Energy Policy Feedback (Power)
Focus Group Discussion
Jakarta, 18 October 2019
Sustainable Infrastructure Assistance Program (46380-023)
TA 9511–INO: Indonesia Energy Sector Assessment and Priorities 2020–2024
1
Contents
2
1. Background
2. Current conditions in the Indonesian power sector
3. Policy identification and assessment
4. Proposed policies
1. Background
3
Background
4
 ADB is supporting Bappenas in the identification of key energy related pillars and
indicators to inform the Medium-Term National Development Plan (RPJMN) 2020–2024
 As part of this, Castlerock has been contracted to assist with policy advice for energy
sector planning in the form of an Energy Sector Assessment and Priorities for 2020–2024.
Areas of focus include:
(i) the electricity sector
(ii) increasing renewable energy
(iii) sustainable energy pricing
(iv) energy efficiency measures
(v) the identification of technological and regulatory innovation
 An assessment of the energy sector’s performance and identification of key issues was
consulted on at a previous FGD. The current FGD consults on potential policy responses
to the previously identified issues
The analysis has been complemented by a national
survey of public opinion
5
2. Current conditions in the Indonesian power sector
6
Energy efficiency is Indonesia’s largest and cheapest
energy resource, but little attention goes to harnessing it
7
From Amory Lovins, Asia Clean Energy Forum 2019
Capacity expansion has enabled growing demand to be
met, but with increasing coal dependency
8
RUPTL 2018-28. Derated capacity is shown. The small reduction in capacity from 2014 to 2015 is due principally to diesel generator retirements
Between 2011 and 2018, generation capacity increased
by 17 GW (52%) with 11 GW being coal-fired
The share of coal in the generation mix has increased
from 44% to 60%, replacing oil-fired generation
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2011 2012 2013 2014 2015 2016 2017 2018 (Jan-
Oct)
Hydro Coal Gas Oil Geothermal Other
0
10,000
20,000
30,000
40,000
50,000
60,000
2011 2012 2013 2014 2015 2016 2017 2018
Deratedcapacity(MW)
Hydro Coal Gas Oil Geothermal Other Peak demand
Renewables expansion is falling far short of the levels
required to meet targets
9
Over the last 10 years, PLN has added 2.3 GW of renewables capacity. Over the next 10 years, PLN needs to add 17-
31 GW of renewables capacity, a 10x increase in the rate of additions
0
5
10
15
20
25
30
35
1 2 3 4 5 6 7 8 9 10
Cumulativecapacityadditions(GW)
Year (2009-18 for actual and 2019-28 for planned)
Actual geothermal (2009-18) Actual hydro (2009-18) Actual other renewables (2009-18) RUKN 2019-38 RUPTL 2019-28
RUKN 2019-38, RUPTL 2018-28 and consultant calculations
Electrification is nearing 100%, but still requires very
significant expansion in absolute terms
10
• 996,000 households without electricity (1.5%)
• 1,340,000 with non-PLN supply (2.0%) – for many less
than Tier 3 service
Off-grid supply and subsidized connections will be
increasingly important in reaching remaining households
– not more generating capacity on large systems
BPS SUSENAS 2018 – primary source of lighting ESDM July 2019
Off-grid represents 28% of
planned 2019 connections
Subsidies are rising again, after a period of decline
11
Subsidies now exceed 2015 levels, despite the major
reforms to tariffs in that year
Electricity subsidies remain poorly targeted. <25% of
450VA customers are in the bottom 20% of households
ESDM July 2019 SUSENAS 2017 and consultant calculations
12.3%
11.0%
10.6% 10.2%
9.8% 9.5% 9.2% 9.2% 9.1% 9.3%
0%
2%
4%
6%
8%
10%
12%
14%
1 2 3 4 5 6 7 8 9 10
Shareoftotalcustomers
Expenditure decile (1 = lowest 10%)
450 VA connections by expenditure decile
101.2 99.3
56.6 58.0
45.7 48.1
65.3
58.6
0
20
40
60
80
100
120
101.2 99.3 56.6 58.0 45.7 48.1 65.3 58.6
2013 2014 2015 2016 2017 2018 2019 2020
Final APBN RAPBN
RPtrillion
Excessive and badly-targeted investment contributes to
rising costs and subsidies
12
Reserve margins are planned to greatly exceed targets
Meanwhile, inadequate networks mean that service
quality remains poor in many regions
RUPTL 2019-28 PLN Statistics 2018
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Margin(%)
Capacity(MW)
Existing (Derated) Ongoing and Committed
Planned Planned reserve margin
Target reserve margin
…although PLN has also consistently failed to deliver
against planned capacity expansion
13
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
110,000
120,000
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Total Installed Capacity, MW
Actual Total Capacity RUPTL 2011‐2020 RUPTL 2013‐2022
RUPTL 2015‐2024 RUPTL 2017‐2026 RUPTL 2019‐2027
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
milliontCO2
NDC - BAU NDC - Unconditional
Pusdatin - BAU Reported actual
It is not possible to assess how fast emissions are
growing and their compliance with NDC commitments
14
From 2012 to 2018, reported emissions grew at 0.8% pa
compared to an NDC commitment of 5.8% pa
Major revisions to estimated energy consumption mean
that reported data is unreliable and inconsistent
BP Statistical Review 2018, Pusdatin (2016) and Indonesia First NDC ESDM Handbook of Economic and Energy Statistics (various years)
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
thousandBOE
2018 edition 2016 edition 2015 edition
2014 FEC (thousand BOE)
2015 HEES : 1,292,796
2016 HEES : 1,114,003 (-14%)
2018 HEES : 855,552 (-34%)
• Actual 2018 emissions are
estimated at 28% below the BAU
level assumed in the NDC
• Pusdatin projections are for BAU
emissions by 2030 to be 40% below
the BAU level assumed in the NDC
NDC commitment
Reduce energy sector
emissions to 19% below
BAU by 2030
3. Policy identification and assessment
15
Major challenges for the sector
16
Inefficient use of
energy
Poor planning Badly-targeted
subsidies
• Higher costs of clean
technologies cannot be
recovered by PLN – leads
to caps on prices that PLN
will pay
• ‘Locked-in’ investments in
coal reduce the ‘space’ for
clean energy capacity
expansion
• Targets are poorly related
to NDC commitments
Slow pace of
decarbonisation
• Energy data and plans
using this are inconsistent
and subject to frequent
and large revisions
• Plans are not based on
cost-benefit analysis and
technology selections do
not reflect social costs
• Lack of external oversight
and transparency
• Over-emphasis on
generation expansion
rather than network
enhancement
• Lack of incentives to
improve energy efficiency
at both production and
consumption levels
• Plans are oriented
towards increasing
consumption, not
improving efficiency
• Increases fiscal cost of
subsidies and reduces
public funds available for
other purposes, such as
supporting clean energy
• Worsens bias against
clean energy with
perceived higher costs
• Counteracts measures to
improve energy efficiency
The energy value chain
17
PRIMARY TRANSFORMATION END-USE
Electricity *
Oil and gas
Refineries, Oil products,
LPG, LNG, gas
pipelines
Coal
Oil
Natural Gas
Households
Industry and Commerce
Transport
Other
ENERGY EFFICIENCY
Biofuels
* Renewable energy resources used principally for
power production are considered under Electricity OVERALL SECTOR MANAGEMENT
Renewables *
Solar, wind, geothermal, hydro,
biomass, waste-to-energy
Key power sector policies and the value chain
[Non-power policies are covered in a separate presentation]
18
OVERALL SECTOR MANAGEMENT
PRIMARY ENERGY
ENERGY TRANSFORMATION – Electricity
END USE – Electricity
1. Redefine and clarify emissions targets
2. Improve data reporting and policy analysis
3. Replace the PLN coal price cap with an export levy
4. Strengthen regulation
5. Separate planning, procurement and system operation from PLN
6. Accelerate use of renewable energy
7. Implement non-PLN off-grid supply
8. Optimise delivery of electricity subsidies
9. Promote end-use efficiency
Energy efficiency is a fundamental theme
19
End-UseTransformation
 Huge potential for savings across the value chain
 6 of 9 proposed electricity policies promote efficiency
Production
Pricing&
Subsidies
Planning&
Operations
Physical
measures
2. Improve data reporting and policy analysis
3. Replace coal price cap with an export levy
