SlideShare une entreprise Scribd logo
1  sur  65
Télécharger pour lire hors ligne
VT4 Project
Commissioning Dept.
Technology Transfer
[Day1-1] Basic of Commissioning
1
Index
1.1 What is Commissioning
1.2 Terminology of Commissioning
1. Summary of Commissioning
2. Commissioning Sequence
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
1.3 Individual system and equipment test
2
1.1 What is Commissioning
1.2 Terminology of Commissioning
1. Summary of Commissioning
Contents
1.3 Individual system and equipment test
3
1.1 What is Commissioning
The primary objective of metallurgical plant commissioning is to ensure that all
systems and equipment of a plant are installed, tested, operated, and
maintained according to the operational requirements of the client. For large
projects, this process usually comprises planning, execution, and control of
thousands of inspection and test activities on sections to be com-missioned,
and these include instrumentation, control loops, and all electrical and
mechanical equipment.
The process of commissioning is integrated into various phases. This is
executed by the project team and includes the plant operational and
engineering staff as well as the con-tractors responsible for the installation and
cold commissioning. The overriding factor is the attention to detail required
with respect to safety of people, protection of equipment and the environment.
4
1.2 Terminology
1.2.1 Pre-Commissioning
Pre-Commissioning activities start when the plant, or system, achieves
Mechanical Completion. Frequently however, Pre-Commissioning
activities overlap Mechanical Completion activities and for this reason
the plant should be separated into easily manageable system package,
each system package will be Pre-Commissioned as a whole and
isolations at the boundaries of the system package will be maintained
until the completion of Pre-Commissioning activities.
Pre-Commissioning activities include: checking for design conformity,
checking the status of electrical, mechanical and instrument such as
calibration, loop check, line check, insulation resistance, relay setting,
flushing , blowing and cleaning activities.
5
1.2 Terminology
2. Cold-Commissioning
Cold Commissioning means individual equipment and system
commissioning and initial startup such as CCW system, compressed air
system and feed water system etc.
Cold Commissioning activities include: checking for design conformity,
checking the status of individual equipment and system capability,
function, interlock and reliability.
6
1.2 Terminology
3. Hot-Commissioning
Hot commissioning means the commissioning of the plant level. In
general, the commissioning activity after initial firing belongs to the hot
commissioning
Hot Commissioning activities include : Initial firing, Steam blowing,
Turbine bypass operation, Synchronizing and plant level function test.
7
1) Check list before the test
① Switch Gear Status
② Shaft turning by manual
③ Start the space heater
④ Lubrication oil pump start (if applicable)
⑤ Check the insulation resistance
⑥ Motor solo test start at DCS HMI
2) Check list during the test
① Direction of rotation
② Starting current
③ Operating current
④ Vibration of Motor bearing
⑤ Temperature of Motor bearing
⑥ Temperature of Motor Winding
Solo Test
1.3 Individual system and equipment test
1
8
No-load Test / Minimum Load Test
1) No-load Test and Minimum Load Test
① No-load Test
No-load Test means equipment's running with that has no flow through
the Fan in case of discharge or suction damper are closed when fan is
running.
② Minimum Load Test
Minimum Load Test means equipment’s running with that has
minimum flow through the pump in case of suction valve open,
minimum flow valve open and discharge valve closed
2) Check Point During No-Load Test and Minimum Load Test
① Direction of rotation
② Starting current and Operating current
③ Vibration of Motor bearing
④ Temperature of Motor bearing
⑤ Temperature of Motor Winding
⑥ Suction/Discharge Pressure
⑦ Flow (if applicable)
1.3 Individual system and equipment test
2
9
Load Test
1) Load Test
The Load test is a test that is performed when the fluid flows normally to the
pump or fan.
2) Check Point During Load Test
① Direction of rotation
② Starting current and Operating current
③ Vibration of Motor/Pump (Fan) bearing
④ Temperature of Motor/Pump (Fan) bearing
⑤ Temperature of Motor Winding
⑥ Suction/Discharge Pressure
⑦ Discharge Flow
1.3 Individual system and equipment test
3
10
2. Commissioning Sequence
Contents
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
11
① Visual Inspection as per P & ID that check point is physical refection status
and instruments installation status
② Cleaning of erected and installed system such as air and flue gas inside
and outside and all area where works performed so that no erection
parts disturb moving equipment and program cycles.
③ Flushing or Blowing the pipelines, including process media pipelines and
impulse piping6. Checking for the possibility of stretching and extension
for pipe lines and cables
④ Checking and preparation for operation of the spring suspensions and
compensators and removing of spring loaded bolts
⑤ Lubrication for operation according to manufacture’s instructions.
Pre-Commissioning Check List
2.1 Pre-Commissioning
1
12
⑥ Checking the alignment of machinery and structure (example;
expansion joints),and provide appropriate documents.
⑦ Leak tests and Hydraulic Test (gas, solid and fluids) of Duct or Pipe Line
⑧ Calibration for Instrument, Control Valve, MOV and Switch.
⑨ Safety Valve and Pressure Relief Valve Setting.
⑩ Signal/loop check from DCS to fields device, including check of
measurement ranges and moving the appropriate equipment from DCS
(stroke test).
⑪ Check all operating and alarm limits in field in system and set fixed
initial values in program for startup, using set point and alarm list.
⑫ Relay Setting, PT and CT Checking for Switch Gear
2.1 Pre-Commissioning
Pre-Commissioning Check List
1
13
2. Commissioning Sequence
Contents
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
 BOP and Common Facilities
 Boiler and Auxiliary System
 Turbine and Auxiliary System
14
Power Receiving
1) Objective
Electrical power back feed from the grid for generating unit startup.
2) Commissioning Sequence
First of commissioning
3) Major System
① GIS or AIS
② TR
③ Switch Gear
④ DC and UPS
2. Cold-Commissioning
2.2 Cold Commissioning
1
15
Water Treatment System (WT)
1) Objective
The water treatment facility treats the raw water and then supplies the
necessary water to the plant. Depending on the application Demin. Water,
Service Water, Potable Water..
2) Commissioning Sequence
after power receiving
3) Major System
① Raw Water Treatment System (Clarifier, RO, MSF)
② Potable Water Treatment System
③ Demin. Water Treatment System
2. Cold-Commissioning
2.2 Cold Commissioning
2
16
Waste Water Treatment System (WWT)
1) Objective
WWT is a facility to purify wastewater from the plant to meet environmental
standards.
2) Commissioning Sequence
after complete power receiving and water treatment system commissioning.
3) Major equipments
① Waste Water Pond
② Oily Waste Water Treatment System
③ Chemical Waste Water Treatment System
④ FGD Waste Water Treatment System
⑤ Coal Yard Waste Water Treatment System
2. Cold-Commissioning
2.2 Cold Commissioning
3
17
Closed Cooling Water System (CCW)
1) Objective
CCW is to supply cooling water to individual devices.
2) Commissioning Sequence
after Power Receiving, WT, WWT.
3) Major equipments
① CCW Head Tank
② CCW Pump
③ CCW Heat Exchanger
2. Cold-Commissioning
2.2 Cold Commissioning
4
18
Compressed Air System
1) Objective
Compressed air system is a facility that produces instrument air and service air to
drive pneumatic equipment such as control valve..
2) Commissioning Sequence
after Power Receiving, WT, WWT.
3) Major equipments
① Air Compressor
② Drier
③ Air Receiving Vessel for Instrument Air
④ Air Receiving Vessel for Service Air
2. Cold-Commissioning
2.2 Cold Commissioning
5
19
Circulating Water System or Main Cooling Water System (CW or MCW)
1) Objective
Circulating Water System is supplied cooling water to condenser, closed cooling
water heat exchanger, etc.
2) Commissioning Sequence
after Power Receiving
3) Major equipment's
① Intake
② Trash Rack
③ Traveling Screen and washing pump
④ Chlorination Generation System and Injection System
⑤ Circulating Water Pump (CWP) or Main Cooling Water Pump (MCWP)
⑥ Debris Filter
⑦ Condenser Tube Cleaning System
⑧ Discharge Culvert
⑨ Auxiliary Cooling Water Pump
2.2 Cold Commissioning
6
2. Cold-Commissioning
20
Auxiliary Steam System
1) Objective
Auxiliary Steam System is to provide for necessary steam of plant startup and
operation as below System
 Turbine Seal Steam and Rotor Pre-Warming
 Turbine Driven BFP
 Deaerator
 Steam Coil Air Heater
 SCR Ammonia Vaporizer
 Air Pre-Heater Soot Blower
 Pulverizer Inerting Steam etc.
2) Commissioning Sequence
after Power Receiving
3) Major equipment's
① Auxiliary Boiler (if applicable)
② Auxiliary Steam Header
③ Auxiliary Pressure Reducing Station for CRH to Aux. Steam Header
④ Auxiliary Pressure Reducing for Main Steam to Aux. Steam Header
2. Cold-Commissioning
2.2 Cold Commissioning
7
21
Condensate System
1) Objective
Condensate System is to transfer condensate from condenser to deaerator
2) Commissioning Sequence
After Water Treatment System commissioning is completed
3) Major equipment's
① Condensate Extraction Pump (CEP)
② CPP
③ Low Pressure Heater
2. Cold-Commissioning
2.2 Cold Commissioning
8
22
Chemical Cleaning
1) Objective
