SlideShare une entreprise Scribd logo
1  sur  38
Slide #Rev.
C3D – Intelligent AWP
Planning and Management
Featuring: Implementation Manager - Chehade Kassouf
Slide #Rev.
Agenda
2018-10-10 2
• Why Intelligent AWP is Required?
• Adding Intelligence to AWP
• Some C3D Features
Slide #Rev.
Why Intelligent AWP is Required?
2018-10-10 3
Slide #Rev.
Building IWP Challenges
• Building IWP manually.
• Revisions causes re-definition of IWP’s.
• Data from many sources in different formats and levels of
granularities.
• Challenges for Workface:
• Building IWP is time consuming.
• Calculations is mainly done outside the system.
• Knowing the need to revise the IWP.
• Effort to re-build the IWP.
2018-10-10 4
Slide #Rev.
Information Transfer Challenges
• Handoff of the CWP from engineering to construction is not well
managed.
• CWP’s have many revisions.
• No document transmittal used to manage the handoff.
• Challenges for Workface:
• As CWP scope can change without notice. Workface team is deprived from
effective look-ahead planning.
• Working with immature CWP defeat purpose of AWP.
2018-10-10 5
Slide #Rev.
Constraints Clearance
• When the term constraint is used it usually means only drawings and
material.
• Systems provide only checkbox for construction constraints clearance.
• Challenges for Workface:
• Many open IWP’s due to construction constraints.
• Visibility on workload on various crews.
• This is more challenging when more than one contractor share the same site.
2018-10-10 6
Slide #Rev.
What AWP systems cover?
• Current AWP systems focus only the permanent work.
• Many additional systems are deployed to cover supporting activities.
• Challenges for Workface:
• More systems means more meetings.
• A large foundation for instance, needs excavation, safety barricade,
dewatering, scaffolding, compaction. Permanent work cannot start without
them.
2018-10-10 7
Slide #Rev.
AWP in Construction Language
2018-10-10 8
CWP release •(Drawing and
BOM)
IWP Release
Plan
•Scoping,
reviews
Constraint
Removal
•Only Drawing
and Material
Issue IWP
•Revision
check,
Approval,
Commit
Short Range
Planning
•Request and
Pull material,
Execute
Only workable ones
shall be released to
construction
The plan should depend
on resources and
construction capacity
Joint constraint removal by
engineering and
construction
Construction needs enough
data to assure if work can be
finished on time
Construction shall be able to
report progress, check efficiency,
improve performance.
Slide #Rev.
Adding Intelligence to AWP
2018-10-10 9
Slide #Rev.
A Workface Utopia
• Start every construction activity with the readiness of a shutdown activity.
• Needed Information:
• IFC Drawings without holds.
• All Material available.
• Safety trained crews.
• Access secured.
• Supporting activities status.
• Budgeted crew composition and man-hours.
• Required equipment and their status.
• ITP and Forms for QC.
• Calculations are done efficiently (budget and actual)
• Clear Sequence of Work.
• Workload for each crew
• In Short add intelligence to AWP
2018-10-10 10
Slide #Rev.
Adding Intelligence
2018-10-10 11
Intelligent
AWP
Front End
Loading
EDMS
Procurement
/ Material