5. Separate SB+SO
4. Strengthen power sector regulation
8. Optimize electricity subsidies
9. Building, MEPS, Industrial
end-use efficiency
Mapping electricity policies to challenges
20
Inefficient use of
energy
Poor planning Badly-targeted
subsidies
Slow pace of
decarbonisation
1. Redefine and clarify emissions targets
3. Replace the PLN coal price
cap with an export levy
4. Strengthen regulation
5. Separate system planning, generation procurement and system operation from PLN
6. Accelerate use of renewable energy
7. Implement non-PLN off-grid supply
8. Optimise delivery of
electricity subsidies
9. Promote end-use efficiency
2. Improve data reporting and policy analysis
Impacts are assessed using the energy ‘trilemma’
framework
SECURITY
SUSTAINABILITY ACCESS & EQUITY
Effective management of primary energy supply from domestic
and external sources, reliability of energy infrastructure, and
ability of energy providers to meet current and future demand.*
Accessibility and affordability of energy
supply across the population.*
Additionally, fair distribution of costs and
benefits of energy supply, for both present
and future generations, and open and
transparent processes for sector
management.
Encompasses achievement of supply- and
demand-side energy efficiencies and
development of energy supply from
renewable and other low-carbon sources.*
* Definition from World Energy Council, “World Energy Trilemma Index 2017”
21
Understanding the impacts
22
SUSTAINABILITY
SECURITY
EQUITY
Highly supportive
Neutral
Highly
counterproductive
In this example, the policy is:
• Highly supportive of sustainability
• Neutral impact on equity
• Moderately counterproductive
with respect to security
Feedback questionnaire
23
 There will be a discussion period after the
presentation and periodic opportunities for questions
 We have also left a questionnaire on your seat
• Electricity (morning session) on one side, Non-Electricity
(afternoon session) on the other
• Any policies you think we have missed?
• Simple evaluation of policies we propose (Agree,
Disagree, Neutral)
• Comments on individual policies, if any
• Optional – your name, institution and contact email
 Please submit your completed questionnaire in the
box near the door when you leave
4. Proposed policies
24
4. Proposed policies
a. Overall Sector Management
25
1. Redefine and clarify emissions targets
26
Issues
 Current NDC targets are essentially
meaningless given data problems and
unrealistic baseline
 As a result, there is a lack of clear
emissions targets to guide planning
Proposed policy
 Redefine emissions target as being 19%
below most recent BAU estimate (ie, not
NDC estimate) by 2030
 Pusdatin to update and publish BAU
projections whenever the underlying data
is revised
As currently defined, emissions could increase by 150%
and still remain within the NDC commitment
Consultant team calculations
535
273
463
820
1,134
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
Actual 19% below
Pusdatin BAU
Pusdatin - BAU NDC -
Unconditional
NDC - BAU
2018 2030
MtCO2
3.5% pa
5.3% pa
8.1% pa
9.9% pa
1. Redefine and clarify emissions targets
Impacts
27
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
2. Improve data reporting and policy analysis
28
Issues
 Energy sector data is currently produced
by multiple agencies, is inconsistent and
is subject to large revisions
 Multiple energy sector plans (RUEN /
RUKN / RIKEN / RUPTL) with frequent
gaps and inconsistencies between them
Proposed policy
 Designate Pusdatin ESDM as the source
of official government energy data
 Annually review progress against targets,
consistency across plans and the impacts
of proposed new policies
 Facilitates comprehensive consideration
of energy efficiency
Electricity demand forecasts vary widely across different
planning documents
Consultant team calculations
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
TWh
Actual RUEN 2015-50 RUKN 2019-38 (medium case) RUPTL 2019-28
2. Improve data reporting and policy analysis
Impacts
29
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
4. Proposed policies
b. Primary Energy
30
3. Replace the PLN coal price cap with an export levy
31
Issues
 Increases mismatch between coal
generation’s financial costs and its
economic costs to society, distorting
planning and operational decisions
 Suppressed prices lead to inefficiency
 Extremely inefficient means of subsidizing
electricity to poor households—most
benefits accrue to large consumers
Proposed policy
 Remove coal price cap
 Apply an additional export levy and
allocate the proceeds to targeted
electricity subsidies
Coal prices would have exceeded the $70/tonne cap in 8
out of the last 10 years
World Bank. Assumes 6,000 kcal/kg
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
Jan2009
Jun2009
Nov2009
Apr2010
Sep2010
Feb2011
Jul2011
Dec2011
May2012
Oct2012
Mar2013
Aug2013
Jan2014
Jun2014
Nov2014
Apr2015
Sep2015
Feb2016
Jul2016
Dec2016
May2017
Oct2017
Mar2018
Aug2018
Jan2019
Jun2019
$/t
Australia, actual PLN cap
3. Replace the PLN coal price cap with an export levy
Impacts
32
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
4. Proposed policies
c. Energy Transformation – Electricity
33
4. Strengthen regulation
34
Issues
 Inadequate resources within DJK to oversee
planning, procurement and to assess efficiency
of PLN’s operations
 Responsibilities shared across MEMR, MOF
and MSOE, diluting oversight
 No transparency or structured public
participation
 No apparent consideration of economic costs
and benefits – leads to inefficiency
Proposed policy
 Establish a new regulatory agency through a
Government or Presidential Regulation
 Builds on DJK, supervised by ESDM but
governed and budgeted by a supervisory
commission (Partial SKK Migas model)
• Review of assumptions and analysis for
preparation of the system plan on and
economic basis
• Development and supervision of generation
procurement processes
• Supervision of system operation in line with the
Grid Code
• Enumeration of terms and conditions of
licenses
• Analysis of operators costs and performance as
a basis for recommending service/tariff
payments
• Conducting public engagement.
Proposed primary functions of a regulatory agency
4. Strengthen regulation
Public Opinion
35
While PLN is generally seen as performing well, there remains strong support for a greater public role in energy
planning and regulation
4. Strengthen regulation
Impacts
36
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
5. Separate planning, procurement and system
operation from PLN
37
Issues
 Conflicts of interest between PLN’s
multiple roles (eg, favouring PLN-owned
capacity in system operating decisions)
 Internalising planning and operational
decisions reduces transparency and
access to alternative views
 PLN generation subsidiaries are
“financially malnourished” due to transfer
prices below full costs
 PLN is vulnerable to pressures from
vested interests
 Planning currently conducted on basis of
PLN’s interests, not the nation’s
Proposed policy
 Phased implementation of the
“independent” system operator as
envisaged in RUKN 2019-2038
• Separation of system operator + single
buyer from PLN
• Transfer of PLN-owned generation to
subsidiary companies
• PPAs put in place with the single buyer
 Accompanied by regulatory, tariff and
subsidy reforms
 Transition in stages based on
achievement of pre-determined
milestones and pre-requisites
 No asset unbundling
5. Separate planning, procurement and system
operation from PLN
38
• Requires step-by-step
transition, with specific
actions by PLN,
Government and IPPs
• Must be conducted in
conjunction with tariff,
subsidy and regulatory
reform
• Mitigates PLN conflicts of
interest, helps insulate
PLN from vested interests,
leads to greater efficiency
of investment and
operations, strengthens
PLN’s generation business
National SB+SO Entity
Competent & Transparent Regulation
PLN 
GencoIPP
Distribution
Single 
Buyer
System 
Operator
Customers
Transmission
PLN Group
Geographic
cross‐subsidy*
PPAs
SOA
TSA
DSAs
Agreements
Energy flows
Cash flows
GovernmentDirect 
subsidy
* As collected from lower cost systems under a national 