 Alkali Cleaning objective is to remove organic matter in condensate and feed
water system
 Acid Cleaning objective is to remove inorganic matter in boiler water wall.
2) Commissioning Sequence
After condensate commissioning and auxiliary steam system
3) Major equipment's
① Temporary Circulating Water Pump for Chemical Cleaning
② Temporary Heat Exchanger for Chemical Cleaning
③ Temporary Chemical Cleaning Water Mixing Tank
④ Temporary Chemical Injection Pump and Tank
2. Cold-Commissioning
2.2 Cold Commissioning
9
23
Feed Water System
1) Objective
Feed Water System is storage feed water, deaerating in feed water, warming
feed water, heat feed water and water feeding to boiler
2) Commissioning Sequence
After condensate system and after Chemical Cleaning
3) Major equipment's
① Deaerator
② Feed Water Storage Tank
③ Motor Driven Boiler Feed Water Pump (MDBFP)
④ Turbine Drive Boiler Feed Water Pump (TDBFP)
⑤ High Pressure Heater
2. Cold-Commissioning
2.2 Cold Commissioning
10
24
Chemical Injection System
1) Objective
Chemical Injection System is to control feed water and condensate pH and
dissolve oxygen
 All Volatile Treatment Method
 pH control chemical : Ammonia or equivalent chemical
 Oxygen Scavenger : Hydrazine or equivalent chemical
 Boiler compound : Phosphate or equivalent chemical (Drum type boiler)
 Combined Water Treatment System
 Startup : AVT Method
 During Stable Operation : O2 Treatment Method
2) Commissioning Sequence
After Condensate and Feed water System Commissioning
3) Major equipment's
① Chemical Storage Tank
② Chemical Injection Pump
2. Cold-Commissioning
2.2 Cold Commissioning
11
25
Fuel Oil Supply System
1) Objective
Fuel Oil Supply System is to supply fuel for boiler startup, normally boiler startup
fuel is used Light Oil.
2) Commissioning Sequence
After refection completed
3) Major equipment's
① Fuel Oil Storage Tank
② Fuel Oil Transfer Pump
2. Cold-Commissioning
2.2 Cold Commissioning
12
26
2. Commissioning Sequence
Contents
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
 BOP and Common Facilities
 Boiler and Auxiliary System
 Turbine and Auxiliary System
27
Draft System
1) Objective
Draft system is to supply combustion air to boiler furnace and remove flue gas
to ambient.
2) Commissioning Sequence
After CCW, Compressed Air system commissioning and duct leak test are
completed.
3) Major equipment's
① Induced Draft Fan (IDF)
② Forced Draft Fan (FDF)
③ Gas Air Heater (GAH) or Air-preheater
④ Steam Coil Air Heater (SCAH)
2. Cold-Commissioning
2.2 Cold Commissioning
1
28
Boiler Startup System
1) Objective
One Through Boiler is necessary boiler startup system for sub critical operation
during boiler startup. separator is separate water in the steam at the boiler water
wall out let and then separated water is strafing in the Separator Storage Vessel
(SSV) and then separated water return to the economizer inlet by Boiler
Recirculation Pump.
2) Commissioning Sequence
After Feed Water System and Chemical Cleaning are Commissioning
Completed
3) Major equipment's
① Boiler Recirculation Pump (BRP)
② Separator
③ Separator Storage Vessel (SSV)
④ Boiler Blow Down System
2. Cold-Commissioning
2.2 Cold Commissioning
2
29
Oil Burner
1) Objective
Burner is to combust fuel and then fossil fuel convert the thermal energy.
2) Commissioning Sequence
After Compressed Air System Commissioning
3) Major equipment's
① Oil burner
② Atomizing Air System
③ Flame Scanner
④ Ignitor
2. Cold-Commissioning
2.2 Cold Commissioning
3
30
2. Commissioning Sequence
Contents
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
 BOP and Common Facilities
 Boiler and Auxiliary System
 Turbine and Auxiliary System
31
Turbine Lube Oil System
1) Objective
Turbine Lube Oil System is providing lubricant to turbine bearing and generator
bearing
2) Commissioning Sequence
After CCW System is completed and Turbine rotor alignment completed
3) Major equipment's
① Lube Oil Tank
② Lube Oil Tank Exhaust Fan
③ Lube Oil Pump (AC)
④ Lube Oil Pump (DC)
⑤ Oil Purifier
2. Cold-Commissioning
2.2 Cold Commissioning
1
32
Turbine Turning Gear
1) Objective
Turbine Turning Gear is rotate the turbine rotor from standstill condition and
stretch bent turbine rotor due to rotor weight during standstill condition.
Turning Gear must operate to prevent excess vent after turbine stop and then
turning gear stop after completed cooling down turbine rotor temperature
2) Commissioning Sequence
After turbine lube oil system completed
3) Major equipment's
① Turning Gear
2. Cold-Commissioning
2.2 Cold Commissioning
2
33
2. Commissioning Sequence
Contents
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
 Initial Firing, Steam Blowing & Turbine Bypass Operation
 Turbine Rolling and Synchronizing
 Overall Generating Unit Test
34
Initial Firing
1) Objective
Initial firing objective is integrated boiler system test such as condensate and
feed water system, draft system, fuel oil supply system and burner etc. related
system of boiler by burner ignition.
2) Commissioning Sequence
After cold commissioning completed
3) Major equipment's
① Condensate and Feed Water System
② Fuel Oil Supply System
③ Drafty System
④ Burner
3. Hot-Commissioning
2.3 Hot Commissioning
1
35
Steam Blowing
1) Objective
Steam Blowing Objective is to protect turbine due to foreign matter from the
boiler and main steam and reheat steam line.
2) Commissioning Sequence
After Initial Firing
3) Major equipment's
① Condensate and Feed Water System
② Fuel Oil Supply System
③ Drafty System
④ Burner
⑤ Main steam, reheat steam and HP/LP bypass station
⑥ Temporary Piping and Silencer for Steam Blowing
3. Hot-Commissioning
2.3 Hot Commissioning
2
36
Turbine Seal Steam System
1) Objective
The section, where the steam turbine rotor exits through the casing is called
gland, and labyrinth fins are installed there. Seal steam is supplied to seal the
section. Also, a gland steam condenser is installed to drain steam leaking from
the gland. Seal steam should always be provided to the turbine, when vacuum
condition is maintained in the condenser. If seal steam is not provided, the
vacuum in the condenser will pull ambient air from the atmosphere through the
gland. The ambient air, which is at a low temperature, will cool the gland rapidly
and as a result the gland casing may deform. This would cause contact between
rotating surface and stationary surface resulting in damage to the rotor.
2) Commissioning Sequence
After turbine turning gear commissioning and complete turbine seal steam line
steam blowing completed
3) Major equipment's
① Turbine Seal Steam Supply and Drain Header and Piping
② Gland Steam Condenser
③ Gland Steam Condenser Exhaust Fan
3. Hot-Commissioning
2.3 Hot Commissioning
3
Note : This activity is possible before initial firing if seal
steam line blowing is completed by auxiliary steam
37
Condenser Vacuum Pump
1) Objective
Condenser Vacuum Pump is to remove non-condensable gas in the
condenser when turbine operating and make condenser vacuum condition
for turbine operating before the boiler ignition.
2) Commissioning Sequence
After CW System Commissioning
3) Major equipment's
① Condenser Vacuum Pump
3. Hot-Commissioning
2.3 Hot Commissioning
4
Note : This activity is possible before initial firing
38
Condenser Vacuum Pulling
1) Objective
This test is in order to the verifying that the Condenser vacuum pressure is
achieved as Turbine bypass operation starting permissive.
2) Commissioning Sequence
After turbine seal steam system and condenser vacuum pump commissioning
3) Major equipment's
① Condenser
② Turbine Seal Steam System
③ Condenser Vacuum Pump
3. Hot-Commissioning
2.3 Hot Commissioning
5
Note : This activity is possible before initial firing if seal
steam line blowing is completed by auxiliary steam
39
Turbine Bypass Operation
1) Objective
Turbine bypass operation is integrated generating unit operation test exclude
turbine system. Main steam and reheat steam are bypassing HP, IP and LP
turbine by HP/LP turbine bypass station.
Generating unit is make turbine steam admission condition such as steam
pressure, steam temperature and steam purity by turbine bypass operation after
boiler firing
2) Commissioning Sequence
After steam blowing and condenser vacuum pulling completed.
3) Major equipment's
① Boiler and Auxiliary System
② BOP and Common System
③ Turbine bypass station
3. Hot-Commissioning
2.3 Hot Commissioning
6
40
Coal Firing Test
1) Objective
Coal firing test objective is actual coal combustion test for rerated system such
as coal silo, coal feeder and pulverizer.
2) Commissioning Sequence
After steam blowing and condenser vacuum pulling completed.
3) Major equipment's
① Coal Handling System
② Coal Silo
③ Coal Feeder
④ Pulverize
⑤ Coal Burner
3. Hot-Commissioning
2.3 Hot Commissioning
7
Note : This activity is possible before initial firing if seal
steam line blowing is completed by auxiliary steam
41
SCR Test
1) Objective
Selective catalytic reduction (SCR) is a means of converting nitrogen oxides,
also referred to as NOx with the aid of a catalyst into diatomic nitrogen (N2) ,
and water (H 2O). A gaseous reductant, typically anhydrous ammonia, aqueous
ammonia or urea, is added to a stream of flue or exhaust gas and is
adsorbed[citation needed] onto a catalyst. Carbon dioxide, CO2 is a reaction
product when urea is used as the reductant.
2) Commissioning Sequence
After steam blowing and condenser vacuum pulling completed.
3) Major equipment's
① Catalyst
② Ammonia Unloading and Storage Tank
③ Ammonia Vaporizer
④ Ammonia Dilution Blower
3. Hot-Commissioning
2.3 Hot Commissioning
8
42
ESP
1) Objective
