LSS
NSC installation within 72 hrs
1
PROJECT DETAIL
Name of the Project: To Improve NSC installation within SLA of 72 Hrs
Project Ref. no. UJN / NSC
Project Leader Name Dheeraj Mehta
Designation Manager
Function MMG - CS
Date Jun2015
Business Unit Ujjain
Project detail
2
Voice of Customer
I have applied for Power connection but they have delayed the installation
Voice of business
Business is losing revenue due to delay in NSC installation, also in some cases leading to
Illegal connection whenever there is delay.
Voice of Process
NSC connections are not installed as per Process SLA of 3 day.
Write down the VoC of your problem
3
PROBLEM STATEMENT
In Power DF, Ujjain City in the month of May’15, NSC installation within 72 hrs. is 55%
GOAL STATEMENT
To Improve NSC installation within 72 hrs. from current May’15 – 55% to 85% within 3
days by 30th Jul’15, for Ujjain City Power DF
CTQ’s FOR YOUR PROJECT
Paste Charter Signed Scanned Copy
CTQ Parameter UoM
At Project Start Target Planned Completion
Date
Actual Completion
DateValue Value
NSC installation within 3 days % 55% 85% 10th Jul 2015 30th Jul 2015
4
In Project Scope Out Of Project Scope
LT NSC connection request below 10
kW
All other NSC request and NSC connection of
Industrial , Agriculture & Govt.
Identify Big Y’s of your project
Operational Expense (OPEX) Reduction
Capital Expense (CAPEX) Reduction
Revenue Enhancement Y
Improve Customer Satisfaction – CSAT Y
Improve Employee Satisfaction Y
Technical Loss Reduction
Commercial Loss Reduction
Project Scope and Big Y
Project Scope
5
If I will do this project then this will impact following Big Y of Organization
Revenue enhancement
Cost Optimization
Customer Responsiveness
Customer/ Intermediary Satisfaction
Others (Pls. Specify)
Definition of Opportunity
Project Team Business Impact
CEO :
Champion :
Project Leader :
Quality Facilitator :
Team Members :
Business Case Problem Statement:
Definition of Defect :
Lean Six Sigma - Project Charter
Financial Impact
Project Title:
CTQs Baseline TargetIn scope Out Scope
Critical Milestones
Project Start Date
Project End Date
Goal Statement:
Project Leader Quality Facilitator Champion BE Head
For providing faster New Service connectivity to customer we have indentified this this project,
as we have noticed the majority of the NSC application received are not installed within 72 Hrs .
This project will help us to reduce the installtion SLA , enhanced revenue & also this will improve
and help in transforming C - SAT .
Mr.Ashok Agarwal
Mr AnupamRajput
Mr Dheeraj Mehta
Sandeep Srivastava
Zahid Husen
Rakesh Gautam
LT NSC connection request All other NSC request , Industrial , Agriculture , Govt.
Connection & load more than 10 kWNSC Connection
.
For Ujjain City currently ( as on May 2015 ) NSC installtion within 3 days is 55% .
To improve NSC installation SLA for Ujjain city from 55% to 85% within 3 days by 10th July
2015
NSC installtion within 3 days 55% 85%
Each NSC Reuest .
Any NSC connection installed out of SLA .
21 K unit increase per year .
1st Jun2015
10th Jul2015
Y
Y
Y
To Reduce NSC Installtion TAT ( SLA )
Mr. Naresh Kumar
Praveen Garg
NSC / CSD
Desk
Material Requisition
send to Main Store
MMG Store
manual count &
registered the
meter No in
system .
Meter allocated
to vendor
Number wise
Daily validation
of balance meter
& installation at
evening