Fabrication
Model /
Drawings
Timesheet /
Stores
Estimate /
Budget
Handover
and QC
Schedule
Crews /
Equipment
Controls the
revision of
CWP/IWP and all
other documents
Provide Ex-works
dates, current
store stock
Provide fabrication
data and their link to
model and drawingsProvide actuals spent
on every IWP
Provide early the
resource required,
how efficient the crew
Document and assure
QC ITP are met
Manage all
constraints based
on sequence.
Provide a datum to
compare against on
progress
Workload, Availability
Slide #Rev.
Some C3D Features
2018-10-10 12
Slide #Rev.
Sample IWP at Short Range Planning
• IWP Scope
• Budgeted Man-Hours:
1098
• Allowable Duration:
9 Working Days
• Needed Man-Power:
12
2018-10-10 13
If More Than 12
Definitely
Overrun
If Less Than 12
Cannot deliver
on-time
Slide #Rev.
Sample IWP at Short Range Planning
• Link With Schedule:
• Parent Activity
Allocated Duration:
56 Days.
• Allocated Manhours:
18000 MHR.
• Needed Man-Power
32.
2018-10-10 14
If More Than 32
No Delays
If Less Than 32
Delays will
Happen
Slide #Rev.
Sample IWP at Short Range Planning
2018-10-10 15
• 3D model and
Constraints
Management:
• Coordination Meeting
results update
Constraints status.
• Paving is delayed.
• Support cannot be
installed
Even if All Material, drawings
are available work cannot start
Slide #Rev.
Linking to Estimate / Budget
• A welding disposition
volume compensation
contract treats an
installation of super
complex spool and that of
straight run the same.
2018-10-10 16
Relying on contractual BOQ man-hours and
not on budgeted man-hours will be mis-
leading. IWP man-hours shall be managed by
the construction
Slide #Rev.
Crew Specialty
• Progress shall
tangible and
objective.
• IWP will need
various specialties
crews.
• Structural Steel
Crews:
• Erection
• Alignment and
shimming
• Bolt tightening
2018-10-10 17
Disregarding this fact, even the total allocated
man-hours tally with budget, the job will have
overruns.
IWP will be complemented by work orders to
assign the proper job to the right crew
Slide #Rev.
C3D AWP
• CWA Management
• CWP Management
• IWP Definition
• IWP Link to Schedule
• IWP Scoping
• IWP Reporting
• IWP Detailed Planning and Progress
2018-10-10 18
Slide #Rev.
CWA Management
2018-10-10 19
Slide #Rev.
CWA Fast Logical Scoping
2018-10-10 20
Slide #Rev.
CWA as Seen in 3D Model
2018-10-10 21
Slide #Rev.
Scoping 3D and Non-3D AWP Components
and their BOQ’s
2018-10-10 22
Slide #Rev.
IWP Definition
2018-10-10 23
Slide #Rev.
IWP Scoping
2018-10-10 24
Slide #Rev.
IWP Scoping via 3D
2018-10-10 25
Slide #Rev.
IWP Scoping via BOQ
2018-10-10 26
Slide #Rev.
Link with Schedule
2018-10-10 27
Slide #Rev.
IWP Link with Schedule
2018-10-10 28
Slide #Rev.
IWP detailed Planning
2018-10-10 29
Slide #Rev.
IWP Planning at lowest level
2018-10-10 30
Slide #Rev.
IWP Constraints
2018-10-10 31
Slide #Rev.
IWP Constraint Clearing via Front End Loading
2018-10-10 32
Slide #Rev.
IWP Printable Report
2018-10-10 33
Slide #Rev.
Samples
2018-10-10 34
Slide #Rev.
Samples
2018-10-10 35
Slide #Rev.
Samples
2018-10-10 36
Slide #Rev.
Q & A
Question and Answer Period
2018-10-10 37
Thank You!
awpconference.com
2018-10-10 38