Electrostatic Precipitation is a physical process by which particulate suspended
in a gas stream is electrically charged in a corona filed and under the influence
of the electric field, is driven to a collecting surface, separating it from the gas.
2) Commissioning Sequence
Before coal firing starting
3) Major equipment's
① EP Casing
② Transformer Rectifier
③ Seal Air Blower
④ Ash Hopper
3. Hot-Commissioning
2.3 Hot Commissioning
9
Note : This activity is possible before initial firing as per local requlation
43
FGD
1) Objective
FGD is conducted removing SOx in the flue gas. The SOx-Absorption is
achieved by natural alkalinity present in seawater in a absorber, where the raw
flue gas comes into an intensive contact to the sprayed seawater. Thus the SOx
is absorbed with optimal removal efficiency.
CaCO3 + SO2→ CaSO3 + CO2 (gas)
2) Commissioning Sequence
Conduct with Coal Firing Test
3) Major equipment's (Sea Water type FGD)
① Absorber
② Sea Water Spray Pump
③ Aeration Basin
④ GGH
3. Hot-Commissioning
2.3 Hot Commissioning
10
44
Safety Valve Popping Test
1) Objective
Safety Valve is to prevent due to overpressure of boiler system
2) Commissioning Sequence
During Turbine bypass operation
3) Major equipment's
① Safety Valve of Super Heater and Reheater
3. Hot-Commissioning
2.3 Hot Commissioning
11
45
2. Commissioning Sequence
Contents
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
 Initial Firing, Steam Blowing & Turbine Bypass Operation
 Turbine Rolling and Synchronizing
 Overall Generating Unit Test
46
Stator Cooling Water System
1) Objective
The stator winding liquid cooling system supplied deionized water to the stator
for cooling the stator winding.
2) Commissioning Sequence
After erection and demin. water treatment system completed
3) Major equipment's
① Stator Winding Cooling Water Tank
② Stator Cooling Pump
③ Stator Water Cooler
④ Stator Leakage Monitoring System
⑤ De-ionizer
3. Hot-Commissioning
2.3 Hot Commissioning
1
47
Generator Seal Oil System
1) Objective
Generator Seal Oil System is to prevent of H2 gas leakage from generator
inside through generator rotor between casing surface.
2) Commissioning Sequence
Turbine Lube Oil System Completed
3) Major equipment's
① Vacuum tank
② Main Seal Oil Pump
③ Emergency Seal Oil Pump
④ Recirculation Seal Oil Pump
⑤ Seal Oil Vacuum Pump
⑥ Liquid Detector
3. Hot-Commissioning
2.3 Hot Commissioning
2
48
H2 / CO2 Control System
1) Objective
H2 Gas is heat transfer ratio batter then air so cooling effective is high and
friction loss is low because specific gravity is less then air.
Hydrogen gas is an explosive substance when exposed to air so rirst fill the
generator with carbon dioxide and change the carbon dioxide to hydrogen.
2) Commissioning Sequence
Generator Seal Oil system is completed
3) Major equipment's
① H2 Generation System and storage vessel (if applicable)
② CO2 Storage Vessel
③ H2 and CO2 Control System and Alanlizer
3. Hot-Commissioning
2.3 Hot Commissioning
3
49
Turbine Steam Admission
1) Objective
Make the steam admission condition by turbine bypass operation and then
steam admission to turbine and then turbine speed accelerate to rated speed as
per turbine acceleration curve.
Check the turbine condition during turbine acceleration such as vibration,
bearing temperature.
2) Commissioning Sequence
Turbine bypass operation is completed
Generator auxiliary system commissioning are completed
Turbine auxiliary system commissioning are completed
3) Major equipment's
① Overall Generating Unit
3. Hot-Commissioning
2.3 Hot Commissioning
4
50
Synchronizing
1) Objective
Synchronizing objective is Generating Unit synchronized with electrical grid and
then generating unit is parallel operation with electrical grid.
2) Commissioning Sequence
After Steam Admission
3) Major equipment's
① Exciter / AVR
② Synchronizer (if applicable)
③ Generator Circuit Breaker
3. Hot-Commissioning
2.3 Hot Commissioning
5
51
2. Commissioning Sequence
Contents
2.1 Pre-Commissioning
2.2 Cold Commissioning
2.3 Hot Commissioning
 Initial Firing, Steam Blowing & Turbine Bypass Operation
 Turbine Rolling and Synchronizing
 Overall Generating Unit Test
52
Plant Initial Load Test
1) Objective
Plant is conducted progressively increased to full load operation after
synchronizing and then find different of operating parameter with design
parameter that data is base on combustion and plant tuning.
2) Commissioning Sequence
After Synchronizing
3) Major equipment's
① Overall generating unit
3. Hot-Commissioning
2.3 Hot Commissioning
1
53
Turbine Temporary Strainer Removal
1) Objective
Generally temporary strainer is installed as turbine main steam and reheat
steam valve for turbine protection due to foreign matter.
Temporary strainer remove after turbine shutdown if archive the appointed full
load operation time.
2) Commissioning Sequence
After initial load test
3) Major equipment's
① Turbine Temporary Strainer
3. Hot-Commissioning
2.3 Hot Commissioning
2
54
Combustion Tuning
1) Objective
Adjust in put parameter such as fuel, feed water, air flow and bias damper and
then optimizer boiler efficiency and boiler combustion parameter such as boiler
outlet O2, unburned carbon, Main steam and Reheat Steam temperature and
pressure as per boiler design data
3. Hot-Commissioning
2.3 Hot Commissioning
3
55
Auto Plant Control Tuning / Unit Master Control Tuning
1) Objective
Generating unit is operated according to operated Load Demand from LDC or
Operator.
Generating unit follow the changed load demand and then unit master is
dispatch the unit load demand current target to boiler master and turbine
master.
Boiler master is dispatched which is received demand from the unit master to
boiler sub group master such as fuel master, air master and feed water master.
Sub group master control are follow the boiler master dispatch demand and
then automatically controlled air flow, fuel flow, feed water flow.
Turbine master is dispatched which is received demand for the unit master to
turbine governor controller. Turbine governor controller is adjusted Generator
Output.
Auto Plant Control Tuning and Unit Master Control Tuning means overall
generating unit is automatically controlled according to operator’s generator
output control.
3. Hot-Commissioning
2.3 Hot Commissioning
4
56
Unit Startup Test (Cold, Warm, Hot)
1) Objective
Generating units Startup Test is in order to verifying that the startup procedure
and then optimize startup parameter and method.
3. Hot-Commissioning
2.3 Hot Commissioning
5
57
Load Rejection Test
1) Objective
A load rejection test is to verify turbine governor’s response when generator
load is suddenly disappeared Incase of GCB is opened.
Turbine control valve is quickly closed, and then turbine speed maintains at
rated speed. Turbine speed is increased at first time, but instantly decreased
and maintained rated speed by turbine governor.
HP and LP bypass valve are quickly open when load rejection occurred.
Boiler is initiated runback at same time and then boiler load is quickly decreased
to around half load.
3. Hot-Commissioning
2.3 Hot Commissioning
6
58
House Load Operation
1) Objective
In case of any electrical grid problem, the operating unit will be immediately
isolated from the electrical grid and thus, it will be cutting back to house load, in
parallel with HP-LP bypass operation, till the time connection with the grid is
restored back.
3. Hot-Commissioning
2.3 Hot Commissioning
7
59
Run Back
1) Objective
if any major equipment is trip, generating unit is process is unbalanced with
control parameter at this time run back is occurred for prevent of plant trip
In case of runback is occurred, the Generating Unit load will reduce to operable
load and then runback resets later preset time.
Run Back Item (for example)
 Induced Draft Fan (50% x2)
 Forced Draft Fan (50% x2)
 Primary Air Fan (50% x2) – if applicable
 Fuel flow (oil or coal) : Actual Flow and Demand Flow are different over
20%
 Boiler Feed Water Pump (50% x2)
 Turbine Trip
3. Hot-Commissioning
2.3 Hot Commissioning
8
60
Load Change Test
1) Objective
Load Change Test is Objective is verifying that the load change capability and
tune and optimize operation parameter according to ramping ramp rate.
This test is normally conducted with Unit master control tuning.
3. Hot-Commissioning
2.3 Hot Commissioning
9
61
Emission Test
1) Objective
Emission Test is verifying that the generating unit’s emissions is compliant
environmental regulation or guarantee value such as SOx, NOx and dust during
generating unit operating.
3. Hot-Commissioning
2.3 Hot Commissioning
10
62
Reliability Test
1) Objective
Reliability test is conducted in order to verifying that the generating unit operable
reliability for commercial operation.
Normally reliability test condition is decided as per contract. Reliability test
period is normally 10 ~ 30 day and generating unit load is maintained full load or
load dispatch center’s dispatching load.
3. Hot-Commissioning
2.3 Hot Commissioning
10
63
Performance Test
1) Objective
Performance test is conducted in order to verifying that the plant efficiency and
capability such as below.
 Net Heat Rate
𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺 𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂 − 𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶
𝐼𝐼𝐼𝐼𝐼𝐼𝐼𝐼𝐼𝐼 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸
 Net Capacity
Generating Unit’s transmission power that is from generator to electrical grid.
Generating Output – Auxiliary Power Consumption
3. Hot-Commissioning
2.3 Hot Commissioning
11
64
Q&A