uniform tariff
Cost recovery tariffs
5. Separate planning, procurement and system
operation from PLN Impacts
39
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
6. Accelerate use of renewable energy
40
Issues
 Indonesia’s deployment of renewable
energy falls far below targets and potential
 Financing and tax incentives are available
but numerous impediments remain
 Caps on prices are a major barrier
Proposed policy
 End linkage of prices to BPP and replace
by prices based on economic benefits
 Consider subsidies to PLN to close any
gap between price and avoided costs
 Address the other significant barriers
0
500
1,000
1,500
2,000
2,500
3,000
3,500
JawaBarat
JawaTengah
DKIJakarta
Banten
Bali
JawaTimur
Lampung
SumateraBarat
S2JB
SulawesiSelatan
SumateraUtara
KalimantanTimurdan…
KalimantanBarat
Riau
Aceh
KalimantanSelatandan…
Belitung
Lombok
Papua(Jayapura)
FloresBagianBarat
Timor
Bangka
Tambara
Sumba
Maluku(Ambon)
FloresBagianTimur
Rp/kWh
Geothermal cost
1,754 Rp/kWh
National Average BPP
1,119 Rp/kWh
PLN (2019) and BPK (2019). Geothermal costs are shown for Java-Bali and may be higher
in more remote grid
Current generation BPP-based price caps make many
renewables projects unviable
6. Accelerate use of renewable energy
Multiple actions are required
41
1. Establish a technically capable regulator
2. Ensure regulatory transparency
3. Provide for public participation
9. Separate Single Buyer/System
Operator functions from PLN
10. Introduce new system
planning tools
13. Introduce modern grid
management practices
11. Introduce balanced PPAs in line
with international practice
5. Require system planning on
an economic basis
7. Relax foreign investment &
local content restrictions
6. De-risk projects in advance of
tenders, e.g. land acquisition
4. Remove BPP price caps &
require reverse auctions
12. Streamline procurement &
negotiations
8. Provide loan, subsidies and/or
credit enhancementsPLN / MSOE
MoF
PLN / MSOE
PLN / MSOE
PLN / MSOE
PLN / MSOE
President
President
President
MEMR
MEMR
Various
President / MoInd
6. Accelerate use of renewable energy
Public Opinion (1)
42
Among those who are aware, there is strong support for renewable energy
6. Accelerate use of renewable energy
Public Opinion (2)
43
Concerns over price impacts remain a barrier. However, there is a greater willingness to pay more if renewable energy
also delivers local economic development and supports access for remote areas
6. Accelerate the use of renewable energy
Impacts
44
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
7. Implement non-PLN off-grid supply
45
Issues
 PLN has proven reluctant to give up rights
to supply in remote areas
 But remote supply is costly, and requires
technologies and approaches not well-
suited to PLN
Proposed policy
 Build upon the framework in Permen
ESDM 38/2016 for off-grid supplies
 Establish mechanisms to identify areas for
off-grid supply, competitive selection of
suppliers and administration of subsidies
 Establish an off-grid subsidy mechanism
In remote areas, grid extension to all households is
infreasible. Off-grid supply will be required
ADB, Least-Cost Electrification Plan for Maluku and Papua, 2019
7. Implement non-PLN off-grid supply
Impacts
46
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
4. Proposed policies
d. End-Use – Electricity
47
8. Optimise delivery of electricity subsidies
48
Issues
 Inefficient targeting of subsidies
• <25% of 450VA customers are low-
income households
• ~40% of low-income households are
supplied at connections of 900+VA
 Leads to higher subsidies than needed
and to the use of alternatives, such as
suspending tariff adjustments
 Leads to inefficient consumption
Proposed policy
 Replace blanket 450VA subsidies with
means-tested subsidies, using the UDB
 Restore automatic tariff adjustments
Better targeting could reduce 450VA subsidies by up to Rp 19
trillion annually (33% of 2020 RAPBN)
Consultant calculations using Susenas 2017 data and PLN billing data for 2018
The calculation presented here assumes that non-subsidized customers do not reduce their
consumption in response to the tariff increase following withdrawal of subsidies. The
available evidence from the impacts of earlier tariff revisions is that such impacts are small.
The calculation also does not allow for subsidies being paid to low-income households with
900+VA connections, who currently are non-subsidised
450VA customers only Without policy With policy
All Subsidised
Non-
subsidised
Customers millions 23.25 5.81 17.44
Share 25% 75%
Average revenue (a) Rp/kWh 379 359 1,352
Sales TWh 24.3 4.4 19.9
Share 18% 82%
Revenues Rp trillion 9.2 1.6 26.9
Change with policy Rp trillion +19.3
(a) Assumes non-subsidised tariff is increased to the 900VA tariff
8. Optimise delivery of electricity subsidies
Public Opinion (1)
49
Current subsidies (including non-energy subsidies) are generally perceived to be poorly targeted
8. Optimise delivery of electricity subsidies
Public Opinion (2)
50
The continuing use of subsidies to lower tariffs, rather than their replacement by direct subsidies, is preferred by around
half of all households
8. Optimise delivery of electricity subsidies
Public Opinion (3)
51
There is evidence of an acceptance of reduced subsidies, if supply quality and access to electricity is improved
8. Optimise delivery of electricity subsidies
Public Opinion (4)
52
Among unelectrified households near to the existing grid, connection fees are the major barrier—suggesting a need to
switch subsidies from consumption to connection
8. Optimize delivery of electricity subsidies
Impacts
53
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
9. Promote end-use efficiency: Industry
54
Issues
 Evidence of significant potential to
improve energy efficiency in industry
 Current ESCO market very under-
developed, meaning little of this potential
is being realised
Proposed policy
 Enforce PP 70/2009 (energy audits)
 Higher Minimum Efficiency Performance
Standards (MEPS) for electric motors
 Consider dedicated industry energy
efficiency financing facility (under PT SMI)
Adopting Chinese-level MEPS for electric motors could alone
save 7.7 PJ (2.1 TWh / 350 MW) by 2030
IEA (2016). IE1 corresponds to current Indonesian MEPS proposals and IE2 to Chinese standards for
electric motors. The calculation of capacity (MW) savings assumes an average capacity factor of 70%
9. Promote end-use efficiency: Buildings
55
Issues
 Evidence of significant potential to
improve energy efficiency in buildings
 Little incentive for new ‘green’ buildings
 Under-developed ESCO market
Proposed policy
 All government facilities required to
reduce energy consumption by 17%* by
2025, creating a market for ESCOs
 National roll-out of a Green Building Code
using the Jakarta and Bandung models
Indonesian buildings are only around two-thirds as
energy-efficient as those in Japan
IECES (2016) using data from JICA (2009)
* National target specified in Draft RIKEN (2013)
9. Promote end-use efficiency: Appliances
56
Issues
 Existing minimum energy performance
standards (MEPS) cover CFLs, but
these are being displaced by LEDs
 MEPS under development for clothes
washers, well pumps, and televisions,
and possibly water coolers or irons
Proposed policy
 Expand the coverage of MEPS
 Make existing and proposed MEPS
more stringent, bringing them closer to
Best-Available-Technology levels
 Phase in BAT requirements to allow time
for consumers to adjust
Improved appliance efficiency could reduce peak electricity
demand by as much as 25% by 2025
LBL (2019)
9. Promote end-use efficiency
Public Opinion
Awareness of the Government’s energy efficiency programs is very low, but energy efficiency measures are widely
supported as awareness increases. The primary benefit is seen as coming from cost reductions
9. Promote end-use efficiency
Impacts
58
SUSTAINABILITY
SECURITY
EQUITY SUSTAINABILITY
SECURITY
EQUITY
TERIMA KASIH
mike.crosetti@castlerockasia.com
william.derbyshire@eca-uk.com
59
If you will not attend the afternoon session,
please complete your questionnaires and
submit in the boxes near the exit doors
This presentation can be downloaded from
https://tinyurl.com/y49po9ak