Contenu connexe

Tendances

Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...CCT International
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastCCT International
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsCCT International
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIMCCT International
 
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013CCT International
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?CCT International
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringCCT International
 
Software Application Presentation Slide
Software Application Presentation SlideSoftware Application Presentation Slide
Software Application Presentation SlideLee Pei Gie
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIMCCT International
 
4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case Study4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case StudyBIM User Day
 
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoptionBIM User Day
 
1st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #11st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #1BIM User Day
 
How BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction projectHow BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction projectJacob Ostwald
 
5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single projectBIM User Day
 
Bim for facility management
Bim for facility managementBim for facility management
Bim for facility managementOmar Selim
 
Introduction to BIM and business case of BIM
Introduction to BIM and business case of BIMIntroduction to BIM and business case of BIM
Introduction to BIM and business case of BIMreem-yousef
 
Bim and project controls
Bim and project controlsBim and project controls
Bim and project controlsOmar Selim
 

Tendances (20)

Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
 
Contractors: Get BIM Ready!
Contractors: Get BIM Ready!Contractors: Get BIM Ready!
Contractors: Get BIM Ready!
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIM
 
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
 
Software Application Presentation Slide
Software Application Presentation SlideSoftware Application Presentation Slide
Software Application Presentation Slide
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIM
 
4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case Study4th Qatar BIM User Day, Case Study
4th Qatar BIM User Day, Case Study
 
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
5th Qatar BIM User Day, Perspectives on UK BIM standards & local adoption
 
Quy trình BIM
Quy trình BIMQuy trình BIM
Quy trình BIM
 
1st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #11st Qatar BIM User Day BIM processes Case Study #1
1st Qatar BIM User Day BIM processes Case Study #1
 
How BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction projectHow BIM is able to optimise the design phase of a construction project
How BIM is able to optimise the design phase of a construction project
 
5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project5th Qatar BIM User Day, Live modeling techniques on a single project
5th Qatar BIM User Day, Live modeling techniques on a single project
 
Bim for facility management
Bim for facility managementBim for facility management
Bim for facility management
 
Introduction to BIM and business case of BIM
Introduction to BIM and business case of BIMIntroduction to BIM and business case of BIM
Introduction to BIM and business case of BIM
 
Bim and project controls
Bim and project controlsBim and project controls
Bim and project controls
 
Bim
BimBim
Bim
 

Similaire à C3D - Intelligent AWP Planning and Management

AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdfMy own
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionGalala University
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Advanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeAdvanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeCCT International
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...Скоробогатов Дмитрий
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...Egyptian Engineers Association
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfssuserfc98db
 
IWP Timeline
IWP TimelineIWP Timeline
IWP TimelineScot Fyfe
 
Collaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdfCollaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdfTim McMahon
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Aestikani Mahani
 

Similaire à C3D - Intelligent AWP Planning and Management (20)

AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
 
atb-brochure.pdf
atb-brochure.pdfatb-brochure.pdf
atb-brochure.pdf
 
GTB-brochure.pdf
GTB-brochure.pdfGTB-brochure.pdf
GTB-brochure.pdf
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Advanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to PracticeAdvanced Work Packaging (AWP) - Reduction to Practice
Advanced Work Packaging (AWP) - Reduction to Practice
 
Spar2010murphy
Spar2010murphySpar2010murphy
Spar2010murphy
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
 
IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 
Collaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdfCollaboration - A Key Enabler of Innovation (Mirion).pdf
Collaboration - A Key Enabler of Innovation (Mirion).pdf
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Implementing Scrum with Kanban
Implementing Scrum with KanbanImplementing Scrum with Kanban
Implementing Scrum with Kanban
 
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
 
Sachin Mohelay
Sachin MohelaySachin Mohelay
Sachin Mohelay
 

Plus de CCT International

Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeCCT International
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCCCT International
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...CCT International
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...CCT International
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementCCT International
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without IsometricCCT International
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...CCT International
 
Digital Pens - Firas Hijazi - FIATECH and COMIT
Digital Pens - Firas Hijazi - FIATECH and COMITDigital Pens - Firas Hijazi - FIATECH and COMIT
Digital Pens - Firas Hijazi - FIATECH and COMITCCT International
 
Advanced Work Packaging - CCT Solutions at a Glance
Advanced Work Packaging - CCT Solutions at a GlanceAdvanced Work Packaging - CCT Solutions at a Glance
Advanced Work Packaging - CCT Solutions at a GlanceCCT International
 
Advanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life ImplementationAdvanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life ImplementationCCT International
 