Contenu connexe

Tendances

Classification of steam Turbine
Classification of steam TurbineClassification of steam Turbine
Classification of steam TurbineShowhanur Rahman
 
Operation of Centrifugal Pumps
Operation of Centrifugal PumpsOperation of Centrifugal Pumps
Operation of Centrifugal PumpsSahyog Shishodia
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINESAI SHARATH GAMPA
 
Steam Turbine and Condenser
Steam Turbine and CondenserSteam Turbine and Condenser
Steam Turbine and CondenserMulugeta Wotango
 
Types of air preheaters and its advantages
Types of air preheaters and its advantagesTypes of air preheaters and its advantages
Types of air preheaters and its advantagesPreeti Agarwal
 
Heat Exchanger
Heat ExchangerHeat Exchanger
Heat ExchangerNathan
 
Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...Hassan ElBanhawi
 
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010Shaun West
 

Tendances (20)

Compressor
CompressorCompressor
Compressor
 
Gas Turbine Powerplants
Gas Turbine Powerplants Gas Turbine Powerplants
Gas Turbine Powerplants
 
Steam turbine Working
Steam turbine WorkingSteam turbine Working
Steam turbine Working
 
cooling tower
cooling tower cooling tower
cooling tower
 
Boiler Mountings
Boiler MountingsBoiler Mountings
Boiler Mountings
 
Classification of steam Turbine
Classification of steam TurbineClassification of steam Turbine
Classification of steam Turbine
 
Gas Turbine Power Plant
Gas Turbine Power PlantGas Turbine Power Plant
Gas Turbine Power Plant
 
Operation of Centrifugal Pumps
Operation of Centrifugal PumpsOperation of Centrifugal Pumps
Operation of Centrifugal Pumps
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
Steam Turbine and Condenser
Steam Turbine and CondenserSteam Turbine and Condenser
Steam Turbine and Condenser
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
This is Gas Turbine.
 This is Gas Turbine. This is Gas Turbine.
This is Gas Turbine.
 
Types of air preheaters and its advantages
Types of air preheaters and its advantagesTypes of air preheaters and its advantages
Types of air preheaters and its advantages
 
Gas turbines
Gas turbinesGas turbines
Gas turbines
 
Heat Exchanger
Heat ExchangerHeat Exchanger
Heat Exchanger
 
boilers
boilersboilers
boilers
 
Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...
 