Updation of
Meter in
CCB for first
billing
Details of
Customer who
has paid
Demand Note
Meter
installed and
updated in
billing system
Registered
Consumer for
Business (for 1
new connection
added in billing
base)
Supplier Input Process Output Customer
Zone wise
distribution of
cases to
vendor for
installation
Sample SIPOC
7
Down Timer Model for VA / NVA Identification
8
Identify VA / NVA for your process
9
Value & Cycle Time Track sheet
Process
Step
1 2 3 4 5 6 7 8 8 9 Total %Total
Value
Added
150 120 60 30 60 120 30 90 660
Material
requisition
sent to
warehouse
for vendor
wise
MMG store
manual
count meter
& registered
the meter
No in
system
Meter
Allocated to
Vendor
Zone wise
distribution
of cases to
vendor for
installation
Vendor
takes the
material &
meter No
allocated to
team
Vendor start
work in field
Daily
validation of
balance
meter &
installation
at evening
Updation of
Meter in IT
system for
first billing
Value
Enabled
Same
number
validated by
MMG
during issue
Non Value
Added 30
2650 3750 6430
Store Tracks
the same
meter No
Site not
ready for
installation
Installation
delay /
Customer
denied /
Out of
Station
Total Time 7090
Time
Notation in:
Total Value Added work time 630
% Value added work time 8.89%
Data Validation
 Ensure that the present CTQ is measurable, if not
o What is secondary measure
o Is new measurement system required
 Ensure that it is from the correct primary source
 In case it is auto generated
o Check / Audit MIS / System (CCB / CRM)
S. no. Data Particulars Data Source Data Period
1 Total Application received CRM - CCB May’15 – Nov ’15
2 Total Installation done CRM - CCB May’15 – Nov ’15
3 Material movement Oracle - WAM - May’15 – Nov ’15
4 Vendor manpower details MMG
5
Please fill this – what all data you have taken for project analysis
Attach Data
10
Vendor Productivity issue
Delay reporting
of vendorsManual tracking of
meters
Off line Meter
request to store
Out calling process
not designed
Meter not available
Cable not available
Premises not ready
Delay in data in MMG grid
Refuse to install
Vendor doing multiple
jobs
Delay in NSC
installation
Board not
installed
Customer requested
delay
On line protocol
sheet not generated
Identify all Potential Causes for Your Problem
11
EDIT CAUSES WRITTEN IN BLUE
Two vendor
same site
Public resistance
for outside
installation
Pareto Analysis – to be done for available data
12
Reason Contribution Cumulative Cumulative Contribution
Premises not ready 400 400 43.96%
Unavailability of Consumer 370 770 84.62%
Demand note Payment delay Updation 89 859 94.40%
Material issues 27 886 97.36%
Two Team on same site 12 898 98.68%
Repeat Visit 10 908 99.78%
Installation Delay 2 910 100.00%
910
400
370
89
27 12 10 2
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
50
100
150
200
250
300
350
400
450
Premises not
ready
Unavailability
of Consumer
Demand note
Payment delay
Updation
Material issues Two Team on
same site
Repeat Visit Installation
Delay
Pareto
Contribution Cumulative Contribution
Problem Why 1 Why 2 Why 3 Why 4 Why 5
Delay in cases in
MMG grid
It runs batch file
on daily basis
System designed
in the same form
No thought given
for delay related
losses
Loksewa gives
SLA of 7 days
Meter manual
tracking
No system
no bar code
option
No interface in
WAM & CCB
No Meter Number
tracking in CCB
Repeat site Visit
No fixing of
