SlideShare une entreprise Scribd logo
1  sur  12
Cert IV Project Management
Learn about the Activity Duration
Estimating (Tools and Techniques) in the
Cert IV Project Management qualification.
Expert Judgment. Activity durations are often difficult to
estimate because of the number of factors that can
influence them, such as resource levels or resource
productivity. Expert judgment, guided by historical
information, can be used whenever possible.
The individual project team members may also provide
duration estimate information or recommended maximum
activity durations from prior similar projects. If such
expertise is not available, the duration estimates are more
uncertain and risky.
Analogous Estimating. Analogous duration estimating
means using the actual duration of a previous, similar
schedule activity as the basis for estimating the duration of
a future schedule activity. It is frequently used to estimate
project duration when there is a limited amount of detailed
information about the project for example, in the early
phases of a project.
Analogous estimating uses historical information and expert
judgment. Analogous duration estimating is most reliable
when the previous activities are similar in fact and not just
in appearance, and the project team members preparing
the estimates have the needed expertise.
Parametric Estimating. Estimating the basis for activity
durations can be quantitatively determined by multiplying
the quantity of work to be performed by the productivity
rate. For example, productivity rates can be estimated on a
design project by the number of drawings multiplied by
labour hours per drawing, or a cable installation in meters
of cable times labour hours per meter.
The total resource quantities are multiplied by the labour
hours per work period or the production capability per work
period, and divided by the number of those resources
being applied to determine activity duration in work
periods.
Three-Point Estimates. The accuracy of the activity
duration estimate can be improved by considering the
amount of risk in the original estimate. Three-point estimates
are based on determining three types of estimates:
• Most likely. The duration of the schedule activity, given the
resources likely to be assigned, their productivity, realistic
expectations of availability for the schedule activity,
dependencies on other participants, and interruptions.
• Optimistic. The activity duration is based on a best-case
scenario of what is described in the most likely estimate.
• Pessimistic. The activity duration is based on a worst-case
scenario of what is described in the most likely estimate.
An activity duration estimate can be constructed by
using an average of the three estimated durations. That
average will often provide a more accurate activity duration
estimate than the single point, most-likely estimate.
Reserve Analysis. Project teams can choose to incorporate
additional time referred to as contingency reserves, time
reserves or buffers, into the overall project schedule as
recognition of schedule risk. The contingency reserve can be
a percentage of the estimated activity duration, a fixed
number of work periods, or developed by quantitative
schedule risk analysis.
The contingency reserve can be used completely or partially,
or can later be reduced or eliminated, as more precise
information about the project becomes available. Such
contingency reserve is documented along with other related
data and assumptions.
There is a tendency to consume contingencies by default!
Two academic theories that discuss this are:
Parkinson’s Law – Work expands to fill the time available;
Student Syndrome – People will start to fully apply
themselves to a task at the last possible moment before a
deadline.
Activity Duration Estimating: Outputs
Activity Duration Estimates. Activity duration estimates
are quantitative assessments of the likely number of work
periods that will be required to complete a schedule activity.
Activity duration estimates include some indication of the
range of possible results. For example:
• 2 weeks ± 2 days to indicate that the schedule activity will
take at least eight days and no more than twelve
(assuming a five-day workweek).
• 15 percent probability of exceeding three weeks to indicate
a high probability-85 percent-that the schedule activity will
take three weeks or less.
Activity Attributes (Updates). The activity attributes are
updated to include the durations for each schedule activity,
the assumptions made in developing the activity duration
estimates, and any contingency reserves.
LMIT’s Diploma in Project Management is Now
Endorsed by AIPM – Get Your Diploma of PM and You’ll
Also Receive a Certificate from AIPM.
LMIT provides online training courses for
the Cert IV Project Management
BSB41507, the Certificate IV of Project
Management and the Diploma of Project
Management BSB51407 in Brisbane, Sydney,
Melbourne, Perth, Adelaide and Canberra.

Contenu connexe

Tendances

Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Gao cost estimating process
Gao cost estimating processGao cost estimating process
Gao cost estimating processGlen Alleman
 
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd Healthcare consultant
 
Day 3 Analogous, estimates and semantics for process
Day 3   Analogous, estimates and semantics for process Day 3   Analogous, estimates and semantics for process
Day 3 Analogous, estimates and semantics for process Arun
 
Variation Over Time (Short/Long Term Data)
Variation Over Time (Short/Long Term Data)Variation Over Time (Short/Long Term Data)
Variation Over Time (Short/Long Term Data)Matt Hansen
 
Identify Root Causes – DCP Overview
Identify Root Causes – DCP OverviewIdentify Root Causes – DCP Overview
Identify Root Causes – DCP OverviewMatt Hansen
 