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
Maintenance of V94 series of gas turbines, Power Gen Russia, Moscow, 2010
 

Similaire à 369051174-Basic-of-Commissioning.pdf

Operation of hydro power plants
Operation of hydro power plants Operation of hydro power plants
Operation of hydro power plants DINESHPRASAD39
 
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche..."Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...Muanisa Waras
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintananceAnasMirza10
 
"IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop""IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop"Muanisa Nisa
 
Work breakdown structure & project life cycle
Work breakdown structure & project life cycleWork breakdown structure & project life cycle
Work breakdown structure & project life cycleSayandeep Dasgupta
 
Validation utility system
Validation utility systemValidation utility system
Validation utility systemArpitSuralkar
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdfKhalidAyaz3
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.pptssuser9e9be71
 
Hot tests at Temelin completed
Hot tests at Temelin completedHot tests at Temelin completed
Hot tests at Temelin completedFrantisek Heczko
 
Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)Ashutosh Sachan
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
OCS Training Virtual - IADC Rig Equipment Inspection Certification
OCS Training Virtual - IADC Rig Equipment Inspection CertificationOCS Training Virtual - IADC Rig Equipment Inspection Certification
OCS Training Virtual - IADC Rig Equipment Inspection CertificationMuanisa Waras
 
Sphere Tank Safety Interlock Using PLC
Sphere Tank Safety Interlock Using PLCSphere Tank Safety Interlock Using PLC
Sphere Tank Safety Interlock Using PLCijsrd.com
 
OCS - Rig inspection workshop accredited by IADC - Bali Schedule
OCS - Rig inspection workshop accredited by IADC - Bali ScheduleOCS - Rig inspection workshop accredited by IADC - Bali Schedule
OCS - Rig inspection workshop accredited by IADC - Bali ScheduleMuanisa Nisa
 
OCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADCOCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADCMuanisa Waras
 

Similaire à 369051174-Basic-of-Commissioning.pdf (20)

Operation of hydro power plants
Operation of hydro power plants Operation of hydro power plants
Operation of hydro power plants
 
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche..."Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
"Rig Inspection Workshop - accredited by OCS Training Institute” Jakarta Sche...
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintanance
 
"IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop""IADC Accredited Rig Inspection Workshop"
"IADC Accredited Rig Inspection Workshop"
 
Work breakdown structure & project life cycle
Work breakdown structure & project life cycleWork breakdown structure & project life cycle
Work breakdown structure & project life cycle
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdfOn Power Plant Operation  cource In Urdu by Khalid ayaz Soomro.pdf
On Power Plant Operation cource In Urdu by Khalid ayaz Soomro.pdf
 
171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt171839416-commissioning-of-hydro-ppt.ppt
171839416-commissioning-of-hydro-ppt.ppt
 
Auditing of hvac by parag
Auditing of hvac by paragAuditing of hvac by parag
Auditing of hvac by parag
 
testing formats
testing formatstesting formats
testing formats
 
Hot tests at Temelin completed
Hot tests at Temelin completedHot tests at Temelin completed
Hot tests at Temelin completed
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
1 80 fineshed
1 80 fineshed1 80 fineshed
1 80 fineshed
 
Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)Standard boiler 500 mwerection manual (boiler auxiliaries)
Standard boiler 500 mwerection manual (boiler auxiliaries)
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
OCS Training Virtual - IADC Rig Equipment Inspection Certification
OCS Training Virtual - IADC Rig Equipment Inspection CertificationOCS Training Virtual - IADC Rig Equipment Inspection Certification
OCS Training Virtual - IADC Rig Equipment Inspection Certification
 
Sphere Tank Safety Interlock Using PLC
Sphere Tank Safety Interlock Using PLCSphere Tank Safety Interlock Using PLC
Sphere Tank Safety Interlock Using PLC
 
job des
job desjob des
job des
 
OCS - Rig inspection workshop accredited by IADC - Bali Schedule
OCS - Rig inspection workshop accredited by IADC - Bali ScheduleOCS - Rig inspection workshop accredited by IADC - Bali Schedule
OCS - Rig inspection workshop accredited by IADC - Bali Schedule
 
OCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADCOCS - Rig Inspection Workshop - accredited by IADC
OCS - Rig Inspection Workshop - accredited by IADC
 

Dernier

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Dernier (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