meter with
consumer number
No system
generated MCR to
fixed vendor
Why analysis for Key Problem from Fishbone and Pareto
13
Run Chart ( Daily )
Track Performance of daily progress
14
2
5
8
6
37
33
24
4
20
12
20
15
30
23
7
18
21
13
34
37
50
41
20 21
30
20
0
10
20
30
40
50
60
01-Jun-15
02-Jun-15
03-Jun-15
04-Jun-15
05-Jun-15
06-Jun-15
07-Jun-15
08-Jun-15
09-Jun-15
10-Jun-15
11-Jun-15
12-Jun-15
13-Jun-15
14-Jun-15
15-Jun-15
16-Jun-15
17-Jun-15
18-Jun-15
19-Jun-15
20-Jun-15
22-Jun-15
23-Jun-15
24-Jun-15
25-Jun-15
26-Jun-15
27-Jun-15
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Mon Tue Wed Thu Fri Sat
June 15
S.
No.
Root Cause Remedial Action
Resp.
Name of the Person /
Function
Target
Date
1
Demand note
Payment case not
move to MMG Grid
Run batch file 3 Hrs interval bases MMG Done
2
Delay from
Consumer side
1. Documentation guidelines / and checklist to be
given to front desk and call center to ready pre
installation activity
2. Calling to consumer who are delay 24 Hrs
3. Installation mark during TF at site for meter fixing
, application No . , cable type
NSC / CSD / MMG Done
3 Vendor Alignment
Two team of two vendor will dedicatedly work on NSC
process
MMG Done
4 Automation
1. For faster & accurate meter number automatic
barcode scanner is planned
2. System generated MCR report to couple meter &
consumer number .
MMG Done
Action planning
15
Action planning
16
Before – Two Step & manual Job After – Automation Calling to Delay Consumer
Before – Manual MCR After – System Generated
MCR
Meter Counting & Updation of Meter Consumer Calling
Meter & consumer Coupling
Meter Fixing Place & Instruction
Instruction to Consumer at site
CTQ Baseline Target Achieved
NSC installation within 3 days 55% 85% 86 %
Sustenance/ Control :
• Mistake Proofing: Wrong meter number & incorrect
consumer detail
•Control Plan: next slide
Project Name: To Improve NSC installation within
SLA of 72hrs
Project Team
Project Champion: Anupam Rajput
Project Leader: Dheeraj Mehta
Quality Facilitator: Naresh Kumar
Team : Zahid Hussain , Praveen Garg , Rakesh Gautam ,
Sandeep Srivastava
Financial Impact: 30 % or 140 consumer per month
come in our network with in 72 Hrs cause 21 K unit
increase per year .
Innovations / Solutions
1. Processes Impacted- Improve Punching Accuracy &
Efficiency in System , reduced failure rate .
2. Process changes –
i Meter Number capturing Automatic (through Bar Coder)
ii Predefine meter with consumer number
3. Trainings/ Communication –
i) Store team ii) Back End team iii ) Vendor Team
4. Best Practices – Bar Code meter Number Capturing .
Project Completion Sheet: Control Phase
17
55%
75% 77%
86%
45%
25% 23%
14%
0%
20%
40%
60%
80%
100%
May 15 Sep 15 Oct 15 Nov 15
CTQ Trend
72 Hrs
> 72 Hrs
Project Completion Sheet: Control Phase
# Action implemented / To be ensured at regular frequency Resp Frequency
1 MMG received Meter from ware house captured the
number via Bar code scanner .
Ashish
Bahal
Weekly
2 Same number will be enter in CCB Ashish
Bahal
Weekly
3 Validating the system number & actual meter number
received
Sandeep
Srivastava
Weekly
4 Meter issued to vendor team through system generated
protocol sheet
Rakesh Daily
5 Application Number mention on site at standard position
for meter installation
Praveen
Garg
Daily
Key actions – Why this problem will NOT REPEAT / REOCCUR?
18
Thanks
19