Top 10 BIM Tips for Contractors
Top 10 BIM Tips for ContractorsTop 10 BIM Tips for Contractors
Top 10 BIM Tips for ContractorsCCT International
 
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...CCT International
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanCCT International
 

Plus de CCT International (14)

Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCC
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset Management
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without Isometric
 
Smart Construction Site
Smart Construction SiteSmart Construction Site
Smart Construction Site
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
 
Digital Pens - Firas Hijazi - FIATECH and COMIT
Digital Pens - Firas Hijazi - FIATECH and COMITDigital Pens - Firas Hijazi - FIATECH and COMIT
Digital Pens - Firas Hijazi - FIATECH and COMIT
 
Advanced Work Packaging - CCT Solutions at a Glance
Advanced Work Packaging - CCT Solutions at a GlanceAdvanced Work Packaging - CCT Solutions at a Glance
Advanced Work Packaging - CCT Solutions at a Glance
 
Advanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life ImplementationAdvanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life Implementation
 
Top 10 BIM Tips for Contractors
Top 10 BIM Tips for ContractorsTop 10 BIM Tips for Contractors
Top 10 BIM Tips for Contractors
 
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
A discrete Event Simulation Model of Asphalt Paving Operations, Ramzi Labban ...
 
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
 

Dernier

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 

Dernier (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 

C3D - Intelligent AWP Planning and Management

  • 1. Slide #Rev. C3D – Intelligent AWP Planning and Management Featuring: Implementation Manager - Chehade Kassouf
  • 2. Slide #Rev. Agenda 2018-10-10 2 • Why Intelligent AWP is Required? • Adding Intelligence to AWP • Some C3D Features
  • 3. Slide #Rev. Why Intelligent AWP is Required? 2018-10-10 3
  • 4. Slide #Rev. Building IWP Challenges • Building IWP manually. • Revisions causes re-definition of IWP’s. • Data from many sources in different formats and levels of granularities. • Challenges for Workface: • Building IWP is time consuming. • Calculations is mainly done outside the system. • Knowing the need to revise the IWP. • Effort to re-build the IWP. 2018-10-10 4
  • 5. Slide #Rev. Information Transfer Challenges • Handoff of the CWP from engineering to construction is not well managed. • CWP’s have many revisions. • No document transmittal used to manage the handoff. • Challenges for Workface: • As CWP scope can change without notice. Workface team is deprived from effective look-ahead planning. • Working with immature CWP defeat purpose of AWP. 2018-10-10 5
  • 6. Slide #Rev. Constraints Clearance • When the term constraint is used it usually means only drawings and material. • Systems provide only checkbox for construction constraints clearance. • Challenges for Workface: • Many open IWP’s due to construction constraints. • Visibility on workload on various crews. • This is more challenging when more than one contractor share the same site. 2018-10-10 6
  • 7. Slide #Rev. What AWP systems cover? • Current AWP systems focus only the permanent work. • Many additional systems are deployed to cover supporting activities. • Challenges for Workface: • More systems means more meetings. • A large foundation for instance, needs excavation, safety barricade, dewatering, scaffolding, compaction. Permanent work cannot start without them. 2018-10-10 7
  • 8. Slide #Rev. AWP in Construction Language 2018-10-10 8 CWP release •(Drawing and BOM) IWP Release Plan •Scoping, reviews Constraint Removal •Only Drawing and Material Issue IWP •Revision check, Approval, Commit Short Range Planning •Request and Pull material, Execute Only workable ones shall be released to construction The plan should depend on resources and construction capacity Joint constraint removal by engineering and construction Construction needs enough data to assure if work can be finished on time Construction shall be able to report progress, check efficiency, improve performance.