369051174-Basic-of-Commissioning.pdf

  • 1. VT4 Project Commissioning Dept. Technology Transfer [Day1-1] Basic of Commissioning
  • 2. 1 Index 1.1 What is Commissioning 1.2 Terminology of Commissioning 1. Summary of Commissioning 2. Commissioning Sequence 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning 1.3 Individual system and equipment test
  • 3. 2 1.1 What is Commissioning 1.2 Terminology of Commissioning 1. Summary of Commissioning Contents 1.3 Individual system and equipment test
  • 4. 3 1.1 What is Commissioning The primary objective of metallurgical plant commissioning is to ensure that all systems and equipment of a plant are installed, tested, operated, and maintained according to the operational requirements of the client. For large projects, this process usually comprises planning, execution, and control of thousands of inspection and test activities on sections to be com-missioned, and these include instrumentation, control loops, and all electrical and mechanical equipment. The process of commissioning is integrated into various phases. This is executed by the project team and includes the plant operational and engineering staff as well as the con-tractors responsible for the installation and cold commissioning. The overriding factor is the attention to detail required with respect to safety of people, protection of equipment and the environment.
  • 5. 4 1.2 Terminology 1.2.1 Pre-Commissioning Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Frequently however, Pre-Commissioning activities overlap Mechanical Completion activities and for this reason the plant should be separated into easily manageable system package, each system package will be Pre-Commissioned as a whole and isolations at the boundaries of the system package will be maintained until the completion of Pre-Commissioning activities. Pre-Commissioning activities include: checking for design conformity, checking the status of electrical, mechanical and instrument such as calibration, loop check, line check, insulation resistance, relay setting, flushing , blowing and cleaning activities.
  • 6. 5 1.2 Terminology 2. Cold-Commissioning Cold Commissioning means individual equipment and system commissioning and initial startup such as CCW system, compressed air system and feed water system etc. Cold Commissioning activities include: checking for design conformity, checking the status of individual equipment and system capability, function, interlock and reliability.
  • 7. 6 1.2 Terminology 3. Hot-Commissioning Hot commissioning means the commissioning of the plant level. In general, the commissioning activity after initial firing belongs to the hot commissioning Hot Commissioning activities include : Initial firing, Steam blowing, Turbine bypass operation, Synchronizing and plant level function test.
  • 8. 7 1) Check list before the test ① Switch Gear Status ② Shaft turning by manual ③ Start the space heater ④ Lubrication oil pump start (if applicable) ⑤ Check the insulation resistance ⑥ Motor solo test start at DCS HMI 2) Check list during the test ① Direction of rotation ② Starting current ③ Operating current ④ Vibration of Motor bearing ⑤ Temperature of Motor bearing ⑥ Temperature of Motor Winding Solo Test 1.3 Individual system and equipment test 1
  • 9. 8 No-load Test / Minimum Load Test 1) No-load Test and Minimum Load Test ① No-load Test No-load Test means equipment's running with that has no flow through the Fan in case of discharge or suction damper are closed when fan is running. ② Minimum Load Test Minimum Load Test means equipment’s running with that has minimum flow through the pump in case of suction valve open, minimum flow valve open and discharge valve closed 2) Check Point During No-Load Test and Minimum Load Test ① Direction of rotation ② Starting current and Operating current ③ Vibration of Motor bearing ④ Temperature of Motor bearing ⑤ Temperature of Motor Winding ⑥ Suction/Discharge Pressure ⑦ Flow (if applicable) 1.3 Individual system and equipment test 2
  • 10. 9 Load Test 1) Load Test The Load test is a test that is performed when the fluid flows normally to the pump or fan. 2) Check Point During Load Test ① Direction of rotation ② Starting current and Operating current ③ Vibration of Motor/Pump (Fan) bearing ④ Temperature of Motor/Pump (Fan) bearing ⑤ Temperature of Motor Winding ⑥ Suction/Discharge Pressure ⑦ Discharge Flow 1.3 Individual system and equipment test 3
  • 11. 10 2. Commissioning Sequence Contents 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning
  • 12. 11 ① Visual Inspection as per P & ID that check point is physical refection status and instruments installation status ② Cleaning of erected and installed system such as air and flue gas inside and outside and all area where works performed so that no erection parts disturb moving equipment and program cycles. ③ Flushing or Blowing the pipelines, including process media pipelines and impulse piping6. Checking for the possibility of stretching and extension for pipe lines and cables ④ Checking and preparation for operation of the spring suspensions and compensators and removing of spring loaded bolts ⑤ Lubrication for operation according to manufacture’s instructions. Pre-Commissioning Check List 2.1 Pre-Commissioning 1
  • 13. 12 ⑥ Checking the alignment of machinery and structure (example; expansion joints),and provide appropriate documents. ⑦ Leak tests and Hydraulic Test (gas, solid and fluids) of Duct or Pipe Line ⑧ Calibration for Instrument, Control Valve, MOV and Switch. ⑨ Safety Valve and Pressure Relief Valve Setting. ⑩ Signal/loop check from DCS to fields device, including check of measurement ranges and moving the appropriate equipment from DCS (stroke test). ⑪ Check all operating and alarm limits in field in system and set fixed initial values in program for startup, using set point and alarm list. ⑫ Relay Setting, PT and CT Checking for Switch Gear 2.1 Pre-Commissioning Pre-Commissioning Check List 1
  • 14. 13 2. Commissioning Sequence Contents 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning  BOP and Common Facilities  Boiler and Auxiliary System  Turbine and Auxiliary System
  • 15. 14 Power Receiving 1) Objective Electrical power back feed from the grid for generating unit startup. 2) Commissioning Sequence First of commissioning 3) Major System ① GIS or AIS ② TR ③ Switch Gear ④ DC and UPS 2. Cold-Commissioning 2.2 Cold Commissioning 1
  • 16. 15 Water Treatment System (WT) 1) Objective The water treatment facility treats the raw water and then supplies the necessary water to the plant. Depending on the application Demin. Water, Service Water, Potable Water.. 2) Commissioning Sequence after power receiving 3) Major System ① Raw Water Treatment System (Clarifier, RO, MSF) ② Potable Water Treatment System ③ Demin. Water Treatment System 2. Cold-Commissioning 2.2 Cold Commissioning 2
  • 17. 16 Waste Water Treatment System (WWT) 1) Objective WWT is a facility to purify wastewater from the plant to meet environmental standards. 2) Commissioning Sequence after complete power receiving and water treatment system commissioning. 3) Major equipments ① Waste Water Pond ② Oily Waste Water Treatment System ③ Chemical Waste Water Treatment System ④ FGD Waste Water Treatment System ⑤ Coal Yard Waste Water Treatment System 2. Cold-Commissioning 2.2 Cold Commissioning 3
  • 18. 17 Closed Cooling Water System (CCW) 1) Objective CCW is to supply cooling water to individual devices. 2) Commissioning Sequence after Power Receiving, WT, WWT. 3) Major equipments ① CCW Head Tank ② CCW Pump ③ CCW Heat Exchanger 2. Cold-Commissioning 2.2 Cold Commissioning 4
  • 19. 18 Compressed Air System 1) Objective Compressed air system is a facility that produces instrument air and service air to drive pneumatic equipment such as control valve.. 2) Commissioning Sequence after Power Receiving, WT, WWT. 3) Major equipments ① Air Compressor ② Drier ③ Air Receiving Vessel for Instrument Air ④ Air Receiving Vessel for Service Air 2. Cold-Commissioning 2.2 Cold Commissioning 5
  • 20. 19 Circulating Water System or Main Cooling Water System (CW or MCW) 1) Objective Circulating Water System is supplied cooling water to condenser, closed cooling water heat exchanger, etc. 2) Commissioning Sequence after Power Receiving 3) Major equipment's ① Intake ② Trash Rack ③ Traveling Screen and washing pump ④ Chlorination Generation System and Injection System ⑤ Circulating Water Pump (CWP) or Main Cooling Water Pump (MCWP) ⑥ Debris Filter ⑦ Condenser Tube Cleaning System ⑧ Discharge Culvert ⑨ Auxiliary Cooling Water Pump 2.2 Cold Commissioning 6 2. Cold-Commissioning
  • 21. 20 Auxiliary Steam System 1) Objective Auxiliary Steam System is to provide for necessary steam of plant startup and operation as below System  Turbine Seal Steam and Rotor Pre-Warming  Turbine Driven BFP  Deaerator  Steam Coil Air Heater  SCR Ammonia Vaporizer  Air Pre-Heater Soot Blower  Pulverizer Inerting Steam etc. 2) Commissioning Sequence after Power Receiving 3) Major equipment's ① Auxiliary Boiler (if applicable) ② Auxiliary Steam Header ③ Auxiliary Pressure Reducing Station for CRH to Aux. Steam Header ④ Auxiliary Pressure Reducing for Main Steam to Aux. Steam Header 2. Cold-Commissioning 2.2 Cold Commissioning 7
  • 22. 21 Condensate System 1) Objective Condensate System is to transfer condensate from condenser to deaerator 2) Commissioning Sequence After Water Treatment System commissioning is completed 3) Major equipment's ① Condensate Extraction Pump (CEP) ② CPP ③ Low Pressure Heater 2. Cold-Commissioning 2.2 Cold Commissioning 8