Contenu connexe

En vedette

Evaluación primaria incluyendo_lomce
Evaluación primaria incluyendo_lomceEvaluación primaria incluyendo_lomce
Evaluación primaria incluyendo_lomce
Jorge Seldas
 
Control automático de transferencia de energía eléctrica
Control automático de transferencia de energía eléctricaControl automático de transferencia de energía eléctrica
Control automático de transferencia de energía eléctrica
Pedro Chavez
 

En vedette (20)

Faithinfutureoverview
FaithinfutureoverviewFaithinfutureoverview
Faithinfutureoverview
 
Format data simpatisan caleg
Format data simpatisan calegFormat data simpatisan caleg
Format data simpatisan caleg
 
Evaluación primaria incluyendo_lomce
Evaluación primaria incluyendo_lomceEvaluación primaria incluyendo_lomce
Evaluación primaria incluyendo_lomce
 
Gate 2016 cepaperimathematicsq5
Gate 2016 cepaperimathematicsq5Gate 2016 cepaperimathematicsq5
Gate 2016 cepaperimathematicsq5
 
Diapo literaria 30
Diapo literaria 30Diapo literaria 30
Diapo literaria 30
 
Bacteria knowledge slides
Bacteria knowledge slidesBacteria knowledge slides
Bacteria knowledge slides
 
AAM
AAMAAM
AAM
 
Social now 2015
Social now 2015 Social now 2015
Social now 2015
 
First Floor
First FloorFirst Floor
First Floor
 
Asta el cap,10
Asta el cap,10Asta el cap,10
Asta el cap,10
 
10 1 introd diseño mecanico rev00
10 1 introd diseño mecanico rev0010 1 introd diseño mecanico rev00
10 1 introd diseño mecanico rev00
 
Holonomics and Futurists: Upgrading the Corporate World
Holonomics and Futurists: Upgrading the Corporate WorldHolonomics and Futurists: Upgrading the Corporate World
Holonomics and Futurists: Upgrading the Corporate World
 
escuela palau de mar
escuela palau de marescuela palau de mar
escuela palau de mar
 
№ 7 (39), ноябрь
№ 7 (39), ноябрь№ 7 (39), ноябрь
№ 7 (39), ноябрь
 
Riberty-Case-Study-2015
Riberty-Case-Study-2015Riberty-Case-Study-2015
Riberty-Case-Study-2015
 
Desempeños priorizados pela 2015
Desempeños priorizados pela 2015Desempeños priorizados pela 2015
Desempeños priorizados pela 2015
 
Cartel de valores 2012
Cartel de valores 2012Cartel de valores 2012
Cartel de valores 2012
 
management of the anxious patients in dental office
management of the anxious patients in dental officemanagement of the anxious patients in dental office
management of the anxious patients in dental office
 
El canvi climàtic
El canvi climàticEl canvi climàtic
El canvi climàtic
 
Control automático de transferencia de energía eléctrica
Control automático de transferencia de energía eléctricaControl automático de transferencia de energía eléctrica
Control automático de transferencia de energía eléctrica
 

Similaire à LSS_ Project Green Belt -Dheeraj Mehta

Service Improvement Plans.pdf
Service Improvement Plans.pdfService Improvement Plans.pdf
Service Improvement Plans.pdf
Boris Berovic
 
Project presentation
Project presentationProject presentation
Project presentation
Niraj Bhujel
 
MGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCCMGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCC
Leonard Burch
 
Milliman cite auto auth brd
Milliman cite auto auth brdMilliman cite auto auth brd
Milliman cite auto auth brd
Alecia Chrin
 
Karens Portfolio 2000 2010
Karens Portfolio 2000 2010Karens Portfolio 2000 2010
Karens Portfolio 2000 2010
Karen_Sampson
 
SAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-ExternalSAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-External
Andrew Si
 

Similaire à LSS_ Project Green Belt -Dheeraj Mehta (20)

IO SM Manco Report_April 2017.pptx
IO SM Manco Report_April 2017.pptxIO SM Manco Report_April 2017.pptx
IO SM Manco Report_April 2017.pptx
 
Service Improvement Plans.pdf
Service Improvement Plans.pdfService Improvement Plans.pdf
Service Improvement Plans.pdf
 
Project presentation
Project presentationProject presentation
Project presentation
 
Predictive Maintenance
Predictive MaintenancePredictive Maintenance
Predictive Maintenance
 
MGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCCMGMT 6103 - Control Phase- CMCC
MGMT 6103 - Control Phase- CMCC
 
Milliman cite auto auth brd
Milliman cite auto auth brdMilliman cite auto auth brd
Milliman cite auto auth brd
 
Zero Defect Competition @ July 22.pptx
Zero Defect Competition  @ July 22.pptxZero Defect Competition  @ July 22.pptx
Zero Defect Competition @ July 22.pptx
 
Karens Portfolio 2000 2010
Karens Portfolio 2000 2010Karens Portfolio 2000 2010
Karens Portfolio 2000 2010
 