Contenu connexe

Tendances

Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Scott Clausen
 
Ser for 2020
Ser for 2020Ser for 2020
Ser for 2020
ProjetoBr
 
Solar PV Road Map
Solar PV Road MapSolar PV Road Map
Solar PV Road Map
Turlough Guerin GAICD FGIA
 
Terna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and ValuesTerna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and Values
Terna SpA
 
Detailed comparison of Brazilian and French obligation schemes to promote ene...
Detailed comparison of Brazilian and French obligation schemes to promote ene...Detailed comparison of Brazilian and French obligation schemes to promote ene...
Detailed comparison of Brazilian and French obligation schemes to promote ene...
Gilberto De Martino Jannuzzi
 

Tendances (20)

Energy sector contribution to climate action
Energy sector contribution to climate actionEnergy sector contribution to climate action
Energy sector contribution to climate action
 
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
PPT Devi Ebtke - OECD Stakeholder Dialogue on Mobilising Clean Energy Finance...
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Photovoltaic market and industry trends 2020 IEA PVPS
Photovoltaic market and industry trends 2020 IEA PVPSPhotovoltaic market and industry trends 2020 IEA PVPS
Photovoltaic market and industry trends 2020 IEA PVPS
 
Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...
Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...
Promotion of Clean Energy, Energy Efficiency and DSM by Maharasthra Electrici...
 
OECD CEFIM Indonesia Questionnaire - Key points
OECD CEFIM Indonesia Questionnaire - Key pointsOECD CEFIM Indonesia Questionnaire - Key points
OECD CEFIM Indonesia Questionnaire - Key points
 
Bhiwandi electricity distribution
Bhiwandi electricity distributionBhiwandi electricity distribution
Bhiwandi electricity distribution
 
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
Why Policy Matters - Renewable Energy Market Momentum at Risk - June 2015
 
Ser for 2020
Ser for 2020Ser for 2020
Ser for 2020
 
Energy efficiency trends in the EU: Have we got off track?
Energy efficiency trends in the EU: Have we got off track?Energy efficiency trends in the EU: Have we got off track?
Energy efficiency trends in the EU: Have we got off track?
 
Energy in Ireland Report Launch 2021
Energy in Ireland Report Launch 2021Energy in Ireland Report Launch 2021
Energy in Ireland Report Launch 2021
 
Solar PV Road Map
Solar PV Road MapSolar PV Road Map
Solar PV Road Map
 
China’s national carbon market development - Zhang Xiliang
China’s national carbon market development - Zhang XiliangChina’s national carbon market development - Zhang Xiliang
China’s national carbon market development - Zhang Xiliang
 
Carsten Rolle, Executive Director WEC Germany
Carsten Rolle, Executive Director WEC Germany Carsten Rolle, Executive Director WEC Germany
Carsten Rolle, Executive Director WEC Germany
 
SE4ALL 11 The energy efficiency transition
SE4ALL 11 The energy efficiency transitionSE4ALL 11 The energy efficiency transition
SE4ALL 11 The energy efficiency transition
 
Terna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and ValuesTerna 2018 2022 Strategic Plan Grid and Values
Terna 2018 2022 Strategic Plan Grid and Values
 
Report: New England Energy Landscape Update
Report: New England Energy Landscape UpdateReport: New England Energy Landscape Update
Report: New England Energy Landscape Update
 
Detailed comparison of Brazilian and French obligation schemes to promote ene...
Detailed comparison of Brazilian and French obligation schemes to promote ene...Detailed comparison of Brazilian and French obligation schemes to promote ene...
Detailed comparison of Brazilian and French obligation schemes to promote ene...
 
