Review the attached assignment and do the following; Complete the Dependency column of the table and include the dependencies and types of dependency for each activity Produce a Project Schedule Network diagram for the project Determine the maximum project duration, assuming two units of resource that you may allocate however you wish Produce a Gantt chart --------------------------------------------------------------------------------------- Classroom Exercise: Small Decorating Project Activity ID Description Duration (days) Dependency(ies) and Type (FS, SS, SF, FF) 1 Decorate Room (Summary Task) - - 2 Remove furnishings 1 3 Fetch Paint 1 4 Fetch wallpaper 1 5 Strip walls 4 6 Paint ceiling and woodwork 2 7 Hang wallpaper 5 8 Replace furnishings 1 9 Tidy up, relax and brag about your DIY skills 1 Using the activity table above: Complete the Dependency column of the table and include the dependencies and types of dependency for each activity Produce a Project Schedule Network diagram for the project Produce a critical path method diagram and identify the critical path of the project. Determine the maximum project duration, assuming two units of resource that you may allocate however you wish Produce a Gantt chart Key: FS: Finish to Start: activity can only start when predecessor is finished regardless of resource availability SS: Start to Start: Activity and its predecessor may start simultaneously if resources are available SF: Start to Finish: Activity must finish before predecessor may start FF: Finish to Finish: Activity must finish at the same time as its predecessor .