Company project kick off
Company project kick off Company project kick off
Company project kick off
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 
Have you tried to lean your IT Service Management? by Daniel Breston
Have you tried to lean your IT Service Management? by Daniel BrestonHave you tried to lean your IT Service Management? by Daniel Breston
Have you tried to lean your IT Service Management? by Daniel Breston
 
SAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-ExternalSAP for SCM OTIF Improvement Project-External
SAP for SCM OTIF Improvement Project-External
 
IntelliPro BPMS - Reference Customer Implementation Guide
IntelliPro BPMS - Reference Customer Implementation GuideIntelliPro BPMS - Reference Customer Implementation Guide
IntelliPro BPMS - Reference Customer Implementation Guide
 
Vidyadhar Thakur_CV
Vidyadhar Thakur_CVVidyadhar Thakur_CV
Vidyadhar Thakur_CV
 
IBM Smarter Process (Stockholm)
IBM Smarter Process (Stockholm)IBM Smarter Process (Stockholm)
IBM Smarter Process (Stockholm)
 
Business proposal (2) (1)
Business proposal (2) (1)Business proposal (2) (1)
Business proposal (2) (1)
 
Six Sigma Process Improvement Foundational Steps
Six Sigma Process Improvement Foundational StepsSix Sigma Process Improvement Foundational Steps
Six Sigma Process Improvement Foundational Steps
 
AI for Business Process Management
AI for Business Process ManagementAI for Business Process Management
AI for Business Process Management
 
Equota Pitch Deck EN 2015
Equota Pitch Deck EN 2015Equota Pitch Deck EN 2015
Equota Pitch Deck EN 2015
 