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
Towards becoming a net greenhouse gas sink: Metrics and Techniques to identif...
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State Roadmap
 

Similaire à Policy feedback FGD (power) Indonesian 2019

PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdfPLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
mza.arifin
 
Ns cef market handbook q1 2020 08 sep20
Ns   cef market handbook q1 2020 08 sep20Ns   cef market handbook q1 2020 08 sep20
Ns cef market handbook q1 2020 08 sep20
Mayank Munjal
 
World energyinvestmentlaunchpresentation
World energyinvestmentlaunchpresentationWorld energyinvestmentlaunchpresentation
World energyinvestmentlaunchpresentation
Energy for One World
 
Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023
WeiCongTan4
 
2021 2025 Industrial Plan Update Presentation
2021 2025 Industrial Plan Update Presentation2021 2025 Industrial Plan Update Presentation
2021 2025 Industrial Plan Update Presentation
Terna SpA
 
Presentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdf
Presentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdfPresentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdf
Presentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdf
NabilaEram
 
Gordon Best- Renewables 2016
Gordon Best- Renewables 2016Gordon Best- Renewables 2016
Gordon Best- Renewables 2016
Gordon Best
 

Similaire à Policy feedback FGD (power) Indonesian 2019 (20)

Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
Concepts of economic attributes part 1
Concepts of economic attributes part 1Concepts of economic attributes part 1
Concepts of economic attributes part 1
 
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdfPLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
PLN - Renewable Energy Development Strategy RUPTL 2021-2030 (MKI).pdf
 
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
Using the TIMES-Ireland Model (TIM) to understand Ireland's Carbon Budget imp...
 
IEA Technology roadmap solar photovoltaic energy 2014
IEA Technology roadmap solar photovoltaic energy 2014 IEA Technology roadmap solar photovoltaic energy 2014
IEA Technology roadmap solar photovoltaic energy 2014
 
Ns cef market handbook q1 2020 08 sep20
Ns   cef market handbook q1 2020 08 sep20Ns   cef market handbook q1 2020 08 sep20
Ns cef market handbook q1 2020 08 sep20
 
IEA World Energy Outlook 2020 launch-presentation
IEA World Energy Outlook 2020 launch-presentationIEA World Energy Outlook 2020 launch-presentation
IEA World Energy Outlook 2020 launch-presentation
 
Doubling global progress on energy efficiency, IEA.pdf
Doubling global progress on energy efficiency, IEA.pdfDoubling global progress on energy efficiency, IEA.pdf
Doubling global progress on energy efficiency, IEA.pdf
 
World energyinvestmentlaunchpresentation
World energyinvestmentlaunchpresentationWorld energyinvestmentlaunchpresentation
World energyinvestmentlaunchpresentation
 
Renewable Energy Technology Overview and Market Trends
Renewable Energy Technology Overview and Market Trends Renewable Energy Technology Overview and Market Trends
Renewable Energy Technology Overview and Market Trends
 
Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023Summary of NETR Published by PWC - Sep 2023
Summary of NETR Published by PWC - Sep 2023
 
GIZ support mechanism for RE development in Vietnam
GIZ support mechanism for RE development in VietnamGIZ support mechanism for RE development in Vietnam
GIZ support mechanism for RE development in Vietnam
 
2021 2025 Industrial Plan Update Presentation
2021 2025 Industrial Plan Update Presentation2021 2025 Industrial Plan Update Presentation
2021 2025 Industrial Plan Update Presentation
 
Corporate Presentation - CPFL Energia
Corporate Presentation - CPFL EnergiaCorporate Presentation - CPFL Energia
Corporate Presentation - CPFL Energia
 
Presentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdf
Presentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdfPresentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdf
Presentation-on-Power-and-Energy-Sector-in-the-Naitoanl-Budget-for-FY2023.pdf
 
Final presentation on power sector t&d
Final presentation on power sector  t&dFinal presentation on power sector  t&d
Final presentation on power sector t&d
 
Transition to a Resource Efficient Pattern of Growth in Energy Sector
Transition to a Resource Efficient Pattern of Growth in Energy SectorTransition to a Resource Efficient Pattern of Growth in Energy Sector
Transition to a Resource Efficient Pattern of Growth in Energy Sector
 
Energy Reimagined - Influencing outcomes of the future of energy mix
Energy Reimagined - Influencing outcomes of the future of energy mixEnergy Reimagined - Influencing outcomes of the future of energy mix
Energy Reimagined - Influencing outcomes of the future of energy mix
 
CREO 2019 power sector outlook
CREO 2019 power sector outlookCREO 2019 power sector outlook
CREO 2019 power sector outlook
 
Gordon Best- Renewables 2016
Gordon Best- Renewables 2016Gordon Best- Renewables 2016
Gordon Best- Renewables 2016
 

Dernier

Dernier (20)

VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 

Policy feedback FGD (power) Indonesian 2019

  • 1. Energy Policy Feedback (Power) Focus Group Discussion Jakarta, 18 October 2019 Sustainable Infrastructure Assistance Program (46380-023) TA 9511–INO: Indonesia Energy Sector Assessment and Priorities 2020–2024 1
  • 2. Contents 2 1. Background 2. Current conditions in the Indonesian power sector 3. Policy identification and assessment 4. Proposed policies
  • 4. Background 4  ADB is supporting Bappenas in the identification of key energy related pillars and indicators to inform the Medium-Term National Development Plan (RPJMN) 2020–2024  As part of this, Castlerock has been contracted to assist with policy advice for energy sector planning in the form of an Energy Sector Assessment and Priorities for 2020–2024. Areas of focus include: (i) the electricity sector (ii) increasing renewable energy (iii) sustainable energy pricing (iv) energy efficiency measures (v) the identification of technological and regulatory innovation  An assessment of the energy sector’s performance and identification of key issues was consulted on at a previous FGD. The current FGD consults on potential policy responses to the previously identified issues
  • 5. The analysis has been complemented by a national survey of public opinion 5
  • 6. 2. Current conditions in the Indonesian power sector 6
  • 7. Energy efficiency is Indonesia’s largest and cheapest energy resource, but little attention goes to harnessing it 7 From Amory Lovins, Asia Clean Energy Forum 2019
  • 8. Capacity expansion has enabled growing demand to be met, but with increasing coal dependency 8 RUPTL 2018-28. Derated capacity is shown. The small reduction in capacity from 2014 to 2015 is due principally to diesel generator retirements Between 2011 and 2018, generation capacity increased by 17 GW (52%) with 11 GW being coal-fired The share of coal in the generation mix has increased from 44% to 60%, replacing oil-fired generation 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 2011 2012 2013 2014 2015 2016 2017 2018 (Jan- Oct) Hydro Coal Gas Oil Geothermal Other 0 10,000 20,000 30,000 40,000 50,000 60,000 2011 2012 2013 2014 2015 2016 2017 2018 Deratedcapacity(MW) Hydro Coal Gas Oil Geothermal Other Peak demand
  • 9. Renewables expansion is falling far short of the levels required to meet targets 9 Over the last 10 years, PLN has added 2.3 GW of renewables capacity. Over the next 10 years, PLN needs to add 17- 31 GW of renewables capacity, a 10x increase in the rate of additions 0 5 10 15 20 25 30 35 1 2 3 4 5 6 7 8 9 10 Cumulativecapacityadditions(GW) Year (2009-18 for actual and 2019-28 for planned) Actual geothermal (2009-18) Actual hydro (2009-18) Actual other renewables (2009-18) RUKN 2019-38 RUPTL 2019-28 RUKN 2019-38, RUPTL 2018-28 and consultant calculations
  • 10. Electrification is nearing 100%, but still requires very significant expansion in absolute terms 10 • 996,000 households without electricity (1.5%) • 1,340,000 with non-PLN supply (2.0%) – for many less than Tier 3 service Off-grid supply and subsidized connections will be increasingly important in reaching remaining households – not more generating capacity on large systems BPS SUSENAS 2018 – primary source of lighting ESDM July 2019 Off-grid represents 28% of planned 2019 connections
  • 11. Subsidies are rising again, after a period of decline 11 Subsidies now exceed 2015 levels, despite the major reforms to tariffs in that year Electricity subsidies remain poorly targeted. <25% of 450VA customers are in the bottom 20% of households ESDM July 2019 SUSENAS 2017 and consultant calculations 12.3% 11.0% 10.6% 10.2% 9.8% 9.5% 9.2% 9.2% 9.1% 9.3% 0% 2% 4% 6% 8% 10% 12% 14% 1 2 3 4 5 6 7 8 9 10 Shareoftotalcustomers Expenditure decile (1 = lowest 10%) 450 VA connections by expenditure decile 101.2 99.3 56.6 58.0 45.7 48.1 65.3 58.6 0 20 40 60 80 100 120 101.2 99.3 56.6 58.0 45.7 48.1 65.3 58.6 2013 2014 2015 2016 2017 2018 2019 2020 Final APBN RAPBN RPtrillion
  • 12. Excessive and badly-targeted investment contributes to rising costs and subsidies 12 Reserve margins are planned to greatly exceed targets Meanwhile, inadequate networks mean that service quality remains poor in many regions RUPTL 2019-28 PLN Statistics 2018 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Margin(%) Capacity(MW) Existing (Derated) Ongoing and Committed Planned Planned reserve margin Target reserve margin
  • 13. …although PLN has also consistently failed to deliver against planned capacity expansion 13 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000 110,000 120,000 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Total Installed Capacity, MW Actual Total Capacity RUPTL 2011‐2020 RUPTL 2013‐2022 RUPTL 2015‐2024 RUPTL 2017‐2026 RUPTL 2019‐2027
  • 14. 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 milliontCO2 NDC - BAU NDC - Unconditional Pusdatin - BAU Reported actual It is not possible to assess how fast emissions are growing and their compliance with NDC commitments 14 From 2012 to 2018, reported emissions grew at 0.8% pa compared to an NDC commitment of 5.8% pa Major revisions to estimated energy consumption mean that reported data is unreliable and inconsistent BP Statistical Review 2018, Pusdatin (2016) and Indonesia First NDC ESDM Handbook of Economic and Energy Statistics (various years) 0 200,000 400,000 600,000 800,000 1,000,000 1,200,000 1,400,000 thousandBOE 2018 edition 2016 edition 2015 edition 2014 FEC (thousand BOE) 2015 HEES : 1,292,796 2016 HEES : 1,114,003 (-14%) 2018 HEES : 855,552 (-34%) • Actual 2018 emissions are estimated at 28% below the BAU level assumed in the NDC • Pusdatin projections are for BAU emissions by 2030 to be 40% below the BAU level assumed in the NDC NDC commitment Reduce energy sector emissions to 19% below BAU by 2030
  • 15. 3. Policy identification and assessment 15
  • 16. Major challenges for the sector 16 Inefficient use of energy Poor planning Badly-targeted subsidies • Higher costs of clean technologies cannot be recovered by PLN – leads to caps on prices that PLN will pay • ‘Locked-in’ investments in coal reduce the ‘space’ for clean energy capacity expansion • Targets are poorly related to NDC commitments Slow pace of decarbonisation • Energy data and plans using this are inconsistent and subject to frequent and large revisions • Plans are not based on cost-benefit analysis and technology selections do not reflect social costs • Lack of external oversight and transparency • Over-emphasis on generation expansion rather than network enhancement • Lack of incentives to improve energy efficiency at both production and consumption levels • Plans are oriented towards increasing consumption, not improving efficiency • Increases fiscal cost of subsidies and reduces public funds available for other purposes, such as supporting clean energy • Worsens bias against clean energy with perceived higher costs • Counteracts measures to improve energy efficiency
  • 17. The energy value chain 17 PRIMARY TRANSFORMATION END-USE Electricity * Oil and gas Refineries, Oil products, LPG, LNG, gas pipelines Coal Oil Natural Gas Households Industry and Commerce Transport Other ENERGY EFFICIENCY Biofuels * Renewable energy resources used principally for power production are considered under Electricity OVERALL SECTOR MANAGEMENT Renewables * Solar, wind, geothermal, hydro, biomass, waste-to-energy
  • 18. Key power sector policies and the value chain [Non-power policies are covered in a separate presentation] 18 OVERALL SECTOR MANAGEMENT PRIMARY ENERGY ENERGY TRANSFORMATION – Electricity END USE – Electricity 1. Redefine and clarify emissions targets 2. Improve data reporting and policy analysis 3. Replace the PLN coal price cap with an export levy 4. Strengthen regulation 5. Separate planning, procurement and system operation from PLN 6. Accelerate use of renewable energy 7. Implement non-PLN off-grid supply 8. Optimise delivery of electricity subsidies 9. Promote end-use efficiency