  • 9. Slide #Rev. Adding Intelligence to AWP 2018-10-10 9
  • 10. Slide #Rev. A Workface Utopia • Start every construction activity with the readiness of a shutdown activity. • Needed Information: • IFC Drawings without holds. • All Material available. • Safety trained crews. • Access secured. • Supporting activities status. • Budgeted crew composition and man-hours. • Required equipment and their status. • ITP and Forms for QC. • Calculations are done efficiently (budget and actual) • Clear Sequence of Work. • Workload for each crew • In Short add intelligence to AWP 2018-10-10 10
  • 11. Slide #Rev. Adding Intelligence 2018-10-10 11 Intelligent AWP Front End Loading EDMS Procurement / Material Fabrication Model / Drawings Timesheet / Stores Estimate / Budget Handover and QC Schedule Crews / Equipment Controls the revision of CWP/IWP and all other documents Provide Ex-works dates, current store stock Provide fabrication data and their link to model and drawingsProvide actuals spent on every IWP Provide early the resource required, how efficient the crew Document and assure QC ITP are met Manage all constraints based on sequence. Provide a datum to compare against on progress Workload, Availability
  • 12. Slide #Rev. Some C3D Features 2018-10-10 12
  • 13. Slide #Rev. Sample IWP at Short Range Planning • IWP Scope • Budgeted Man-Hours: 1098 • Allowable Duration: 9 Working Days • Needed Man-Power: 12 2018-10-10 13 If More Than 12 Definitely Overrun If Less Than 12 Cannot deliver on-time
  • 14. Slide #Rev. Sample IWP at Short Range Planning • Link With Schedule: • Parent Activity Allocated Duration: 56 Days. • Allocated Manhours: 18000 MHR. • Needed Man-Power 32. 2018-10-10 14 If More Than 32 No Delays If Less Than 32 Delays will Happen
  • 15. Slide #Rev. Sample IWP at Short Range Planning 2018-10-10 15 • 3D model and Constraints Management: • Coordination Meeting results update Constraints status. • Paving is delayed. • Support cannot be installed Even if All Material, drawings are available work cannot start
  • 16. Slide #Rev. Linking to Estimate / Budget • A welding disposition volume compensation contract treats an installation of super complex spool and that of straight run the same. 2018-10-10 16 Relying on contractual BOQ man-hours and not on budgeted man-hours will be mis- leading. IWP man-hours shall be managed by the construction
  • 17. Slide #Rev. Crew Specialty • Progress shall tangible and objective. • IWP will need various specialties crews. • Structural Steel Crews: • Erection • Alignment and shimming • Bolt tightening 2018-10-10 17 Disregarding this fact, even the total allocated man-hours tally with budget, the job will have overruns. IWP will be complemented by work orders to assign the proper job to the right crew
  • 18. Slide #Rev. C3D AWP • CWA Management • CWP Management • IWP Definition • IWP Link to Schedule • IWP Scoping • IWP Reporting • IWP Detailed Planning and Progress 2018-10-10 18
  • 20. Slide #Rev. CWA Fast Logical Scoping 2018-10-10 20
  • 21. Slide #Rev. CWA as Seen in 3D Model 2018-10-10 21
  • 22. Slide #Rev. Scoping 3D and Non-3D AWP Components and their BOQ’s 2018-10-10 22
  • 25. Slide #Rev. IWP Scoping via 3D 2018-10-10 25
  • 26. Slide #Rev. IWP Scoping via BOQ 2018-10-10 26
  • 27. Slide #Rev. Link with Schedule 2018-10-10 27
  • 28. Slide #Rev. IWP Link with Schedule 2018-10-10 28
  • 29. Slide #Rev. IWP detailed Planning 2018-10-10 29
  • 30. Slide #Rev. IWP Planning at lowest level 2018-10-10 30
  • 32. Slide #Rev. IWP Constraint Clearing via Front End Loading 2018-10-10 32
  • 33. Slide #Rev. IWP Printable Report 2018-10-10 33
  • 37. Slide #Rev. Q & A Question and Answer Period 2018-10-10 37

Notes de l'éditeur

  1. Work orders to manage other crews and pre-requisite activity. Coordination with activity (pivot gantt to distribute load of daily work)