  • 23. 22 Chemical Cleaning 1) Objective  Alkali Cleaning objective is to remove organic matter in condensate and feed water system  Acid Cleaning objective is to remove inorganic matter in boiler water wall. 2) Commissioning Sequence After condensate commissioning and auxiliary steam system 3) Major equipment's ① Temporary Circulating Water Pump for Chemical Cleaning ② Temporary Heat Exchanger for Chemical Cleaning ③ Temporary Chemical Cleaning Water Mixing Tank ④ Temporary Chemical Injection Pump and Tank 2. Cold-Commissioning 2.2 Cold Commissioning 9
  • 24. 23 Feed Water System 1) Objective Feed Water System is storage feed water, deaerating in feed water, warming feed water, heat feed water and water feeding to boiler 2) Commissioning Sequence After condensate system and after Chemical Cleaning 3) Major equipment's ① Deaerator ② Feed Water Storage Tank ③ Motor Driven Boiler Feed Water Pump (MDBFP) ④ Turbine Drive Boiler Feed Water Pump (TDBFP) ⑤ High Pressure Heater 2. Cold-Commissioning 2.2 Cold Commissioning 10
  • 25. 24 Chemical Injection System 1) Objective Chemical Injection System is to control feed water and condensate pH and dissolve oxygen  All Volatile Treatment Method  pH control chemical : Ammonia or equivalent chemical  Oxygen Scavenger : Hydrazine or equivalent chemical  Boiler compound : Phosphate or equivalent chemical (Drum type boiler)  Combined Water Treatment System  Startup : AVT Method  During Stable Operation : O2 Treatment Method 2) Commissioning Sequence After Condensate and Feed water System Commissioning 3) Major equipment's ① Chemical Storage Tank ② Chemical Injection Pump 2. Cold-Commissioning 2.2 Cold Commissioning 11
  • 26. 25 Fuel Oil Supply System 1) Objective Fuel Oil Supply System is to supply fuel for boiler startup, normally boiler startup fuel is used Light Oil. 2) Commissioning Sequence After refection completed 3) Major equipment's ① Fuel Oil Storage Tank ② Fuel Oil Transfer Pump 2. Cold-Commissioning 2.2 Cold Commissioning 12
  • 27. 26 2. Commissioning Sequence Contents 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning  BOP and Common Facilities  Boiler and Auxiliary System  Turbine and Auxiliary System
  • 28. 27 Draft System 1) Objective Draft system is to supply combustion air to boiler furnace and remove flue gas to ambient. 2) Commissioning Sequence After CCW, Compressed Air system commissioning and duct leak test are completed. 3) Major equipment's ① Induced Draft Fan (IDF) ② Forced Draft Fan (FDF) ③ Gas Air Heater (GAH) or Air-preheater ④ Steam Coil Air Heater (SCAH) 2. Cold-Commissioning 2.2 Cold Commissioning 1
  • 29. 28 Boiler Startup System 1) Objective One Through Boiler is necessary boiler startup system for sub critical operation during boiler startup. separator is separate water in the steam at the boiler water wall out let and then separated water is strafing in the Separator Storage Vessel (SSV) and then separated water return to the economizer inlet by Boiler Recirculation Pump. 2) Commissioning Sequence After Feed Water System and Chemical Cleaning are Commissioning Completed 3) Major equipment's ① Boiler Recirculation Pump (BRP) ② Separator ③ Separator Storage Vessel (SSV) ④ Boiler Blow Down System 2. Cold-Commissioning 2.2 Cold Commissioning 2
  • 30. 29 Oil Burner 1) Objective Burner is to combust fuel and then fossil fuel convert the thermal energy. 2) Commissioning Sequence After Compressed Air System Commissioning 3) Major equipment's ① Oil burner ② Atomizing Air System ③ Flame Scanner ④ Ignitor 2. Cold-Commissioning 2.2 Cold Commissioning 3
  • 31. 30 2. Commissioning Sequence Contents 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning  BOP and Common Facilities  Boiler and Auxiliary System  Turbine and Auxiliary System
  • 32. 31 Turbine Lube Oil System 1) Objective Turbine Lube Oil System is providing lubricant to turbine bearing and generator bearing 2) Commissioning Sequence After CCW System is completed and Turbine rotor alignment completed 3) Major equipment's ① Lube Oil Tank ② Lube Oil Tank Exhaust Fan ③ Lube Oil Pump (AC) ④ Lube Oil Pump (DC) ⑤ Oil Purifier 2. Cold-Commissioning 2.2 Cold Commissioning 1
  • 33. 32 Turbine Turning Gear 1) Objective Turbine Turning Gear is rotate the turbine rotor from standstill condition and stretch bent turbine rotor due to rotor weight during standstill condition. Turning Gear must operate to prevent excess vent after turbine stop and then turning gear stop after completed cooling down turbine rotor temperature 2) Commissioning Sequence After turbine lube oil system completed 3) Major equipment's ① Turning Gear 2. Cold-Commissioning 2.2 Cold Commissioning 2
  • 34. 33 2. Commissioning Sequence Contents 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning  Initial Firing, Steam Blowing & Turbine Bypass Operation  Turbine Rolling and Synchronizing  Overall Generating Unit Test
  • 35. 34 Initial Firing 1) Objective Initial firing objective is integrated boiler system test such as condensate and feed water system, draft system, fuel oil supply system and burner etc. related system of boiler by burner ignition. 2) Commissioning Sequence After cold commissioning completed 3) Major equipment's ① Condensate and Feed Water System ② Fuel Oil Supply System ③ Drafty System ④ Burner 3. Hot-Commissioning 2.3 Hot Commissioning 1
  • 36. 35 Steam Blowing 1) Objective Steam Blowing Objective is to protect turbine due to foreign matter from the boiler and main steam and reheat steam line. 2) Commissioning Sequence After Initial Firing 3) Major equipment's ① Condensate and Feed Water System ② Fuel Oil Supply System ③ Drafty System ④ Burner ⑤ Main steam, reheat steam and HP/LP bypass station ⑥ Temporary Piping and Silencer for Steam Blowing 3. Hot-Commissioning 2.3 Hot Commissioning 2
  • 37. 36 Turbine Seal Steam System 1) Objective The section, where the steam turbine rotor exits through the casing is called gland, and labyrinth fins are installed there. Seal steam is supplied to seal the section. Also, a gland steam condenser is installed to drain steam leaking from the gland. Seal steam should always be provided to the turbine, when vacuum condition is maintained in the condenser. If seal steam is not provided, the vacuum in the condenser will pull ambient air from the atmosphere through the gland. The ambient air, which is at a low temperature, will cool the gland rapidly and as a result the gland casing may deform. This would cause contact between rotating surface and stationary surface resulting in damage to the rotor. 2) Commissioning Sequence After turbine turning gear commissioning and complete turbine seal steam line steam blowing completed 3) Major equipment's ① Turbine Seal Steam Supply and Drain Header and Piping ② Gland Steam Condenser ③ Gland Steam Condenser Exhaust Fan 3. Hot-Commissioning 2.3 Hot Commissioning 3 Note : This activity is possible before initial firing if seal steam line blowing is completed by auxiliary steam
  • 38. 37 Condenser Vacuum Pump 1) Objective Condenser Vacuum Pump is to remove non-condensable gas in the condenser when turbine operating and make condenser vacuum condition for turbine operating before the boiler ignition. 2) Commissioning Sequence After CW System Commissioning 3) Major equipment's ① Condenser Vacuum Pump 3. Hot-Commissioning 2.3 Hot Commissioning 4 Note : This activity is possible before initial firing
  • 39. 38 Condenser Vacuum Pulling 1) Objective This test is in order to the verifying that the Condenser vacuum pressure is achieved as Turbine bypass operation starting permissive. 2) Commissioning Sequence After turbine seal steam system and condenser vacuum pump commissioning 3) Major equipment's ① Condenser ② Turbine Seal Steam System ③ Condenser Vacuum Pump 3. Hot-Commissioning 2.3 Hot Commissioning 5 Note : This activity is possible before initial firing if seal steam line blowing is completed by auxiliary steam
  • 40. 39 Turbine Bypass Operation 1) Objective Turbine bypass operation is integrated generating unit operation test exclude turbine system. Main steam and reheat steam are bypassing HP, IP and LP turbine by HP/LP turbine bypass station. Generating unit is make turbine steam admission condition such as steam pressure, steam temperature and steam purity by turbine bypass operation after boiler firing 2) Commissioning Sequence After steam blowing and condenser vacuum pulling completed. 3) Major equipment's ① Boiler and Auxiliary System ② BOP and Common System ③ Turbine bypass station 3. Hot-Commissioning 2.3 Hot Commissioning 6
  • 41. 40 Coal Firing Test 1) Objective Coal firing test objective is actual coal combustion test for rerated system such as coal silo, coal feeder and pulverizer. 2) Commissioning Sequence After steam blowing and condenser vacuum pulling completed. 3) Major equipment's ① Coal Handling System ② Coal Silo ③ Coal Feeder ④ Pulverize ⑤ Coal Burner 3. Hot-Commissioning 2.3 Hot Commissioning 7 Note : This activity is possible before initial firing if seal steam line blowing is completed by auxiliary steam
  • 42. 41 SCR Test 1) Objective Selective catalytic reduction (SCR) is a means of converting nitrogen oxides, also referred to as NOx with the aid of a catalyst into diatomic nitrogen (N2) , and water (H 2O). A gaseous reductant, typically anhydrous ammonia, aqueous ammonia or urea, is added to a stream of flue or exhaust gas and is adsorbed[citation needed] onto a catalyst. Carbon dioxide, CO2 is a reaction product when urea is used as the reductant. 2) Commissioning Sequence After steam blowing and condenser vacuum pulling completed. 3) Major equipment's ① Catalyst ② Ammonia Unloading and Storage Tank ③ Ammonia Vaporizer ④ Ammonia Dilution Blower 3. Hot-Commissioning 2.3 Hot Commissioning 8