PRAFUL CHAUHAN
PRAFUL CHAUHANPRAFUL CHAUHAN
PRAFUL CHAUHAN
 

LSS_ Project Green Belt -Dheeraj Mehta

  • 2. PROJECT DETAIL Name of the Project: To Improve NSC installation within SLA of 72 Hrs Project Ref. no. UJN / NSC Project Leader Name Dheeraj Mehta Designation Manager Function MMG - CS Date Jun2015 Business Unit Ujjain Project detail 2
  • 3. Voice of Customer I have applied for Power connection but they have delayed the installation Voice of business Business is losing revenue due to delay in NSC installation, also in some cases leading to Illegal connection whenever there is delay. Voice of Process NSC connections are not installed as per Process SLA of 3 day. Write down the VoC of your problem 3
  • 4. PROBLEM STATEMENT In Power DF, Ujjain City in the month of May’15, NSC installation within 72 hrs. is 55% GOAL STATEMENT To Improve NSC installation within 72 hrs. from current May’15 – 55% to 85% within 3 days by 30th Jul’15, for Ujjain City Power DF CTQ’s FOR YOUR PROJECT Paste Charter Signed Scanned Copy CTQ Parameter UoM At Project Start Target Planned Completion Date Actual Completion DateValue Value NSC installation within 3 days % 55% 85% 10th Jul 2015 30th Jul 2015 4
  • 5. In Project Scope Out Of Project Scope LT NSC connection request below 10 kW All other NSC request and NSC connection of Industrial , Agriculture & Govt. Identify Big Y’s of your project Operational Expense (OPEX) Reduction Capital Expense (CAPEX) Reduction Revenue Enhancement Y Improve Customer Satisfaction – CSAT Y Improve Employee Satisfaction Y Technical Loss Reduction Commercial Loss Reduction Project Scope and Big Y Project Scope 5 If I will do this project then this will impact following Big Y of Organization
  • 6. Revenue enhancement Cost Optimization Customer Responsiveness Customer/ Intermediary Satisfaction Others (Pls. Specify) Definition of Opportunity Project Team Business Impact CEO : Champion : Project Leader : Quality Facilitator : Team Members : Business Case Problem Statement: Definition of Defect : Lean Six Sigma - Project Charter Financial Impact Project Title: CTQs Baseline TargetIn scope Out Scope Critical Milestones Project Start Date Project End Date Goal Statement: Project Leader Quality Facilitator Champion BE Head For providing faster New Service connectivity to customer we have indentified this this project, as we have noticed the majority of the NSC application received are not installed within 72 Hrs . This project will help us to reduce the installtion SLA , enhanced revenue & also this will improve and help in transforming C - SAT . Mr.Ashok Agarwal Mr AnupamRajput Mr Dheeraj Mehta Sandeep Srivastava Zahid Husen Rakesh Gautam LT NSC connection request All other NSC request , Industrial , Agriculture , Govt. Connection & load more than 10 kWNSC Connection . For Ujjain City currently ( as on May 2015 ) NSC installtion within 3 days is 55% . To improve NSC installation SLA for Ujjain city from 55% to 85% within 3 days by 10th July 2015 NSC installtion within 3 days 55% 85% Each NSC Reuest . Any NSC connection installed out of SLA . 21 K unit increase per year . 1st Jun2015 10th Jul2015 Y Y Y To Reduce NSC Installtion TAT ( SLA ) Mr. Naresh Kumar Praveen Garg
  • 7. NSC / CSD Desk Material Requisition send to Main Store MMG Store manual count & registered the meter No in system . Meter allocated to vendor Number wise Daily validation of balance meter & installation at evening Updation of Meter in CCB for first billing Details of Customer who has paid Demand Note Meter installed and updated in billing system Registered Consumer for Business (for 1 new connection added in billing base) Supplier Input Process Output Customer Zone wise distribution of cases to vendor for installation Sample SIPOC 7
  • 8. Down Timer Model for VA / NVA Identification 8
  • 9. Identify VA / NVA for your process 9 Value & Cycle Time Track sheet Process Step 1 2 3 4 5 6 7 8 8 9 Total %Total Value Added 150 120 60 30 60 120 30 90 660 Material requisition sent to warehouse for vendor wise MMG store manual count meter & registered the meter No in system Meter Allocated to Vendor Zone wise distribution of cases to vendor for installation Vendor takes the material & meter No allocated to team Vendor start work in field Daily validation of balance meter & installation at evening Updation of Meter in IT system for first billing Value Enabled Same number validated by MMG during issue Non Value Added 30 2650 3750 6430 Store Tracks the same meter No Site not ready for installation Installation delay / Customer denied / Out of Station Total Time 7090 Time Notation in: Total Value Added work time 630 % Value added work time 8.89%
  • 10. Data Validation  Ensure that the present CTQ is measurable, if not o What is secondary measure o Is new measurement system required  Ensure that it is from the correct primary source  In case it is auto generated o Check / Audit MIS / System (CCB / CRM) S. no. Data Particulars Data Source Data Period 1 Total Application received CRM - CCB May’15 – Nov ’15 2 Total Installation done CRM - CCB May’15 – Nov ’15 3 Material movement Oracle - WAM - May’15 – Nov ’15 4 Vendor manpower details MMG 5 Please fill this – what all data you have taken for project analysis Attach Data 10
