2. Project Details.
Original Contract Value of the Project- Dhs.-
163,000,000.00
Forecast Value of the Project- Dhs.-
202,000,000.00
Value Invoiced( May 09)- Dhs.-
128,023,637.70
Type of Contract-
LumpSum
As per Contract-
Date of Commencement of Project- 22
Dec.2007
Date of Completion of Project- 22 April
2009
Current Status
Date of Completion of Project- 11
Nov.2009
Percentage Completion-
55%
3. VILLAS -TARGET FINISH DATE
1. 40 VILLAS EXPECTED TO BE FINISH AT THE END OF JUNE
2009.
2. 10 VILLAS EXPECTED TO BE FINISH AT THE END OF JULY
2009.
3. 10 VILLAS EXPECTED TO BE FINISH AT THE END OF
AUGUST 2009.
4. 10 VILLAS EXPECTED TO BE FINISH AT THE END OF
SEPTEMBER 2009.
5. BALANCE 9 VILLAS EXPECTED TO BE FINISH AT THE END
OF OCTOBER 2009.
TOTAL WORK DONE UPTO 31st May 2009
Structural-92%
Finishes- 51%
Over all- 58%