Tendances (9)

Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Resource management
Resource managementResource management
Resource management
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Gao cost estimating process
Gao cost estimating processGao cost estimating process
Gao cost estimating process
 
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
Who would ever fore see risk identification? by Dr.Mahboob ali khan Phd
 
Day 3 Analogous, estimates and semantics for process
Day 3   Analogous, estimates and semantics for process Day 3   Analogous, estimates and semantics for process
Day 3 Analogous, estimates and semantics for process
 
Variation Over Time (Short/Long Term Data)
Variation Over Time (Short/Long Term Data)Variation Over Time (Short/Long Term Data)
Variation Over Time (Short/Long Term Data)
 
Agile Projects | Rapid Estimation | Techniques | Tips
Agile Projects | Rapid Estimation | Techniques | TipsAgile Projects | Rapid Estimation | Techniques | Tips
Agile Projects | Rapid Estimation | Techniques | Tips
 
Identify Root Causes – DCP Overview
Identify Root Causes – DCP OverviewIdentify Root Causes – DCP Overview
Identify Root Causes – DCP Overview
 

Similaire à Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupTùng Trần Thanh
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resouresMayank Kothawade
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling Reema
 
Project Scheduling
Project SchedulingProject Scheduling
Project SchedulingReema
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)danieljohn810
 
Industrial egineering
Industrial egineeringIndustrial egineering
Industrial egineeringRajeev Sharan
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimatingharwoodr
 
Cost management
Cost managementCost management
Cost managementshkadry
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)Peter Mello
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.NIILM University
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration EstimationHarsh Behl
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 

Similaire à Cert IV Project Management - Activity Duration Estimating (Tools and Techniques) (20)

Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resoures
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Session 7 4th edition PMP
Session 7 4th edition PMPSession 7 4th edition PMP
Session 7 4th edition PMP
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Industrial egineering
Industrial egineeringIndustrial egineering
Industrial egineering
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
Cost management
Cost managementCost management
Cost management
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.
 
Agile planning
Agile planningAgile planning
Agile planning
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 

Plus de danieljohn810

Change Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from StaffChange Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from Staffdanieljohn810
 
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...danieljohn810
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2danieljohn810
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Managementdanieljohn810
 
Destination Wedding Etiquette
Destination Wedding EtiquetteDestination Wedding Etiquette
Destination Wedding Etiquettedanieljohn810
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequencesdanieljohn810
 
Australian Workplace Health and Safety Resources
Australian Workplace Health and Safety ResourcesAustralian Workplace Health and Safety Resources
Australian Workplace Health and Safety Resourcesdanieljohn810
 
Cert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative RequirementsCert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative Requirementsdanieljohn810
 
Certificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS TermsCertificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS Termsdanieljohn810
 
Writing Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training CoursesWriting Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training Coursesdanieljohn810
 
Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)danieljohn810
 
Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management danieljohn810
 
Occupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSOccupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSdanieljohn810
 
Executive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA TrainingExecutive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA Trainingdanieljohn810
 
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...danieljohn810
 
Occupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and PrioritiesOccupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and Prioritiesdanieljohn810
 
Office 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfOffice 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfdanieljohn810
 
Glossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and SafetyGlossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and Safetydanieljohn810
 
How to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS InformationHow to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS Informationdanieljohn810
 
Diploma Human Resources
Diploma Human ResourcesDiploma Human Resources
Diploma Human Resourcesdanieljohn810
 

Plus de danieljohn810 (20)

Change Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from StaffChange Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from Staff
 
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Management
 
Destination Wedding Etiquette
Destination Wedding EtiquetteDestination Wedding Etiquette
Destination Wedding Etiquette
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequences
 
Australian Workplace Health and Safety Resources
Australian Workplace Health and Safety ResourcesAustralian Workplace Health and Safety Resources
Australian Workplace Health and Safety Resources
 
Cert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative RequirementsCert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative Requirements
 
Certificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS TermsCertificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS Terms
 
Writing Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training CoursesWriting Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training Courses
 
Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)
 
Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management
 
Occupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSOccupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHS
 
Executive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA TrainingExecutive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA Training
 
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
 
Occupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and PrioritiesOccupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and Priorities
 
Office 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfOffice 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdf
 
Glossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and SafetyGlossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and Safety
 
How to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS InformationHow to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS Information
 
Diploma Human Resources
Diploma Human ResourcesDiploma Human Resources
Diploma Human Resources
 

Dernier

Zeeman Effect normal and Anomalous zeeman effect
Zeeman Effect normal and Anomalous zeeman effectZeeman Effect normal and Anomalous zeeman effect
Zeeman Effect normal and Anomalous zeeman effectPriyanshuRawat56
 