  • 11. Vendor Productivity issue Delay reporting of vendorsManual tracking of meters Off line Meter request to store Out calling process not designed Meter not available Cable not available Premises not ready Delay in data in MMG grid Refuse to install Vendor doing multiple jobs Delay in NSC installation Board not installed Customer requested delay On line protocol sheet not generated Identify all Potential Causes for Your Problem 11 EDIT CAUSES WRITTEN IN BLUE Two vendor same site Public resistance for outside installation
  • 12. Pareto Analysis – to be done for available data 12 Reason Contribution Cumulative Cumulative Contribution Premises not ready 400 400 43.96% Unavailability of Consumer 370 770 84.62% Demand note Payment delay Updation 89 859 94.40% Material issues 27 886 97.36% Two Team on same site 12 898 98.68% Repeat Visit 10 908 99.78% Installation Delay 2 910 100.00% 910 400 370 89 27 12 10 2 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% 0 50 100 150 200 250 300 350 400 450 Premises not ready Unavailability of Consumer Demand note Payment delay Updation Material issues Two Team on same site Repeat Visit Installation Delay Pareto Contribution Cumulative Contribution
  • 13. Problem Why 1 Why 2 Why 3 Why 4 Why 5 Delay in cases in MMG grid It runs batch file on daily basis System designed in the same form No thought given for delay related losses Loksewa gives SLA of 7 days Meter manual tracking No system no bar code option No interface in WAM & CCB No Meter Number tracking in CCB Repeat site Visit No fixing of meter with consumer number No system generated MCR to fixed vendor Why analysis for Key Problem from Fishbone and Pareto 13
  • 14. Run Chart ( Daily ) Track Performance of daily progress 14 2 5 8 6 37 33 24 4 20 12 20 15 30 23 7 18 21 13 34 37 50 41 20 21 30 20 0 10 20 30 40 50 60 01-Jun-15 02-Jun-15 03-Jun-15 04-Jun-15 05-Jun-15 06-Jun-15 07-Jun-15 08-Jun-15 09-Jun-15 10-Jun-15 11-Jun-15 12-Jun-15 13-Jun-15 14-Jun-15 15-Jun-15 16-Jun-15 17-Jun-15 18-Jun-15 19-Jun-15 20-Jun-15 22-Jun-15 23-Jun-15 24-Jun-15 25-Jun-15 26-Jun-15 27-Jun-15 Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Mon Tue Wed Thu Fri Sat June 15
  • 15. S. No. Root Cause Remedial Action Resp. Name of the Person / Function Target Date 1 Demand note Payment case not move to MMG Grid Run batch file 3 Hrs interval bases MMG Done 2 Delay from Consumer side 1. Documentation guidelines / and checklist to be given to front desk and call center to ready pre installation activity 2. Calling to consumer who are delay 24 Hrs 3. Installation mark during TF at site for meter fixing , application No . , cable type NSC / CSD / MMG Done 3 Vendor Alignment Two team of two vendor will dedicatedly work on NSC process MMG Done 4 Automation 1. For faster & accurate meter number automatic barcode scanner is planned 2. System generated MCR report to couple meter & consumer number . MMG Done Action planning 15
  • 16. Action planning 16 Before – Two Step & manual Job After – Automation Calling to Delay Consumer Before – Manual MCR After – System Generated MCR Meter Counting & Updation of Meter Consumer Calling Meter & consumer Coupling Meter Fixing Place & Instruction Instruction to Consumer at site
  • 17. CTQ Baseline Target Achieved NSC installation within 3 days 55% 85% 86 % Sustenance/ Control : • Mistake Proofing: Wrong meter number & incorrect consumer detail •Control Plan: next slide Project Name: To Improve NSC installation within SLA of 72hrs Project Team Project Champion: Anupam Rajput Project Leader: Dheeraj Mehta Quality Facilitator: Naresh Kumar Team : Zahid Hussain , Praveen Garg , Rakesh Gautam , Sandeep Srivastava Financial Impact: 30 % or 140 consumer per month come in our network with in 72 Hrs cause 21 K unit increase per year . Innovations / Solutions 1. Processes Impacted- Improve Punching Accuracy & Efficiency in System , reduced failure rate . 2. Process changes – i Meter Number capturing Automatic (through Bar Coder) ii Predefine meter with consumer number 3. Trainings/ Communication – i) Store team ii) Back End team iii ) Vendor Team 4. Best Practices – Bar Code meter Number Capturing . Project Completion Sheet: Control Phase 17 55% 75% 77% 86% 45% 25% 23% 14% 0% 20% 40% 60% 80% 100% May 15 Sep 15 Oct 15 Nov 15 CTQ Trend 72 Hrs > 72 Hrs
  • 18. Project Completion Sheet: Control Phase # Action implemented / To be ensured at regular frequency Resp Frequency 1 MMG received Meter from ware house captured the number via Bar code scanner . Ashish Bahal Weekly 2 Same number will be enter in CCB Ashish Bahal Weekly 3 Validating the system number & actual meter number received Sandeep Srivastava Weekly 4 Meter issued to vendor team through system generated protocol sheet Rakesh Daily 5 Application Number mention on site at standard position for meter installation Praveen Garg Daily Key actions – Why this problem will NOT REPEAT / REOCCUR? 18