  • 43. 42 ESP 1) Objective Electrostatic Precipitation is a physical process by which particulate suspended in a gas stream is electrically charged in a corona filed and under the influence of the electric field, is driven to a collecting surface, separating it from the gas. 2) Commissioning Sequence Before coal firing starting 3) Major equipment's ① EP Casing ② Transformer Rectifier ③ Seal Air Blower ④ Ash Hopper 3. Hot-Commissioning 2.3 Hot Commissioning 9 Note : This activity is possible before initial firing as per local requlation
  • 44. 43 FGD 1) Objective FGD is conducted removing SOx in the flue gas. The SOx-Absorption is achieved by natural alkalinity present in seawater in a absorber, where the raw flue gas comes into an intensive contact to the sprayed seawater. Thus the SOx is absorbed with optimal removal efficiency. CaCO3 + SO2→ CaSO3 + CO2 (gas) 2) Commissioning Sequence Conduct with Coal Firing Test 3) Major equipment's (Sea Water type FGD) ① Absorber ② Sea Water Spray Pump ③ Aeration Basin ④ GGH 3. Hot-Commissioning 2.3 Hot Commissioning 10
  • 45. 44 Safety Valve Popping Test 1) Objective Safety Valve is to prevent due to overpressure of boiler system 2) Commissioning Sequence During Turbine bypass operation 3) Major equipment's ① Safety Valve of Super Heater and Reheater 3. Hot-Commissioning 2.3 Hot Commissioning 11
  • 46. 45 2. Commissioning Sequence Contents 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning  Initial Firing, Steam Blowing & Turbine Bypass Operation  Turbine Rolling and Synchronizing  Overall Generating Unit Test
  • 47. 46 Stator Cooling Water System 1) Objective The stator winding liquid cooling system supplied deionized water to the stator for cooling the stator winding. 2) Commissioning Sequence After erection and demin. water treatment system completed 3) Major equipment's ① Stator Winding Cooling Water Tank ② Stator Cooling Pump ③ Stator Water Cooler ④ Stator Leakage Monitoring System ⑤ De-ionizer 3. Hot-Commissioning 2.3 Hot Commissioning 1
  • 48. 47 Generator Seal Oil System 1) Objective Generator Seal Oil System is to prevent of H2 gas leakage from generator inside through generator rotor between casing surface. 2) Commissioning Sequence Turbine Lube Oil System Completed 3) Major equipment's ① Vacuum tank ② Main Seal Oil Pump ③ Emergency Seal Oil Pump ④ Recirculation Seal Oil Pump ⑤ Seal Oil Vacuum Pump ⑥ Liquid Detector 3. Hot-Commissioning 2.3 Hot Commissioning 2
  • 49. 48 H2 / CO2 Control System 1) Objective H2 Gas is heat transfer ratio batter then air so cooling effective is high and friction loss is low because specific gravity is less then air. Hydrogen gas is an explosive substance when exposed to air so rirst fill the generator with carbon dioxide and change the carbon dioxide to hydrogen. 2) Commissioning Sequence Generator Seal Oil system is completed 3) Major equipment's ① H2 Generation System and storage vessel (if applicable) ② CO2 Storage Vessel ③ H2 and CO2 Control System and Alanlizer 3. Hot-Commissioning 2.3 Hot Commissioning 3
  • 50. 49 Turbine Steam Admission 1) Objective Make the steam admission condition by turbine bypass operation and then steam admission to turbine and then turbine speed accelerate to rated speed as per turbine acceleration curve. Check the turbine condition during turbine acceleration such as vibration, bearing temperature. 2) Commissioning Sequence Turbine bypass operation is completed Generator auxiliary system commissioning are completed Turbine auxiliary system commissioning are completed 3) Major equipment's ① Overall Generating Unit 3. Hot-Commissioning 2.3 Hot Commissioning 4
  • 51. 50 Synchronizing 1) Objective Synchronizing objective is Generating Unit synchronized with electrical grid and then generating unit is parallel operation with electrical grid. 2) Commissioning Sequence After Steam Admission 3) Major equipment's ① Exciter / AVR ② Synchronizer (if applicable) ③ Generator Circuit Breaker 3. Hot-Commissioning 2.3 Hot Commissioning 5
  • 52. 51 2. Commissioning Sequence Contents 2.1 Pre-Commissioning 2.2 Cold Commissioning 2.3 Hot Commissioning  Initial Firing, Steam Blowing & Turbine Bypass Operation  Turbine Rolling and Synchronizing  Overall Generating Unit Test
  • 53. 52 Plant Initial Load Test 1) Objective Plant is conducted progressively increased to full load operation after synchronizing and then find different of operating parameter with design parameter that data is base on combustion and plant tuning. 2) Commissioning Sequence After Synchronizing 3) Major equipment's ① Overall generating unit 3. Hot-Commissioning 2.3 Hot Commissioning 1
  • 54. 53 Turbine Temporary Strainer Removal 1) Objective Generally temporary strainer is installed as turbine main steam and reheat steam valve for turbine protection due to foreign matter. Temporary strainer remove after turbine shutdown if archive the appointed full load operation time. 2) Commissioning Sequence After initial load test 3) Major equipment's ① Turbine Temporary Strainer 3. Hot-Commissioning 2.3 Hot Commissioning 2
  • 55. 54 Combustion Tuning 1) Objective Adjust in put parameter such as fuel, feed water, air flow and bias damper and then optimizer boiler efficiency and boiler combustion parameter such as boiler outlet O2, unburned carbon, Main steam and Reheat Steam temperature and pressure as per boiler design data 3. Hot-Commissioning 2.3 Hot Commissioning 3
  • 56. 55 Auto Plant Control Tuning / Unit Master Control Tuning 1) Objective Generating unit is operated according to operated Load Demand from LDC or Operator. Generating unit follow the changed load demand and then unit master is dispatch the unit load demand current target to boiler master and turbine master. Boiler master is dispatched which is received demand from the unit master to boiler sub group master such as fuel master, air master and feed water master. Sub group master control are follow the boiler master dispatch demand and then automatically controlled air flow, fuel flow, feed water flow. Turbine master is dispatched which is received demand for the unit master to turbine governor controller. Turbine governor controller is adjusted Generator Output. Auto Plant Control Tuning and Unit Master Control Tuning means overall generating unit is automatically controlled according to operator’s generator output control. 3. Hot-Commissioning 2.3 Hot Commissioning 4
  • 57. 56 Unit Startup Test (Cold, Warm, Hot) 1) Objective Generating units Startup Test is in order to verifying that the startup procedure and then optimize startup parameter and method. 3. Hot-Commissioning 2.3 Hot Commissioning 5
  • 58. 57 Load Rejection Test 1) Objective A load rejection test is to verify turbine governor’s response when generator load is suddenly disappeared Incase of GCB is opened. Turbine control valve is quickly closed, and then turbine speed maintains at rated speed. Turbine speed is increased at first time, but instantly decreased and maintained rated speed by turbine governor. HP and LP bypass valve are quickly open when load rejection occurred. Boiler is initiated runback at same time and then boiler load is quickly decreased to around half load. 3. Hot-Commissioning 2.3 Hot Commissioning 6
  • 59. 58 House Load Operation 1) Objective In case of any electrical grid problem, the operating unit will be immediately isolated from the electrical grid and thus, it will be cutting back to house load, in parallel with HP-LP bypass operation, till the time connection with the grid is restored back. 3. Hot-Commissioning 2.3 Hot Commissioning 7
  • 60. 59 Run Back 1) Objective if any major equipment is trip, generating unit is process is unbalanced with control parameter at this time run back is occurred for prevent of plant trip In case of runback is occurred, the Generating Unit load will reduce to operable load and then runback resets later preset time. Run Back Item (for example)  Induced Draft Fan (50% x2)  Forced Draft Fan (50% x2)  Primary Air Fan (50% x2) – if applicable  Fuel flow (oil or coal) : Actual Flow and Demand Flow are different over 20%  Boiler Feed Water Pump (50% x2)  Turbine Trip 3. Hot-Commissioning 2.3 Hot Commissioning 8
  • 61. 60 Load Change Test 1) Objective Load Change Test is Objective is verifying that the load change capability and tune and optimize operation parameter according to ramping ramp rate. This test is normally conducted with Unit master control tuning. 3. Hot-Commissioning 2.3 Hot Commissioning 9
  • 62. 61 Emission Test 1) Objective Emission Test is verifying that the generating unit’s emissions is compliant environmental regulation or guarantee value such as SOx, NOx and dust during generating unit operating. 3. Hot-Commissioning 2.3 Hot Commissioning 10
  • 63. 62 Reliability Test 1) Objective Reliability test is conducted in order to verifying that the generating unit operable reliability for commercial operation. Normally reliability test condition is decided as per contract. Reliability test period is normally 10 ~ 30 day and generating unit load is maintained full load or load dispatch center’s dispatching load. 3. Hot-Commissioning 2.3 Hot Commissioning 10
  • 64. 63 Performance Test 1) Objective Performance test is conducted in order to verifying that the plant efficiency and capability such as below.  Net Heat Rate 𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺𝐺 𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂𝑂 − 𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴𝐴 𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 𝐼𝐼𝐼𝐼𝐼𝐼𝐼𝐼𝐼𝐼 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸  Net Capacity Generating Unit’s transmission power that is from generator to electrical grid. Generating Output – Auxiliary Power Consumption 3. Hot-Commissioning 2.3 Hot Commissioning 11