2. Project Details.
Original Contract Value of the Project- Dhs.-261,604,057
Forecast Value of the Project- Dhs.-261,604,057
Value Invoiced( May 09)- Dhs.-
40,756,098
Type of Contract-
LumpSum
As per Contract
Date of Commencement of Project- 08 MAY 2008
Date of Completion of Project- 03 NOV.2009
Current Status
Date of Completion of Project- 17 JUNE 2010
Percentage Completion-
7%
Delay
Current Delay- 186