/chemical industry > Power industry > Mining & Minerals www.costengineering.eu
  • 9. Cleopatra Enterprise www.costengineering.eu
  • 10. Modules Project Analysis Cost Estimation Workflow Risk Interfacing Analyses Websharing www.costengineering.eu
  • 11. Characteristics www.costengineering.eu
  • 12. Cost Estimation Module > Creating solid cost estimates for various elements of a project from feasibility up to construction > Allocate all types of costs: direct, allowances, indirect, escalation and contingencies > Creating cost objects e.g. Assemblies > Monitor and control estimate revisions > Perform “What-if” analysis www.costengineering.eu
  • 13. Cost types www.costengineering.eu
  • 14. Direct costs Objects Composites Unit-Rates Details www.costengineering.eu
  • 15. Breakdown structures www.costengineering.eu
  • 18. Project Analysis > Learn from your past projects > Compare multiple projects and historical data > Analyze scope development > Perform health checks to be more confident > Scheduling and cash flow trending > Benchmark your organization > Business intelligence through regression analysis, pivot tables, or other methods of data mining www.costengineering.eu
  • 19. Workflow Module > Control your document routing > Monitor progress on your projects > Quickly draw your workflow > Personalized dashboard www.costengineering.eu
  • 21. Show case: Example Plant www.costengineering.eu
  • 22. Show case: Example Plant > Scope > Distillate process: raw product to middle distillate > By products: top and bottom > 28 pieces of equipment (columns, heat exchangers, tanks, pumps, vessels) > Executed in Western-Europe > Price level date 2010 > Finish date: November 2011 > Project life cycle: from feed to execution > Plant design > 3D model > Process flow diagram > Equipment list www.costengineering.eu
  • 23. Show case: Example Plant > Class 4 estimate (40% accuracy): > Based on Factors > Parametric Equipment Models > Applying Hand methodology > Distribution of disciplines > Class 3 estimate (20% accuracy): > Object re-use (Engineering Standards) > Tuning for more accuracy > Include allowance, indirect, escalation and contingency > Disciplines: piping, mechanical, E&I, civil, etc. > Parts to be estimated > Class 2 estimate (10% accuracy) > Detailed Unit-Cost > Bill of Quantity / Material take off input > Equipment Parameters www.costengineering.eu
  • 24. Show case: Example Plant > Benchmarking > Compare Class 4 with Class 3 Estimate > Compare Class 3 with Class 2 Estimate > Analyze using Metrics > View Key Quantities > Scope Development > Create What-if scenario and compare alternatives > Show Comparison report > Cash Flow Analysis > Show cash flow and schedule www.costengineering.eu
  • 25. Questions ? Cost Engineering HQ - PO box 25, 3330 AA Zwijndrecht, IJsselmeer 32e, 3332 EX Zwijndrecht, The Netherlands T: +31 78 620 09 10 F: +31 78 620 91 42 E-mail: info@costengineering.eu www.costengineering.eu