Motilal Oswal Gift City Fund PPT - Apr 2024.pptx
Motilal Oswal Gift City Fund PPT - Apr 2024.pptxMotilal Oswal Gift City Fund PPT - Apr 2024.pptx
Motilal Oswal Gift City Fund PPT - Apr 2024.pptxMaulikVasani1
 
Delhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
Top Rated Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Call Girls in Nagpur High Profile
 
Résumé (2 pager - 12 ft standard syntax)
Résumé (2 pager -  12 ft standard syntax)Résumé (2 pager -  12 ft standard syntax)
Résumé (2 pager - 12 ft standard syntax)Soham Mondal
 
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...amitlee9823
 
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdfreStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdfKen Fuller
 
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)sonalinghatmal
 
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)Delhi Call girls
 
Top Rated Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
Top Rated  Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...Top Rated  Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
Top Rated Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...Call Girls in Nagpur High Profile
 
Production Day 1.pptxjvjbvbcbcb bj bvcbj
Production Day 1.pptxjvjbvbcbcb bj bvcbjProduction Day 1.pptxjvjbvbcbcb bj bvcbj
Production Day 1.pptxjvjbvbcbcb bj bvcbjLewisJB
 
Vip Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...
Vip  Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...Vip  Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...
Vip Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...shivangimorya083
 
Delhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Callshivangimorya083
 
Dark Dubai Call Girls O525547819 Skin Call Girls Dubai
Dark Dubai Call Girls O525547819 Skin Call Girls DubaiDark Dubai Call Girls O525547819 Skin Call Girls Dubai
Dark Dubai Call Girls O525547819 Skin Call Girls Dubaikojalkojal131
 
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...robinsonayot
 
Personal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando NegronPersonal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando Negronnegronf24
 
Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.GabrielaMiletti
 
Booking open Available Pune Call Girls Ambegaon Khurd 6297143586 Call Hot In...
Booking open Available Pune Call Girls Ambegaon Khurd  6297143586 Call Hot In...Booking open Available Pune Call Girls Ambegaon Khurd  6297143586 Call Hot In...
Booking open Available Pune Call Girls Ambegaon Khurd 6297143586 Call Hot In...Call Girls in Nagpur High Profile
 

Dernier (20)

Zeeman Effect normal and Anomalous zeeman effect
Zeeman Effect normal and Anomalous zeeman effectZeeman Effect normal and Anomalous zeeman effect
Zeeman Effect normal and Anomalous zeeman effect
 
Motilal Oswal Gift City Fund PPT - Apr 2024.pptx
Motilal Oswal Gift City Fund PPT - Apr 2024.pptxMotilal Oswal Gift City Fund PPT - Apr 2024.pptx
Motilal Oswal Gift City Fund PPT - Apr 2024.pptx
 
Delhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Delhi 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Top Rated Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Deccan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
Sensual Moments: +91 9999965857 Independent Call Girls Paharganj Delhi {{ Mon...
Sensual Moments: +91 9999965857 Independent Call Girls Paharganj Delhi {{ Mon...Sensual Moments: +91 9999965857 Independent Call Girls Paharganj Delhi {{ Mon...
Sensual Moments: +91 9999965857 Independent Call Girls Paharganj Delhi {{ Mon...
 
Résumé (2 pager - 12 ft standard syntax)
Résumé (2 pager -  12 ft standard syntax)Résumé (2 pager -  12 ft standard syntax)
Résumé (2 pager - 12 ft standard syntax)
 
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Btm Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
 
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdfreStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
reStartEvents 5:9 DC metro & Beyond V-Career Fair Employer Directory.pdf
 
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
Toxicokinetics studies.. (toxicokinetics evaluation in preclinical studies)
 
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Salarpur Sector 81 ( Noida)
 
Top Rated Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
Top Rated  Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...Top Rated  Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
Top Rated Pune Call Girls Warje ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
 
Production Day 1.pptxjvjbvbcbcb bj bvcbj
Production Day 1.pptxjvjbvbcbcb bj bvcbjProduction Day 1.pptxjvjbvbcbcb bj bvcbj
Production Day 1.pptxjvjbvbcbcb bj bvcbj
 
Vip Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...
Vip  Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...Vip  Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...
Vip Modals Call Girls (Delhi) Rohini 9711199171✔️ Full night Service for one...
 
Delhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip CallDelhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
Delhi Call Girls South Ex 9711199171 ☎✔👌✔ Whatsapp Hard And Sexy Vip Call
 
Dark Dubai Call Girls O525547819 Skin Call Girls Dubai
Dark Dubai Call Girls O525547819 Skin Call Girls DubaiDark Dubai Call Girls O525547819 Skin Call Girls Dubai
Dark Dubai Call Girls O525547819 Skin Call Girls Dubai
 
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
 
Personal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando NegronPersonal Brand Exploration - Fernando Negron
Personal Brand Exploration - Fernando Negron
 
Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.Brand Analysis for reggaeton artist Jahzel.
Brand Analysis for reggaeton artist Jahzel.
 
Booking open Available Pune Call Girls Ambegaon Khurd 6297143586 Call Hot In...
Booking open Available Pune Call Girls Ambegaon Khurd  6297143586 Call Hot In...Booking open Available Pune Call Girls Ambegaon Khurd  6297143586 Call Hot In...
Booking open Available Pune Call Girls Ambegaon Khurd 6297143586 Call Hot In...
 
VVVIP Call Girls In East Of Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In East Of Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In East Of Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In East Of Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 

Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)

  • 1. Cert IV Project Management
  • 2. Learn about the Activity Duration Estimating (Tools and Techniques) in the Cert IV Project Management qualification.
  • 3. Expert Judgment. Activity durations are often difficult to estimate because of the number of factors that can influence them, such as resource levels or resource productivity. Expert judgment, guided by historical information, can be used whenever possible. The individual project team members may also provide duration estimate information or recommended maximum activity durations from prior similar projects. If such expertise is not available, the duration estimates are more uncertain and risky.
  • 4. Analogous Estimating. Analogous duration estimating means using the actual duration of a previous, similar schedule activity as the basis for estimating the duration of a future schedule activity. It is frequently used to estimate project duration when there is a limited amount of detailed information about the project for example, in the early phases of a project. Analogous estimating uses historical information and expert judgment. Analogous duration estimating is most reliable when the previous activities are similar in fact and not just in appearance, and the project team members preparing the estimates have the needed expertise.
  • 5. Parametric Estimating. Estimating the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate. For example, productivity rates can be estimated on a design project by the number of drawings multiplied by labour hours per drawing, or a cable installation in meters of cable times labour hours per meter. The total resource quantities are multiplied by the labour hours per work period or the production capability per work period, and divided by the number of those resources being applied to determine activity duration in work periods.
  • 6. Three-Point Estimates. The accuracy of the activity duration estimate can be improved by considering the amount of risk in the original estimate. Three-point estimates are based on determining three types of estimates: • Most likely. The duration of the schedule activity, given the resources likely to be assigned, their productivity, realistic expectations of availability for the schedule activity, dependencies on other participants, and interruptions. • Optimistic. The activity duration is based on a best-case scenario of what is described in the most likely estimate. • Pessimistic. The activity duration is based on a worst-case scenario of what is described in the most likely estimate.
  • 7. An activity duration estimate can be constructed by using an average of the three estimated durations. That average will often provide a more accurate activity duration estimate than the single point, most-likely estimate.
  • 8. Reserve Analysis. Project teams can choose to incorporate additional time referred to as contingency reserves, time reserves or buffers, into the overall project schedule as recognition of schedule risk. The contingency reserve can be a percentage of the estimated activity duration, a fixed number of work periods, or developed by quantitative schedule risk analysis. The contingency reserve can be used completely or partially, or can later be reduced or eliminated, as more precise information about the project becomes available. Such contingency reserve is documented along with other related data and assumptions.
  • 9. There is a tendency to consume contingencies by default! Two academic theories that discuss this are: Parkinson’s Law – Work expands to fill the time available; Student Syndrome – People will start to fully apply themselves to a task at the last possible moment before a deadline.
  • 10. Activity Duration Estimating: Outputs Activity Duration Estimates. Activity duration estimates are quantitative assessments of the likely number of work periods that will be required to complete a schedule activity. Activity duration estimates include some indication of the range of possible results. For example: • 2 weeks ± 2 days to indicate that the schedule activity will take at least eight days and no more than twelve (assuming a five-day workweek). • 15 percent probability of exceeding three weeks to indicate a high probability-85 percent-that the schedule activity will take three weeks or less.
  • 11. Activity Attributes (Updates). The activity attributes are updated to include the durations for each schedule activity, the assumptions made in developing the activity duration estimates, and any contingency reserves. LMIT’s Diploma in Project Management is Now Endorsed by AIPM – Get Your Diploma of PM and You’ll Also Receive a Certificate from AIPM.
  • 12. LMIT provides online training courses for the Cert IV Project Management BSB41507, the Certificate IV of Project Management and the Diploma of Project Management BSB51407 in Brisbane, Sydney, Melbourne, Perth, Adelaide and Canberra.