  • 19. Energy efficiency is a fundamental theme 19 End-UseTransformation  Huge potential for savings across the value chain  6 of 9 proposed electricity policies promote efficiency Production Pricing& Subsidies Planning& Operations Physical measures 2. Improve data reporting and policy analysis 3. Replace coal price cap with an export levy 5. Separate SB+SO 4. Strengthen power sector regulation 8. Optimize electricity subsidies 9. Building, MEPS, Industrial end-use efficiency
  • 20. Mapping electricity policies to challenges 20 Inefficient use of energy Poor planning Badly-targeted subsidies Slow pace of decarbonisation 1. Redefine and clarify emissions targets 3. Replace the PLN coal price cap with an export levy 4. Strengthen regulation 5. Separate system planning, generation procurement and system operation from PLN 6. Accelerate use of renewable energy 7. Implement non-PLN off-grid supply 8. Optimise delivery of electricity subsidies 9. Promote end-use efficiency 2. Improve data reporting and policy analysis
  • 21. Impacts are assessed using the energy ‘trilemma’ framework SECURITY SUSTAINABILITY ACCESS & EQUITY Effective management of primary energy supply from domestic and external sources, reliability of energy infrastructure, and ability of energy providers to meet current and future demand.* Accessibility and affordability of energy supply across the population.* Additionally, fair distribution of costs and benefits of energy supply, for both present and future generations, and open and transparent processes for sector management. Encompasses achievement of supply- and demand-side energy efficiencies and development of energy supply from renewable and other low-carbon sources.* * Definition from World Energy Council, “World Energy Trilemma Index 2017” 21
  • 22. Understanding the impacts 22 SUSTAINABILITY SECURITY EQUITY Highly supportive Neutral Highly counterproductive In this example, the policy is: • Highly supportive of sustainability • Neutral impact on equity • Moderately counterproductive with respect to security
  • 23. Feedback questionnaire 23  There will be a discussion period after the presentation and periodic opportunities for questions  We have also left a questionnaire on your seat • Electricity (morning session) on one side, Non-Electricity (afternoon session) on the other • Any policies you think we have missed? • Simple evaluation of policies we propose (Agree, Disagree, Neutral) • Comments on individual policies, if any • Optional – your name, institution and contact email  Please submit your completed questionnaire in the box near the door when you leave
  • 25. 4. Proposed policies a. Overall Sector Management 25
  • 26. 1. Redefine and clarify emissions targets 26 Issues  Current NDC targets are essentially meaningless given data problems and unrealistic baseline  As a result, there is a lack of clear emissions targets to guide planning Proposed policy  Redefine emissions target as being 19% below most recent BAU estimate (ie, not NDC estimate) by 2030  Pusdatin to update and publish BAU projections whenever the underlying data is revised As currently defined, emissions could increase by 150% and still remain within the NDC commitment Consultant team calculations 535 273 463 820 1,134 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 Actual 19% below Pusdatin BAU Pusdatin - BAU NDC - Unconditional NDC - BAU 2018 2030 MtCO2 3.5% pa 5.3% pa 8.1% pa 9.9% pa
  • 27. 1. Redefine and clarify emissions targets Impacts 27 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 28. 2. Improve data reporting and policy analysis 28 Issues  Energy sector data is currently produced by multiple agencies, is inconsistent and is subject to large revisions  Multiple energy sector plans (RUEN / RUKN / RIKEN / RUPTL) with frequent gaps and inconsistencies between them Proposed policy  Designate Pusdatin ESDM as the source of official government energy data  Annually review progress against targets, consistency across plans and the impacts of proposed new policies  Facilitates comprehensive consideration of energy efficiency Electricity demand forecasts vary widely across different planning documents Consultant team calculations 0 200 400 600 800 1,000 1,200 1,400 1,600 1,800 TWh Actual RUEN 2015-50 RUKN 2019-38 (medium case) RUPTL 2019-28
  • 29. 2. Improve data reporting and policy analysis Impacts 29 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 30. 4. Proposed policies b. Primary Energy 30
  • 31. 3. Replace the PLN coal price cap with an export levy 31 Issues  Increases mismatch between coal generation’s financial costs and its economic costs to society, distorting planning and operational decisions  Suppressed prices lead to inefficiency  Extremely inefficient means of subsidizing electricity to poor households—most benefits accrue to large consumers Proposed policy  Remove coal price cap  Apply an additional export levy and allocate the proceeds to targeted electricity subsidies Coal prices would have exceeded the $70/tonne cap in 8 out of the last 10 years World Bank. Assumes 6,000 kcal/kg 0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 Jan2009 Jun2009 Nov2009 Apr2010 Sep2010 Feb2011 Jul2011 Dec2011 May2012 Oct2012 Mar2013 Aug2013 Jan2014 Jun2014 Nov2014 Apr2015 Sep2015 Feb2016 Jul2016 Dec2016 May2017 Oct2017 Mar2018 Aug2018 Jan2019 Jun2019 $/t Australia, actual PLN cap
  • 32. 3. Replace the PLN coal price cap with an export levy Impacts 32 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 33. 4. Proposed policies c. Energy Transformation – Electricity 33
  • 34. 4. Strengthen regulation 34 Issues  Inadequate resources within DJK to oversee planning, procurement and to assess efficiency of PLN’s operations  Responsibilities shared across MEMR, MOF and MSOE, diluting oversight  No transparency or structured public participation  No apparent consideration of economic costs and benefits – leads to inefficiency Proposed policy  Establish a new regulatory agency through a Government or Presidential Regulation  Builds on DJK, supervised by ESDM but governed and budgeted by a supervisory commission (Partial SKK Migas model) • Review of assumptions and analysis for preparation of the system plan on and economic basis • Development and supervision of generation procurement processes • Supervision of system operation in line with the Grid Code • Enumeration of terms and conditions of licenses • Analysis of operators costs and performance as a basis for recommending service/tariff payments • Conducting public engagement. Proposed primary functions of a regulatory agency
  • 35. 4. Strengthen regulation Public Opinion 35 While PLN is generally seen as performing well, there remains strong support for a greater public role in energy planning and regulation
  • 37. 5. Separate planning, procurement and system operation from PLN 37 Issues  Conflicts of interest between PLN’s multiple roles (eg, favouring PLN-owned capacity in system operating decisions)  Internalising planning and operational decisions reduces transparency and access to alternative views  PLN generation subsidiaries are “financially malnourished” due to transfer prices below full costs  PLN is vulnerable to pressures from vested interests  Planning currently conducted on basis of PLN’s interests, not the nation’s Proposed policy  Phased implementation of the “independent” system operator as envisaged in RUKN 2019-2038 • Separation of system operator + single buyer from PLN • Transfer of PLN-owned generation to subsidiary companies • PPAs put in place with the single buyer  Accompanied by regulatory, tariff and subsidy reforms  Transition in stages based on achievement of pre-determined milestones and pre-requisites  No asset unbundling
  • 38. 5. Separate planning, procurement and system operation from PLN 38 • Requires step-by-step transition, with specific actions by PLN, Government and IPPs • Must be conducted in conjunction with tariff, subsidy and regulatory reform • Mitigates PLN conflicts of interest, helps insulate PLN from vested interests, leads to greater efficiency of investment and operations, strengthens PLN’s generation business National SB+SO Entity Competent & Transparent Regulation PLN  GencoIPP Distribution Single  Buyer System  Operator Customers Transmission PLN Group Geographic cross‐subsidy* PPAs SOA TSA DSAs Agreements Energy flows Cash flows GovernmentDirect  subsidy * As collected from lower cost systems under a national  uniform tariff Cost recovery tariffs
  • 39. 5. Separate planning, procurement and system operation from PLN Impacts 39 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 40. 6. Accelerate use of renewable energy 40 Issues  Indonesia’s deployment of renewable energy falls far below targets and potential  Financing and tax incentives are available but numerous impediments remain  Caps on prices are a major barrier Proposed policy  End linkage of prices to BPP and replace by prices based on economic benefits  Consider subsidies to PLN to close any gap between price and avoided costs  Address the other significant barriers 0 500 1,000 1,500 2,000 2,500 3,000 3,500 JawaBarat JawaTengah DKIJakarta Banten Bali JawaTimur Lampung SumateraBarat S2JB SulawesiSelatan SumateraUtara KalimantanTimurdan… KalimantanBarat Riau Aceh KalimantanSelatandan… Belitung Lombok Papua(Jayapura) FloresBagianBarat Timor Bangka Tambara Sumba Maluku(Ambon) FloresBagianTimur Rp/kWh Geothermal cost 1,754 Rp/kWh National Average BPP 1,119 Rp/kWh PLN (2019) and BPK (2019). Geothermal costs are shown for Java-Bali and may be higher in more remote grid Current generation BPP-based price caps make many renewables projects unviable
  • 41. 6. Accelerate use of renewable energy Multiple actions are required 41 1. Establish a technically capable regulator 2. Ensure regulatory transparency 3. Provide for public participation 9. Separate Single Buyer/System Operator functions from PLN 10. Introduce new system planning tools 13. Introduce modern grid management practices 11. Introduce balanced PPAs in line with international practice 5. Require system planning on an economic basis 7. Relax foreign investment & local content restrictions 6. De-risk projects in advance of tenders, e.g. land acquisition 4. Remove BPP price caps & require reverse auctions 12. Streamline procurement & negotiations 8. Provide loan, subsidies and/or credit enhancementsPLN / MSOE MoF PLN / MSOE PLN / MSOE PLN / MSOE PLN / MSOE President President President MEMR MEMR Various President / MoInd
  • 42. 6. Accelerate use of renewable energy Public Opinion (1) 42 Among those who are aware, there is strong support for renewable energy
  • 43. 6. Accelerate use of renewable energy Public Opinion (2) 43 Concerns over price impacts remain a barrier. However, there is a greater willingness to pay more if renewable energy also delivers local economic development and supports access for remote areas
  • 44. 6. Accelerate the use of renewable energy Impacts 44 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 45. 7. Implement non-PLN off-grid supply 45 Issues  PLN has proven reluctant to give up rights to supply in remote areas  But remote supply is costly, and requires technologies and approaches not well- suited to PLN Proposed policy  Build upon the framework in Permen ESDM 38/2016 for off-grid supplies  Establish mechanisms to identify areas for off-grid supply, competitive selection of suppliers and administration of subsidies  Establish an off-grid subsidy mechanism In remote areas, grid extension to all households is infreasible. Off-grid supply will be required ADB, Least-Cost Electrification Plan for Maluku and Papua, 2019
  • 46. 7. Implement non-PLN off-grid supply Impacts 46 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 47. 4. Proposed policies d. End-Use – Electricity 47
  • 48. 8. Optimise delivery of electricity subsidies 48 Issues  Inefficient targeting of subsidies • <25% of 450VA customers are low- income households • ~40% of low-income households are supplied at connections of 900+VA  Leads to higher subsidies than needed and to the use of alternatives, such as suspending tariff adjustments  Leads to inefficient consumption Proposed policy  Replace blanket 450VA subsidies with means-tested subsidies, using the UDB  Restore automatic tariff adjustments Better targeting could reduce 450VA subsidies by up to Rp 19 trillion annually (33% of 2020 RAPBN) Consultant calculations using Susenas 2017 data and PLN billing data for 2018 The calculation presented here assumes that non-subsidized customers do not reduce their consumption in response to the tariff increase following withdrawal of subsidies. The available evidence from the impacts of earlier tariff revisions is that such impacts are small. The calculation also does not allow for subsidies being paid to low-income households with 900+VA connections, who currently are non-subsidised 450VA customers only Without policy With policy All Subsidised Non- subsidised Customers millions 23.25 5.81 17.44 Share 25% 75% Average revenue (a) Rp/kWh 379 359 1,352 Sales TWh 24.3 4.4 19.9 Share 18% 82% Revenues Rp trillion 9.2 1.6 26.9 Change with policy Rp trillion +19.3 (a) Assumes non-subsidised tariff is increased to the 900VA tariff
  • 49. 8. Optimise delivery of electricity subsidies Public Opinion (1) 49 Current subsidies (including non-energy subsidies) are generally perceived to be poorly targeted
  • 50. 8. Optimise delivery of electricity subsidies Public Opinion (2) 50 The continuing use of subsidies to lower tariffs, rather than their replacement by direct subsidies, is preferred by around half of all households
  • 51. 8. Optimise delivery of electricity subsidies Public Opinion (3) 51 There is evidence of an acceptance of reduced subsidies, if supply quality and access to electricity is improved
  • 52. 8. Optimise delivery of electricity subsidies Public Opinion (4) 52 Among unelectrified households near to the existing grid, connection fees are the major barrier—suggesting a need to switch subsidies from consumption to connection
  • 53. 8. Optimize delivery of electricity subsidies Impacts 53 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 54. 9. Promote end-use efficiency: Industry 54 Issues  Evidence of significant potential to improve energy efficiency in industry  Current ESCO market very under- developed, meaning little of this potential is being realised Proposed policy  Enforce PP 70/2009 (energy audits)  Higher Minimum Efficiency Performance Standards (MEPS) for electric motors  Consider dedicated industry energy efficiency financing facility (under PT SMI) Adopting Chinese-level MEPS for electric motors could alone save 7.7 PJ (2.1 TWh / 350 MW) by 2030 IEA (2016). IE1 corresponds to current Indonesian MEPS proposals and IE2 to Chinese standards for electric motors. The calculation of capacity (MW) savings assumes an average capacity factor of 70%
  • 55. 9. Promote end-use efficiency: Buildings 55 Issues  Evidence of significant potential to improve energy efficiency in buildings  Little incentive for new ‘green’ buildings  Under-developed ESCO market Proposed policy  All government facilities required to reduce energy consumption by 17%* by 2025, creating a market for ESCOs  National roll-out of a Green Building Code using the Jakarta and Bandung models Indonesian buildings are only around two-thirds as energy-efficient as those in Japan IECES (2016) using data from JICA (2009) * National target specified in Draft RIKEN (2013)
  • 56. 9. Promote end-use efficiency: Appliances 56 Issues  Existing minimum energy performance standards (MEPS) cover CFLs, but these are being displaced by LEDs  MEPS under development for clothes washers, well pumps, and televisions, and possibly water coolers or irons Proposed policy  Expand the coverage of MEPS  Make existing and proposed MEPS more stringent, bringing them closer to Best-Available-Technology levels  Phase in BAT requirements to allow time for consumers to adjust Improved appliance efficiency could reduce peak electricity demand by as much as 25% by 2025 LBL (2019)
  • 57. 9. Promote end-use efficiency Public Opinion Awareness of the Government’s energy efficiency programs is very low, but energy efficiency measures are widely supported as awareness increases. The primary benefit is seen as coming from cost reductions
  • 58. 9. Promote end-use efficiency Impacts 58 SUSTAINABILITY SECURITY EQUITY SUSTAINABILITY SECURITY EQUITY
  • 59. TERIMA KASIH mike.crosetti@castlerockasia.com william.derbyshire@eca-uk.com 59 If you will not attend the afternoon session, please complete your questionnaires and submit in the boxes near the exit doors This presentation can be downloaded from https://tinyurl.com/y49po9ak